Loading...
Agenda 09/11/2012 Item #16C19!' Y; 20 ' 2 Crerr 1 r EXECUTIVE SU)IMARY Recommendation to approve a work order under Request for Quotation 08- 5011 -68 in the amount of $255,747.25 to Mitchell &Stark Construction, for Request Utility Contracting Services for the Wastewater Pump Station 103.03 Rehabilitation Project Number 70046. OBJECTIVE: The public purpose of this project is to meet demand, stay in compliance, and serve customers efficiently through the Wastewater �ump Station 103.03 Rehabilitation Project. The work consists of structural, mechanical, and electrical improvements to the pump station. CONSIDERATIONS: On June 24, 2008, as Agenda Item 10G, the Board of County Commissioners (Board) adopted the 2008 Water Master Plan Update that identified the requirement for rehabilitating lift stations. The proposed scope of work for Project 70046, "Wastewater Pump Station Technical Support," is consistent with the 2010 Wastewater CIP Update, page 2 of 4, line 66, as identified in the 2011 'User Fee Rate Study. Wastewater Pump Station 103.03 is located within the right -of -way of Cypress Way East in the Palm River Estates area north of Immokalee Road. The primary issuing compelling rehabilitation of this pump station involves the corrosion of components due to the hydrogen sulfide gases. The scope of work includes removing the existing pumps and replacing them with more efficient pumps, removing the existing deteriorating pipes and electrical panels and replacing them to accommodate the required upgrades. The county electronicallv distributed Request ',for Quotation 08- 5011 -68, PS 103.03 Rehabilitation on July= 11. 2012, to the five vendors under Fixed -Term Underground Utilities Contract No. 08 -501 i. Four of those. contractors submitted quotations by the August i, 2012, deadline. The quotations are summarized in the table',, below. VENDOR SUB -TOTAL A LOWANCE TOTAL PROJECT Mitchell & Stark $ 212,500.00 $ 43,247.25 $ 255,74725 Quality Enterprises $ 259,354.90 is 43,247.25 $ 302,602.15 Douglas N Higgins $ 288,520.00 43,247.25 $ 331,767.25 Haskins Inc $ 293,950.00 $ 43,247.25 $ 337,197.25 Kyle Construction No Quote Received N6 Quote Rec'd No Quote Received The engineer's estimate of probable construction cost was $331,562.25. Staff reviewed the quotations and determined Mitchell & Stark Construction to be the lowest qualified and responsive bidder at approximately 22.9 percent below the engineer's total cost estimate. The quote tabulation and graph are Attachments 1 and 2. The Purchasing Department concluded that bidding was competitive and representative of market conditions using the awarded vendors from Contract No. 08 -5011. The project design professional, Agnoli Barber & Brundage, Inc., also recommends award of this work order to Mitchell & Stark Construction per the attached letter dated August 16, 2012. Packet Page -2718- 9/11 12012 Item 16.`'. . Mitchell & Stark Construction has a satisfactory performance and warranty record on other similar utility- related construction projects with Collier County. The bid specifications informed the bidders there may be unforeseen conditions associated with the project. The total project cost includes an allowance, in the amount of $43,247.25, for Owner – Directed Work due to unforeseen corrosive or geological conditions that includes but is not limited to, repairs due to structural deterioration, replacement of defective mechanical equipment, and deficient electrical components. Subject to the Purchasing Policy, staff will negotiate a price for any unforeseen conditions prior to the start of any additional work. FISCAL IMPACT: Funding is available in and is consistent with the FY12 Capital Budget approved by the Board on September 22, 2011. The source of funding is the Wastewater User Fee Fund 414. Funds are available in Project 70046, Wastewater Pump Station Technical Support Project. The operating budget impact of the completed project is reflected in the table below. The total capital cost to implement Project 70046 Pump Station Rehabilitation is $255,747.25. This is a maintenance project; therefore, operating costs are not expected to change significantly. Elements FY 2012 FY 2013 FY 2014 - FY2032 Capital Outlay $ 255,747.25 $0 $0 Operating Cost Change * $0 $0 $0 *This reflects the approximate cost savings in the annual operating budget for each fiscal year over the life of the asset. LEGAL CONSIDERATIONS: This item has been reviewed and approved by the County Attorney's Office, is legally sufficient for Board action and only requires a majority vote for approval —SRT. GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. RECOMMENDATION: That the Board of County Commissioners, as Ex- officio Governing Board of the Collier County Water -Sewer District, approve a work order under Request For Quotation 08- 5011 -68 in the amount of $255,747.25, which includes an allowance in the amount of $43,247.25 for unforeseen conditions, to Mitchell & Stark Construction; and, authorize the Chairman to sign and execute the work order after approval by the County Attorney's Office. Prepared By: Zamira Del Toro, Project Manager, Public Utilities Planning and Project Management Department. Attachments: Attachment 1- Quote tabulation Attachment 2- PPMD Bid Analysis Attachment 3- Recommendation Letter Attachment 4- Work Order Packet Page -2719- 9" '2:x'6 ' iter' COLLIER COUNTY Board of County Commissioners Item Number: 16.C.1. Item Summary: Recommendation to approve a work order under Request for Quotation 08- 5011 -68 in the amount of $255,747.25 to Mitchell & Stark Construction, for Underground Utility Contracting Services for the Wastewater Pump Station 103.03 Rehabilitation Project Number 70046. Meeting Date: 9/11/2012 Prepared By Name: DeltoroZamira Title: Project Manager,Public Utilities Engineering 8/16/2012 2:55:29 PM Submitted by Title: Project Manager,Public Utilities Engineering Name: DeltoroZamira 8/16'201= -:5_:3( PM Approved By Name: Steve Messner Title: Plant Manager,Water Date: 8/17/2012 10:16:05 AM Name: JohnssenBeth Date: 8/17/2012 10:37:33 AM Name: HapkeMargie Title: Operations Analyst, Public Utilities Date: 8/17/2012 10:38:22 AM Name: WidesTom Title: Director - Operations Support - PUD,Utilities Fina Date: 8/17/2012 2:01:50 PM Packet Page -2720- 9/11/201 12 Item 1 6.'_' ' . Name: WardKelsev Title: Manager - Contracts Administration,Purchasing & Ge Date: 8/20/2012 11:43:44 AM Name: ChmelikTom Title: Director, Public Utilities Engineering Date: 8/20/2012 12:46:08 PM Name: MarkiewiczJoanne Title: Manager - Purchasing Acquisition,Purchasing & Gene Date: 8/20/2012 3:06:06 PM Name: PajerCraig Title: Project Manager, Senior,Public Utilities Engineering Date: 8/22/2012 9:29:' )3 PM Name: ParkerNicole Title: Contracts Specialist,Purchasing & General Services Date: 8/24/2012 10:47:31 AM Name: TeachScott Title: Deputy County Attorney,County Attorney Date: 8/24/2012 11:37:02 AM Name: YilmazGeorge Title: Administrator, Public Utilities Date: 8/24/2012 12:00:22 PM Naive: KlatzkowJeff Title: County Attorney Date: 8/27/2012 2:10:45 PM Name: UsherSusan Title: Management /Budget Analyst, Senior,Office of Manage Date: 9/2/2012 9:15:49 AM Name: KlatzkowJeff Title: County Attorney Date: 9/4/2012 8:47:37 AM Name: IsacksonMark Title: Director -Corp Financial and Mgmt Svs,CMO Date: 9/4/2012 11:22:26 AM Packet Page -2721- - N c 7 Y N a��ao 0 m d (1 aci m a � O D � m O C L) m L A .0 m O O O t°Jo C !� O 3 0 y 0 O 0 o a3LL Ede a 0 v m L) '� to to to rn cn m to to m Ito to to to to d cn rn (tn to to � � J J J J J �- ti I O Ti O� of O� 01 c O, OI O� O� O Oi G N N m m 3 m > > ° m c p ti m O O C O U p m N C U U m "-. W U N C U N m c4 m O `m P - O 0 m N G > N D CL 2 ami N U c m d— O N m N C 0 U u d N C m O c C y O w m U W O C 1 m y m y N m N y r/i m Y c m -= Z C O U m O CO 0 U r - m `m m C y . c m a a m - c `o U c m 0 0 0 0 0 0 C, 0 0 0 0 0 0 0 0 0 o 0 O 0 o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o tp N 0 N H O 0 0 0 0 0 0 0 0 0 0 0 0 L 0 c v O� O C O (fl O 10 fA O N 69 t0 f;; 0 m to 0 C 0 N 0 0 to In t9 to M t0 fA O m C O V3 O C C O FA C O b9 O N V ' N U EA °� t/3 0 fH fA O to tpa Efl m( fA t9 N� c CL 0 y c o ` Q E E E mo o w C O J troll C= 0 O 0 0 0 0 0 0 0 0 0 0 0 0 t0 0 U0 0 U? 0 In 0 O 0 to 0 O t0 r O O O O t0 O 0 In N 40 N 1p U In f` w$ N N tf1 O u� In r` O o N w r m m m 1� n O 0 N m N O g O m V) 0 N 0 0 m O � f• v N o c M N N t0 m 0 0 O t0 I t0 N N t0 M t0 O LO N w W 10 P- t0 W N t0 W N N M t0 N L M Hi m fA m Vi to Hi M /H fA .1) fA f9 V t9 (h R fA Q N EA 7 to O M d c C E ._ vm m p o y T m c LL E B ; � L 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O 0 O N o N � 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 W V O O f• � C 0 0 7 0 t0 O t0 0 0 0 0 10 O N 0.l (0 O O t0 ` 7 N W •- W m tP cV N W c O N m M V 7 O In O tb � � O N r- N M C LL'i m N N M !- - U FA N H9 EA E9 fA M 69 EA 69 fA 69 E/1 0) fA to tf3 69 fA N f9 V M M M� Z O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O O N N 0 0 0 t,T O W N N i0 M t0 L0 M N N (D N O O O 0 N O V r 40 M O 0 O O O 0 O N H 0 O M/ O 10 n Q o O N N M � 1� fA FA M1'f fA f9 69 fH M N V! FA fA V! FA EA N FA N 49 .- EH N ff3 V to M M cn fA EA '� to to to rn cn m to to m Ito to to to to d cn rn (tn to to � � J J J J J �- ti I O Ti 0*9� W911 ZWZ /fit- /6 0 Y N N m m 3 m > > ° m c p ti m O O C O U p m N C U U m U N C U N m c4 m `m P - O 0 m N G > N N CL 2 ami N U c m d— O N m N C 0 U N C m O c C y O w m U C 1 m y m y N m N y r/i m Y c m N C O U m O CO 0 U - m `m m C y . c m a a m - c `o U c m m w n 'a vi N N 3 c .N q y m w r - m m a > > Y W m L y L O O (/7 N > 2m2- L > Y L O U °� O d 0 O tpa m c m( C O c CL 0 y c o ` Q E E E mo o w C O J troll C= C L C } m LL m D Y an d E N O Si m 3 M> U U :0 N N O U QC _ O O N > - y N a 3 'a y m 0 0 c c E m 0 m p a o a p p v o m o c S M o L m m E .O m m $ m 'm e >- m Q m p 2 c C E ._ vm m p o y T m c LL E B ; C L O u U C tp O Y ° O c c F . 3 _ C 0*9� W911 ZWZ /fit- /6 0 Bid Results of RFQ 08- 5011 -68 (PS 103.03 Rehabilitation) $450,000.00 .............. ..._..... .._..... .................. $400,000.00 ........ ............................ $350,000.00 ................. ........ ......... _. ____........_ __....... __....... 9/11 /2012 Item 1 �.�. � , KEY: Dashed Green - AVERAGE BID ow Packet Page -2723- 9111!2C`12 Item Ir' -.' MEAN !� �i lJl`d ��1� 6�y INC.. August 16, 2012 Ms. Zamira DelToro Project Manager Collier County Public Utilities 3339 Tamiami Trail East, Suite 303 Naples, FL 34112 Re: Bid Award for the Rehabilitation of LS 103.03 ABB PN 10- 0109 -3 Dear Ms. DelToro: Agnoli, Barber & Brundage (ABB) has completed its review of the bids provided by Collier County for the rehabilitation of the above lift station. Competitive bids were submitted by Haskins, DN Higgins, Quality Enterprises and Mitchell and Stark. The Mitchell and Stark Construction Company submitted the lowest bid at $25,747.25. ABB has worked with Mitchell and Stark on previous utility projects in Collier County which have been favorable experiences. We recommend that contract be awarded to Mitchell and Stark for their above bid amount. Please contact me if you have any questions. Sincerely, Steven A. Martin, P.E. Project Manager Packet Page -2724 NVORF ORDER Item! 1E �. tie: r uluert Dune `tJtilit i. ontract Date: Marci i 'C . 200;; nixed Term Contract i-xpires Marcia iU. 2013. (RFQ #08- 5011 -64) BCC approval Date: September 11, 2012 This Work Order is for Underground Utility Construction services for work knowii as: Project Name: PS 103.03 Rehabilitation Project No: 70046.4.4.I The work is specified in the Proposal Page, dated August 7. 2012. which is attached hereto and made a part of this Work Order. In accordance with Tenrts and Conditions of the Agreement referenced above and Request for Quotation #08-5011-68 dated July 11, 2012, as modified by Addendum 1 thru 2, attached hereto a part of this Work Order # (please fill out once received) is assigned to: Mitchell & Stark Construction. Scone of Work: Per Quote Tabulation form attached and the following: Existing valve vault, wet well piping and puttnps shall be removed. The wet well shall be patched and coated. New wet well piping.. pumps, guide bar;_, brackets. floats, etc. are proposed along with new above ground piping and valves, electrical upgrades are also included. 1 he Contractor is responsible for all required bypassing and shall provide power to pump station throughout construction. Task I - From Item I to Item 20 of Quote. Supply and install pumps, control panels, piping in the wet well and above ground and other necessary materials to complete the work as intended by the plans. Task 11 - Item 21 of Quote. Owner- Directed Work for geological or Corrosion Unforeseen Conditions Schedulef Work: A limited NTP will be issued to Contractor to purchase materials and obtain permits. Another NTT' will be issued to complete work within 180 days from the date of the Notice to Proceed. Compensation: In accordance with Section 2 - Statement of Work for Agreement 408 -5011. the County will compensate the Firm in accordance with follov�inv method(s): QNeaotiated Lump Suin: Lum m p Su Plug, Reimbursable Costs, [7�1`ime & Material (non- guaranteed, owner directed work): ❑Cost Plus Fixed Fee. as provided in the attached proposal. "Mask IT 5212.500.00 fLumf Sunni Iasi, I1 5 43,247_25. ('Dime d Material! S_,- a5.74 r._5 TOTAL COST FOR TASKS I & 11 $ 255,747 25 PREPARED Zannra DelToro, Project Manager Planning & Project Management Department APPROVED ICY: Craig Pajer, P<E: ;PrincipgProject Manager Planning & .Pict Management Department APPROVED BY: — Tom Chmelik, P.E.. Director Manning & Project: Management Department Packet Page -2725- Daie -- Date. t Z' Z-�} APPROVED By-,"' ,Beth .1 olinssep/Operations Manager Wastewater Department APPROVED BY: -- - - -------- S16 ve Me e , 'r I sn s .) irector Wastewater Department APPROVED BY:. Nicole Parke�, Procurement Speajulist Ptirchasing'T'NTMIment- `4'# APPROVED M : George Yi1mv-:° Aliainistrator Public Utilities P 'I! !2C' I _- It err 16.` ' ......... .. . Date bate Date Date AT- ]'EST: BOARD OF COUNTY ("ON41MISSIONERS Dm-i,-,Ii( E. Brock. Clerk Collier County. Florida By: _ . ........ ..... By: Deputy Clerk Fred Wt C ovle. Chamriai. Mitchell Stark Construction (Print Narne!Titie) Approved as to Form and LeualSufficienev: ATTEST: . ......... ....... .... Bv: Gniiiy Pepin ­7 Assistant COL111tv Attorney, (Print Name/Title) Packet Page -2726- 9/11/2012 Item, 16.0.1. fnisLative Services Division Purchasing COLLIER COUNTY FLORIDA REQUEST FOR QUOTATION RFQ #08-5011 -68 Pump Station 103.03 Rehabilitation PROPOSALPAGE DUE DATE. August 7 2012 at 11:00 a.m. The undersigned, as quoter, hereby declares that the firm has examined the specifications and is informed fully in regard to all terms and conditions pertaining to the project and, if this Proposal is accepted, to furnish same in full, according to the following: See separate Quate Sciedul IN 'WITNESS WHEREOF, WE have hereunto subscribed our names on this ? day or 2C12 in the County of (n II / . in the state of FI , 1`t 1, �,,.!, ' Firms Compiete Legal Name — 3 Telephone Number 2. FAX Number Email Address City �, - - -- - - -- 3,t c7 Zip — ........ Florida Certificate o L,hority Document Number i 9 '2 Item 011 -Ca E0, tp- 6.3. bs eF? C/) v) --j _j _j Co CO (1, ; "o Cf) 11� Packet Page -2728- J,Ij Q,, ifi z, :CC) � �o jl a- ��I��c.�IIII�:i =i a. t J! vj f 4= Packet Page -2728- J,Ij Q,, ifi 6 LU O Packet Page -2729- 9/11/2012 Itern "6 72 0 > U) CL .2 0 Tl L) co U t-I Cr E: U, Cr Z. En Cc 0 U) Cn. 0 O Co ED Vi .2 'm ro 10- 2 U C� c a`m C D 0 Co Y= am, .iz a) > V) C: C) L) LL o < 2 CL C: V) C', C U) Cr Cr G7 ru [C CC w Co Ch th Q5 CD Co U t7 :3 U) C) 0 o o 0 Co CL CD 76 C_ 7E w zn _ U m 0 C: 0 D Cm 2 0 0 a 0 2 m > C U) U 0 t 0 .2 -2,u Packet Page -2729- 9/11/2012 Itern "6 72 0 > U) CL .2 0 Tl L) co U t-I Cr E: U, Cr Z. En Cc 0 U) Cn. 0 t. P. = IV 3 t._5� " "Annual Contract for Underground Utility Contracting Services THIS AGREEMENT is made and entered into this day of (Ylckr-c_6 , 2008, by and between the Board of County Commissioners for Collier County, Florida, a political subdivision of the State of Florida (hereinafter referred to as the "County" or "Owner ") and Mitchell & Stark Construction authorized to do business in the State of Florida, whose business address is 6001 Shirley Street, Naples, Florida 34109 (hereinafter referred to as the "Contractor "). WITNESSETH: COMMENCEMENT: The contract shall be for the period of twenty four (24) months. Additionally, by mutual agreement and funding availability, the contract may be renewed for two (2) terms of twenty four (24) months each. In no event, including renewal options, shall the contract exceed six (6) years. The Purchasing /General Services Director or his designee may, at his discretion, extend the Agreement under all of the terms and conditions contained in this Agreement for up to one hundred eighty (180) days. The Purchasing /General Services Director, or his designee, shall give the Contractor written notice of the County's intention to extend the Agreement term not less than ten (10) days prior to the end of the Agreement term then in effect. 2. STATEMENT OF WORK: The Board of County Commissioners deemed five firms to be pre - qualified and awarded a Contract to each firm. Each awardee will enter into an Agreement to provide complete services for a wide range of minor -to- medium scale future construction, renovation and retrofit projects on an as- needed basis as may be required by the Owner it accordance with the terms and conditions of RFP 08 -5011 and the Contractor's proposal made an integral part of this agreement. The execution of this Agreement shall not be a commitment to the Contractor that any work will be awarded tc, the Contractor. Rather. this Agreement governs the rights and obligation of the Quotation procedure outiined in the next paragraphs and ali Work undertaken by Contractor for Owner pursuant to this Agreement and that procedure during the term and any extension of the term of this Agreement. The Owner shall provide a summary of Work to be opportunity to submit a formal quotation for the information sought within seven (7) working days. Thousand ($50,000) or less, the Owner shall obta selected firms, negotiate favorable project terms Order to initiate the projects. performed which will afford the Contractor the Work; the Contractor shall respond with the For projects with an estimated cost of Fifty n a proposal from one or more of the five (5) and conditions, and issue a numbered Work For projects with an estimated cost over Fifty Thousand Dollars ($50,000) and less than Two Hundred Thousand Dollars ($200,000), competitive quotes shall be solicited from all of the contracted firms; the Contractor shall respond with the information and or proposal sought within ten (10) working days, the Owner shall negotiate favorable project terms and conditions, and issue a numbered Work Order to initiate the projects. Division Administrator and County Attorney approval is required at this level. For projects over Two Hundred Thousand Dollars ($200,000) and less than Seven Hundred Fifty Thousand ($750,000), competitive quotations shall be solicited from all of the contracted firms. Staff recommendations will then be submitted to the Board of County Commissioners for approval after County Attorney and Division Administrator approval. Pnae -1- Packet Page -2730- 9111/2012 Item 16.C.'l . ir. ea-^r Request. io' - _�=Latlon, trl- Owne` reserve_ the riQn: tG spe -cii the perioc o' and the collection of liquidated damages in the even; of late completion. Work orders shall not be required for emergency work but will be authorized by Purchase Order only. The Forms attached to this Agreement as Exhibits A through D shall not be required for emergency work. The Contractor will be compensated for time and material work, either emergency or scheduled, in accordance with the rate sheet with material and specialty equipment markup. 3. EMERGENCY WORK: Contractors under this Agreement will be on an on -call rotation schedule for emergency underground utility contracting services. The on -call Contractor shall be required to have a cell phone number, along with a home number, to the County so that the County will be able to contact the Contractor when needed. This schedule will be rotated on a one (1) week basis. In the event that a Contractor cannot be on -call as scheduled, it will be rotated to the next scheduled Contractor, and the schedule will continue with each Contractor having no more than two (2) weeks in a row on -call. 4. THE CONTRACT SUM: The Owner shall pay the Contractor for the performance of the Work pursuant to the quoted price offered by the Contractor in his response to a specific Request for Quotation. Any County agency may utilize the service offered under this contract, provided sufficient funds are included in their budget(s). 5. NOTICES: All notices from the County to the Contractor shall be deemed duly served if mailed by registered or certified mail to the Contractor at the following address: Mitchell & Stark Construction Brian Penner, CEO 6001 Shirley Street, Naples, Florida 34109 Phone: 239 -597 -2165 Fax: 239 - 566 -7865 All notices from the Contractor to the County shall be deemed duly served if mailed by registered or certified mail to the County at the following address: Collier County Government Complex Attn: Purchasing /General Services Director Purchasing Department 3301 East Tamiami Trail, Purchasing Building G Naples, Florida 34112 239 - 252 -8407 The Contractor and the County may change the above mailing address at any time upon giving the other party written notification. All notices under this Service Agreement must be in writing. 6. NO PARTNERSHIP: Nothing herein contained shall create or be construed as creating a partnership between the County and the Contractor or to constitute the Contractor as an agent of the County. Paae -2- Packet Page -2731- 9!11,'2012 Item 16._` PERMITS: "ICEWSES, TAXES. it compi�an :e wit; i �ectror �'i 6.�:: rionaa �TaTUTes; ail permiT necessary for the prosecution of the Work shall be obtained by the Contractor. Payment for al such permits issued by the County shall be processed internally by the County. Contractor is not responsible for paying for permits issued by Collier County, but is responsible for acquiring all permits. Owner may require the Contractor to deliver internal budget transfer documents to applicable Collier county agencies when the Contractor is acquiring permits. All permits, fees and licenses necessary for the prosecution of the Work which are not issued by Collier County shall be acquired and paid for by the Contractor. Contractor shall pay all sales, consumer, use and other similar taxes associated with the Work or portions thereof, which are applicable during the performance of the Work. 8. NO IMPROPER USE: The Contractor will not use, nor suffer or permit any person to use in any manner whatsoever, county facilities for any improper, immoral or offensive purpose, or for any purpose in violation of any federal, state, county or municipal ordinance, rule, order or regulation, or of any governmental rule or regulation now in effect or hereafter enacted or adopted. In the event of such violation by the Contractor or if the County or its authorized representative shall deem any conduct on the part of the Contractor to be objectionable or improper, the County shall have the right to suspend the Contract of the Contractor. Should the Contractor fail to correct any such violation, conduct, or practice to the satisfaction of the County within twenty -four (24) hours after receiving notice of such violation, conduct, or practice, such suspension to continue until the violation is cured. The Contractor further agrees not to commence operation during the suspension period until the violation has been corrected to the satisfaction of the County. 9. TERMINATION: Should the Contractor be found to have failed to perform his services in a manner satisfactory to the County and requirements of this Agreement, the County may terminate said Agreement immediately for cause; further the County may terminate this Agreement for convenience with a seven (7) day written: notice. The County shall be sole judge of non- performance. 10. NO DISCRIMINATION: The Contractor agrees that there shall be no discrimination as to race, sex, color, creed or national origin. 11. INSURANCE: The Contractor shall provide insurance as follows: A. Commercial General Liability: Coverage shall have minimum limits of $2,000,000 Per Occurrence, Combined Single Limit for Bodily Injury Liability and Property Damage Liability. This shall include Premises and Operations; Independent contractors; Products and Completed Operations and Contractual Liability. B. Business Auto Liability: Coverage shall have minimum limits of $1,000,000 Per Occurrence, Combined Single Limit for Bodily Injury Liability and Property Damage Liability. This shall include Owned Vehicles, Hired and Non -Owned Vehicles and Employee Non - Ownership. C. Workers' Compensation: Insurance covering all employees meeting Statutory Limits in compliance with the applicable state and federal laws. The coverage must include Employers' Liability with a minimum limit of $500,000 for each accident. Paae -3- Packet Page -2732- 9/11/2012 Item 16.x.' JJecia - :eouirements �;oliie� '-. Din-rP, Ei3aro .o -: :,ommissione;5 L_ 115Lt:U &: HIS certificate Hoide. anc inctudec aS ar Addifionai insures on the ;omprenensive Oeneru. Liability. Current, valid insurance policies meeting the requirement herein identified shall be maintained by Contractor during the duration of this Agreement. Renewal certificates shall be sent to the County 30 days prior to any expiration date. There shall be a thirty (30) day notification to the County in the event of cancellation or modification of any stipulated insurance coverage. Contractor shall insure that all subcontractors comply with the same insurance requirements that he is required to meet. The same Contractor shall provide County with certificates of insurance meeting the required insurance provisions. 12. INDEMNIFICATION: To the maximum extent permitted by Florida law, the Contractor/Vendor /Consultant shall indemnify and hold harmless Collier County, its officers and employees from any and all liabilities, damages, losses and costs, including, but not limited to, reasonable attorneys' fees and paralegals' fees, to the extent caused by the negligence, recklessness, or intentionally wrongful conduct of the Contractor/Vendor /Consultant or anyone employed or utilized by the Contractor/Vendor /Consultant in the performance of this Agreement. This indemnification obligation shall not be construed to negate, abridge or reduce any other rights or remedies which otherwise may be available to an indemnified party or person described in this paragraph. This section does not pertain to any incident arising from the sole negligence of Collier County. 13. BONDS. A. The Owner shall use its discretion for bonding where a project may be in excess of fifty thousand dollars ($50,000) but completed in less than sixty (60) days. B. When required by Owner, the Contractor shall furnish a Performance and /or Payment Bond prior to commencing performance, for the full amount of the Work which shall act as a security guaranteeing the performance of the Contractor's work and the payment by the Contractor to any other party (ies) providing labor and /or materials in connection with each construction or renovation project performed by the Contractor in excess of fifty thousand dollars ($50,000). The bonds shall be furnished using the forms prescribed in Exhibit "A ". C. If the surety for any bond furnished by Contractor is declared bankrupt, becomes insolvent, its right to do business is terminated in the State of Florida, or it ceases to meet the requirements imposed by the Contract Documents, the Contractor shall, within five (5) calendar days thereafter, substitute another bond and surety, both of which shall be subject to the Owner's approval. 14. PAYMENTS. Generally, the Contractor will be paid upon completion; however, for Work in excess of thirty (30) days, the Contractor may indicate on his response to the Request for Quotation his wish to receive Progress Payments. Before any payment will be made, Contractor must provide Owner with a fully executed Release and Affidavit in the form attached hereto as Exhibit "B" as a condition precedent to release of each progress payment. All applications for payment, whether for full payment or a progress payment shall be in writing, and in substantially the form attached hereto as Exhibit "C ". low Pane -4- Packet Page -2733- 0/• "fir) 1tam, i DL X'ITJ J' 1' —'-Ir _)'rt' oc - �` _ a ". ',�� a l� ill atI_ _ To' a� /��. poi [ion; trier eo r)ecaus - o- aefeCTwe o' iricOnnplei worm. uutsianciing puncniis *. item subsequentiy discovered evidence or subsequen� inspections. The Owner may nullify the wnoie or any part of any approval for payment previously issued and Owner may withhold any payments otherwise due Contractor under this Agreement or any other agreement between Owner and Contractor, to such extent as may be necessary in the Owner's opinion to protect it from loss because of: (a) defective Work not remedied; (b) third party claims failed or reasonable evidence indicating probable fling of such claims; (c) failure of Contractor to make payment properly to subcontractors or for labor, materials or equipment; (d) reasonable doubt that the Work can be completed for the unpaid balance of the Contract Amount; (e) reasonable indication that the Work will not be completed within the Contract Time; (f) unsatisfactory prosecution of the Work by the Contractor; or (g) any other material breach of the Contract Documents. If any conditions described above are not remedied or removed, Owner may, after three (3) days written notice, rectify the same at Contractor's expense. Owner also may offset against any sums due Contractor the amount of any liquidated or unliquidated obligations of Contractor to Owner, whether relating to or arising out of this Agreement or any other agreement between Contractor and Owner. 16. SUBMITTALS AND SUBSTITUTIONS. Any substitution of products /materials from specifications shall be approved in writing by Owner in advance. 17. CONTRACT TIME AND TIME EXTENSIONS. A. Time is of the essence in the performance of any Work under this Agreement and Contractor shall diligently pursue the completion of the Work, and coordinate the Work being done on the Project by its subcontractors and materialmen, as well as coordinating its Work with all work of others at the Project Site, so that its Work or the work of others shall not be delayed or impaired by any act of omission by Contractor. Contractor shall be solely responsible for all construction: means, methods, techniques, sequences, and procedures as well as coordination of all portions of the Work under the Contract Documents, and the coordination of Owner's supplies and contractors. B. Should Contractor be obstructed or delayed in the prosecution of or completion of the Work as a result of unforeseeable causes beyond the control of Contractor, and not due to its fault or neglect, including but not restricted to acts of Nature or of the public enemy, acts of Government, fires, floods, epidemics, quarantine regulation, strikes or lockouts, Contractor shall notify the Owner in writing within forty -eight (48) hours after the commencement of such delay, stating the cause or causes thereof, or be deemed to have waived any right which Contractor may have had to request a time extension. C. No interruption, interference, inefficiency, suspension or delay in the commencement or progress of the Work from any cause whatever, including those for which Owner may be responsible, in whole or in part, shall relieve Contractor of his duty to perform or give rise to any right to damages or additional compensation from Owner. Contractor expressly acknowledges and agrees that it shall receive no damages for delay. Contractor's sole remedy, if any, against Owner will be the right to seek an extension to the Contract Time; provided, however, the granting of any such time extension shall not be a condition precedent to the aforementioned "No Damage for Delay" provision. This paragraph shall expressly apply to claims for early completion, as well as to claims based on late completion. 18.CHANGES iN THE WORK. Owner shall have the right at any time during the progress of the Work to increase or decrease the Work. Promptly after being notified of a change, Contractor Pane -5- Packet Page -2734- 9!1 1120'12 Item 16.x'.' . snai s {i7mi ar ITB' ll7e� esti"'" -"aT: ,), aim c c, o' ume "1CC -..-` s- — o" savincz esee: a� re Tor a. c r s,-, o' the mange. �xcep it ar emergence ericiangen iit o* property, o- a, exmressiv se` Tort ` herein, no addition or changes to the Work: shall be mane except upon written order o- Owne -. and Owner shall not be liable to the Contractor for any increased compensation without such written order. No office, employee or agent of Owner is authorized to direct any extra or changed work orally. A Change Order in the form attached as Exhibit "D" to this Agreement, shall be issued and executed promptly after an agreement is reached between Contractor and Owner concerning the requested changes. Contractor shall promptly perform changes authorized by duly executed Change Orders. The Contract Amount and Contract Time shall be adjusted in the Change order in the manner as Owner and Contractor shall mutually agree. 19. COMPLIANCE WITH LAWS. Contractor agrees to comply, at its own expense, with all federal, state and local laws, codes, statutes, ordinances, rules, regulations and requirements applicable to the Project, including but not limited to those dealing with taxation, workers'. compensation, equal employment and safety (including, but not limited to, the Trench Safety Act, Chapter 553, Florida Statutes). If Contractor observes that the Contract Documents are at variance therewith, it shall promptly notify Owner in writing. 20. CLEAN UP. Contractor agrees to keep the Project site clean at all times of debris, rubbish and waste materials arising out of the Work. At the completion of the Work, Contractor shall remove all debris, rubbish and waste materials from and about the Project site, as well as all tools, appliances, construction equipment and machinery and surplus materials, and shall leave the Project site clean and ready for occupancy by Owner. 21.ASSIGNMENT. Contractor shall not assign this Agreement or any part thereof, without the prior consent in writing of Owner. If Contractor does, with approval, assign this Agreement or any part thereof, it shall require that its assignee be bound to it and to assume toward Contractor all of the obligations and responsibilities that Contractor has assumed toward Owner. 22. WARRANTY. Contractor shall obtain and assign to Owner all express warranties given to Contractor or any subcontractors by any materialmen supplying materials, equipment or fixtures to be incorporated into the Project. Contractor warrants to Owner that any materials and equipment furnished under the Contract Documents shall be new unless otherwise specified, and that all Work shall be of good quality, free from all defects and in conformance with the Contract Documents. Contractor further warrants to Owner that all materials and equipment furnished under the Contract Documents shall be applied, installed, connected, erected, used, cleaned and conditioned in accordance with the instructions of the applicable manufacturers, fabricators, suppliers or processors except as otherwise provided for in the Contract Documents. If, within one (1) year after final completion, ..any Work is found to be defective or not in conformance with the Contract Documents, Contractor shall correct it promptly after receipt of written notice from Owner. Contractor shall also be responsible for and pay for replacement or repair of adjacent materials or Work which may be damaged as a result of such replacement or repair. These warranties are in addition to those implied warranties to which Owner is entitled as a matter of law. Paae -6- Packet Page -2735- ;;sear. wek oroomel, an cr?L .eou . 24. TESTS AND INSPECTIONS. If the Contract Documents or any codes, laws, ordinances, rules or regulations of any public authority having jurisdiction over the Project requires any portion of the Work to be specifically inspected, tested or approved, Contractor shall assume full responsibility therefore, pay all costs in connection therewith and furnish to the Owner the required certificates of inspection, testing or approval. All inspections, tests or approvals shall be performed in a manner and by organizations acceptable to the Owner. 25. PROTECTION OF WORK. A. Contractor shall fully protect the Work from loss or damage and shall bear the cost-of any such loss or damage until final payment has been made. If Contractor or anyone for whom Contractor is legally liable is responsible for any loss or damage to the Work, or other work or materials of Owner or Owner's separate contractors, Contractor shall be charged with the same, and any monies necessary to replace such loss or damage shall be deducted from any amounts due Contractor. B. Contractor shall not load nor permit any part of any structure to be loaded in any manner that will endanger the structure, nor shall Contractor subject any part of the Work or adjacent property to stresses or pressures that will endanger it. C. Contractor shall not disturb any benchmark established by the Owner with respect to the Project. If Contractor, or its subcontractors, agents or anyone, for whom Contractor is legally liable, disturbs the Owner's benchmarks, Contractor shall immediately notify Owner. The Owner shall re-establish-the benchmarks and Contractor shall be liable for all costs incurred by Owner associated therewith. 26. EMERGENCIES. In the event of any emergency affecting the safety or protection of persons or the Wore; or property at the Project site or adjacent thereto, Contractor, without special instruction or authorization from Owner is obligated to act to prevent threatened damage, injury or loss. Contractor shall give the Owner written notice within forty -eight (48) hours after the occurrence of the emergency, if Contractor believes that any significant changes in the Work or variations from the Contract Documents have been caused thereby. If the Owner determines that a change in the Contract Documents is required because of the action taken in response to an emergency, a Change Order shall be issued to document the consequences of the changes or variations. If Contractor fails to provide the forty -eight (48) hour written notice noted above, the Contractor shall be deemed to have waived any right it otherwise may have had to seek an adjustment to the Contract Amount or an extension to the Contract Time. 27. COMPLETION. When the entire Work (or any portion thereof designated in writing by Owner) is ready for its intended use, Contractor shall notify Owner in writing that the entire Work (or such designated portion) is substantially complete and request that Owner issue a Certificate of Completion (substantial or final Certificate of Completion). Within a reasonable time thereafter, Owner and Contractor shall make an inspection of the Work (or designated portion thereof) to determine the status of completion. If Owner does not consider the Work (or designated portion) substantially complete, the Owner shall notify Contractor in writing giving the reasons therefor. Pane -7- Packet Page -2736- 9/11/2012 Item 16.C.11, ")wnc` consi4e : the Won to c.IesipncTer- Do -tion' substantiali ' complete `Jwner snail IDreDare an-- oeiiver is :,oniracior a '�'-ertificaie Or :fompleIlOr, ( substantial o final Certificate of which shall fix the date of Substantial Completion for the entire Wort-, (or designated portion thereof) and include a tentative punchlist of items to be completed or corrected by Contractor before final payment. Owner shall have the right to exclude Contractor from the Work and Project site (or designated portion thereof) after the date of Substantial Completion, but Owner shall allow Contractor reasonable access to complete or correct items on the tentative punchlist. Upon receipt of written certification by Contractor that the Work is completed in accordance with the Contract Documents and is ready for final inspection and acceptance, and upon receipt of a final Application for Payment, Owner will make such inspection and, if Owner finds the Work acceptable and fully performed under the Contract Documents, he shall promptly issue a final Certificate for Payment, recommending that on the basis of his observations and inspections, and the Contractor's certification that the Work has been completed in accordance with the terms and conditions of the Contract Documents, that the entire balance found to be due Contractor is due and payable. Final payment shall not become due and payable until Contractor submits: (1) The Release and Affidavit in the form attached as Exhibit "B ". (2) Consent of Surety (if applicable) to final payment. (3) If required by Owner, other data establishing payment or satisfaction of all obligations, such as receipt, releases and waivers of liens, arising out of the Contract Documents, to the extent and in such form as may be designated by Owner. Owner reserves the right to inspect the Work and make an independent determination as to the Works acceptability. Unless and until the Owner is completely satisfied, the final payment shall not become due and payable. 28. LIQUIDATED DAMAGES. The "Commencement Date' shall be established in the Notice to Proceed to be issued by the Owner. Contractor shall commence the work within five (5) calendar days from the Commencement Date. No Work shall be performed at the Project site prior to the Commencement Date. Any Work performed by Contractor prior to the Commencement Date shall be at the sole risk of Contractor. The Work shall be substantially completed within the time specified in the Request for Quotation. The date of substantial completion of the Work (or designated portions thereof) is the date certified by the Owner when construction is sufficiently complete, in accordance with the Contract Documents, so Owner can occupy or utilize the Work (or designated portions, thereof) for the use for which it is intended. The Work shall reach final completion and be ready for final acceptance by Owner within the time specified in the Request for Quotation. Owner and Contractor recognize that since time is of the essence for any work under this Agreement, Owner will suffer financial loss if the Work is not substantially completed within the time specified in the Request for Quotation. Should Contractor fail to substantially complete the Work within the specified time period, Owner shall be entitled to assess as liquidated damages, but not as a penalty, the amount specified in the Request for Quotation for each calendar day thereafter until substantial completion is achieved. The Project shall be deemed to be substantially completed on the date the Owner issues a Certificate of Substantial Completion pursuant to the terms hereof. Contractor hereby expressly Paae -8- Packet Page -2737- 9 11112012 Ite —Ii : 16.G . a`- r nr rio � wr. . . TL see! ••rz -, °7. �ls _F'_ iiciuiaaiec iaamaae us penan\ wnic.- tr-,-- paaie: as represents G gar arnc reasonaDie estimate o" the Owner c: actual damages a the time of contractinc if .ontra -Lo` faiis tc substantially complete the Work in a timely manner. When any period of time is referenced by days herein, it shall be computed to exclude the first day and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day shall be omitted from the computation, and the last day shall become the next succeeding day which is not a Saturday, Sunday or legal holiday. 29. CONTRACT ADMINISTRATION. This Agreement shall be administered on behalf of the County by the Public Utilities Engineering Department. 30. COMPONENT PARTS OF THIS CONTRACT. This Contract consists of the attached or referenced component parts, all of which are as fully a part of the Agreement as if herein set out verbatim, including: Contractor's Proposal, Insurance Certificate, Request for Proposal No. 08- 5011, any addenda, Exhibits A, B, C and D, any Quotation/Work Order made or issued pursuant to this Agreement, and any related plans or specifications for any such Quotations or Work Orders. 31.SUBJECT TO APPROPRIATION. It is further understood and agreed, by and between the parties herein that this Agreement is subject to appropriation by the Board of County Commissioners. 32. PROHIBITION OF GIFTS TO COUNTY EMPLOYEES. No organization or individual shall otter or give, either directly or indirectly, any favor, gift, loan, fee, service or other item of value to any County employee, as set forth in Chapter 112, Part III, Florida Statutes, Collier County Ethics Ordinance No. 2004 -05. and County :Administrative Procedure 5311. Violation of this provision may result ir, one or more of the following consequences: a. Prohibition by the individual, firm, and /or any employee of the firm from contact with County staff for a specified period of time; b. Prohibition by the individual and /or firm from doing business with the County for a specified period of time, including but not limited to: submitting bids, RFP, and /or quotes; and, c. immediate termination of any contract held by the individual and /or firm for cause. 33. IMMIGRATION LAW COMPLIANCE: By executing and entering into this agreement, the Contractor is formally acknowledging without exception or stipulation that it is fully responsible for complying with the provisions of the Immigration Reform and Control Act of 1986 as located at 8 U.S.C. 1324, et seq. and regulations relating thereto, as either may be amended. Failure by the Contractor to comply with the laws referenced herein shall constitute a breach of this agreement and the County shall have the discretion to unilaterally terminate this agreement immediately. 34. VENUE: Any suit or action brought by either party to this Agreement against the other party relating to or arising out of this Agreement must be brought in the appropriate federal or state courts in Collier County, Florida, which courts have sole and exclusive jurisdiction on all such matters. 35. OFFER EXTENDED TO OTHER GOVERNMENTAL ENTITIES: Collier County encourages and agrees to the successful proposer extending the pricing, terms and conditions of this solicitation or resultant contract to other governmental entities at the discretion of the successful proposer. Paae -9- Packet Page -2738- 9/ i '.- 2012- Item 16. Cl. IN WITNESS WHEREOF, the Contracto, and the County, have each, respectively; oy an autriorizec person or agent, hereunder set their hangs and seals on the date and year first above written. ATTEST: Dwight E. Brock, ` fft of Courts By: �. Dated. . r' ea .x.. Attest. 43 trum f 4 ign6turt "100 BOARD OF COUNTY COMMISSIONERS COLLIER COUNTY, FLORIDA By:_ Yom Henning, Chairm Z,=L � By: First Otness -Type /Prints Witness: me Second Witness Type /Print Witness Name Approved as to form and legal s ie Rob4rt N. ZachaiV Assistant County Attorney Mitchell & Stark Construction Contractor Signature Typed Signature C, --o ) U >� Title Page -10- Packet Page -2739- waives anc. relinquisne-c an\ rigni wnicrt r ilia\ have is seei: cnarameriz- ME; &)ove notes iiquiaatec camages as a penalty, which the paizies agree represents a fai° anc' reasonable estimate of the Owner's actual damages at the time of contracting if Contractor fails to substantially complete the Work in a timely manner. When any period of time is referenced by days herein, it shall be computed to exclude the first day and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a. day made a legal holiday by the law of the applicable jurisdiction, such day shall be omitted from the computation, and the last day shall become the next succeeding day which is not a Saturday, Sunday or legal holiday. 29. CONTRACT ADMINISTRATION. This Agreement shall be administered on behalf of the County by the Public Utilities Engineering Department. 30. COMPONENT PARTS OF THIS CONTRACT. This Contract consists of the attached or referenced component parts, all of which are as fully a part of the Agreement as if herein set out verbatim, including: Contractor's Proposal, Insurance Certificate, Request for Proposal No. 08- 5011, any addenda, Exhibits A, B, C and D, any Quotation/Work Order made or issued pursuant to this Agreement, and any related plans or specifications for any such Quotations or Work Orders. 31. SUBJECT TO APPROPRIATION. It is further understood and agreed, by and between the parties herein that this Agreement is subject to appropriation by the Board of County Commissioners. 32. PROHIBITION OF GIFTS TO COUNTY EMPLOYEES. No organization or individual shall offer or give, either directly or indirectly, any favor, gift, loan, fee, service or other item of value to any County employee, as set forth in Chapte 112, Part III, Florida. Statutes, Collier County Ethics Ordinance No. 2004 -05, and. County Administrative Procedure 5311. Violatior: of this provision may result in one or more of the following consequences: a. Prohibition by the individual, firm, and /or any employee of the firm from contact with County staff for a specified period of time; b. Prohibition by the individual and /or firm from doing business with the County for a specified period of time, including but not limited to: submitting bids, RFP, and /or quotes; and, c. immediate termination of any contract held by the individual and /or firm for cause. 33. IMMIGRATION LAW COMPLIANCE: By executing and entering into this agreement, the Contractor is formally acknowledging without exception or stipulation that it is fully responsible for complying with the provisions of the Immigration Reform and Control Act of 1986 as located at 8 U.S.C. 1324, et seq. and regulations relating thereto, as either may be amended. Failure by the Contractor to comply with the laws referenced herein shall constitute a breach of this agreement and the County shall have the discretion to unilaterally terminate this agreement immediately. 34. VENUE: Any suit or action brought by either party to this Agreement against the other party relating to or arising out of this Agreement must be brought in the appropriate federal or state courts in Collier County, Florida, which courts have sole and exclusive jurisdiction on all such matters. 35. OFFER EXTENDED TO OTHER GOVERNMENTAL ENTITIES: Collier County encourages and agrees to the successful proposer extending the pricing, terms and conditions of this solicitation or resultant contract to other governmental entities at the discretion of the successful proposer. Paae -9- Packet Page -2740- :" "x;'20 I � Item 1 G. - EXHIB[" A PUBLIC PAYMENT BOND Bond No. Contract No, 08 -5011 KNOW ALL ME BY THESE PRESENTS: That as Principal, and , as Surety, located at (Business Address) are held and firmly bound to as Oblige in the sum of ($ for the payment whereof we bind ourselves, our heirs, executors, personal representatives, successors and assigns, jointly and severally. WHEREAS, Principal has entered into a contract dated as of the day of , 200_, with Oblige for in accordance with drawings and specifications, which contract is incorporated by reference and made a part hereof, and is referred to as the Contract. THE CONDITION OF THIS BOND is that if Principal: Promptly makes payment to all claimants as defined in Section 255.05(1), Florida Statutes, supplying Principal with labor, materials or supplies, used directly or indirectly by Principal in the prosecution of the work provided for in the contract, then this bond is void; otherwise it remains in full force. Any changes in or under the Contract and compliance or noncompliance with any formalities connected with the Contract or the changes do not affect sureties obligation under this Bond. The provisions of this bond are subject to the time limitations of Section 255.0592. In no event will the Surety be liable in the aggregate to claimants for more than the penal sum of this Payment Bond, regardless of the number of suits that may be filed by claimants. IN WITNESS WHEREOF, the above parties have executed this instrument this day of 200_, the name of under - signed representative, pursuant to authority of its governing body. P,gnp -11- Packet Page -2741- Tic ^e :, sea!e -- an.' oeiive " ir, the r)resen;,� o'6, Witnesses as to Principal STATE OF _ COUNTY OF By: _ Name: Its: The foregoing instrument was acknowledged before me this of 200_, by as of a corporation, on behalf of the corporation. He /she is personally known to me OR has produced as identification and did (did not) take an oath. My Commission Expires: (AFFIX OFFICIAL SEAL) ATTEST: Witness as to Surety (Signature of Notary) Name: (Legibly Printed) Notary Public, State of Commission No.: SURETY: (Printed Name) (Business Address) (Authorized Signature) (Printed Name) OR Page -12- Packet Page -2742- Witnesses As Attorney in Fact (Attach Power of Attorney; (Business Address) (Printed Name) (Telephone Number) STATE OF COUNTY OF The foregoing instrument was acknowledged before me this day of 200_, by as of Surety, on behalf of Surety. He /She is personally known to me OR has produced as identification and who did (did not) take an oath. My Commission Expires: (AFFIX OFFICIAL SEAL) (Signature of Notary) Name: (Legibly Printed) Notary Public, State of _ Commission No.: Paae -13- Packet Page -2743- 6=XHiBE k PUBLIr PERFORMANCE BONZ. . ?. Contract No. 08 -5011 KNOW ALL MEN BY THESE PRESENTS: That as Principal, and as Surety, located at (Business Address) are held and firmly bound to as Oblige in the sum of ($ ) for the payment whereof we bond executors, personal representatives, successors and assigns, jointly and severally. WHEREAS, Principal has entered into a contract dated as of the 200_, with Oblige for day of ourselves, our heirs, in accordance with drawings and specifications, which contractor is incorporated by reference and made a pat hereof, and is referred to as the Contract. THE CONDITION OF THIS BOND is that if Principal: 1. Performs the Contract at the times and in the manner prescribed in the Contract, and 2. Pays Oblige any and all losses, damages, costs and attorneys' fees that Oblige sustains because of any default by Principa" under the Contract, including, but not limited to, all delay damages, whether liquidated or actual, incurred by Oblige; anc 3. Performs the guarantee of all work and materials furnished under the Contract for the time specified in the Contract, then this bond is void; otherwise it remains in full force. Any changes it or under the Contract and compliance or noncompliance with any formalities connected with the Contract or the changes do not affect Sureties obligation under this bond. The Surety, for value received, hereby stipulates and agrees that no changes, extensions of time, alterations or additions to the terms of the Contract or other work to be performed hereunder, or the specifications referred to therein shall in anywise affect its obligations under this bond, and it does hereby waive notice of any such changes, extensions of time, alternations or additions to the terms of the Contract or to work or to the specifications. Pana -1A- Packet Page -2744- "11 /20 41 "r- item 6'.:_'i v nis instrumen'" sna bE construer- ir, all respects a5 'c common la\n oond. I -. is expressiN, unaerstooc that the time provisions and statute of limitations undery Section 255.05, Florida Statutes, shall not apply to this bond. In no event will the Surety be liable in the aggregate to Oblige for more than the penal sum of this Performance bond regardless of the number of suits that may be filed by Oblige. IN WITNESS WHEREOF, the above parties have executed this instrument this day of 200_, the name of each party being affixed and these presents duly signed by its undersigned representative, pursuant to authority of its governing body. Signed, sealed and delivered in the presence of: Witnesses as to Principal STATE OF _ COUNTY OF PRINCIPAL: By: _ Name: Its: The foregoing instrument was acknowledged before me this 200_, by , as ,a He /She is personally known to me OR has produced did (did not) take an oath. My Commission Expires: (AFFIX OFFICIAL SEAL) day of of corporation, on behalf of the corporation. as identification and (Signature of Notary) Name: (Legibly Printed) Notary Public, State of Commission No.: Pant- -15- Packet Page -2745- Witness as to Surety Witnesses (Printed Name) (Business Address) (Authorized Signature) (Printed Name) OR As Attorney in Fact (Attach Power of Attorney) (Business Address) (Printed Name) iTelephone Number STATE OF COUNTY OF The foregoing instrument was acknowledged before me this day of 200_, by as of Surety, on behalf of Surety. He /She is personally known to me OR has produced as identification and who did (did not) take an oath. My Commission Expires: (AFFIX OFFICIAL SEAL) (Signature of Notary) Name: (Legibly Printed) Notary Public, State of _ Commission No.: Pane -1R- Packet Page -2746- EXHIS" i RELEASE AND, A = =IDAV7 =CRIV COUNTY OF COLLIER STATE OF FLORIDA ) 9/1 0 12 Item 1 .; . `i . Before me, the undersigned authority, personally appeared who after being duly sworn, deposes and says: (1) In accordance with the Contract Documents and in consideration of $ paid, ( "Contractor ") releases and waives for itself and it's subcontractors, material -men, successors and assigns, all claims demands, damages, costs and expenses, whether in contract or in tort, against the Board of County Commissioners of Collier County, Florida, relating in any way to the performance of the Agreement between Contractor and Owner, dated , 200_ for the period from to (2) Contractor certifies for itself and its subcontractors, material -men, successors and assigns, that all charges for labor, materials, supplies, lands, licenses and other expenses for which Owner might be sued or for which a lien or a demand against any payment bond might be filed, have been fully satisfied and paid. (3) Contractor agrees to indemnify, defend and save harmless Owner from all demands or suits, actions, claims of liens or other charges filed or asserted against the Owner arising out of the performance by Contractor of the Work covered by this Release and Affidavit. (4) This Release and Affidavit is given in connection with Contractor's [monthly /final] Application for Payment No. M ITS: DATE: Witnesses STATE OF _ COUNTY OF CONTRACTOR President [Corporate Seal] The foregoing instrument was acknowledged before me this day of , 200_, by , as of , a corporation, on behalf of the corporation. He /she is personally known to me or has produced as identification and did (did not) take an oath. My Commission Expires: NAME: (Signature of Notary) (Legibly Printed) (AFFIX OFFICIAL SEAL) Notary Public, State of Commissioner No.: Pane -17- Packet Page -2747- i EXHIBiF =ORIV OF COI!'T 121\ ^:. E PLYMEI (County Project Manager) RFP No (County Department) Project No. Collier County Board of County Commissioners (the OWNER) Application Date 08 -5011 iierc FROM: (Contractor's Representative) Payment Application No. (Contractor's Name) for Work accomplished through the (Contractor's Address) Date: RE: (Project Name) Original Contract Time: Original Contract Amount: $ Revised Contract Time: Total Change Orders to Date $ Revised Contract Amount $ Total value of Work Completed and stored to Date $ Percent Work completed to Date: % Less Retainage $ Percent Contract Time completed Total earned Less Retainage $ to Date % Less previous payment (s) $ AMOUNT DUE THIS APPLICATION: $ ATTACH SCHEDULE OF VALUES AND ACCOMPANYING DOCUMENTATION TO THIS APPLICATIOR CONTRACTOR'S CERTIFICATION: The undersigned CONTRACTOR certifies that:.(1) all previous progress payments received from OWNER on account of Work done under the Contract referred to above have been applied to discharge in full all obligations of CONTRACTOR incurred in connectior with Work covered by prior Applications for Payment numbered 1 through inclusive; (2) title to all materials and equipment incorporated in said Work or otherwise listed in or covered by this Application for Payment will pass to OWNER at time of payment free and clear of all liens, claims, security interests and encumbrances (except such as covered by Bond acceptable to OWNER); (3) all amounts have been paid for work which previous payments were issued and received from the OWNER and that current payment is now due; (4) and CONTRACTOR agrees that all overruns as shown on the monthly estimate summary shall, in fact, be added to the revised contract and shall be incorporated into a future Change Order: By CONTRACTOR: (Contractor's Name) (Signature) DATE: (Type Name & Title) (shall be signed by a duly authorized representative of CONTRACTOR) Payment to the CONTRACTOR for the above AMOUNT DUE THIS APPLICATION is recommended: By Design Professional : (DP's Name) (Signature) DATE: (Type Name & Title) Payment to the CONTRACTOR for the above AMOUNT DUE THIS APPLICATION is approved: By OWNER'S Project Manager: (Signature) DATE: _ (Type Name and Title) Rana -1 R- Packet Page -2748- XHIBI E. CHANGS ORDE F' CHANGE ORDER NO. TO: DATE: PROJECT NAME: PROJECT NO.: 9! ";' II 2 0 E2 1terr, 'I EE .:,.' CONTRACT NO. 08 -5011 Under our AGREEMENT dated , 200_ You hereby are authorized and directed to make the following change(s) in accordance with terms and conditions of the Agreement: FOR THE (Additive) (Deductive) Sum of: $ ($ ) Original Agreement Amount $ Sum of Previous Changes $ This Change Order (Add) (Deduct) $ Present Agreement Amount $ The time for completion shall be (increased /decreased) by calendar days due to this Change Order. Accordingly, the Contract Time is now U calendar days. The substantial completion date is and the final completion date is Your acceptance of this Change Order shall constitute a modification to our Agreement and will be performed subject to all the same terms and conditions as contained in our Agreement indicated above, as fully as if the same were repeated in this acceptance. The adjustment, if any, to the Agreement shall constitute a full and final settlement of any and all claims of the Contractor arising out of or related to the change set forth herein, including claims for impact and delay costs. Accepted: 200 CONTRACTOR: OWNER: BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA By: By: DESIGN PROFESSIONAL: By: Panes -1 A- Packet Page -2749- iW .x01 �4vCie'G.. GER7PPP' .A 7 - OF LI.ABILE € t' INSURANCE 9;"ii 112_ - fte THIS CEP.TIFIC4.Tc 1S ISSUECk x.. L: ME_" TEF 0= W= ORMATIDE ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE- ": ob :-L. lresue a ce C=ou;. Iii- . HOLDER. THIS CERTIFICATE DOES NOT AMENC. EXTEND OF O 't47 N. Meridian SL. Ste. 30C ALTER THE COVERAGE AFFORDED BYTHE POLICIES BELOV� lianapolis IN 46260 Aone:317- 844 -7759 Fax:317- 844 -9910 INSURERS AFFORDING COVERAGE NAIC# INSURED INSURER A: Zurich amerieen In$. company INSURER B: arch Specialty insurance CO- 21199 Mitchell & Stark Construction INSURER C: Comparep , Inc. - Florida 6001 SIzirle Street INSURER D: Naples FL 3109 INSURER E: P nMICDAr_CC THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. LTR NSR TYPE OF INSURANCE POLICY NUMBER DATE MMIDD DATE MMIDD LIMITS • X GENERAL LIABILITY X COMMERCIAL GENERAL LIABILITY CLAIMS MADE ' K OCCUR GL0464148403 (08) 03/01/08 03/01/09 EACH OCCURRENCE $1,000,000 RENITED PREMISES Eaoccurence $ 300, 000 MED EXP (Any one person) $ 10,000 PERSONAL & ADV INJURY $ 1,000,000 GENERAL AGGREGATE $ 2,000,000 GEN'L AGGREGATE LIMIT APPLIES PER: POLICY X JECOT F7 LOC PRODUCTS - COMP /OP AGG $ 2,000,000 • AUTOMOBILE LIABILITY ANY AUTO ALL OWNED AUTOS SCHEDULED AUTOS HIRED AUTOS NON- OWNEDAUTOS BAP464148303(08) i 03/01/08 03/01/09 I COMBINED SINGLE LIMIT (Ea accident) $1,000,000 X BODILY INJURY (Per person) $ X BODILY INJURY (Per accident) $ X PROPERTY DAMAGE (Per accident) $ GARAGE LIABILITY ANY AUTO AUTO ONLY - EA ACCIDENT $ j OTHER THAN EA ACC i AUTO ONLY: AGG F B EXCESSIUMBRELLA LIABILITY F. OCCUR CLAIMS MADE ULP000476303 (08) DEDUCTIBLE X RETENTION $ 0 03/01/08 03/01/09 EACH OCCURRENCE S 2(j,000,001 AGGREGATE $20,000,000 $ $ $ A WORKERS COMPENSATION AND EMPLOYERS' LIABILITY ANY PROPRIETOR/PARTNER/EXECUTIVE OFFICER/MEMBER EXCLUDED? yes, describe under SPECIAL PROVISIONS below S WC464148503 (08) 03/01/08 03/01/09 X TORY LIMITS ER E.L. EACH ACCIDENT $ 1,000,000 E.L. DISEASE - EA EMPLOYEE $1,000,000 E.L. DISEASE - POLICY LIMIT $1,000,000 OTHER DESCRIPTION OF OPERATIONS I LOCATIONS / VEHICLES / EXCLUSIONS ADDED BY ENDORSEMENT I SPECIAL PROVISIONS ADDITIONAL INSURED [GENERAL LIABILITY]: COLLIER COUNTY BOARD. OF COMMISSIONERS. RE: CONTRACT #08- 5011 - 11ANNUAL CONTRACT FOR UNDERGROUND UTILITY CONTRACTING SERVICES ". CERTIFICATE HOLDER COLLIER COUNTY BOARD OF COMMISSIONERS 3301 EAST TAMIAMI TRAIL NAPLES FL 34112 ACORD 25 (2001108) COLLI -8 CANCELLATION SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATIO DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL 3 0 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO SO SHALL IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE INSURER, ITS AGENTS OR REPRESENTATNES. Packet Page -2750- CORPORATION 1988 .iC1.�' -r ti ,.y YOU ARE THE RECIPIENT OF THIS CERTIFICATE IAN.' WORDING TO INCLUDE THE HOLDEF. AS AF ADDITIONAL INSURES, PROVIDE COVEF.AGE OA A PRIMARY AND NON - CONTRIBUTORY BASIS, OR PROVIDE F WAIVER OF SUBROGATION APPLIES ONLY WHERE REQUIRED BY WRITTEN CONTRACT OR AGREEMENT IF YOU ARE THE REQUESTOR TO PROVIDE THIS CERTIFICATE: Tobias Insurance Group, Inc. has, upon your request, issued the attached Certificate of Insurance. If you did not already, we highly recommend that you provide our Agency with a copy of the insurance and indemnification provisions of the contract pertaining to the certificate request so that we may properly ascertain whether your insurance program addresses the terms, types and amounts of insurance coverage referenced by the contract. While most certificates can be issued at no cost to you, the contract may identify insurance requirements that require the purchase of insurance coverage at an additional premium. In some instances, the coverage identified in the contract may be outside the underwriting guidelines of the insurance carrier and cannot be obtained. In other instances, you may not wish to purchase the additional coverage and may attempt to negotiate changes in the insurance requirements. In performing the review of your contracts, neither Tobias Insurance Group, Inc. nor its employees are providing legal advice or a legal opinion concerning any portion of the contract. Our Agency is not undertaking to identify all potential liability that might arise under this contract. This review is provided for your information and should not be relied upon by third parties. Any description of insurance coverage is subject to the terms, conditions, exclusions and other provisions of the policies and any applicable regulations, rating rules or plans. Packet Page -2751- f vD 7PY County Administrabve Services Division Purchasing December 20, 2011 Mr. Brian Penner Mitchell & Stark Construction 6001 Shirley Street Naples, FL 34109 Fax: 239 -566 -7865 Email: boenner(W- mitchellstark.com RE: Renewal of Contract #08 -5011 "Underground Utility Contracting Services" Dear Ms. Penner: Collier County would like to renew the above agreement under the same terms and conditions for one (1) additional year in accordance with the renewal clause in the agreement. Per your agreement/contract, you may at time of renewal request a price increase. If you are agreeable please indicate your intentions by providing the appropriate information as requested below: I am agreeable to renewing the above referenced contract under the g 9 same terms, conditions, and pricing as the existing contract. The following attached documentation must be provided with response. • Provide updated and current insurance certificate I am not agreeable to renewal of this contract. By your signature this contract will be in effect from March 11, 2012 until March 10, 2013. Pt alk*V D pet mt- 3327 Tamiarti Tral East • Naples, Florida 34112.4901 • www.WftWV.rteVPtrrchaWng Packet Page -2752- 9!h1f29 '6 2, lie- 16.x, .;. Page 2 of 2 RE: Renewal of Contract #08 -5011 "Underground Utility Contracting Services" Please return this letter to the Purchasing Department with your response and a current insurance certificate at your earliest convenience: If you have any questions you may contact me at 239-252 - 6020, email brendareaves(M-colliengov.net and fax 239 - 252 -6592. y Best regards, f Steve Y. Camell Director — Purchasing / General Services '1�f���l��,tfr� S fi�4..h i 'r � � ^�` + _ i `I s S +� re� •��2�iW 'luu` w f � � � .. 1 R 6 ■ reY a�s�S. i cbi?w czf, �. ^ 1 Name of Company e, L ^IS ,— C c • -v L Company Signature - Telephone Number (Corporate Officer Print Corporate Officer ' FAX Number �- Name Signature Date j Email'Address 2 '1�f���l��,tfr� S fi�4..h i 'r � � ^�` + _ i `I s S +� re� •��2�iW 'luu` w f � � � .. d Ei �/i0 a�s�S. i cbi?w czf, �. ^ 1 Contact Name - Telephone Number FAX Number 30z — -5 G -- 7 Email'Address Address S T= N l e 5 3 / C: Pam Libby, PUED - Packet Page -2753- a a �C Adn-onisnuve Services Dvision "Urc..hasinq REQUEST FOR QUOTATIONS FOR MULTIPLE PROECTS UNDER CONTRACT #08 -5011 "Annual Contract for Underground Utilities" Date: July 11, 2012 From: Nicole Parker, Contract Specialist 239 - 252 -4270, Telephone Number 239 - 252 -6549, Fax Number nicoieparker c(�colliergov.net To: Prospective Vendors Subject: RFQ #08- 5011 -68 Pump Station 103.03 Rehabilitation Project As provided in the referenced contract, the Collier County Purchasing Department is soliciting quotes for the referenced project. Your response must be received in the Purchasing Department, 3327 E. Tamiami Trail Naples, Florida 34112 or via email to nicoleDarker(�collieroo�l.ne° no later than 11:00 a.m. on August 7, 2012. Any response received after that time shall not ae considered. All quotations for this project shall be in accordance with the terms, conditions, and specifications stated herein and in accordance with the terms and conditions of Contract #08 -5011 of which your firm was an awardee. NO OTHER FIRMS ARE ELIGIBLE TO SUBMIT OR RECEIVE AN AWARD FOR THIS PROJECT. If you have any questions regarding the specifications or intended scope of work, you must make those inquiries by 11:00 a.m. July 25, 2012. For general questions, you may contact the Purchasing staff member noted above. Your quotation response for this project is due no later than the date and time specified above. We will not accept any quotation responses later than the noted time and date. If your firm is unable to respond electronically, your quotation must be received in the office of the Purchasing Department at the above referenced address no later than the time and date specified. No late quotation responses will be accepted. We look forward to your participation in this request for information /quotation process. cc: Zamira DelToro, Project Manager Packet Page -2754- RFQ _ContractDriven_RevisedSeptem ber2009 1 9!11 1121012 Item 1 ✓. .`,. Genera'! inror mat :or The proposed project will be quoted anti awaraed to the contractor with the lowest cost Each Contractor will be able to take a visual inspection of the existing conditions of the Pump Station; the Project Site (PS103.03) will be available to the bidders on July 18, 2012 (Wednesday) from 9:00 a.m. to 10:00 a.m. if Contractors want to attend. However, a non - mandatory pre -bid meeting is scheduled for July 20, 2012 (Friday) at 3:30 p.m. at the Purchasing Conference Room A. Although this is not a mandatory meeting, it is advisable that all bidders attend. II. Specifications 1. See emailed file for this project. Pump Station 103.03, Civil and Electrical Plans, Project Specifications, Quote form, etc. 2. Days to substantial and final completion from notice to proceed for this project: Pump Station 103.03, 120 days to Substantial + 60 Days to Final 111. Instructions 1. Complete Vendor's name, sign and date on all pages where so indicated. This will constitute your acceptance of the specifications, terms and conditions as listed. If taking exception to any part or section of this request for information /quotation, please indicate such exceptions on a separate sheet entitled "Exceptions." 2. Your quote may not be accepted unless all requested information is furnished. 3. The Collier County Purchasing Department reserves the right to reject any and all quotes. 4. All quotations for this project must be made on the quotation form furnished by the County. No quote will be considered unless the quotation form is properly signed. 5. All work completed shall be under the terms and conditions of the above referenced contract. 6. Liquidated Damages Owner and Contractor recognize that, since time is of the essence for this agreement, Owner will suffer financial loss if the Work is not substantially completed within the time specified above. Should Contractor fail to substantially complete the Work within the number of calendar days for substantial completion established herein, Owner shall be entitled to assess, as liquidated damages, but not as a penalty, $558.00 for each calendar day thereafter until Substantial Completion is achieved. Further, in the event Substantial Completion is reached, but the contractor fails to reach Final Completion, Owner shall also be entitled to assess, as liquidated damages, but not as a penalty, a sum certain per day, in the amount of $279.00 for each day after the time set for Final Completion. 7. Performance and payment bonds shall be required if the lowest responsive quote exceeds $200,000. RFQ_ContractDriven_Revised Septem ber2009 2 Packet Page -2755- "11 201 Iterr i E. r`'dentn ,�auve ',ervicesDvision urdhasing COLLIER COUNTY FLORIDA REQUEST FOR QUOTATION RFQ #08- 5011 -68 Pump Station 103.03 Rehabilitation PROPOSAL PAGE DUE DATE: August 7, 2012 at 11:00 a.m. The undersigned, as quoter, hereby declares that the firm has examined the specifications and is informed fully in regard to all terms and conditions pertaining to the project and, if this Proposal is accepted, to furnish same in full, according to the following: See separate Quote Schedule IN WITNESS WHEREOF, WE have hereunto subscribed our names on this , 2012 in the County of , in the state of day of Firm's Complete Legal Name Telephone Number FAX Number Email Address Address City State Zip Florida Certificate of Authority Document Number (www.sunbiz.org /se.arch/html) Signature Title Print Name Date RFQ_ContractDHven_RevisedSeptem ber2009 3 Packet Page -2756- 9,111 i'20 it 2 Item 16.G ' . From: ParkerNicole Sent: Monday, July 16, 2012 7:39 AM To: ParkerNicole; Ryan; Belwell; Mike Westhafer; Brian Penner; Tammy Ludwig; Brandy Bartolone (brandyb@dnhiggins.com); Lou Gaudio; Marcie Cohen; Kyle Construction Inc; HHASKINS @HASKINSINC.NET Cc: DeltoroZamira Subject: ADDENDUM #1 - RFQ #08- 5011 -68 Pump Station 103.03 Good morning —the pre -quote meeting time for this project has been changed to: Friday,—* 20 2012 at 11:30am at Purchasing Conference Room A Thank You!!! From: ParkerNicole Sent: Wednesday, July 11, 2012 11:40 AM To: ParkerNicole; Ryan; Belwell; Mike Westhafer; Brian Penner; Tammy Ludwig; Brandy Bartolone (brandyb @dnhiggins.com); Lou Gaudio; Marcie Cohen; Kyle Construction Inc; HHASKINS @HASKINSINC. NET Cc: DeltoroZamira Subject: RFQ #08- 5011 -68 Pump Station 1.03.03 Good rnornln — please see tnce iittalined! R, C'j, Q(joJie' ne;:; , t�OP, and Pans Tnari . IN; - - ie, par; e! Procurement Strategist Collier County Purchasing Department 3327 -1arniami Trail East Napkes, R_ 4112 Tel: 239 -252 -4270 Fax: 139-252-6549 Email: nicoleparkerPcollierRov. net Packet Page -2757- From: ParierNicoie Sent: Wednesday, August 01, 2012 11:45 AM To: ParkerNicoie; Ryan; Belwell; Mike Westhafer; Brian Penner; Tammy Ludwig; Brandy Bartolone (brandyb@dnhiggins.com); Lou Gaudio; Marcie Cohen; Kyle Construction Inc; HHASKINS @HASKINSINC.NET Cc: DeltoroZamira; PajerCraig Subject: ADDENDUM #2 - RFQ #08- 5011 -68 Pump Station 103.03 Hello - Please see the attached quote from Flyte — Thanks!!!!!!!! From: ParkerNicoie Sent: Monday, July 16, 2012 7:39 AM To: ParkerNicoie; Ryan; Belwell; Mike Westhafer; Brian Penner; Tammy Ludwig; Brandy Bartolone (brandyb @dnhiggins.com); Lou Gaudio; Marcie Cohen; Kyle Construction Inc; HHASKINS @HASKINSINC.NET Cc: DeltoroZamira Subject: ADDENDUM #1 - RFQ #08- 5011 -68 Pump Station 103.03 Good morning — the pre -quote meeting time for this project has been Changed to: Friday, JuIV 20, 201.2 at 11:30am at Purchasing Conference Room A Thank, You!! From: ParkerNicoie Sent: Wednesday, July 11, 2012 11:40 AN Ta: ParkerNicoie; Ryan; Belwell; Mike Westnafer; Briar Penner; Tammy Ludwig; Brandy Bartolone (brandyb@dnhiggins.com); Lou Gaudio; Marcie Cohen; Kyle Construction Inc; HHASKINS @HASKINSINC.NET Cc: DeltoroZamira Subject: RFQ #08- 5011 -68 Pump Station 103.03 Good morning, — please see the attached PFt1.. C'tuott. Schedule, SpE cifhc:ations and Plana. Thank,. Nicole Parker Procurement Strategist Collier County Purchasing Department 3327 Tamiami Trail East Naples, FL 34112 Tel; 239- 252 -42,'0 Fax: 239 252 6549 Email: nicoleparker @collierRov.net Packet Page -2758-