Agenda 05/22/2018 Item #16C 905/22/2018
EXECUTIVE SUMMARY
Recommendation to authorize payment of invoices in the amount of $635,540.62 to US Energy
Service & Pure Air Control Services, Inc., for indoor air quality testing and mitigation services
related to the Hurricane Irma storm recovery mission completed prior to the FEMA March 4,
2018 deadline.
OBJECTIVE: To provide final payment of invoices in the amount of $635,540.62 to US Energy Service
& Pure Air Control Services, Inc., for indoor air quality testing and mitigation services related t o the
Hurricane Irma storm recovery mission completed prior to the FEMA March 4, 2018 deadline.
CONSIDERATIONS: Hurricane Irma made landfall in Collier County during the afternoon of
September 10, 2017 as a Category 4 hurricane, severely impacting Collier County as well as the entire
State. In the wake of the hurricane, twenty-nine (29) county facilities experienced water intrusion and a
substantial amount of humidity due to the resulting extended power loss to HVAC systems. Some of the
impacted facilities include: County Courthouse, IFAS, CCSO Special Operations Facility, GMD
Transportation, GMD Development Services, North Collier Regional Park facilities, etc. This caused
visible signs of mold and indoor air quality hazards within County owned facilities. The mitigation efforts
involved the deconstruction of County facility walls, flooring, insulation, HVAC equipment remediation,
etc., that had been contaminated due to the water intrusion and high humidity levels. Failure to mitigate
these hazards could have significantly impacted business operations and placed county staff, including
customers, in potential hazardous indoor air quality conditions. Collier County Facilities Management
was tasked with providing indoor air quality testing and mitigation ser vices to remediate the safety
hazards identified. The extent of damage left by Hurricane Irma required County staff to employ Pure Air
for these services, as the few local vendors available were utilized to their full capacity. In total, the
County procured work at twenty-nine (29) county locations related to indoor air quality testing and
mitigation services.
The Facilities Management Director directed staff to utilize this vendor without a contract in place to
address urgent need and demand. Procurement ordinance 2017-08 states: “Following a declaration of the
existence of an emergency situation by the County, the Collier County Board of County Commissioners
or their designee may declare the existence of an emergency procurement condition and may suspen d any
or all of the provisions of this article and authorize an emergency procurement.”
Pure Air conducted services under an emergency purchase order, based on the emergency procurement
procedures. The purchase order was created on September 13, 2017 in the amount of $1.00. By
November 13, 2017, the purchase order had been increased four times to support the amount of work
being conducted for a final total of $947,917.50. Notably, Pure Air has already been paid for work
performed up to October 4, 2017, in the amount of $197,714.00.
Purchase Order Approval History:
Date: Increased: Total: Notes:
September 15, 2017 $1.00 $1.00 Purchase Order Requisitioned
September 22, 2017 $5,479.00 $5,480.00 Increased
October 26, 2017 $39,150.00 $44,630.00 Increased
October 26, 2017 $3,287.50 $47,917.50 Increased
November 13, 2017 $900,000.00 $947,917.50 Increased
During the PUD Disaster Recovery meeting of November 8, 2017, County staff was advised by its FEMA
16.C.9
Packet Pg. 869
05/22/2018
consultant, CDR Maguire, to continue utilizing the phase one purchase order for Pure Air until no later
than March 10, 2018, per FEMA regulations for reimbursement purposes. The County was also advised
to submit the Osceola County piggyback contract rate sheet, for price reasonableness purposes only; that
piggyback contract was not used for this emergency. On February 15, 2018, the FEMA deadline was
updated to March 4, 2018. At that time, no further work was conducted with Pure Air, under the
emergency purchase order. Any subsequent work beyond the March 4, 2018 deadline is being solicited
using the FEMA phase two permanent work process.
FISCAL IMPACT: Funds are available in the County established Hurricane Irma project 50154 in the
County-wide Capital Fund 301for recovery efforts of emergency repairs. The fiscal impact of
$635,540.62 may be reimbursed by FEMA funding and is coming from the established recovery fund.
The Osceola County Contract is being used for cost reasonableness for payment of the invoices.
LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority
vote for Board approval. -SRT
GROWTH MANAGEMENT IMPACT: There are no Growth Management impacts associated with
this action.
RECOMMENDATION: That the Board of County Commissioners authorize payment of invoices in
the amount of $635,540.62 to US Energy Service & Pure Air Control Services, Inc. for indoor air quality
testing and mitigation services related to the Hurricane Irma storm recovery mission completed prior to
the FEMA March 4, 2018 deadline.
Prepared by: Miguel Carballo, CFM, Manager of Facilities, Public Utilities Department
ATTACHMENT(S)
1. PUD Disaster Recovery Meeting Notes 11-8-17 (PDF)
2. Pure Air - Rate Sheet for Cost Reasonableness (PDF)
3. FEMA Deadline Change Email (PDF)
4. Pure Air - Rate Sheet (PDF)
5. Pure Air - Invoice Spreadsheet (PDF)
16.C.9
Packet Pg. 870
05/22/2018
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.C.9
Doc ID: 5618
Item Summary: Recommendation to authorize payment of invoices in the amount of $635,540.62
to US Energy Service & Pure Air Control Services, Inc. for indoor air quality testing and mitigation
services related to the Hurricane Irma storm recovery mission completed prior to the FEMA March 4,
2018 deadline.
Meeting Date: 05/22/2018
Prepared by:
Title: – Facilities Management
Name: Linda Best
05/09/2018 5:18 PM
Submitted by:
Title: Deputy Department Head – Solid and Hazardous Waste
Name: Dan Rodriguez
05/09/2018 5:18 PM
Approved By:
Review:
Facilities Management Linda Best Additional Reviewer Completed 05/09/2018 5:19 PM
Solid and Hazardous Waste Dan Rodriguez Additional Reviewer Completed 05/09/2018 7:39 PM
Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 05/10/2018 8:08 AM
Procurement Services Sara Schneeberger Additional Reviewer Completed 05/10/2018 9:26 AM
Procurement Services Catherine Bigelow Additional Reviewer Completed 05/10/2018 9:28 AM
Public Utilities Operations Support Joseph Bellone Additional Reviewer Completed 05/11/2018 7:50 AM
Procurement Services Ted Coyman Additional Reviewer Completed 05/11/2018 9:07 AM
Facilities Management Miguel Carballo Additional Reviewer Completed 05/11/2018 2:57 PM
Solid and Hazardous Waste Sarah Hamilton Additional Reviewer Completed 05/11/2018 3:03 PM
Public Utilities Department Sarah Hamilton Level 1 Division Reviewer Completed 05/14/2018 9:35 AM
Public Utilities Department Joseph Bellone Level 2 Division Administrator Review Completed 05/14/2018 9:56 AM
County Attorney's Office Scott Teach Level 2 Attorney Review Completed 05/15/2018 9:16 AM
Grants Therese Stanley Additional Reviewer Completed 05/15/2018 12:53 PM
Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 05/15/2018 10:59 AM
County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 05/15/2018 11:34 AM
Office of Management and Budget Susan Usher Additional Reviewer Completed 05/15/2018 4:15 PM
16.C.9
Packet Pg. 871
05/22/2018
County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 05/16/2018 9:10 AM
Board of County Commissioners MaryJo Brock Meeting Pending 05/22/2018 9:00 AM
16.C.9
Packet Pg. 872
Paying Fund Service Date Time Period Vendor Description Estimated Cost Verified Cost Notes Guidance
301 9/13/2017 Action Automatic Door Co WO# 201771831 - CAT Morande - Security gate
not closing - west gate.
PO 4500180321 - Work has not started -
Waiting on replacement parts continue emergency work
301 9/13/2017 Action Automatic Door Co WO# 201771853 - Building W -Maintenance lot
gate damaged.
PO 4500180321 - Work has not started -
Waiting on replacement parts continue emergency work
301 9/22/2017 Simmonds Electrical WO# 201772768 - Immokalee Jail - Re-secure
lighting rods and cables.1,215$ PO 4500180360 - Waiting on replacement
parts continue emergency work
301 9/28/2017 Commercial Electrical
Systems
Work requested 9/28/17 - Various locations -
Repair all down or damaged life safety security
equipment.
Work started but paused as cameras were
back ordered and unavailable.ordered but not received; continue emergency work
301 9/28/2017 Power Pro Tech
Various locations - Do full service on all
generators to return to and confirm pre-storm
working order.
PO 4500180358 - Work is ongoing -
Waiting on technicians/parts in order to
complete all on the list.
continue emergency work
301 10/19/2017 Simmonds Electrical
Replace knocked down 35’ pole with single
fixture (Government Center Bldg. W Parking Lot
Pole #82). Work has not begun. Estimate
received 10/31/17. Division was not notified of
the damage until 10/19/17
5,354$ 5354 PO 4500180360 Cat E - Buildings - continue as permanent work; FEMA compliant; put on
Facilities permanent work list
301 Chris Tel Everglades City Museum; historical justify & finish by November 9; not expected to be completed by Nov 9;
ok
301 DEC courthouse & judges chambers justify & finish by November 9; will be completed by Nov 9; ok if go past
301 FA Remodeling
Isle of Capri Fire Station - we have to replace
part of the metal roof and install new gutters
and downspouts that were affected by the
storm.
PO 4500180343 - vendor is waiting to get
the 5V metal roof available. Due to high
demand for this material and low stock
available FA haven’t been able to receive
the material and complete the installation.
temporary measures taken; not continued because unavalable materials
needed to be procured; continue emergecy work
301 FA Remodeling Pelican Bay Admin building - replacing many
shingles that were removed by the Hurricane.
PO 4500180343 - Due to the high demand
for roof supplies and low stock available
our roof contractor FA remodeling haven’t
been able to complete the repairs needed.
temporary measures taken; not continued because unavalable materials
needed to be procured; continue emergecy work
301 Pure Air indoor air quality pre-testing complete- now
remediation & post testing 900,000$ will not be complete by Nov 9; ok to continue
301 Barefoot Beach Restroom roof damage, water
not functioning justify & finish by November 9; will not complete by Nov 9; ok
301 Pepper Ranch Visitors Center mold proceed on emergecy basis
301 Sun & Fun - exhaust hood hole with water
pouring in, damage to building will be on Facilities permanent list; may have a temporary component
412 AMEC engineering reports keep going
412 EQ Diesel spill in Wellfield remediation - Tamiami
25 200,000$ PO 4500181796
justify & finish by November 9; Testing new well to see if ground water is
still contaminated. Will know more when results come in. quarterly
monitoring for a couple of years
16.C.9.a
Packet Pg. 873 Attachment: PUD Disaster Recovery Meeting Notes 11-8-17 (5618 : US Energy Service & Pure Air Control
Paying Fund Service Date Time Period Vendor Description Estimated Cost Verified Cost Notes Guidance
412 Quality Enterprises Tamiami 25- Diesel Fuel Spill; put site back
together, repairs to site / well 60,000$ PO #4500180425- ?
emergency work done; no permanent work yet; Have been billed for all
emergency to this point.; ok to continue emergency with QE; get quote
and be invoiced per quote
412 Power Pro Tech Temporary generators at Tamiami 18 and Raw
Water Booster Station 30,000$ PO 4500180391
RWBS done but not sure if billed yet. Tamiami 18 still has portable
generator. Power Pro Tech is only for temp, will need to have quotes for
permanent.
412 N/A Tamiami 18- generator damaged beyond repair
during Irma.140,000$ N/A this is the permanent component; follow FEMA compliant permanent
work guidance; already on permanent list
414 AMEC engineering reports keep going
414 Data Flow Systems, Inc.
Over 40 Telemetry Control Units (TCU) were
damaged during Irma. This TCU needs extensive
repair. Refer to PDF DFS 1 with Order #51852-
RA.
5,188$ 5,188$
Normal circumstances for repair is one
week turn around time; due to Irma,
receipt of repaired TCU & invoice is
undetermined. Using IRMA PO
4500180383.
justify & finish by November 9; last items will not be done by Nov 9;
maybe 2 more weeks from 11/15
414 Data Flow Systems, Inc.
Over 40 Telemetry Control Units (TCU) were
damaged during Irma. This TCU needs extensive
repair. Refer to PDF DFS 2 with Order #51447-RA
2,166$ 2,166$
Normal circumstances for repair is one
week turn around time; due to Irma,
receipt of repaired TCU & invoice is
undetermined. Using IRMA PO
4500180383.
justify & finish by November 9; last items will not be done by Nov 9;
maybe 2 more weeks from 11/15
414 Data Flow Systems, Inc.
Over 40 Telemetry Control Units (TCU) were
damaged during Irma. These TCUs are
moderately damaged and will be invoiced as
repairs are determined.
25,000$
Normal circumstances for repair is one
week turn around time; due to Irma,
receipt of repaired TCUs and invoice(s) is
undetermined. Using IRMA PO
4500180383.
justify & finish by November 9; 22 remaining, 2 under warranty, 20 not
under warranty; will not be done by Nov 9; maybe 2 more weeks from
11/15
414 Hart's Electrical, Inc.
Replace TVSS Unit for Master Pump Station
102.00 damaged during IRMA; to provide 30
amp Fused Switch for Fuse Protection to be
installed at Main Service.
3,395$ 3,395$
This is a 'not to exceed' estimate for
budget consideration. Using IRMA PO
4500180375.
justify & finish by November 9; will not be complete by Nov 9; part is 2
weeks out from 11/15
414 Power Pro Tech
Various locations - Do full service on all
generators to return to and confirm pre-storm
working order.
not complete; may be 2 weeks from 11/15
414 US Submergent Remove grit from NCWRF 900,000$ proceed after BCC approvalf; Dec BCC meeting; also on permanent work
list
414 Xylem Dewatering diesel pump repair 103 Piper Blvd justify & finish by November 9; not complete 11/15; Work scheduled
474 AMEC engineering reports keep going
412 / 414 Carter Fence Company temp fix to fence / gate for security at NESA
Orange Tree Water / Wastewater plant site 1,000$
new 11/13; do not proceed; temp fix manual operation accomplished;
guard compete; temp work proceeding in cost center 210105 under
regular procurement without expectation of reimbursement
2,273,318$ 16,103$
16.C.9.a
Packet Pg. 874 Attachment: PUD Disaster Recovery Meeting Notes 11-8-17 (5618 : US Energy Service & Pure Air Control
“
ible 46B"
Pnctt ScLed」LItm Dt.cruto!UDrt of
Mcra[Ic
Uma Pnce
CatA●dI暉力醸■ol Httent饉 Pcr Hour Sl10 00
Cctrficd kdoor Ar Quahy
Profcsrroorl
PoHotr S90003
PFOf●●lmal brnccr Pc H●ur ,95004
Radon Mersurcmcnt Spcqlttst Pば Hour S8005c薇 :ned MmbЮ bmSt Pa Hour S8506
Ll●msodん 由●ste COnsutant Pcr Hour S9007
暉 P“Hotr 1258
Pnmpl IndorAn Qualrty
Pmfcssrorul
P“Hour S95009
Bt@rsok-Frngu!Per Samp ●S3500
10 Bt@rorob - Bact6.Per mmpe S3500
Brorcmroh - Albcdos Per Sm●I●S5500
12 B―lFe Smple3 Pcr Smplc S3500
13 Bull Alb●ltOl cOnha14g
M8訥 mal型 墾哺mpl“PerSele S5500
14 Lagondla Pnamophrh -
Ddcctlon
Pcr Sample S8000
151 LgtOndla PncЩ 関口■:こ ‐Idmaty Pcr Srmplc ∞
16 鮨v●Vil
16.C.9.b
Packet Pg. 875 Attachment: Pure Air - Rate Sheet for Cost Reasonableness (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery
1
BustosHeather
From:BestLinda
Sent:Tuesday, March 27, 2018 3:31 PM
To:CarballoMiguel
Subject:FW: Emergency Work Outstanding Projects
Importance:High
Linda Jackson Best, MBA
Sr. Operations Analyst
Facilities Management Division
| 3335 Tamiami Trail East | Suite 101 | Naples, FL 34112 |
| Phone: 239.252.2627| Cell: 239.572-5261 |
Email:LindaBest@colliercountyfl.gov
NOTE: I will be in training out of the office Wednesday, March 28th through Friday, March 30th
-I will return your emails as time permits.
From:CurryAmia
Sent:Thursday, February 15, 2018 5:26 PM
To:JohnsonChristopher <Christopher.Johnson@colliercountyfl.gov>; CamachoDilia
<Dilia.Camacho@colliercountyfl.gov>; BishopMargaret <Margaret.Bishop@colliercountyfl.gov>; MolinaroDavid
<David.Molinaro@colliercountyfl.gov>; HamiltonSarah <Sarah.Hamilton@colliercountyfl.gov>; RaineyJenniferA
<JenniferA.Rainey@colliercountyfl.gov>; GrahamRobert <Robert.Graham@colliercountyfl.gov>; Jerome Harris
<Jerome.Harris@cdrmaguire.com>; PajerCraig <Craig.Pajer@colliercountyfl.gov>; CarballoMiguel
<Miguel.Carballo@colliercountyfl.gov>; tim.hancock@stantec.com; BergeronDonna
<Donna.Bergeron@colliercountyfl.gov>; LewisRandy <Randy.Lewis@colliercountyfl.gov>; BelloneJoseph
<Joseph.Bellone@colliercountyfl.gov>; AbbottAlicia <Alicia.Abbott@colliercountyfl.gov>; CaporaleVanessa
<Vanessa.Caporale@colliercountyfl.gov>; tracy.doyle@cdrmaguire.com; GoJanet <Janet.Go@colliercountyfl.gov>;
OvaresRaquel <Raquel.Ovares@colliercountyfl.gov>; BigelowCatherine <Catherine.Bigelow@colliercountyfl.gov>;
CherbiniMichael <Michael.Cherbini@colliercountyfl.gov>; MessnerSteve <Steve.Messner@colliercountyfl.gov>;
MarkuBendisa <Bendisa.Marku@colliercountyfl.gov>; FinnEd <Ed.Finn@colliercountyfl.gov>; ArnoldKelly
<Kelly.Arnold@colliercountyfl.gov>; TraczLarry <Larry.Tracz@colliercountyfl.gov>; MartinezOscar
<Oscar.Martinez@colliercountyfl.gov>; Robin Sheley <Robin.Tooma@collierclerk.com>; 'Carlos Pena'
<Carlos.Pena@cdrmaguire.com>; MildenAnthony <Anthony.Milden@colliercountyfl.gov>; RaabeMike
<Mike.Raabe@colliercountyfl.gov>; ZimmermanSue <Sue.Zimmerman@colliercountyfl.gov>; MoncivaizGilbert
<Gilbert.Moncivaiz@colliercountyfl.gov>; BrogdonHoward <Howard.Brogdon@colliercountyfl.gov>; WilliamsJames
<James.Williams@colliercountyfl.gov>; AtkinsonDayne <Dayne.Atkinson@colliercountyfl.gov>; TrtanCorinne
<Corinne.Trtan@colliercountyfl.gov>; CondominaAmanda <Amanda.Condomina@colliercountyfl.gov>; LibbyPamela
<Pamela.Libby@colliercountyfl.gov>; KellyPat <Pat.Kelly@colliercountyfl.gov>; RussoAnthony
<Anthony.Russo@colliercountyfl.gov>; ChmelikTom <Tom.Chmelik@colliercountyfl.gov>; HamiltonScott
<Scott.Hamilton@colliercountyfl.gov>; StanleyTherese <Therese.Stanley@colliercountyfl.gov>; GonzalezGreily
<Greily.Gonzalez@colliercountyfl.gov>; DarrouxRichard <Richard.Darroux@colliercountyfl.gov>; WalkerJeff
<Jeff.Walker@colliercountyfl.gov>
16.C.9.c
Packet Pg. 876 Attachment: FEMA Deadline Change Email (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
2
Subject:FW: Emergency Work Outstanding Projects
Importance:High
Greetings Irma Recovery Team!
Thank you all for your quick responses.Please see our submittal in the email chain below for
Hurricane Irma emergency work extension requests.
The great news is that we are down to just 8 emergency work items, only 4 of which are expected to
extend past the original emergency work deadline and so need extension requests.
The not as good news is that I was just informed that the emergency work deadline is not March 10,
but is actually March 4.For each of the 4 items currently marked as not needing an extension
request, please let me know right away if the new deadline changes your answer to “Yes” or if it stays
“No”.
Respectfully,
Amia
AmiaCurry@colliergov.net
P -239-252-6028
C -239-285-7573
From:CurryAmia
Sent:Thursday, February 15, 2018 5:04 PM
To:MarkuBendisa <Bendisa.Marku@colliercountyfl.gov>
Subject:RE: Emergency Work Outstanding Projects
Hi Bendisa,
We identified 4 items that are anticipated to extend past the original emergency work
deadline.They are highlighted in yellow below.Also included for informational purposes are 4 items
that are still ongoing but will be complete prior to the emergency work deadline.As we just
discussed, PUD understood the deadline to be March 10.I will notify our team that it is March 4 and
advise if that changes the need for an extension request for the 4 items currently listed as “No”.
Paying
Fund Vendor Description Estimated Cost
301 Simmonds
Electrical
WO# 201772768 -Immokalee Jail -Re-
secure lighting rods and cables.$ 20,000
PO 4500180360 -Waiti
Pending exhaust covers to be delivered. Should arrive any
day. Confirmation received that this will be completed
before March 10th.
301 DEC courthouse & judges chambers $ 70,000 02/15 –Will be complete this week.
301 Pure Air
indoor air quality pre-
testing complete-now remediation &
post testing
$ 950,000
02/15 –Six locations currently being remediated. Will be
complete before March 10th. All remaining will
handled under the permanent procurement process.
16.C.9.c
Packet Pg. 877 Attachment: FEMA Deadline Change Email (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
3
412 EQ Diesel spill in Wellfield remediation -
Tamiami 25 $ 120,000
PO 4500181796; 02/15
quarterly monitoring will be required for a couple of
years; insurance adjuster paying vendor directly and
carrier will evaluate reimbursing insurance fund for
amount over $100k; not all covered by insurance and
monitoring will be ongoing so request extension
412 Power Pro Tech Temporary generator at Tamiami 18 $ 200,000
PO 4500180391; 02/15
on site and will continue until permanent work complete;
request extension
412 RKS
Assess Tamiami 18; analysis to
determine repair or replacement of
generator that powers 5 Tamiami wells
$ 20,000
PO 4500183536; 2/14
process to get procurement process utilized for new
generator design approved.
with Purchasing to ensure FEMA compliant bid for
replacement.; 02/15
services; request extension
412 Mitchell & Stark SCRWTP Rolling Door safety issue $ 5,000
02/14 -Low bid received
work scheduled for February 20th, estimated to take 2
days
414 US Submergent Remove contaminated materials from
NCWRF $ 940,000 02/14 -work may extend past March 1
extension
$ 2,325,000
Respectfully,
Amia
AmiaCurry@colliergov.net
P -239-252-6028
C -239-285-7573
From:MarkuBendisa
Sent:Thursday, February 8, 2018 5:12 PM
To:CurryAmia <Amia.Curry@colliercountyfl.gov>; KearnsAllison <Allison.Kearns@colliercountyfl.gov>; AmannStephanie
<Stephanie.Amann@colliercountyfl.gov>; HammondJoshua <Joshua.Hammond@colliercountyfl.gov>; ForesterDebrah
<Debrah.Forester@colliercountyfl.gov>; CamachoDilia <Dilia.Camacho@colliercountyfl.gov>; PattersonAmy
<Amy.Patterson@colliercountyfl.gov>
Cc:PriceLen <Len.Price@colliercountyfl.gov>; David Weaver <David.Weaver@cdrmaguire.com>
Subject:Emergency Work Outstanding Projects
Good afternoon,
As discussed Tuesday at the County Manager’s Office during Hurricane Irma Meeting, Collier County is in the process of
requesting from FEMA an extension for the Emergency work (Category A and Category B). Please provide me with your
outstanding projects that fall under CAT A and CAT B that will not be completed by March 4, 2018. If you do not have any
projects please let me know.
Thank you,
16.C.9.c
Packet Pg. 878 Attachment: FEMA Deadline Change Email (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
4
Bendisa Marku
Senior Operations Analyst
3299 East Tamiami Trail, Ste 601
Naples, Florida 34112
239.252.8440
Bendisa.Marku@colliercountyfl.gov
Under Florida Law, e-mail addresses are public records. If you do not want your e-mail address released in response to a
public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing.
16.C.9.c
Packet Pg. 879 Attachment: FEMA Deadline Change Email (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
16.C.9.d
Packet Pg. 880 Attachment: Pure Air - Rate Sheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
16.C.9.d
Packet Pg. 881 Attachment: Pure Air - Rate Sheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
16.C.9.d
Packet Pg. 882 Attachment: Pure Air - Rate Sheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
16.C.9.d
Packet Pg. 883 Attachment: Pure Air - Rate Sheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
16.C.9.d
Packet Pg. 884 Attachment: Pure Air - Rate Sheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
16.C.9.d
Packet Pg. 885 Attachment: Pure Air - Rate Sheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
16.C.9.d
Packet Pg. 886 Attachment: Pure Air - Rate Sheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
16.C.9.d
Packet Pg. 887 Attachment: Pure Air - Rate Sheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
16.C.9.d
Packet Pg. 888 Attachment: Pure Air - Rate Sheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
16.C.9.d
Packet Pg. 889 Attachment: Pure Air - Rate Sheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
16.C.9.d
Packet Pg. 890 Attachment: Pure Air - Rate Sheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
16.C.9.d
Packet Pg. 891 Attachment: Pure Air - Rate Sheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
Status Description Last Sub Status description Inv Ref. date Inv Ref. number
Resubmitted FT to FT-In review 11/29/2017 17101958
Resubmitted FT to FT-In review 12/6/2017 17112080 REVISED
Resubmitted FT to FT-In review 12/6/2017 17112046
Resubmitted FT to FT-In review 1/2/2018 17122132
Resubmitted FT to FT-In review 1/19/2018 17122168 REVISED
Resubmitted FT to FT-In review 2/1/2018 18012266
Resubmitted FT to FT-In review 2/1/2018 17122157
Resubmitted FT to FT-In review 2/1/2018 17122129
Resubmitted FT to FT-In review 3/2/2018 18022486 REVISED
Resubmitted FT to FT-In review 2/27/2018 18022401 REVISED
Resubmitted FT to FT-In review 2/22/2018 17122170 REVISED
Resubmitted FT to FT-In review 2/22/2018 18012248 REVISED
Resubmitted FT to FT-In review 2/23/2018 18022365
Resubmitted FT to FT-In review 2/23/2018 18012337
Resubmitted FT to FT-In review 2/24/2018 18022336
Resubmitted FT to FT-In review 2/27/2018 18022400
Resubmitted FT to FT-In review 2/27/2018 18022364
Resubmitted FT to FT-In review 2/27/2018 18022369
Resubmitted FT to FT-In review 2/27/2018 18022366
Resubmitted FT to FT-In review 2/27/2018 18022420
Resubmitted FT to FT-In review 2/27/2018 18022363
Resubmitted FT to FT-In review 2/28/2018 18022404
Resubmitted FT to FT-In review 2/28/2018 18022433
Resubmitted FT to FT-In review 2/28/2018 18022402
Resubmitted FT to FT-In review 2/28/2018 18022403
Resubmitted FT to FT-In review 2/28/2018 18012338
Resubmitted FT to FT-In review 2/28/2018 18022449
Resubmitted FT to FT-In review 2/28/2018 18022453
Resubmitted FT to FT-In review 2/28/2018 18022450
Resubmitted FT to FT-In review 2/28/2018 18022452
Resubmitted FT to FT-In review 2/28/2018 18022454
Resubmitted FT to FT-In review 2/28/2018 18022372
Resubmitted FT to FT-In review 2/28/2018 18022423
Resubmitted FT to FT-In review 2/28/2018 18022422
Resubmitted FT to FT-In review 2/28/2018 18022371
Resubmitted FT to FT-In review 2/28/2018 18022456
Resubmitted FT to FT-In review 2/28/2018 18022421
Resubmitted FT to FT-In review 2/28/2018 18022374
Resubmitted FT to FT-In review 2/28/2018 18022373
16.C.9.e
Packet Pg. 892 Attachment: Pure Air - Invoice Spreadsheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
Resubmitted FT to FT-In review 3/1/2018 18022459
Resubmitted FT to FT-In review 3/1/2018 18022451
Resubmitted FT to FT-In review 3/2/2018 18022485
Resubmitted FT to FT-In review 3/2/2018 18022484
Resubmitted FT to FT-In review 3/2/2018 18032498
Resubmitted FT to FT-In review 3/2/2018 18022483
Resubmitted FT to FT-In review 3/5/2018 18022428 REVISED
16.C.9.e
Packet Pg. 893 Attachment: Pure Air - Invoice Spreadsheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
Amount Due date 1 Text Inv Receipt Date
48,400.00 12/27/2017 REMEDIATION-BLDG L-IRMA 12/4/2017
48,435.00 1/3/2018 IRMA-REMEDIATION BLDG L 2/14/2018
38,270.00 1/3/2018 IRMA-REMEDIATION-PUB UTIL 2/14/2018
5,300.00 1/30/2018 IRMA-REMEDIATION-NCR PARK 1/4/2018
12,350.00 2/16/2018 IRMA-BLDG HLTH CK-BLDG L 2/16/2018
21,650.00 3/1/2018 REMEDAITION-GMD-IRMA 2/9/2018
32,550.00 3/1/2018 REMEDIATION-TRANSPT-IRMA 2/9/2018
68,725.35 3/1/2018 REMEDIATION-PUO-IRMA 2/9/2018
5,225.00 3/30/2018 IRMA-BLDG HEALTH CHK-IFAS 3/5/2018
20,925.00 3/27/2018 IRMA-REMEDIATION-OLD JAIL 3/2/2018
4,815.00 3/22/2018 IRMA-BLDG HLTH CK-BLDG H 2/26/2018
4,141.00 3/22/2018 IRMA-BLDG HLTH CK-SO CID 2/26/2018
10,425.00 3/23/2018 IRMA-REMEDIATN-EXHBT HALL 3/1/2018
12,040.00 3/23/2018 IRMA-REMEDTN-IMMOK SPORTS 3/1/2018
13,700.00 3/24/2018 IRMA-REMEDIATION-BLDG L 3/1/2018
29,256.11 3/27/2018 IRMA-REMEDIATION-GG COMM 3/1/2018
18,147.50 3/27/2018 IRMA-REMEDTN-MARCO AIRPRT 3/1/2018
11,400.00 3/27/2018 IRMA-REMEDIATN-CCG COMPLX 3/1/2018
6,125.00 3/27/2018 IRMA-REMEDIATION-NCRP 3/1/2018
3,400.00 3/27/2018 IRMA-REMEDIATION-BLDG H 3/1/2018
22,197.00 3/27/2018 IRMA-REMEDTN-MARCO AIRPRT 3/1/2018
7,525.00 3/28/2018 IRMA-REMEDIATION-SOE 3/2/2018
63,150.00 3/28/2018 IRMA-REMEDIATION-IFAS 3/2/2018
8,350.00 3/28/2018 IRMA-REMEDIATION-VETERANS 3/2/2018
7,950.00 3/28/2018 IRMA-REMEDIATION-MAX HASS 3/2/2018
30,325.00 3/28/2018 IRMA-REMEDIATION-WW COLL 3/2/2018
2,605.00 3/28/2018 IRMA-REMEDIATION-VETERANS 3/5/2018
2,763.00 3/28/2018 IRMA-REMEDIATION-GGC COMM 3/5/2018
2,569.00 3/28/2018 IRMA-REMEDIATION-BLDG C2 3/5/2018
1,040.00 3/28/2018 IRMA-BLDG HEALTH CHCK-SOE 3/5/2018
3,040.00 3/28/2018 IRMA-BLD HLTH CK-OLD JAIL 3/5/2018
2,160.00 3/28/2018 IRMA-BLDG HEALTH CHCK-GMD 3/5/2018
2,071.00 3/28/2018 IRMA-BLDG CHK-EXHIBT HALL 3/5/2018
1,972.00 3/28/2018 IRMA-BLDG HLTH CHK-NCRP 3/5/2018
2,665.00 3/28/2018 IRMA-BLDG HLTH CHK-C&VB 3/5/2018
1,773.00 3/28/2018 IRMA-BLDG CHK-MAX HASSE P 3/5/2018
1,472.00 3/28/2018 IRMA-BLDG HLTH CK-BLDG L 3/5/2018
3,410.00 3/28/2018 IRMA-BLDG CHK-IMMOK ARPRT 3/5/2018
2,805.00 3/28/2018 IRMA-BLDG HLTH CK-BLDG L 3/5/2018
16.C.9.e
Packet Pg. 894 Attachment: Pure Air - Invoice Spreadsheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
32,915.16 3/29/2018 IRMA-REMEDIATION-SPEC OPS 3/2/2018
2,995.00 3/29/2018 IRMA-BLDG CHK-MI AIRPORT 3/5/2018
3,088.00 3/30/2018 IRMA-BLDG HLTH CHK-WW COL 3/5/2018
3,408.00 3/30/2018 IRMA-BLDG CHK-TRANS DEPT 3/5/2018
1,025.00 3/30/2018 IRMA-BLDG HLTH CHK-BLDG H 3/5/2018
2,865.00 3/30/2018 IRMA-BLDG CHK-SPEC OPS CT 3/5/2018
4,122.50 4/2/2018 IRMA-REMEDIATION-CRTHSE 3/6/2018
635,540.62
16.C.9.e
Packet Pg. 895 Attachment: Pure Air - Invoice Spreadsheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
Days Outstandin Last process date Date of Work Start Date of Work End
158 2/1/2018 10/23/2017 11/16/2017
86
2/20/2018 11/27/2017 11/30/2017
86
2/20/2018 11/20/2017 12/8/2017
127 2/1/2018 12/12/2017 12/14/2017
84 3/19/2018 12/19/2017 12/20/2017
91 2/20/2018 1/22/2018 2/1/2018
91 2/20/2018 1/3/2018 1/16/2018
91 2/20/2018 11/20/2017 12/8/2017
67 3/19/2018 2/28/2018 2/28/2018
70 3/21/2018 2/19/2018 2/23/2018
74 3/9/2018 12/19/2017 12/19/2017
74 3/9/2018 1/12/2018 1/12/2018
71 3/9/2018 2/6/2018 2/9/2017
71 3/9/2018 1/29/2018 2/7/2018
71 3/7/2018 2/1/2018 2/8/2018
71 3/9/2018 2/14/2018 2/18/2018
71 3/9/2018 2/5/2018 2/7/2018
71 3/9/2018 2/14/2018 2/20/2018
71 3/9/2018 2/8/2018 2/15/2018
71 3/9/2018 2/13/2018 2/15/2018
71 3/7/2018 2/12/2018 2/12/2018
70 3/9/2018 2/19/2018 2/22/2018
70 3/7/2018 2/19/2018 2/26/2018
70 3/9/2018 2/13/2018 2/17/2018
70 3/9/2018 2/12/2018 2/16/2018
70 3/7/2018 1/29/2018 2/8/2018
67 3/7/2018 2/13/2018 2/17/2018
67 3/7/2018 2/14/2018 2/17/2018
67 3/7/2018 2/14/2018 2/20/2018
67 3/7/2018 2/22/2018 2/22/2018
67 3/7/2018 2/23/2018 2/23/2018
67 3/7/2018 2/7/2018 2/7/2018
67 3/9/2018 2/15/2018 2/15/2018
67 3/9/2018 2/14/2018 2/14/2018
67 3/8/2018 2/7/2018 2/7/2018
67 3/9/2018 2/22/2018 2/22/2018
67 3/9/2018 2/14/2018 2/14/2018
67 3/9/2018 2/14/2018 2/14/2018
67 3/13/2018 2/8/2018 2/8/2018
16.C.9.e
Packet Pg. 896 Attachment: Pure Air - Invoice Spreadsheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
70 3/7/2018 2/22/2018 2/26/2018
67 3/9/2018 2/22/2018 2/22/2018
67 3/9/2018 2/28/2018 2/28/2018
67 3/9/2018 2/27/2018 2/27/2018
67 3/9/2018 3/1/2018 3/1/2018
67 3/9/2018 2/28/2018 2/28/2018
66 3/13/2018 2/22/2018 2/24/2018
16.C.9.e
Packet Pg. 897 Attachment: Pure Air - Invoice Spreadsheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
Notes
Pure Decon and dumpster
fee not found on bid
Pure Decon and dumpster
fee not found on bid
Pure Decon halomist fee
not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
16.C.9.e
Packet Pg. 898 Attachment: Pure Air - Invoice Spreadsheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
Pricing not found on bid
16.C.9.e
Packet Pg. 899 Attachment: Pure Air - Invoice Spreadsheet (5618 : US Energy Service & Pure Air Control Services, Inc. ;IRMA Storm Recovery Mission.)