Minutes 02/26/2018 III
PELICAN BAY SERVICES DIVISION
WATER MANAGEMENT COMMITTEE MEETING
FEBRUARY 26,2018
The Water Management Committee of the Pelican Bay Services Division met on Monday,
February 26 at 2:00 p.m. at the SunTrust Bank Building, 801 Laurel Oak Drive, Suite 302,
Naples, Florida 34108. The following members attended.
Water Management Committee Mike Shepherd
Tom Cravens, Chairman Scott Streckenbein (ex-officio)
Jacob Damouni
Pelican Bay Services Division Staff Mary McCaughtry, Operations Analyst
Neil Dorrill, Administrator Lisa Jacob, Associate Project Manager
Marion Bolick, Operations Manager Barbara Shea, Recording Secretary
Also Present
Jim Carr, Agnoli, Barber& Brundage
APPROVED AGENDA (AS PRESENTED)
1. Pledge of Allegiance
2. Roll call
3. Agenda approval
4. Approval of 08/03/17 meeting minutes
5. Audience comments
6. Bay Colony beach dune swale maintenance &permit mod to restore drainage
7. Size of weir crest at discharge of OLS/Villages/Las Brisas lake
8. Current lake chemical treatments
a. Types of chemicals used
b. Established frequency standard of chemical applications
c. Annual cost per lake
9. Aerators
a. Annual maintenance costs, including service contract costs
b. Maintenance issues
c. Effectiveness
d. Status of installation of aerators—final phase
10. Blue tilapia test lakes
a. Annual cost of using blue tilapia(per lake)
b. *Authorization for restocking the Ridgewood Park lake
c. Consideration of expanded use of blue tilapia
11. Other business
12. Adjournment
*indicates possible action items
1
Pelican Bay Services Division Water Management Committee Meeting
February 26,2018
ROLL CALL
All members were present and a quorum was established
AGENDA APPROVAL
Mr. Shepherd motioned, Mr. Damouni seconded to approve the agenda as
presented. The motion carried unanimously.
APPROVAL OF 08/03/17 MEETING MINUTES
Mr. Shepherd motioned, Mr. Streckenbein seconded to approve the
08/03/17 meeting minutes as presented. The motion carried unanimously.
AUDIENCE COMMENTS
Mr. Peter Gerbosi commented on a streetlight pole,across from the Willow Brook,
that was destroyed by Hurricane Irma. Mr. Dorrill commented that the pole is the subject
of an insurance/FEMA claim.
BAY COLONY BEACH DUNE SWALE MAINTENANCE
Residents of the Carlysle condominium in Bay Colony expressed concerns over
frequent flooding in their parking garage and related drainage issues. Mr. Dorrill
commented on a drainage maintenance project completed last spring, which included
removal of vegetation and exotics from the entire beach dune swale, as well as drainage
maintenance work at the Brighton and Biltmore which included cleaning pipes and creating
a retention area in the swale.
Mr. Dorrill commented that he will direct Earth Tech, our environmental
consultant,to evaluate whether removal of additional vegetation from the swale is required.
He also suggested a possible cost-sharing project with the Carlysle(similar to the Brighton
and Biltmore project) which would include cleaning pipes and creating an additional
retention area,to correct/improve the drainage flow from the parking garage to the swale.
SIZE OF WEIR CREST AT DISCHARGE OF OLS/VILLAGES/LAS BRISAS
LAKE
Mr. Shepherd commented on flooding of resident property resulting from high
water levels of Lake 3-1 during heavy rains. He suggested that the weir which is designed
to take water away from this lake, does not have sufficient capacity.
Mr. Dorrill requested that Mr. Can (our ABB engineer) provide a proposal to
complete an engineering analysis and estimate to construct an additional conveyance pipe,
pending whatever design and permit review is needed.
CURRENT LAKE CHEMICAL TREATMENTS
TYPES OF CHEMICALS USED
Mr. Cravens commented that tribune and hydrothol are the primary chemicals being
used by the PBSD to treat algae. Mr. Bolick commented that on average, the cost of each
chemical treatment is $130 - $200.
2
Pelican Bay Services Division Water Management Committee Meeting
February 26,2018
ESTABLISHED FREQUENCY STANDARD OF CHEMICAL
APPLICATIONS
Mr. Bolick commented that two spray technicians (on staff) monitor our 45 lakes
to determine when they receive chemical applications. There is no set established
frequency standard of chemical applications.
ANNUAL COST
Mr. Bolick commented that the annual PBSD FY18 budget for chemicals (to treat
lake algae) is $135,500.
AERATORS
MAINTENANCE ISSUES
Mr. Cravens commented on our numerous malfunctioning solar aerators. Some
have been out of service since before Hurricane Irma.
EFFECTIVENESS
Mr. Cravens questioned how the effectiveness of aerators could be measured.
STATUS OF INSTALLATION OF AERATORS—FINAL PHASE
Mr.Shepherd motioned,Mr.Damouni seconded to recommend to the full
board that we temporarily suspend our plans to put aerators in the
remaining unaerated lakes until the 3 month blue tilapia evaluation is
complete, and then we will revisit the plan at that time. The motion
carried unanimously.
BLUE TILAPIA TEST LAKES
ANNUAL COST OF USING BLUE TILAPIA
Mr. Cravens commented that he estimates the cost of installing blue tilapia in all
45 lakes would be approximately$17,000.
CONSIDERATION OF EXPANDED USE OF BLUE TILAPIA
Mr. Cravens commented on the history, costs, and results of our blue tilapia testing
in the Ridgewood Park lake and the Community Center lake since June 2014. Upon review
of the blue tilapia's efficiency in combatting algae and its cost effectiveness,the committee
was in favor of expanding the use of blue tilapia to additional lakes.
Mr. Peter Gerbosi commented on the algae problem in the Willow Brook lake and
requested that the PBSD install blue tilapia in this lake.
Ms. Diane Lustig commented on a possible increase in our alligator population
resulting from an increase in abundance of blue tilapia.
Mr.Shepherd motioned,Mr.Damouni seconded to recommend to the full
board that Mr. Bolick choose 20 of the worst lakes and stock them with
an appropriate number of blue tilapia and we reassess in 3 months, and
if satisfactory,we expand to the rest of the lakes; and if no material effect,
3
Pelican Bay Services Division Water Management Committee Meeting
February 26,2018
then we drop back and continue discussion. The motion carried
unanimously.
Mr.Shepherd motioned,Mr.Damouni seconded to recommend to the full
board that we temporarily suspend application of bacteria in all lakes
pending an evaluation of the performance of the blue tilapia after 3
months. The motion carried unanimously.
. OTHER BUSINESS
LAKE BANK EROSION—REMEDIATION IN FUTURE YEARS
Mr. Shepherd motioned,Mr. Cravens seconded to recommend to the full
board that our accrual rate be sufficiently high that we can tend to one
additional lake each year starting in FY20 until all the lakes are
satisfactorily remediated. The motion carried unanimously.
ADJOURNMENT
The meeting was adjourned at 3:26 p.m.
%'-A4 A/tie-2 AJ
Tom Cravens, Chairman
Minutes approved [ 4I as presented OR[ 1 as amended ON 8 1 date
4