Agenda 06/26/2012 Item #16A116i 26/2012 item EXECUTIVE SUMMARY Recommendation to award a Work Order for the Golden Gate Stormwater Improvements for Coronado Parkway and Hunter Boulevard to Haskins, Inc., in the amount of $360,811 plus a ten (10) percent contingency of $36,081.10, totaling $396,892.10 (Project Number 51029). OBJECTIVE: The purpose of the project is to address a failing stormwater system in Golden Gate City. There are approximately one hundred forty-five (145) underground storm drainage pipe systems of varying lengths designed to convey stormwater runoff from neighborhoods and county maintained roadways to the canal system. The drainage system was constructed in the 1960's and has exceeded its life span. The Coronado Parkway & Hunter Boulevard drainage improvements are part of the larger regional drainage system that needs to be replaced. CONSIDERATION: The request for quotes was solicited using the Underground Utility Contract No. 08 -5011 on May 18, 2012. Five (5) bids were received by the due date of May 31, 2012. The bids were reviewed by the Transportation Engineering Department staff and the Project's Design Professional in conjunction with the Purchasing Department. The following bids were received: 1 Haskins, Inc. $360,811.00 2 Kyle Construction $453,997.00 3 Quality Enterprises, Inc. $483,632.35 4 Mitchell & Stark $485,640.00 5 DN Higgins $531,449.00 The Transportation Engineering Department cost estimate for the project calculated for budget purposes was approximately $400,000; however, the electronic request for quotes went out with an erroneous cost estimate of less than $200,000.00. Once the quotes were received it was apparent that the $200,000 estimate provided was incorrect and thereafter the design engineer corrected and revised his estimate to approximately $370,000. The internal county and the revised design engineer's estimates are consistent with the quotes submitted by the contractors. Payment and performance bonds will be required. The low bidder is approximately $10,000 less than the design engineer's estimate. Staff recommends awarding the work order to the lowest and responsive bidder: Haskins, Inc. LEGAL CONSIDERATIONS: This item has been reviewed and approved by the County Attorney's Office, is legally sufficient for Board action and only requires a majority vote for approval —SRT. Packet Page -889- FISCAL IMPACT: Funds in the amount of $396,892.10 are currently available within the Stormwater Management Capital Improvement Program. The source of funding is Ad Valorem. GROWTH MANAGEMENT IMPACT: The project is in accordance with the goals and objectives of the Drainage Sub - element of the Growth Management Plan for Collier County Stormwater Management. RECOMMENDATION: That the Board of County Commissioners award a Work Order under Contract No. 08 -5011 — Golden Gate City Coronado Parkway and Hunter Boulevard Stormwater Improvements to Haskins, Inc., in the amount of $360,811.00 plus a ten (10) percent contingency of $36,081.10, totaling $396,892.10, and authorize the Chairman to sign the attached Work Order after final legal review by the Office of the County Attorney. Prepared By: Margaret A. Bishop, P.E., Sr. Project Manager, Transportation Engineering Department Attachments: (1) Bid Tabulation, (2) Work Order Packet Page -890- i. Irk /2 � i. t ,r C �2 5C 1 G 1� 6 i COLLIER COUNTY Board of County Commissioners Item Number: 16.A.11. Item Summary: Recommendation to award a Work Order for the Golden Gate Stormwater Improvements for Coronado Parkway and Hunter Boulevard to Haskins, Inc. in the amount of $360,811 plus a ten (10) percent contingency of $36,081.10 totaling $396,892.10 (Project Number 51029). Meeting Date: 6/26/2012 Prepared By Name: BishopMargaret Title: Project Manager, Senior,Transportation Engineering & Construction Management 6/1/2012 9:38:31 AM Approved By Name: TaylorLisa Title: Management /Budget Analyst,Transportation Administr Date: 6/4/2012 2:19:15 PM Name: MarkiewiczJoanne Title: Manager - Purchasing Acquisition,Purchasing & Gene Date: 6/4/2012 4:14:23 PM Name: ShueGene Date: 6/4/2012 4:26:06 PM Name: AhmadJay Title: Director - Transportation Engineering,Transportation Engineering & Construction Management Date: 6/5/2012 7:37:28 AM Name: BetancurNatali Title: Executive Secretary,Transportation Engineering & C Date: 6/5/2012 9:12:49 AM Name: PutaansuuGary Title: Project Manager, Principal,Transportation Engineer Date: 6/5/2012 9:58:51 AM Packet Page -891- Name: CummingsRhonda Title: Contracts Specialist,Purchasing & General Services Date: 6/5/2012 5:04:31 PM Name: WardKelsey Title: Manager - Contracts Administration,Purchasing & Ge Date: 6/6/2012 10:17:32 AM Name: TeachScott Title: Deputy County Attorney,County Attorney Date: 6/6/2012 10:35:30 AM Name: MarcellaJeanne Title: Executive Secretary,Transportation Planning Date: 6/13/2012 5:07:32 PM Name: KlatzkowJeff Title: County Attorney Date: 6/14/2012 4:06:25 PM Name: UsherSusan Title: Management/Budget Analyst, Senior,Office of Manage Date: 6/18/2012 2:01:44 PM Name: OchsLeo Title: County Manager Date: 6/18/2012 3:17:35 PM Packet Page -892- h O C O U � 0 O � N � O d d LL 9 a r� N A m L d m l0 A C m � N as Packet Page -893- O o 0 0 O O OI O O 0 O OI 0 0 0 OIO O 0 0 O OI 0 oI O O Ol of of OI OI0 OIO� 0 0 0 0 OI 0 O O oI OI OI of OI OI OI of O O 010 OI OI C C Q O O N OIIc OI O�O O O 1nI O N 0�0�0 u) O N 'R u) O O N OIN I� u) OIO O M 1� Oi OIC u) V m M uJ O o7l O�N a0 N V' (D u) C u7 OI R CIO O O o (Dl u)I u) O Mf O o O O I u)I C Or LO N N'� IM aD O)I t��Mll� N M' , Q) C7I Ni tO�NIOJI nI� IOIr v`� �M MIMMMMMMMM�MM�lMMMMMM�M�M��� MI W 0 0 O O 0 0 O O 0 0 O O 0 0 O O 0 0 O O 0 0 O O 0 0 O O 0 0 O O 0 0 O O O u) O O 0 0 D O 0 0 O 0 0 0 0 0 V O C O co o o m O w m o O cV Oi N N u'i C O O V7 m E v C col ui 0 So o o O w 7 V' u) CO V) M N O O Lo r M u) O o I� O r d OD O N M m W Q N N M N 1� < u7 F- M Z M M M M M M M M f9 M M M M M M M M M M M M M M M M M f9 M oo000oo g 000 0 o g 00000o0oo.00000o o 0 0 0 0 0 0 0 0 0 0 0 0 0 'D, 0 a 0 0 0 O O 0 0 C C(D 0 0 O o C O o O O C C O C O O co C o o O O O O u) C o Oi Q 0 0 0 O O co o O N N O O o m a N O .- N w m 0 O) O DD 0 0 0 7 O n 0 0 0 V c', O m o m O? O O< o O u) u) r O N r m M N W N r r N w N u7 c) m N r� r N N M F V _ H �MM MMM M M M M MM M M 69 M M 69 Go.). M 69 to M N W 0 0 o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 0 0 D o 0 0 0 0 U O O O O of fV V' o 0 0 0 N O f� O G O O a sf T O C O O O O O r O ov rnv(or oor a oc N r Mcli w r N N c) u) F 7 z M M M M M M M M M M M M M M M M M M M M M M M M M M M 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o o o o o o o 0 0 0 0 0 0 (a I O O O N u) O O O O O O O O O O N O O u) 0 0 0 u) 0 0 0 M J ui O u) u) h m M O N O W M O u) N N O O G O D7 N O h M f� m M r N N h N M< N? M M N O R O O) r u) w O I� m M N I� w m O O N Il O <O o O< 10 o 0 M G d r W r M Im f0 O) M W � N r v m N I� h< 19MM MMM MMM M MM(9 MM MMM MMMMM M 69 M M W u) 0 O 0 0 O O 0 0 u) M 0 0 M M 0 01c, M M O u) u) I� O? u) OOOO O) u) O r O o 1A O N u) a O O u) u) u) O M O O O O S U u1 O ui ui f� N cV N cV N N u) 1� O n M m N N (C m u) O v 1� (") u) m N m N V M oD u) O r u) m c0 (D O r O.. o e sr ui Z M �) M M M M M M M M M M M M M M M M M M M M M M M M 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o o 0 0 0 O O C u1 In O C O O O C O O G C O `v co o O O O O C u) O C G I� ,J 0 0 0 0 N O OD u) O N N O GD u) (") a a ? N a m c0 D7 V' W 0) N O O N V' u) O I� r co O Q1 u) N O O) u) O ui O u) O at F O m O N N n O .4 M A r M O N N a m N of r r m r u) N N u) aD r I� ( CD M N N M r O r N H co N r < I 69 4,% MMMM MMM 69(A MMMMMM M MMfg MMMMM M 0 0 O O 0 0 O O 0 0 O O 0 0 O O 0 0 O O 0 0 O O 0 0 O O 0 0 OO 0 0 O O 0 O O 0 0 O O 0 0 O O 0 0 u7 0 0 0 0 0 CWi 0 0 0 l('j ui cV u) u) m m m O r N O O N< a (V 7 O u) 1� O C N o O u) (`') M M? M M O r C o oo u) a o m o 10 r n o -1 M M M M M M M M 69 M M M M M M M M M M M M M M M M M M M 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O 0 0 O 0 0 0 0 0 0 0 0 0 0 0 :O 0 J Q O C O O O O O O O o O o o O O o 0 w 0 u) O m O O o N O O o O N (O O O 9 O O 0 0 O O (n N O u) 0 0 O O aD H O O O N W n m o u) m W W u) c0 V I'% r 10 M N I'% M r N I� 0 O r r Lo 0) M (C N N v N 1� r M r w r u) o m M M r o N M o f N r N r I M M 69 f9 in M M M M M M M M of M M M M M M M M M M M M M W_ O(D 0 0 pp O 0 0 O O 0 0 O O 0 0 O O 0 0 O O 0 0 O O 0 0 O O 0 0 pp 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 u) 0 0 0 0 0 O O O O O r u1 2 W N O) o O 01 M O W N O O O M o 1� M O o o O O O O O O O u) O r N r N N- M r M M V w W C+D O N M 7 O Oo O r 0. N 2 M M M M M M M M M M M M M M M M M M M M M M M M M M M 69 ~ Z N to In Q Q LL 6 LL LL LL LL LL Q LL J LL LL J J LL LL J J Q Q Q LL} J co >- (n LL! J J VJ d J J J J J J J J J J W w w w W w W w 1u111 m 0 0 0 O o O o O O a N of N r 0 0 0 0 0 o u) w o (°V� r O r W Or 100 ]co 1�2 W O C m C7 J E m m o O Z U m m m LL' N o CL @ o d m A y m v d 's o ° °- 0 0 o o o m m � m > y ° m W U w c o o E: m « - :� _ x o x o >>> a�i W m° 2 m E m° 3 W E m o•o- E o- o- o•o omm > > o ? > ° m °) >o� y (� o m C. —'f- m E E E E E EOOrrUUU m°) a. CL fL v SEE> cD c 0 0 0 0 0 0 o m c y o m U U Q Q m W cM�l N O m � c 3 m > > > > >> o o d a w M w w o u) x u'S m '—` °: m m o m U ac o o> 7 7° U m U Co U U x x = � E d m (co E o 0 C N f0 y U N N U U i0 co U of o (D N < x sr O) J N m j(D l0 c`'D O m m .- (6 U) rG d U r r r N 11 Cl 5 O r N r r N r 0� d N U K� f IO) O N N N N M N -NI u) N N N N Packet Page -893- WORK ORDER Agreement for "Underground Utility Contractors" Dated: March 11, 2008 (RFQ #65 Contract 08 -5011) This Work Order is for construction of stormwater improvements for the Golden Gate City regional drainage project for work known as: Project Name: Golden Gate City Coronado Parkway & Hunter Boulevard Drainage Improvements Project No: 51029 The work is specified in the proposal dated May 31, 2012 which is attached hereto and made a part of this Work Order. In accordance with Terms and Conditions of the Agreement referenced above, this Work Order is assigned to: Haskins, Inc. Scope of Work: As detailed in the attached request for quotes: Schedule of Work: Complete work within ninety (90) days from the date of the Notice to Proceed which is accompanying this Work Order. Compensation: In accordance with Article Five of the Agreement, the County will compensate the Firm in accordance with following method(s): ❑Negotiated Lump Sum; ❑Lump Sum Plus Reimbursable Costs; ❑Time & Material (established hourly rate — Schedule A); ®Low Bid, as provided in the attached request for quotes. AaW TOTAL FEE $360,811.00 PREPARED BY: Margaret A. Bishop, PE, Sr. Project Manager Transportation Engineering Department APPROVED BY: Gary Putaansuu, PE, Principal Project Manager Transportation Engineering Department APPROVED BY: Jay Ahmad, PE, Director Transportation Engineering Department APPROVED BY: Nick Casalanguida, Administrator Growth Management Division Packet Page -894- Date Date Date Date ATTEST: Dwight E. Brock, Clerk By: Deputy Clerk ATTEST: By: (Print Name/Title) Approved as to Form and Legal Sufficiency: Assistant County Attorney ^'2,6 2Q', � Ite i BOARD OF COUNTY COMMISSIONERS Collier County, Florida im Fred W. Coyle, Chairman Haskins, Inc. (Print Name/Title) Packet Page -895-