Agenda 05/08/2012 Item #16E45/8/2012 Item 16.E.4. EXECUTIVE SUMMARY Recommendation to accept reports and ratify staff - approved change orders and changes to work orders. OBJECTIVE: To enable the Board to oversee the execution of administrative change orders and changes to work orders and promote accountability in the use of staff authority. CONSIDERATIONS: On April 22, 2003, the Board approved a recommendation to implement a plan to enable changes to BCC - approved contracts (Section XV.C, Collier County Purchasing Policy) of not greater than 10 percent of the current Board approved amount or $10,000 (whichever is greater) to be authorized by staff. Also included in the report are changes to Work Orders. These include work orders issued under CCNA Contracts that are less than or equal to $200,000 (Section VII.C, Collier County Purchasing Policy), and changes to work orders for all other contracts (Section XV.G, Collier County Purchasing Policy) that are not greater than 10 percent of the current Board Approved amount or $100,000 (whichever is greater). The Administrative report identifies the percentage changes to contracts or work orders that have occurred since the prior BCC approved amount which are below the threshold limits as referenced above. The plan calls for staff to submit a monthly report listing these change orders from the previous reporting period. Enclosed is the monthly report of the Administrative Change Orders and Administrative Changes to Work Orders. These reports cover the period of March 22, 2012 through April 18, 2012. FISCAL IMPACT: The total for 6 changes to contracts is $9,280.00. The total for 4 changes to work orders is $10,000.00. LEGAL CONSIDERATIONS: This item raises no legal issues and requires majority vote for approval. -JAK GROWTH MANAGEMENT IMPACT: There is no Growth Management Impact associated with this action. RECOMMENDATION: That the Board of County Commissioners accepts the enclosed Administrative Change Orders Report and Administrative Changes to Work Orders Report and ratifies the listed change orders and changes to work orders. PREPARED BY: Diana Diaz DeLeon, CPPB, Contracts Technician, Purchasing Department Packet Page -1122- 5/8/2012 Item 16.E.4. COLLIER COUNTY Board of County Commissioners Item Number: 16.E.4. Item Summary: Recommendation to accept reports and ratify staff - approved change orders and changes to work orders. Meeting Date: 5/8/2012 Prepared By Name: DeLeonDiana Title: Contracts Technician, Purchasing 4/26/2012 9:22:53 AM Submitted by Title: Contracts Technician, Purchasing Name: DeLeonDiana 4/26/2012 9:22:55 AM Approved By Name: DeLeonDiana Title: Contracts Technician, Purchasing Date: 4/26/2012 10:44:56 AM Name: MarkiewiczJoanne Title: Manager - Purchasing Acquisition,Purchasing & Gene Date: 4/26/2012 12:51:49 PM Name: MuckelCynthia Title: Applications Analyst,lnformation Technology Date: 4/26/2012 8:58:45 PM Name: PriceLen Title: Administrator, Administrative Services Date: 4/27/2012 9:06:47 AM Name: KlatzkowJeff Packet Page -1123- Title: County Attorney Date: 4/27/2012 9:18:22 AM Name: FinnEd Title: Senior Budget Analyst, OMB Date: 4/27/2012 4:29:25 PM Name: OchsLeo Title: County Manager Date: 4/30/2012 3:46:29 PM Packet Page -1124- 5/8/2012 Item 16.E.4. N_ W O (O N � T C d L > 0I .d O L @L P� aE N U d p) U y O a L v N � O � U Q w d L CM 7 d O C .0 E U Q w > C O O. O o E 3 @ O m a w W C ii O O W O Q U 0 U w Z 'O d R L L> o E z m O O Q w Q c d r .@ d CL o c a` C C Z Z E @ O �6 o � z y m ro c e L >CL uua d C l6 � N � o d o N d z o O o � 0 o c U C @ I 0 e O O -0 o m O O M d C) 3 �2 N p� c OJ cc @ d V3 � @ C O O � of» � O aai a C d0 O rn 2 R U a Cl) @ M �2 d C) r m N fn m Q) Ln a) n M m O C t`. rn d > L N L d CL U d > = a E @ o J O U @ C 0 d C O CL >0 T c 'a of 06 E 06 d fA m d IM ° N 1 @ O IS E # x c p N d L U w y N m -0 O C C d C OO ¢ZoU� I- � a i6 E N C IM U CN @ o (+1 J O O E 3 CD C 2 U d w O y 0 0 e O 0 O 0 w O CD f» O of» O rfl 0 fA C) O m d @ _rn U m CL U e 0 0 O 0 ro (ND M C9 O 69 LD l27 N LO Lo r- -O �u d Co 04 @ U 0 u m 0 O O Co OU Y U @ d D G @ �D 2 d N E L U cn C O oe E c d # C a) ` 0) d O N C ¢ LO N y ` 7 W O L ._ O U > p H CN d CM c � � C d M o � E V (6 v C J CD fOp O O O N d CD a` 3 2 C d Z N @ 0 d > O e 0 0 O 0 ro (ND M C9 O 69 LD l27 N LO Lo r- 0 0 0 O O Co l� M to O CD r» O N Co 04 @ a 0 u m C O O Co OU Co Ln .1 M Gr-9 ndi Vi C O p C O c N C O oe E c d # C a) @ O Y d aL > @ `c n a o 0 � � C d M E V (6 d +L' c p o Z CD fOp O ` N d CD a` o U 2 C d d O @ 0 °- U) U 3 Y d d � @ -O N c m o La c U) it o v � d O O p N Q p Co C N d O @ d C Co C a) IM C @ o rn L Z C Y O O O • d d L_ M > O 7 0 0 0 O O Co l� M to O CD r» O N ro Cl) Ln `* rn v� @ a d r o d 0 ° U O O Co M In � m Co C N d L C z 0 O O Co L Q Co Ln .1 M Gr-9 ndi Vi C O p C O c U N c C ° Y ¢ d # d N CL 2 N ° aL > @ `c ci � � C d C ° E V (6 d +L' c p o Z d Itn c O rn T � � M N d CD Ln � m 4k ;_ U T � O N 2 @ M O @ 0 °- U) U a d 3 N r C _ La c Z v � C) p N 3 d C Co C d O" O a Packet Page -1125- 5/8/2012 Item 16.E.4. �i 0 O O J O i o � Lri C � O � N l w O O O j N a) o F O C C O � CD N O O LO CIT r 0 O o N w U 0 � d L Y � • `m c CL F°- n d @ a o m m � a ndi rn d C 2 d # w N ci � � C R U c p o Z O 3 Z Ln d O N w O u1 N � - .0 C 01 a o a E Mm E _ o Z o 0 m M O L U 0. E U cc ° o m_ a O U W O d m w _ O = 0 N ` O O w p U 01 Oa U w OJ c C 10 N � o' U L U � U p O o m e r c0 u0i i p p a c E LQ O Q U i» ar = r E o U Q 0 M N _ O L Ol !n '7 E _ 07 , = N (A d O Of a a` 0 o a` LL c o ° � ° _ o > O Cli c Z z U E a c 0 Z Z U Z c m U y — `o u wu OD r_ or v d c m c o c d C G O r >GU V U N U{q 00 Cli y v y � 0f N O O E; a N E O ° mz IL 6 IM L V O 3 0 0 N Q� W w R `a U .0. O 61 16 U a Packet Page -1126- 5/8/2012 Item 16.E.4. C O O (O `) a o a E L° 3 U w q V _ O fa IL w o o w _ O = 0 07 ` O O w p O Q CD U U w ¢ 2 i» U W F ¢ C Ct: C U O c0 O E N p m cQ V, o Q,w N _ O L Ol !n '7 E _ 07 , = N (A d O Of a a` 0 o a` LL c o ° � ° _ o > O Cli c Z z U E a c 0 Z Z U Z c m U y — `o u wu OD r_ or v d c m c o c d C G O r >GU V U N U{q 00 Cli y v y � 0f N O O E; a N E O ° mz IL 6 IM L V O 3 0 0 N Q� W w R `a U .0. O 61 16 U a Packet Page -1126- 5/8/2012 Item 16.E.4. d d v N o A U p Y < L N U c o� y d 'O m pl Z e cc O Q -5 E U .O U m d C � M 7 d Q O Y E O w 3 d c s in c I Y E L O w U a' c c •O � ` Q o � Y Q U ° w 3 r w c 9 v C E p U m Q Q vi O Y O d C O d L 7 S p o O1Y E p 0 w U w J � d r E Z d CL 'o c a a d CL x w o V Z 'd0 Z O O � U d wY O 0 A U � N O Q O Z d d a 2 Z p i d •p d C a > d U 0 d N d 7 °= o ca Z 0 N cc Z 0 U K Ld d r Y C� - U n N N O E •0 N U — d O 'p N p INa O L d l0 3 3 1 N CO to (0 0 y E d N o ac 0 `j 0 O O O N O U 69 d > CL E m CD 0 0 N 0o a 0 Lq O d ° a O � � d 3 .o N E Ln t} U � c � O `p J U d Mn a a d wO N ca L o O N � ma to m coo m E d d c p O @ U > E a7 C CD D C (D 3 O Y O = 0 O Z C N C c O d O J U c J a CO CL N C J D U N O J C � N w a5 a � 0 U d O O � 0 U O N M y d y M N !O N > 0 In d LO 0) � m m Cr' IT o M E d J � C_ CD O C O N CO 0 N d d Y N J C = [D x o m 2 W d C c as o m rn d N d N •0 a M c a z CO 3t R' a7 ca m m 0 N C ..d. O O C O C O .m cc 01 ° r 0 'as o o cl QIn0 0 F- d m L O U d N 07 N t C d »- 10 rn 0 CD N L C W O U 0 d 0 o 2_ 0 0 0 O 0 O O n fR 0 fA 0 0 C V to Q 'z O C v ffl V- U E c� U M N O o n N �, N N N 'd0 O O W 9 V) d) N i a O 0) v J O C T pl Y (a � C d C J M d O N J 0 F- c Q O .:. c x m L V C y O O a7 C N FL c O N n m cn U F L E O cc F d O M C N d¢ d E .0 m a m N 61 m O O Y � MUU �cn 0 N O O fD O d CL O d L 01 Z � O N_ �o V N O O 0 v a m- U d N Packet 0 0 o° O 0 O O v m 69 0 CO fA O 0 °v CO En Q Z O O CO Eli EO U cc E C7 0 C 'o d a M r r O cc U C O N 0 d L 0 0 O 0 CD O O n EA °o 00 0 V Ess Z O I O c I 0 O) L d L j Q N E a0 -- L n Q � n C C N n O O O N N N O O T cc C N 9 C. c o rn i a � J O c T pl Y (a � C "O C' CJ m s O � CL ci C as d ~ N U la r L V v 0 7 N a a d N MA C c a5 d _� d — N W U C O (a _d Of d U C)L)6 �U F-O a ui E r1 U U r n N O O fD O w O ` CL O O d Z Z d d Page -1127- ° o a0 n CO N M M O O O L N m V) 0 M 5/8/2012 Item 16.E.4. C m (D m _o Y O U 3 c Y cc d d O 0. d m Q U) M w C U 3 a5 LL � () O � � CO O 0 C_ -p C NCk 0 7 M C O pl Y (a � C "O C7 O m E a) 9 L C1vU E 0 ci C as N L V O ° - L a d U V > Q N 0 0 0 O w 0 E N d g Q }o 3 O a L U ti O F- Cot�er Count Ad� Sees Division Purchasing XContract Change Request 5/8/2012 Item 16.E.4. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #: 08- ! Mod #: 6 PO/Work Order #: 1 Project Name: Watershed Management 5122 Original BCC Approval Date; Agenda Item # 4500106318 Plans Project M N/A Project Manager: Mac Department: Land j ContractorlFirm Name: PBSJ now Last BCC Approval Date; Agenda Item # Hatcher Development Services ! Atkins IOriginal Contract/Work Order Amount $ 575,736.95 3/10/09 15A10 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 1.879,134.33 10113/09 1097 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 1.879.134.33 Dollar Amount of this Change $0.00 -0.00% Change from Current BCC Approved Amount Revised New Contract/Work Order Total T1,879,134.33 Cumulative Changes 1 $ 17303,397.38 0.00%1 Change from Original Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed date: I Last approved date: 3131/12 1 Revised date (includes this change): May 31, March 25, 2009 ! 2012 Number of days added (if Explain why additional days are needed (detailed /specific): ): The time extension is to extension, must attach current ! allow a thorough review and revision of the Water Quality Model and report. insurance certificate(s) from SAP I or obtain from vendor )7 61 Days Add new task(s) Change task(s) ❑ Delete task(s) I XOther (specify): Time Extension 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): NA 2. Provide detailed rationale for the requested change:The time extension, is to allow completion of the final report and delivery of acceptable final products. 3. Provide explanation why change was not anticipated in original scope of work: An overly ambitious attempt to meet deadlines did not allow sufficient time for completion of final deliverable. i 4. Describe the impact if this change is not processed: Failure to complete the Water Quality Model and report would result in an inferior model and report. Type of Change / Modification 1. Planned / Elective I X 2. Unforeseen conditionsicircumstance ❑ 3. Quantity or once adjustment X 4. Correction of error(s) ; ❑ 5. Value added I X 6. Schedule adjustment Change Requested By 1 Contractor /Consultant ❑1 Owner ; X Using Department ❑ Design Professional ❑ Regulatory Agency (specify): Other (specify): Purchasing Professional Participated in Negotiation of Change / Modification: ❑ Yes X No Approved by (Name and Title): Reviewed by (Purchasing Professional): Packet Page -1128- } . 1 Date:312212012 Date: 5/8/2012 Item 16.E.4. cxrwzy Purchasing Department A irrinis.. on Change Modification Form PU hRsi x Contract Change Request ❑ Work Order Modification Contract #: 09- Change #: 2 POtWork Order #: N/A Project Name: Visa Commercial Credit i 52955 Card Project #: N/A Project Manager: Department: Purchasing Contractor /Firm Name: Sun Trust Catherine Bigelow Banks, Inc. Original Contract/Work Order Amount - - NSA Original BCC Approval Date; Agenda Item # Current BCC Approved Amount - N /A Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount a - SAP Contract Expiration Date (Master) Dollar Amount of this Change SM00 #DIV /0! Total Change from Original Amount Revised Contract/Work Order Total $0.00 #DIV 10! Change from Current BCC Approved Amount Cumulative Changes $0.00 #DIV /0! Change from Current Amount Completion Date, Description of1he Task(s) Change, and'Rationale forthe.Change Original completion date: 10 /10/13 Last approved completion date: N/A Revised completion date (includes this change): N/A i 1 Number of days added : N/A Explain why additional days are needed (detailed /specific): N/A C Add new task(s) C Change task(s) C Delete task(s) x Other (specify) 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Schedule A, delegation of Program Administrator has been changed to account for one of the Program Administrators leaving the County and the rmer Purchasing Director moving to Public Services. Provide detailed rationale for the .requested change: Program Administrators have changed from Joanne Markiewicz, Linda Valentine and Steve Carnell to Joanne Markiewicz, Catherine Bigelow and Rhonda Tibbetts. Provide explanation why change was not anticipated in original scope of work: Purchasing was not aware that Linda Valentine would be leaving the County and that Steve Carnell would be placed as Administrator of Public Services 4. Describe the impact if this change is not processed: Sun Trust Banks would not have the signatures of the Two new Program Administrators. Type.of Change l Modification 1. Planned / Elective X 2. Unforeseen conditions/circumstance Ci 3. Quantity or price adjustment 1 14. Correction of error(s) l 5. Value added Eli o. Schedule adjustment Change Requested By Contractor /Consultant x Using Department Design Professional R auiatory Agency specify): j ED Other (specify). Purchasing Professional Participated in Negotiation of Change i Modification: C Yes No Approved by: ! > r Date: "f Name and Tit!e:Catherine Bigeiow,..Sr. Business Technology Analyst r Date:lY f Reviewed by: �-�� � �� l L/ .)curement Strategists Name'tyyn M Wood Packet Page -1129- Revised: 31261 12 Mr Cwt Adm nisrAve Services DNIson Purchasing ® Contract Change Request 5/8/2012 Item 16.E.4. Purchasing Department Change Modification Form ❑ Work Order Modification j Contract #: 11- Change #: 8 PO/Work Order #: Project Name: Riverwood Main 553 i4500128483 I Replacement Project Project #: 71010.5 Project Manager: Dayne Department: PUPPMD Contractor /Firm Name: Andrew Site Atkinson Work Original Contract/Work Order Amount $ - 955;626:67 5124/1:1 16C3 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 955,626:67 5/24/11 16C3 Last BCC Approval Date; Agenda Item # Current ContracVWork Order Amount $ 955.;626:67 4110/2012 SAP Contract Expiration Date (Master) Dollar Amount of this.Change $0.00 0.00% Total Change from Original Amount Revised ContractfWork Order Total $955,626.67 0.00% Change from Current BCC Approved Amount Cumulative Changes $0.00 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change i 1 Original completion date3 /5/12: Last approved completion date: Revised completion date (includes this 4110112 change): 5/10/12 Number of days added :30 Explain why additional days are needed (detailed /specific): I Because of the unforeseen conditions due to unlocated utiiites that cause delay in the ro'ect. I ! ❑ Add new task(s) ❑ Change task(s) ❑ Delete task(s) Other (specify): IVY V a ucLannu gnu spnunrr axpranauon or the requestea cnange(s) to the tasK(s): NA 2. Provide detailed rationale for the requested change: a. Contractor needs more time to complete this project due to the unforeseen conditions due to unlocated utilites that cause delay in the project. 3. Provide explanation why change was not anticipated in original scope of work: a. Due to the age to the system, proper as builts could not be obtained. As a results not all utiiites could be accurately located till the work began. 4. Describe the impact if this change is not processed: a. Project cannot be completed in the time allocated Type of Change / Modification I ❑ 1. Planned / Elective ❑ 2. Unforeseen conditions /circumstance 1 ❑ 3 Quantity or price adjustment ❑ 4. Correction of error(s) i LIJ 5. Value added ! [ 6. Schedule adiustment Change Requested By ❑ Contractor /Consultant ® Owner ❑ Using Department ❑ Design Professional ' ❑ Regulatory Agency s eci" : ! ❑ Other (specify Purchasing Professional Participated in Negotiation of Change/ Modification' ❑ Yes EJ No Revised: 3/26/', 2 1 Packet Page -1130- o' Comer Cowity AdmstraM Services Division Purchasing R Contract Change Request 5/8/2012 Item 16.E.4. Purchasing Department Change Modification Form ❑ Work Order Modification i Contract #: 11- Change #: 7 POIWork Order #: Project Name: Palm Springs Main 5678 4500131327 Replacement Project Project #: 71010.6 Project Manager: Dayne Department: PUPPMD i Contractor /Firm Name: SW Utilities Atkinson i Original Contract /Work Order Amount $ 794,538100 9/13/11 16C6 Original BCC Approval Date; Agenda Item # 1"Current BCC Approved Amount $ 794,538.00 9/1.3/11 16C6 Last BCC Approval Date; Agenda Item # ICurrent Contract/Work Order Amount $ 794;538.00 4/10/2012 SAP Contract Expiration Date (Master) Dollar Amount of this Change - $0.00 0.00% Total Change from Original Amount Revised Contract /Work Order Total $794,538.00 0.00% Change from Current BCC Approved Amount Cumulative Changes $0.00 0.00% Change from Current Amount i Completion Date, Description of the Task(s) Change, and Rationale for the Change j Original completion date31111/12: Last approved completion date: I Revised completion date (includes this 4/10/12 change): 5110112 Number of days added :30 Explain why additional days are needed (detailed /specific): Because of the amount of rock that was found and how shallow the rock was found it took the contractor longer to complete the project. j ❑ Add new task(s) ❑ Change task(s) I ❑ Delete task(s) Other (specify): 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): NA Provide detailed rationale for the requested change: a. Contractor needs more time to complete this project due to the amount of rock and how shallow the rock 3. Provide explanation why change was not anticipated in original scope of work: a. Although the design accounted for the removal of rock, the amount of rock and how shallow the rock was could not be quantified until the work began. As a result, it took the contractor longer complete the project 4. Describe the impact if this change is not processed: a. Project cannot be completed in the time allocated Type of Change /Modification ❑ 1. Planned / Elective ❑ 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment 1 I 1 4. Correction of error(s) I ❑ 5. Value added j 6. Schedule adjustment Change Requested By ❑ Contractor/Consultant Owner I ❑ Using Department ❑ Design Professional I ! i Regulatory Agency (specify): ! ❑ Other (specify): j Purchasing Professional Participated in Negotiation of Change / Modification: ❑ Yes ❑ No / Approved by: f'' Date:i f �� " Name and Title: P- viewed by: `� 1 ; ; Date: i ;urement Strategist e' Revised: Y26,". 2 1 Packet Page -1131- C:.�lit�er C ;ourtty Adrninistraue Savrw Division plod asiN I Contract Change Request Contract #:07- Mod #: 05 4131 #: 80055 1 Project I 1 Ruberto 5/8/2012 Item 16.E.4. i Purchasing Department Change Modification Form Work Order Modification PO/Work Order Project Name: Gordon #:4500098650 r Greenway Park Department: Parks & Contractor/Firm Name: Recreation Associates, Inc. Original Contract/Work Order Amount $ 1240,041.:00 12111/07 10G Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 1,240,041:00 /pfLS;/1( 0, rk�DIt( Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 1,1.92,1g5:00 / ` SAP Contract Expiration Date (Master) Dollar Amount of this Change $9,280.00 -3.11% Total Change from Original Amount Revised Contract/Work Order Total $1,201,475.00 -3.11% Change from Current BCC Approved Amount Cumulative Changes ($38.566.00 )] 0.78% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: March 6, 2008 June 30, 2012 change):June 30, 2012 Number of days added (if Explain why additional days are needed (detailed/specific): None i extension, must attach current insurance certificate(s) from SIRE or obtain from vendor): O days X Add new task(s) Change task(s) Delete task(s) El Other (specify): I � I 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Building permits filing. j2. Provide detailed rationale for the requested change: New building code will go into effect on March 15, 2012. All construction documents have been finalized to the existing code and will be grandfather to the existing Code. i 3. Provide explanation why change was not anticipated in original scope of work: The completion date was extended to comply with other permitting agencies. 4. Describe the impact if this change is not processed: New Code would increase the cost for construction and will I add time for the contractor to apply for the permit after the project is awarded to the successful contractor. i Type of Change t Modification I ❑ 1. Planned / Elective I ❑ 2. Unforeseen conditions/circumstance I CI 3. Ouantity or price adjustment i 4. Correction of errors I X 5. Value added ❑ 6. Schedule adjustment Change Requested By F X Contractor /Consultant 1 X Owner Using Department Design Professional i Regulatory Agency (specify): I Ll Other (specify). Purchasing Professional Participated in Negotiation of Change / Modification: Yes No Approved b . I Date: March 12, 2012 i Name and Titre: 7-1 n! Rt= _ �3� �7' Nt,fF.�J,4 irC� j Reviewed by Date: March 12, 2012 Revised: 7127111 ,.l r , Packet Page -1132- ism ® Contract Change Request 5/8/2012 Item 16.E.4. Purchasing Department Change Modification Form ❑ Work Order Modification I Contract #: 14.218 Mod #: T, 3 I POtWork Order #: 4500125166 Project Name: Roberts Center Renovation #B- 10 -UC -12 -0016 i Project Project M CD10 -07 Project Manager. Rosa i Department: HHVS Contractor /Finn Name: Goodwill industries Munoz of Southwest Florida, Inc. Original Contract/Work Order Amount $ :._.- 13a4.5D36fJ 10126111?;.:16D3 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount ...:; - 174,503 0 0204-2012: 401 Last BCC Approval Date; Agenda Item # Current Contract/1Nork Order Amount V' ° 174:5i13;60' Dollar Amount of this Change ...1- $0.00 0.00%1 Change from Current BCC Approved Amount Revised New Contract/Work Order Total 3 174.503.50 0 Cumulative Chances $0.00 0.007/o Change from Original Amount 0 Completion Bate, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed date: 07/01110 Number of days added (if extension, must attach current insurance certificate(s) from SAP or obtain from vendor): 183 days Last approved date: j Revised date (includes this change): 1 Explain why additional days are needed (detaiieWspecific): Additional days are needed due to Fire Marshall of Immokalee Fire Control District requiring the following: 1. he requirement of a monitored fire alarm system based on the existing sprinkler system and the occupancy load concentrated. 2. Three existing exit signs (front door and two rear half) need to be changed to exitiemergency combos. 3. Purchase and install a supra -safe at the front door - order form delivered to our office. 4. Purchase and install an "R" sion at the front door. 5. Purchase and install a "FX' sign. Location to be determined. 1 Add new taskis} i 1 I Chanoe task(s) i Delete taskW I X Other (soeci v): Extension t. Provide a detailed and specific explanation of the requested change(s) to the task(s): The goal of this modification is to grant an extension until October 30, 2012. Although this contra was extended through April 30, 2C12 via SCC approval on 2 -14-12 (item no 101), we were recently informed of the lmmokalee Fire Inspector's requirement of the following additional items that have to be addressed for this facility: monitored fire alarm system based on the existing sprinkier system and the occupancy load concentrated, change of existing exit signs, installation of a supra -safe at front door, R, signs at the front door and an FDC sign location to be determined. Addionaf time is needed in order to complete the additional requested items. Z. Provide detailed rationale for the requested change: The extension will allow for a safe environment for persons who visit this public facility, and which will allow for a certificate of completion be given. Z. Provide explanation why change was not anticipated in original scope of work: This was an unforeseen circumstance due to Fire Marshall Inspectioniresults close to end of prole . 4. Describe the impact if this change is not processed: This public facility cannot open to Collier County senior citizens who receive free lunch meals due to this requirement. Revised: 1/1712011 i Packet Page -1133 Type of, Change / Modification 5/8/20 catian Item 16.E.4. � / EiecWe --_ -- _ - I - ..., clrixJmslance I U 3. Quantify or price adjustment ! 4. Correction of ermr(s1 Revised: 111212411 2 Packet Page -1134- Adni ni ►+e Senrces Division Purdl­iasinc Contract Change Request 5/8/2012 Item 16.E.4. Purchasing Department Change Modification Form ® Work Order Modification 1 Contract #: 09- ! Mod #: 3 1 PO/Work Order #: Project Name: Gordon River Extension 5252 4500130618 Maintenance Project Project-#: 51005 Project Manager: Jerry 1 Department: Land Contractor /Firm Name: Agnoli, Barber, I Kunz Development Services and Brundage. Inc Original Contract/Work Order Amount '$ 39,700.00 Current BCC Approved Amount #N/A , Current Contract /Work Order Amount $ 40,500:00 Dollar Amount of this Change $10,000.00 Revised Contract /Work Order Total Change from Current BCC Approved Amount $50,500,00 Cumulative Changes $i0,800.0 N!A Original BCC Approval Date; Agenda Item # Last approved completion date: 10 -4- Revised completion date (includes this Last BCC A' provaI Date; Agenda Item # 3/8/2013 SAP Contract Expiration Date (Master) 2710% Total Change from Original Amount #NIA Change from Current BCC Approved Amount 24.69% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: 10 -4- Revised completion date (includes this completion date: 10 -4 -12 12 1 change): N/A Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach current insurance certificate(s) from SIRE N/A or obtain from vendor): N/A Add new task(s) Change task(s) Delete task(s) Other (specify): Provide a detailed and specific explanation of the requested change(s) to the task(s): The requested change is to add a $10,000 time and material allowance to the WO for Engineering services during construction. 2. Provide detailed rationale for the requested change: The original lump sum scope included engineering assistance during construction in Task III. During final completion of the construction plans, also included in the WO. unforeseen issues of concern were identified by the City of Naples which needed to be addressed (the proposed work is located just within City limits). The issues were resolved within the original project schedule however, the budget for assistance j during construction was used up prior to bid award. This WO adjustment was authorized by the previous change order, CO # 2, a zero dollar change which combined Task 2 (Design and Permitting) with Talk 3 (Bid Assistance and Assistance During Construction). With the project finalized and remaining on schedule, the current amount for services during construction has a zero balance. This CO request is to provide for a new and necessary, $10,000 not to exceed task on a time and material basis for assistance during construction. I 3. Provide explanation why change was not anticipated in original scope of work: The circumstances leading up this change request were unanticipated because subsequent final design plan concerns identified by the City of Naples warranted changes which ultimately led to an optimum final design, that resulted in a cost savings to the project of $94.585. The changes were swiftly addressed and the project schedule was maintained. The completion timeframe is ! short as work is schedule to begin subsequent to Easter season and ending prior to rainy season. i 1 4. Describe the impact if this change is not processed: We would go to construction without the services of the design professional. This is not recommended as their assistance may be needed to address issues during construction, since they are the engineer of record . Type of Change 1 Modification '—] 1. Planned / Elective ®2. Unforeseen conditions /circumstance 3. Quantity or price adjustment j 4. Correction of errors 5. Value added I LJ 6. Schedule adjustment Revised: 7127/11 1 Packet Page -1135- Contractor /Consultant, Design Professional Purchasing Professional Particii Approved by: Name and and Title: Reviewed by` Procurement Sirate ist's Name: 'range rieaty _- Using -Y (specify): Other of Change / Modification: [❑ Yes Date: ?. I Date: 5/8/2012 Item 16.E.4. :)artment MCi!y): Revised: 7/27111 2 Packet Page -1136- 5/8/2012 Item 16.E.4. CC, e r County Purchasing Department Ad^nn ri,:k4i ve Services Jivisl0r) Change Modification Form ❑ Contract Change Request Q Work Order Modification Contract #: I Mod #: 1 ! PO/Work Order #: 45- Project Name: Collier Area Transit 09 -5207 120345 ± intelligent Transportation Svstems (ITS`, Project #: 33045 Project Manager: Llama Department: ATM Contractor /Firm Name: Renaissanc: I Carte, I Planning Group Inc Onginal Contract/Work Order Amount $ 47;.940.:00 9,291.09, 16B3 Original BCC Approval Date: Agenda Item # Current BCC Approved Amount $ ' -.- ^.- Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount S - 47,940:00 912812012. SAP Contract Expiration Date (Master) Dollar Amount of this Change 50:00 0-00%1 Total Change from Original Amount Revised Contract,Mlork Order Total $47.940,00 C.00% Change from Current BCC Approved Amount Cumulative Chances 1 $0.00 0.00% Chanae from Current Amount Completion Date, Description of the Taskls) Change, and Rationale for the Change Original notice to proceed Last approved completion date Revised completion date (inciudes this completion date_ 7i7; "2 % %-'12 1 change): 3/31/201? Number of oays added: 267 i Explain why additional days are needed ioetailedlspecific): (rf extension, must attach current This change order is to extenc the Work Order by adding 267 days to the proiect insurance certificate(s) from SIRE completion. Renaissance is the orime proiect management firm overseeing the or obtain from vendor;: Electronic Fareboxes implementation proiect. The vendor selected for this proiect is Fare Logistics and when the contract is awarded to them they will be implementing the Electronic rareboxes proiect which is scheduled for compietion by February of 20" j Therefore, we are extending the Renaissance work order to be completed concurrently with the Fare Logistics proiect. ❑ Add new task(s) Lj Change task(s) ❑ Delete task(s) Other (specify': Time Extension 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): This change order is to extend the Work Order by adding 257 oays tc the proiect completion. The revised new completion date would be 3'31;2013. 2. Provide detailed rationale for the requested change: Renaissance is the prime project management firm overseeing the Electronic Fareboxes implementation proiect. The vendor selected for this protect is rare Logistics and when the contract is awarded to them they will be implementing the iectronic Fareboxes project which is scheduled for completion by February of 2013. Therefore, we are extending the Renaissance work order to be completed concurrently with the Fare Logistics project. 3. Provide explanation why change was not anticipated in original scope of work: neinassance's contract inciuoes proiect manaaement of the Electronic Fareboxes implementation from beginning to end. Their contract includes the deveiopment of the RFP for the irrroiementation and integration the Fareboxes proiect, as well as oversioht of the entire protect from beoinninc to completion:. 4. Describe the impact if this change is not processed: If the Rennassance contract is not extended they will not be able to oversee the entire project until its full completion. Type of Change ! Modification i. Pranned ± 'Elective ! ❑ Unforeseen condltlonsfcircumstance UantitV or price adjustment 4 5orrection of error's; :l 5. `v'aiue added Z- 5. Scheduie adjustment Change Requested By Contractor'Consultant Owner Z Usinc Department Desion Professional El Recuiatory Agencv (soecitv;: Other !specify;: Revised: 7!271"', Packet Page -1137- D 5/8/2012 Item 16.E.4. — urc�hasing Professional Particmated in Negotiador -OfChanae Modification: Yes by'. = Cate; Name and I ifie: Reviewed by: Awl Date: r1rocurement Strategists Name::::: Revised: 7,27,111 Packet Page -1138- 5/8/2012 Item 16.E.4. County Purchasing Department ,�trrirt�tr, +erriw sj,;�cn Change Modification Fortn Ji Contract Change Request E-] ''i.Nork Order ModifiC:ation Contract : Mod #: 1 j PO/Work Order #-: 44- j Project Name: Coiiier ,Area Transit 109 -520- ' 1 ?38' 1 inteilioent Transoatation Systems ,' Proiect #: 03045 i Project Manager: vlama Department: ATIv1 Contractor/Firm Name: Renaissance j Carter I Plamnina Groot~ Inc Originai ContractivVork Order Amount e 189.400 :0C 9(29109, 16BE Original BCC Aporoval Date; Acenda Item # !Current BCC Approved Amount w " °0 -+�- -- ^- Last BCC Aporoval Date; Aaenca Item iCurreni Contract/Work Order Amount 31 89,400.00 9/2812012 SAP Contract Exoiration Cate (Master; IDollar Amount of this Change 50.00 �— CLDCO% Total Chance from Original Amount Revised Contract/Wpn Order Totaf j 89,400 00 j 0 000% w { Change from Current BCC Aooroved Amount !LUmu12tive Chances 0 0 '1L%I Change from Current Amount Completion Date, Description of the Taskisj Change, and Rationale for the Change i Driamal notice m proceed Last approved compietion date: Revised compietion date (inciudes this compietion date: 5/1012012 ! 5,112C'2 change): 12/31;2012 Numcer of a2vs acted. 235 Explain wily acidibonai gays are npecied ceTailed! specific ' (i? eX -vn5i0 mUSi ai aC urgent I hi_ Change order ,s to extend th= work Oder by adding %�5 QavS t0 the DfO1F'C insurance Cer iTlCat° 5? irOm SIRE CDmpletlOr. Renaissance ,s the Rnme prO]e= rnan20eMent firm overseeing the i or dblain from. vendor':: Implementation proieC: i he contract with Avail T eCnnolocies which/ is the Contr aac cr mpiementlnC and IntegratlnQ the TS prOiect, is scneduled for compietion by end of 201--. Therefore, we are extendinc the Renaissance work Order to be completed 1 concurrently with the Avail 7S proiect Add new iask�s) I f Chance 125Ki,sj Jeiete taS C(Sj Other (specify): Time _xten510r 1. Provide a detailed and specific explanation of the requested changets) to the task(s): ! TINS mange order is to extend the Work Order by adding 235 days to the protect compietion. The revised new compietion date would be 12,'31,2012 Provide detailed rationale for the requested change: ena;ssance is the proles/ management firm, overseeing the T S inlolemeniatlon project. The Contract with avail TeCnnologles wnicn is the ContraCIOr impiementing and integrating the iTS groiect, is scheduied for compietion by end of 2r'?. T herefore, we are extendinc the Renaissance Work order to, be Comoieted COncurrentiy With the .Avail i T -- proles.. Provide explanation why change was not anticipated in original scope of work: Reinassance's contract inciudes proiect , management of the TS impiementation from beginning to end- ,heir contras- Includes the deveicoment of the RFC for the implementation and Integration the i - D''DieCl. as well as oversight of ine entire Dried from beginninc tc compietion. 4. Describe the impact is this change is not processed: If the Rennassance contraL: is not extended they will not be able tz, oversee the entire Droiect anti; its full compietion. Type of Change /Modification Pianned i _iecIlve _. IDnforeseen. conditionsiclrCurnslance e ^I Z. Quantity or Dnce adiustmen; �Jr'e tiOr? gf e- or',s't Value added SCheduie adl'usiment J,E Packet Page -1139- Revised: T27-1 Aoproved bv� N2me -,nd, Titie reviewed by: Procurement St 'areaisi's N2M=-: Packet Page -1140- 5/8/2012 Item 16.E.4. Date: 5/8/2012 Item 16.E.4. C�& COUK0 Purchasing Department Admnstdm Service Divislan Change Modification Fors Purchsasing ''ontrac Change Request ,1 Work Order Modification i Contract #: 09 -5262 ; Change #: 2 POfWork Order #: 4500133676 Project Name: IMM USDA Build -Out Project #: 46C)40 i Project Manager: Department; Airport i Contractor /Firm Name: G. G;adv Minor Thomas Veroo Authority', i0noinal Contract /Work ;.order amount 47,710.00: N/,A Original BCC Approval Date, .Agenda Item # ICurrent BCC Approved Amount -4r- Last BCC Approval Date; Agenda Item iCurrant Contract /Work Order Amount 47,.7 ID. i0.0 (1-c7, 3 SAP Contract Expiration Date (Master; I Doliar Amount of this Chance 50:00 0.00'1/6 1! Total Change from Original Amount i �Revised Contract/Work Order Total $47,710.00 ; 0.00 t ; Chang e from Current BCC Approved Amount jC.umuiative Chances so. Do {x.00 %i Chance from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Onoina completion date: 4131'2 Last approveo completion date: Revise d -o moietion Gaic t inClSJdeS this 4/13/1.2 change): August " ":. 2012 Numbe- of Gays adder 120 Expiain why additional days are needed (;detailed /specific;: Proiect nas teen deiaved in the USDA approval process. USDA approval to bid the proieC toox ionger than anticipated. _+ Add new iaSl (Si C range Lask {,Sj L Delete task1s} 3 Mier i,spec►ry : Extend Schedule 1. Provide a detailed and specific explanation of the requested changes) to the task(s): Ext °nd tne Schedule Dy 120 days from April 13, 2012 to August 11, 2012. 2. Provide detailed rationale for the requested change: The project has been delayed in the the USDr, approval 3. Provide explanation why change was not anticipated in original scope of work: The amount of time required for the USDA to approve the bid package took longer than anticipated. 4. Describe the impact if this change is not processed: Tne .Alrpor .Authority will not be abie to compiete the project Type of Change r Modification Planned ' ciective -1 Unforeseen conditions circumstance i 3 Quantity or once adiustment 4. Correction of error;S; _i Value added 6. Schedule adlusiment I Change. Requested By J Contractor /Consultant Owner Usina DeRariment _ U Design Professional U Regulatory Agency (specify ): ; Other (soeGifyi: Purr asina P; ofessio,,ai Participated in Negotiation of Change Modification J Yes No t Approved by .� t^. �'� Date: , Name and Title: "comas Veroo, Airport M2nager Reviewed by: Procurement Strategists Name: i I Revised: 3.'25/': Packet Page -1141-