Agenda 03/13/2012 Item #16E23/13/2012 Item 16.E.2. EXECUTIVE SUMMARY Recommendation to accept reports and ratify staff - approved change orders and changes to work orders. OBJECTIVE: To enable the Board to oversee the execution of administrative change orders and changes to work orders and promote accountability in the use of staff authority. CONSIDERATIONS: On April 22, 2003, the Board approved a recommendation to implement a plan to enable changes to BCC - approved contracts (Section XV.C, Collier County Purchasing Policy) of not greater than 10 percent of the current Board approved amount or $10,000 (whichever is greater) to be authorized by staff. Also included in the report are changes to Work Orders. These include work orders issued under CCNA Contracts that are less than or equal to $200,000 (Section VII.C, Collier County Purchasing Policy), and changes to work orders for all other contracts (Section XV.G, Collier County Purchasing Policy) that are not greater than 10 percent of the current Board Approved amount or $100,000 (whichever is greater). The Administrative report identifies the percentage changes to contracts or work orders that have occurred since the prior BCC approved amount which are below the threshold limits as referenced above. The plan calls for staff to submit a monthly report listing these change orders from the previous reporting period. Enclosed is the monthly report of the Administrative Change Orders and Administrative Changes to Work Orders. These reports cover the period of January 26, 2012 through February 24, 2012. FISCAL IMPACT: The total for 6 changes to contracts is $5,997.87. The total for 8 changes to work orders is $6,690.00. LEGAL CONSIDERATIONS: This item raises no legal issues and requires majority vote for approval. -JAK GROWTH MANAGEMENT IMPACT: There is no Growth Management Impact associated with this action. RECOMMENDATION: That the Board of County Commissioners accepts the enclosed Administrative Change Orders Report and Administrative Changes to Work Orders Report and ratifies the listed change orders and changes to work orders. PREPARED BY: Diana Diaz DeLeon, CPPB, Contracts Technician, Purchasing Department Packet Page -1458- COLLIER COUNTY Board of County Commissioners Item Number: 16.E.2. 3/13/2012 Item 16.E.2. Item Summary: Recommendation to accept reports and ratify staff - approved change orders and changes to work orders. Meeting Date: 3/13/2012 Prepared By Name: DeLeonDiana Title: Contracts Technician, Purchasing 3/1/2012 10:42:50 AM Submitted by Title: Contracts Technician, Purchasing Name: DeLeonDiana 3/1/2012 10:42:51 AM Approved By Name: pochopinpat Title: Administrative Assistant,Facilities Management Date: 3/1/2012 11:47:32 AM Name: MarkiewiczJoanne Title: Manager - Purchasing Acquisition,Purchasing & Gene Date: 3/1/2012 1:10:14 PM Name: MarkiewiczJoanne Title: Manager - Purchasing Acquisition,Purchasing & Gene Date: 3/1/2012 1:33:24 PM Name: WardKelsey Title: Manager - Contracts Administration,Purchasing & Ge Date: 3/1/2012 1:50:11 PM Name: PriceLen Packet Page -1459- Title: Administrator, Administrative Services Date: 3/1/2012 3:35:57 PM Name: KlatzkowJeff Title: County Attorney Date: 3/2/2012 4:04:33 PM Name: FinnEd Title: Senior Budget Analyst, OMB Date: 3/5/2012 1:18:33 PM Name: OchsLeo Title: County Manager Date: 3/5/2012 2:04:49 PM Packet Page -1460- 3/13/2012 Item 16.E.2. N w O � G N y C > 2 t O C a 0 m ) a O L U W E U Q o O U w N m t0 O rn y c y Of a0i c a `y M w V N � O "> E E w 0 Q w m E d 0 O t O E U Q w > > E O a 'o L E U U w U o m w w � o E , o �' ` E w O Q U U w of d c U o E m p) U O m Q w Q d � E � o D a O Ci Z Z m C y a Z 2 O Z A m 0 a c u O ` > n U U a N y N LL O 7 } O a. w m Z LL 0 Co 0 O Co a o 'Co m U O 5 o a) O a) m C o m M a) o O d N O > a o Oi - va `o m L m o a r- O -r- (D N O N a) U LO c Co M ' 'D LO Ld w c E C > C! a c O J N a m O LL N m 2 )n m o w J a 0 (D 0 o 0 c a 00 cc LO `o U- O) C Ln O O @ @ O w N N @ O) � CD Q 3 a oaa) O Q o 0 w O N C m O N O a m o � U) @ o ate) C � o � on «_ O O N y E U o a) @ T C •0 u1 3 > C X > m m M @ o E 3 Q NLq O Y N E (Mn ° F0- O) c a) N C m NL O r J () N O C C O m � •Z o r m m > o O 0 C a) 0 O X Cu Cu 00 m 'O a @ N O N a) m Y L O 0 @ d o 0 m ao N m (n LO o ai OR y 0 C U M 2 L (n a) -- « m a) y �M N U N C Ln o C O O) - o N w � � ,°n a Q y CL a v O p a C L ' O a) n 3 E a) a) c N 3 � m c w .0 O 0 °o 0 00 O Co (q to O O Co O (mo Co w 0 0 C Co m 69 0 O Co (C Co w a�m � O N ada L) O CL @ Q Cu c m a N O c U 0)r m LL o � o Z N CL a Z O I Co C ai C O Co m a E a o U L) O U 7 « N o � N m E O O 0 0) N C r 'o .T• rn c 3 E � o N L .O a) c c @ O Y m 3 0 o .. a1 0 O Of � C A L � `O 'a I Co ' > 'M O M Packet Page -1461- 3/13/2012 Item 16.E.2. M m N rn 7 C) Co 69 Cli v O N O ri T L O N V" w N 0 ci N c (A N C a) a @ C y O X Cu Cu N Q 'O a @ N Q Z N a) m @ L O 0 � Cr o Z N ur U � O Q .- c m 0 °o 0 00 O Co (q to O O Co O (mo Co w 0 0 C Co m 69 0 O Co (C Co w a�m � O N ada L) O CL @ Q Cu c m a N O c U 0)r m LL o � o Z N CL a Z O I Co C ai C O Co m a E a o U L) O U 7 « N o � N m E O O 0 0) N C r 'o .T• rn c 3 E � o N L .O a) c c @ O Y m 3 0 o .. a1 0 O Of � C A L � `O 'a I Co ' > 'M O M Packet Page -1461- 3/13/2012 Item 16.E.2. M m N rn 7 C) Co 69 Cli v O N O ri T L O N V" w N 0 ci N c (A N T � a @ C y O 3 -° 3 c 0 w F O m y � � E 0 o � C o Z N ur U U p a o N @ o0 N N a T ((O m 0 o 0 a @ E u o a, N_ E E (D m '0 C @ Co T N O a C) N v O L 00 Zr�J(4 O f- O y o N O C C ca M V) a ° (� N o o . C O o) a C Co O Cl. c N m � o U Z @ N > N O O �0 0 °o 0 00 O Co (q to O O Co O (mo Co w 0 0 C Co m 69 0 O Co (C Co w a�m � O N ada L) O CL @ Q Cu c m a N O c U 0)r m LL o � o Z N CL a Z O I Co C ai C O Co m a E a o U L) O U 7 « N o � N m E O O 0 0) N C r 'o .T• rn c 3 E � o N L .O a) c c @ O Y m 3 0 o .. a1 0 O Of � C A L � `O 'a I Co ' > 'M O M Packet Page -1461- 3/13/2012 Item 16.E.2. M m N rn 7 C) Co 69 Cli v O N O ri T L O N V" w N 0 ci N c (A N c N 7 O E c 0 w F O @ Y � � E 0 o � C o Z 3 ° @ a o N ' > U @ a) CD E m j C aw T ((O m 0 > ' -v o 0 o a`) y a) N_ E E aa)) a C @ O N U T N 0 3 o a C' d O a) a) y O C N M V) a ° (� N o o a m m Co ro in o) a a m Co O Cl. -`o N T o U c a) @ r- it CL7 O C O 'N 'W m Z Co v >a O @ 0 a) O 0 rn C; OD Om) Nr v M 64 00 to V (o M m m W ID m a m M (A N 0 w0 - O E a) ur N 3 N C O U ID 0 U m N x r E c C a) � E > a > @ 0 am m E 0 a) m Z 3 ° @ a o N O 0' () c -0 o) LU N @ T ((O m 0 C T C O m r H a H N_ Co U C @ a L 0 O d m O Packet Page -1462- 3/13/2012 Item 16.E.2. w ee & &§7 \ k / k E £ Co )E , 0 —m cc /k )_ cc E CM &tom E } �O� ° 0} Co 2 t 7 = > N 0 Co _ M CT —E ƒ _| k ]) &; Iq =y /2Co 6} Co )69 E _ ) _ Cl 2k$ - 'DtM EiE _ - �v� - U \ m _ x - > Ef t5 C \ {E CO L) �\ g _ \ \ F- k\ _ �_ k .7 2 0 w ELJ CD � IM § - M < . a .. ƒf ar E tf <0 M 2>a a� !27 j \\ $t\ \ }} 2 6d f �z -,,A E 3 E ! -0| R 00> 2kk 2 3 / `_ ¢$� /$ /R\( \)k iaGoa ± /§§ \} \ 2 / 0 \ �k CM 0) \ 5o { t y & § § ) i CD M \ {[ \ \ /k Co 37) \ — Packet Page -1462- 3/13/2012 Item 16.E.2. w 0 O O � O � � wfn co .0 a C N R N � c > a) O ` LvU ° o a) p O aE ) o � ci to U N R 69 U c i a) E c m O O C ° R O 0 69 � L o R R L O a) LL W � m o C/) N O C ur R c o a) Q � a Z U (D R C R a 7 N O O � N � L N m C R m 3 ac) o 0 E O O L a) C N > > U o R °0- o w .0 'o !° a0 OE a) 3 a R O Y O O 2 0 3 )O R N N ED O O C cO eq N N — u') m O N O o E o ao 0 C c U U c N m w o u) ate) oa U R 0 c o d C �E 0 L T a) dm a) T o m� a a) 0 co N o O O a 3 CJ°0Uc? H c d O is cis E cm R u) m N U a) C O O > O O No ? m E c o a N O Pa( O 0 O 0 CD m ti C') u9 m a 'U c O R y°9 c 0 L 0 O � )0 3 � O M = � E R Q\ R Z D d p� U U C O N m L o C 6 > R N y a) N y R U Y T O O Y E _ m � f/) m U N Y O N N @ Cc,) N (O M O L? N C O 7 O M � C) c c w D) 00 a) C p m E a) 0) E c a) > m c Y ° a) W 0 E r a) E E a L MS E a) m E a) > w R o m Samo °' UZUUco 10— ai a c R N L U 0 O O O - d :ket Page -1463-; o co O co co co O 'O N 0 lh C O O OD o 0 U O U C R R N _ a) R y O cli E o c °) o O O m N O N L L @ iq a E >o N O C co 04 0) N E co CU U� rn C 3 `o m � j U � c z m � N C N N a) w N R U C C 0) N N � � m o r a0 L L E ° rn L C Q rn c Y C R a > R R O U C N R y E m � C) R R O L Q ID U ay N N CD C C,4 N N O_ T G a) x O N Vo 0) > > o a) c c 3 a N co U N to > m y a _ 0 U O R R o a o a uN ca L < @ H N V m O 0 O p R R U p L R O O `o 3 a a) o) c R O N L U N 0 m 3 O � O O -1 d > > X V O 'u 3/13/2012 Item 16.E.2. 0 O O N 69 O 0) ui O O 69 Q Z O O m 69 m o) o C � c E C R Q CL a) N c � m a) H � CD N N C a) o O � N O m t O (7 Ch M a C Q. T (D 0 O N C) a) p R u1 M L R 5c)U� N O �> r! 6 rn c L U O aj 0) R •� U d N > O 2 9 N W a R U O 0 O O O � L p N C) d a c U t N � O C O O w o U U m c N � O C U) O 0 Y E ^ N m C jQy+ C6 O 2d > � m m 0 0 O 0 C O m O o E °o a E E Y U a) R ` O O Y E N c U_ U Q ro co L 40 N a! o C a) E a p m U 0 O Q EL a) fr o Lj m a Q Z O Q 40 m Y � c d C R O p O U R 7 C O o m0 a[ E N E O 69 a) E = U 'O W () a) ~ E O c a) m 0 y LL r a) w Z cc G O U O Q a 0 LL c 7 of a) Q O O. x Y w Z O c 00 $ Z 0 U 0) N Q O cc N v] N N N O 0) C c N O O L N p O �U vocn � v C � 0 C N C 0 U y > > m O Z m m L +U E �E c cny r Z Z0 2 IM ykY o 3 d O U O) V 0) op^� p LU r O O R C Lo aA C N rya R c > acLia EL V) L) N N LL > m y a c N of N R U W UO > O > O LL a15 o -j D a d = Z O 0 O O � O � � wfn co .0 a C N R N � c > a) O ` LvU ° o a) p O aE ) o � ci to U N R 69 U c i a) E c m O O C ° R O 0 69 � L o R R L O a) LL W � m o C/) N O C ur R c o a) Q � a Z U (D R C R a 7 N O O � N � L N m C R m 3 ac) o 0 E O O L a) C N > > U o R °0- o w .0 'o !° a0 OE a) 3 a R O Y O O 2 0 3 )O R N N ED O O C cO eq N N — u') m O N O o E o ao 0 C c U U c N m w o u) ate) oa U R 0 c o d C �E 0 L T a) dm a) T o m� a a) 0 co N o O O a 3 CJ°0Uc? H c d O is cis E cm R u) m N U a) C O O > O O No ? m E c o a N O Pa( O 0 O 0 CD m ti C') u9 m a 'U c O R y°9 c 0 L 0 O � )0 3 � O M = � E R Q\ R Z D d p� U U C O N m L o C 6 > R N y a) N y R U Y T O O Y E _ m � f/) m U N Y O N N @ Cc,) N (O M O L? N C O 7 O M � C) c c w D) 00 a) C p m E a) 0) E c a) > m c Y ° a) W 0 E r a) E E a L MS E a) m E a) > w R o m Samo °' UZUUco 10— ai a c R N L U 0 O O O - d :ket Page -1463-; o co O co co co O 'O N 0 lh C O O OD o 0 U O U C R R N _ a) R y O cli E o c °) o O O m N O N L L @ iq a E >o N O C co 04 0) N E co CU U� rn C 3 `o m � j U � c z m � N C N N a) w N R U C C 0) N N � � m o r a0 L L E ° rn L C Q rn c Y C R a > R R O U C N R y E m � C) R R O L Q ID U ay N N CD C C,4 N N O_ T G a) x O N Vo 0) > > o a) c c 3 a N co U N to > m y a _ 0 U O R R o a o a uN ca L < @ H N V m O 0 O p R R U p L R O O `o 3 a a) o) c R O N L U N 0 m 3 O � O O -1 d > > X V O 'u 3/13/2012 Item 16.E.2. 0 O O N 69 O 0) ui O O 69 Q Z O O m 69 m o) o C � c E C R Q CL a) N c � m a) H � CD N N C a) o O � N O m t O (7 Ch M a C Q. T (D 0 O N C) a) p R u1 M L R 5c)U� N O �> r! 6 rn c L U O aj 0) R •� U d N > O 2 3/13/2012 Item 16.E.2. N W IM a l0 U O O 0 O 0 O p cG t Y O Y O N r ; U E O` ° m o 0 3 o x 3 m Z L 0yj 0 0 O a3 N a C O - a) y -5 -2 N O 0 C d 01 m ° OY 3 C a N e Y u) o y Y Q .� R O O w O y 3 O U (L,) E C O O C Ci N Mn L O a) y wC 3 y o 3 F c L 3 U N° N y i m E ° E° 3 E 3 o y O O E o ro m > ,c pQ ro m e N u N E o st ° Nw W 69 .� yg L �` C 6 {q w w L C U .2 U C () a) N C a) N °� L_ N 0 3 N C y oa'$ a) C y o�° o c L O C O)O O E p o '° mY o o rna Via° O L �L o'o ° m° ecox t O Q to p t» m O t oo' vi a7 7 O U�w o cm m rn$ m w N c c c E c c E c O C O (0 47 Uf6 U DC O .O N L) 00 O y O O O p yZ y o C N Q m a, x E E 3 0 U�w y� E12 v; L) 7 fA °3r m y U .F O u�i o> m O m 3 .o � c� w '4 C C O „a y O) O C C C r= w O O@ C d' > d U O O Q .0 L Q Q y C$ Q N C U 0 m Z °~ Z m m o Z m O �j aQ Q N a) O aa)) a _ U -c d o c C O O C C C ° o o O p= O N C Z° o y �° o C U o Q y F S p O °°° O "° E cYi o w Q m N 2 U m ° a C m ZO N+ 69 a) fN3 C (a 6c 9 c Q c Z > a a> ) y m v m m a E c m g E > C w m m Y a) aa) ° E C F C C p c 3 :9 Sm N C c 'co: _ cE� a3 0) a) C O E rn cc a) am 0 U a) tm Aga � °° mua c2.o ca C° o a c' .2 a) m. Q d Q m o c m. Q a o o ° m a om° a.� @ `m a c c `° = a` :� o c oa f-� E o ° acef¢ y o aOi aasQ c a�o) a) C @ L T y N a) to O) Vl a) m a) co l0 y .0 2 m to z 0 o a o $ o E U o E o x o m as w o o o m a o a) a cL C Lo L 7 ° O C 0 E d° L Z O U � 0i O V! a) Y U fN, 0 Y U d U` M N M % O U N N M O O N N m o a) C y O N N O 'O •o N O N a) o a) O N N a) O a) O O a7 U ^L 0o C U� o O1 m M .L-. C O L-. C Y— 7 o [h a1 M U N f O O N y 't o of O N a y w ° p N C Y -0 Y.-. L.L.. > w ° cl x L) o y m o cm '0 o m o y 0 N 7 co OO 7 U C C j O 0° � I-- E ? a E O CO 2` Q O O) V m y N Z m `m m Q 3 Y L o C fy6 > >> O 01 C 7 3 O W i m c= a m L= a R° 9 cc Z2 °Z X y = xt a5 o aa)) w w o f o d a°)) -' o w m- o -' o ° E O U V O m O a7 U a7 .0 m V] O) C c °- .� _� a) m C y I c a '° .� a) Q N C 'O^ R 'O^ N O j N a) Q c) m y O° Q O a) N O a) N % a v a U O U O L1J H N (0 cc r- f— T a = N L) m F T O O LL a3 C .> a) a) C a) N Y a m o` O` a) D! Q C c °a'a R o a� Ql °v °m > U) N m N m Lo w m 7 U O U .L. N N U f N y w a) O O ° 0= N ° p o N O c0 �0 Qf D a o a o!P oz m oZ m U a) `y NO > N a) N N N al C a) Z `° ° 2 ~ ° Packet 72 Page - 1464 -' 0 3/13/2012 Item 16.E.2. 3/13/2012 Item 16.E.2. - Co Cow-my Purchasing Department rli5ts3n Change Modification Form Contract Change Request L Work Order Modification Contract #: i0-5494 1 Mod#: 1 PO/Work Order #: -w44- 1 Project game: MKY Taxiway Construct Project #: 33127 i Project Manager: Robert Department: Airpor Authority I Contractor /Firm Name: DeAngelis Tweedie Diamond Original Contract/Work Order Amount $ 51959000.00 10112/10,148 Original BCC Approval Date: Agenda Item # Current BCC Approved Amount S51 00 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $54'18704,07,,00 SAP Contract Expiration Date (Master) Doilar Amount of this Change $91,-523.00- -1,33% Total Change from Original Amount Revised Contract.ANork Order Total $5,879.930.00 I - 1.33% Change from Current BCC Approved Amount Cumulative �Chancies (579,070,00} 0.16% Change from Current Amount Completion hate, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: 2/2112 3/3/12 change): N/A Number of days added (if =xplain why additional days are needed (detailed /specific): extension, must attach current insurance certificates) from SIRE N/A or obtain from vendor): N/A Add new task(s) i LJ Change task(s) I U Delete task(s) I Z Other (specify): provide credit for l I unused materials 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): (1) Remove unforeseen debris as specified per work directive # 1, add demucking at FPL lines, increase height of berm as specified per work directive # 3, Provide additional electrical conduit and phone conduit per FPL and Centuryl-ink requirements, soil boring for demucking, demuck at taxiway as specified per work directive # 2, density testing for taxiway demucking, and furnish and install 12' gate. (2) Provide credit for unused quantities of soil mixing, geo fabric, unclassified excavation, and FPL conduit.(See attacned supporting documentation) Provide detailed rationale for the requested change: 1. Unforeseen buried debris not included in original scope of work required to be removed for son preparation in paved apron expansion area, contractor performed this work at no additional cost, 2. FPL power lines required to be relocated and not within original scope of work required demucking for sub surface soil stabilization within paved apron expansion area, 3. Berm height along West side of taxiwav A as specified per proiect plans, was below water level at time of construction due to construction during rainy season, contractor performed work- at no additional cost, 4. Additional FPL & Century Link conduits required for relocation of utilities not within original scope of work, S. Soil boring to determine actual depth of peat layer within taxiwav conducted to determine viability of performing demucking as alternative to soil mixing for budgetary savings on soil mixing quantity, b. Demucking within areas determined through soil borings to nave areas of reduced peat reducing quantity and budgetary cost of soil mixing, 7. Density tasting required for determination of appropriate sub - surface soil stabilization of areas de- mucked in ieiu of soil mixing, E. Airport management requested addition of 12 ft, sliding gate along fence line at North perimeter of North /South apron expansion area at Mainsail Drive to provide alternative limited access for airport ooerationai use. Provide explanation why change was not anticipated in original scope of work: Sub -sur-face conditions in some areas of overall proje . varied from anticipated conditions, 4. Describe the impact if this change is not processed: Project cost= would exceed oudget and would not perform to reouired specifications. Type of Change / Modification LJ 1 planned 1 Elective 2, Unforeseen Conditions /circumstance k Quantity or price adjustment j i_ i 4. Correction of errorisl ®5 'Value added ! 1 i 6. Schedule adjustment Revised_ 7!2T11 1 Packet Page -1465- 3/13/2012 Item 16.E.2. a, change Requested By Contractor /Consultant 1 Owner Design Professional I J Re uiato Acncv !s eci" 1: _U Usin De artment Purchasing Professi L Other !s ecity): hgR97'articipated in Necro't ion of Chance f Modification: L Yes No I r � Approved by://f �f Date: ae and TrMe: Kobert Tweedie, Airport Manager r N m Reviewed by; Procurement Strategist's Name � n ood � RevAsed: W27!; 1 Packet Page -1466- CD Ner C Wtt AcirrinisIrEive Services Division Rurrhasinrg Contract Change Request 3/13/2012 Item 16.E.2. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #: Mod #: 01 (one) PO/Work Order M Project Name: Lely MSTU Dora] 11 -5604R 90,524.42 4500129815 Circle Roadway Sidewalk Revised Contract/Work Order Total $98,619.27 Cumulative Changes Improvements (at Bridge) Project #: Project Manager: Darryl Department: ATM Contractor /Firm Name: BONNESS 4500129815 Richard Department INC Original Contract/Work Order Amount $ 9Q524;42 Current BCC Approved Amount $ 90;524.42 _I Current Contract/Work Order Amount $ 90,524.42 Dollar Amount of this Change $8,094.85 Revised Contract/Work Order Total $98,619.27 Cumulative Changes $8,094.85 ( Original BCC Approval Date; Agenda Item # 1� Last BCC Approval Date; Agenda Item # SAP Contract Expiration Date (Master) 8.94% Total Change from Original Amount 8.94% Change from Current BCC Approved Amount 8.94% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: 03- Revised completion date (includes this completion date: 10 -17 -11 05 -12 change): 03 -05 -12 Number of days added (if Explain why additional days are needed (detailedispecific): no days added extension, must attach current insurance certificate(s) from SIRE - obtain from vendor): 0 (zero) c� Add new task(s) I ❑ Change task(s) ❑ Delete task(s) I ❑ Other (specify): 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Change is to address sub - surface rock found in place where a directional bore is called for in the project. The directional bore called out in the contract is necessary in order to provide electrical conduit for 4 new light fixtures on Doral Bridge. After 3 failed attempts to bring the conduit to the surface the contractor requested that design consultant and staff review the situation for a recommendation on how to proceed. The proposed solution was to excavate the rock which obstructed the contractor's directional bore in order to allow the conduit to be exposed at the ground surface. The entire evolution of the work item required adding mobilization, excavation, adding backfill ( #57 stone), dewatering, installation of shoring so that the pit would not cave in, and installation of quazite pull boxes. ADD TASK 21 Mobilization 1.00 LS $950.29 $950.29 Additional Detail: Additional to original contract is the mobilization of certain equipment for the proposed change. Additional equipment required is excavation backhoe equipment, jack hammer, dewatering pumps (3 dewatering pumps required), shipping of required shoring material (both metal and wood materials), shipping of new Quazite pull boxes to site. ADD TASK 22 Excavate Bore Pit - includes Rock Hammering, 1.00 $4,253.36 $4,253.36 Removal, #57 Stone And Backfill Additional Detail: Excavation of `bore pit' requires removal and replacement of approximately 38 cubic yards of soil and rock and then backfill with #57 stone. DD TASK 23 Lewatering 1.00 LS $766.07 $766.07 Revised: 7127,' ','i i Packet Page -1467- iAuumonai uetait: Dewatering operations are necessary for removal of water during 3/13/2012 Item 16.E.2. 1e4 safety of personnel working in the 'bore pit'. ADD TASK 24 Trench Shield Or Shoring 1.00 LS $814.91 $814.91 Additional Detail: Shoring is needed for stabilization of sides of 'bore pit' and to ensure safety of personnel working in the bore pit. ADD TASK 25 Install Quazite DOT Pull Boxes 2.00 EACH $655.11 $1,310.22 Additional Detail: 2 (two) additional quazite pull boxes are required to tie into the new conduit after installation the resulting depth of the new conduit (directional bore) was deeper than the original project specification to ensure proper clearance for sanitary sewage line found in the path of the directional bore. 2. Provide detailed rationale for the requested change: Change was required to address an unforeseen sub- surface rock condition which impeded the installation of the directional bore and associated electrical conduit. 3. Provide explanation why change was not anticipated in original scope of work: The sub - surface rock could not be located. The only possible method to find such rock would be to perform a thorough geo- technical study which was beyond the scope of the work and would have been cost prohibitive. 4. Describe the impact if this change is not processed: If not processed the necessary conduit would not be installed and the 4 lights on the bridge would not have power. I Type of Change /Modification I ❑ 1. Planned / Elective I ❑ 4. Correction of error(s) I Z 2. Unforeseen conditions /circumstance j ❑ 5 Value added a ❑ 3. Quanti or rice ad�ustm„nt I ❑ 6 Schedule adjustment Change Requested By II Contractor /Consultant ® Owner �I Using Department ® Design Professional g ❑ Regulatory Agency (specify): ® Other (specify): Lely MSTU Advisory Committee Purchasing Professional Participated in Ne otiation of Change / Modification ❑ Yes Z No t Approved by: J Date: / >{. ;2 Name and Title: er i Reviewed by:%,t,%1�7%.�,t� 'i '`fit ✓' Date:'7 Procurement strategist's Name: Rhonda Cumming m s, Procurement Strategist Revised: 7;27/11 2 Packet Page -1468- I - 3/13/2012 AtpOl 16.E.2. F����r� Ac�mm�efi*Sam���C�omcm ~~r~'~'~~` pwnchas,m Change Modification Form Z Contract Change Request Fl Work Order Modification I Project Name: NCWRF Compliance 5446 14500117097 Assurance Project Project #: 73950,1 i Project Manager: Peter Department: PPMD Contractor/Firm Name: D.N. Higgins Original Contract/Work Order Amount 31 8,683,000,00 3/46110, IGA Original BCC Approval Date-, Agenca Item # Current BCC Approved Amount $ 8,683�000.00 N/A_ Last BCC Approval Date-, Agenda Item Current Contract/Work Order Amount $ S,683i,000.OD Acid new task(s) Change task(s) F SAP Contract Expiration Date (Master) Dollar Amount of this Change TO,00 0.00% Total Chanqe from Onainal Amount Revised Contract/Work Oroer Total F--s-876-83, 000. 00 1 0.00% Change from Current 6CC Approved Amount Cumulative Changes 1 $).00 1 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date. R Revised completion date (includes this completion date. 11/1912011 3/15/12 change)� 7/1312012 Number of days added (if Explain why additional days are needed (detailed/specific): The project was extension, must attach current substantially complete as of 1112312011. The additional days are needed to negouale insurance certificatet"s) from SIRE I and reconcile final project costs in order to close out the project, or obtain from vendor): 120 to Final Completion date Acid new task(s) Change task(s) F F-I Delete task(s) Other (specify': Add days to final 1 i completion for project close out negotiations and reconciliation of 1 costs Provide a detailed and specific expianation of the requested change(s) to the task(s): This change order is to add time at no cost. Substantial Completion certificate was issued and dated November 23, 20 11, and the County has beneficial use of the project. This change order will add 7 days to the last approved Substantial Completion date and 120 days to the last approved Final Completion Date. Total time extension of seven days was required ` Directives- Final Completion time extension is required to allow negotiations of outstanding Work Directives and to close out the 'Droject. 2. Provide detailed rationale for the requested change: The time extension will ensure conformance with all contract requirements. Substantial Completion of this project has provided upgrades in sustainability and DEP permit compliance assurance aa well as energy savings. This project a>sohe|psensunetheoonbnuous product/#n of Irrigation Quality water for the County's irrigation customers, The requested time extension provides an equitable adjustment of the original Contract Time to accommodate justified delays associated with Work Directives and Owner furnished equipment J\ Provide explanation why change was not anticipated inoriginal scope mf work: Due hounforeseen conditions in the field during construction. there was no way to foresee the additional time required toaccomplish |the contract work. Modified project items such ae removal of additional q�tmthe aeya�oObBs��a�D�]��/ re/��auonvvonk.an�stonnvvatergradingtorneetregu\adoryuornphance-ereuomp\etedond5na\'' piping \ w �r��o)rB6tDC»o�e out the pr )e± negotiations — 4. Describe the impact if this change is not processed: In order to meet all contractual requirements, it is ij necessary to negotiate final quantities and and final project . schedule, if this time extension is not implemented, there would be delays in final close out of the or- ect. The contractor is contractually d Revised- 7,27/1 Packet Page -1469- time extension as the delays were beyond his control. Failure to provide the i 3/13/2012 Item 16.E.2. higher bids on future projects as prospective contractors might be uncertain if their justified time extension j requests would be honored. Type of Change ! Modffraation 1. Planned 1 _lective 2. Unforeseen conditionsicircumstance 3. Quantity or price ad't 4. Correction of error(s) I z 5. value added i L9 6. Schedule adjustment Change Requested By ® Contractor /Consultant j [, Owner �Llmen [� Design ene s eci ): t Purchasing Professional Participated in Negotiation of Change / Modification- Yes LJ No Approved by: Date C..- V Name and Title Peter Schalt. Senior Project Manager' Reviewed by Date: Procurement Strategist's Name: Nicole Parker. Procurement Strategist Revised: 712711 ? 2 Packet Page -1470- Comer AdrrdndraM SeNmm OMsion Purchasing ® Contract Change Request 3/13/2012 Item 16.E.2. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #:11 -5661 Mod #: 3 PO/Work Order #: 4500128826 Project Name: Progress Avenue Roadway Improvements from Airport- Pullin Road to Commercial Boulevard $ ( N/A Last BCC Approval Date; Agenda Item # Project #: 60182.3 Project Manager: Julio F. Ordohez 7Erngineenng epartment: Transportation Contractor/Firm Name: Better Roads, Inc. Original Contract Amount $ 475,243.02 r 1 ff Original BCC Approval Date: 6114/11- 16.A.18 Current BCC Approve=! Amount $ 475,243.02 N/A Last BCC Approval Date; Agenda Item # Current Contract Amount $ 482, 006.13 Dollar Amount of this Change Z Change task(s) I ® Delete task(s) 1 ❑ Other (specify ): ($20,205.24) Change from Original Amount i f Revised New Contract Total ! ❑ I-❑ $ 461,800.89 Change Requested By Cumulative Changes ($13442.13) - 4.19 °!° Change from CurrentAmount Completion Date, Description of the Task(s) Change, and Rationale for the Change I I Original notice to proceed date: September 6th. 2011 I Last approved date: February 18th. 2012 Revised date (includes this change ): February 18th. 2012 Number of days added (if extension, must attach current insurance certificate's) from SAP or obtain from vendor }: 0 ! To authorize the performance of punch list work aenerated during the Walk Thru InSDection New Day items are added: Removal & Replacement of a Frame and Grate at the existing drainage structure on Progress Avenue and Airport Road, Modify Existing Sanitary Manhole top Removal of a vault and a Extension of an existing Fire Hydrant at the Proaress Avenue /industrial Boulevard intersection. The ouantity for Super Pave is also beino reduced to its final amount. There is no need for a time extension. ® Add new task(s) Z Change task(s) I ® Delete task(s) 1 ❑ Other (specify ): 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Provide for new pay items for punch list work and reduction of the paving work. 2. Provide detailed rationale for the requested change: Improve safety along the facility. 3. Provide explanation why change was not anticipated in original scope of work: The Collier County Wastewater Department changed the design to better fit existing conditions. 4 Describe the impact if this change is not processed- The project cannot be completed for final contract close out. j i Type of Change / Modification ! ❑ I-❑ 1 Planned / Elective ® 2. Unforeseen conditions /circumstance 3. Quantity and price adjustment 4 Correction of error(s) ®5 Value added i ❑ 6. Schedule adjustment Change Requested By ❑ Contractor /Consultant ® Owner I Using Department Tansporiation ❑ Desi n Professional ❑ Regulatory Agency (specify): I Other specs : Purchasing Professional Participated in Negotiation of Change / Modification: M Yes ❑ No Approved by (Name and R' r Date: Reuiewed y (Purch sing Pro sionalj` tho rrrrnings, ontract Socialist Date: V Revised: 111212011 v Packet Page -1471- - -_ -. - -- - -- — �+(7 %nistl�c..t'' ve Ser 4ces - ,vis>cin "'uiii ic�J(Ei£i [' Contract Change Request 3/13/2012 Item 16.E.2. Purchasing Department Change Modification Form 7 Work Order Modification Contract*. 11 -5767 I Mod #: 1 POtWork Order #: 450017 -3195 Project Dame: Tavior Rd. Roadway Improvements from Pine Ridoe Rd. to J &C Blvd. Project #: 601$2.2 j Project Manager: j Department: Transportation Contractor /Firm Name: Quality Enterprises Julio F. Ordor ez Enaineerina j USA. inc. Oriainal Contract/Work Order Amount $ 1,346.946.86 N/A Original BCC Approval Date: 10,25/'11 -10.D Current BCC Approved Amount $ 1,346.946.86 NIA Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 1,346.946.86 Dollar Amount of this Change $2,550.00 0.19 0lo Change from Current BCC Approved Amount i Revised New Contract/Work Order Tats! $ 1,349,496.B6 Cumulative Chances 152,550.00 0.19 °io I Change from Original Amount } Completion Date, Description of the Task(s) Change, and Rationale for the Change Onginai notice to proceed date: Last approved date. December 4th. 2012 Revised date (includes this change): January 9th, 2012 December 4th, 2012 Number of days added (if To authorize the Installation of a Sanitary Sewer Lateral requested by the Collier Countv extension, must attach current } Wastewater Deoartment. There is no need for a time extension. insurance certificate(s) from SAP or obtain from vendor): 0 Z Add new task(s) i ❑ Change task(s) Deiete task(s) ❑ Other (specify): 1. Provide a detailed and speck explanation of the requested change(s) to the task(s): Install a sanitary sewer 1 lateral to better match existina conditions. as reauested by the Collier County Wastewater Department t 2. Provide detailed rationale forthe requested change: Unforeseen conditions encountered in the County's existing sanitary sewer system. 3. Provide explanation why change was not anticipated in original scope of work: The existing sanitary sewer iaterai was found installed in a wav not acceptable by the County, so it has to be fixed. 4. Describe the impact if this change is not processed: Stormwater improvements on Taylor Road cannot be constructed as oriainaliv desioned. Type of Change ! Modification 1. Planned / Elective X 2. Unforeseen conditionsicircumstance ! 1_7 3. Quantity and price adiustment Lrj 4. Correction of error(s'i Li 5. Vaiue added I ; 6_ Schedule adjustment Change Requested By LJ Contractor/Consultant 0 Owner ❑ Usino Department: Transportation Design Professional ❑ Reaulatory Agency (specify): r, Other (specify). Wastewater Department Purchasing Professionai Partici:,ated in Negotiation of Change / Modification.: Yes No Approved by (Name and Title)-.Julio Ord rip apai Pr ectV3naaer i Date: �Y I --7 Rehr e by (Purchasi Prof s' nay' Rf�o>�5t ,.i figs, co&ractspe6aiist ;Date: �j 1 Revised. Packet Page -1472- CAS CMmq purt�iasmg Z Contract Change Request Contract #: 10 -5498 Mori #: 5 Project #: 38127 Project Manager: Robert 1 Tweedie 3/13/2012 Item 16.E.2. c)7/f -711--� Purchasing Department Change Modification Form ❑ Work Order Modification PO/Work Order #: 45- 127225 Project Name: MKY Taxiway Construct Department: Airport Authority ContractorlFirm Name: DeAngelis i ' Diamond Original Contract /Work Order Amount .$ 5,9:59,O0000 10112/10 "1 R Original BCC Approval Date: Agenda item # Current BCC Approved Amount $5,:95970GE60 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $5, SAP Contract Expiration Date (Master) Dollar Amount of this Change $6,0 5;29 - 1.231% Total Change from Original Amount Revised Contract /Work Order T otal 55, 8a5,9e5.26 -1.23% Change from Current BCC Approved Amount Cumulative Changes ($73.D34.74) 1 0.10% Change from Current Amount ' Completion lute, Description of the Task {s} Change; and Rationale: for the Change Original notice tc proceed Last approved =mpietion date: Revised completion date (includes this I completion date: 2/2/12 3/3/12 change): N /A. Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach currant insurance certificate(s) from SIRE N/A or obtain from vendor): N/A l 17 Add new task(s" I ❑ Change task(s) [( Delete task(s) J>Q Other (specify): provide credit for unused materials and perform additional j 1 work as specified below, 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): a) Furnish and install L854 Radio Control and HD remote control for pilot controlled lighting system compatibility with new constant current regulators. b) Reference schedule schedule of values item # 9 "existing water meter to be relocated ". This task to be deleted and credit to be issued. c) Install bollards and recondition existing fire hydrant per requirement of East Naples Fire District. d) Install approximately 150 linear feet of D type curbing and placement /grading of 57 stone to match new paved grade elevation around FAA AWC5 facility. e) Reference schedule of values item # 52, "installation of cable junction box ". This task is deleted and credit to be issued. (Please refer to attached "Request for Change Crder # 14" dated January 24, 2012 and related back up docmurnentation) 2. Provide detailed rationale for the requested change: a) Existing pilot controlled lighting system radio control unit not compatible with newly installed expanded lighting regulator configuration to provide activation of taxiway lighting system. b) Existing water meter to be relocated per schedule of values item # 9 was not required due to existing field conditions. c) installation of bollards and reconditioning of fire hydrant is a condition of issuance of permit approval by Fire District for relocation of fire hydrant and associated fire hydrant water main replacement per plans and specifications. d) Curbing and placement/ grading of stone is necessary to prevent drainage problems associated with runoff sheet flow of water from pavement within AWLS area. e) installation of new cable junction box per schedule of values item # 52 not required due to existing field conditions. 3. Provide explanation why change was not anticipated in original scope of work: a) Electrical system schematic furnished to provide design guidance for fighting system included radio interface unit required for expanded regulator installation which was not installed with existing system. Therefore unit will not function in existing configuration. Existing radio control unit is dated and radio interface unit to provide compatabiiity is not.availabie. Engineer's recommendation is to replace existing unit with new unit capable of interface with both newly installed lighting regulators. b) Water meter relocation not required per field conditions. ci installation of bollards and recondition of fire hydrant were not anticipated to be a requirement per County permit review, but required by East Naples Fire Control District inspector at inspection. d) Curbinc and placement /grading of stone is at owner's request to minimize water sheet flow off of new apron pavement into Revised: 7127111 1 Packet Page -1473- 3/13/2012 Item 16.E.2. AWLS area and prevent ponding and possible maintenance issues for FAA owned AWOS equipment. , e) Cable junction box installation was not required due to existing field conditions. 4. Describe the impact if this change is not processed. (1) if 1.854 radio control unit is not installed, the pilot controlled lighting system for newly installed taxiway edge lights will not function. (2) Failure to install bollards and recondition relocated fire hydrant will result in non - compliance with East Napies Fire District permit approval of relocated fire hydrant and associated water main, resulting in enforcement action. (3) Lack of curbing and graded stone may result in excessive water collection and oonding within FAA AWDS station area which may result in outages and other maintenance related issues. Type of Change ( Modification El 1. Planned 1 Elective ® 2. unforeseen conditions /circumstance ❑X) 3. Quantitv or price adjustment 4. Correction of error(s) ( 5. Value added ❑ 6. Schedule adjustment Change Requested By ContractorlConsultant I Owner ; ❑ Using Deoartment I ( (J Design Professional ❑ Repuiatgry Agency (specify): ❑ Other (specify): Purchasing Professional Participated in Negotiation of Change / Modification ❑ Yes ❑ No Approved by Date: _ 1I ' f I Name and 7416: Robert Tweedie, Airport Manager n Reviewed by: 1 Date; Procurement Strategists Na Lyn Wood / Revised: 7127.111 2 Packet Page -1474- C-,OTrr,r Comitty 0004��� Adniinistcate Services Division Purchasing ❑ Contract Change Request 3/13/2012 Item 16-E.2. Purchasing Department Change Modification Form Xwork Order Modification Contract #: Mod #: 1 1 PO/Work Order #: I Project Name: Bldg., "K" Switchgear 1 09 -5252 „/ 4500127928 I Modifications Project #: 52525.1 Project Manager: Department: Contractor /Firm Name: Dollar Amount of this Change Robert Fuentes Facilities Management Pelican En g., Consultants, LLC. Original ContractfWork Order Amount $68.274.00 N/A Original BCC Approval Date; Agenda Item # Current BCC Approved Amount „/ -1 1 1 N/A Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount ; $68.274:00 '?> J ,Ci3 SAP Contract Expiration Date (Master) Dollar Amount of this Change '$0:00" 0.00% Total Change from Original Amount Revised Contract/Work Order Total $68.27_4.00 0.00% Change from Current BCC Approved Amount Cumulative Changes $0.00 0.00% Change from Current Amount Compietion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: 6 -13 -2011 2 -13 -2012 change): 11 -13 -2012 I Number of days added (if - Explain why additional days are needed (detailed /specific): e t Lead times on equipment have delay installation, time to research documentation of insuGatt �A original 25 year old equipment was time consuming and difficult. 1 or ,-): �;Ok4 44-ii i ❑ Add new task(s) ❑ Change task(s) ❑ Delete task(s) Other (specify): 1. Provide a detailed and specific explanation of the requested change(s) to the tastes): Due to the long lead time that the manufacturer Cummins on the ATS and other components has increased the time installation and inspections. The remaining equipment will be delivered by May 2012. 2. Provide detailed rationale for the requested change: The original equipment that is 25years old was obsolete and there was no literature thus requiring extensive research on the units. 3. Provide explanation why change was not anticipated in original scope of work: during the initial investigation by the Engineer, the original drawings did not match existing equipment. 4. Describe the impact if this change is not processed: if this change is not process the Engineering firm will not be able to complete the project and finalize as built drawings. Type of Change] Modification I ❑ 1 Planned / Elective 2. Unforeseen conditions /circumstance I ❑ 3. Quantity or price adjustment i 1 4 Correction of error(s) I ❑ 5. Value added 1 2 6. Schedule adjustment I i Change Requested By 1-1 Contractor /Consultant 1 Ea Owner I ❑ Using Department Design Professional ❑ Regulatory Agency (specify): I { I Other (specify): Purchasing Professional Participated'in Negotiation of Change / Modification: ❑ Yes ❑ No Approved by,." 1 Date. Name and .Titd"p:, --- ,Q -!viewed by: Date: _ 3 )curement Strategist's Name: Revised 71271' Packet Page -1475- C�.4tritmy. . Adiliri*911im Services avision Purchasing ❑ Contract Change Request 3/13/2012 Item 16.E.2. , Purchasing Department Change Modification Form E Work Order Modification Original Contract/Work Order Amount $ 11,750.00 ;1 /A Original BCC Approval Date; Agenda Item # Current BCC Approved Amount *WA change): 08/24 /2012 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 11,750.00 Zot SAP Contract Expiration Date (Master) Dollar Amount of this Change $0.00 ` '0.00% Total Change from Original Amount Revised Contract/Work Order Total ( Other (specify): Extend schedule $11,750.00 #MA Change from Current BCC Approved Amount) Cumulative Changes I $0.00 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change I Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: 02126 12012 0212612012 change): 08/24 /2012 Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach current insurance certificate(s) from SIRE ! f sE ( L �,} or obtain from vendor): 180 Add new task(s) 1 LJ Change task(s) ❑ Delete task(s) ( Other (specify): Extend schedule i180 days .. r-rvvluC a uvwncu anu specinc explanation oT Lne requested cnange(s) to the task(s): Extend schedule one hundred eighty (1 S0) days. 2. Provide detailed rationale for the requested change: To provide sufficient time for engineer to submit certifications SFWMD, to receive SFWMD response, and to allow time to respond to any requests for additional information by SFWMD. 3. Provide explanation why change was not anticipated in original scope of work: Initial cost of rain materials was higher than anticipated and staff researched other options, which added time to schedule. Raw materials necessary to build custom baffles approved by SFWMD is delayed in shipping. Difficult to anticipate how long final regulatory agency approval will take. 4. Describe the impact if this change is not processed: Future construction at IMM will not be permitted because certification of outstanding SFWMD applications for IMM will not be completed and SFWMD will not approve any future al)biications Type of Change / Modification ❑ 1. Planned 1 Eiective ! ® 2. Unforeseen conditions /circumstance ❑ 3. Quantity or once adjustment Li 4. Correction of error(s) ! L71 5. Value added i 6. Schedule adjustment Change Requested By Contractor /Consultant ® Owner I F-1 Using Department Design Professional I ❑ Regulatory Agency (specify): ❑ Other (specify): Purchasing Professional Participated th Negotiation of Change / Modification: ❑ Yes ❑ No Approved : I Date: //c! Dame and Title: Thomas Vergo, Project Wriager ^ i I Reviewed by: r 1 Date: Procurement Strategist's N4rrie'., i Revised: 7127111 1 Packet Page -1476- c er C=nt Adn-vilistrP. We el'vire-s D visfll Fiur,:tiasincg ❑ Contract Change Request 3/13/2012 Item 16.E.2. Purchasing Department Change Modification Form ® Work Order Modification Contract #: 09- Mod #: 01 PO/Work Order M ( Project Name: County -Wide I 5262 -Cl 1 4500132461 Engineering Services: Immokalee Current Contract/Work Order Amount $ 37,799:05 Downtown Stormwater Improvements Project #. I Project Manager: Department: ImmoKalee Contractor /Firm Name: CDM Smith 4500132461 i Bradley Muckel CRA l Original Contract/Work Order Amount $ 37,799:05 - 44W4e-,+9C--Origina( BCC Approval Date; Agenda Item # Current BCC Approved Amount $ " ast BCC Approval Date; Agenda item # Current Contract/Work Order Amount $ 37,799:05 3/, .2C i SAP Contract Expiration Date (Master) Dollar Amount of this Change $000; 0.00% Total Change from Original Amount Revised Contract/Work Order Total $37,799.05 0.00% Change from Current BCC Approved Amount Cumulative Changes $0.00 I 0.00 °lo Chance from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: ( Revised completion date (includes this completion date: September 30, September 30, 2012 change): September 30, 2012 20'12 Number of days added (if Explain why additional days are needed (detailed /specific): NIA extension, must attach current insurance certificate(s) from SIRE or obtain from vendor): 0 days [>CJ Add new task(s) (® Change task(s) Delete task(s) J Other (specify;: t. Provide a detailed and specific explanation of the requested change(s) to the task(s): T asks 1 -5 on the existing work order have now been completed at a cost much lower than originally anticipated. There is currently a balance of $'31,979.76 remaining on the work order. This change will reallocate the remaining funds to new tasks as outlined in the attached proposal from CDM Smith to be accomplished at a total cost of $31,979.76. 2. Provide detailed rationale for the requested change: The Engineer of Record for this project, CDM Smith, will be required to provide.certain services during the course of construction to include shop drawing reviews, contractor invoice review /approvals, periodic interpretation requests, as well as other services as identified in the attached proposal. Should the cost of said services exceed $31,979.76, a subsequent modification will be executed fo[iowing County purchasing policy procedures. 3. Provide explanation why change was not anticipated in original scope of work: This project is being undertaken using both CRA and grant funds. CRA funds were used to design the project. Grant funds are being used to construct the project. At the onset of the project, it was assumed that these services would be covered by grant funds. However, recently the granting agency put a cap of $67,950 on the amount of grant funds authorized to be expended on engineering services. Therefore, the tasks outlined on the attached CDM Smith proposal need to be paid for using the remaining $31,979.76 in CRA funds on the existing work order. The allowable $67,950 in engineering grant funds will be totally used up on the CEI (construction engineering inspection) services on the project. 4. Describe the impact if this change is not processed: There would be no Professional Engineer of record involved in any of the tasks listed in the attached work order. This would be a deviation from County policy. Revised: 7!27111 1 Packet Page -1477- 3/13/2012 Item 16.E.2. Type of Change 1 Modification 1. Planned / Elective j Z 2. Unforeseen conditionsicircurnstance ❑ 3.. Quantity or price adjustment 4. Correction of errorfs) ❑ S. Value added I Lj c Schedule adjustment Change Requested By j Contractor /Consultant owner 17 Using Department i Design Professional ; ❑ Regulatory Agencv (specify): ❑ Other (specify) j j Purchasing Professional Participated in Negotiation of Change/ Modification: ❑ Yes Z No j Approved by: Date: Name and Title: BradleV Muckel, CRA Protect Manager Reviewed by: ,. f ,� ! , G Date: _ q —/ Z Procurement Strategist's Name: Lyri Wo Revised: 7/27/11 2 Packet Page -1478- cAeer cownty Adm M*81W Sera = Divig W Putahssing ❑ Contract Change Request 3/13/2012 Item 16.E.2. Purchasing Department Change Modification Form E Work Order Modification Contract #: Mod #: 1 Pomork Order M Project Name: MarGood Harbor Park 08 -5060 1 4500127065 Last BCC Approval Date; Agenda Item # Project #: 80024 Project Manager: Department: Contractor /Firm Name: Dollar Amount of this Change Vicky Ahmad Parks & Recreation McGee & Associates, LC 098 Original Contract/Work Order Amount $ 1,692.42 Last approved c9mpl9fion date: Original BCC Approval Date; Agenda Item # Current BCC Approved Amount N/A 4129rTT 7 2---, ' Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 1,6914Z, %222.f ^ l-;L SAP Contract Expiration Date (Master) Dollar Amount of this Change $1,500:00 88.63% Total Change from Original Amount Revised Contract/Work Order Total Delete task(s) $3,192.42 11 #VALUEI Change from Current BCC Approved Amount Cumulative Changes Additional services $1,500.00 1 88.63°/6" Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved c9mpl9fion date: Revised completion date (includes this completion date: 5!212011 4129rTT 7 2---, change): 5/712012 Number of days added (if Explain why additional days are needed (detailedlspecific): extension, must attach current insurance certificate(s) from SIRE Need additional funds for irrigation and landscape services to project completion and or obtain from vendor): 60 CD close out. new task(s) ❑ Change task(s) Delete task(s) Other (specify}: Additional services 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Provide revised Landscaping & Irrigation plans. The time extension is needed for the irrigation and landscape installation and final closeout services. 2. Provide detailed rationale for the requested change: • Plan revision: Landscape & Irrigation adjustments related to the maintenance building and proposed shelter deletions and plant adjustments for Margood building patio area. • Additional reviews & responses relating to revisions and /or changes: response to retention area depths and sod issue, completed irrigation meter application form, response to patio area changes, comments to i retention areas changes, response to sidewalk changes, response to canoe launch beach area plant removal, response to clarify canoe launch beach tree removal. 3. Provide explanation why change was not anticipated in original scope of work: Some unexpected changes such as plantings to the patio, retention areas, sidewalk review, beach issues, dumpster & tree removal during construction. 4. Describe the impact if this change is not processed: We need the landscape architect to review/ approve landscape, irrigation issues during construction. Type of Change / Modification I. Planned i Elective 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment j ❑ 4. Correction of error(s) ��i 5. Value added 1 E 6. Schedule adjustment Change Requested By Revised: 7127111 1 Packet Page -1479- u Lontractor/consu►tant ■ Owr Design Professional ❑ Rea Purchasing Professional Participated in Approved by: Vicky Ahmad Name and Titie: Projec Manager Reviewed by: Procurement Strategist's Name: 3/13/2012 Item 16.E.2. 7TU-singDerpanment Other (specify): i Modification: ❑ Yes No Date: Date: Revised: 7/27111 2 Packet Page -1480- C16 County Ap r;istabve Services Division Contract Change Request 3/13/2012 Item 16.E.2. Purchasing Department Change Modification Form ® Work Order Modification Contract #: 09- Mod #: 1 Last approved completion PO/Work Order #: Project Name: Master Mobility Plan 1 5262 change): N/A remains June 30, 2012 i Number of days added (if extension, must 4500126165 Phase III Project #: 33062 Project Manager: NIA Department: Transportation Contractor /Firm Name: Wilson Miller I j ®Other (specify }: Debbie Armstrong I Change orginal manhour estimate Planning A. To add additional, enhanced public involvement activities to the project. i B. To amend the original Attachment A- Manhour and Cost Summary to reflect a Planner as the sole provider of all I the services described in the scope of work, and removing services by a Project Manager. A Planner is paid at a rate of $110 per hour, per Contract 09 -5262, and a Project Manager is paid at a rate of $148 per hour, per Original Contract/Work Order Amount $ 58,130.00 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount p1j Current Contract/Work Order Amount $ ... 68,130.00, 2-o (3 Last BCC Approval Date; Agenda Item # SAP Contract Expiration Date (Master) Dollar Amount of this Change $5,_190.00 7.62% Total Change from Original Amount Revised ContractANork Order Total $73.320.00 7.62% Change from Current BCC Approved Amount Cumulative Chanoes $5,190.00 7.62% Change from Current Amount Completion Date, Description of the Tasks ) .Change. and Rationale for the Change Original notice to proceed completion Last approved completion Revised completion date (includes this date: June 30, 2012 1 date: June 30, 2012 change): N/A remains June 30, 2012 i Number of days added (if extension, must Explain why additional days are needed (detailed /specific): attach current insurance certificate(s) from SIRE or obtain from vendor): N/A NIA j ❑ Add new task(s) Z Change tasks} 7 Delete task(s) j ®Other (specify }: I Change orginal manhour estimate 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): A. To add additional, enhanced public involvement activities to the project. i B. To amend the original Attachment A- Manhour and Cost Summary to reflect a Planner as the sole provider of all I the services described in the scope of work, and removing services by a Project Manager. A Planner is paid at a rate of $110 per hour, per Contract 09 -5262, and a Project Manager is paid at a rate of $148 per hour, per Contract 09 -5262. i I 7 6r�a»iein 'iaiailart rsfi�nsia fnr fi•n rannc4arr r•kn�nno• A. The importance of an enhanced public involvement process was stressed by the County Commission at the beginning Phase 11 of the Master Mobility Plan, and the resulting "enhanced" effort was well received. In keeping with the Board's guidance, Staff wants to enhance /increase the public involvement opportunities in Phase 111. S. A Planner is now able to provide all the services described in the scope and therefore there is no need to pay a higher hourly rate for a Project Manager. 3. Provide explanation why change was not anticipated in original scope of work: A. The basic, minimum level of effort in the original scope of work did not contemplate the Commission's desire for an enhanced program, nor did it contemplate the public's desire to participate in all stages of plan development. Additional grant funds remaining at the end of Phase 11 work permits the enhancement of the public involvement effort for this third phase. B. The original work order was entered into in March o'1201, 1, with full knowledge that would not begin until Phase 11 was completed in early 2012 (grant funds needed to be obligated at that time); since we completed Phase 11, the consultant re- evaluated" the scope of services to be provided in Phase I11 and determined that a Project Manager was no longer needed. 4. Describe the impact if this change is not processed: A. The basic level of public involvement, included in the original scope, will still be accomplished; Staff believes that the additional effort should be provided in keeping with the Commission's earlier Phase 11 guidance. B. We would pav a higher rate per hour to pay for Packet Page -1481- ement services that are no ion Revised: 7,'77/11 3/13/2012 Item 16.E.2. Type of Change:! Modification I _; 1. Planned 1 Elective 2. Unforeseen conditionslcircumstance ❑ 3. Quantity or price adiustment j ❑ 4. Correction of error(s) 5 Vaiue added I L J 6 Schedui= adiustment Change Requested By _❑ Contractor/Consultant ! 7, Owner Using Department U Design Professional ❑ Regulatory Agency (specify): ❑ Other (soe�ify) Purchasing Professional Participated in Negotiation or Change / Modification: ® Yes lJ No Approved by Y I Date: f Name and Tale: ! Reviewed by: Date: Procurement Strategist's Name: %!1It— h 4, it JIPAA . � Revised: 7/27/11 z Packet Page -1482- N F, � A .J.0 ,Vv 3/13/2012 Item 16.E.2. Purchasing Department AdminiAnafi e Serum [IMsion Change Modification Form Purchasing ❑ Contract Change Request E Work Order Modification Contract #: 09- Mod #: 1 PO/Work Order #: Project !'dame: Developer Responsibility 5262 4500130645 Evaluations Project M 60109 Project Manager: Laurie Department: Transportation Contractor /Firm dame: CH2MHiIl Beard Planning I Original Contract/Work Order Amount :88;08100 n/a Original BCC Approval Date; Agenda Item # Current BCC Approved Amount nta. - . - -. ?n /a Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount ;88;080;00 3/8/2013 SAP Contract Expiration Date (Master) Dollar Amount of this Change $0:i00 0.00% Total Change from Original Amount Revised Contract/Work Order Total $88,080.00 Provide detailed rationale for the requested change: Without extending the completion date I will no longer be #VALUE! Change from Current BCC Approved Amount Cumulative Chanaes $0.00 4. Describe the impact if this change is not processed: i will be unable to do my job and the County will not be able 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: March 8, 2012 March 8, 2012 change): March 8, 2013 Number of days added (if ! Explain why additional days are needed (detailed /specmc): Transportation Planning extension, must attach current has an ongoing use for evaluations on proposed developments, developer contribution insurance certificate(s) from SIRE agreements and fair share payments. The work order should stay open through the or obtain from vendor): 365 contract date. j ❑ Add new task(s) ❑ Change task(s) ! L Delete task(s) Other (specify): j Chan e of completion date only 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): N/A Provide detailed rationale for the requested change: Without extending the completion date I will no longer be able to have this contractor do the evaluations necessary to determine the amount of and collect fair share payments from entities that are responsible for payments to the County. i j3. Provide explanation why change was not anticipated in original scope of work: The contracts are annually j reviewed and when needed extended an additional year. Work is ongoing. j 4. Describe the impact if this change is not processed: i will be unable to do my job and the County will not be able to bill the entities for fair share payments of work performed by the County on their behalf. I Type of Change / Modification 1. Pianned / Elective 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adiustment 4 Correction of error(s) I 5 Value added I 6. Schedule adjustment Change Requested By i l Contractor /Consultant I ® Owner (Transportation Planning) I El Using Departme ❑ Design Professional I ❑ Regulatory Agency (specify): ❑ Other (specify): Purchasing Professional Participated in Negotiation of Change / Modification:. Yes ❑ No Approved by: r %/1 �1 Date: 02/10/12 Name and Title Laurie Beard--07anp Ration Planner L_ �` •� Dace: reviewed by:. � �o-�, .t�� f , ° ocurement Strategist's Name: Rhonda Cummings Revised: 7/2"11 Packet Page -1483- rtr r t SerJtces 17,visicr , 3/13/2012 Item 16.E.2. Purchasing Department Change Modification Form _ _LJ Contract Change Request ® Work Order Modification Contract #09- 5262 -CI Mod #: 1 PO/Work Order #: Project Name: Fire Line Metering — Blue 1 4500125604 _ Skies j Project #: 70036 Project Manager: Department: PUPPMD 1 Contractor /Firm Name: RWA, Inc. Alicia Abbott I Original Contract/Work Order Amount $ 26,780.00 N/A Original BCC Approval Date; Agenda Item # Current BCC Approved Amount ❑ 5. Value added ® N/A Last BCC Approval Date; Agenda item # Current Contract/Work Order Amount $ 26,780.00 - g l ( 3 Dollar Amount of this Change $0.00 0`.00% Total Change from Original Amount Revised Contract/Work Order Total $26,780.00 #DIV /0! Change from Current BCC Approved Amount Cumulative Changes $0.00 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed 1 Last approved completion date: Revised completion date (includes this completion date :December 6, 2011 1 December 6, 2011 ;change); October 1, 2012 Number of days added (if I Explain why additional days are needed (detailed /specific): extension, must attach current This work order is under Contract 09 -5262, which is in place and will not expire until insurance certificates) from SIRE I March 7, 2014. Additional days are required for the consultant to provide services or obtain from vendor): 300 I during final design, bidding and construction of the project. By ratifying this change, the Board is allowing the balance of the work to continue. ❑ Add new task(s) ❑ Change task(s) ❑ Delete task(s) i . ; Other fY): s eci ( p� . Schedule Change ;. Provide a detailed and specific explanation of the requested change(s) to the task(s): The requested change is to add additional time to the work order. Delays during the design phase were due to obtaining adequate information on the existing fire system, and obtaining a right of entry from the Homeowner's Association to construct on their property. 2. Provide detailed rationale for the requested change: The additional time requested will allow for the consultant to proceed with the remaining services required to complete the project. 3. Provide explanation why change was not anticipated in original scope of work: This delay was not anticipated due to difficulty obtaining data (such as existing record drawings), necessary to complete the design, and a delay in otaining homeowner association approval. It was initially thought that all the work could be done in the right of way. 4. Describe the impact if this change is not processed: If this change order is not processe ill This project is to maintain compliance with the Collier County Cross Connection Control Ordinance that requires all community water systems to establish a routine cross connection program to detect and control cross - connections, and prevent backflow of contaminants into the water system. L i~ r, e uj w^! -k 0 - — e (�x cc u ca f o sx v C c-tec' -c€ -,14 c «x. 00 e ' e-- cx fu € r. `6, r,�__. j Type of Change / Modification ❑ 1 Planned / Elective j ❑ 2. Unforeseen conditions /circumstance 1 ❑ 3. Quantity or price adjustment ❑ 4. Correction of error(s) ❑ 5. Value added ® 6. Schedule adjustment Change Requested By Contractor/Consultant ❑ Owner i ❑Using Department ❑ Design Professional i ❑ Regulatory Agency (specify)_ 1 ❑ Other (specify): Purchasing Professional Participated in Neacifiation of Change / Modification: ❑Yes 11 No i r7proveo oy � /JAI .h 1 Date: L­'� Name and Title: Reviewed by: !Date: Purchasing Professional's Name: Revised: 7!27111 1 Packet Page -1484- er Ckywity Adrrrinisirame Services Duision Purchasing ❑ Contract Change Request 3/13/2012 Item 16.E.2. Purchasing Department Change Modification Form ® Work Order Modification Contract #09- 5262 -CI Mod #: 1 POIWork Order #: Project Name: t=ire Line Metering - Victoria 1 Current Contract/Work Order Amount $ 44,140:00 4500125574 Shores Project #: 70036 Project Manager. Department: PUPPMD ContractorlFirm Name: RWA Inc. extension, must attach current Alicia Abbott insurance certificate(s) from SIRE March 7, 2012. Additional days are required for the consultant to provide services Original Contract/Work Order Amount $ , 44.140:00 Current BCC Approved Amount Revised compietion date (includes this Current Contract/Work Order Amount $ 44,140:00 Dollar Amount of this Change $0.00 Revised Contract/Work Order Total $44,140.00 N/A Original BCC Approval Date; Agenda Item # NIA Last BCC Approval Date; Agenda Item # 0.00% Total Change from Original Amount DIV /01 Change from Current BCC Approved Amount 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: Revised compietion date (includes this completion date: December 6, December 6, 2011 change): October 1, 2012 2011 Number of days added (if Explain why additional days are needed (detailed /specific): extension, must attach current This work order is under Contract 09 -5262, which is in place and will not expire until insurance certificate(s) from SIRE March 7, 2012. Additional days are required for the consultant to provide services or obtain from vendor): 300 during final design, bidding and construction of the project. By ratifying this change, the Board is allowing the balance of work to be completed. ❑ Add new task(s) ❑ Change task(s) ❑ Delete task(s) ® Other (specify): Schedule Chan e 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): The requested change is to add additional time to the work order. Delays during the design phase weredue to obtaining adequate information on the existing fire system, and obtaining a right of entry from the Homeowner's Association to construct on their property. 2. Provide detailed rationale for the requested change: The additional time requested will allow for services required to complete the project. 3. Provide explanation why change was not anticipated in original scope of work: This delay was not anticipated because there was difficulty obtaining data on the existing fire system, which was necessary to complete the design, and a delay in otaining approval from the homeowner associations. I 4. Describe the impact if this change is not processed: If this change order is not processed tlk-autezawillhe c - This project is to V maintain compliance with the Collier County Cross Connection Control Ordinance that requires all community water systems to establish a routine cross connection program to detect and control cross - connections, and prevent backflow of contaminants into the waters stem. �. c .- ' ettl _ s l i �- f - t?'S O r f+c. d.. Wi , L. r- . - a 11 - Type of Change ! Modification 6L'-d t i- ❑ 1. Planned/ Elective ❑ 2. Unforeseen conditions /circumstance I ❑ 3. Quantity or price adjustment LJ 4 Correction of error(s) 5. Value added [ 6. Schedule adiustment Change Requested By � Contractor /Consultant ❑owner ❑ Using Department ❑ Design Professional ❑ Regulatory A enc (s eci ❑ Other (specify): Purchasing Professional Participated in Negotiation of Change / Modific ' , : ❑ Yes ❑1 No Date: Name and Title: ' Reviewed by: .� Date: % r f Professional's Name: 9 Packet Page -1485- Revised: 7127111 1