Agenda 01/10/2012 Item #16E61/10/2012 Item 16.E.6. EXECUTIVE SUMMARY Recommendation to accept reports and ratify staff - approved change orders and changes to work orders. OBJECTIVE: To enable the Board to oversee the execution of administrative change orders and changes to work orders and promote accountability in the use of staff authority. CONSIDERATIONS: On April 22, 2003, the Board approved a recommendation to implement a plan to enable changes to BCC - approved contracts (Section XV.C, Collier County Purchasing Policy) of not greater than 10 percent of the current Board approved amount or $10,000 (whichever is greater) to be authorized by staff. Also included in the report are changes to Work Orders. These include work orders issued under CCNA Contracts that are less than or equal to $200,000 (Section VII.C, Collier County Purchasing Policy), and changes to work orders for all other contracts (Section XV.G, Collier County Purchasing Policy) that are not greater than 10 percent of the current Board Approved amount or $100,000 (whichever is greater). The Administrative report identifies the percentage changes to contracts or work orders that have occurred since the prior BCC approved amount which are below the threshold limits as referenced above. The plan calls for staff to submit a monthly report listing these change orders from the previous reporting period. Enclosed is the monthly report of the Administrative Change Orders and Administrative Changes to Work Orders. These reports cover the period of November 28, 2011 through December 20, 2011. FISCAL IMPACT: The total for 7 changes to contracts is a deduction of $1.201.851.05. The total for 2 changes to work orders is $54.513.50. LEGAL CONSIDERATIONS: This item raises no legal issues and requires majority vote for approval. -JAK GROWTH MANAGEMENT IMPACT: There is no Growth Management Impact associated with this action. RECOMMENDATION: That the Board of County Commissioners accepts the enclosed Administrative Change Orders Report and Administrative Changes to Work Orders Report and ratifies the listed change orders and changes to work orders. PREPARED BY: Diana De Leon, CPPB, Contracts Technician, Purchasing Department Packet Page -1430- 1/10/2012 Item 16.E.6. COLLIER COUNTY Board of County Commissioners Item Number: 16.E.6. Item Summary: Recommendation to accept reports and ratify staff - approved change orders and changes to work orders. Meeting Date: 1/10/2012 Prepared By Name: DeLeonDiana Title: VALUE MISSING 12/28/2011 8:42:46 AM Submitted by Title: VALUE MISSING Name: DeLeonDiana 12/28/2011 8:42:47 AM Approved By Name: SmithKristen Title: Administrative Secretary,Risk Management Date: 12/28/20118:52:48 AM Name: WardKelsey Title: Manager - Contracts Administration,Purchasing & Ge Date: 12/28/2011 11:36:29 AM Name: CarnellSteve Title: Director - Purchasing/General Services,Purchasing Date: 12/28/20113:11:10 PM Name: PriceLen Title: Administrator - Administrative Services, Date: 12/29/20117:14:15 AM Name: KlatzkowJeff Packet Page -1431- Title: County Attorney, Date: 12/29/2011 8:43:25 AM Name: FinnEd Date: 1/3/2012 12:38:55 PM 1/10/2012 Item 16.E.6. Name: IsacksonMark Title: Director -Corp Financial and Mgmt Svs,CMO Date: 1/3/2012 2:26:30 PM Packet Page -1432- _N w O CD N ^ a) C > Tr L U CQ.O e OQ U w CM c r .10c d oO M w v u0i o X U a w m c O1 m o .0 O E U a w L m > C O G C a E H U U N � U O m a w w d' w � ` p 0 w o Q (P V U N w a) a _ C U O O (n rnU E Z 0 m C. a o a N Q c � d 'EC v m 'o o a` O a O C 2 z m c Z 2 j O U O t) CM p a7 C 0 >a U OL) W N � N ` LL 7 3 0 p a. a w W U w a) z Packet Page -1433- 0 N V 00 0 N v, m Co a T N N O O Di N fA 7 rn ui a Co v, m Cb M 7 to ao a Lo r D) 7 61) N °BEN ns C i E 0 M (. o m m a) CD U [n U U d) w w a c o � � E a) E O t_ U) T co ti ov)a� ° w18-7 O Z U U m m v c m o a) a N a7 a) ,N Y E- N t U CM o C U L 3 U y O c U d � O .n 1/10/2012 Item 16.E.6. e O C O y p 7 C C N �Up C U � c � o � w O �y C O a) N a ° C E ° 2 E ° O O M O N U CV y a7 Cli a w U a) r d) a) C_ N � N dv ° a3i o O a) CL a o O a) O O O C U O a7 U O a C A C pp O = U N N a) w a `» o m w O 3 L > O ° O C C N v C a m fg a C a 0 m a) c ao :3o E o C) U rN N C) C D) N CI) y C C a7 O C C C C m 01 y M N d E C O y (d D O () N a) ayi E m U CL o U c U � a r O O H ID C Y a O O Y � 3 C ° c p 05 3 U N O N p in u 7 U O Q t .2 C C m m c O a) S a) o O M Q .2) •� a) E m o `o v� f6 ❑ m m E ❑ a)a =a o N (D Q p p U tM `- 7O— C a 7 Q L? p y o c E o a) p ❑ aD O �a rn c m �3 ;__ J U M O o> d Oy O a N O 3 0 o 0 O C; ti L6 y Z ° O c C CDN C6 C C E o a o ° o Co o m O o ° C Cl) w o O O) 76 C O 2 a a M c m o0 N N w C a) a M rn O E Co C m° 4i fA a) O a) a r Ci O o o ClM c O o O Ea v U O M Y N m N a y = O O y O O O CD U tp C C N M p h M M a DI m C N Co 0 M `O m E f» (M C `» o a C p Cl N M J M n v Di a) m 3 tG M Co a) _ L _0 J CO co MM O E O M fD fH a) N 69 U 3 - m o as O a m o r O W N 3 N O Co y D~) a) M <L N E N CD y C) a a MUi O 0 tp w H C 7 V > N a) Co 0 O �> m m J C L y a a O N Co m 7 N Y N w a CL L) O N y 'T C O N C ) Co M d C 3 O U Y —m a) a) U y a) E L C I a) a p y 2 a) Co In L N @ 2 p @ 7 O y U a Z Co L m t p O E C 'E O Y a m a1 a fa Mn U m @ o > w c U C c N c C v oo o M Ea a) W O p y R m U m 8 M¢ ikt O V EaJ ik N va N N #d N mat CJC' Da Ta Ca r C,U? m°��a U m o LO'D U z��M r° )°- CD Qz�0FL- fa rn a) rn _ Cb CM _ C .- C N V p Z C) O O U p O U d N C > O M O O Packet Page -1433- 0 N V 00 0 N v, m Co a T N N O O Di N fA 7 rn ui a Co v, m Cb M 7 to ao a Lo r D) 7 61) N °BEN ns C i E 0 M (. o m m a) CD U [n U U d) w w a c o � � E a) E O t_ U) T co ti ov)a� ° w18-7 O Z U U m m v c m o a) a N a7 a) ,N Y E- N t U CM o C U L 3 U y O c U d � O .n 1/10/2012 Item 16.E.6. e O C O y p 7 C C N �Up C U � c � o � w O �y C O a) N a ° C E ° 2 E ° O O M O N U CV y a7 Cli a w U a) r d) a) C_ N � N dv ° a3i o O a) CL a o O a) O O O C U O a7 U O a C A C pp O = U N N a) w a `» o m w O 3 L > O ° O C C N v C a m fg a C a 0 m a) c ao :3o E o C) U rN N C) C D) N CI) y C C a7 O C C C C m 01 y M N d E C O y (d D O () N a) ayi E m U CL o U c U � a r O O H ID C Y a O O Y � 3 C ° c p 05 3 U N O N p in u 7 U O Q t .2 C C m m c O a) S a) o O M Q .2) •� a) E m o `o v� f6 ❑ m m E ❑ a)a =a o N (D Q p p U tM `- 7O— C a 7 Q L? p y o c E o a) p ❑ aD O �a rn c m �3 ;__ J U M O o> d Oy O a N O 3 0 � / CV cli LO CV It Ic g ) j CD -J \ }p -6 tM 0\ // E a Co co 0 CL \ C /\ Ik - \ \ |_® )0 kE Pa ) \ § / ck lPag -1434- 1/10/2012 Item 16.E.6. N _ L: rM 2 J E k / �t o fE \ r / ) / L) / z\ \ Lo ®£ ( a) —I ? f }) / 3 E ) G �� c IZ ( E ) Co 2 L �§ a .2 co 2k2 & ■ ° §k {� �L) e — § m _ § , \ § —2« w kE ° � 401, ) L) CCL \ � ) w a F- I. .. ) 2 E M CL § ® w2 wl, \ < <2? < « >42,\ — :i k ] - � & E M. ° ; CL2 �� } � / CV cli LO CV It Ic g ) j CD -J \ }p -6 tM 0\ // E a Co co 0 CL \ C /\ Ik - \ \ |_® )0 kE Pa ) \ § / ck lPag -1434- 1/10/2012 Item 16.E.6. N ) / / E / z\ \ ° §0} a) ? f }) / 2 ) &�§ &- ] /k /\ 4) >auui <— $z0.2 Co 2 a .2 9« & ■ U- k § {� i e — , \ Eo § ■z ° > � / CV cli LO CV It Ic g ) j CD -J \ }p -6 tM 0\ // E a Co co 0 CL \ C /\ Ik - \ \ |_® )0 kE Pa ) \ § / ck lPag -1434- 1/10/2012 Item 16.E.6. N 0), t N W C 3 C O O w U Y o L U ° 3 M > c d — d C 0O o c �O cm ° M 0 Y Ucc U U m t � 3 o 0 Y E ° w 9 Q O = Y E A Q V � w c d 0 O Y E � Q U3ty O CL W IY W O Y O 2 S U W H M Z_ 0 Q N } LL f I G w W U W 9 C CD U c O U E U m a a Q V O C m � 7 = 0 O E o � w C d A CL 'o o a` m io O O x w_ O u Z O = d Z O � O U Y C M R: L) 2 O Z E°o E Z 2 o 2 `O ; M 0 9 N C d d O L O > a` L) a` ie y d 3 .d. C o a` m O = Z LO N M O 0 E d •� m �U m N O. L U N C � L O N U .E C Y m O N � N m � U Q a do m m o CL m �U O) dO C � O C N v m � m � m o O c C. 0 m N N rcoi c E ai o c C w C y N ya aa) w C c p 0 O Q Q E Z ;o t0, m c d 0 0 y M .� a ° 5 E O U O W ro N O N M N Cl) U U a M O C `o to O O Y ay 0 w O 3 _ N O � U c O O O N N y N LL � N N ° d o L O O � c c v` O 0 Cc f6 E L O N N _ �0 v c � N E v ro O S N f06 O m °n u4 M c °1 ° I v o C 4 o v c 5 y m _o o m U U ° N ) Y c o m M Co U) 3 @ N 0 W m.ca !n O U 0 N N 2 E m m 0 ik m o > U 0 Y O �QoEn Z g E E 0 c N O Y S U 0 y = U N O L V N 3 y n > p 0) F- O > .; 11 c m 0 'm O m o e O O O O v N O j O 0' ti N o w n `o °a r O y O CD w c m m v o ° o v 10 0 w C N m c Ul Ch 2 O m O1 N m CD O n_ C O O LO a fA C N d N O T N C O O m Y E�Cp 3 U O d Y c U O r U N 0 U O O N p- 72 LO o O N M C N_ O O W) 2 !?R Ott O M O `o m m E ° N 0] > m L � tM w o o O m 'E > _ma y CO Xk N d w v i m m � z 0 F°o IM C m L � U O iz� CL Z m 0 N Pad to LOe+i c w 0 O E Q N d 0 Y O .0.� d Of e6 L U m ;et Page -1435- 1/10/2012 Item 16.E.6. AdminigmM Services i7tvision aim ® Contract Change Request 1/10/2012 Item 16.E.6. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #: 11- Mod #: 1 PO1Work Order #: Project Name: Bayshore Drive South 5651 $ 943,599.42 4500129882 Corridor Improvements Project #: Project Manager: David Department: Bayshore CRA I Contractor /Firm Name: Quality Procurement Strategist's Na Lyn M Wood Buchheit Enterprises, Inc. IOriginal Contract/Work Order Amount $ 943,599.42 'Current BCC Approved Amount Last BCC Approval Date; Agenda item # Current Contract/Work Order Amount $ 943,599.42 Dollar Amount of this Change $0.00 Revised Contract(Work Order Total $943,599.42 Cumulative Changes $0.00 11;16.6:3. Original BCC Approval Date; Agenda Item # Last approved completion date: Last BCC Approval Date; Agenda item # 12/5/2011 SAP Contract Expiration Date (Master) 0.000 Total Change from Original Amount 0 Change from Current BCC Approved Amount 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this i completion date: 12/0512011 12/5/11 change): 02/05/2042 Number of days added (if ,i' Explain why additional days are needed (detailed /specific): FPL did not maintain its extension, must attach current expected schedule, which halted production for six weeks, insurance certificate(s).fro�n �iRE Procurement Strategist's Na Lyn M Wood or obtain from vendor): tt�G j ❑Add new task(s) I ❑ Change task(s) ❑ Delete task(s) i FA Other s eci (P fy): I 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Add time. Provide detailed rationale for the requested change: FPL did not maintain its expected schedule and delayed the project by six weeks. 3. Provide explanation why change was not anticipated in original scope of work: FPL work is outside the control of the contractor. 4. Describe the impact if this change is not processed: Project will not be completed Type of Change i Modification ❑ 1. Planned / Elective 0.2. Unforeseen conditions /circumstance 3. Quantitv or price adjustment I ❑ 4. Correction of error(s) ❑ a. Value added ❑ 6. Schedule adjustment Approved by: i ✓ .-�' '" ., �. date: w Name and Title: David Buchheit, Project Manager Reviewed by:� �� ( Date: Procurement Strategist's Na Lyn M Wood Revised: 7127111 1 Packet Page -1436- 51704 4, 50066 t Proie- Mariager: 1 Lukasz 1/10/2012 Item 16.E.6. Pur;:Thasing Depar-Lment lihiork Omer Modification :10/Work Order� - 1 PrOjec4l Niana e: P--fican rlavZomrnunity 450013.00,115 1 1 Crosswalks Department: Pelican Bay ar, Services DKtision 1-ontraminc! LLP !Drigin all i COM-act/Vti-ork Drder,�rnount s 36232&.050 (r, _rM/ it CLlrrent 6CC A-npry ed Arnourrt :.62,32B 00 C-;Dntrac;-L;,Worj-, 'Drder Amount —36892q-. 4-8 Dolfal- Amount of Change �43309. �CC 4:15'ti4-,sed 1--ontract/yVork C)rde, -,, z3taj i 4 8 ,inginai 3CC Apprcv-al Cates AgzavleF•# "ast BCC Appro\oi Date:- Agenda Ite-M # SAP COnt-iact E-Piration D-ate Totai Chanae tiorn Original mount :Change frorn Current BCC ,.o , Pro'veo Amount Change itorn Current Amount -OmP-'efor: Date, Descr'PbOn Of the T ?,shqfs1 C-hange, and Rationale for the Char-me Original notice C) Dxoceacf _ast ar)Drovet� COMDietion .ante: ised connoietion date r1OMOie- Or. �aje�' -j!Z1 4 "'� I I . I-V �a j, 4/1 (inc a nae': Numbe; Cr -"av-',Z add e,' .'ff Exz)i2irl -wh". additionai davl� I are Illeedet (detaii- Lpe, ad -7101: ex:enr4iDn� M-S-1 attacn 'jurrant an , �ficate(s) -,'Orr SIRE . Ot tair f M rn ire ndah: 0 L aS is' , aermfied ant SolmC' -1C expianation Of the 7'eqUesterd zhanae(st to thre taSjqs,,,,: 4,. RernOvai and of 9,4 !-F, of -Urbirq- Ra-lnovaf and inst2llaflor, of 2,00 SCI. YCL Of asohalt arld base. C. ACjjLjSt L - iayOU41 'Vater valves. D" Palmed survey effected Provide detailed ;-atjor-,aie for the requested -�hajaa- The addhionai lurbi.10 and, roadbase is ne--essary to Conect m'n a e , PrOblerl"s cr-eating, watel- ponding at tWO CrOsswall-, iocations, 'de q: & -,-�;ianation Wnif zhar nge was not anfi ciDaL=-d j.- scope J3 c1^ rk: Preliminary survey imorm atio, Iter"fliry tile elevatior pri3biems at the aurh and, road Chaves impacting"the-drainage bUt.2Ce7,visua; inspecjon identified t, le gf ^d,ie?l 'L3 tiler survev jja during Ou- und deteiiatjor� OiF, b and asphalt thaj wouid Crea pr-,:�j e cL � a v , - -he • b,- & i m p, ac t i Desc, 9 = th te ponding for et�er7bve drainage of ttie area in t In this �hanga is notmrocessed': N � Ile raDai.'S are -IM Made i e exisiting grabes will not allow ne Ieljv Crosswalk - 2flng,� StFjj,1_Jinc water aft'ver cer.,ain rain ev-ent*s. a ype Of � n rlae Unforeseen a If 1r —y or Brice adjustment •, Vaiue added z4;F;eGu'e acwstment Reauested Ev j fxg '/� ' DePai-zmenl kgermy "specify": Dthe� Fic E' "tiCT--eC-' iri •Nec-OtMtio-, & Change �' Modifi j I or es Date: Name —fV,'a—naQe,, ... em eni ra- L Legis��s Namne:Ninoie Parker st revise- : T! , I Packet Page -1437- CO*'7e-r CbUXty ndrwnlstraiive Senticas lion r?urchasq x Contract Change Request 1/10/2012 Item 16.E.6. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #: 11- Mod #: 1 � Ao-,.hd a ( POANork Order #: N/A Project Name: Third Party Administrator 5729 Current Contract/Work Order Amount' 12/31114 for Health Plan Project #: N/A Project Manager: Jeff Department: Risk Contractor /Firm Name: Allegiance Total Change from Original Amount Walker Management Benefit Plan Management, Inc. Original Coniract/Work Order Amount ' 3;5 i Original BCC Approval Date; Agenda item # Current BCC Approved Amount Original notice to proceed eed Last approved completion date. Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount' 12/31114 change): N/A Number of days added (if Dollar Amount of this e Chan 9 , > '��<�. a 0.00 /o Total Change from Original Amount Revised Contract/Work Order Total $690,976.00 0.00% Change from Current BCC Approved Amount Cumulative Changes $0.00 0.00% Change from Current Amount Cople#tlate��esorritron ,ofixtMe Ts} rvhaln 9 � � �n+dx�a'tto�r�ale for tt�� Change. Original notice to proceed eed Last approved completion date. Revised completion date (includes this completion date: 12131/14 12/31114 change): N/A Number of days added (if Explain why additional days are needed (detailed /specific): N/A extension, must attach current insurance certificate(s) from SIRE or obtain from vendor): NIA ❑ Add new task(s) ❑Change task(s) ❑ Delete task(s) x Other (specify): Clarify contract language 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): There is no change to tasks. This is a clarification of Run Out fees and PPO process fees. 2. Provide detailed rationale for the requested change: To clarify contract language for future use. 3. Provide explanation why change was not anticipated in original scope of work: This amendment does not change the original scope of work, but clarifies payment for the work. 4. 5. Describe the impact if this change is not processed: The Run Out fees would have to be clarified when the contract finally terminates and the County would pay $113,834 more in PPO process fees. Type ; -af Char ge t Nlo , J ica jon x 1. Planned / Elective ❑ 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment ❑ 4. Correction of error(s) ❑ 5. Value added I ❑ o" Schedule adjustment Change, Req.uested¢By ❑ Contractor /Consultant ❑ Owner x Usin De artment Design Professional I ❑ Regulatory Agency s eci ): I ther h; eci Purchasing Professional Participated in Negotiation of Change / Modification: x Yes ( I No i Approved b : Date: Name and T e: Jeff Walker, Risk Management Director Reviewed by: t Date: ll Purchasing Professional's Name: Lyn , ood Revised: 7127/11 1 Packet Page -1438- V1 1/10/2012 Item 16.E.6. EXf nIT A -1 Contract Amendment #1 "11 -5729 - Third Party Administrator for Health Plan" This amendment, dated -e yhx -Z2 2011 to the referenced agreement shall be by and between the parties to ifie original Agreement, Allegiance Benefit Plan Management, Inc. (to be referred to as "TPA ") and Collier County, Florida, (to be referred to as "Plan Sponsor "). Statement of Understanding RE: Contract # 11 -5729 - "'Third. Party Administrator for Health Plan" In order to continue the services provided for in the original Contract document referenced above, the TPA agrees to amend the above referenced Contract as follows. Appendix A, Fee Schedule, Section B shall be amended as follows: B. Run out fees. Run Out services shall be based upon a separate run out agreement executed at the time Run Out is requested. However, the fees therefore shall be calculated as follows: There shall be a single fee payable in advance, equal to three (3) times the administration fee paid for the month immediately preceding the date Run Out Services are requested to process claims for a twelve 12) month period beLbmine 7anuary 1. 2012 and ending December 3 L 2011, Appendix A, Fee Schedule, Section L shall be amended as follows: L. PPO access fees for any PPO organization or claim negotiation company that assesses a per Plan Participant fee, a per Claim fee, or a percentage of claims savings fees not to exceed twenty-five (25 %) percent of the actual savings amount between the charges billed by the Health Care Provider and the discounted amount agreed to between the PPO or Claims Negotiation Company and the Health Care Provider, except for those entities specifically listed below, for which no service fee applies. The amount charged under this Agreement shall be equal to the amount charged by the PPO or Claims Negotiation Company, The TPA, its parents or its affiliates, may be paid a service fee by the PPO for claim repricing or other administrative services associated with the claims discount or negotiation. The Plan Sponsor will receive a report that outlines the total billed charges, the total discounts obtained, the net claims cost and the total claim savings to the Plan. Any additional fee in excess of this amount must be approved in advance by the Plan Sponsor. The TPA may be paid a fee not to exceed twenty -five (25 %) percent of net savings payable to TPA, its parent or its affiliates, realized as a result of any negotiation or reduction in the amount of claims paid or any recovered funds obtained by TPA through employment of cost containment companies. Specific fees at the inception of this contract for which a per Participant per month rate is charged are: -0- per Plan Participant per month for Community Health Partners Pl4O The network access fee for the Ciana PPO network is $5.50 PPPM 11 -5 729 — Third Party Administrator for Health Plan Amendment #1 Packet Page -1439- 1/10/2012 Item 16.E.6. All other terms and conditions of the agreement shall remain in force. IN WITNESS MMEREOF, the TPA and the Plan Sponsor have each, respectively, by an authorized person or agent, hereunder set their hands and seals on the date(s) indicated below. Accepted: &&/744-Gc t ( ?q1 I CONTRACTOR: OWNER: Allegiance Benefit Plan Management, Inc. BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA BSr: DEPARTMENT DIRECTOR Ronald K. Dewsnup, President and General Manager Bv. r Jeff DIVISION ADMINISTRATOR Lcn Price CONTRACT S.PECLALIST L} 4 M ood PURCHASING/GENERAL SERVICES DIRECTOR By: �A ' 4, Stephen Y, Carnell 11 -5729 - Third Party Administrator for Health Plan Amendment #1 Packet Page -1440- C0173�r GOHtY A.Ltrinlvvxive Services m-4m El Contract Change Request 1/10/2012 Item 16.E.6. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #: Mod#: PO/Work Order #: Project Name: 11-5747 1 4500132527 NCRWTP Main Electrical Switchgear Replacement Project Project Manager: Department: I Contractor/Firm Name: 70069.6 I Jason Tomassetti, P.E. I PUPPMD E . Simmonds Electrical, Inc. Original Contract/Work OrderAmount $ 1,497,195.48 G911 11, 1 OD 1 1 Original BCC Approval Date; Agenda Item Current BCC Approved Amount 1,497,195.48' -10D 09/13/11, Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 1.,497,195.48 3/10/2013 SAP Contract Expiration Date (Master) Dollar Amount of this Change ($1,219,000:00) -81.42%1 Total Change . from Original Amount Revised Contract/Work Order Total $278,195.48 - _(si -81.42%1 Change from Current BCC Approved Amount Cumulative Changes - F 219,000 7 00)] -81.42%1 Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change I Original notice to proceed completion date: 3/1012013 I Last approved completion date: 3110/2013 Revised completion date (includes this added 1 change): 4/24/2013 Number of days added 6 if _ Explain why additional days are needed "detailed/specific)-:—Due to a discrepancy extension, must attach current between the construction checklist and original contract, an additional 45 days needs insurance certificate(s) from SIRE to be added to the contract time. The contract indicates a 465 contract time. however or obtain from vendor): 45 —Add —Chanqe 510 days is the correct contract 'time. new task(s) i M task(s) F� Delete task(s) I O-O—ther (ip_�ec_ FfF), I Time Extension & Deduct for I Direct Material Purchase Provide a detailed and specific explanation of the requested cWi-n-ge(s) task(s): Requesting a time zxtension of 45 calendar days due to discrepancy between construction checklist and contract. Direct Material Purchase in order to save the County $69,000 in sales tax. 2. Provide detailed rationale for the requested change: Additional time is needed due to discrepancy. A deduct change order is requested in order to process a direct material purchase for savings in sales tax. 3. Provide explanation why change was not anticipated in original scope of work: The direct material purchase was anticipated when the contract was awarded. A time extension is needed based on discrepancy noted above. 4. Describe the impact if this change is not processed: Based on the delivery time for material, schedule will not be met with current contract time. If DMP is not processed, County will need to pay $69,000 in sales tax. Type of Change / Modification Z 1. Planned / Elective 4. Correction of error(s) ❑ 2. Unforeseen condition s/circumstance LJ 5. Value 1 ❑ 3. Quantity or.price adjustment added I L>A 6. Schedule adjustment Approved by Date: t f I Name and Title: Tom Chmelik, P.E., Director, PUPPM I Reviewed by,- Procurement Strategist's Name: Nicole Parker �-7 Date: 756 Revised: 7127,111 1 Packet Page -1441- ININ&M, COM- COMILY Admini&ahe. Services Divism Purchasing E Contract Change Request Contract * 1 1 - Mod#: 1 5706 1 Project *: 80058.1 1 Project Manager: Clir 1/10/2012 Item 16.E.6. I It 11 Purchasing Department Change Modification Form ❑ Work Order Modification PO/Work Order M 45- Project Name: Bluebill Ave. Beach 129620 Access & Turnaround Drop off Department: CZM Contractor/Firm Name: DeAngelis Diamond Construction, Inc. Original Contract/Work Order Amount Original notice to proceed :�fJZ,itt Original BCC Approval Date; Agenda Item # Current BCC Approved Amount ,aga-fin, change): 2.3.12 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount extension, must attach current SAP Contract Expiration Date (Master) Dollar Amount of this Change. U.T10- 0.00% Total Change from Original Amount Revised Contract/Work Order Total 5422.890,00 0.00 Change from Current BCC Approved Amount lCumulative Changes sa rlr% 0.00%1 Change from Current Amount Comp escription,pf.the Task(s) Change, �;and: Rationalle.'forthe:; Change ,- Original notice to proceed Last approved completion date: Revised completion date (includes this completion date: 2.3.12 2.3.12 change): 2.3.12 Number of days added (if Explain why additional days are needed (detailed/specific): NIA extension, must attach current insurance certificate(s) from SIRE or obtain from vendor): Id /A -9—Add new tasks) I El Change task(s) Delete task(s) Other (specify): I Provide a detailed and specific explanation of the requested change(s) to the task(s): Changes and modifications to the original scope of work was required and necessary due to unforeseen site conditions that were encountered during the installation of the underground utility sewer line, a cluster of undetected electrical conduits were discovered under the road of Gulf Share Drive and required further explorations to determine the anginal intent and termination points, in addition to the unforeseen site conditions value enhancements were added to the original scope of i work to provide electrical accommodations for the future installation of the restroom facility, and increased unit measures were added to the existing scope of work to provide value enhancements. During the course of construction it was further determined that certain technical aspects of the original scope of work was not necessary or required and subsequently I deductions to the scope of work was implemented that resulted in contractual credits that were further negotiated in consideration all the cost to address the unforeseen site conditions and the contract add-ons. The final analysis of the total cost considerations of add-ons and deductions reflected a net zero dollar transaction to the final contract cost. 2. Provide detailed rationale for the requested change: The unforeseen site conditions revealed a large cluster of electrical conduits that were exposed and unconnected, further discovery explorations of adjoining property As-builts and cooperation with the transportation department road staff was implemented to determine the original intent of the lines and the point of termination; the consequential impacts associated with this discovery resulted in road paver separation and asphalt settlement that required further repairs in order to restore the site to the original conditions. During the original design phase of the project certain technical assumptions and anticipations were carefully calculated and incorporated into the bid plans and specifications as precautionary measures, however, during the course of construction it was further determined that the technical assumptions were not necessary or required and subsequently resulted in contractual credits. 3. Provide explanation why change was not anticipated in original scope of work: The unforeseen site conditions that were encountered could not have been detected prior to the construction process. Proper steps were initially taken to expose and discover any unknown site conditions through a collaborative effort with other property stakeholders and private vendors (i.e. No-Cuts) that were implemented via the contractors contractual requirements and the design professional's research and analysis during the pre-conceptual design phase. There was no reasonable explanation to the existence stence and discovery of the unknown cluster of electrical conduits and the lines were properly capped and terminated. Packet Page -1442- Revised: 7/2711! 1 N A/ A 0% 1 P ^ I/ 1i I I1 I/ I uiLu I z Item 10. C, 4. Describe the impact if this change is not processed: The contractual cost to cover the unforeseen site conditions and the contractual add -ons and deductions will not be ratified as required under the terms and conditions of the contract. i �ED 1. F I �4.0 fined / Elective 2. 'ection of error(s) 5. added lA or Approved by: Date: Name and Title: Clint Perrym�Proje-ct , a ge r Reviewed by: ' �j r I Dater+ Procurement Strategists Name: Lyn, Whod f Revised: 7!27111 2 Packet Page -1443- ►a Cti'il►" COUXty klTnngmhe Semmes Neon Purchasing XContract Change Request qj 1 /10/2012 Item 16.E.6. Purchasing Department, Change Modification Form ❑ Work Order Modification Contract #: 08- Mod #: 5 PO/Work Order #: Project Name: Watershed Management 5122 $ 4500106318 Plans Project #: ft%/ Project Manager: Mac Department: Land Contractor /Firm Name: PBSJ now / Hatcher Development Services Atkins Original Contract/Work Order Amount $ 575,736.95 3/10/09 16A10 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 1,879,134.33 10/13/09 10B Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 1,879,134.33 insurance certificate(s) from SAP Dollar Amount of this Change or obtain from vendor . 91 Days $0:00 0.00% Change from Current BCC Approved Amount Revised New Contract/Work Order Total [E I,879,134.33 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): NA Cumulative Changes $ 1,303,397.38 0.00% Chan a from Original Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change i Original notice to proceed date: March 25, 2009 Last approved date: 12/31/11 Revised date (includes this change): March 31, 2012 Number of days added (if Explain why additional days are needed (detailed /specific): ): The time extension is to extension, must attach current allow a more through public discussion and vetting of issues and completion of final insurance certificate(s) from SAP deliverables. Finalization of water quality model and final presentation to BCC took or obtain from vendor . 91 Days longer than expected. ❑ Add new task(s) ❑ Change task(s) ❑ Delete tasks) XOther (specify): Time Extension 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): NA 2. Provide detailed rationale for the requested change:The time extension is to allow completion of final reports and I deliver acceptable final products. Provide explanation why change was not anticipated in original scope of work: An overly ambitious attempt to I3. meet planning deadlines did not allow sufficient time for public discussion and completion of final reports. 4. Describe the impact if this change is not processed: Failure to complete the Watershed Management Plans would result in a Growth Management Plan deficiency. Type of Change / Modification LJ I. Planned / Elective 1 X 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment ❑ 4. Correction of error(s C7 5. Value added I X 6 Schedule adjustment Change Requested By ❑ Contractor /Consultant ❑ Owner X Using Department ❑ Design Professional 1 ❑ Regulatory Agency (specify) J -[]Other (specify): Purchasing Professional Participated in Negotiation of Change / Modification: ❑ Yes X No Approved by (Name and Title): tv J t r-- , jt t{ Date:12/1612011 .a Reviewed by (Purchasing Professional): Date: Packet Page -1444- Irw c4ner County -Admismhee Seeuces Nisbr) ru=asing Z contract change Request Contract #:11- Mod#: 2 '687 #: 60016 1 Project Manager i Ordoi5ez Original Contract/Work Order Amount Current BCC Approved Amount Current Contract/Work Order Amount Dollar Amount of this Chanae Revised New Contract/Work Order Total Cumulative Changes 1/10/2012 Item 16.E.6. I Purchasing Department Change Modification Form 17 Work Order Modification PO/Work Order # - Project Name: Pine Ridge Road Right 4500129480 Turn Lane 1mprovements at Livinaston Road Department: Transportation —li Contractor/Firm Name; Bonness, Inc. '-44,J,44.U2 :L21, t ,,Aa Original BCC Approval Date- Agenda Item # 94;;344.02: — Last BCC Approval Date; Agenda Item T 96.5T8.02 $2839,95 5.310 Change from Original Amount S 99,357.97 55.013.95 I 2.94-70/o Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original notice to proceed date: Last approved date: January I:Eft, 2012 Revised date (includes this change): October 3rd, 2011 March 1st, 2012 Number of days added (if 1. This change order is needed to replace an existing light pole (45' high) with a shorter f extension, must attach current light i)cie (30' hiah' in order to provide a safe offset distance from existino Dower lines i insurance certificate(s) from on Pine Ridoe Road at the Livinaston Road intersection. This item was not identified SAP or obtain from vendor): 60 durino the design phase of the Droiect. There is a need for time extension to provide for the Drocurement of 30' high pole: the contractor may need up to sixty (60 days to have the special pole fabricated, delivered and installed. The rest of the work will b� done Der the oriainal contract time so liquidated damages will not be _applied. Add new tasks) ❑Change tasks) I Delete tasks) I Other (specify): 2. Provide a detailed and specific explanation of the requested change(s) to the task(s): This chance order is needed tc replace an existino liaht Dole (45' high) with a shorter light pole (30' hiah) Provide detailed rationale for the requested change: The existing light pole was located too close to the existing Dower lines. a safe offset distance needs to be maintained which can only be achieved with a shorter Dole. ii 4. Provide explanation why change was not anticipated in original scope of work: The existing light ooie Droximity to the existing power lines was not identified during the design phase of the Droiect. 5. Describe the impact if this change is not processed: The County will not be able to reiocate the street liaht Dole and maintain the level of service of the existino street liaht system on Pine Ridae. Type of Change I Modification Planned / 1E)ective reseen conditionsicircumstance U 3. Quantity and price adiustment Li 4. Correction of errons) 5. Value added 6. Schedule adiustment Change Requested By. Contractor/Consultant Owner Using Deoartment Transportation Other ispecify th t y ,,—I Design Professional Re2u!atop( Agencv (specify1: O �urchasinq Professional Participated in Negotiation of,Cti@noe',7 Modifications Z Yes L1 No I Approved by (Name and Titiel il lot. UWn"' P.F--Principal Project Manaqer" Date, -Pvawed by (P r h 2 sin rofessional) Rhonda Cummings: ciaiist Date 12--lio Packet Page -1445- OT Mr cow Y. aam>7�s�ue sen�aes ck►rision Purdwing ❑ Contract Change Request 1/10/2012 Item 16.E.6. Purchasing Department Change Modification Form ® Work Order Modification T!QV i. Si Contract #: 08 -5060 Mod #: 03 (three) PO/Work Order #: Project Name: Immokalee MSTU Main Project #: Project Manager: 4500118491 Department: Immokalee Street Improvement Project Contractor /Firm Name: JRL Design - 4500118491 Bradley Muckel CRA Studio LLC Original ContractlWork Order Amount Original notice to proceed completion date: July 12, 2010 n1a' Original BCC Approval Date; Agenda Item # Current BCC Approved Amount Explain why additional days are needed (detailed /specific): Additional days are needed n1a Last BCC Approval Date; Agenda Item # Current Contract/VVork Order Amount $; :'34, °382:00 ;' or obtain from vendor): 245 days SAP Contract Expiration Date (Master) Dollar Amount of this Change ,-; 3:501 158.55% Total Change from Original Amount Revised Contract/Work Order Total $88,895.50 .engineering was excluded in the base contract. task(s) ED Delete task(s) El Other s eci (P fy): 158.55% Change from Current BCC Approved Amount Cumulative Changes $54,51150 scope of work to include irrigation directional bore in medians along Main Street (SR 29); and 3) extension of limit of work to 158.55% Change from Current Amount Completion Date,, Description' of the Task(s,) Change., and Rationale -for the Change .. . _ Original notice to proceed completion date: July 12, 2010 Last approved completion date: February 29, 2012 Revised completion date (includes this change): October 31, 2012 Number of days added (if Explain why additional days are needed (detailed /specific): Additional days are needed extension, must attach current due to 1) the project now being classified as FDOT — JPA (Joint Participation insurance certificate(s) from SIRE Agreement) Project requiring an increase in the time line schedule, increased reviews, or obtain from vendor): 245 days and added construction administration; and 2) due to an increase in scope of work to include irrigation directional bore in medians along Main Street (SR 29); and 3) extension of limit of work to include Jefferson Street in the median and to incorporate removal of the FDOT "white sticks" and related curb replacement; and 4) provide civil engineering services for all items per FDOT regulations. It should be noted that all civil Add new task(s) ❑ Change .engineering was excluded in the base contract. task(s) ED Delete task(s) El Other s eci (P fy): 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): This change represents a monetary and contract duration 'increase to JRL PO #4500118491 due to an increase in geographical project limits, scope of work and regulatory reviews to include specifically: 1) the project now being classified as FDOT — JPA Project requiring an increase in the time line schedule, increased reviews, and added construction administration; and 2) due to an increase in scope of work to include irrigation directional bore in medians along Main Street (SR 29); and 3) extension of limit of work to include Jefferson Street in the median and to incorporate removal of the FDOT "white sticks" and related curb replacement; and 4) provide civil engineering services for all items per FDOT regulations. It should be noted that all civil engineering was excluded in the base contract. 2. Provide detailed rationale for the requested change: This change is necessary in order to irrigate the medians in the middle of Main Street in Immokalee. This requires boring under roadways in numerous locations in order to run irrigation pipes. This project has recently been classified as an FDOT "JPA" (Joint Participation Agreement) project. This means that the Immokalee MSTU will be entering into a legal Agreement with FDOT which identifies specific review /approval criterion. Accordingly, this contract time extension and budgetary increase will allow for sufficient time for FDOT Plan review and comments and subsequent design consultant response and plan revisions. 3. Provide explanation why change was not anticipated in original scope of work: The time for FDOT plan review was not known at the onset of the project. Staff anticipates that the plan review and associated response as necessary can be done within the proposed extended timeframe for completion date of February 29, 2012. 4. Describe the impact if this change is not processed: The "sight line" intersection improvements in the initial contract have also recently been recognized by FDOT as work requiring to be covered by a Joint Participation Agreement. This means that, without this change, the design consultant would not be able -provide the required engineered plans or Revised: 7127111 Packet Page -1446- 1 4 provide adequate revisions by a licensed Florida Civil Engineer to plans as required by the FDt 1 /10/2012 Item 16. E Type oFChange!/ Modification 1. Planned / Elective ® 2. Unforeseen conditions /circumstance —3duantity or price adjustment ❑ 4. Correction of errors E 5. Value added ® 6. Schedule adjustment Change Requested'By ® Contractor /Consultant Owner ® Design Professional ®Usin De artment ® Regulatory Agency (specify): : FDOT ❑ Other specify): Purchasing Professional Participated in Negotiation of Change / Modification: ❑ Yes ® No proved by: Date: me and Title: Brady Muckel, MSTU Project Manager ( terim) P viewed by: is Date: Procurement Strategist's N(arri - Lyn Wood Packet Page -1447- Revised: 7127111 2 1/10/2012 Item 16. E.6. Purchasing Department Change Modification Form Z Work Carder Modification Contract M 09- Mod#: 1 POMork Order #: Project Name: Pelican Bay South Berra 5262SSM Current Contract/Work Order Amount 4500129570 and Swale Permitting Project #: N/A Project Manager: Kyle Department: Pelican Bay ContractoriFirm Name: Wilson Miller, Total Change from Original Amount Lukasz Services Division I Inc Original Contract/Work Order Amount Original .BCC Approval Date; Agenda Item # Current BCC Approved Amount WA NtX Last BCC Approval Date, Agenda Item # Current Contract/Work Order Amount S .' D1.7'D0: 31712013 SAP Contract Expiration Date (Master) Dollar Amount of this Change $0100, 0.00% Total Change from Original Amount Revised Contract/Work Order Total _$5,017.00 ❑ Add new task(s) ❑ Change task(s) #VALUE! Change from Current BCC Approved Amount Cumulative Changes $0.00 2. Provide detailed rationale for the requested change: To allow consultant the necessary time to complete the pre - 0.00% Change from Current Amount I Completion Date;_Description. of the Task(s) Change, and Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date (includes this completion date December29, December 29, 2011 change): February 27, 2012 2011 Procurement Strategist's Name'. Nicole Parker Number of days added (if Explain why additional days are needed (detailedlspecific): { extension, must attach current Coordination with PBSD staff and meetings with regulatory agencies to determine the insurance certificate(s) from SIRE j type permit required for proposed berm restoration. or obtain from vendor): *0- 60 ! ❑ Add new task(s) ❑ Change task(s) El Delete task(s) ® Other (specify): 1. Provide a detailed and specific explanation of the requested change(s) to the task(s): Collect historic imformation for presentation to the regulatory agencies to coordinate a less extensive permit that may otherwise be required. I 2. Provide detailed rationale for the requested change: To allow consultant the necessary time to complete the pre - permit application package for determining the type permitting required. ! 3. Provide explanation why change was not anticipated in original scope of wank: Prior to consulting with the agencies their was no way to-anticipate the permits that are now being required for the proposed work contemplated. I 4. Describe the impact if this change is not processed: The permitting process would not be completed and restoration work of the berm would not be able to proceed. Type of Change .I Modification 1. Planned / Elective 2. Unforeseen conditions /circumstance 3. Quantity or price adjustment LL 4. Correction of error(s) j LJ 5. Value added S. Schedule adjustment j Change Requested By Contractor /Consultant ► Owner j Using Department ! ❑ Design Professional Regulatory Agency (specify): Other (specify): Purchasing ProfessionaJP`articipated in Negotiation of Change 1 Modification: Li Yes X No i' f r'/ Approved by: , Date: Name and Title:- yid Lukaszf /P;.SD 0per ons Manager j Reviewed by: Date: Procurement Strategist's Name'. Nicole Parker F Packet Page -1448- Revised: 7/27111 1