Agenda 01/10/2012 Item #16A 41/10/2012 Item 16.A.4. EXECUTIVE SUMMARY Recommendation to approve final acceptance of the water and sewer utility facilities for Fiddler's Creek, Phase 3, Unit 4 and to authorize the County Manager, or his designee, to release any Utilities Performance Security to the Project Engineer or the Developer's designated agent. OBJECTIVE: The Board of County Commissioners, Ex- Officio the Governing Board of the Collier County Water -Sewer District, to accept final and unconditional conveyance of these water and /or sewer facilities. CONSIDERATIONS: 1) The Developer of Fiddler's Creek, Phase 3, Unit 4, has constructed the water and sewer facilities within dedicated easements to serve this development. See attached location map. 2) Preliminary acceptance of these utility facilities was approved by the Land Development Services staff on December 12, 2006. At that time, the value of these utility facilities (assets) was $11,630 for the water facilities and $7,773.50 for the sewer facilities (see attachment[s]). This final acceptance is in accordance with Collier County Ordinance No. 2004 -31, as amended. 3) Staff recorded all preliminary acceptance documents in the public records of Collier County, which have been reviewed and approved by the County Attorney's office as to form and legal sufficiency. 4) The water and sewer facilities have been operated and maintained by the Collier County Water -Sewer District during, not less than, the required one (1) year warranty period. 5) A final inspection to discover defects in materials and workmanship has been conducted by the Land Development Services staff in coordination with Public Utilities and these facilities have been found to be satisfactory and acceptable. 6) The PUD Monitoring staff has reviewed this request in relation to possible issues raised by the applicable Home Owners Association (HOA). Staff is unaware of any issues that would serve to negate the recommendation to release the applicable security. FISCAL IMPACT: Approval of this Executive Summary will have no specific financial impact. However, approval of this Executive Summary will result in the Collier County Water -Sewer District receiving unconditional title to the utility facilities, which at the time of preliminary acceptance, had a total (undepreciated) value of $19,403.50. GROWTH MANAGEMENT IMPACT: Approval of this Executive Summary will have no growth management impact. Packet Page -694- 1/10/2012 Item 16.A.4. LEGAL CONSIDERATIONS: This item is legally sufficient and requires a majority vote for Board action. - JBW RECOMMENDATION: That the Board of County Commissioners, Ex- Officio the Governing Board of the Collier County Water -Sewer District, authorize final acceptance of these water and sewer utility facilities for Fiddler's Creek, Phase 3, Unit 4, and authorize the County Manager, or his designee, to release any Utilities Performance Security (UPS) to the Project Engineer or the Developer's designated agent. PREPARED BY: Jodi Hughes, Technician, Land Development Services /Engineering Services, Growth Management Division, Planning and Regulation Attached Documents: 1. Location Map 2. Asset Sheet Packet Page -695- COLLIER COUNTY Board of County Commissioners Item Number: 16.A.4. 1/10/2012 Item 16.A.4. Item Summary: Recommendation to approve final acceptance of the water and sewer utility facilities for Fiddler's Creek, Phase 3, Unit 4 and to authorize the County Manager, or his designee, to release any Utilities Performance Security to the Project Engineer or the Developer's designated agent. Meeting Date: 1/10/2012 Prepared By Name: HughesJodi Title: Technician,Engineering & Environmental Services 12/6/20116:51:55 AM Approved By Name: BeardLaurie Title: Planner,Transportation Planning Date: 12/6/20117:16:35 AM Name: PuigJudy Title: Operations Analyst, CDES Date: 12/6/20119:16:29 AM Name: Steve Messner Title: Plant Manager,Water Date: 12/6/20119:28:42 AM Name: Paul Mattausch Title: Director - Water,Water Date: 12/6/2011 12:10:12 PM Name: McKennaJack Title: Manager - Engineering Review Services,Engineering & Environmental Services Date: 12/7/2011 12:03:02 PM Name: LorenzWilliam Title: Director - CDES Engineering Services,Comprehensive Packet Page -696- Date: 12/8/2011 10:52:04 AM Name: SunyakMark Title: Project Manager, Principal,Public Utilities Engineering Date: 12/9/20114:55:34 PM Name: NagySteve Title: Manager - Wastewater Collection, Wastewater Date: 12/12/20112:41:03 PM Name: Pam Libby Title: Manager - Operations- Water/WW,Water Date: 12/14/2011 8:12:54 AM Name: ChmelikTom Title: Project Manager, Principal,Public Utilities Engine Date: 12/21/20114:31:12 PM Name: MarcellaJeanne Title: Executive Secretary,Transportation Planning Date: 12/27/2011 9:10:10 AM Name: WhiteJennifer Title: Assistant County Attorney,County Attorney Date: 12/27/2011 11:20:20 AM Name: FederNorman Title: Administrator - Growth Management Div,Transportati Date: 12/28/2011 10:18:23 AM Name: KlatzkowJeff Title: County Attorney, Date: 12/29/20119:09:00 AM Name: IsacksonMark Title: Director -Corp Financial and Mgmt Svs,CMO Date: 12/31/2011 1:33:59 PM Name: SheffieldMichael Title: Manager- Business Operations, CMO Date: 1/3/2012 8:33:28 AM Packet Page -697- 1/10/2012 Item 16.A.4. 0 D 0 z D V T v 0 r M n M M 2 D N M w C Z a V/ M D IF M,,-- i m scut ' 1/10/2012 Item 16.A.4. Packet Page -698- 1/10/2012 Item 16.A.4. CERTIFICATION OF CONTRIBUTORY ASSETS PROJECT NAME: FIDDLERS CREEK PHASE 3 UNIT 4- HYACINTH LANE AOW NAME & ADDRESS OF OWNER: 951 Land Holdings LTD. 3470 Club Center Boulevard Naples, FL 34114 ORIGINAL TYPE OF UTILITY SYSTEM: POTABLE WATER (Materials) 10" DR -18 Water Main 10" 240 LF $14.50 $3,480.00 10" DR -14 Water Main 10" 20 LF $18.80 $376.00 8" DRA8 Water Main 8" 460 LF $9.50 $4,370.00 8" DR -14 Water Main 8" 20 LF $11.20 $224.00 Single Water Service Complete 1" 6 EA $190.00 $1,140.00 Double Water Service Complete 1.5" 2 EA $295.00 $590.00 8" Gate Valve 8" 1 EA $650.00 $650.00 Permanent Bacterial Sampling Point 314" 1 EA $800.00 $800.00 TOTAL COST: $11,630.00 I do hereby certify that the quantities of material described above are true and accurate representation of the as- installed cost of the system being contributed to Collier County Utilities, Inc.. CERTIFYING: Aaron Hunt - Branch E.I. Project Manager OF: Guymann Construction of FL, INC. STATE OF FLORIDA ) ) SS: COUNTY OF COLLIER) The foregoing instrument was signed and acknowledged before me this 12th day of July, 2006 by Aaron Hunt - Branch who is personally known to me and who did not take an oath. 'LM r SEAL: Notary Public c�, `v Au,� Notary Pf>blic State of Florida Pae 1 : Deanna M Painter g My Commission DD439676 of fL°V Expires 06/12/2009 Packet Page -699- CERTIFIAION OF CONTRIBUTORY ASETS 1/10/2012 Item 16.A.4. .. . PROJECT NAME: FIDDLERS CREEK PHASE 3 UNIT 4- HYACINTH LANE NAME & ADDRESS OF OWNER TYPE OF UTILITY SYSTEM: 951 Land Holdings LTD. 3470 Club Center Boulevard Naples, FL 34114 SANITARY SEWER (Materials ORIGINAL 8" PVC SDR -26 Sanitary Sewer 8" 537 LF $5.50 $2,953.50 Manhole, IET Lined, 4' Diameter 4' 2 EA $1,950.00 $3,900.00 Single Sanitary Sewer Service w/ Cleanout 6" 2 EA $100.00 $200.00 Double Sanitary Sewer Service w/ Cleanout 6" 4 EA $180.00 $720.00 TOTAL COST $7,773.50 I do hereby certify that the quantities of material described above are true and accurate representatior the as- installed cost of the system being contributed to Collier County Utilities, Inc.. CERTIFYING: Aaron Hunt- Branch, E.I. Project Manager O _ � C OF: Guymann Construction of FL, INC. STATE OF FLORIDA ) COUNTY OF COLLIER) The foregoing instrument was signed and acknowledged before me this 12th day of July, 2006 by Aaron Hunt - Branch who is personally known to me and who did not take an oath. TC,rQM Notary Public Packet Page -700- SEAL: am State of Florida inter n DD439676 2009