Loading...
Agenda 09/24/2013 Item #16A13 9/24/2013 16.A.13. EXECUTIVE SUMMARY Recommendation to approve Change Order No. 4 for Zero Dollars to Contract No. 12- 5820R with ZEP Construction, Inc. to complete the White Blvd. Bridge Replacement Project(Project No. 66066). OBJECTIVE: To receive authorization from the Board of County Commissioners (BCC) to transfer funds within this contract from the allowance designated for bridge items to the allowance designated for roadway items in which there was an overrun. CONSIDERATIONS: The BCC approved Contract No. 12-5820R with ZEP Construction, Inc. for the White Blvd. Bridge Replacement Project at its September 11, 2012 meeting. The contract amount of$1,982,066.74 contained an allowance of$177,468, however the schedule of values contained separate allowances for bridge and roadway items, further breaking down the allowances into separate amounts. Certain items in the roadway segment portion of the contract exceed the amount of the roadway allowance. In order to balance the contract and reflect the final quantities consumed in each portion of the project, funds from the bridge allowance need to be transferred into the roadway allowance. A change order was requested to be presented to the BCC by Finance for approval of this allowance transfer in place of a previously executed change letter. The project was completed on August 19, 2013, and the final contract amount is $1,879.340.46. This is an overall savings of$102,726.27 from the original contract amount. FISCAL IMPACT: A change order is required to move funds between separate allowance items within the same contract to properly reflect final quantities of items used in the construction project. An overall savings of$102,726.27 was achieved from the original contract amount for the project. The bridge replacement project is now complete; the asset has an estimated useful life of 100 years, and given the lifecycle costs of a bridge, actual maintenance costs are anticipated to be minimal for the first five to seven years in service. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval.—SRT GROWTH MANAGEMENT IMPACT: This recommendation is consistent with the County's Growth Management Plan. RECOMMENDATION: That the BCC approve Zero Dollar Change Order No. 4 to Contract No. 12-5820R, the White Blvd. Bridge Replacement Project, to allow the payment of the final pay request. Prepared by: Kevin H. Dugan, Project Manager,TECM Attachment: 1) Change Order No. 4 Packet Page-1376- 9/24/2013 16.A.13. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.A.16.A.13. Item Summary: Recommendation to approve Change Order No. 4 for Zero Dollars to Contract No. 12-5820R with ZEP Construction, Inc. to complete the White Blvd. Bridge Replacement Project(Project No. 66066). Meeting Date: 9/24/2013 Prepared By Name: LehmannJune Title: Operations Coordinator 9/13/2013 10:04:45 AM Approved By Name: AhmadJay Title:Director-Transportation Engineering,Transportation Engineering&Construction Management Date: 9/13/2013 10:35:48 AM Name: Dugan Kevin Title: Project Manager,Transportation Engineering&Const Date: 9/13/2013 10:45:21 AM Name: RitterSteve Title:Manager-Road Construction,Transportation Engineering&Construction Management Date: 9/13/2013 11:35:53 AM Name: TaylorLisa Title: Management/Budget Analyst,Transportation Administr Date: 9/13/2013 1:05:48 PM Name: CummingsRhonda Title: Contracts Specialist,Purchasing&General Services Date: 9/13/2013 5:44:44 PM Name: KearnsAllison Date: 9/16/2013 8:30:56 AM Packet Page-1377- 9/24/2013 16.A.13. Name: ShueGene Date: 9/16/2013 8:51:07 AM Name: LynchDiane Title:Administrative Assistant Date: 9/16/2013 2:56:06 PM Name: MarkiewiczJoanne Title: Manager-Purchasing Acquisition,Purchasing& Gene Date: 9/16/2013 3:09:09 PM Name: WardKelsey Title: Manager-Contracts Administration,Purchasing&Ge Date: 9/16/2013 4:19:37 PM Name: MarcellaJeanne Title: Executive Secretary,Transportation Planning Date: 9/17/2013 10:08:52 AM Name: TeachScott Title: Deputy County Attorney,County Attorney Date: 9/17/2013 9:07:30 PM Name: KlatzkowJeff Title: County Attorney Date: 9/18/2013 8:52:11 AM Name: UsherSusan Title: Management/Budget Analyst, Senior,Office of Manage Date: 9/18/2013 9:38:54 AM Name: IsacksonMark Title:Director-Corp Financial and Mgmt Svs,CMO Date: 9/18/2013 10:23:51 AM Packet Page -1378- 9/24/2013 16.A.13. RECEIVED cHANGE ORDER SP I 1 2C13 '---:, r T.E.&G.M. Dept. CHANGE ORDER NO4:* CONTRACT NO. 12-5820R BCC Date:9111/12 Agenda Item: 1111 TO:Mr.Rade Vuialdija ZEP Construction.Inc. 7802 Jean Blvd. Ft.Myers FL 33967 DATE:September 10.2013 PROJECT NAME:White Blvd.:13n dee Replagent PROJECT NO.: 66066 Under our AGREEMENT dated September 11.2013.you are directed to move funds from the ALLOWANCES to various ITEMS to cover over runs(See Attachment A). FOR THE Sum of:SO Zero dollars. Original Agreement Amount $1,982,066.74 Sum of Previous Changes $0 This Change Order $0 Present Agreement Amount $1.982.066.74 y./ The time for completion shall be increased by 0 calendar days due to this Change Order. viX Accordingly,the Contract Time is now 285 calendar days.,,- te substantial completion date is July 19, 2013, and the final completion date is August 19,2013_' 'our acceptance of this Change Order shall constitute a modification to our Agreement and will be performed subject to all the same terms and conditions as contained in our Agreement indicated above,as fully as if the same were repeated in this acceptance. The adjustment,if any,to the Agreement shall constitute a full and final settlement of any and all claims of the Contractor arising out of or related to the change set forth herein,including claims for impact and delay costs. ..- 7 / ... ...- Ptepared by , . ,<:‘- i ,,L' .,......"--- Date: ffi. , , Kevin Dugan, tr'ct M. ger Transportation Engineering Department / c frie Accepted By: . Pt..) jIA— Date: q§/1-3 Rade Vujaklija,Pr . et Man er - ZEP Construction,Inc. *----324------- .- 'I' ' --- Approved by t-- „,--...-t-4—e-- / Or Date: c?-//- Steve Ritter.Road Construction Manager Transportation Engineering Department ,,,,, / /2 .A.pproved by: 4-'-.)...- :- Date: , , , ..illy AhmadyPE,Director Transportation Engineering Department ,, -/ , 1,' Approved be: -I Dat ; Nick CaSalanguidit,Adniinistrator Growth Managetne -Divisi _4 . --- vi Approved by: ' , - „ ,j, . Date: Rhnnda Cummins. 'thburement Strategis , -*\ Packet Page-1379- ...-- 9/24/2013 16 A 13. IN WITNESS WHEREOF,the Contractor and the County have each,respectively,by an authorized person or agent,hereunder set their hands and seals on the date(s)indicated below. Accepted: 20 ATTEST: OWNER: BOARD OF COUNTY COMMISSIONERS Dwight E.Brock,Clerk COLLIER COUNTY,FLORIDA By: Georgia A.Hiller,Esq..Chairwoman Approved as to form and Legal sufficiency: 4914 Assistant County Attorney AININk Packet Page -1380- -- --- —� 013 16.A.13. Accelerated Bridge Construction, Project p66066 Attachment A Change Order#4Description Part I Roadway Items Transfer$125,000.00 from Bridge Items Allowance to Roadway hems Allowance to cover overruns Delete From Existing Pay Items CC- 950-2\RG -8riduc Items Allowance l LS $150'000.00 (+) $125,000.00 Revised Allowance $150,000.00 $(\25,000.80) — $25,000.00 Balance to date $25,000.00 Add to Fxistin Pay Items CC' 950-RDW —Roadway Items Allowance l LS Cu).$27,468.00 =f $125,000.00 Revised Allowance $27,468.00 f $l25`OQ0.O0= $]52`46O.O0 L�� / Balance to date $152.408.00 TOTAL = S0.00 Part II Bridge Items Transfer$21,326.00 from Bridge Items Allowance to Items 400-2-4, 455-34.3 and 530-1, to cover overruns Packet Page -1381- 9/24/2013 16.A.13. ,•0004 Delete From Existing Pay Items CC- 950—BRG —Bridge Items Allowance 1 LS (a) $25,000.00 (+) $21,326.00 Revised Allowance $25.000.00 $(21.326.00)= S3.674.00 Balance to date $3.674.00 Add to Existing Pa ' Items 400-2-4— Concrete Class IL Superstructure Sidewalk =+ $9,360.00 Original Quantity: 50 CY Increase Quantity by: 12 CY x $780.00 Revised Quantity: 62 CY Increase Existing Pay Item 400-2-4: $39,000.00+ $9,360.00 = Revised Contract Amount: $48,360.00 455-34-3 — Prestressed Concrete Piling =+ $11,880.00 Original Quantity: 2240 LF Increase Quantity by: 132 LF x $90.00 Revised Quantity: 2372 LF Increase Existing Pay Item 455-34-3: $201,600.00 + $11,880.00 = Revised Contract Amount: $211480.00 530-1 Riprap—Sand —Cement =+ $86.00 Original Quantity: 60 CY Increase Quantity by: .20 CY x $430.00 / Revised Quantity: 60.20 CY Increase Existing Pay Item 530-1: $25,800.00 + $86.00 = Revised Contract Amount: $25.886.00 Subtotal Bridge Items: / =+ $21.326.00 TOTAL = S0.00 Roadway Items oomot Packet Page-1382- 9/24/2013 16.A.13. Transfer $84,492.92 from Roadway Items Allowance to Items 104-11, 110-7-1, 334-1-13, 337-7- 32, 350-1-1, 520-2-41, 522-2, 530-3-4 and 530-78 , to cover overruns Delete From Existing Pay Items CC- 950— RDW — Roadway Items Allowance 1 LS (il? $152,468.00 =(+) $90,476.18 / Revised Allowance $152,468.00 $(84,492.92)= $61,991.82 Balance to date $61,991.82 Add to Existing Pay Items 104-11 — Floating Turbidity Barriers + $594.50 Original Quantity: 518 I,F Increase Quantity by: 82 LF x $7.25 Revised Quantity: 600 LE V Increase Existing Pay Item 104-11: $3,755.50+ $594.50 = Revised Contract Amount: $4.350.00 110-7-1 — Mail Box. F&I Single =+ $186.62 Original Quantity: 6 EA /- Increase Quantity by: 1 EA x 186.62 I/ Revised Quantity: 7 EA Increase Existing Pay Item 110-7-1: $1,119.72 + $186.62= Revised Contract Amount: $1.306.34 334-1-13 — Super Pave Asphalt = + $43,337.64 Original Quantity: 341 TN Increase Quantity by: 353.2 TN x $122.70 Revised Quantity: 694.2 TN Increase Existing Pay Item 334-1-13: $41,840.70+S43,337.64 = Revised Contract Amount: $85.178.34 337-7-32 — Friction Course Asphalt + $5,353.39 Original Quantity: 114 TN Packet Page-1383- 9/24/2013 16.A.13. Increase Quantity by: 31 TN x $172.69 Revised Quantity: 145 TN Increase Existing Pay Item 337-7-13: $19.686.66 + $5.353.39= Revised Contract Amount: $25,040.05 350-1-1 — Cement Concrete Pavement =+ $6,645.12 Original Quantity: 344 SY Increase Quantity by: 159.7 SY x $41.61 Revised Quantity: 503.7 SY Increase Existing Pay Item 350-1-1: $14.31.3.84 + $6.645.12 = tr`jr Revised Contract Amount: $20,958.96 520-2-41 —Drop Curb =+ $12.50 Original Quantity: 64 LF Increase Quantity by: 1 LF x $12.50 Revised Quantity: 65 LF Increase Existing Pay Item 520-2-41: $800.00+ $1 2.50 = Revised Contract Amount: $812.50 / 522-2—Concrete Sidewalk _+ $5,983.26 Aiow Original Quantity: 301 SY Increase Quantity by: 129.62 x $46.16 L/ Revised Quantity: 430.62 Increase Existing Pay Item 522-2: $13,894.16+$5,983.26= Revised Contract Amount: $19.877.42 530-3-4—Rip-Rap Rubble - =+ $25.808.56 Original Quantity: 293 TN Increase Quantity by: 468.65 TN x $55.07 Revised Quantity: 761.65 TN Increase Existing Pay Item 530-3-4: $16,135.51 + $25.808.56 = Revised Contract Amount: $41.944.07 530-78 —Rip-Rap Articulating Block = + $2,554.59 Original Quantity: 281 SY Increase Quantity by: 20.7 SY x $123.41 Revised Quantity: 301.7 SY Packet Page-1384- ....... ....... . 9/24/2013 16.A.13: Increase Existing Pay Item 530-78: $34,678.21 + $2,554.59= Revised Contract Amount: $37.232.80 Subtotal Roadway Items: =+ $90.476.18 • TOTAL ROADWAY = $0.00 Signing and Pavement Marking hems Transfer $284.02 from Signing & Pavement Marking Items Allowance to Items 706-3, 711-11- 111 and 711-11-211 , to cover overruns Delete From Existing Pay Items CC- 950 - SPM Signing & Pavement Items Allowance 1 LS (ii] $612.00 =(+) $284.02 Revised Allowance $612.00 $(284.02) = $327.98 Balance to date / $327.98 Add to Existing Pay Items 706-3 — Retro Reflective Pavement Markings $27:71 Original Quantity: 44 EA Increase Quantity by: 4 EA x $5.68 Revised Quantity: 48 EA Increase Existing Pay Item 706-3: $249.92 + $22.72= Revised Contract Amount: $272.64 711-11-111 — Thermoplastic Pavement Markings (White) =+ $104.52 Original Quantity: 0.32 NM Increase Quantity by: 0.02 NM x $5.226.07 "- Revised Quantity: 0.34 NM x$5,226.07 Increase Existing Pay Item 711-11-1 11: $1,672.34+ $104.52=- Revised Contract Amount: $1.776.86 Packet Page -1385- 9/24/2013 16.A.13. 711-11-211 — Thermoplastic Pavement Markings (Yellow) _+ $156.78 Original Quantity: 0.32 NM Increase Quantity by: 0.03 NM x $5,j26.07 Revised Quantity: 0.35 NM Increase Existing Pay Item 711-1 1-21 1: $1,672.34 + $156.78 = Revised Contract Amount: $1.829.12 Subtotal Roadway Items: = + $284.02 TOTAL SIGNING & PAVEMENT = S0.00 Net amount of Notification#4=$0.00 Packet Page -1386- 9/24/2013 16.A.13. Co x County Purchasing Department Adnnistive Servers Division Change Modification Form Durthasing ® Contract Change Request ❑Work Order Modification Contract#: 12- Change#:4 PO/Work Order#: Project Name:White Blvd Bridge 5820R 1 4500139885 Replacement -Project#:66066 Project Manager: Kevin , Department: Transportation Contractor/Firm Name:ZEP l Dugan Construction Mgmt Construction Original Contract/Work Order Amount $ `1,982#.066 '4':', :::::‘..,;t:n!„,,,,WrI1112 Original BCC Approval Date;Agenda Item# Current BCC Approved Amount .$' 1;962,0M74 -L' ..l Last BCC Approval Date;Agenda Item# Current Contract/Work Order Amount $ , 1,982,066.74' SAP Contract Expiration Date (Master) Dollar Amount of this Change 0.01" 0.00% Total Change from Original Amount Revised ContracWVork Order Total $1,982,066.74 0.00% Change from Current BCC Approved Amount Cumulative Changes $0.00 0.00% Change from Current Amount 1 Completion Date,Description of the Task(s)Change,and Rationale forethe Change Original completion date: July 5, Last approved completion date: I Revised completion date(includes this 2013 August 19, 2013 ' change):August 19, 2013 Number of days added: 45 Each step on the contract modification checklist form has been reviewed prior to me submitting for approval (this box must be initialed by Project Manager) t ❑Add new task(s) ❑ Change task(s) i (❑ Delete task(s) Other(specify): Balance Overruns 1. Provide a detailed and specific explanation of the requested change(s)to the task(s): Several items were overrun in Road items. Funds need to be transferred from the Bridge Allowance to cover the overruns in Road items. 2. Provide detailed rationale for the requested change:A change order is required to move funds between separate allowance items within the same contract to properly reflect final quantities of items used in the construction project. An overall savings of$102,726.27 was achieved from the original contract amount for the project. 3. Provide explanation why change was not anticipated in original scope of work: The overruns arose due to conditions encountered in the field. 4. Describe the impact if this change is not processed: The contractor will not receive compensation for work that was necessary to complete the project. Type of Change!Modification . w, ❑ 1. Planned/ Elective 0 2. Unforeseen conditions/circumstance ❑ 3 Quantity or price adjustment 11L 4. Correction of error(s) ; ❑ 5. Value added -- l 6, Schedule adjustment Change RequestedBY .. r . ,: ❑Contractor/Consultant ( ® Owner ❑ Using Department ❑ Design Professional { ❑ Regulatory Agency(specify): , ❑ Other s ecif : , Purchasing Professional Participated in Negotiation of Change/Modification: Yes No Revised:7/27/11 1 Packet Page -1387- 9/24/2013 16.A.13. Approved by t Date !_ Name and Title in H. Mgr-, .sect a��er Reviewed by' Date ' 1( A? Pi ocureme ' r i - s Name -' • :_ t.. ,s r / Revised'.727f11 2 Packet Page -1388-