Agenda 04/24/2018 Item #16C704/24/2018 EXECUTIVE SUMMARY Recommendation to approve and authorize the Chairman to execute a Sixth Amendment to Contract No. 04-3673 with Carollo Engineers, Inc., f/k/a Carollo Engineers, P.C., pertaining to the design of the Northeast Water Reclamation Facility and Water Treatment Plant, authorize a purchase order in the amount of $149,943 to Carollo Engineers, Inc. and authorize the necessary budget amendments. OBJECTIVE: To ensure the proactive coordination of northeast development activities conducted by the Water Division, Wastewater Division, Solid and Hazardous Waste Division, Facilities Division and the Parks & Recreation Division, by obtaining approval of a Sixth Amendment to Contract No. 04-3673. CONSIDERATIONS: On September 26, 2017 as Agenda Item 16C1, the Board of County Commissioners approved Contract Amendment Number 5 reactivating Contract No. 04-3673, "Professional Engineering Services for Design of the Northeast Water Reclamation Facility and Water Treatment Plant," with Carollo Engineers, Inc. Thereafter, staff issued Purchase Order No. 4500182517 to update the design criteria for the Northeast Regional Water Reclamation Facility (NEWRF) and the Northeast Regional Water Treatment Plant (NERWTP), including technology updates. The design criteria update is approximately 30% complete. Site plan modifications will be contemporaneously initiated under the Amendment’s revised scope of work to address the following three categories (reference Attachment 1): 1) Pipeline Realignment Since the original design plans were completed, development plans for the lands surrounding the proposed facility have changed, requiring pipeline realignments for: The Big Corkscrew Island Regional Park (BCIRP), Phase I immediately west of the Northeast Utility Facility (NEUF) site; Pipeline and well site modifications driven by BCIRP changes from the original design; The future design and development of Phase II of the BCIRP; Design and construction of an access road from Oil Well Road to the SE corner of the future Phase II of the BCIRP; Connections to and from the former Orange Tree Utility site; The Northeast Recycling Drop-off Center (NERDC) (potable water supply); The Sheriff’s Substation (potable water supply); and The Agricultural Center (potable water supply). 2) Civil Site Design In anticipation of northeast development activity and construction of the BCIRP Phase I, staff is preparing to commence development of the Northeast Utility Facility site. This scope of work identifies strategies and site considerations that will allow commencement of civil/site development construction efforts in advance of final design of the treatment facilities. This effort will include the evaluation of site design components that can be constructed in advance of the water and wastewater treatment facilities. Early site work to be considered will include the evaluation of environmental permit requirements, clearing and grubbing, site grading, stormwater facilities, access roads, fencing, landscaping with irrigation, yard piping, and potential electrical service improvements. Extensive northeast utility transmission mains passing through the BCIRP Phase I need to be constructed concurrently or in advance of the BCIRP 16.C.7 Packet Pg. 869 04/24/2018 Phase I to avoid disrupting park operations thereafter. 3) Orange Tree Wastewater Treatment Plant (OTWWTP) Effluent Disposal The Orange Tree Wastewater Treatment Plant disposes its treated effluent by applying it to rapid infiltration basins (percolation ponds). When the water table is high, these ponds are less efficient and disposal issues result. To improve effluent disposal reliability, staff plans to construct one of the previously designed NEUF deep injection wells on NEUF property approximately one mile north of the former Orange Tree Utility Site. This deep injection well and the necessary piping will provide adequate effluent disposal capacity for the current OTWWTP capacity as well as any foreseeable expansion. This design scope of work includes the alignment of pipelines that will con vey the blended effluent to the proposed deep injection well site. The items included in the above three categories will be represented on one Northeast Base Map so that pipe alignment decisions may be made in full consideration of competing interests. This base map will be used to drive future designs and construction packages as needed to keep pace with development. If the NEWRF and NERWTP construction is deferred, this work is still required to ensure that nearby projects are constructed in consideration of utility requirements. In addition, the scope of work includes platting the parent parcel that contains the NEWRF, the NERWTP, the BCIRP and the NERDC. Dividing the parcel will optimize future efforts to proceed with a phased development plan. FISCAL IMPACT: The above amendment of $149,943 will be split evenly between the water and wastewater user-fee supported capital funds. Budget amendments are required to move funding from the Orangetree Compliance project 70173 in the amount of $75,000 in the Water User-fee Capital Fund (412) and $75,000 in the Wastewater User-fee Capital Fund 414 into the Northeast Utility Facility project 70194. GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities and to remain in compliance with all regulatory programs, including concurrency requirements, the Federal Department of Environmental Protection’s readiness reporting pursuant to permit conditions, and all other laws and administrative codes and regulations. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval. -SRT RECOMMENDATION: That the Board of County Commissioners approves and authorizes the Chairman to execute the attached Sixth Amendment to Contract No. 04-3673 with Carollo Engineers, Inc., in the amount of $149,943, and to authorize the necessary budget amendments. Prepared by: Tom Chmelik, P.E., PMP, Public Utilities Engineering and Project Management Director ATTACHMENT(S) 1. Attachment 1: Amendment 6 with exhibits (PDF) 16.C.7 Packet Pg. 870 04/24/2018 COLLIER COUNTY Board of County Commissioners Item Number: 16.C.7 Doc ID: 5167 Item Summary: Recommendation to approve and authorize the Chairman to execute a Sixth Amendment to Contract No. 04-3673 with Carollo Engineers, Inc., f/k/a Carollo Engineers, P.C., pertaining to the design of the Northeast Water Reclamation Facility and Water Treatment Plant, authorize a purchase order in the amount of $149,943 to Carollo Engineers, Inc. and authorize the necessary budget amendments. Meeting Date: 04/24/2018 Prepared by: Title: Division Director - Public Utilities Eng – Public Utilities Planning and Project Management Name: Tom Chmelik 03/20/2018 11:51 AM Submitted by: Title: Division Director - Public Utilities Eng – Public Utilities Planning and Project Management Name: Tom Chmelik 03/20/2018 11:51 AM Approved By: Review: Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 03/20/2018 12:28 PM Water Steve Messner Additional Reviewer Completed 03/21/2018 2:16 PM Wastewater Steve Messner Additional Reviewer Completed 03/21/2018 2:16 PM Public Utilities Operations Support Joseph Bellone Additional Reviewer Completed 03/26/2018 7:59 AM Procurement Services Ted Coyman Additional Reviewer Completed 03/27/2018 10:17 AM Solid and Hazardous Waste Dan Rodriguez Additional Reviewer Completed 03/27/2018 11:25 AM Solid and Hazardous Waste Sarah Hamilton Additional Reviewer Completed 03/29/2018 9:49 AM Procurement Services Sandra Herrera Additional Reviewer Completed 03/29/2018 4:59 PM Public Utilities Department Heather Bustos Level 1 Division Reviewer Completed 04/02/2018 11:23 AM Public Utilities Department George Yilmaz Level 2 Division Administrator Review Completed 04/04/2018 9:26 PM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 04/10/2018 8:46 AM Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 04/10/2018 9:03 AM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 04/11/2018 1:22 PM Office of Management and Budget Susan Usher Additional Reviewer Completed 04/17/2018 4:47 PM County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 04/18/2018 7:57 AM 16.C.7 Packet Pg. 871 04/24/2018 Board of County Commissioners MaryJo Brock Meeting Pending 04/24/2018 9:00 AM 16.C.7 Packet Pg. 872 16.C.7.a Packet Pg. 873 Attachment: Attachment 1: Amendment 6 with exhibits [Revision 1] (5167 : Northeast Water Reclamation Facility and Water Treatment Plant 16.C.7.a Packet Pg. 874 Attachment: Attachment 1: Amendment 6 with exhibits [Revision 1] (5167 : Northeast Water Reclamation Facility and Water Treatment Plant 16.C.7.a Packet Pg. 875 Attachment: Attachment 1: Amendment 6 with exhibits [Revision 1] (5167 : Northeast Water Reclamation Facility and Water Treatment Plant 16.C.7.a Packet Pg. 876 Attachment: Attachment 1: Amendment 6 with exhibits [Revision 1] (5167 : Northeast Water Reclamation Facility and Water Treatment Plant 16.C.7.a Packet Pg. 877 Attachment: Attachment 1: Amendment 6 with exhibits [Revision 1] (5167 : Northeast Water Reclamation Facility and Water Treatment Plant 16.C.7.a Packet Pg. 878 Attachment: Attachment 1: Amendment 6 with exhibits [Revision 1] (5167 : Northeast Water Reclamation Facility and Water Treatment Plant 16.C.7.a Packet Pg. 879 Attachment: Attachment 1: Amendment 6 with exhibits [Revision 1] (5167 : Northeast Water Reclamation Facility and Water Treatment Plant 16.C.7.a Packet Pg. 880 Attachment: Attachment 1: Amendment 6 with exhibits [Revision 1] (5167 : Northeast Water Reclamation Facility and Water Treatment Plant 16.C.7.a Packet Pg. 881 Attachment: Attachment 1: Amendment 6 with exhibits [Revision 1] (5167 : Northeast Water Reclamation Facility and Water Treatment Plant