Agenda 04/24/2018 Item #16A1004/24/2018
EXECUTIVE SUMMARY
Recommendation to award Bid #18-7267 to Coastal Concrete Products, LLC, for the construction
of Lely Branch Canal Weir Project, in the amount of $444,380, Project No. 60202, authorize the
Chairman to execute the Contract, and authorize the necessary budget amendments.
OBJECTIVE: To commence with the construction of the Lely Branch Canal Weir at the north side of
Rattlesnake Hammock Road near St. Peter’s Church in east Naples.
CONSIDERATIONS: The Lely Branch Weir is a supplemental water conservation element of the Lely
Area Stormwater Improvement Plan (LASIP). The implementation of LASIP with modified canals and
new water control features during the last decade has provided milestone water management
improvements in the Lely area by effectively conveying floodwaters, providing dry season conservation
pools, and regulating freshwater releases to the receiving estuaries. This weir is required to facilitate
groundwater recharge and mitigate some observed lowering of the area lakes resultin g from stormwater
conveyance improvements to the Lely Branch Canal performed as a part of LASIP. The structure will
also be equipped with manually operable water control gates to convey floodwaters during the wet
season. The County staff, in consultation with local Engineering firm Agnoli, Barber and Brundage Inc.
has developed detailed feasibility engineering, design, plans and specifications, and obtained the
necessary regulatory permits for construction of the structure. The County has also been awarded a
partial funding grant of 40% of the construction cost up to $200,000 from the South Florida Water
Management District.
The County advertised the solicitation for construction contract bids for the project on January 17, 2018,
in the Naples Daily News, and in the County’s web based bidding portal with BidSync
(www.bidsync.com <http://www.bidsync.com>). The County received the following five bids by the
February 16, 2018 due date:
Contractor Bid
1 Coastal Concrete Products, LLC $ 444,380.00
2 Quality Enterprises, Inc. $ 449,125.40
3 Douglas N. Higgins, Inc. $ 454,000.00
4 Zep Construction, Inc $ 638,786.80
5 Thomas Marine Construction, Inc. $ 674,310.00
The Procurement Services Staff and the Design Engineer tabulated and verified the bids recei ved.
Coastal Concrete Products, LLC, is the apparent lowest, responsive and responsible bidder. Staff and the
Design Consultants performed a bid analysis to determine if there were any anomalies in the bids, and
noted no discrepancies. The lowest bid is approximately 33% above the Engineer’s Opinion of Probable
Cost, which was $333,815. The higher quotes of the bids were due to the present overall demand of
contractors for post IRMA recovery work, and overall increase of general construction activities i n the
area. However, the three lowest bidders were within $10,000 or 2.25% of the lowest bid, which indicated
that a fair and reasonable competitive market condition prevailed, and justifiable.
Therefore, Staff recommends awarding Bid #18-7267 to Coastal Concrete Products, LLC, the lowest
responsive and responsible bidder.
FISCAL IMPACT: Total cost of the project is $444,380. SFWMD funds 40% of construction costs in
the amount of $177,752 available in Fund (711), Project 60202. A budget amendment is required to
recognize the required 60% match of 266,628 within GMD Match Grant Fund 712, Project 60202. Local
16.A.10
Packet Pg. 672
04/24/2018
Funds are available within the Stormwater Capital Fund (325), Projects 60202 and 60143 via transfer.
The transfer is supported by General Fund (001) revenue provided to Stormwater Capital Program.
The maintenance of this weir, like rest of the LASIP water control structures, is included in the Road
Maintenance Division’s maintenance schedule. Therefore, maintenance costs are unchanged.
GROWTH MANAGEMENT IMPACT: The proposed construction projects are in accordance with
the goals, objectives, and policies of all applicable sections of the Stormwater Management and the
Conservation and Coastal Management elements of the Growth Management Plan.
LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority
vote for Board approval. -SRT
RECOMMENDATION: To award Bid #18-7267 “Lely Branch Canal Weir” construction project to
Coastal Concrete Products, LLC, in the amount of $444,380; authorize the Chairman to execute the
attached contract; and authorize all budget amendments necessary to recognize and appropriate funds for
the project.
Prepared By: Ananta Nath P.E, Sr. Project Manager / Capital Project Planning, Impact Fees, and
Program Management Division
ATTACHMENT(S)
1. 18-7267 Bid Tabulation (PDF)
2. 18-7267 Bid Recommendation Letter for EOR (PDF)
3. 18-7267 - Approved NORA (PDF)
4. [Linked] 18-7267 Coastal_Contract_VendSign (PDF)
16.A.10
Packet Pg. 673
04/24/2018
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.A.10
Doc ID: 5207
Item Summary: Recommendation to award Bid #18-7267 to Coastal Concrete Products, LLC, for
the construction of Lely Branch Canal Weir Project, in the amount of $ 444,380, Project No. 60202,
authorize the Chairman to execute the Contract, and authorize the necessary budget amendments.
Meeting Date: 04/24/2018
Prepared by:
Title: – Capital Project Planning, Impact Fees, and Program Management
Name: Ananta Nath
04/04/2018 12:18 PM
Submitted by:
Title: Division Director - IF, CPP & PM – Capital Project Planning, Impact Fees, and Program
Management
Name: Amy Patterson
04/04/2018 12:18 PM
Approved By:
Review:
Growth Management Department Judy Puig Level 1 Reviewer Completed 04/06/2018 8:26 AM
Capital Project Planning, Impact Fees, and Program Management Gino Santabarbara Additional Reviewer Completed 04/06/2018 9:58 AM
Capital Project Planning, Impact Fees, and Program Management Amy Patterson Additional Reviewer Completed 04/06/2018 10:57 AM
Capital Project Planning, Impact Fees, and Program Management Gerald Kurtz Additional Reviewer Completed 04/06/2018 11:53 AM
Growth Management Department Gino Santabarbara Additional Reviewer Skipped 04/09/2018 4:14 PM
Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 04/09/2018 5:03 PM
Procurement Services Ted Coyman Additional Reviewer Completed 04/10/2018 10:07 AM
Procurement Services Sandra Herrera Additional Reviewer Completed 04/11/2018 10:26 AM
Procurement Services Adam Northrup Additional Reviewer Completed 04/11/2018 1:15 PM
Procurement Services Swainson Hall Additional Reviewer Completed 04/11/2018 3:21 PM
Growth Management Department Gino Santabarbara Deputy Department Head Review Skipped 04/12/2018 10:30 AM
Growth Management Department Thaddeus Cohen Department Head Review Completed 04/12/2018 1:34 PM
County Attorney's Office Scott Teach Level 2 Attorney Review Completed 04/12/2018 5:12 PM
Grants Edmond Kushi Level 2 Grants Review Completed 04/13/2018 8:34 AM
Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 04/13/2018 9:17 AM
County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 04/13/2018 11:35 AM
16.A.10
Packet Pg. 674
04/24/2018
Grants Therese Stanley Additional Reviewer Completed 04/14/2018 11:21 AM
Office of Management and Budget Susan Usher Additional Reviewer Completed 04/14/2018 12:30 PM
County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 04/15/2018 9:32 PM
Board of County Commissioners MaryJo Brock Meeting Pending 04/24/2018 9:00 AM
16.A.10
Packet Pg. 675
Project Manager: Anata Nath
Procurement: Adam Northrup Bid Tabulation
18-7267 - Lely Branch Canal Weir
Notifications Sent: 11,141
Packages Downloaded: 96
Bidders: 5
Item No.Description Unit Quantity Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost
1 MOBILIZATION LS 1 $42,500.00 $42,500.00 $82,519.12 $82,519.12 $45,000.00 $45,000.00 $68,614.00 $68,614.00 $72,900.00 $72,900.00
2 PROVIDE/MAINTAIN AS-BUILT PLANS LS 1 $5,000.00 $5,000.00 $4,064.90 $4,064.90 $1,400.00 $1,400.00 $5,158.00 $5,158.00 $2,380.00 $2,380.00
3 PROVIDE CONSTRUCTION SURVEYING AND LAYOUT LS 1 $5,000.00 $5,000.00 $2,049.13 $2,049.13 $1,500.00 $1,500.00 $4,421.00 $4,421.00 $2,535.00 $2,535.00
4 MAINTENANCE OF TRAFFIC LS 1 $7,500.00 $7,500.00 $6,480.01 $6,480.01 $3,000.00 $3,000.00 $2,950.00 $2,950.00 $1,625.00 $1,625.00
5 CLEARING AND GRUBBING LS 1 $12,500.00 $12,500.00 $2,864.74 $2,864.74 $1,900.00 $1,900.00 $3,465.00 $3,465.00 $7,500.00 $7,500.00
6 EROSION CONTROL LS 1 $7,500.00 $7,500.00 $10,842.58 $10,842.58 $2,000.00 $2,000.00 $3,353.00 $3,353.00 $7,200.00 $7,200.00
7 CANAL GRADING AND REWORK GABIONS LS 1 $25,000.00 $25,000.00 $12,892.52 $12,892.52 $3,000.00 $3,000.00 $11,508.00 $11,508.00 $10,800.00 $10,800.00
8 PARKING LOT RESTORATION LS 1 $18,000.00 $18,000.00 $19,544.32 $19,544.32 $6,000.00 $6,000.00 $7,368.00 $7,368.00 $24,200.00 $24,200.00
9 FENCING, BLACK CLAD VINYL COATED CHAIN LINK (6' HIGH)LF 20 $180.00 $3,600.00 $64.34 $1,286.80 $57.00 $1,140.00 $110.00 $2,200.00 $90.00 $1,800.00
10 FENCE GATE, BLACK CLAD VINYL COATED CHAIN LINK (SINGLE, 6' HIGH, 6' WIDE)EA 1 $400.00 $400.00 $1,351.08 $1,351.08 $750.00 $750.00 $1,105.00 $1,105.00 $1,000.00 $1,000.00
11 RIP RAP (RUBBLE)(BANK & SHORE)(30" THICK)(INCLUDES BEDDING STONE)CY 140 $150.00 $21,000.00 $180.08 $25,211.20 $270.00 $37,800.00 $210.00 $29,400.00 $100.00 $14,000.00
12 PERFROMANCE TURF (BAHIA)(INCLUDES WATER, FERTILIZER & MOWING)SY 220 $4.00 $880.00 $12.13 $2,668.60 $9.00 $1,980.00 $5.89 $1,295.80 $9.00 $1,980.00
13 WEIR CONTROL STRUCTURE WITH GATES (INCLUDES HANDRAIL AND PILING)LS 1 $250,000.00 $250,000.00 $234,540.66 $234,540.66 $303,630.00 $303,630.00 $434,500.00 $434,500.00 $475,500.00 $475,500.00
14 8" FORCEMAIN RELOCATION LS 1 $12,500.00 $12,500.00 $10,886.22 $10,886.22 $13,000.00 $13,000.00 $30,945.00 $30,945.00 $19,890.00 $19,890.00
15 PROJECT INFORMATION SIGN EA 2 $1,500.00 $3,000.00 $961.76 $1,923.52 $950.00 $1,900.00 $1,252.00 $2,504.00 $500.00 $1,000.00
16 DRAINAGE ALLOWANCE FIXED 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00
17 PROJECT TOTAL $444,380.00 $449,125.40 $454,000.00 $638,786.80 $674,310.00
Bidders Checklist
Material Manufacturers
List of Major Subcontractors
Statement of Experience of Bidder
Trench Safety Act
Immigrations Law Affidavit Certification
E-Verify
Substitiute W-9/W-9
Bid Bond
Insurance Requirements
Grant Forms
xx
x
x
x
x
x
xx
x
x x x
xx x
x x x
x
x x
x
x
x
x
x x
x
x
x x xx
xxx
xx xx
Coastal Concrete ZEP ConstructionDN Higgins Thomas MarineQuality Enterprises
x x
16.A.10.a
Packet Pg. 676 Attachment: 18-7267 Bid Tabulation (5207 : Lely Branch Canal Weir)
Page 1 of 2
March 13, 2018
Via email to Ananta.Nath@colliercountyfl.gov
Ananta Nath, P.E., Project Manager
Collier County Capital Project Planning,
Impact Fees and Program Management
Stormwater Management Section
2685 Horseshoe Drive South, Suite 104
Naples, FL 34104
Sub: 18-7267 – Lely Branch Canal Weir: Bid Analysis
Dear Mr. Nath:
We have reviewed the bids received at the February 16, 2018 bid opening for the above-referenced
project. A tabulation of bids was received from the County for review on February 26, 2018.
Proposals were received from the following bidders:
Firm Bid Total
Coastal Concrete Products, LLC $444,380.00
Quality Enterprises USA, Inc. $449,125.40
Douglas N Higgins, Inc. $454,000.00
ZEP Construction, Inc. $636,786.80
Thomas Marine Construction, Inc. $674,310.00
The lowest bid from Coastal Concrete Products, LLC. was approximately 33% above engineer’s
opinion of probable construction cost (OPC), but within the overall project budget. Considering
the lowest three bids are within approximately $10,000 of each other, or within 2.25% of the low-
bid, it is our opinion that the project generated good interest from contractors and resulted in a
competitive bidding environment. We believe there are two main reasons for the bid prices being
higher than the OPC:
1) It is a relatively small project. Typically, large weir structures of this type are
installed with roadway or canal projects where there is a lot of other construction
work.
16.A.10.b
Packet Pg. 677 Attachment: 18-7267 Bid Recommendation Letter for EOR (5207 : Lely Branch Canal Weir)
Page 2 of 2
2) Contractors in the area are very busy with the post-IRMA recovery construction
activities as well as a general increase in construction activity. Therefore, they
don’t have to be as competitive with their bid prices since they have back-load of
work.
We have reviewed the bid schedules provided by the County for accuracy and find that there are
no accounting errors. Subject to Collier County Purchasing Department review and approval of
bidder qualifications and responsiveness, we are not aware of any outstanding issues or problems
with Coastal Concrete Products, LLC. that would prevent us from recommending their selection
as the low-bidder. Agnoli, Barber & Brundage, Inc. looks forward to working successfully with
Coastal Concrete Products, LLC on this project.
Should you have any questions, please feel free to contact me.
Sincerely,
AGNOLI, BARBER & BRUNDAGE, INC.
Edward F. Tryka, III, P.E.
Vice President, Transportation
EFT/drr
16.A.10.b
Packet Pg. 678 Attachment: 18-7267 Bid Recommendation Letter for EOR (5207 : Lely Branch Canal Weir)
16.A.10.c
Packet Pg. 679 Attachment: 18-7267 - Approved NORA (5207 : Lely Branch Canal Weir)
CONSTRUCTION AGREEMENT
THE BOARD OF COUNTY COMMISSIONERS OF COLLIE=R COUNTY, FLORIDA, ("Owner')
hereby contracts with Coastal Concrete Products, LLC dba Coastal Site Development
("Contractor") of 7742 Alico Road, Fort Myers, FL 33992, a corporation, authorized to do business
in the State of Florida, to perform all work ("Work") in connection with Lely Branch Canal Weir,
Invitation to Bid No. 18-7267 ("Project"), as said Work is set forth in the Plans and Specifications
prepared by Agnoli Barber & Brundage, Inc., the Engineer and/or Architect of Record ("Design
Professional") and other Contract Documents hereafter specified.
Owner and Contractor, for the consideration herein set forth, agree as follows:
Section 1. Contract Documents.
A, The Contract Documents consist of this Agreement, the E=xhibits described in Section 6
hereof, the Legal Advertisement, the Bidding Documents and any duly executed and issued
addenda, Change Orders, Work Directive Changes, Field Orders and amendments relating
thereto. All of the foregoing Contract Documents are incorporated by reference and made a part
of this Agreement (all of said documents including the Agreement sometimes being referred to
herein as the "Contract Documents" and sometimes as the "Agreement" and sometimes as the
"Contract"). A copy of the Contract Documents shall be maintained by Contractor at the Project
site at all times during the performance of the Work,
B. Owner shall furnish to the Contractor one reproducible set of the Contract Documents and
the appropriate number of sets of the Construction Documents, signed and sealed by the Design
Professional, as are reasonably necessary for permitting.
Section 2. Scope of Work.
Contractor agrees to furnish and pay for all management, supervision, financing, labor, materials,
tools, fuel, supplies, utilities, equipment and services of every kind and type necessary to
diligently, timely, and fully perform and complete in a good and workmanlike manner the Work
required by the Contract Documents.
Section 3. Contract Amount.
In consideration of the faithful performance by Contractor of the covenants in this Agreement to
the full satisfaction and acceptance of Owner, Owner agrees to pay, or cause to be paid, to
Contractor the following amount (herein "Contract Amount"), in accordance with the terms of
this Agreement: Four Hundred Forty -Four Thousand Three Hundred and Eighty
Dollars ($444,3$0.00).
Section 4. Bonds,
A. Contractor shall provide Performance and Payment Bonds, in the form prescribed in
Exhibit B-1 and R-2, in the amount of 100% of the Contract Amount, the costs of which are to be
paid by Contractor. The performance and Payment Bonds shall be underwritten by a surety
authorized to do business in the State of Florida and otherwise acceptable to Owner; provided,
however, the surety shall meetthe requirements of the Department of the Treasury Fiscal Service,
"Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as
Acceptable Reinsurance Companies" circular. This circular may be accessed via the web at
1
Consiructlan Services Agreement: Revised 022018
www.fms.treas.gov/c570/c570.html#certified. Should the Contract Amount be less than
$500,000, the requirements of Section 287.0935, F.S. shall govern the rating and classification of
the surety.
B. If the surety for any bond furnished by Contractor is declared bankrupt, becomes insolvent,
its right to do business is terminated in the State of Florida, or it ceases to meet the requirements
imposed by the Contract Documents, the Contractor shall, within five (5) calendar days thereafter,
substitute at its cost and expense another bond and surety, both of which shall be subject to the
Owner's approval.
Section 5. Contract Time and Liquidated Damages.
A. Time of Performance,
Time is of the essence in the performance of the Work under this Agreement. The
"Commencement Date" shall be established in the written Notice to Proceed to be issued by the
Project Manager, as hereinafter defined. Contractor shall commence the Work within five (5)
calendar days from the Commencement Date. No Work shall be performed at the Project site
prior to the Commencement Date. Any Work performed by Contractor prior to the
Commencement Date shall be at the sole risk of Contractor, Contractor shall achieve Substantial
Completion within one hundred and twenty (120) calendardays from the Commencement Date
(herein "Contract Time"). The date of Substantial Completion of the Work (or designated portions
thereof) is the date certified by the Design Professional when construction is sufficiently complete,
in accordance with the Contract Documents, so Owner can occupy or utilize the Work (or
designated portions thereof) for the use for which it is intended. Contractor shall achieve Final
Completion within Ninety (80) calendar days after the date of Substantial Completion, Final
Completion shall occur when the Agreement is completed in its entirety, is accepted by the Owner
as complete and is so stated by the Owner as completed. As used herein and throughout the
Contract Documents, the phrase "Project Manager" refers to the Owner's duly authorized
representative and shall mean the Division Administrator or Department Director, as applicable,
acting directly or through duly authorized representatives.
B. Liquidated Damages in General.
Owner and Contractor recognize that, since time is of the essence for this Agreement, Ownerwill
suffer financial loss if Contractor fails to achieve Substantial Completion within the time specified
above, as said time may be adjusted as provided for herein. In such event, the total amount of
Owner's damages, will be difficult, if not impossible, to definitely ascertain and quantify. Should
Contractor fail to achieve Substantial Completion within the number of calendar days established
herein, Owner shall be entitled to assess, as liquidated damages, but not as a penalty, One
Thousand Five Hundred and Eighty -Four Dollars ($1,584.00) for each calendar day
thereafter until Substantial Completion is achieved. Further, in the event Substantial
Completion is reached, but the Contractor fails to reach Final Completion within the required
time period, Owner shall also be entitled to assess and Contractor shall be liable for all actual
damages incurred by Owner as a result of Contractor failing to timely achieve Final Completion,
The Project shall be deemed to be substantially completed on the date the Project Manager (or
at his/her direction, the Design Professional) issues a Certificate of Substantial Completion
pursuant to the terms hereof. Contractor hereby expressly waives and relinquishes any right
which it may have to seek to characterize the above noted liquidated damages as a
penalty, which the parties agree represents a fair and reasonable estimate of the Owner's
actual damages at the time of contracting if Contractor fails to Substantially or Finally
Complete the Work within the required time periods.
z ��7
Conslrucllon Services Agreement: Revised 022018
C. Computation of Time Periods.
When any period of time is referenced by days herein, it shall be computed to exclude the first
day and include the last day of such period, If the last day of any such period falls on a Saturday
or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day
shall be omitted from the computation, and the last day shall become the next succeeding day
which is not a Saturday, Sunday or legal holiday.
D. Determination of Number of Days of Default.
For all contracts, regardless of whether the Contract Time is stipulated in calendar days or working
days, the Owner will countdefault days in calendar days.
E. Right of Collection.
The Owner has the right to apply any amounts due Contractor under this Agreement or any other
agreement between Owner and Contractor, as payment on such liquidated damages due under
this Agreement in Owner's sole discretion. Notwithstanding anything herein to the contrary,
Owner retains its right to liquidated damages due under this Agreement even if Contractor, at
Owner's election and in its sole discretion, is allowed to continue and to finish the Work, or any
part of it, after the expiration of the Contract Time including granted time extensions.
F. Completion of Work by Owner.
In the event Contractor defaults on any of its obligations under the Agreement and Owner elects
to complete the Work, in whale or in part, through another contractor or its own forces, the
Contractor and its surety shall continue to be liable for the liquidated damages under the
Agreement until Owner achieves Substantial and Final Completion of the Work. Owner will not
charge liquidated damages for any delay in achieving Substantial or Final Completion as a result
of any unreasonable action or delay on the part of the Owner.
G. Final Acceptance by Owner.
The Owner shall consider the Agreement complete when the Contractor has completed in its
entirety all of the Work and the Owner has accepted all of the Work and notified the Contractor in
writing that the Work is complete. Once the Owner has approved and accepted the Work,
Contractor shall be entitled to final payment in accordance with the terms of the Contract
Documents.
H. Recovery of Damages Suffered by Third Parties.
Contractor shall be liable to Owner to the extent Owner incurs damages from a third party as a
result of Contractor's failure to fulfill all of its obligations under the Contract Documents. Owner's
recovery of any delay related damages under this Agreement through the liquidated damages
does not preclude Owner from recovering from Contractor any other non -delay related damages
that may be owed to it arising out of or relating to this Agreement.
Section 6. Exhibits Incorporated.
Exhibits Incorporated: The following documents are expressly agreed upon, attached hereto and
made a part of this Agreement for Solicitation 18-7267 Lely Branch Canal Weir.
Exhibit A-1: Contractor's laid Schedule
Exhibit A-2: Contractor's Bid Submittal Forms and Addendums
E=xhibit A-3: Contractor's List of Key Personnel
Exhibit B-1; Payment Bond Forms
Exhibit B-2: Performance Bond Forms
Exhibit B-3: Insurance Requirements
3
Consiruction Services Agreement: Revised 022018
Exhibit C: Release and Affidavit Form
Exhibit D: Contractor Application for Payment Form
Exhibit E: Change Order Form
Exhibit F: Certificate of Substantial Completion Form
Exhibit G: Final Payment Checklist
Exhibit H: General Terms and Conditions
Exhibit I; Supplemental Terms and Conditions ® Applicable El Not Applicable
The following documents are expressly agreed to be incorporated by reference and made a part
of this Agreement for Solicitation 18-7267 Lely Branch Canal Weir, The complete contract
documents, including Addendum with attachments, are available on the County's on-line
bidding system: https,//www.bidsyne.com/bids.yne-cas , which the parties agree
comprise the final integrated agreement executed by the parties.
Sections corresponding to any checked box ( ® ) expressly apply to the terms of this
Agreement and are available through the County's on-line bidding system.
®Exhibit J: Technical Specifications
®Exhibit K: Permits
®Exhibit L: Standard Details
®Exhibit M: Plans and Specifications prepared by Agnoli Barber & Brundage, Inc.
and identified as follows: 18-7267 Plans (Civil) and 18-7267 Plans (Weir)
as shown on flan Sheets 1 through 12,
Section 7. Notices
A. All notices required or made pursuant to this Agreement by the Contractor to the Owner
shall be shall be deemed duly served if delivered by U.S. Mail, E-mail or Facsimile, addressed to
the following:
Collier County Board of County Commissioners, Florida
c/o Capital Projects Planning, Impact Fees & Program Management
2685 S. Horseshoe Drive, Unit 103
Naples, Florida 34104
Attention: Ananta Nath, Project Manager
Phone: (239) 252-6048
Email: Ona ta.Nath@golliercountyfl..g�y
B. All notices required or made pursuant to this Agreement by Owner to Contractor shall be
made in writing and shall be deemed duly served if delivered by U.S. Mail, E-mail or Facsimile,
addressed to the following:
Coastal Concrete Products, LLC dba Coastal Site Development
7742 Aliso Road
Fort Myers, FL 33912
Attention: David E. Torres, Manager
Phone: (239) 208-4079
Email: Dtorresecoastalconereteprod,coati
4
Construollon Services Agreement: Revised 022018
C. Either party may change its above noted address by giving written notice to the other party
in accordance with the requirements of this Section.
Section 8. PUBLIC (ENTITY CRIMES.
8.1 By its execution of this Contract, Construction Contractor acknowledges that it has been
informed by Owner of the terms of Section 287.133(2)(a) of the Florida Statutes which read as
follows:
"A person or affiliate who has been placed on the convicted vendor list following
a conviction for a public entity crime may not submit a bid on a contract to provide
any goods or services to a public entity for the construction or repair of a public
building or public work, may not submit bids on leases of real property to a public
entity, may not be awarded or perform work as a contractor, supplier,
subcontractor, or consultant under a contract with any public entity in excess of
the threshold amount provided in s. 257.017 for CATEGORY TWO for a period of
36 months from the date of being placed on the convicted vendor list."
Section 9. Modification.
No modification or change to the Agreement shall be valid or binding upon the parties unless in
writing and executed by the party or parties intended to be bound by it.
Section 10. Successors and Assicins.
Subject to other provisions hereof, the Agreement shall be binding upon and shall inure to the
benefit of the successors and assigns of the parties to the Agreement,
Section 11. Governina t.aw.
The Agreement shall be interpreted under and its performance governed by the laws of the State
of Florida.
Section 12. No Waiver.
The failure of the Owner to enforce at any time or for any period of time any one or more of the
provisions of the Agreement shall not be construed to be and shall not be a waiver of any such
provision or provisions or of its right thereafter to enforce each and every such provision.
Section 13. Entire Agreement.
Each of the parties hereto agrees and represents that the Agreement comprises the full and entire
agreement between the parties affecting the Work contemplated, and no other agreement or
understanding of any nature concerning the same has been entered into or will be recognized,
and that all negotiations, acts, work performed, or payments made prior to the execution hereof
shall be deemed merged in, integrated and superseded by the Agreement.
Section 14. Severability.
Should any provision of the Agreement be determined by a court to be unenforceable, such a
determination shall not affect the validity or enforceability of any other section or part thereof.
O
s
Constrvelion Services Agreement Revised 022018
Section 15. Channe Order Authorization.
The Project Manager shall have the authority on behalf of the Ownerto execute all Change Orders
and Work Directive Changes to the Agreement to the extent provided for under the Owner's
procurement ordinance and policies and accompanying administrative procedures.
Section 16. Construction.
Any doubtful or ambiguous language contained in this Agreement shall not be construed against
the party who physically prepared this Agreement. The rule sometimes referred to as "fortius
contra proferentum (pursuant to which ambiguities in a contractual term which appears on its
face to have been inserted for the benefit of one of the parties shall be construed against the
benefited party) shall not be applied to the construction of this Agreement.
Section 17. Order of Precedence
In the event of any conflict between or among the terms of any of the Contract Documents, the
terms of the Construction Agreement and the General Terms and Conditions shall take
precedence over the terms of all other Contract Documents, except the terms of any
Supplemental Conditions shall take precedence over the Construction Agreement and the
General Terms and Conditions. To the extent any conflict in the terms of the Contract Documents
including the Owner's Board approved Executive Summary cannot be resolved by application of
the Supplemental Conditions, if any, or the Construction Agreement and the General Terms and
Conditions, the conflict shall be resolved by imposing the more strict or costly obligation under
the Contract Documents upon the Contractor at Owner's discretion_
a
Constructlon Services Agreement: Revised 022018
IN WITNESS WHEREOF, the parties have executed this Agreement on the date(s)
indicated below.
TWO WITNESSES:
Nkt,&9: Llklhl�
FIRST WITNESS
116 hw�Z�14
rint Name
OND WITNESS
Print Name
Date:
ATTEST:
Dwight E. Brock, Clerk
BY:
Approved as to Form and Legality:
Assistant County Attorney
Print Name
CONTRACTOR:
Coastal Concrete Products, LLC dba
Coastal Sv o
M
By: 7
,.
t� i✓ v 5-YYal1(IAGi,QX LA -5- I
Print Name and Title Date
OWNER:
BOARD OF COUNTY COMMISSIONERS
OF COLLIER COUNTY FLORIDA
BY:
Andy Solis Date
Chairman
Construction Services Agreement: Revised 022DIO
Q�
EXHIBIT A-1: CONTRACTOR'S BID SCHEDULE
(FOLLOWING THIS PAGE)
B
Construction $grVlCes Agreement' Revised 022018 %
Attachement A - Bid Schedule
18-7267 - Lely Branch Canal Weir
Item No.
Desert bon
Unu
uuulil y
Unll Cast
Total Cast
I
MOBILIZATION
LS
1
$42,S00.00
$42,500,00
2
PROVIt)EIMAINTAIN AS-SUILT PLATES
LS
1
1
$5,000.00
S5,000.0
3
PI;OVTDI; CONSTRUCTION SURVEYING AND LAYOUT
I.S
$5,0)0-00
SS 000.00
4
MAINTENANCE OF TRAFFIC
LS
1
$7 500,00
$7 500,40
5
CLEARING AND GRU1BBTNG
L$
I
$12,50D.00
$12,500,00
6
EROSION CONTROL
LS
1
$7.5001.00
$7.500,00
1
CANAL GRADING AND REWORKGA13IONS
L$
I
$250100.00
525000.00
e
PARKING LOT RESTORATION
LS
1
S18,00 .0
$18,000,00
9
10
FENCING BLACK CLAD VINYL COATED C>IAIN LINKS HIGH
FENCE GATE SLACK CLAD YINYt, 0A,rED CHAIN LINK SINGLE 6' HIGH 6 WIDE]
LP
FA
20
1
$180100
$400.00
$3,600.00
3400.0
I I
RIP RAPRUI313LF. BANK & SHORE)(3011 THICK INCLUDES BEDDING STONE
CY
140
$150.00
$21,000.0.0
12
13
to
15
IG
17
1pEKFF,0MANCE 1 -URF BAHIA INCLUDES WATFR FERTIT.IZER & MOWING SY 220
WEIR CONTROL STRUCTURE WITH OATES INCLUDES HANDRAIL AND PILING LS 1
a^ PORCEMAIN RELOCATION LS 1
PROJECT INFORMATION SIGN EA 2
IDIXAINAGE ALLOWANCE FIXED I
PRUJECI"j'OTAI
$4,00
$250,000.00
S12,500.00
S1,500.00
$30 000.00
$880.00
$730 NO -CD
$12.500.00
$3,D00-00
$30.000,00
$444,380,00
EXHIBIT A-2: CONTRACTOR'S BID SUBMITTAL FORMS AND ADDENDUM
(FOLLOWING THIS PAGE)
9
Construction Services Agreement: Revised 022018
HID RESPONSE FORM
BOARD OF COUNTY COMMISSIONERS
COLLIER COUNTY, FLORIDA
Lely Branch Canal Weir
RID NO. I8-7267
Full Name ofBiddet'. Coastal Concrete lrroducts, LLC dha Coastal Site L7eueloprnPIIt
Main Business Address 7747 Alio Road Fort Myers, 1 33912
Place of Business _.7742 Alico Road, Fort Myers, FL 33912
Telephone No. 239,298,4Q79 No. 239_334.1399
State Contractor's License #
State of Florida Certificate of Authority Document Number- l 100001 Q7Ez
Federal 'Fax Identification Number 27-3688614
DUNS # CCR# Cage Code
To: BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA
(hereinafter called the Owner)
The undersigned, as Bidder declares that the only person or parties interested in this Bid as principals are those
named herein, that this Bid is submitted without collusion with any other person, firm or corporation; that it has
carefully examined the location of the proposed Work, the proposed form of Agreement and all otter Contract
Documents and Bonds, and the Contract Drawings and Specifications.
Bidder proposes, and agrees if this Bid is accepted, Bidder will execute the Agreement included in the Bidding
Documents, to provide all necessary machinery, [acts, apparatus and other means of construction, including utility
and transportation services necessary to do all the Work, and furnish all the materials and equipment specified or
referred to in the Contract Documents N the manner and time herein prescribed and according to the requirements of
the Owner as therein set forth, furnish the Contractor's Bonds and Insurance specified in the General Conditions of
the Contract, and to do all other things required of the Contractor by the Contract Documents, and that it will take
full payment the sums set forth in the following Bid Schedule;
Unit prices shall be provided in no more than two decimal points, and in the case where further decimal
points are inadvertently provided, rounding to two decimal points will be Conducted by Procurement Services
Division staff.
MATERIAL MANUFACTURERS
THIS FORM MUST BE COMPLETED OR BID SHALL BE DEEMED NON-RESPONSIVE
All Bidders shall confirm by signature that they will provide the manufacturers and materials outlined in this Bid
specifications, including compliance with Florida Statute 255.20 to provide lumber, timber and other forest products
produced and manufactured in the State of Florida as long as the price, Fitness and quality are equal. Exceptions
(when equals are acceptable) may he requested by completing the Material Manufacturer Exception List below. If
an exception for a manufacturer and/or material is proposed and listed below and is not approved by
Engineer/Project Manager, Bidder shall furnish the manufacturer named in the specification. Acceptance of this
forth does not constitute acceptance of material proposed on this list,
Complete and sign section A QR B.
Section AI (Acceptance of all manufactures and materials in Bid specifications)
On behalf of my firm, I confirm that we will use all manufacturers and materials as specifically outlined in
the Bid specifications.
Company;
Signature:
E. Torres- Manager Date: _t}21IG/I8_
Section B (Exception regt6ded to Bid specifications manufacturers and materials)
EXCEPTIQN M,6TERIAL >,,X1 ]1 PTION MAIL IJEA U}
1.
2.
3,
4.
5.
Please insert additional pages as necessary.
Company: — CQustal Concrete, Prodnots. LLC &a Coastal Silo, Dovelgpment
F_ Torres -Manager Date U2/16i`i$
0
LIST OF MAJOR SUBCONTRACTORS
THIS LIST MUST BE COMPLETED OR BID MAY BE DEEMED NON-RESPONSIVE
The undersigned states that the following is a list of the proposed subcontractors for the major categories outlined in
the requirements of the Bid specifications,
The undersigned acknowledges its responsibility for ensuring that the Subcontractors for the [Hajar categories listed
herein avr "qualified" (as defined in Ordinance 2017-05 and Section 15 of Instructions to Bidders) and meet all legal
requirements applicable to and necessitated by the Contract Documents, including, but not limited to propel`
licenses, certifications, registrations and insurance coverage. The Owner reserves the right to disqualify any Bidder
who includes non-compliant or non-qualified Subcontractors in its bid offer. Further, the Owner may direct the
Successful Bidder to remove/replace any Subcontractor, at no additional cost to Owner, which is found to be non-
compliant with this requirement either before or after the issuance of the Award of Contract by Owner. (Attach
additional sheets as needed), Further, the undersigned aclutowledges and agrees that promptly after the Award of
Contract, and in accordance with the requirements of the Contract Documents, the Successful Bidder shall identify
all Subcontractors it intends to use on the Project. The undersigned further agrees that all Subcontractors
subsequently identified for any portion of work on this Project must be qualified as noted above.
Major Category of Work
Subcontractor and Address
1. Electrical
_
2. Mechanical
3. Plumbing
d. Site Work
_
5. Identify other subcontractors
that represent more than 10%
of price or that affect the
critical path of the schedule
To be determined
Company:
Signature:
3gor Date: U2l16118
0
STATEMENT OF EXPERIENCE OF BIDDER
The Bidder is required to slate below what work of similar magnitude completed within the last tine (5) years is a
judge of its experience, skill and business standing and of
its ability to conduct the work as completely and as
rapidly as required under the terms of the Agreement.
Prgiect. prid Lgpation
Reference (include phone # or cmjil_uddress)
Roadway Extension, Utilities & Drainage of
Terry Cole— Hole Montes
Rattlesnake Hammock Road, Naples, FL
239-254-2024
2. Sabal Palm Culverts & drainage on Sabal
Emilio Robau — Robau and Associates
Palm Road, Naples, FL
239.206.8044
3. Roadway Extension, Utilities & Drainage of
Nick Kouloheras-- Habitat for Humanity of
Woodcrest Drive in Naples, Its.
Collier County 239.438.0934
4. Sidewalk & Drainage Improvement
Tim Pinter and Mike Daniels — City of
Project -Various Location in Marco Island
Marco Island 239.384.3970
g, Roadway Extension, Utilities & Drainage of
Nielt Kouloheras —Habitat for Humanity of
Faith landing in Immokalee, FL
Collier County 239.438.0934
Cypress Way East Sidewalk Improvement
Shgnnon Bassett—Collier County
Project, Naples, FL
239.253.3170
Company:. Coastal Concrete Products, LLC dba CnastajeLDevelopment
Signature:
David B. Torres - Manager Date: 02/ 61 f 1�
(a
TRENCR SArETY ACT
Bidder acknowledges that included in the various items of the bid and in the Total Bid Price are costs for complying with the
Florida, Trench Safety Act (90-96, Laws of Florida) effective October 1, 1490. The Bidder further identifies the cost to be
summarized below:
Trench Safety Units of
Unit Unit
Extended C.�
Measure Measure
fDescriAka (LF.SY)
(QuantiW (Cost
Overall Trench LS
Safety
1,
1
Q
2.
3.
4.
5.
- -
TOTAL $
Failure to complete the above may result in the Bid being declared non-responsive.
Company.
Signature:
Ir Dake: 02/16/18
0
DID BOND
KNOW ALL MEN BY THESE PkE3ENTS, tl
(herein after
Philadelohla Inderrinily Insurance Company_- , (herein o;
existing under the laws of the State of
and authorized to do lausincas In the s
f1mily bound unto the, Colll.er County
in the full and just sum of Five Percent of Amount Bid
good end lawful money of the United States of America, to bo pa
well and truly to be made, the Principal and the Surety bind there
and assigns, jointly and severally and firmly by those presents.
Whom^ the Principal is about to submit, or has submitted to the
equipment and Incidentals necasaary to Nrnlsh, install, and fully
No. 18.7267 Lely Branch Canal Weir.
NOW, THEREFORE, if the Owner shall accept the lid of the PRIM'
required Agreemant with the Owner and within ten days after the date
the terms of such Bid, and give such band or bonds in an ainoum of 14
Bidding Documents or Contract Documents with good and suffici
Agreement and €br the prompt payment of labor+ materials and suppl[
event of the failure of the PRINCJPA4 to enter Into such Agresmen
Owner the Tcqulred certificates of insurance, if the PRINCIPAL
$__ -. -_ noted above as liquidated damages, and not as a I
then this obligation shall be null and veld, otherwise to remaln in full f
Flve Percent (5%) of Amouni Old
IN TESTIMONY Thereof, the Principal and Surety hava caused tl
18th day of February _, 2018 ,
we Coastal Concrete ProducM._LLQ
led the Principal) and
the Surety), a corporation chartered and
h Its principal offices in tho city of
of Florida are held and
(hereinafter called the Owner),
dollars ($ 8% of Amount Bid }
an demand of the Owner, to which payment
;s, their heirs, and executors, administrators,
, a Bid for furnishing ail labor, materials,
le the Work on the Project known as Did
[PAL and the PRTNCIPAL shall enter into the
Fe written Notice of Await in.accordanee with
%a the total Contract Amount as specified In the
at surety fbr the faithful performance of the
I furnished in the prosecurion thereof or, in the
or to give such bond or bonds, and deliver to
call pay to the OBLIGEI; the fixed sum
fnaity, as provided in thi Bidding J�cagm t )„u
ce and effect.
se presents to be duly signed and. ed this 1 ”
principel
A
(Seal)
f
Lmol Resident Producing Agent For Alter-}SijWtr.Group- Inc.
Surety.
0
99
PHILADELPHIA INDEMNITY INSURANCE COMPANY
One Bala Plaza, Suite 100
[talc Cydwyd, PA 19004.0950
Power of Attorney
KNOW ALL PERSONS BY THESE PRRSENTS: That PHILADELPHIA INDEMNITY INSURANCE COMPANY (the Company), a corporation organised and
existing under the laws of the Cominonwealth of Pennsylvania, docs hereby co lstinlle and appoint David T. Sating, Warren M. Alter and Jonathan A, Bursevich of
Alter Surety Groun, Inc,. its true and lawful Attorney-in-fhot with full eatllnrity to execute on its behalf bends, undertakings, tecognixances and other eoatraots of
indemnity and wrttipps obligatory in the nature thereof, issued in the course of its business wrd to bind the Company thereby, in an Amount not to exceed 5.000.D04.
This Power of Atioracy is granted and is sighed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directom of
PHILADELPHIA INDEMNITY INSURANCE COMPANY on the ld'h of November, 2016.
RESOLVED: 'T'haI the Board of Dircctora hereby authorizes the President or any Vice President of the
Company: (t) Appoint Attorney(3) in Fact and authori2e die Anorney(s) in Piet to
execute on behalf of the Company bands and undertakings, contracts of indemnity and
other writings obligatory in the nature thereof and to attach die seal of the Company
tbccto; and (2) to remove, at any time, Any such Attorney -in -pact and revoke the
authority given. And, be it
FUPTHER
RESOLVE 13, That the signatures of such officers and the seal of the Company may be affixed to any
such Power of Aftorrrey or certificate relating thereto by facsimile, and any such Power of
Attorney to exceuted and certified by facsimile signatures and fhcsirnile seal shall be
Valid and binding upon the Company in ft future with respect to any bond or
undertaking to which it is attached,
1N TESTIMONY WHEREOF, P141LADELPHIA INDEMNITY INSURANCE COMPANY HAS CAUSED THIS INSTRUMENT TO BE SIONeD AND ITS
CORPORATE S13ALTO BE AFFIXED By ITS AUTHORIZED OPPICE THIS 27TH DAY OF OCTOBER, 2017.
...............
r.YA gip•"r.,�F __
5 I ^a
Edward $oyago, Corporate Secretary
PHILADELPHIA INDEMNITY INSURANCE COMPANY
Robert A, O'Leary Jr„ President & CEO
Philadelphia Indemnity Insurance Company
On this 27°h day of October, 2017, before me came the individual wba executed the prcccding inairurnernt, to me personally known, and being by me duly swoni said
that he is the therein described and authorized officer of the PHILADELPHIA ]INDEMNITY INSURANCE COMPANY; that the sent affixed to said instrument is
the Corporate seal ofsaid Company; that the said Corporate Seal and his signature were duly Affixed.
r
xis
Notary Public:
ra�.rivsm�r++ryry.ww cw+ry
hly C9mmY,riu l.pn., #�1,7 A'��
hlt>i�Nfi Rtlk
residing at:
(Notary Seal)
My commission expires:
,S ,lc rieruber 25, 2021
1. Edward Sayago, Corporate Secretary of PHILADELPHIA INDEMNITY INSURANCE COMPANY, do hereby certil� that the foregoing resolution of the Board of
Directors and this Power of Attorney issued pursuant thereto on this 27'' day of October, 2017 are true and correct and arc still in full force and cf%ct. 1 do further
certify that Robert D, O'Leary Jr., who executed the Power of Attomay os President, waa on the date of execution of tha attached Power of Attorney the duly elected
President of PHILADELPH (A ]NDEMNTTY INSURANCE COMPANY.
February
In TesliimtTy-fttre&-1 bolia subscribed my name and affixed the facsimile seal of each Company this U (YCbay of-, 20
..
�.'t�44j9
r.YA gip•"r.,�F __
5 I ^a
Edward $oyago, Corporate Secretary
PHILADELPHIA INDEMNITY INSURANCE COMPANY
Q)
Upon notification that its Bid has been awarded, the Sucoessful Bidder will execute the Agreement form attached to
the Bidding Documents within ten (10) calendar clays and deliver the Surety Bond or Bonds and Insurance
Certdficates as r'equit'ed by the Contract Documents. The bid security attached is to become the property of the
Owner in the event the Agreement, Insurance Certificates and Bonds are not executed and delivered to Owner
within the time above set forth, as liquidated damages, for the delay and additional expense to the Owner, it being
recognized that, since time is of the essence, Owner will suffer financial loss if the Successful Bidder fails to execute
and deliver to Owner the required Agreement, Insurance Certificates and Bonds within the required time period. In
the event of such failure, the total amount of Owner's damages, will be difficult, if not impossible, to definitely
ascertain and quantify. It is hereby agreed that it is appropriate and fair that Owner receive liquidated damages fi,om
the Successful Bidder in the event it fails to execute and deliver the Agreement, insurance Certificates, and Bonds as
required hereunder. The Successful Bidder hereby expressly waives and relinquishes any right which it may have to
seek to characterize the above noted liquidated damages as a penalty, which the parties agree represents a fair and
reasonable estimate of Owner's actual damages at the time of bidding if the Successful Bidder fails to execute and
deliver the Agreement, insurance Certificates, and Bonds in a timely manner,
Upon receipt of the signed and approved agreement and Purchase Order, the undersigned proposes to commence
work at the site within five (5) calendar days from the commencement date stipulated in the written Notice to
Proceed unless the Project Manager, in writing, subsequently notifies the Contractor of a modified (later)
cominencement date. The undersigned further agrees to substantially complete all work covered by this Bid within
one hundred and twenty (120) consecutive calendar days, computed by excluding the commencement date and
including the last day of such period, and to be fully completed to the point of final acceptance by the Owner within
Ninety (90) consecutive calendar days after Substantial Completion, computed by excluding commencement date
and including the last day of such period.
Respectfully Submitted:
Slate of FLOIRJDA
County of IEEE
David E Tones , being first duly sworn on oath deposes and says that
the Bidder on the above Bid is organized as indicated and that all statements herein made are made on behalf of such
Bidder and that this deponent is authorized to make them.
David E. T also deposes and says that it has examined and carefully
prepared its Bid from the Bidding Documents, including the Contract Drawings and Specifications and has checked
the same in detail before submitting this Bid; that the statements contained herein are true and correct.
(a) Co��2ratiQr�
The Bidder is a corporation organized and existing under the laws of the State of , which operates
under the legal name of and the full names of its officers
are as follows:
Secretary.
Treasurer
Manager_
'The
is authorized to sign construction bids and contracts for the
company by action of its Board of Directors taken a certified copy of which is
hereto attached (strike out this last sentence if not applicable).
(b) 92-21 r hi
The Bidder is a co -partnership consisting of individual partners whose full names arc as follows:
David E. Torres via Revocable Trust
George P. Bauer via Revocable Trust
The co -partnership does business under the legal name of-
Coastal
f:Coast I C n e Products, LLC
0
(c) Individual a
The Ridder is an individual whose full. name is and if operating ti J4>,a
mm
trach nae, said trade nae is
Complete For information contained in (a) Corporation, (b) Co -Partnership or (c) Individual From previus, 9V
Coastal
Coastal Concrete products, LLC dba .
STATE OF t �'
COUNTY OF
' foregoi g instrument was acknowledged
s personal) a or has produced
dentification and did (did not) take an oath.
My Commission Expu,es:
(AFFIX OFFICIAL SEAW
r Nbtary pob1t4 slate 01 Florida
ro
MBdtaa A9uter
� EMpirei 2169120 y' 145958
Coastal STtQ Development
LEgal Entity
BY: 2mdd E. T 1Tes
Name of Bidder (Typed)
Signature
ana r ye���
Title
before me this RC day of •-- , 24 f by
of
L c oratio , on ifehalf of the colporati n, lie he
as
NAME:
(Legibly Primed)
Notary Public, State of qpeA..
Commission No.;1 X4,14 --sl s
0
Coy le -r Country
Administrmve Services Deparhent
Provuremenl Servim Dmvi an
FORM 10- VENDOR DECLARNNON STATEMCNT
BOARD OF COUNTY COMMISSIONERS
Collier Cou n ty Government Complex
Naples, Florida 34112
Dear Commissioners:
The undersigned, as Vendor declares that this response is made without connection or arrangement with any uthcr person and this
proposal is in every respect fair and made In good Faith, without collusion or fi•aud.
The Vendor agrees, if this solicitation submittal is accepted, to execute a Collier County document for the purpose of establishing a
formal contractual relationship between the film and Collier County, for the performance of all requirements to which the solicitation
pertains. The Vendor states that the submitted is based upon the documents listed by the above referenced Solicitation. Further, the
vendor agrees that If awarded a contract fpr these goods and/or services, tite vendor will not be eligible to compete, submit a
proposal, be awarded, or perform as a sub -vendor for any future associated with work that is a result of this awarded contract.
IN WITNESS WHEREOF, WE have hereunto subscribed our names on this IS
mday of 0 T%,X 2012 in the County of
A e e- , in the State of AIo r d ok ,
F'irm's Legal Name: S'I-z� � (a -,c re- 4r- ?,-9d v c-�5 tL Cr �t g .fir, S
Address: L( M, C, o
City, State, Zip Code: 6'- S, '-f --3 c t
Florida Certificate of
Authority Document
Number
Federal Tax
Identification Number
*CCR 4 or CAGE Code
*Only if Grant Funded
Telephone:
Signature by:
(Typed and written)
Titie:
j_ 10000 fo-�-s` }
0
4��
Additional Contact Information
Send payments to:
S 4 v-%e- Os 0 -6,r-,P—
(required if different from
Company name used as payee
above)
Contact name:
Title:
Address:
City, State, ZIP
Telephone:
Email:
Office servicing Collier
��� �'� � �"� � a v
County to place orders
(required if dirferent from
above)
Contact name:
Title:
Address:
City, State, ZIP
Telephone:
Email:
140 CL
Secondary Contact for this
Solicitation:
Email:
�r
{�C 0� i c% c� L4o�s4c1� CO %^C.lre_ 4e c , C c� r`n
Phone:
- — 2. D °6 L( U
4��
Coler C014V ty
AdminlsiraWe SeWes Departmant
PfOWmmehl SONres Divisloh
FORM I I - IMMIGRATION AFFIDAVIT CERTIFICATION
This Affidavit is required and should be signed, notarized by an authorized principal of the firm and submitted with formal solicitation
submittals. Further, Vendors are required to enroll in the E -Verify program, and provide acceptable evidence of their enrollment, at
the time of the submission of the Vendor's proposal. Acceptable evidence consists of a copy of the properly completed E -Verify
Company Profile page ora copy of the fully executed E -Verify Memorandum of Understanding for the company. Failure to include
this Affidavit and gggeptalile evidenee of enrollment in the E-VeriF )r gram m deem the Vendor's Proposal as non-
responsive.
Collier County will not intentionally award County contracts to any Vendor who knowingly employs unautliorized alien workers,
constituting a violation of the employment provision contained in 8 U.S.C. Section 132.4 a(e) Section 274A(e) of the Immigration
and Nationality Act ("INA").
Collier County may consider the employment by any Vendor of unauthorized aliens a violation of Section 274A (e) of the INA. Such
Violation by the recipient of the Employment Provisions contained In Section 274A (e) of the INA shall be grounds for unilateral
termination of the contract by Collier County.
Vendor attests that they are fully compliant with all applicable immigration laws (specifically to the 1986 Immigration Act and
subsequent Amendment(s)) and agrees to comply with the provisions of the Memorandum of Understanding with E -Verify and to
provide proof ofenrollment in The Employment Eligibility Verification System (E -Verify), operated by the Department of Homeland
Security in partnership with the Social Security Administration at the time of submission of the Vendor's proposal.
Company Narre +j�r-( CoINC 1-0-�C- pro,�vc' 't -C )(,4 ce,r', a1 i�P— fi
Print Name
Signature
State of
Comity of
titleC�' '
Date 3 11 rh g.
The signee of these Affidavit guarantees, as evidenced by the sworn affidavit required herein, the truth and accuracy ofthis
affidavit to interrogatories hereinafter made.
C:ommissian No.:
(a
Cner C¢r��tt�y
AdminMra6ve 5ervlccs pep��ev�l
p�tturameM 9wwx� Tiemion
FORM 12 - VENDOR SUASTITUTC W - 9
Request for Taxpayer Identification Number and Certification
In accordance with the Internal Revenue Service regulations, Collier County is required to collect the following information
for tax reporting purposes fi•om individuals and companies who do business with the County (including social security numbers
if used by the individual or company for tax reporting purposes). Florida Statute 119,671(5) requires that the county
notify you in writing of the reason for collecting this information, which will be used for no other purpose than herein stated.
Please complete all information that applies to your business and return with your quote nr proposal,
1. General information (provide all inforntation)
Taxpayer Name ce�� Canc-ce }e
(as shown on Income tax return)
Business Name (if dr, j,�ererr(from taxpay r name]
Address -4--)-`t z- �ftlt c -- _
State
TIZ—
City,
ZiD -.-,3'36N, \-'�-
Telephone Emailcr�s�Co``-
Order Information (Must be filled out) Remit f Payment Information (Must be filled out)
Address �i?- ktC e—o Address t"Z- M' -C o Q-.�
City -F-�State Zip `� L
Email ry c~ c�+cis�l�or�cfee�,�
2. Company Status (check only one)
City 'T�- S state 'F1--• Zip 33•, v2 -
Email G t i u
C�-"a<-lv tt'e—
,Individual 1 We Proprietor
Corporation
_Partnership
_Tax Exempt (Federal income tax-exempt entity
Limited Liability Company
under Internal Revenue Service guidelines IRC
Enter the tax classification
(D = Disregm ded Entity, C = Corporation. P - Partnership)
3. Taxpayer Identification Number (for tax reportrngptrrposes only)
Federal Tax Identification Number (TIN) p2 4 ' IS6 8 FS (j l
(Vendors_wlto do not have a TIN, will be required to provide a social security number prior to an award),
A. Sign and Date Form: Certifiention:
Under enalties offleriurv, t Cereify that th fn orn tro i.ApwynI m is Correct to nay knowled e.
Signature
Date
51') G 7 t r+r•e
Title -�
Po t'
Phone Number
840±f
ME
FORM 13 - OR)DERS CHECKLIST
1l1+11'ORTANI: Please read carefully, sign in the spaces indicated and return with your Bid. Bidder should
check off each of the following iterns as the necessary action is completed,
The Bid has been signed,
2. The Bid prices offered have been reviewed.
3. The price extensions and totals have been checked,
4. Bid Schedule has been completed and attached.
5. Any required drawings, descriptive literature, etc, have been included.
6. Any delivery information required is included.
7. The following on-line standard documents have been reviewed in Bidsync:
1. Construction bid instructions form
2, Construction services agreement
3. Purchase order terms and conditions
9. All of the following bid forms have been 7. Bid Bond Fonn (Form 7)
completed and signed: 8. Insurance and Bonding Requirements (Form 8)
I. Bid Form (Form 1) 9. Conflict of Interest Affidavit (Form 9)
2, Contractors Key Personnel (Form 2) 10. Vendor Declaration Statement (Form
3. Material Manufacturers (Form 3) 10)
4. List of Major Subcontractors (Form 4) 11. Immigration Law Affidavit
5. Statement of Experience (Form 5) Certification (Form l 1)
6, 'French Safety Act (Form 6) 12, Vendor Substitute W-9 (Form 12)
9, Bidders Checklist (Form 13 — this farm)opies of required infannatlon have been attached
1. Company's E -Verify proFle page or memorandum of understanding
2. Certificate of Authority to Conduct Business in State of Florida
3. Any required professional licenses — valid and current
(ie: General Contractors license, Underground Utility and Excavation, Builders,
Trade Contractors, etc., as applicable, requested and/or required.)
10, if required, the amount of Bid bond has been checked, and the Bid bond or cashier's check has been
submitted.
11. Any addenda have been signed and acknowledgement form attached and included.
12. The Bid will be uploaded in time to be received no later than the specified gp�Uin& date and time, otherwise
the Bid cannot be considered.
Coo s, +a �.'t) � r t -L rJ o . c: a 51
Bidder Name'"
d v l �[ 5o rpt e.•
Date -3 1 t
(a
STATE OF FLORIDA
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION
CONSTRUCTION INDUSTRY LICENSING BOARD
CCyC151p4[i4
The GENERAL CONTRA07OR
Named below IS CERTIFIED
Under the provisions of Chapter 489 FS,
Expiration date: AUG 31, 2018
TORRES, DAVID ELIAS
COASTAL CONCRETE PRODUCTS, LLC
7742 AUCQ RO
FLIRT MYERS FL 33912
ISSUEO: os11o12018 DISPLAYAS REQUIRED BY LAW
$E011 L16D8100001769
0
—Ve r em - 4
Company ID Number: 422570
To be accepted as a participant in I -Verify, you should only sign the Employaw s Sectian
of the signature page. It you have any queations, contact 5-Verifij at 888.4$4.4210.
Pegg 12 of 13 1 E -Verify MQU for EMPIOVer i RCV19tOn DIM 491[71M wm.dho, UOV1r-XOYity
(a
WWI
sl r,.yGrt.•1WI NI11
Company 1D Number: 422670
Nofth American 111cJtisify
CIO-OfIcallon Systems
Code
of EmOOYoes: P to 4
Number of Sites Verified
for;
ire you rrerilPwing for more khaa I site? if #os, pleme provide the numbe - of s1<tes verlfWd fog'
each State:
o VLOAIDA
I sitc(s)
t1�x rl�.��Rrairl rogntinq to tato Program AdMIPIRf. OOT(SO fOy YOUt CaMpany On 1pollolf
questions or aperatfonM problems'
Maroc;
Tclghoda Mmber:
David E Torres
(239) 263 � 9700 Fax Number: 03'9) 263 -1058
F,niall Address:
tltorres rt oodtrfalconeY4teprod.cum
Name:
Teluphona Num#er:
Clin�'loEte M 1Vullcup
(239) 263 - 9790 eat. 204 rax NxuO= (139) 263 - 1058
P,md3f Addrus;
cwC]lcuteQcaastnlcancrcteprrod.sam
p3ga -i3 aP f 3 l E_Vugy 141)J [7e'jp!a}c. , qG'11z!zm ^Ate QMI!C2 vmnAf.OhP5.Q0VM-VGYffV
Detail by Entity Name
Flari1 r3Pi��s�� LY'_]1.'H1.51
penart+n�jm vi. Slain I Iii : r I Search Rpipg'V5 1 Jetnll 9v l7oe=qa NUtmbe� $
Detail by Entity Name
Florida Limited Liability Company
COASTAL CONCRETE
PRODUCTS, LL.0
Fllinn Information
Document Number
LIOODO107847
FEIIEIN Number
27-3688614
Date Filed
10/1512010
Effective Date
14/1612010
State
FL
Status
ACTIVE
Principal Address
7742 Alico Rd
Ft. Myers, FL 33912
Changed- 0112312014
Mailing Address
7742 Allco Rd
Ft. Myers, FL 33912
Changed: 4112312014
Renlstered Anetlt Name & Address
TORRES, DAVID E
7742 Alico Rd
Ft, Myers. FL 33912
Address Changed: 01/23/2014
Authorized Personls) t]etall
Name & Address
Title MGF?
TORRES, DAVIQ E
7742 Alico Rd
Ft. Myers, FL 33912
Annual Reports
Report Year Filed Date
2016 01125/2016
2017 41112/2017
Page I of 2
DJ'1131UH JF (:GHPURn116149
http://search,sunbiz.oi-g inquiry/Coi-poi-ationSearch/Seai-chResu[tDetaiI?inquii•ytype=Entity... 3!6/2018
Detail by Entity Name
2018 01/18/2018
Document Images
DI/1812016 --ANNUAL REPORT
01/12/2017 --ANNUAL REPORT
01!25/2016 -- ANNUAL REPORT
U1/1212U15 -- ANNUAL REPORT
01/23/20:4 -- ANNUAL RE RT
01/25/2043 -- ANNUAL REPORT
02/03/2012 ANNUAL REPORT
03/02/2011 --ANNUAL REPORT
Page 2 of 2
10/15/2010 -- Florida limited Liability Viev: image in PDF format
. i—da Ll �::a^Iti-, of G 2Y1; of tl.,,s
http://search.sunbiz.org/Inquiry/Corporation Se arch/SearchResultDetaiI?inquirytype=Entity... 3/6/2018
EXHIBIT A-3: CONTRACTOR'S KEY PERSONNEL ASSIGNED TO THE PROJECT
Name
David Machado
Personnel Cateaory
Construction Superintendent
Maritza Aguiar Project Manager
10
Conslruclion Services AgreertleW' Revised 022018 Q
INSTR 5538064 OR 5496 PG 2047 RECORDED 4/10/2018 2:59 PM PAGES 8
DWIGHT E. BROCK, CLERK OF THE CIRCUIT COURT, COLLIER COUNTY FLORIDA
REC $69.50
ALTER SURETY GROUP, INC.
Bond Department - Public Works Bond
In compliance with Florida Statute Chapter 255.05, the provisions and limitations of section 255.05
Florida Statutes, including but not limited to, the notice and time limitations in Sections 255.05(2)
and 255.05(10) are incorporated in this bond by reference.
Bond Number
PB12159900161
Contractor Coastal Concrete Products, LLC dba Coastal Site Development
Address & 7742 Alico Road
Phone No. Fort Myers, FL 33912
(239)263-9700
Surety Philadelphia Indemnity Insurance Company
Address & One Bala Plaza, Suite 100
Phone No. Bala Cynwyd, PA 19004
610-617-7900
Owner Name Board of County Commissioners of Collier County
Address & 2685 S. Horseshoe Drive, Unit 103
Naples, FL. 34104
Phone No. (239) 252-6048
Contracting Public Entity
(if different from the owner)
Address &
Phone No.
Contract/Project Number
Project Name
Project Location
Legal Description
And Street Address
Contract No. 18-7267
Lely Branch Canal Weir
Naples, FL.
Naples, FL.
Description of Improvement: Weir Control Structure with Gates, 8 " Forcemain Relocation, Drainage
This bond is given to comply with section 255.05 Florida Statutes and any action instituted by a claimant
under this bond for payment must be in accordance with the notice and time limitation provisions in Section
255.05(2) and (10), Florida Statutes. Any provision of this bond which conflict with or purports to grant
broader or more expanded coverage in excess of the minimum requirements of the applicable statute shall
be deemed deleted herefrom. This bond is a statutory bond, not a common law bond.
This is the front page of the bond.
All other page(s) are deemed subsequent to this page regardless of any page number(s) that may be
pre-printed thereon.
OR 5496 PG 2048
v
L PAYMEMi'
L
P.r.oductjZ•WQgdW goolte
PljgO
IN, 'Coastal Concrete
f
T.,
"ru'Ruipat
.Foftv-Ebu�-Th ThFAQWundLqa-gid4jy-;Q'olj the
mj*
April
-jAtg-RMrh Qanal IAIAfr
18
Wift ft
M
a
* 00
MOW,
-AM
* Amo
Sri
ril
W40
OR 5496 PG 2049
The provisions and lknitations of section 2(14.05 Florida
Statutes; including but not limited to the n time
Ocs, and
limitations in Secftns 255.05(2) and 255.05(10), am
Incorporated in this bond by reference,
C�1!\.(NIST `1N L.
StAt5 OF
COUNTY QF
SRN
#ONNotary Public State ofFlorlda
a . Maritza Aguiar
MygrrimlaslonGG 146869
or
SX ires 12/00/2021
q1j
0 TM` P W
Ii As Per Attached Power of Attomey
4N" WOUAMOW
Tal
dot_ _04,
pt�iit:`�if..
AA
ggW
4upp-Pe Go pany hia 1pg;lMni� l
J2
.Sala GNmmwd;--PA .19004=
X)
/_ 9
d i
73
Tal
dot_ _04,
pt�iit:`�if..
AA
ggW
4upp-Pe Go pany hia 1pg;lMni� l
J2
.Sala GNmmwd;--PA .19004=
OR 5496 PG 2050
Karol Kelly
W- MW -0# Bodda.
�Mhim!A�)ade.--.
-PR
4 pT��
p
(po
ray
One Bala Plaza
IE
Suite 100
Bala Cyn=d. Pk--.j9QD-4fQ95Q
flushiess.AffdtaW
1(619) 206-703§1 —
.�
nal -
Ad Id ;M n-Ifid wwMd fdu 1NQV: lik-ef-aff
'November 15th, 2021
- WTOW�T.A-I'
;1.Q tw."Dawn Ams eitz
MGM MW -
DAWN;AUSPITZ
r,WN # 6614S743
N Comm
T Lis 2027
E)"U, Nov. S, 1021
F OIS c COT
U
S
ATE M
,R mo w
MWIMTHROUGH
r
FLOR A jtUjjW�- _
EIV: _��AW
OR 5496 PG 2051
EXHIBIT B-2: PUBLIC PERFORMANCE BOND
18.7267
Bond No. PB121S59900161
Contract No: 18-72e7
KNOW ALL MEN BY THESE PRESENTS: That Coastal Concrete Products, Ll(' .._ha _oastal Site Development
7742 Alico Road, Fort Myers, FL.X1.2 as Principal, and Philadelphia Indemnity Insurance Company
as Surety, located at
One Bala Plaza, -Suite 100 Bala Cynwyd PA 19004-0950
(Business Address) are held and firmly bound to
The Board of County Commissioners of Collier County , as Obligee in the sum of
)forthe payment whereof we bond ourselves, our heirs, executors, personal
successors and assigns, jointly and severally.
WHEREAS, Principal has entered into a contract dated as of the 5th day of
April 1 2018 with Obligee for
Lely Branch Canal Weir Contract #18 7767 In
accordance with drawings and specifications, which contract is Incorporated by reference and
made a part hereof, and is referred to herein as the Contract,
THE CONDITION OF THiS BOND is that if Principal:
1. Performs the Contract at the times and in the manner prescribed in the Contract; and
2. Pays Obligee any and all losses, damages, costs and attorneys' fees that Obligee sustains
because of any default by Principal under the Contract, Including, but not limited to, all delay
damages, whether liquidated or actual, incurred by Obligee; and
3. Performs the guarantee of all work and materials furnished under the Contract for the time
specified in the Contract, then this bond is void; otherwise it remalns,in full force. Any changes in
or under the Contract and compliance or noncompliance with any formalities connected with the
Contract or the changes do not affect Sureties obligation under this Bond,
The Surety, for value received, hereby stipulates and agrees that no changes, extensions of time,
alterations or additions to the terms of the Contract or other work to be performed hereunder, or
the specifications referred to therein shall in anywlse affect Its obligations under this bond, and it
does hereby waive notice of any such changes, extensions of time, alterations or additions to the
terms of the Contract or to work or to the specifications.
This Instrument shall be construed in all respects as a common law bond. It is expressly
understood that the time provisions and statute of limitations under Section 255.05, Florida
Statutes, shall not apply to this bond.
In no event wit the Surety be liable in the aggregate to Obilgee for more than the penal sum of
this Performance Bond regardless of the number of suits that may be filed by Obligee.
iN WITNESS WHEREOF, the above parties have executed this instrument this rth_ day of
April __ 20 18 , the name of each party being affixed and these presents duly -
signed by its undersigned representative, pursuant to authority of its governing body.
14
Construcdo" Sendras Agreement: Revised 022018
OR 5496 PG 2052
04644e)pledonddsiJIV W
OF
The.
he fareigoing. inW.Ument
.) o t
coR c D oO dE a
�� •tee ;t�►� • pttx��•
. •���I�t� slidi�(dId�t
��#v �Notary Public State of Florida
Maritza Aguiar
My ComM1.610 GG 146969
Et,piroe 12109!2021
coastalCoo rete rodu is LLC C stall-SiteDevelop'ment
' s,i;tl11 N;
. r
d0d Wore. rad tits$ �&day.. 0i
Gi? ON
OR 5496 PG 2053
$rt As Per Attached Power of Attorney
1Nitnamses: to lure
Karol Kelly
1URSY:
I
Philadelphia Iridemnity lnsqranqe.Co!B2any
Iptr "0 -
I jitp 1 no
�7
(Printed Name)
Ad*q
qrl
ft W�;AttoMid
: i
C V,;
David T. Satine
-One gala. Elgi�j j
W, ..... .... ...... ..
(61 M-206,76aa-,
T.
1.9
Philadawww I A , V-8.9tt
49
November 15th, 20 1
QawnAUIRdZ,.--t.-:
z"d
flAt
00*0 -n ALQIIP%4,*
.01
DAWN AUSPITZ
COMIMMON 0 GG14S743
EXPIRES Nov. 15, 2021
9rAiE Of ok"
RU INSURANCE
WY
*how
*** OR 5496 PG 2054 ***
State of FLORIDA
county of collier
I HEREBY CERTIFY `THAT ,th`i`s is a t Me
and correct copy of ,'dpcument recoa,ded
in the OFFICIAL RE RD t Collier%c6unty
WITNESS my hand a d of ata se4)
date, 4/10/2018 1-}
DWIGHT E. BROCK CSE )p tztI ftgjT COURT
BY. D.1c.
r f
181'
PHILADELPHIA INDEMNITY INSURANCE COMPANY
One Bala Plaza, Suite 100
Bala Cynwyd, PA 19004-0950
Power of Attorney
KNOW ALL PERSONS BY THESE PRESENTS: That PHILADELPHIA INDEMNITY INSURANCE COMPANY (the Company), a corporation organized and
existing under the laws of the Commonwealth of Pennsylvania, does hereby constitute and appoint Warren M. Alter, David T. Saline and Jonathan A. Bursevich of
Alter Surety Group, Inc, its true and lawful Attomey-in-fact with full authority to execute on its behalf bonds, undertakings, recognizances and other contracts of
indemnity and writings obligatory in the nature thereof, issued in the course of its business and to bind the Company thereby, in an amount not to exceed $25.000.000.
This Power of Attorney is granted and is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of
PHILADELPHIA INDEMNITY INSURANCE COMPANY on the 14" of November, 2016.
RESOLVED: That the Board of Directors hereby authorizes the President or any Vice President of the
Company: (1) Appoint Attorney(s) in Fact and authorize the Attorneys) in Fact to
execute on behalf of the Company bonds and undertakings, contracts of indemnity and
other writings obligatory in the nature thereof and to attach the seal of the Company
thereto; and (2) to remove, at any time, any such Attomey-in-Fact and revoke the
authority given. And, be it
FURTHER
RESOLVED: That the signatures of such officers and the seal of the Company may be affixed to any
such Power of Attorney or certificate relating thereto by facsimile, and any such Power of
Attorney so executed and certified by facsimile signatures and facsimile seal shall be
valid and binding upon the Company in the future with respect to any bond or
undertaking to which it is attached.
IN TESTIMONY WHEREOF, PHILADELPHIA INDEMNITY INSURANCE COMPANY HAS CAUSED THIS INSTRUMENT TO BE SIGNED AND ITS
CORPORATE SEALTO BE AFFUMD BY ITS AUTHORIZED OFFICE THIS 27TH DAY OF OCTOBER, 2017.
3�4�g�itMY S6��iw.
jy 1
5
Edward Sayago, Corporate Secretary
a KIV x#
PHILADELPHIA INDEMNITY INSURANCE COMPANY
(Jel)
�tihhai�tV,:.�"
Robert D. O'Leary Jr., President & CEO
Philadelphia Indemnity Insurance Company
On this 27' day of October, 2017, before me came the individual who executed the preceding instrument, to me personally known, and being by me duly sworn said
that he is the therein described and authorized officer of the PHILADELPHIA INDEMNITY INSURANCE COMPANY; that the seal affixed to said instrument is
the Corporate seal of said Company; that the said Corporate Seal and his signature were duly affixed
ro..,wrn.' cw+r Notary Public: LY-
wco.,w,wcar.. s.p.u.rmr
residing at: Bala Cynwyd. PA
(Notary Seal)
My commission expires: September 25, 2021
I, Edward Sayago, Corporate Secretary of PHILADELPHIA INDEMNITY INSURANCE COMPANY, do hereby certify that the foregoing resolution of the Board of
Directors and this Power of Attorney issued pursuant thereto on this 27"day of October, 2017 are tare and correct and are still in full force and effect, I do further
certify that Robert D. O'Leary Jr., who executed the Power of Attorney as President, was on the date of execution of the attached Power of Attorney the duly elected
President of PHILADELPHIA INDEMNITY INSURANCE COMPANY,
In Testimony Whereof I have subscribed my name and affixed the facsimile seal of each Company this 6th day of April 20 18
;jNtWhh
a'
jy 1
Edward Sayago, Corporate Secretary
a KIV x#
PHILADELPHIA INDEMNITY INSURANCE COMPANY
�tihhai�tV,:.�"
EXHIBIT 13-3: INSURANCE REQUIREMENTS
The Contractor shall at its own expense, carry and maintain insurance coverage from responsible
companies duly authorized to do business in the State of Florida as set forth in EXHIBIT B of this
solicitation. The Contractor shall procure and maintain property insurance upon the entire project,
if required, to the full insurable value of the scope of work.
The County and the Contractor waive against each other and the County's separate Contractors,
Contractors, Design Consultant, Subcontractors, agents and employees of each and all of them,
all damages covered by property insurance provided herein, except such rights as they may have
to the proceeds of such insurance. The Contractor and County shall, where appropriate, require
similar waivers of subrogation from the County's separate Contractors, Design Consultants and
Subcontractors and shall require each of them to include similar waivers in their contracts.
Collier County shall be responsible for purchasing and maintaining its own liability insurance.
Certificates issued as a result of the award of this solicitation must identify "For any and all work
performed on behalf of Collier County", or, the specific solicitation number/contract number and
title.
The General Liability Policy provided by Contractor to meet the requirements of this solicitation
shall name Collier County, Florida, as an additional insured as to the operations of Contractor
under this solicitation and shall contain a severability of interests provisions.
The Certificate Halder shall be named as Collier County Board of County Commissioners, OR,
Board of County Commissioners in Collier County, OR Collier County Government, OR Collier
County. The Certificates of Insurance must state the Contract Number, or Project Number, or
specific Project description, or must read: For any and all work performed on behalf of Collier
County_
The amounts and types of insurance coverage shall conform to the minimum requirements set
forth in EXHIBIT B with the use of Insurance Services Office (ISO) forms and endorsements or
their equivalents. If Contractor has any self-insured retentions or deductibles under any of the
below listed minimum required coverage, Contractor must identify on the Certificate of Insurance
the nature and amount of such self- insured retentions or deductibles and provide satisfactory
evidence of financial responsibility for such obligations. All self-insured retentions or deductibles
will be Contractor's sole responsibility.
CoverageLs shall be maintained without interruption from the date of commencement of the Work
until the date of completion and acceptance of the scope of work by the County or as specified in
this solicitation, whichever is longer.
The Contractor and/or its insurance carrier shall provide thirty (30) days written notice to the
County of policy cancellation or non -renewal on the part of the insurance carrier or the Contractor.
The Contractor shall also notify the County, in a like manner, within twenty-four (24) hours after
receipt, of any notices of expiration, cancellation, non -renewal or material change in coverage or
limits received by Contractor from its insurer and nothing contained herein shall relieve Contractor
of this requirement to provide notice. In the event of a reduction in the aggregate limit of any policy
to be provided by Contractor hereunder, Contractor shall immediately take steps to have the
aggregate limit reinstated to the full extent permitted under such policy.
17
Construction Services Agreement= Revised 022D1 8 �,�"�
Should at any time the Contractor not maintain the insurance coverages required herein, the
County may terminate the Agreement or at its sole discretion shall be authorized to purchase
such coverages and charge the Contractor for such coverage Us purchased. If Contractor fails
to reimburse the County for such costs within thirty (30) days after demand, the County has the
right to offset these costs from any amount due Contractor under this Agreement or any other
agreement between the County and Contractor. The County shall be under no obligation to
purchase such insurance, nor shall it be responsible For the coveragem purchased or the
insurance company or companies used. The decision of the County to purchase such insurance
coverageLsl shall in no way be construed to be a waiver of any of its rights under the Contract
Documents.
If the initial or any subsequently issued Certificate of Insurance expires prior to the completion of
the scope of work, the Contractor shall furnish to the County renewal or replacement Certificates)
of Insurance not later than ten (10) calendar days after the expiration date on the certificate.
Failure of the Contractorto provide the County with such renewal certificates) shall be considered
justification for the County to terminate any and all contracts.
1s
Construction Services Agreement' Revised 022018"��
1. Worker's Compensation
Statutory Limits of Florida Statutes, Chapter 440 and all Federal Goverment
Statutory Limits and Requirements
Evidence of Workers' Compensation coverage or a Certificate of Exemption
issued by the State of Florida is required, Entities that are formed as Sale
Proprietorships shall not be required to provide a proof of exemption, An
application for exemption can be obtained online at
hilps://apps.fldft.com/bocr,xcnio—t/
2. ® Employer's Liability
$_1,000,000 single limit per occurrence
3. ® Commercial General
Bodily Injury and Property Damage
Liability (Occurrence
Form) patterned after the
$_1,000,000 —single limit per occurrence, $2,000,000 aggregate for Bodily injury
current ISO forth
Liability and property Damage Liability. This shall include Premises and
Operations; Independent Contractors; Products and Completed Operations and
Contractual Liability.
4. ® Indemnification
To the maximum extent permitted by Florida law, the ContractorNendor shall
defend, indemnify and hold harmless Collier County, its officers and employees
from any and all liabilities, damages, losses and costs, including, but not limited
to, reasonable attorneys' Fees and paralegals' fees, to the extent caused by the
negligence, recklessness, or intentionally wrongful conduct of the Contractor/
Vendor or anyone employed or utilized by the ContractorNendor in the
performance of this Agreement.
5. ® Automobile liability
$_1,000,000 Each Occurrence, Bodily Injury & Property Darnage.
Owned/Non-owned/Hired, Automobile Included
G. ® Other insurance as
Watercraft $ Per Occurrence
noted:
® United States Longshoreman's and Harborworker's Act coverage shall be
maintained where applicable to the completion of the work.
$ 1,000,000 Por Occurrence
❑ Maritime Coverage (Jones Act) shall be maintained where applicable to the
completion of the work.
Per Occurrence
0 Aircraft Liability coverage shall be carried in limits of not less than
$5,000,000 each occurrence if applicable to the completion of the Services under
this Agreement.
Per Occurrence
® Pollution S 1,000,000 Per Occurrence.
❑ Professional Liability $ Per claire & in the aggregate
❑ Project Professional Liability $ Per Occurrence
❑ Valuable Papers Insurance $ Per Occurrence
❑ Cyber Liability $, Per Occurrence
❑ Technology Errors & Omissions S� Per Occurrence
7. 9 Bid bond Shall be submitted with proposal response in the Form of certified funds,
cashiers' check or an irrevocable letter of credit, a cash bond posted with the
0
Construction Services Agreement: Revlsad 022018
County Clerk, or proposal bond in a sum equal to 5% of the cost proposal. All
checks shall be made payable to the Collier County Board of County
Commissioners on a bank or trust company located in the State of Florida and
insured by the Federal Deposit Insurance Corporation.
8. ® Performance and For projects in excess of $200,000, bonds shall be submitted with the executed
Payment Bonds contract by Proposers receiving award, and written for 100% of the Contract
award amount, the cost borne by the Proposer receiving an award. The
Performance and Payment Bonds shall be underwritten by a surety authorized to
do business in the State of Florida and otherwise acceptable to Owner; provided,
however, the surety shall be rated as "A-" or better as to general policy holders
rating and Class V or higher rating as to financial size category and the amount
required shall not exceed 5% of the reported policy holders' surplus, all as
reported in the most current Best Key Rating Guide, published by A.M. Best
Company, Inc. of 75 Fulton Street, New York, New York 10038.
9. ® Vendor shall ensure that all subcontractors comply with the same insurance requirements that he is required
to meet. The same Vendor shall provide County with certificates of insurance meeting the required insurance
provisions.
10. ® Collier County must be named as "ADDITIONAL INSURED" on the Insurance Certificate for
Commercial General Liability where required. This insurance shall be primary and non-contributory with
respect to any other insurance maintained by, or available for the benefit of, the Additional Insured and the
Vendor's policy shall be endorsed accordingly.
11. ® The Certificate Holder shall be named as Collier County Board of County Commissioners, OR, Board of
County Commissioners in Collier County, OR Collier County Government, OR Collier County. The Certificates
of Insurance must state the Contract Number, or Project Number, or specific Project description, or must read:
For any and all work performed on behalf of Collier County.
12. ® Thirty (30) Days Cancellation Notice required.
12/20/17 - GG
Company: Coastal Concrete Products LLC dba Coastal Site Development
Signature:
E. Torres - Manager Date: 02/16/18
20
Construction Services Agreement: Revised 022018
EXHIBIT C, RELEASE AND AFFIDAVIT FORM
COUNTY OF (COLLIER)
STATE OF (FLORIDA)
Before me, the undersigned authority, personally appeared
who after being duly sworn, deposes and says:
(1) In accordance with the Contract Documents and in consideration of $ to be
received, ("Contractoe') releases and waives for itself and it's
subcontractors, material -men, successors and assigns, all claims demands, damages, costs and expenses,
whether in contract or in tort, against the Board of County Commissioners of Collier County, Florida, relating in
any way to the performance of the Agreement between Contractor and Owner, dated
,20 for the period from to , This
partial waiver and release is conditioned upon payment of the consideration described above. It is not effective
until said payment is received in paid funds.
(2) Contractor certifies for itself and its subcontractors, material -men, successors and assigns, that all charges
for labor, materials, supplies, lands, licenses and other expenses for which Owner might be sued or for which a
lien ora demand against any payment bond might be filed, shall be fully satisfied and paid upon Owner's payment
to Contractor.
(3) Contractor agrees to indemnify, defend and save harmless Owner from all demands or suits, actions, claims
of liens or other charges filed or asserted against the Owner arising out of the performance by Contractor of the
Work covered by this Release and Affidavit.
(4) This Release and Affidavit is given in connection with Contractor's [monthly/final] Application for Payment
No.
CONTRACTOR
BY:
Witness ITS: _
President
DATE:
Witness
STATE OF
COUNTY OF
[Corporate Seal]
The foregoing instrument was acknowledged before me this day of
20 , by , as of
_ a corporation, on behalf of the corporation, He/she is personally
known to me or has produced as identification and did
(did not) take an oath.
My Commission Expires:
(AFFIX OFFICIAL SEAL)
(Signature of Notary)
NAME:
(Legibly Printed)
Notary Public, State of
Commissioner No.:
21
Construction Services Agreement: Revised 022016
EXHIBIT D
FORM OF CONTRACT APPLICATION FOR PAYMENT
Collier County Board of County Commissioners the OWNER or Collier County Water -Sewer
Owner's Project
Manager's Name:
Contractors Signature:
Bid No.
Type Title:
County's Division Name
Payment to the CONTRACTOR for the above AMOUNT DUE THIS APPLICATION Is recommended b
Project No.
Submitted by Contractor
Representative: Name
Date:
Application Date:
Owner's Project Manager Name:
Contractor's Name &
Address:
Signature-,
Payment Application No.
Original Contract Time:
Original Contract Price:
$
Revised Contract Time:
Total Change Orders to Date:
$
Revised Contract Amount:
$
Total Value of Work Completed &
Stored to Date:
$
Retainage @10%
through [Insert Date]
$
Retainage a 10% through [insert
date]
$
Retainage @ %
after Insert date
$
Less Retainage
$
Total Earned Less Retainacie,
$
Less previous payment(s
Percent Work Completed
to Date:
%
AMOUNT DUE THIS
APPLICATION:
$
Percent Contract Time
Completed to Date:
%
$
Liquidated Damages to
Be Accrued
$
Remaining Contract Balance
ATTACH SCHEDULE OF VALUES AND ACCOMPANYING DOCUMENTATION TO THIS APPLICATION
CONTRACTOR'S CERTIFICATION:
The undersigned CONTRACTOR certifies that: (1) 211 previous progress payments received from OWNER on account of
Work done under the Contract referred to above have been applied to discharge in full all obligations of CONTRACTOR
incurred in connection with Work covered by prior Applications for payment numbered 1 through _ inclusive; (2) title
to all materials and equipment incorporated in said Work or otherwise listed in or covered by this Application for Payment
will pass to OWNER at time of payment free and clear of all liens, claims, security interests and encumbrances (except such
as covered by Bond acceptable to OWNER); (3) all amounts have been paid for work which previous payments were Issued
and received from the OWNER and that current payment is now due; and (4) CONTRACTOR has only Included amounts
in this Application for Payment properly due and owing and CONTRACTOR has not included within the above referenced
amount any claims for unauthorized or changed Work that has not been properly approved by Owner In writing and in
advance of such Work.
Contractor's dame
Contractors Signature:
Date:
Type Title:
Shaft be signed by an authorized
representative of the Contractor_
Payment to the CONTRACTOR for the above AMOUNT DUE THIS APPLICATION Is recommended b
Design Professional's Name:
Signature:
Date:
Payment to the CONTRACTOR for the above AMOUNT DUE THIS APPLICATION Is recommended h
Owner's Project Manager Name:
Signature-,
fate:
22
Construction Services Agreement' Revised 022018 Q�
EXHIBIT D Continued SCHEDULE OF VALUES
Prntrcr Nu b,,;
Nut
RMH Ta'
. E rplanaIIDn for the twa coiumnS under previous AppiIca IIons: The Thru Date Is where you will plate all information until the contrad Is tcmplete unless a release or reduction of feta Inap Issuo for
into play. If this happens, ah lnformatloo up to The date of the %change in retainage is placed In the Thru Date column, Information after That date is placed In the Since Date column, This states
what has happened since the change in relainage.
23
Conslructivn Services Agreement: Revised 022018
Exhibit D
(Continued) Stored Materials Record
Fnrmiila• A + 121 - f: - D = E
A
B
C
D
E
Invoice Previously
Date Description Supplier Number Received
Received
This Period
Previously
Installed
Installed
This Period
Balance To
Install
24 0Consiructlen Services Agreement: Revised 022018
EXHIBIT E: CHANGE ORDER
An electronic data entry form may be found at:
htt ;/Jbccs Ol/SiteDirecto /ASD/Purchasin /Formsl/Farms/Default.as x
Change Order Form
Contract0_ ChangtME-1 Purchase Order*: Project#:�
Contractodli'l n Name:
Project Manager Name
Project N ante:
Department
Criginul ContractWwsr tYdar Amount
original SCC AFprcvai DoE; Agands Item #t
Curfent BCC ApFr4ypd Amount
Lest i Approval Dote: Awnde aunt
CUrrrank r_mkacbW ork Ofdor Amount
SAP Cantraet Expiration Data {%gear!
Dolbr Amolrntof this Chsnga
*0IV:4!
TctaIChamge from OriginsIAmouni
l is adCentractVVa(K Order Total
5
acn *DlV!0!j
ChangehornCwfent SCC Approved Arrounl
Cumul9tive Chsn Es
5
1) #0IWO!
L
Ch ang afro mCLirr=nt Amount
Completion Date, Desv0ptlon of the Task{sj Change, and Ratlanate for the Change
Notice to Prones= Origin al Last Approved ,M421id DAD
5
Date Completion Dat Dale i�•ryeatsitz+angea
0ofDays Added SeiectTaska f3 Add newtasklsj M Detetetask[sl Ll Changetaskl9} Q Oth*tmmH ,7-vj
Provide response to the following: 1.1 detailed and sper:kfk explanxtiontrationaleof the requested chanii to the tasklsl and ! or
the additional days added (If requestadl:7)why this change was not included in the original contract: and, 3_j describe the impact if
this change is not processed. Attach additional information from Sht Deign Professional andlor Conlraelaf d M11,04.
Prepared by: Data;
[ rojew Manager Namt and D4parifne4i
Acfeplanctof this ChsngtOrder shall c4A6tilulea modificarion 10 conte3d 1 viotkorder klentili above5ndwril N Subjecl10 all the same
iormsand BonoainrsasComaiatdinihaconlracl1workorlfrindicated above. asfullpasy the samev+erestatedin1hliacaeptanw@ The
a]jt umem,itany,totieContrjiCiShallaonntiNreafuIIandOnalsettlerrentofanyan1allalaimsoftheCQrvaCwr1Ver,0r1ConsuRant!
Deg p n Profen s ianx i arlaing out of or related Ir31he Cha nge set forth htrtln, including c Ilirns lot tm psd arnd dttay cos rs.
Accepted by- Date:
( onuaclorrVendorl onsullarl: e,ign roiessan3iand Narneof li Apf'rActappftcaZ5le;
Ap p roved 6y: Date' _
[Design Pra tasiorra and Nameof Fum, Hpro$cl appika lei
Ap proved by: Date,
[ f4xuremerlFfofessional
z!' �On, : Ak ;,11-203- 1110 ' NNW;
T:
25
Construction Services Agreement. Revised 022018
EXHIBIT F: CERTIFICATE OF SUBSTANTIAL COMPLETION
OWNER'S Project No -
PROJECT:
CONTRACTOR
Contract For
Contract Date
Design Professional's Project No.
This Certificate of Substantial Completion applies to all Work under the Contract Documents or to the
following specified parts thereof:
To
OWNER
And
To
Substantial Completion is the state in the progress of the Work when the Work (or designated
portion) is sufficiently complete in accordance with the Contract Documents so that the Owner can
occupy or utilize the Work for its intended use. The Work to which this Certificate applies has been
inspected by authorized representatives of OWNER, CONTRACTOR AND DESIGN PROFESSIONAL, and
that Work is hereby declared to be substantially complete in accordance with the requirements of the
Contract Documents on:
DATE OF SUBSTANTIAL COMPLETION
A tentative list of items to be completed or corrected is attached hereto. This list may not be afi-inclusive,
and the failure to include an item in it does not alter the responsibility of CONTRACTOR to complete all the
Work in accordance with the Contract Documents. The items in the tentative list shall be completed or
corrected by CONTRACTOR within days of the above date of Substantial Completion.
The responsibilities between OWNER and CONTRACTOR for security, operation, safety, maintenance,
treat, utilities, insurance and warranties shall be as follows:
2a
conslrUC000 Services Agreement: Revised 022018 ,
RESPONSIBILITIES:
OWN ER:
CONTRACTOR
The following documents are attached to and made a part of this Certificate:
This certificate does not constitute an acceptance of Work not in accordance with the Contract
Documents nor is it a release of CONTRACTOR'S obligation to complete the Work in accordance with the
Contract Documents.
Executed by Design Professional on 20
Design Professional
By:
Type Name and Title
CONTRACTOR accepts this Certificate of Substantial Completion on
20
CONTRACTOR
By:
Type Name and Title
OWNER accepts this Certificate of Substantial Completion on 120
OWNER
By:
Type Name and Title
27
Construction Services Agreement: Revised 022018
EXHIBIT G: FINAL PAYMENT CHECKLIST
Bid No.: Project No,; Date: .2o
Contractor:
The following items have been secured by the
for the Project known as
and have been reviewed and found to comply with the requirements of the Contract Documents.
Original Contract Amount: Final Contract Amount:
Commencement Date'
Substantial Completion Time as set forth in the Agreement: Calendar Days.
Actual Date of Substantial Completion:
Final Completion Time as set forth in the Agreement; Calendar Days,
Actual Final Completion Date:
YES NO
1. All Punch List items completed on
2. Warranties and Guarantees assigned to Owner (attach to this form).
3. Effective date of General one year warranty from Contractor is:
43p
28
Construction Services Agreement. Revised 022018
4.
2 copies of Operation and Maintenance manuals for equipment and
system submitted (list manuals in attachment to this form).
5.
As -Built drawings obtained and dated:
_
6.
Owner personnel trained on system and equipment operation.
7.
Certificate of Occupancy No.: _
issued on __ (attach to this form).
8.
Certificate of Substantial Completion issued on
9.
Final Payment Application and Affidavits received from Contractor on:
10.
Consent of Surety received on _
11.
Operating Department personnel notified Project is in operating phase.
12.
All Spare Parts or Special Tools provided to Owner:
13.
Finished Floor Elevation Certificate provided to Owner;
14.
Other:
If any of the above is not applicable, indicate by NIA, If NO is checked for any of the above, attach
explanation.
Acknowledgments:
By Contractor:
(Company Name)
(Signature)
(Typed Name & Title)
By Design
Professional
(Firm Name)
(Signature)
(Typed Name & Title)
By Owner:
(Department Name)
(Signature)
(Name & Title)
43p
28
Construction Services Agreement. Revised 022018
EXHIBIT H. GENERAL TERMS AND CONDITIONS
1. INTENT OF CONTRACT DOCUMENTS.
1.1 It is the intent of the Contract Documents to describe a functionally complete Project (or
portion thereof) to be constructed in accordance with the Contract documents. Any work, materials
or equipment that may reasonably be inferred from the Contract Documents as being required to
produce the intended result shall be supplied whether or not specifically called for. When words
which have a well-known technical or trade meaning are used to describe work, materials or
equipment, such words shall be interpreted in accordance with that meaning. Reference to standard
specif!cations, manuals or codes of any technical society, organization or association or to the laws
or regulations of any governmental authority having jurisdiction over the Project, whether such
reference be specific or by implication, shall mean the latest standard specification, manual, code,
law or regulation in effect at the time the Work is performed, except as may be otherwise specifically
stated herein.
1.2 If before or during the performance of the Work Contractor discovers a conflict, error or
discrepancy in the Contract Documents, Contractor immediately shall report same to the Project
Manager in writing and before proceeding with the Work affected thereby shall obtain a written
interpretation or clarification from the Project Manager; said interpretation or clarification from the
Project Manager may require Contractor to consult directly with Design Professional or some other
third party, as directed by Project Manager. Contractor shall take field measurements and verify field
conditions and shall carefully compare such field measurements and conditions and other
information known to Contractor with the Contract Documents before commencing any portion of the
Work.
1.3 Drawings are intended to show general arrangements, design and extent of Work and are
not intended to serve as shop drawings. Specifications are separated into divisions for convenience
of reference only and shall not be interpreted as establishing divisions for the Work, trades,
subcontracts, or extent of any part of the Work. In the event of a discrepancy between or among the
drawings, specifications or other Contract Document provisions, Contractor shall be required to
comply with the {provision which is the more restrictive or stringent requirement upon the Contractor,
as determined by the Project Manager. Unless otherwise specifically mentioned, all anchors, bolts,
screws, fittings, fillers, hardware, accessories, trim and other parts required in connection with any
portion of the Work to make a complete, serviceable, finished and first quality installation shall be
furnished and installed as part of the Work, whether or not called for by the Contract Documents.
2, INVESTIGATION AND UTILITIES.
2.1 Subject to Section 2.3 below, Contractor shall have the sole responsibility of satisfying itself
concerning the nature and location of the Work and the general and local conditions, and particularly,
but without limitation, with respect to the following: those affecting transportation, access, disposal,
handling and storage of materials; availability and quality of labor; water and electric power,
availability and condition of roads; work area; living facilities; climatic conditions and seasons;
physical conditions at the work -site and the project area as a whole; topography and ground surface
conditions; nature and quantity of the surface materials to be encountered; subsurface conditions;
equipment and facilities needed preliminary to and during performance of the Work; and all other
costs associated with such performance. The failure of Contractor to acquaint itself with any
applicable conditions shall not relieve Contractor from any of its responsibilities to perform under the
Contract Documents, nor shall it be considered the basis for any claim for additional time or
compensation.
29
Construction Services Agreement: Revised 02203
2.2 Contractor small locate all existing roadways, railways, drainage facilities and utility services
above, upon, or under the Project site, said roadways, railways, drainage facilities and utilities being
referred to in this Sub -Section 2.2 as the "Utilities". Contractor shall contact the owners of all Utilities
to determine the necessity for relocating or temporarily interrupting any Utilities during the
construction of the Project. Contractor shall schedule and coordinate its Work around any such
relocation or temporary service interruption. Contractor shall be responsible for properly shoring,
supporting and protecting all Utilities at all times during the course of the Work. The Contractor is
responsible for coordinating all other utility work so as to not interfere with the prosecution of the
Work (except those utilities to be coordinated by the Owner as may be expressly described
elsewhere in the Contract Documents).
2.3 Notwithstanding anything in the Contract Documents to the contrary, if conditions are
encountered at the Project site which are (i) subsurface or otherwise concealed physical conditions
which differ materially from those indicated in the Contract Documents or (ii) unknown physical
conditions of an unusual nature, which differ materially from those ordinarily found to exist and
generally recognized as inherent in construction activities of the character provided for in the
Contract Documents, and which reasonably should not have been discovered by Contractor as part
of its scope of site investigative services required pursuant to the terms of the Contract Documents,
then Contractor shall provide Owner with prompt written notice thereof before conditions are
disturbed and in no event later than three (3) calendar days after first observance of such conditions.
Owner and Design Professional shall promptly investigate such conditions and, If they differ
materially and cause an increase or decrease in Contractor's cost of, or time required for,
performance of any part of the Work. Owner will acknowledge and agree to an equitable adjustment
to Contractor's compensation or time for performance, or both, for such Work. If Owner determines
that the conditions at the site are not materially different from those indicated in the Contract
Documents or not of an unusual nature or should have been discovered by Contractor as part of its
investigative services, and that no change in the terms of the Agreement is justified, Owner shall so
notify Contractor in writing, stating its reasons. Claims by Contractor in opposition to such
determination by Owner must be made within seven (7) calendar days after Contractor's receipt of
Owner's written determination notice. If Owner and Contractor cannot agree on an adjustment to
Contractor's cost or time of performance, the dispute resolution procedure set forth in the Contract
Documents shall be complied with by the parties.
3. SCHEDULE.
3.1 The Contractor, within ten (10) calendar days after receipt of the Notice of Award, shall
prepare and submit to Project Manager, for their review and approval, a progress schedule for the
Project (herein "Progress Schedule"), The Progress Schedule shall relate to all Work required by
the Contract Documents, and shall utilize the Critical Path method of scheduling and shall provide
for expeditious and practicable execution of the Work within the Contract Time. The Progress
Schedule shall indicate the dates for starting and completing the various stages of the Work.
3.2 The Progress Schedule shall be updated monthly by the Contractor. All monthly updates to
the Progress Schedule shall be subject to the Project Manager's review and approval. Contractor
shall submit the updates to the Progress Schedule with its monthly Applications for Payment noted
below. The Project Manager's review and approval of the submitted Progress Schedule updates
shall be a condition precedent to the Owner's obligation to pay Contractor.
3.3 All work under this Agreement shall be performed in accordance with the requirements of all
Collier County Noise Ordinances then in effect. Unless otherwise specified, worst will generally be
s
Constru4%on Services Agreement Revised 02201 0
limited to the hours of 7 a.m. to 7 p.m,, Monday through Saturday. No work shall be performed
outside the specified hours without the prior approval of the Project Manager,
4. PROGRESS PAYMENTS.
4.1 Prior to submitting its first monthly Application for Payment, Contractor shall submit to Project
Manager, for their review and approval, a schedule of values based upon the Contract Price, listing
the major elements of the Work and the dollar value for each element. After its approval by the
Project Manager, this schedule of values shall be used as the basis for the Contractor's monthly
Applications for Payment. This schedule shall be updated and submitted each month along with a
completed copy of the Application for Payment form signed by the Contractor's authorized
representative and attached to the Agreement as Exhibit D.
4.2 Prior to submitting its first monthly Application for Payment, Contractor shall provide to the
Project Manager the list of its Subcontractors and materialmen submitted with its Bid showing the
work and materials involved and the dollar amount of each subcontract and purchase order.
Contractor acknowledges and agrees that any modifications to the list of Subcontractors submitted
with Contractor's Bid and any subsequently identified Subcontractors are subject to Owner's prior
written approval. The first Application for Payment shall be submitted no earlier than thirty (30) days
after the Commencement Date. Notwithstanding anything herein to the contrary, if approved by
Owner in its sole discretion, Contractor may submit its invoice for any required Payment and
Performance Bonds prior to the first Application of Payment provided that Contractor has furnished
Owner certified copies of the receipts evidencing the premium paid by Contractor for the bonds.
4.3 Unless expressly approved by Owner in advance and in writing, said approval at Owner's
sole discretion, Owner is not required to make any payment for materials or equipment that have not
been incorporated into the Project. If payment is requested on the basis of materials and equipment
not incorporated into the Project, but delivered and suitably stored at the site or at another location,
and such payment and storage have been agreed to by Owner in writing, the Application for Payment
also shall be accompanied by a bill of sale, invoice or other documentation warranting that the Owner
has received the materials and equipment free and clear of all liens, charges, security interests and
encumbrances, togetherwith evidence that the materials and equipment are covered by appropriate
property insurance and other arrangements to protect Owner's interest therein, all of which shall be
subject to the Owner's satisfaction. Thereafter, with each Application for Payment, Contractor also
shall complete and submit to Owner as part of its Application for Payment, the Stored Materials
Record attached hereto and made a part hereof as Exhibit D.
4.4 Contractor shall submit its monthly Application for Payment to the Project Manager or his or
her designee, as directed by Owner (which designee may include the Design Professional). After
the date of each Application for Payment is stamped as received and within the timeframes set forth
in Section 218.735 F.S., the Project Manager, or Design Professional, shall either: (1) Indicate its
approval of the requested payment; (2) indicate its approval of only a portion of the requested
payment, stating in writing its reasons therefore; or (3) return the Application for Payment to the
Contractor indicating, in writing, the reason for refusing to approve payment, Payments of proper
invoices in the amounts approved shall be processed and paid in accordance with Section 218.735,
F.S. and the administrative procedures established by the County's Procurement Services Division
and the Clerk of Court's Finance Department respectively.
4.5 In the event of a total denial by Owner and return of the Application for Payment by the Project
Manager, the Contractor may make the necessary corrections and re -submit the Application for
Payment. The Owner shall, within ten (10) business days after the Application for Payment is
31�
Construction Services Agreement: Revised 022018 Q
stamped and received and after Project Manager approval of an Application for Payment, pay the
Contractor the amounts so approved.
4.6 Owner shall retain ten percent (10%) of the gross amount of each monthly payment request
or ten percent (10%) of the portion thereof approved by the Project Manager for payment, whichever
is less. Such sum shall be accumulated and not released to Contractor until final payment is due
unless otherwise agreed to by the Owner in accordance with Florida Statute 255.078. The Project
Manager shall have the discretion to establish, in writing, a schedule to periodically reduce the
percentage of cumulative retainage held throughoutthe course of the Project schedule. Ownershall
reduce the amount of the retainage withheld on each payment request subsequent to fifty percent
(50%) completion subject to the guidelines set forth in Florida Statute 255.078 and as set forth in the
Owner's procurement ordinance and policies.
4.7 Monthly payments to Contractor shall in no way imply approval or acceptance of Contractor's
Work.
4.8 Each Application for Payment, subsequent to the first pay application, shall be accompanied
by a Release and Affidavit, in the form attached as Exhibit C, acknowledging Contractor's receipt of
payment in full for all materials, labor, equipment and other bills that are then due and payable by
Owner with respect to the current Application for Payment. Further, to the extent directed by Owner
and in Owner's sole discretion, Contractor shall also submit a Release and Affidavit from each
Subcontractor, sub -subcontractor, or supplier in the form attached as Exhibit C acknowledging that
each Subcontractor, sub -subcontractor or supplier has been paid in full through the previous month's
Application for Payment. The Owner shall not be required to make payment until and unless these
affidavits are furnished by Contractor.
4.9 Contractor agrees and understands that funding limitations exist and that the expenditure of
funds must be spread over the duration of the Project at regular intervals based on the Contract
Amount and Progress Schedule. Accordingly, prior to submitting its first monthly Application for
Payment, Contractor shall prepare and submit for Project Manager's review and approval, a detailed
Project Funding Schedule, which shall be updated as necessary and approved by Owner to reflect
approved adjustments to the Contract Amount and Contract Time. No voluntary acceleration or early
completion of the Work shall modify the time of payments to Contractor as set forth in the approved
Project Funding Schedule.
4.10 Notwithstanding anything in the Contract documents to the contrary, Contractor
acknowledges and agrees that in the event of a dispute concerning payments for Work performed
under this Agreement, Contractor shall continue to perform the Work required of it under this
Agreement pending resolution of the dispute provided that Owner continues to pay Contractor all
amounts that Owner does not dispute are due and payable.
4.11 Payments will be made for services furnished, delivered, and accepted, upon receipt and
approval of invoices submitted on the date of services or within six (6) months after completion of
contract. Any untimely submission of invoices beyond the specified deadline period is subject to non-
payment under the legal doctrine of "laches" as untimely submitted. Time shall be deemed of the
essence with respect to the timely submission of invoices under this agreement.
4.12 The County may, at its discretion, use VISAIMASTER card credit network as a payment
vehicle for goods and/or services purchased as a part of this contract. The County may not accept
any additional surcharges (credit card transaction fees) as a result of using the County's credit card
for transactions relating to this solicitation
32
Construdlon Services Agreernent Revlsed 022018
G. PAYMENTS WITHHELD.
5.1 The Project Manager may decline to approve any Application for Payment, or portions
thereof, because of subsequently discovered evidence or subsequent inspections that reveal non-
compliance with the Contract Documents. The Project Manager may nullify the whole or any part of
any approval for payment previously issued and Owner may withhold any payments otherwise due
Contractor under this Agreement or any other agreement between Owner and Contractor, to such
extent as may be necessary in the Owners opinion to protect it from loss because of:
(a) Defective Work not remedied; (b) third party claims filed or reasonable evidence indicating
probable filing of such claims; (c) failure of Contractor to make payment properly to subcontractors
or for labor, materials or equipment; (d) reasonable doubt that the Work can be completed for the
unpaid balance of the Contract Amount; (e) reasonable indication that the Work will not be completed
within the Contract Time; (f) unsatisfactory prosecution of the Work by the Contractor; or (g) any
other material breach of the Contract Documents by Contractor,
5.2 If any conditions described in 5,1, are not remedied or removed, Owner may, after three (3)
days written notice, rectify the same at Contractor's expense. Provided however, in the event of an
emergency, Owner shall not be required to provide Contractor any written notice prior to rectifying
the situation at Contractor's expense. Owner also may offset against any sums due Contractor the
amount of any liquidated or non -liquidated obligations of Contractor to Owner, whether relating to or
arising out of this Agreement or any other agreement between Contractor and Owner.
5.3 In instances where the successful contractor may owe debts (including, but not limited to
taxes or other fees) to Collier County and the contractor has not satisfied nor made arrangement to
satisfy these debts, the County reserves the right to off -set the amount owed to the County by
applying the amount owed to the vendor or contractor for services performed of for materials
delivered in association with a contract,
6. FINAL PAYMENT,
6.1 Owner shall make final payment to Contractor in accordance with Section 218.735, P.S. and
the administrative procedures established by the County's Procurement Services Division and the
Clerk of Court's Finance Department after the Work is finally inspected and accepted by Project
Manager as set forth with Section 20.1 herein, provided that Contractor first, and as an explicit
condition precedent to the accrual of Contractor's right to final payment, shall have furnished Owner
with a properly executed and notarized copy of the Release and Affidavit attached as Exhibit C. as
well as, a duly executed copy of the Surety's consent to final payment and such other documentation
that may be required by the Contract Documents and the Owner. Prior to release of final payment
and final retainage, the Contractor's Representative and the Project Manager shall jointly complete
the Final Payment Checklist, a representative: copy of which is attached to this Agreement as Exhibit
G.
6.2 Contractor's acceptance of final payment shall constitute a full waiver of any and all claims
by Contractor against Owner arising out of this Agreement or otherwise relating to the Project, except
those previously made in writing in accordance with the requirements of the Contract Documents
and identified by Contractor as unsettled in its final Application for Payment. Neither the acceptance
of the Work nor payment by Owner shall be deemed to be a waiver of Owner's right to enforce any
obligations of Contractor hereunder or to the recovery of damages for defective Work not discovered
by the Design Professional or Project Manager at the time of final inspection.
33
Construction Services Agreement; Revised 02209$ ,r3�
7. SUBMITTALS AND SUBSTITUTIONS.
7.1 Contractor shall carefully examine the Contract Documents for all requirements for approval
of materials to be submitted such as shop drawings, data, test results, schedules and samples.
Contractor shall submit all such materials at its own expense and in such form as required by the
Contract Documents in sufficient time to prevent any delay in the delivery of such materials and the
installation thereof,
7,2 Whenever materials or equipment are specified or described in the Contract Documents by
using the name of a proprietary item or the name of a particular supplier, the naming of the item is
intended to establish the type, function and quality required. Unless the name is followed bywords
indicating that no substitution is permitted, materials or equipment of other suppliers may be
accepted by Owner if sufficient information is submitted by Contractor to allow the Owner to
determine that the material or equipment proposed is equivalent or equal to that named. Requests
for review of substitute items of material and equipment will not be accepted by Owner from anyone
other than Contractor and all such requests must be submitted by Contractor to Project Manager
within thirty (30) calendar days after Notice of Award is received by Contractor, unless otherwise
mutually agreed in writing by Owner and Contractor.
7.3 If Contractor wishes to furnish or use a substitute item of material or equipment, Contractor
shall make application to the Project Manager for acceptance thereof, certifying that the proposed
substitute shall adequately perform the functions and achieve the results called for by the general
design, be similar and of equal substance to that specified and be suited to the same use as that
specified. The application shall state that the evaluation and acceptance of the proposed substitute
will not prejudice Contractor's achievement of substantial completion on time, whether or not
acceptance of the substitute for use in the Work will require a change in any of the Contract
Documents (or in the provisions of any other direct contract with Owner for the Project) to adapt the
design to the proposed substitute and whether or not incorporation or use by the substitute in
connection with the Work is subject to payment of any license fee or royalty. All variations of the
proposed substitute from that specified will be identified in the application and available maintenance,
repair and replacement service shall be indicated. The application also shall contain an itemized
estimate of all costs that will result directly or indirectly from acceptance of such substitute, including
costs for redesign and claims of other contractors aftected by the resulting change, all of which shall
be considered by the Project Manager in evaluating the proposed substitute, The Project Manager
may require~ Contractor to furnish at Contractor's expense additional data about the proposed
substitute.
7A If a specific means, method, technique, sequence or procedure of construction is indicated
in or required by the Contract Documents, Contractor may furnish or utilize a substitute means,
method, sequence, technique or procedure of construction acceptable to the Project Manager, if
Contractor submits sufficient information to allow the Project Manager to determine that the
substitute proposed is equivalent to that indicated or required by the Contract Documents. The
procedures for submission to and review by the Project Manager shall be the same as those provided
herein for substitute materials and equipment.
7.5 The Project Manager shall be allowed a reasonable time within which to evaluate each
proposed substitute and, if need be, to consult with the Design Professional, No substitute will be
ordered, installed or utilized without the Project Managers prior written acceptance which shall be
evidenced by a Change Order, a Work Directive Change, a Field Order or an approved Shop
Drawing. The Owner may require Contractor to furnish at Contractor's expense a special
performance guarantee or other surety with respect to any substitute. The Project Manager will
34
Construction Services Agreement: Revised 022018
record time required by the Project Manager and the Project Manager's consultants in evaluating
substitutions proposed by Contractor and making changes In the Contract Documents occasioned
thereby. Whether or not the Owner accepts a proposed substitute, Contractor shall reimburse Owner
for the charges of the Design Professional and the Design Professional's consultants for evaluating
each proposed substitute.
S. DAILY REPORTS, SIGNED AND SEALED AS-BUILTS AND MEETINGS.
8.1 Unless waived in writing by Owner, Contractor shall complete and submit to Project Manager
on a weekly basis a daily log of the Contractor's work for the preceding week in a format approved
by the Project Manager. The daily log shall document all activities of Contractor at the Project site
including, but not limited to, the following;
8,1,1 Weather conditions showing the high and low temperatures during work hours,
the amount of precipitation received on the Project site, and any other weather conditions which
adversely affect the Work;
8.1.2 Soil conditions which adversely affect the Work;
8.13 The hours of operation by Contractor's and Sub -Contractor's personnel;
8.1.4 The number of Contractor's and Sub -Contractor's personnel present and working
at the Project site, by subcontract and trade,
8.1.5 All equipment present at the Project site, description of equipment use and
designation of time equipment was used (specifically indicating any down time);
8.1.6
Description of Work being performed at the Project site;
8.1.7
Any unusual or special occurrences at the Project site;
8.13
Materials received at the Project site;
8.1.9
A list of all visitors to the Project
8.1.10
Any problems that might impact either the cost or quality of the Work or the time
of performance.
The daily log shall
not constitute nor take the place of any notice required to be given by Contractor
to Owner pursuant to the Contract Documents.
8.2 Contractor shall maintain in a safe place at the Project site one record copy of the Contract
Documents, including, but not limited to, all drawings, specifications, addenda, amendments,
Change Orders, Work Directive Changes and Field Orders, as well as all written interpretations and
clarifications issued by the Design Professional, in good order and annotated to snow all changes
made during construction. The annotated drawings shall be continuously updated by the Contractor
throughout the prosecution of the Work to accurately reflect all field changes that are made to adapt
the Work to field conditions, changes resulting from Change Orders, Work Directive Changes and
Field Orders, and all concealed and buried installations of piping, conduit and utility services. All
buried and concealed items, both inside and outside the Project site, shall be accurately located on
the annotated drawings as to depth and in relationship to not less than two (2) permanent features
35�
Canstruc ion Serviees Agreement. Revised 022018
(e.g. interior or exterior wall faces). The annotated drawings shall be clean and all changes,
corrections and dimensions shall be given in a neat and legible manner in a contrasting color. The
"As -Built" record documents, together with all approved samples and a counterpart of all approved
shop drawings sha4l be available to the Project Manager or Design Professional for reference. Upon
completion of the Work and as a condition precedent to Contractor's entitlement to final payment,
these "As -Built" record documents, samples and shop drawings shall be delivered to Project
Manager by Contractor for Owner.
8.3 Contractor shall keep all records and supporting documentation, which concern or relate to
the Work hereunder for a minimum of five (5) years from the date of termination of this Agreement
or the date the Project is completed or such longer period as may be required by law, whichever is
later, pursuant to Florida Public Records Law Chapter 119 and comply with specifically those
contractual requirements in 119.0701(2)(a) -(b) as follows:
IF THE CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION OF
CHAPTER 119, FLORIDA STATUTES, TO THE CONTRACTOR'S DUTY TO PROVIDE
PUBLIC RECORDS RELATING TO THIS CONTRACT, CONTACT THE CUSTODIAN OF
PUBLIC RECORDS AT:
Communication and Customer Relations Division
3299 Tamiami Trail East, Suite 102
Naples, FL 34112-5746
Telephone: (239) 252-8383
The Contractor must specifically comply with the Florida Public Records Law to:
1. Keep and maintain public records required by the public agency to perform the service.
2. Upon request from the public agency's custodian of public records, provide the public
agency with a copy of the requested records or allow the records to be inspected or
copied within a reasonable time at a cost that does not exceed the cost provided in this
chapter or as otherwise provided by law.
3. Ensure that public records that are exempt or confidential and exempt from public
records disclosure requirements are not disclosed except as authorized by law for the
duration of the contract term and following completion of the contract if the Contractor
does not transfer the records to the public agency.
4. Upon completion of the contract, transfer, at no cost, to the public agency all public
records in possession of the Contractor or keep and maintain public records required by
the public agency to perform the service. If the Contractor transfers all public records to
the public agency upon completion of the contract, the Contractor shall destroy any
duplicate public records that are exempt or confidential and exempt from public records
disclosure requirements. If the Contractor keeps and maintains public records upon
completion of the contract, the Contractor shall meet all applicable requirements for
retaining public records. All records stored electronically must be provided to the public
agency, upon request from the public agency's custodian of public records, in a format
that is compatible with the information technology systems of the public agency,
9. CONTRACT TIME AND TIME EXTENSIONS.
9.1 Contractor shall diligently pursue the completion of the Work and coordinate the Work being
done on the Project by its subcontractors and material -men, as well as coordinating its Work with all
as ��
Construction Services Agreement: Revised 022018
work of others at the Project Site, so that its Work or the work of others shall not be delayed or
impaired by any act or omission by Contractor. Contractor shall be solely responsible for all
construction means, methods, techniques, sequences, and procedures, as well as coordination of
all portions of the Work under the Contract Documents, and the coordination of Owner's suppliers
and contractors as set forth in Paragraph 12.2. herein.
9.2 Should Contractor be obstructed or delayed in the prosecution of or completion of the Work
as a result of unforeseeable causes beyond the control of Contractor, and not due to its fault or
neglect, including but not restricted to acts of Nature or of the public enemy, acts of government,
fires, floods, epidemics, quarantine regulation, strikes or lockouts, Contractor shall notify the Owner
in writing within forty-eight (48) hours after the commencement of such delay, stating the cause or
causes thereof, or be deemed to have waived any right which Contractor may have had to request
a time extension.
9.3 No interruption, interference, inefficiency, suspension or delay in the commencement or
progress of the Work from any cause whatever, including those for which Owner may be responsible,
in whole or in part, shall relieve Contractor of its duty to perform or give rise to any right to damages
or additional compensation from Owner. Contractor expressly acknowledges and agrees that it shall
receive no damages for delay. Contractor's sole remedy, if any, against Owner will be the right to
seek an extension to the Contract Time; provided, however, the granting of any such time extension
shall not be a condition precedent to the aforementioned "No Damage For Delay" provision. This
paragraph shall expressly apply to claims for early completion, as well as to claims based on late
completion.
9A In no event shall any approval by Owner authorizing Contractor to continue performing Work
under this Agreement or any payment issued by Owner to Contractor be deemed a waiver of any
right or claim Owner may have against Contractor for delay damages hereunder.
10. CHANGES IN THE WORK.
10.1 Owner shall have the right at any time during the progress of the Work to increase or
decrease the Work_ Promptly after being notified of a change, Contractor shall submit an itemized
estimate of any cost or time increases or savings it foresees as a result of the change. Except in an
emergency endangering life or property, or as expressly set forth herein, no addition or changes to
the Work shall be made except upon written order of Owner, and Owner shall not be liable to the
Contractor for any increased compensation without such written order. No officer, employee or agent
of Owner is authorized to direct any extra or changed work orally, Any alleged changes must be
approved by Owner in writing prior to starting such items. Owner will not be responsible for the costs
of any changes commenced without Owner's express prior written approval. Failure to obtain such
prior written approval for any changes will be deemed: (i) a waiver of any claim by Contractor for
such items and (ii) an admission by Contractor that such items are in fact not a change but rather
are part of the Work required of Contractor hereunder.
10.2 A Change Order, in the form attached as Exhibit E to this Agreement, shall be issued and
executed promptly after an agreement is reached between Contractor and Owner concerning the
requested changes. Contractor shall promptly perform changes authorized by duly executed Change
Orders, The Contract Amount and Contract Time shall be adjusted in the Change Order in the
manner as Owner and Contractor shall mutually agree.
10.3 If Owner and Contractor are unable to agree on a Change Order for the requested change,
Contractor shall, nevertheless, promptly perform the change as directed by Owner in a written Work
37 p�
GonsMicllon 8"ices Agreement: Revised 022018
Directive Change. In that event, the Contract Amount and Contract Time shall be adjusted as
directed by Owner. If Contractor disagrees with the Owner's adjustment determination, Contractor
must make a claim pursuant to Section 11 of these General Conditions or else be deemed to have
waived any claim on this matter it might otherwise have had.
10,4 In the event a requested change results in an increase to the Contract Amount, the amount
of the increase shall be limited to the Contractor's reasonable direct labor and material costs and
reasonable actual equipment costs as a result of the change (including allowance for labor burden
costs) plus a maximum ten percent (10%) markup for all overhead and profit. In the event such
change Work is performed by a Subcontractor, a maximum ten percent (10%) markup for all
overhead and profit for all Subcontractors' and sub -subcontractors' direct labor and material costs
and actual equipment costs shall be permitted, with a maximum five percent (5%) markup thereon
by the Contractor for all of its overhead and profit, for a total maximum markup of fifteen percent
(15%). All compensation due Contractor and any Subcontractor or sub -subcontractor for fleld and
home office overhead is included in the markups noted above. Contractor's and Sub -Contractor's
bond costs associated with any change order shall be included in the overhead and profit expenses
and shall not be paid as a separate line item. No markup shall be placed on sales tax, shipping or
subcontractor markup.
10.5 Owner shall have the right to conduct an audit of Contractor's books and records to verify the
accuracy of the Contractor's claim with respect to Contractor's costs associated with any Change
Order or Work Directive Change,
10.6 The Project Manager shall have authority to order minor changes in the Work not involving
an adjustment to the Contract Amount or an extension to the Contract Time and not inconsistent with
the intent of the Contract Documents. Such changes may be effected by Field Order or by other
written order. Such changes shall be binding on the Contractor.
10.7 Any modifications to this Contract shall be in compliance with the County procurement
ordinance and policies and Administrative procedures in effect at the time such modifications are
authorized.
11. CLAIMS AND DISPUTES.
11.1 Claim is a demand or assertion by one of the parties seeking an adjustment or interpretation
of the terms of the Contract Documents, payment of money, extension of time or other relief with
respect to the terms of the Contract documents. The term "Claim" also includes other disputes and
matters in question between Owner and Contractor arising out of or relating to the Contract
Documents. The responsibility to substantiate a Claim shall rest with the party making the Claim.
11.2 Claims by the Contractor shall be made in writing to the Project Manager within forty-eight
(48) hours from when the Contractor knew or should have known of the event giving rise to such
Claim or else the Contractor shall be deemed to have waived the Claim. Written supporting data
shall be submitted to the Project Manager within fifteen (15) calendar days after the occurrence of
the event, unless the Owner grants additional time in writing, or else the Contractor shall be deemed
to have waived the Claim, Ail Claims shall be priced in accordance with the provisions of Subsection
10.4.
11.3 The Contractor shall proceed diligently with its performance as directed by the Owner,
regardless of any pending C4m, action, suit or administrative proceeding, unless otherwise agreed
39 25
Construction Services Agreement: Revised 022018
to by the Owner in writing. Owner shall continue to make payments in accordance with the Contract
Documents during the pendency of any Claim.
12. OTHER WORK.
12.1 Owner may perform other work related to the Project at the site by Owner's own forces, have
other work performed by utility owners or let other direct contracts. If the fact that such other work
is to be performed is not noted in the Contract Documents, written notice thereof will be given to
Contractor prior to starting any such other work. If Contractor believes that such performance will
involve additional expense to Contractor or require additional time, Contractor shall send written
notice of that fact to Owner and Design Professional within forty-eight (48) hours of being notified of
the other work. If the Contractor fails to send the above required forty-eight (48) hour notice, the
Contractorwill be deemed to havewaived any rights it otherwise may have had to seek an extension
to the Contract Time or adjustment to the Contract Amount.
12.2 Contractor shall afford each utility owner and other contractor who is a party to such a direct
contract (or Owner, if Owner is performing the additional work with Owner's employees) proper and
safe access to the site and a reasonable opportunity for the introduction and storage of materials
and equipment and the execution of such work and shall properly connect and coordinate its Work
with theirs. Contractor shall do all cutting, fitting and patching of the Work that may be required to
make its several parts come together properly and integrate with such other work. Contractor shall
not endanger any work of others by cutting, excavating or otherwise altering their work and will only
cut or alter their work with the written consent of the Project Manager and the others whose work will
be affected. The duties and responsibilities of Contractor under this paragraph are for the benefit of
such utility owners and other Contractors to the extent that there are comparable provisions for the
benefit of Contractor in said direct contracts between Owner and such utility owners and other
contractors.
12,3 If any part of Contractor's Work dependsfor proper execution or results upon the work of any
other contractor or utility owner (or Owner), Contractor shall inspect and promptly report to Project
Manager in writing any delays, defects or deficiencies in such work that render it unavailable or
unsuitable for such proper execution and results. Contractor's failure to report will constitute an
acceptance of the other work as fit and properfor integration with Contractor's Work_
13. INDEMNIFICATION AND INSURANCE.
13.1 To the maximum extent permitted by Florida law, the ContractorNendor/Consultant shall
defend, indemnify and hold harmless Collier County, its officers and employees from any and all
liabilities, damages, losses and costs, including, but not limited to, reasonable attorneys' fees and
paralegals' fees, to the extent caused by the negligence, recklessness, or intentionally wrongful
conduct of the Contractor/Vendor/Consultant or anyone employed or utilized by the
ContractorNendor/Consultant in the performance of this Agreement.
13.2 The duty to defend under this Article 13 is independent and separate from the duty to
indemnify, and the duty to defend exists regardless of any ultimate liability of the Contractor, Owner
and any indemnified party. The duty to defend arises immediately upon presentation of a claim by
any party and written notice of such claim being provided to Contractor. Contractor's obligation to
indemnify and defend under this Article 13 will survive the expiration or earlier termination of this
Agreement until it is determined by final judgment that an action against the Owneror an indemnified
party for the matter indemnified hereunder is fully and finally barred by the applicable statute of
limitations.
39 Q
Construction Services Agreement: Revised 022018
13.3 Contractor shall obtain and carry, at all times during its performance under the Contract
Documents, insurance of the types and in the amounts set forth in Exhibit B-3 to the Agreement.
Further, the Contractor shall at all times comply with all of the terms, conditions, requirements and
obligations set forth under Exhibit B-3.
14, COMPLIANCE WITH LAWS.
14.1 Contractor agrees to comply, at its own expense, with all federal, state and local laws, codes,
statutes, ordinanoes, rules, regulations and requirements applicable to the Project, including but not
limited to those dealing with taxation, worker's compensation, equal employment and safety
(including, but not limited to, the Trench Safety Act, Chapter 553, Florida Statutes). If Contractor
observes that the Contract Documents are at variance therewith, it shall promptly notify Project
Manager in writing, To the extent any law, rule, regulation, code, statute, or ordinance requires the
inclusion of certain terms in this Agreement in order for this Agreement to be enforceable, such terms
shall be deemed included in this Agreement. Notwithstanding anything in the Contract Documents
to the contrary, it is understood and agreed that in the event of a change in any applicable laws,
ordinances, rules or regulations subsequent to the date this Agreement was executed that increases
the Contractor's time or cost of performance of the Work, Contractor is entitled to a Change Order
for such increases, except to the extent Contractor knew or should have known of such changes
prior to the date of this Agreement.
14.2 By executing and entering into this agreement, the Contractor is formally acknowledging
without exception or stipulation that it is fully responsible for complying with the provisions of the
Immigration Reform and Control Act of 1986 as located at 8 U.S,C. 1324, et seg- and regulations
relating thereto, as either may be amended. Failure by the Contractor to comply with the laws
referenced herein shall constitute a breach of this agreement and the County shall have the
discretion to unilaterally terminate this agreement immediately.
14,3 Statutes and executive orders require employers to abide by the immigration laws of the United
States and to employ only individuals who are eligible to work in the United States,
The Employment Eligibility Verification System (E-Verify) operated by the Department of Homeland
Security (DHS) in partnership with the Social Security Administration (SSA), provides an Internet-
based means of verifying employment eligibility of workers in the United States; it is not a substitute
for any other employment eligibility verification requirements. The program will be used for Collier
County formal Invitations to Bid (ITB) and Request for Proposals (RFP) including professional
services and construction services.
Exceptions to the program:
• Commodity based procurement where no services are provided.
• Where the requirement for the affidavit is waived by the Board of County Commissioners
Contractors/ Bidders are required to enroll in the E-Verify program, and provide acceptable evidence
of their enrollment, at the time of the submission of the Contractor'slbidder's proposal. Acceptable
evidence consists of a copy of the properly completed E-Verify Company Profile page or a copy of
the fully executed E-Verify Memorandum of Understanding for the company, Contractors are also
required to provide the Collier County Procurement Services Division an executed affidavit certifying
they shall comply with the E-Verify Program. The affidavit is attached to the solicitation documents.
If the Bidder/Contractor does not comply with 12rovidling both the acceptable E-Verily
evidence and the executed affidavit the bidder's 1 Contractor's proposal may be deemed non-
responsive.
40
Cnnstructlon SBNICBS Agreement: Revised 022018 t ��"
Additionally, Contractors shall require all subcontracted Contractors to use the E -Verify system for
all purchases not covered under the "Exceptions to the program" clause above.
For additional information regarding the Employment Eligibility Verification System (E -Verify)
program visit the following website: http,Jlwww,dhs,goylE _Verify. It shall be the Contractor's
responsibility to familiarize themselves with all rules and regulations governing this program.
Contractor acknowledges, and without exception or stipulation, any firm(s) recelving an award shall
be fully responsible for complying with the provisions of the Immigration Reform and Control Act of
1986 as located at 8 U.S.C. 1324, et sea. and regulations relating thereto, as either may be amended
and with the provisions contained within this affidavit. Failure by the awarded firm(s) to comply with
the laws referenced herein or the provisions of this affidavit shall constitute a breach of the award
agreement and the County shall have the discretion to unilaterally terminate said agreement
immediately.
15. CLEANUP AND PROTECTIONS.
15.1 Contractor agrees to keep the Project site clean at all times of debris, rubbish and waste
materials arising out of the Work. At the completion of the Work, Contractor shall remove all debris,
rubbish and waste materials from and about the Project site, as well as all tools, appliances,
construction equipment and machinery and surplus materials, and shall leave the Project site clean
and ready for occupancy by Owner.
15.2 Any existing surface or subsurface improvements, including, but not limited to, pavements,
curbs, sidewalks, pipes, utilities, footings, structures, trees and shrubbery, not indicated in the
Contract Documents to be removed or altered, shall be protected by Contractor from damage during
the prosecution of the Work. Subject to the Section 2.3 above, any such improvements so damaged
shall be restored by Contractor to the condition equal to that existing at the time of Contractor's
commencement of the Work.
FC�3*11 [CIZ BJ;R kv
16.1 Contractor shall not assign this Agreement or any part thereof, without the prior consent in
writing of Owner. Any attempt to assign or otherwise transfer this Agreement, or any part herein,
without the Owner's consent, shall be void. If Contractor does, with approval, assign this Agreement
or any part thereof, it shall require that its assignee be bound to it and to assume toward Contractor
all of the obligations and responsibilities that Contractor has assumed toward Owner.
17. PERMITS, LICENSES AND TAXES.
17.1 Pursuant to Section 218.80, F,S., Owner will pay for all Collier County permits and fees,
including license fees, permit fees, impact fees or inspection fees applicable to the Work through an
internal budget transfer(s). Contractor is not responsible for paying for permits issued by Collier
County, but Contractor is responsible for acquiring all permits. Owner may require the Contractor to
deliver internal budget transfer documents to applicable Collier County agencies when the
Contractor is acquiring permits. Owner will not be obligated to pay for any permits obtained by
Subcontractors.
17.2 All permits, fees and licenses necessary for the prosecution of the Work which are not issued
by Collier County shall be acquired and paid for by the Contractor,
41
Construction Services Agreement: Revised 022016
C*
17.3 Contractor shall pay all sales, consumer, use and other similar taxes associated with the
Work or portions thereof, which are applicable during the performance of the Work.
18. TERMINATION FOR DEFAULT.
18.1 Contractor shall be considered in material default of the Agreement and such default shall be
considered cause for Owner to terminate the Agreement, in whole or in part, as further set forth in
this Section, if Contractor: (1) fails to begin the Work under the Contract Documents within the time
specified herein; or (2) fails to properly and timely perform the Work as directed by the Project
Manager or as provided for in the approved Progress Schedule; or (3) performs the Work unsuitably
or neglects or refuses to remove materials or to correct or replace such Work as may be rejected as
unacceptable or unsuitable; or (4) discontinues the prosecution of the Work; or (5) fails to resume
Work which has been suspended within a reasonable time after being notified to do so; or (6)
becomes insolvent or is declared bankrupt, or commits any act of bankruptcy; or (7) allows any final
judgment to stand against it unsatisfied for more than ten (10) days; or (8) makes an assignment for
the benefit of creditors; or (9) fails to obey any applicable codes, laws, ordinances, rules or
regulations with respect to the Work; or (10) materially breaches any other provision of the Contract
Documents.
18.2 Owner shall notify Contractor in writing of Contractor's default(s). If Owner determines that
Contractor has not remedied and cured the default(s) within seven (7) calendar days following receipt
by Contractor of said written notice or such longer period of time as may be consented to by Owner
in writing and in its sole discretion, then Owner, at its option, without releasing or waiving its rights
and remedies against the Contractor's sureties and without prejudice to any other right or remedy it
may be entitled to hereunder or by law, may terminate Contractor's right to proceed under the
Agreement, in whole or in part, and take possession of all or any portion of the Work and any
materials, tools, equipment, and appliances of Contractor, take assignments of any of Contractor's
subcontracts and purchase orders, and complete all or any portion of Contractor's Work by whatever
means, method or agency which Owner, in its sole discretion, may choose.
18.3 If Owner deems any of the foregoing remedies necessary, Contractor agrees that it shall not
be entitled to receive any further payments hereunder until after the Project is completed. All moneys
expended and all of the costs, losses, damages and extra expenses, including all management,
administrative and other overhead and other direct and indirect expenses (including Design
Professional and attorneys' fees) or damages incurred by Owner incident to such completion, shall
be deducted from the Contract Amount, and if such expenditures exceed the unpaid balance of the
Contract Amount, Contractor agrees to pay promptly to Owner on demand the full amount of such
excess, including costs of collection, attorneys' fees (Including appeals) and interest thereon at the
maximum legal rate of interest until paid. If the unpaid balance of the Contract Amount exceeds all
such costs, expenditures and damages incurred by the Owner to complete the Work, such excess
shall be paid to the Contractor. The amount to be paid to the Contractor or Owner, as the case may
be, small be approved by the Project Manager, upon application, and this obligation for payment shall
survive termination of the Agreement.
18.4 The liability of Contractor hereunder shall extend to and include the full amount of any and
all sums paid, expenses and losses incurred, damages sustained, and obligations assumed by
Owner in good faith under the belief that such payments or assumptions were necessary or required,
in completing the Work and providing labor, materials, equipment, supplies, and other items therefore
or re -letting the Work, and in settlement, discharge or compromise of any claims, demands, suits,
and judgments pertaining to or arising out of the Work hereunder.
42 Q Construction Services Agreement: Revised 022018
18.5 If, after notice of termination of Contractor's right to proceed pursuant to this Section, it is
determined for any reason that Contractor was not in default, or that its default was excusable, or
that Owner is not entitled to the remedies against Contractor provided herein, then the termination
will be deemed a termination for convenience and Contractor's remedies against Owner shall be the
same as and limited to those afforded Contractor under Section 19 below,
18.6 In the event (i) Owner fails to make any undisputed payment to Contractor within thirty (30)
days after such payment is due or Owner otherwise persistently fails to fulfill some material obligation
owed by Owner to Contractor under this Agreement, and (ii) Owner has failed to cure such default
within fourteen (14) days of receiving written notice of same from Contractor, then Contractor may
stop its performance under this Agreement until such default is cured, after giving Owner a second
fourteen (14) days written notice of Contractor's intention to stop performance underthe Agreement,
If the Work is so stopped for a period of one hundred and twenty (128) consecutive days through no
act or fault of the Contractor or its Subcontractors or their agents or employees or any other persons
performing portions of the Work under contract with the Contractor or any Subcontractor, the
Contractor may terminate this Agreement by giving written notice to Owner of Contractor's intent to
terminate this Agreement. If Owner does not cure its default within fourteen (14) days after receipt
of Contractor's written notice, Contractor may, upon fourteen (14) additional days' written notice to
the Owner, terminate the Agreement and recover from the Owner payment for Work performed
through the termination date, but in no event shall Contractor be entitled to payment for Work not
performed or any other damages from Owner.
19, TERMINATION FOR CONVENIENCE AND RIGHT OF SUSPENSION.
19.1 Owner shall have the right to terminate this Agreement without cause upon seven (7)
calendar days written notice to Contractor. In the event of such termination for convenience,
Contractor's recovery against Owner shall be limited to that portion of the Contract Amount earned
through the date of termination, together with any retainage withheld and reasonable termination
expenses incurred, but Contractor shall not be entitled to any other or further recovery against
Owner, including, but not limited to, damages or any anticipated profit on portions of the Work not
performed.
19.2 Owner shall have the right to suspend all or any portions of the Work upon giving Contractor
not less than two (2) calendar days' prior written notice of such suspension. If all or any portion of
the Work is so suspended, Contractor's sole and exclusive remedy shall be to seek an extension of
time to its schedule in accordance with the procedures set forth in the Contract Documents. In no
event shall the Contractor be entitled to any additional compensation or damages. Provided,
however, if the ordered suspension exceeds six (6) months, the Contractor shall have the right to
terminate the Agreement with respect to that portion of the Work which is subject to the ordered
suspension.
20. COMPLETION.
20.1 When the entire Work (or any portion thereof designated in writing by Owner) is ready for its
intended use, Contractor shall notify Project Manager in writing that the entire Work (or such
designated portion) is substantially complete. Within a reasonabletime thereafter, Owner, Contractor
and Design Professional shall make an inspection of the Work (or designated portion thereof) to
determine the status of completion. If Owner, after conferring with the Design Professional, does
not consider the Work (or designated portion) substantially complete, Project Manager shall notify
Contractor in writing giving the reasons therefore. If Owner, after conferring with the design
Professional, considers the Work (or designated portion) substantially complete, Project Manager
43
ConstruCtien Services Agreement: lReAsed 022018
0
shall prepare and deliver to Contractor a Certificate of Substantial Completion which shall fix the
date of Substantial Completion for the entire Work (or designated portion thereof) and include a
tentative punch -list of items to be completed or corrected by Contractor before final payment. Owner
shall have the right to exclude Contractor from the Work and Project site (or designated portion
thereof) after the date of Substantial Completion, but Owner shall allow Contractor reasonable
access to complete or correct items on the tentative punch -list. The Project Manager, shall
coordinate with the Contractor the return of any surplus assets, including materials, supplies, and
equipment.
20,2 Upon receipt of written certification by Contractor that the Work is completed in accordance
with the Contract Documents and is ready for final inspection and acceptance, Project Manager and
Design Professional will make such inspection and, if they find the Work acceptable and fully
performed under the Contract Documents shall promptly approve payment, recommending that, on
the basis of their observations and inspections, and the Contractor's certification that the Work has
been completed in accordance with the terms and conditions of the Contract Documents, that the
entire balance found to be due Contractor is due and payable. Neither the final payment nor the
retainage shall become due and payable until Contractor submits,
(1) Receipt of Contractor's Final Application for Payment.
(2) The Release and Affidavit in the form attached as Exhibit C.
(3) Consent of surety to final payment.
(4) Receipt of the final payment check list.
(5) If required by Owner, other data establishing payment or satisfaction of all obligations,
such as receipts, releases and waivers of liens, arising out of the Contract
Documents, to the extent and in such form as may be designated by Owner.
Owner reserves the right to inspect the Work and make an independent determination as to the
Work's acceptability, even though the Design Professional may have issued its recommendations.
Unless and until the Owner is completely satisfied, neither the final payment nor the retainage shall
become due and payable.
21. WARRANTY,
21.1 Contractor shall obtain and assign to Owner all express warranties given to Contractor or any
subcontractors by any subcontractor or material men supplying materials, equipment or fixtures to
be incorporated into the Project. Contractor warrants to Owner that any materials and equipment
furnished under the Contract Documents shall be new uniessotherwise specified, and that all Work
shall be of good quality, free from all defects and in conformance with the Contract documents,
Contractor further warrants to Owner that all materials and equipment furnished under the Contract
Documents shall be applied, installed, connected, erected, used, cleaned and conditioned in
accordance with the instructions of the applicable manufacturers, fabricators, suppliers or processors
except as otherwise provided for in the Contract Documents. If, within one (1) year after Substantial
Completion, any Worts is found to be defective or not in conformance with the Contract Documents,
Contractor shall correct it promptly after receipt of written notice from Owner. Contractor shall also
be responsible for and pay for replacement or repair of adjacent materials or Work which may be
damaged as a result of such replacement or repair. Further, in the event of an emergency, Owner
may commence to correct any defective Work, without prior notice to Contractor, at Contractor's
expense. These warranties are in addition to those implied warranties to which Owner is entitled as
a matter of law.
44
Construction Services Agreernanl, Revised 022018 T
21.2 No later than 30 days prior to expiration of the warranty, the Project Manager, or another
representative of the Owner, shall conduct an inspection of the warranted work to verify compliance
with the requirements of the Agreement. The Contractor's Representative shall be present at the
time of inspection and shall take remedial actions to correct any deficiencies noted in the inspection.
Failure of the Contractor to correct the cited deficiencies shall be grounds for the Owner to disqualify
the Contractor from future bid opportunities with the Owner, in addition to any other rights and
remedies available to Owner.
22. TESTS AND INSPECTIONS,
22.1 Owner, Design Professional, their respective representatives, agents and employees, and
governmental agencies with jurisdiction over the Project shall have access at all times to the Work,
whether the Work is being performed on or off of the Project site, for their observation, inspection
and testing. Contractor shall provide proper, safe conditions for such access. Contractor shall
provide Project Manager with timely notice of readiness of the Work for all required inspections, tests
or approvals.
22.2 If the Contract Documents or any codes, laws, ordinances, rules or regulations of any public
authority having jurisdiction over the Project requires any portion of the Work to be specifically
inspected, tested or approved, Contractor shall assume full responsibility therefore, pay all costs in
connection therewith and furnish Project Manager the required certificates of inspection, testing or
approval. All inspections, tests or approvals shall be performed in a manner and by organizations
acceptable to the Project Manager.
22.3 Contractor is responsible, without reimbursement from Owner, for re -inspection fees and
costs; to the extent such re -inspections are due to the fault or neglect of Contractor.
22.4 If any Work that is to be inspected, tested or approved is covered without written concurrence
from the Project Manager, such work must, if requested by Project Manager, be uncovered for
observation. Such uncovering shall be at Contractor's expense unless Contractor has given Project
Manager timely notice of Contractor's intention to coverthe same and Project Manager has not acted
with reasonable promptness to respond to such notice. If any Work is covered contrary to written
directions from Project Manager, such Work must, if requested by Project Manager, be uncovered
for Project Manager's observation and be replaced at Contractor's sole expense.
22.5 The Owner shall charge to Contractor and may deduct from any payments due Contractor all
engineering and inspection expenses incurred by Owner in connection with any overtime work. Such
overtime work consisting of any work during the construction period beyond the regular eight (8) hour
day and for any work performed on Saturday, Sunday or holidays.
22,6 Neither observations nor other actions by the Project Manager or Design Professional nor
inspections, tests or approvals by others shall relieve Contractor from Contractor's obligations to
perform the Work in accordance with the Contract Documents.
23. DEFECTIVE WORK.
23.1 Work not conforming to the requirements of the Contract Documents or any warranties made
or assigned by Contractor to Owner shall be deemed defective Work. If required by project Manager,
Contractor shall as directed, either correct all defective Work, whether or not fabricated, installed or
completed, or if the defective Work has been rejected by Project Manager, remove it from the site
and replace it with non -defective Work. Contractor shall bear all direct, indirect and consequential
45
ConsVucllon Services Agreement: Revised 022018
costs of such correction or removal (including, but not limited to fees and charges of engineers,
architects, attorneys and other professionals) made necessary thereby, and shall hold Owner
harmless for same.
23.2 If the Project Manager considers it necessary or advisable that covered Work be observed
by Design Professional or inspected or tested by others and such Work is not otherwise required to
be inspected or tested, Contractor, at Project Manager's request, shall uncover, expose or otherwise
make available for observation, inspection or tests as Project Manager may require, that portion of
the Work in question, furnishing all necessary labor, material and equipment. If it is found that such
Worst is defective, Contractor shall bear all direct, indirect and consequential costs of such
uncovering, exposure, observation, inspection and testing and of satisfactory reconstruction
(including, but not limited to, fees and charges of engineers, architects, attorneys and other
professionals), and Owner shall be entitled to an appropriate decrease in the Contract Amount. If,
however, such Work is not found to be defective, Contractor shall be allowed an increase in the
Contract Amount and/or an extension to the Contract Time, directly attributableto such uncovering,
exposure, observation, inspection, testing and reconstruction.
23.3 If any portion of the Work is defective, or if Contractor fails to supply sufficient skilled workers,
suitable materials or equipment or fails to finish or perform the Work in such a way that the completed
Work will conform to the Contract Documents, Project Manager may order Contractor to stop the
Work, or any portion thereof, until the cause for such order has been eliminated. The right of Project
Manager to stop the Work shall be exercised, if at all, solely for Owner's benefit and nothing herein
shall be construed as obligating the Project Manager to exercise this right for the benefit of Design
Engineer, Contractor, or any other person.
23.4 Should the Owner determine, at its sole opinion, it is in the Owner's best interest to accept
defective Work, the Owner may do so, Contractor shall bear all direct, indirect and consequential
costs attributable to the Owner's evaluation of and determination to accept defective Work. If such
determination is rendered prior to final payment, a Change Order shall be executed evidencing such
acceptance of such defective Work, incorporating the necessary revisions in the Contract
Documents and reflecting an appropriate decrease in the Contract Amount. If the Owner accepts
such defective Work after final payment, Contractor shall promptly pay Owner an appropriate amount
to adequately compensate Owner for Its acceptance of the defective Work.
23.5 If Contractor fails, within a reasonable time after the written notice from project Manager, to
correct defective Work or to remove and replace rejected defective Work as required by Project
Manager or Owner, or if Contractor fails to perform the Work in accordance with the Contract
Documents, or if Contractor fails to comply with any of the provisions of the Contract Documents,
Owner may, after seven (7) days written notice to Contractor, correct and remedy any such
deficiency. Provided, however, Owner shall not be required to give notice to Contractor in the event
of an emergency. To the extent necessary to complete corrective and remedial action, Owner may
exclude Contractor from any or all of the Project site, take possession of all or any part of the Work,
and suspend Contractor's services related thereto, take possession of Contractor's tools, appliances,
construction equipment and machinery at the Project site and incorporate in the Work all materials
and equipment stored at the Project site or forwhich Owner has paid Contractor but which are stored
elsewhere. Contractor shall allow Owner, Design Professional and their respective representatives,
agents, and employees such access to the Project site as may be necessary to enable Owner to
exercise the rights and remedies under this paragraph. All direct, indirect and consequential costs
of Owner in exercising such rights and remedies shall be charged against Contractor, and a Change
Order shall be issued, incorporating the necessary revisions to the Contract Documents, including
an appropriate decrease to the Contract Amount. Such direct, indirect and consequential costs shall
4s
0onstrUG1100 Services Agreement: Revised 022018
O
include, but not be limited to, fees and charges of engineers, architects, attorneys and other
professionals, all court costs and all costs of repair and replacement of work of others destroyed or
damaged by correction, removal or replacement of Contractor's defective Work, Contractor shall not
be allowed an extension of the Contract Time because of any delay in performance of the Work
attributable to the exercise by Owner of Owner's rights and remedies hereunder.
24. SUPERVISION AND SUPERINTE=NDENTS.
24,1 Contractor shall plan, organize, supervise, schedule, monitor, direct and control the Work
competently and efficiently, devoting such attention thereto and applying such skills and expertise
as may be necessary to perform the Work in accordance with the Contract Documents. Contractor
shall be responsible to see that the finished Work complies accurately with the Contract Documents.
Contractor shall keep on the Work at all times during its progress a competent resident
superintendent, who shall be subject to Owner's approval and not be replaced without prior written
notice to Project Manager except under extraordinary circumstances. The superintendent shall be
employed by the Contractor and be the Contractor's representative at the Project site and shall have
authority to act on behalf of Contractor, All communications given to the superintendent shall be as
binding as if given to the Contractor. Owner shall have the right to direct Contractor to remove and
replace its Project superintendent, with or without cause. Attached to the Agreement as Exhibit. A-1
is a list identifying Contractor's Project Superintendent and all of Contractor's key personnel who are
assigned to the Project; such identified personnel shall not be removed without Owner's prior written
approval, and if so removed must be immediately replaced with a person acceptable to Owner.
24.2 Contractor shall have a competent superintendent on the project at all times whenever
contractor's work crews, or work crews of other parties authorized by the Project Manager are
engaged in any activity whatsoever associated with the Project. Should the Contractor fail to comply
with the above condition, the Project Manager shall, at his discretion, deduct from the Contractor's
monthly pay estimate, sufficient moneys to account for the Owner's loss of adequate project
supervision, not as a penalty, but as liquidated damages, separate from the liquidated damages
described in Section 5.8, for services not rendered.
25. PROTECTION OF WORK.
25.1 'Contractor shall immediately notify Project Manager and Design Professional. The Owner
or Design Professional shall reestablish the benchmarks and Contractor shall be liable for all costs
incurred by Owner associated therewith.
26. EMERGENCIES.
25.1 In the event of an emergency affecting the safety or protection of persons or the Work or
property at the Project site or adjacent thereto, Contractor, without special instruction or authorization
from Owner or Design Professional is obligated to act to prevent threatened damage, injury or loss.
Contractor shall give Project Manager written notice within forty-eight (48) hours after Contractor
knew or should have known of the occurrence of the emergency, if Contractor believes that any
significant changes in the Work or variations from the Contract Documents have been caused
thereby. If the Project Manager determines that a change in the Contract Documents is required
because of the action taken in response to an emergency, a Change Order shall be issued to
document the consequences of the changes or variations. If Contractor fails to provide the forty-eight
(46) hour written notice noted above, the Contractor shall be deemed to have waived any right it
otherwise may have had to seek an adjustment to the Contract Amount or an extension to the
Contract Time.
47
ConStr= ion Services Agreement Revised 022018
27. USE OF PREMISES.
27.1 Contractor shall maintain all construction equipment, the storage of materials and equipment
and the operations of workers to the Project site and land and areas identified in and permitted by
the Contract Documents and other lands and areas permitted by law, rights of way, permits and
easements, and shall not unreasonably encumber the Project site with construction equipment or
other material or equipment. Contractor shall assume full responsibility for any damage to any such
land or area, or to the owner or occupant thereof, or any land or areas contiguous thereto, resulting
from the performance of the Work.
28. SAFETY.
28.1 Contractor shall be responsible for initiating, maintaining and supervising all safety
precautions and programs in connection with the Work. Contractor shall take all necessary
precautions for the safety of, and shall provide the necessary protection to prevent damage, injury
or loss to:
28.1.1 All employees on or about the project site and other persons and/or organizations
who may be affected thereby;
28.1.2 All the Work and materials and equipment to be incorporated therein, whether in
storage on or off the Project site; and
28.1.3 Other property on Project site or adjacent thereto, including trees, shrubs, walks,
pavements, roadways, structures, utilities and any underground structures or improvements not
designated for removal, relocation or replacement in the Contract Documents.
28.2 Contractor shall comply with all applicable codes, laws, ordinances, rules and regulations of
any public body having jurisdiction for the safety of persons or property or to protect them from
damage, injury or loss. Contractor shall erect and maintain all necessary safeguards for such safety
and protection. Contractor shall notify owners of adjacent property and of underground structures
and improvements and utility owners when prosecution of the Work may affect them, and shall
cooperate with them in the protection, removal, relocation or replacement of their property.
Contractor's duties and responsibilities for the safety and protection of the Work shall continue until
such time as the Work is completed and final acceptance of same by Owner has occurred.
All new electrical installations shall incorporate NFPA 70E Short Circuit Protective Device
Coordination and Arc Flash Studies where relevant as determined by the engineer.
All electrical installations shall be labeled with appropriate NFPA 70E arch flash boundary and PPE
Protective labels.
28,3. Contractor shall designate a responsible representative located on a full time basis at the
Project site whose duty shall be the prevention of accidents. This person shall be Contractor's
superintendent unless otherwise designated in writing by Contractor to Owner.
28.4 Alcohol, drugs and all illegal substances are strictly prohibited on any Owner property. All
employees of Contractor, as well as those of all subcontractors and those of any other person or
entity for whom Contractor is legally liable (collectively referred to herein as "Employees"), shall not
possess or be under the influence of any such substances while on any Owner property. Further,
48 0 Construction Services Agreement; Revised 022418
Employees shall not bring on to any Owner property any gun, rifle or other firearm, or explosives of
any kind.
28.5 Contractor acknowledges that the Work may be progressing on a Project site which Is located
upon or adjacent to an existing Owner facility. In such event, Contractor shall comply with the
following,
28.5.1 All Owner facilities are smoke free. Smoking is strictly prohibited;
28,5.2 All Employees shall be provided an identification badge by Contractor. Such
identification badge must be prominently displayed on the outside of the Employees' clothing at all
times. All Employees working at the Project site must log in and out with the Contractor each day;
28.5.3 Contractor shall strictly limit its operations to the designated work areas and
shall not permit any Employees to enter any other portions of Owners property without Owner's
expressed prior written consent;
28,5.4 All Employees are prohibited from distributing any papers or other materials
upon Owner's property, and are strictly prohibited from using any of Owner's telephones or other
office equipment;
28.5.5 All Employees shall at all times comply with the OSHA regulationswith respect
to dress and conduct at the Project site. Further, all Employees shall comply with the dress, conduct
and facility regulations issued by Owner's officials onsite, as said regulations may be changed from
time to time;
28,5.6 All Employees shall enter and leave Owner's facilities only through the ingress
and egress points identified in the site utilization pian approved by Owner or as otherwise designated,
from time to time, by Owner in writing;
28.5.7 When requested, Contractor shall cooperate with any ongoing Owner
investigation involving personal injury, economic loss or damage to Owner's facilities or personal
property therein;
28.5.5 The Employees may not solicit, distribute or sell products while on Owner's
property. Friends, family members or other visitors of the Employees are not permitted on Owner's
property; and
28.5,9 At all times, Contractor shall adhere to Owners safety and security
regulations, and shall comply with all security requirements at Owner's facilities, as said regulations
and requirements may be modified or changed by Owner from time to time.
29. PROJECT MEETINGS.
Prior to the commencement of Work, the Contractor shall attend a pre -construction conference with
the Project Manager, Design Professional and others as appropriate to discuss the Progress
Schedule, procedures for handling shop drawings and other submittals, and for processing
Applications for Payment, and to establish a working understanding among the parties as to the
Work. During the prosecution of the Work, the Contractor shall attend any and all meetings convened
by the Project Manager with respect to the Project, when directed to do so by Project Manager or
4913 Construction Services Agreement: Revised 022018
Design Professional. The Contractor shall have its subcontractors and suppliers attend all such
meetings (including the pre -construction conference) as may be directed by the Project Manager.
30. VENDOR PERFORMANCE EVALUATION.
Owner has implemented a Vendor Performance Evaluation System for all contracts awarded in
excess of $25,000. To this end, vendors will be evaluated on their performance upon
completionhermination of this Agreement.
31. MAINTENANCE OF TRAFFIC POLICY.
For all projects that are conducted within a Collier County Right -of -Way, the Contractor shall provide
and erect Traffic Control Devices as prescribed in the current edition of the Manual On Uniform
Traffic Control Devices (MUTCD), where applicable on focal roadways and as prescribed in the
Florida Department of Transportation's Design Standards (DS), where applicable on state roadways.
These projects shall also comply with Collier County's Maintenance of Traffic Policy, #5507,
incorporated herein by reference. Copies are available through Risk Management and/or
Procurement Services Division, and is available on-line at oolliergov.net/purchasing.
The Contractor will be responsible for obtaining copies of all required manuals, MUTCD, FDOT
Roadway & Traffic Design Standards Indexes, or other related documents, so to became familiar
with their requirements. Strict adherence to the requirements of the Maintenance of Traffic ("MOT")
policy will be enforced under this Contract.
All costs associated with the Maintenance of Traffic shall be included on the line item on the bid
page. if MOT is required, MOT is to be provided within ten (10) days of receipt of Notice of Award.
32, SALES TAX SAVINGS AND DIRECT PURCHASE.
32.1 Contractor shall pay all sales, consumer, use and other similar taxes associated with the
Work or portions thereof, which are applicable during the performance of the Work. No markup shall
be applied to sales tax. Additionally, as directed by Owner and at no additional cost to Owner,
Contractor shall comply with and fully implement the sales tax savings program with respect to the
Work, as set forth in section 32.2 below;
32.2 Notwithstanding anything herein to the contrary, because Owner is exempt from sales tax
and may wish to generate sales tax savings for the Project, Owner reserves the right to make direct
purchases of various construction materials and equipment included in the Work ("Direct Purchase").
Contractor shall prepare purchase orders to vendors selected by Contractor, for execution by Owner,
on forms provided by Owner. Contractor shall allow two weeks for execution of all such purchase
orders by Owner. Contractor represents and warrants that it will use its best efforts to cooperate
with Owner in implementing this sales tax savings program in order to maximize cost savings for the
Project, Adjustments to the Contract Amount will be made by appropriate Change Orders for the
amounts of each Owner Direct Purchase, plus the saved sales taxes. A Change Order shall be
processed promptly after each Direct Purchase, or group of similar or related Direct Purchases,
unless otherwise mutually agreed Upon between Owner and Contractor. With respect to all Direct
Purchases by Owner, Contractor shall remain responsible for coordinating, ordering, inspecting,
accepting delivery, storing, handling, installing, warranting and quality control for all Direct
Purchases. Notwithstanding anything herein to the contrary, Contractor expressly acknowledges
and agrees that all Direct Purchases shall be included within and covered by Contractor's warranty
to Owner to the same extent as all other warranties provided by Contractor pursuant to the terms of
50,0
Conslructlon Services Agreement: Revised 022018
the Contract documents. In the event Owner makes a demand against Contractor with respect to
any Direct Purchase and Contractor wishes to make claim against the manufacturer or supplier of
such Direct Purchase, upon request from Contractor Owner shall assign to Contractor any and all
warranties and Contract rights Owner may have from any manufacturer or supplier of any such Direct
Purchase by Owner.
32.3 Bidder represents and warrants that it is aware of its statutory responsibilities for sale tax
under Chapter 212, Florida Statutes, and for its responsibilities for Federal excise taxes.
33. SUBCONTRACTS.
33.1 Contractor shall review the design and shall determine how it desires to divide the sequence
of construction activities. Contractor will determine the breakdown and composition of bid packages
for award of subcontracts, based on the current Project Milestone Schedule, and shall supply a copy
of that breakdown and composition to Owner and Design Professional for their review and approval
prior to submitting its first Application for Payment. Contractor shall take into consideration such
factors as natural and practical lines of severability, sequencing effectiveness, access and availability
constraints, total time for completion, construction market conditions, availability of labor and
materials, community relations and any other factors pertinent to saving time and costs.
33.2 A Subcontractor is any person or entity who is performing, furnishing, supplying or providing
any portion of the Work pursuant to a contract with Contractor. Contractor shall be solely responsible
for and have control over the Subcontractors. Contractor shall negotiate all Change Orders, Work
Directive Changes, Field Orders and Requests for Proposal, with all affected Subcontractors and
shall review the costs of those proposals and advise Owner and Design Professional of their validity
and reasonableness, acting in Owner's best interest, prior to requesting approval of any Change
Order from Owner. All Subcontractors performing any portion of the Work on this Project must be
"qualified" as defined in Collier County Ordinance 2913-69, meaning a person or entity that has the
capability in all respects to perform fully the Agreement requirements with respect to its portion of
the Work and has the integrity and reliability to assure good faith performance.
33.3 In addition to those Subcontractors identified in Contractor's bid that were approved by
Owner, Contractor also shall identify any other Subcontractors, including their addresses, licensing
information and phone numbers, it intends to utilize for the Project prior to entering into any
subcontract or purchase order and prior to the Subcontractor commencing any work on the Project,
The list identifying each Subcontractor cannot be modified, changed, or amended without prior
written approval from Owner_ Any and all Subcontractor work to be self -performed by Contractor
must be approved in writing by Owner in its sole discretion prior to commencement of such work.
Contractor shall continuously update that Subcontractor list, so that it remains current and accurate
throughout the entire performance of the Work.
33.A Contractor shall not enter into a subcontract or purchase order with any Subcontractor, if
Owner reasonably objects to that Subcontractor. Contractor shall not be required to contract with
anyone it reasonably objects to. Contractor shall keep on file a copy of the license for every
Subcontractor and sub -subcontractor performing any portion of the Work, as well as maintain a log
of all such licenses_ All subcontracts and purchase orders between Contractor and its Subcontractors
shall be in writing and are subject to Owner's approval. Further, unless expressly waived in writing
by Owner, all subcontracts and purchase orders shall (1) require each Subcontractor to be bound to
Contractor to the same extent Contractor is bound to Owner by the terms of the Contract Documents,
as those terms may apply to the portion of the Work to be performed by the Subcontractor, (2) provide
for the assignment of the subcontract or purchase order from Contractor to Owner at the election of
51�
Construction Services AgreeMonL Revised 022018
Owner upon termination of Contractor, (3) provide that Owner will be an additional indemnified party
of the subcontract or purchase order, (4) provide that Owner, Collier County Government, will be art
additional insured on all liability insurance policies required to be provided by the Subcontractor
except workman's compensation and business automobile policies, (5) assign all warranties directly
to Owner, and (6) identify Owner as an intended third -party beneficiary of the subcontract or
purchase order. Contractor shall make available to each proposed Subcontractor, prior to the
execution of the subcontract, copies of the Contract Documents to which the Subcontractor will be
bound, Each Subcontractor shall similarly make copies of such documents available to its sub -
subcontractors.
33.5 Each Subcontractor performing work at the Project Site must agree to provide field (on-site)
supervision through a named superintendent for each trade (e.g., general concrete forming and
placement, masonry, mechanical, plumbing, electrical and roofing) included in its subcontract or
purchase order. In addition, the Subcontractor shall assign and name a qualified employee for
scheduling direction for its portion of the Work. The supervisory employees of the Subcontractor
(including field superintendent, foreman and schedulers at all levels) must have been employed in a
supervisory (leadership) capacity of substantially equivalent level on a similar project for at least two
years within the last five years, The Subcontractor shall include a resume of experience for each
employee identified by it to supervise and schedule its work.
33.6 Unless otherwise expressly waived by Owner in writing, all subcontracts and purchase orders
shall provide:
33.6.1 That the Subcontractor's exclusive remedy for delays in the performance of the
subcontract or purchase order caused by events beyond its control, including delays claimed to be
caused by Owner or Design Professional or attributable to Owner or Design Professional and
Including claims based on breach of contract or negligence, shall be an extension of its contract time.
33.6.2 In the event of a change in the work, the Subcontractor's claim for adjustments in
the contract sum are limited exclusively to its actual costs for such changes plus no more than 10%
for overhead and profit.
33.6.3 The subcontract or purchase order, as applicable, shall require the Subcontractor
to expressly agree that the foregoing constitute its sole and exclusive remedies for delays and
changes in the Work and thus eliminate any other remedies for claim for increase in the contract
price, damages, losses or additional compensation. Further, Contractor shall require all
Subcontractors to similarly incorporate the terms of this Section 33.6 into their sub -subcontracts and
purchase orders.
33.6.4 Each subcontract and purchase order shall require that any claims by
Subcontractor for delay or additional cost must be submitted to Contractor within the time and in the
manner in which Contractor must submit such claims to Owner, and that failure to comply with such
conditions for giving notice and submitting claims shall result in the waiver of such claims.
34. CONSTRUCTION SERVICES.
34.1 Contractor shall maintain at the Project site, originals or copies of, on a current basis, all
Project files and records, including, but not limited to, the following administrative records:
34,1.1 Subcontracts and Purchase Orders
34.1.2 Subcontractor Licenses
52
Construction Services Agreement: Revised 022018
34.1.3
Shap Drawing Submittal/Approval Logs
34.1.4
Equipment Purchase/Delivery Logs
34.1.5
Contract Drawings and Specifications with Addenda
34.1.6
Warranties and Guarantees
34. 17
Cost Accounting Records
34.1.8
Labor Costs
34.1 .9
Material Costs
34.1.14
Equipment Costs
34.1.11
Cost Proposal Request
34.1,12
Payment Request Records
34.1,13
Meeting Minutes
34.1.14
Cost -Estimates
34.1,15
Bulletin Quotations
34.1.16
Lab Test Reports
34.1.17
Insurance Certificates and Bonds
34.1.18
Contract Changes
34,1,19
Permits
34.1.20
Material Purchase Delivery Logs
34.1.21
Technical Standards
34.1.22
Design Handbooks
34.1.23
"As -Built" Marked Prints
34.1.24
Operating & Maintenance Instruction
34.1.25
Daily Progress Reports
34,1.26
Monthly Progress Reports
34.1,27
Correspondence Files
34.1.28
Transmittal Records
34.1.29
inspection Reports
34.1.30
Punch Lists
34.1.31
PMIS Schedule and Updates
34.1,32
Suspense (Tickler) Files of Outstanding
Requirements
The Project files and records shall be available at all times to Owner and Design Professional or their
designees for reference, review or copying.
34,2 Contractor Presentations
At the discretion of the County, the Contractor may be required to provide a brief update on the
Project to the Collier County Board of County Commissioners, "Board", up to two (2) times per
contract term. Presentations shall be made in a properly advertised Public Meeting on a schedule
to be determined by the County Manager or his designee. Prior to the scheduled presentation date,
the Contractor shall meet with appropriate County staff to discuss the presentation requirements and
format. Presentations may include, but not be limited to, the following information, Original contract
amount, project schedule, project completion date and any changes to the aforementioned since
Notice to Proceed was issued.
35, SECURITY.
The Contractor is required to comply with County Ordinance 2004-52, as amended. Background
checks are valid for five (5) years and the Contractor shall be responsible for all associated costs. If
required, Contractor shall be responsible for the costs of providing background checks by the Collier
County Facilities Management Division for all employees that shall provide services to the County
ss 13
Construction Services Agreement' Revised 022018 DO-
under this Agreement. This may include, but not be limited to, checking federal, state and local law
enforcement records, including a state and FBI fingerprint check, credit reports, education, residence
and employment verifications and other related records. Contractor shall be required to maintain
records on each employee and make them available to the County for at least four (4) years.
All of Contractor's employees and subcontractors must wear Collier County Government
Identification badges at all times while performing services on County facilities and properties.
Contractor ID badges are valid for one (1) year from the date of issuance and can be renewed each
year at no cost to the Contractor during the time period in which their background check is valid, as
discussed below. All technicians shall have on their shirts the name of the contractor's business.
The Contractor shall immediately notify the Collier County Facilities Management Division via e-mail
(DL-FMOPS(Mcolliergov.net) whenever an employee assigned to Collier County separates from their
employment. This notification is critical to ensure the continued security of Collier County facilities
and systems. Failure to notify within four (d) hours of separation may result in a deduction of $500
per incident.
CCSO requires separate fingerprinting prior to work being performed in any of their locations. This
will be coordinated upon award of the contract. If there are additional fees for this process, the
Contractor is responsible for all costs.
36. VENUE.
Any suit or action brought by either party to this Agreement against the other party relating to or
arising out of this Agreement must be brought in the appropriate federal or state courts in Collier
County, Florida, which courts have sole and exclusive jurisdiction on all such matters.
37, VALUE ENGINEERING.
All projects with an estimated cost of $10 million or more shall be reviewed for consideration of a
Value Engineering (VI=) study conducted during project development. A "project" shall be defined as
the collective contracts, which may include but not be limited to: design, construction, and
construction, engineering and inspection (CEI) services, Additionally, any project with an estimated
construction value of $2 million or more may be reviewed for VE at the discretion of the County.
38. ABOVEGROUND/UNDERGROUND TANKS.
35.1 The contractor shall ensure compliance with all NFPA regulations: specifically 110 & 30/30A;
FDEP chapter 62 regulations; specifically 761, 762, 777, and 780; 376 & 403 Florida Statutes; and
STI, UL, PEI, ASMI=, NAGE, NLPA, NIST & API referenced standards pertaining to the storage of
hazardous materials and petroleum products.
38.2 The contractor shall notify the Solid & Hazardous Waste Management Department (SHWMD)
prior to the installation, removal, or maintenance of any storage tank, including day tanks for
generators, storing 1 will be storing petroleum products or hazardous materials. The contractor shall
provide a 10 day and 48-hour notice to SHWMD 239-252-2508 prior to commencement.
The contractor shall provide the plans pertaining to the storage tank systems containing hazardous
materials 1 petroleum products to the SHWMD prior to plans submittal to a permitting entity and then
SHWMD must approve the plans prior to contractor's submittal for permitting,
54C
Construction Services Agreement: Revised 02201 B +
39. STANDARDS OF CONDUCT: PROJECT MANAGER, SUPERVISOR, EMPLOYEES.
The Contractor shall employ people to work. on Owner's projects who are neat, clean, well-groomed
and courteous. Subject to the Americans with Disabilities Act, Contractor shall supply competent
employees who are physically capable of performing their employment duties. The Owner may
require the Contractor to remove an employee it deems careless, incompetent, insubordinate or
otherwise objectionable and whose continued employment on Owner's projects is not in the best
interest of the County.
40. DISPUTE RESOLUTION.
Prior to the initiation of any action or proceeding permitted by this Agreement to resolve disputes
between the parties, the parties shall make a good faith effort to resolve any such disputes by
negotiation. The negotiation shall be attended by representatives of Contractor with full decision-
making authority and by Owner's staff person who would make the presentation of any settlement
reached during negotiations to Owner for approval. Failing resolution, and prior to the
commencement of depositions in any litigation between the parties arising out of this Agreement, the
parties shall attempt to resolve the dispute through Mediation before an agreed-upon Circuit Court
Mediator certified by the State of Florida, The mediation shall be attended by representatives of
Contractor with full decision-making authority and by Owner's staff person or designee who would
make the presentation of any settlement reached at mediation to Owner's Board for approval.
Should either party fail to submit to mediation as required hereunder, the other party may obtain a
court order requiring mediation under Section 44.102, Fla. Stat.
Any suit or action brought by either party to this Agreement against the other party relating to or
arising out of this Agreement must be brought in the appropriate federal or state courts in Collier
County, Florida, which oourts have sole and exclusive jurisdiction on all such matters.
55
Construction services Agreement' Revised 022018 CCR
EXHIBIT I:
SUPPLEMENTAL TERMS AND CONDITIONS
(FOLLOWING THIS PAGE)
56
Construction Services Agreemanl: Revised 022018 Q
Exhibit I - 18-7267 - SFWMD Supplemental Conditions and Forms
EXHIBIT[ -Of
SUPPLEMENTAL CONTRACT PROVISIONS
South Florida Water Management District (SFWMr))
The supplemental conditions contained in this section are intended to cooperate with, to supplement, and
to modify the general conditions and other specifications. In cases of disagreement with any other section
of this contract, the Supplemental Conditions shall govern.
1. Records, Access and Retention
A. Maintenance of Recotxl.s_: The Contractor shall maintain all financial and non-financial records and
reports directly or indirectly related to the negotiation or performance of this contract including
supporting documentation for any service rates, expenses, research or, reports. Such records shall be
maintained and made available for inspection for a period of five (5) years from the expiration date of
the contract.
B. Examination of Recrd : The: SFWMD shall have the right to examine in accordance with generally
accepted governmental auditing standards all records directly or indirectly related to this contract.
Suoh examination may be mads only within five (5) years from the expiration date of this contract,
C. Extended Av4itabflity of Records for Lepl pis tes: In the event that the SFWMD should become
involved in a legal dispute with a third party arising fruit performance under this contract, the County
shall "tend the period of maintenance for all records relating to the contract until the final disposition
of the legal dispute. All such records shall be made readily available to the SFWMD.
2, Discriminatory Vendor Dist — The contractor will not discriminate against any person on legally
protected basis in any activity under this solicitation or a contract. Any entity or affiliate that has been
placed on the discriminatory vendor list may not submit a bid on a contract to provide any goods or
services to a public entity, may not submit a bid on a contract with a public entity for the construction or
repair of a public building or public work, may not submit bids on leases of real property to a public entity,
may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a
contract with any public entity, and many not transact business with any public entity,
3. Employment Eligibility Verification - Executive Order 11-116, signed May 27, 2011, by the
Governor of Florida, requires contracts to utilize the U.S. Department of Homeland Security's E -Verify
system to verify the employment eligibility of all new ernployees hired by the vendor during the
Contract/Work Order term and include in all subcontracts under this Contract/Work Order, the requirement
that subcontractors performing work or providing services pursuant to this Agreement utilize the E -Verify
system to verify the employment eligibility of all new employees hired by the subcontractor during the
ttmii of the subcontract,.
d. Indemnification - Contractor agrees to indemnify, pay on behalf, and hold the SFWMD harmless
from all damages arising in connection with a contract.
5. Ownership Rights — Both the SFWMI) and the County shall have joint ownership rights to all work
items, including but not limited to, all documents, tcchnicai reports, research notes, scientific data, computer
programs, including the source and object code, which are developed, created or otherwise originated
hereunder by the other party, its contractor(s), as required by the Statement of Work. Both parties' rights to
deliverables received under a contract shall include the unrestricted and peg etual right to use, reproduce,
modify and distribute such deliverablesat no additional cost to the other party.
6. Compliance with Terms and Conditions - Contractors and its subcontractors shall comply with
all applicable federal, state and local laws and regulations relating to the performance of the contract.
Contract Provisions - I.
CCR
EXHIBIT I-02
CERTIFICATIONS AND ASSURANCES
FUNDING CERTIFICATIONS AND ASSURANCES
THE FOLLOWING DOCUMENTS NEED TO BE RETURNED WITH SOLICIATION DOCUMENTS
BY DEADLINE TO BE, CONSIDERED RESPONSIVE
Cetilftcation Regarding Debarment, Suspension, and Other Responsibility Matters - Primary Covered
Transactions
Acknowledgement of Grant `i"etms and Conditions
Certs and Assurances - I
01.0
EXHIBIT 1-02
CERTIFICATIONS AND ASSURANCES
COLLIER COUNTY
Certification Regarding Debarment, Suspension, and 41ber Responsibility Matters
Primary Covered Transactions
(1) The prospective primary participant certifies to the best of its knowledge and belief, that it and its principals:
(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily
excluded from covered transactions by any Federal department or agency;
(b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment
rendered against them for commission of fraud or a criminal offense in connection with obtaining,
attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public
transaction; violation of Federal or State antitrust statutes or commission ofembezzlement, theft, forgery,
bribery, falsification or destruction of records, making false statements, or receiving stolen property;
(c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal,
State or local) with commission of any of the offenses enumerated in paragraph (1)(b) of this certification;
and
(d) Have not within a three-year period preceding this application/proposal had one or more public
transactions (Federal, State or local) terminated for cause or default.
(2) Where the prospective primary participant is unable to certiry to any of the statements in this certification,
such prospective participant shall attach an explanation to this proposal.
David E. Torres
Nance
Manager
Title
Coastal Concrete Products, LLC
dba Coastal Site Development_
Firm
7742 Alico Road Fort Myers, FL 3
Street Address, City, State, Zip
Signature
Lely Branch Canal Weir
Project Naive
18-7267
Project Number
27-3680694
Tax ID Number
DUNS Number
Certs and Assurances - 2
COP
EXHIBIT I-02 CERTIFICATIONS AND ASSURANCES
COLLIER COUNTY
Acknowledgement of Terms, Conditions and Grant Clauses
Flow Down 0Terins and Conditions frorn (lie Grant Agreement
Subcontracts: If the vendor subcontracts any of the work required under this Agreement, a copy of the signed
subcontract must be available to the Department for review and approval. The vendor agrees to include in
the subcontract that (l) the subcontractor is bound by the terns of this Agreement, (ii) the subcontractor is
bound by all applicable state and federal laws and regulations, and (iii) the subcontractor shall hold the
Department and Recipient harmless against all claims of whatever nature arising out of the subcontractor's
performance of work under this Agreement, to the extent allowed and required by law. The recipient shall
document in the quarterly report the subcontractor's progress in performing its work under this agreement.
For each subcontract, the Recipient shall provide a written statement to the Department as to whether the
subcontractor is a minority vendor as defined in Section 288.703, Fla. Stat.
Certification
Dn behalf of my firm, I acknowledge, and agree to perform all of the specifications and grant requirements
identified in this solicitation document(s).
Coastal Concrete Products, LLC dba
Vendor/Contractor Name -coastal-site-De4eJ4pm9n;� Date 02/2312018
Authorized Signature
Address 7742 Allco RoadT�drt Myers, FL 33912
Solicitation/Contract tt 18-7267
David E. Torres - Manager
Certs and Assurances - 3
��C�