Agenda 09/10/2013 Item #11D 9/10/2013 11.D. EXECUTIVE SUMMARY Recommendation to award Invitation to Bid number 13-6122R in the amount of$1,214,943.99 to Kyle Construction,Inc.,to replace the water mains on 91st and 92nd Avenues North, under Project Number 71010. OBJECTIVE: Provide compliant and reliable potable water service to the Collier County Water-Sewer District(CCWSD)customers on 91St and 92nd Avenues North. CONSIDERATIONS: On June 24, 2008, Agenda Item 10G, the Board of County Commissioners (Board) adopted the 2008 Water Master Plan Update that identified the requirement for rehabilitating the potable water distribution system. The proposed scope of work is consistent with the 2008 Water Master Plan Update, Project 71010, "Distribution System Renewal and Replacement," Section 8, Table 8-2, page 3 of 5, line 91; and with the 2010 Potable Water CIP Update, page 3 of 4, line 90, as identified in the 2011 User Fee Rate Study. The design of this project is under a separate work order to Johnson Engineering,Inc.,under the Fixed Term Professional Engineering Services Contract Number 09-5262. The water mains on 91st and 92nd Avenues are approximately 50 years old. The distribution system was installed in the late 1960s. The pipe has reached the end of its useful life. Due to the pipe's age, there is an ever increasing number of water main leaks and breaks, which directly affects the CCWSD's ability to supply uninterrupted service to its customers. There are a limited number of isolation valves in this area, limiting operational control during maintenance of the distribution system. The system also lacks a sufficient number of fire hydrants. The CCWSD considers the 91st and 92nd Avenues Water Main Replacement Project to be a mission-critical part of its overall distribution system rehabilitation program. • The project includes removing the asbestos pipe and replacing it with PVC pipe, as well as replacing valves, meters and service lines. The new water distribution system will provide a reliable source of potable water and will help sustain a compliant level of water quality. Several additional fire hydrants will be added at new locations, ensuring sufficient fire flow and improving the coverage for fire fighting. All roadways within the project area will be resurfaced at the completion of the underground work. This project will directly benefit approximately 436 residents. Invitation to Bid number 13-6122R was advertised on June 7, 2013, with 1,410 vendor email addresses being notified. A total of 56 bidders downloaded full packages. Bids were publicly opened on July 8, 2013. The 11 bids received are summarized in the following table. BIDDER TOTAL Kyle Construction, Inc. $1,214,943.99 Andrew Sitework, LLC. $1,323,543.73 Quality Enterprises USA, Inc. $1,339,162.79 Denco Construction, Inc. $1,396,832.50 DN Higgins, Inc. $1,564,532.00 ADJ Excavating of Florida $1,569,140.71 Mitchell & Stark Construction $1,575,738.00 Haskins, Inc. $1,666,364.00 TB Landmark Construction $1,682,754.06 Southwest Utilities Systems $1,780,931.00 Strickler Bros, Inc. $1,895,558.00 Packet Page-180- 9/10/2013 11 .D. Staff reviewed the bids and determined the lowest qualified and responsive bidder to be Kyle Construction, Inc., as shown by the bid tabulation and graph in Attachments 1 and 2. The design professional,Johnson Engineering, Inc.,recommends award of the bid to Kyle Construction in its July 15, 2013, recommendation letter (Attachment 3) as the bid is $193,111.01 (13.7%) below its $1,408,055 estimate of probable construction cost. The project cost includes an allowance of $100,000.00 that includes, but is not limited to, additional piping and appurtenance replacement and unforeseen site conditions, as determined by staff, which may be required during construction. The price for any additional work shall be negotiated prior to commencement in accordance with the county's Purchasing Policy and the terms of the agreement. An initial neighborhood information meeting was held on May 23, 2013,to review the overall project and gather initial feedback from residents. Following the award of contract, a second neighborhood information meeting will be held to familiarize the residents with project specifics and to introduce the Project Delivery Team. FISCAL IMPACT: The source of funds is Water User Fees, Fund (412). Funding is available under the Distribution Renewal and Replacement Project, Project Number 71010, and is consistent with the FY13 budget approved by the Board on September 20, 2012. This compliance driven project is a direct replacement of assets that have reached the end of their useful lives. The project cost is $1,214,943.99. The assets will have an approximate life of fifty years and is not expected to generate additional annual operating costs LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval.—SRT GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the viability of public facilities. RECOMMENDATION: That the Board of County Commissioners, Ex-officio the Governing Board of the Collier County Water-Sewer District, award Invitation to Bid 13-6122R, "91st and 92nd Avenue North Water Main Replacement Project," in the amount of $1,214,943.99 to Kyle Construction, Inc. and authorize the Chairwoman to sign and execute the attached agreement after final review and approval by the County Attorney's Office. Prepared By: Jereme Shaidle, P.E., Senior Project Manager, Public Utilities Division Attachments: 1. Bid Tabulation 2. Public Utilities Bid Analysis 3. Recommendation Letter 4. Contract—(Due to the size of the contract(105 pages),a web link has be provided for viewing at http://www.colliergov.net/FTP/AgendaSent913/ITEM 11 AWaterMainReplacement.pdf A hard copy is also available at the County Manager's Office.) Packet Page-181- 9/10/2013 11 .D. COLLIER COUNTY Board of County Commissioners Item Number: 11.11.D. Item Summary: Recommendation to award Invitation to Bid number 13-6122R in the amount of$1,214,943.99 to Kyle Construction, Inc., to replace the water mains on 91st and 92nd Avenues North, under Project Number 71010. Meeting Date: 9/10/2013 Prepared By Name: ShaidleJereme Title: VALUE MISSING 8/16/2013 9:32:26 AM Submitted by Title: VALUE MISSING Name: ShaidleJereme 8/16/2013 9:32:27 AM Approved By Name: HapkeMargie Title: Operations Analyst,Public Utilities Date: 8/16/2013 11:38:03 AM Name:Evelyn Colon Title: Purchasing-Procurement Specialist Date: 8/16/2013 4:19:06 PM Name: MarkiewiczJoanne Title:Manager-Purchasing Acquisition,Purchasing&Gene Date: 8/19/2013 9:17:49 AM Name: Amia Marie Curry Date: 8/19/2013 5:15:03 PM Name: WardKelsey Packet Page-182- 9/10/2013 11.D. Title: Manager-Contracts Administration,Purchasing& Ge Date: 8/20/2013 9:26:10 AM Name: Steve Messner Title: Plant Manager,Water Date: 8/20/2013 10:07:52 AM Name: Pam Libby Title: Manager-Operations-Water/WW,Water Date: 8/20/2013 12:01:06 PM Name: HapkeMargie Title: Operations Analyst,Public Utilities Date: 8/20/2013 2:55:04 PM Name: JacobsSusan Title: Operations Analyst,Public Utilities Date: 8/20/2013 3:17:07 PM Name: SunyakMark Title: Project Manager,Principal,Public Utilities Engine Date: 8/22/2013 12:06:55 PM Name: ChmelikTom Title:Director, Public Utilities Engineering Date: 8/23/2013 10:24:04 AM Name: TeachScott Title: Deputy County Attorney,County Attorney Date: 8/23/2013 12:11:01 PM Name: YilmazGeorge Title: Administrator,Public Utilities Date: 8/23/2013 5:29:22 PM Name: KlatzkowJeff Title: County Attorney Date: 8/26/2013 9:14:51 AM Name: UsherSusan Title: Management/Budget Analyst, Senior,Office of Manage Date: 8/30/2013 12:21:24 PM Amok Name: KlatzkowJeff Packet Page-183- 9/10/2013 11 .D. Title: County Attorney Date: 8/30/2013 1:35:36 PM Name: OchsLeo Title: County Manager Date: 8/30/2013 2:28:52 PM Packet Page-184- eN. ill 9/10/2013 11.D. i i II !gagga ggaa a 4 1144 44444 14 4444 "1" 11E! ! 1 !Z !!!!1 ...11#.' .1. 1 z..1 -..-4 Afta i / 1 ra-Fir gaga 8 1 Raga Rag !1!:1 MI lags 0 0ilm gat. I Hill III! 1 1 IIII Jill .1 Pli t Eirr Bugg g g mg gag! I ,e1 t MI 1311 ! 1 MI—Ma 1 az I HP" MI ;PI MU P WA I ilia27. via ,411 le g la a .a -..,..- I . 1 “W 888 8 8 888 seas ,-,7 g g a a— 111R811 T1 WI ;WI i IT IF", 4 4 ni 4 i - .T.,... - gi -.a.a -r. - 1 niTiu ass; s a gm 8888 BP gggg §fit aaas a 1 MI pa 9.2 1,aa I 1111! 1111 I 1 1111-11!!! '12 :Ili I a. 1 A gaga 8282 g 8 MI 8888 i : !MI aata 0 t j!i EasJ 4 ' I . ... '^... ." 2 a INii gP1 ;' 1 MI ;;;;1 P ;111 1 Ea--a aSAd 1 I.11S i iiiii III 17' IT 1111 ; 11; ....... 5.. .., 4 -- ev:e e ..t.- i --. -- .- 1 I1 ,omf... i MI- !ggg g g 4888 881: 1. ,p4; . i 11R1 .71111 ! 1 II31 !!-,,, - --- gt,.. I 1 88884 8888 8 8 889 ;MI g; rig; i i4 !1!1 1 1 T: 4" ..4 : : n i SV".1 *2- a . 1.... -z..1 . a.. 1 :s Mg gni 1 1 ...„. .,.....- d ----r. 1 Ag8g5 889 R g 285' 8.2882 MA ARAB 5EMI ff..1.5 1 I HD 51551 il !ill Aggg g2gR :lAAR A8801._ 1 FrEq aaas a! 1„11 ;.1al - ....A Pg!1 "q VI 21! ;gm 1 a Yin- R=88 8 8 8882 8888 A g.g. i limz, 13.g g a egga .1.. A ar.aal [ i ilill IPA 1 1 111! 11111 11 1111 i ! 8888 888a gig 121" 1W ; Mg RIZ aaas - 8888 8888 8118 1513 8818 8:11011 .18 888^ ..1/ 410000 i .iiii 1 I '1100 11 1 ,,7-,-AAA A .11 1/1 Al 40041 14 1 ign All lid 1111 1111 Iiiiii il III 1111/ HE , ii i i---- ii----1--4--0-.. 1:-1 1 if if Packet Page-185- ._ _ .. ;II 9/10/2013 11 .D. P. 5 R 88 g ; I 1; '15 $ I § I I § ; ; WI 8 S 8 `^' I ; i gg . 1 S g I ge g t g g WI '51 ; 5 I g g 1 ; • g g g g 1111 . 11 g g g § I 1 1 1 1 1 1 1 1 1 I 1 1 FY1 ,1 f I 1 1 1i I g 1 ! § r " I 11 171717 "51 H II - .11 4 - I 1 I 1 1 ! 1910 1 Iii1;11 ! 1 1 lilt . I 1 1 1 i .121i g . gs,:E iY8t0 MOM 1 1 41131: filvli 11111111H iiiiill 111.111H1 A Packet Page -186- 9/10/2013 11 .D. Aftik Engineers Kyle Andrew Der Estimate Construction Sitework Quality Constr $1,408,055.00 $1,214,943.99 $1,323,543.73 $1,339,162.79 $1,389, Packet Page-187- 9/10/2013 11 .D. ico DN Higgins ADJ Excavating Mitchell & Stark Haskins uction .832.50 $1,564,532.00 $1,569,140.71 $1,575,738.00 $1,666,364.00 Packet Page-188- 9/10/2013 11 .D. SouthWest TB Landmark Strickler Bros. Utilities $1,682,754.06 $1,780,931.00 $1,895,558.00 Packet Page-189- 9/10/2013 11.D. -6 ° _o 0 ..6 .6 i N .... U E a s y N t 6 \o C o f h ti e-I as i N E .` H W 1- 0 Y G Q 0 t O 0 t N L u V c Q a, cc � %Ji • . I Mil Z I . N I I • al ti Cl I S, "0 I JL • • ........ I . . I >�o •I tr. , o c)• O I ( �P� 1 I CO I I ap a 3 N CO ,rS. cP o 'H ; ! ! ih V} V} V} V} V} L} V} V} Packet Page-190- 9/10/2013 11.D. SINCE 1946 #11 1 I July 15, 2013 Mr. Jereme Shaidle Collier County Public Utilities Planning and Project Management Department 3339 East Tamiami Trail, Suite 303 Naples,Florida 34112 Re: Collier County—91st& 92"d Avenue North Water Main Replacement Low Bidder: Kyle Construction, Inc. Dear Jereme: The bid opening for the above-referenced project took place on Monday, July 8, 2013. Collier County provided the results of the bid opening to Johnson Engineering on July 10, 2013. Johnson Engineering performed an evaluation of the results and our recommendation is contained herein. Amok Collier County received eleven (11) bids by the deadline established on the Invitation to Bid. At the bid opening performed by Collier County, the following bids were received and for convenience purposes, we have listed the bids from lowest to highest. BIDDER BASE BID AMOUNT Kyle Construction, Inc. 1,214,943.99 Andrew Sitework, LLC 1,329,543.73 Quality Enterprises USA, Inc. 1,339,162.79 Denco Construction,Inc. 1,396,832.50 DN Higgins, Inc. 1,564,532.00 ADJ Excavating of Florida 1,569,140.71 Mitchell & Stark Construction 1,575,738.00 Haskins, Inc. 1,666,364.00 TB Landmark Construction 1,682,754.06 Southwest Utilities Systems 1,780,931.00 Strickler Bros, Inc. 1,895,558.00 2122 Johnson Street•Post Office Box 1550•Fort Myers,Florida 33902-1550 (239)3:Packet Page-191-;4-3661 9/10/2013 11 .D. Mr. Jereme Shaidle Re: Bid Recommendation Project: 91St& 92nd Avenue North Water Main Replacement July 15, 2013 Page 2 For comparison purposes, Johnson Engineering provided Collier County with an Opinion of Probable Construction Cost to be approximately $1,408,055.00. Following the bid opening, Collier County prepared the enclosed Bid Tabulation Analysis, which included an analysis for mathematical errors. No mathematical errors appear to have been found. The results show Kyle Construction, Inc. as the low bidder. Internet Research From the Florida Department of State, Division of Corporations website, Kyle Construction, Inc. is an active Florida Limited Liability Company under Document Number P93000009639, FEI Number 65-0382581 filed on February 1, 1993. Their current address is 3636 Prospect Avenue, Unit 1, Naples, FL 34104. There are two officers listed for the corporation and both reside in Naples,Florida. Based upon our review of the analysis, the low bidder, Kyle Construction, Inc. appears to be a reasonable and responsive bid. Subject to concurrence with Collier County's Purchasing and Contracts Division, and the contractor furnishing the appropriate bonding and other required insurances, we believe selection of Kyle Construction, Inc. by Collier County for the intended work contained within the bid documents to be an appropriate choice. Should you have any questions,or require additional information, please let me know. Very truly yours, JOHNSON EN.0 -RING,INC. M� 'Iael S. Dicke,, '.E. Director of Utility Services MSD/ljb 20129009-012 cc: File Packet Page-192-