Loading...
Agenda 06/25/2013 Item #16A 7�1 6/25/2013 16.A.7. EXECUTIVE SUMMARY Recommendation to approve final acceptance of the private roadway and drainage improvements for the final plat of Veronawalk Phase 3B, (AR -6688) with the roadway and drainage improvements being privately maintained and authorize the County Manager, or his designee, to execute the attached resolution authorizing final acceptance of the improvements and acceptance of the plat dedications, and release of the maintenance security in the amount of $352,552. OBJECTIVE: To have the Board of County Commissioners accept final approval of the infrastructure improvements associated within the subdivision accept the plat dedications, and to release the maintenance security in the amount of $352,552.14. CONSIDERATIONS: 1) On July 31, 2007, the Engineering Services Department granted preliminary acceptance of the roadway and drainage improvements in Veronawalk Phase 3B. 2) The roadway and drainage improvements will be maintained by the project's homeowners association. 3) The required improvements have been constructed in accordance with the Land Development Code. The Engineering Services Department has inspected the improvements and is recommending final acceptance of the improvements. 4) A resolution for final acceptance has been prepared and approved by the County Attorney's Office. The resolution is a requirement of Section 10.02.05 C.3 of the Land Development Code. A copy of the document is attached. 5) This PUD has been found to be in substantial compliance. FISCAL IMPACT: The roadway and drainage improvements will be maintained by the project's homeowners association. The existing security in the amount of $352,552.14 will be released upon Board approval. The original security in the amount of $2,998,747.00 has been reduced to the current amount based on the previous work performed and completed and pursuant to the terms of the Construction and Maintenance Agreement dated January 5, 2006. LEGAL CONSIDERATIONS: This item has been approved as to form and legality, and requires a majority vote for approval. - ERP GROWTH MANAGEMENT IMPACT: There is no growth management impact. Packet Page -413- 1 6/25/2013 16.A.7. i RECOMMENDATION: To have the Board of County Commissioners accept final approval of n the infrastructure improvements associated within the subdivision known as Veronawalk Phase 3B, (AR -6688) and authorize the County Manager, or his designee, to execute the attached resolution authorizing final acceptance of the improvements and acceptance of the plat dedications, and release of the maintenance security in the amount of $352,552.14. Prepared By: John Houldsworth, Senior Site Plans Reviewer, Engineering Services, Growth Management Division, Planning and Regulation Attachments: 1) Location Map, 2) Bond Basis, 3) Resolution Packet Page -414- 6/25/2013 16.A.7. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.A.16.A.7. Item Summary: Recommendation to approve final acceptance of the private roadway and drainage improvements for the final plat of Veronawalk Phase 313, (AR -6688) with the roadway and drainage improvements being privately maintained and authorize the County Manager, or his designee, to execute the attached resolution authorizing final acceptance of the improvements and acceptance of the plat dedications, and release of the maintenance security in the amount of $352,552. Meeting Date: 6/25/2013 Prepared By Name: HouldsworthJohn Title: Site Plans Reviewer, Senior,Engineering & Environm 5/30/2013 7:55:04 AM Approved By Name: BeardLaurie Title: Planner,Transportation Planning Date: 5/30/2013 10:27:08 AM Name: PuigJudy Title: Operations Analyst, GMD P &R Date: 5/31/2013 2:15:42 PM Name: McKennaJack Title: Manager - Engineering Review Services,Engineering & Environmental Services Date: 6/3/2013 2:07:49 PM Name: PepinEmily Title: Assistant County Attorney, CAO Litigation Date: 6/5/2013 4:32:30 PM Name: MarcellaJeanne Title: Executive Secretary,Transportation Planning n Date: 6/6/2013 11:37:09 AM Packet Page -415- Name: FinnEd Title: Senior Budget Analyst, OMB Date: 6/7/2013 5:50:12 PM Name: KlatzkowJeff Title: County Attorney Date: 6/14/2013 9:59:56 AM Name: OchsLeo Title: County Manager Date: 6/15/2013 12:36:12 PM Packet Page -416- 6/25/2013 16.A.7. m M z z n n r 'O S n N m iW O D O Z 3 D V' m 3 D 6/25/2013 16.A.7 NOT M SCALE G WAL eawue eou,cvArro (en. Is,( CANAL A- s 2� k 0® 5� Z S z z --- - --- —__ = mA N N Y rn — m O z �N Packet Page -417- F T CIXIJER �LLEVAfO (9 yp COLUER IWIEVA �.�„ <" _A °� U p w N G;2 s O m O I NOT M SCALE G WAL eawue eou,cvArro (en. Is,( CANAL WAJX 2� k 0® GP. Q L RIGHT-OF-WAY 5� Z N z z mA N N O rn — m O z �N Packet Page -417- • � 6/25/201316.A.7. VERONAWALK PHASE 36 OPINION OF PROBABLE COST Sanitary Collection System Potable Water Drainage Paving Lighting Landscaping (Code Minimum) Irrigation (Code Minimum) Total Probable Cost • 110% Bond Amount C7 10/14/2004 -# 141649v1 N0506- P3"00 -EDES $ 787,176 $ 511,313 $ 246,058 $ 714,507 $ 101,825 $ 97,750 $ 267,504 $ 2,726,134 $ 2,998,747 David J. Hurst, P. E:- FL Registration #60727 WilsonMiller, Inc. -FL Lic. #LC- 0000170 WilsonMlller, Inc. - Certificate of Authorization #43 Packet Page -418- SANITARY COLLECTION SYSTEM PHASE 3B 6/25/2013 16.A.7. DESCRIPTION QUANTITY UNIT TYPE UNIT PRICE TOTAL PRICE TV sewer (preliminary) 8511 LF $ 2.88 $ 24,469.13 TV sewer (final) 8511 LF $ 2.93 $ 24,958.51 8" PVC Gravity Main (0-6 cut) 3070 LF $ 18.40 $ 56,488.00 8" PVC Gravity Main (6-8' cut) 1971 LF $ 22.43 $ 44,199.68 8" PVC Gravity Main (8-10' cut) 1,595 LF $ 31.63 $ 50,441.88 8" PVC Gravity Main (10 -12' cut) 885 LF $ 40.25 $ 35,621.25 8" PVC Gravity Main (12 -14' cut) 5e6 LF $ 49.45 $ 27,988.70 8" PVC Gravity Main (14 -16' cut) 424 LF $ 59.80 $ 25,355.20 Manhole 4' Diameter (0-6 cut) 25 EA $ 1,495.00 $ 37,375.00 Manhole 4' Diameter 6-8' cut) 9 EA $ 1,667.50 $ 15,007.50 Manhole 4' Diameter (8 -10' cut) 7 EA $ 2,185.00 $ 15,295.00 Manhole 4' Diameter(10 -12' cut) 7 EA $ 2,645.00 $ 18,515.00 Manhole 4 Diameter(12 -14' cut) 6 EA $ 3,105.00 $ 18,630.00 Manhole 4' Diameter(14 -16 cut) 7 EA $ 3,450.00 $ 24,150.0D 6" Forcemain 3690 LF $ 15.53 $ 57,287.25 6" Plug Valve 1 EA $ 1,265.00 $ 1,265.00 Pump Station - Complete 1 EA $ 150,000.00 $ 150,000.00 Single sanitary sewer service 38 EA $ 368.00 $ 13,984.00 Double sanitary sewer service 90 EA $ 483.00 $ 43,470.00 10/1 /2004 - # 1416490 N0506 -P3B- 000 -EDES SUB -TOTAL SANITARY= $ 684,601 15 %CON7INGENCY= $ 102,676 TOTAL SANITARY= $ 787,176 Packet Page -419- • 0 POTABLE WATER Due co sR 0 6/25/2013 16.A.7. DESCRIPTION QUANTITY UNIT TYPE UNIT PRICE TOTAL PRICE 2" PVC Double Service 13/4!'PVC 93 EA $ 460.00 $ 42,780.00 Single Service 32 EA $ 345.00 $ 11,040.00 Connect to existing water with gap configuration 2 LS $ 2,000.00 $ 4,000.00 6" PVC Water Main (C -900, CL -150) 938 LF $ 14.95 $ 14,023.10 6" PVC Water Main (C -900, CL -200) 170 LF $ 17.95 $ 3,051.50 8" PVC Water Main (C -900, CLA 50) 1383 LF $ 20.90 $ 28,486.70 8" PVC Water Main (C -900, CL -200) 40 LF $ 23.35 $ 934.00 10" PVC Water Main, (C-9W, CLA 50) 3366 LF $ 24.50 $ 82,436.13 10" PVC Water Main (C -900, CL -200) 119 LF $ 25.80 $ 3,070.20 12" PVC Water Main (C -900, CLA 50) 3471 LF $ 26.74 $ 92,810.53 12" PVC Water Main (C -900, CL -200) 217 LF $ 27.17 $ 5,895.89 Fire Hydrant Assembly 38 EA $ 2,415.00 $ 91,770.00 6" Gate Valve w/ Box 5 EA $ 575.00 $ 2,875.00 8" Gate Valve w/ Box 4 EA $ 1,096.65 $ 4,386.60 10" Gate Valve w/ Box 10 EA $ 1,265.00 $ 12,650.00 12" Gate Valve w/ Box 16 EA $ 1,700,00 $ 25,500.00 Permanent Blowoff 6" 6 EA $ 1,650.00 $ 8,250.00 Temporary Bacterial Sample Point 4 EA $ 977.50 $ 3,910.00 Permanent Bacterial Sample Point 6 EA $ 1,125.00 $ 6,750.00 1011 /2004 - # 1416490 N0506- P3B- 000 -EDES SUB -TOTAL POTABLE WATER= a 444,0w 15% CONTINGENCY- $ 66,693 TOTAL POTABLE WATER= $ 511,313 Packet Page -420- 'o 0 • 6/25/2013 16.A.7. STORM SEWER PHASE 3B DESCRIPTION QUANTITY UNIT TYPE UNIT PRICE TOTAL PRICE 15" RCP 832 LF $ 25.30 $ 21,049.60 18" RCP 2810 LF $ 27.56 $ 77,443.60 24" RCP 525 LF $ 40.03 $ 21,015.75 Grate Inlet 31 EA $ 1,340.90 $ 4,022.70 Valley Gutter Inlet (Top and Bottom) 40 EA $ 1,908.18 $ 76,327.23 18" Flared End 15 EA $ 806.00 $ 12,090.00 24" Flared End 2 EA $ 1,007.241$ 2,014.48 10/1 /2004 - # 141649V1 N0506 -P36- 000 -EDES Packet Page -421- SUB -TOTAL DRAINAGE = $ 213,963 16% CONTINGENCY= $ 32,094.60 TOTAL DRAINAGE = $ 248,057.86 r� • • 6/25/2013 16.A.7. PAVING rnAaC Ja DESCRIPTION QUANTITY UNIT TYPE UNIT PRICE TOTAL PRICE 314" As haftic Concrete (Type S- 111)(1 st lift) 26,811 SY $ 2.30 $ 61,665.30 314" Asphaltic Concrete (Type S- I11)(2nd lift) 26,811 SY $ 1.76 $ 47,173.95 12" Stabilized Subgrade 31,355 SY $ 2.42 $ 75,723.34 29,943.27 4' Limerock Base for Sidewalk 8,679 SY $ 3.45 $ 6" Limerock Base 25,761 SY $ 3.62 $ 93,319.29 8" Limerock Base 5,59 SY $ 4.83 $ 27,020.95 Sodding (Bahia) 2,373 SY $ 1.15 $ 2,729.21 24" Valley Gutter 21,359 LF $ 5.18 $ 110,533.03 Curb & gutter (Type "E -2 ") 608 LF $ 8.05 $ 4,894.40 Curb & gutter (Modified Type " F") 754 LF $ 7.48 $ 5,636.15 4' Concrete Sidewalk 8,679 SY $ 18.40 $ 159,697.46 17' Solid stripe thermoplastic 315 LF $ 1.96 $ 615.83 24" Solid stripe thermoplastic 70 LF $ 4.03 $ 281.75 Blue Reflective pavement marker 381 EA $ 5.75 $ 218.50 Stop Sign 81 EA $ 140.30 $ 1,122.40 Street Sign 81_ EA $ 92.00 $ 736.00 TOTAL PAVING — $ 621311 1011 /2004 - # 1416490 N0506- P3B- 000 -EDES SUB- — 15% CONTINGENCY - $ 93,196.63 TOTAL PAVING = $ 714,607.46 Packet Page -422- Al STREET LIGHTING PHASE 36 6/25/2013 16.A.7. DESCRIPTION QUANTITY UNIT TYPE UNIT PRICE TOTAL PRICE 25 concrete pole and fixture 10,260 LF 1 $ 8.631$ 88,543.80 10/1 /2004 - # 1416490 N0506 -P3B- 000 -EDES Packet Page -423- SUB -TOTAL LIGHTING = $ 88,544 15% CONTINGENCY= $ 13,281.57 TOTAL LIGHTING = $ 101,825.37 0 LANDSCAPING 10 6/25/2013 16.A.7. PHASt ses DESCRIPTION QUANTITY UNIT TYPE UNIT PRICE TOTAL PRICE 1 LS $ 85,000.00 11,$ 85,000.00 Code minimum landscaping — $ 85 000 10/1/2004 - # 1416490 N0506 -P36- 000 -EDES SUBTOTAL LANDSCAPING — 15% CONTINGENCY = $ 12,750.00 TOTAL LANDSCAPING = $ 97,750.00 Packet Page -424- 11� to �1. J . 0 6/25/2013 16.A.7. IRRIGATION PHASE 3B DESCRIPTION QUANTITY UNIT TYPE UNIT PRIC TOTAL PRICE 4" irrigation Main (C -900, CL 150) 12,294 LF $ 11.50 $ 141,383.53 4" Irrigation Main (C -900, CL 200) 190 LF $ 17.25 $ 3,277.50 8" Irrigation Main (C -900, CL 150) 3,643 LF $ 19.79 $ 72,104.39 8" x 4" TEE 12 EA $ 46.00 $ 552.00 8" Gate Valve w/ Box _21 EA $ 977.50 $ 1,955.00 4" Gate Valve w/ Box 121 EA $ 805.00 $ 9,660.00 Controller w/ Rain Sensor 11 EA $ 3,450.00 $ 3,450.00 Electric Solonoid Valve 1 EA $ 230.00 $ 230.00 10/1/2004 - # 1416490 N0506- P3B- 000 -EDES SUE - l V I AL IMU T14 "VOW — P aaFo i s 16% CONTINGENCY= $ 34,891.86 TOTAL IRRIGATION = $ 267,604.29 Packet Page -425- 6/25/2013 16.A.7. RESOLUTION NO. 2013- A RESOLUTION OF THE BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA AUTHORIZING FINAL ACCEPTANCE OF CERTAIN ROADWAY AND DRAINAGE IMPROVEMENTS IN VERONAWALK PHASE 3B, ACCORDING TO THE PLAT THEREOF RECORDED IN PLAT BOOK 45, PAGES 5 THROUGH 11; RELEASE OF THE MAINTENANCE SECURITY; AND ACCEPTANCE OF THE PLAT DEDICATIONS WHEREAS, the Board of County Commissioners of Collier County, Florida, on July 20, 2005 approved the plat of Veronawalk Phase 3B for recording; and WHEREAS, the Developer has constructed and maintained the roadway and drainage improvements in accordance with the approved plans and specifications as required by the Land Development Code (Collier County Ordinance No. 04-41, as amended); and WHEREAS, the Developer is requesting final acceptance of the roadway and drainage improvements and release of his maintenance security; and WHEREAS, the Engineering Services Section of the Growth Management Division has inspected the roadway and drainage improvements, and is recommending acceptance of said facilities. NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA, that final acceptance is hereby granted for those roadway and drainage improvements in Veronawalk Phase 3B, pursuant to the plat thereof recorded in Plat Book 45, pages 5 through 11, and the Clerk is hereby authorized to release the maintenance security and accept the plat dedications. BE IT FURTHER RESOLVED AND ORDERED that the County accept the plat dedications; and the Veronawalk Homeowner's Association will maintain the roadway and drainage improvements within this project, with Collier County having no responsibility for maintenance of the roadway or drainage improvements. This Resolution adopted after motion, second and majority vote favoring same, this day of , 2013. ATTEST: BOARD OF COUNTY COMMISSIONERS DWIGHT E. BROCK, CLERK COLLIER COUNTY, FLORIDA By: /` Deputy Clerk GEORGIA A. HILLER, ESQ. 1 of 2 Packet Page -426- Approved as to form and legality: Emily R Pepin Assistant County Attorney CP \13- EIS - 02463 \3 2of2 Packet Page -427- 6/25/2013 16.A.7.