Agenda 05/13/2013 Item #16C85/14/2013 16.C.8. EXECUTIVE SUMMARY Recommendation to approve a work order for $590,318.25 to Kyle Construction under Request for Quotation 08- 5011 -78 for Underground Utility Contracting Services for the Wastewater Pump Station 158.00 Rehabilitation Project, Project Numbers 70046 and 70051. OBJECTIVE: Bring outdated utility infrastructure into compliance with current county standards, while meeting demand, protecting public health and safety, providing proactive environmental protections, and supplying backup pumping capability during power outages. CONSIDERATIONS: On June 24, 2008, as Agenda Item 10G, the Board of County Commissioners (Board) adopted the 2008 Wastewater Master Plan Update that identified the requirement for rehabilitating lift stations. The proposed scope of work for Project 70046, "Wastewater Pump Station Technical Support," is consistent with the 2010 Wastewater CIP Update, page 2 of 4, line 66, as identified in the 2011 User Fee Rate Study. The proposed scope of work for Project 70051, "Collections Power Systems Technical Support," is consistent with the 2010 Wastewater CIP Update, page 3 of 4, line 66, as identified in the 2011 User Fee Rate Study. Pump Station 158.00 is located in The Strand, a 575 -acre residential and golf course community west of I -75 and north of Immokalee Road. Wastewater service in this community is comprised of eight pump stations that collect sewage from small local gravity systems. Seven of the pump stations are connected into a common force main system that discharges into. Pump Station 158.00, located on Strand Boulevard just north of Immokalee Road. The number of households and businesses benefitted by the project are 1,239 residential households, one club house, and 133,948 square feet of retail space. The scope of work includes the addition of a standby diesel pump as part of the emergency power program. If any of the following four conditional criteria are met, then a permanent generator or standby diesel pump is required: 1) pump stations that have 25 hp or greater motors, 2) pump stations that are fed by four or more other pump stations, 3) pump stations that pump directly to a wastewater force main that pumps directly to the plant, or 4) pump stations that is operationally critical to hospitals, nursing homes, and environmentally sensitive areas. This project meets the first three criteria, and therefore warrants the installation of a standby emergency diesel pump, in this application. The emergency diesel pump will allow the continued pumping of wastewater flows during power outages, and increases station reliability. In addition, existing pumps will be replaced with more efficient lower horsepower pumps driven by variable frequency drives to prevent high pressure conditions in the force main that could cause Master Pump Station 107.00 to overflow. The confined space valve vault will be eliminated by moving piping and appurtenances above grade. Packet Page -2701- 5/14/2013 16.C.8. The Purchasing Department electronically distributed Request for Quotation 08- 5011 -78, Pump Station 158 Improvements, on March 13, 2013, to the five vendors under the Fixed -Term Underground Utilities Contract No. 08 -5011. Four of those contractors submitted quotations by the April 12, 2013, deadline. The quotations are summarized in the table below. VENDOR PROJECT COST Kyle Construction $ 590,318.25 Quality Enterprises $ 593,014.00 Haskins, Inc. $ 594,804.00 Douglas N Higgins $ 647,265.00 Mitchell & Stark Did Not Quote The engineer's opinion of probable construction cost was $444,896.00. Staff reviewed the quotations and determined Kyle Construction to be the lowest qualified and responsive bidder at approximately 33 percent above the engineer's cost estimate. A contributing factor to the higher quote price is that the estimate for the Xylem diesel pump and fuel tank was based on a standard integral fuel tank and a standard sound enclosure. During the bid process, modifications to the diesel pump specifications were made, which included custom fabrication for the fuel tank to minimize corrosion and a more robust sound insulation enclosure. This likely resulted in an increase to the vendor provided quote for the diesel pump during design. The quote tabulation and graph are Attachments 1 and 2, respectively. The Purchasing Department concluded that bidding was competitive and representative of market conditions. The project design professional, Stantec Consulting Services, Inc., also recommends award of this work order to Kyle Construction per the attached letter dated April 18, 2013 (Attachment 3). Kyle Construction has a satisfactory performance and warranty record on other similar utility - related construction projects with Collier County. The bid specifications informed the bidders there may be unforeseen conditions associated with the project. The project cost includes an allowance of $39,000.00 for owner- directed work due to unforeseen corrosive or geological conditions that include, but are not limited to, repairs due to structural deterioration, and /or replacement of defective mechanical equipment and deficient electrical components. Any additional work required due to unforeseen conditions will be addressed in accordance with the Purchasing Policy prior to authorization. FISCAL IMPACT: Funding is available in, and is consistent with, the FY 13 Capital Budget approved by the Board on September 20, 2012. The source of funding is the Wastewater User Fee Fund (414). The operating budget impact of the completed project is reflected in the table below. The total capital cost to implement Project 70046 Pump Station Rehabilitation is $590,318.25. There will be a minimal annual power cost saving of approximately $414 based on a 15% power savings (15% x $2,762 = $414). There will be an increase in maintenance cost for the standby pump of approximately $1,060. The resultant operating cost increase is $ 646 annually. Packet Page -2702- 5/14/2013 16.C.8. Elements FY 2013 FY 2014 FY 2014 - FY2033 Capital Outlay $ 590,318.25 $0 $ 0 Operating $ 0 $ 646 $ 12,920 Cost Change * *This reflects the approximate cost in the annual operating budget for each fiscal year over the life of the asset. LEGAL CONSIDERATIONS: This item has been reviewed and approved by the County Attorney's Office, is legally sufficient for Board action and only requires a majority vote for approval —SRT. GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. RECOMMENDATION: That the Board of County Commissioners, as Ex- officio Governing Board of the Collier County Water -Sewer District, approve a work order under Request For Quotation 08- 5011 -78 in the amount of $590,318.25, which includes an allowance in the amount of $39,000.00 for unforeseen conditions, to Kyle Construction; and authorize the Chairwoman to sign and execute the work order after approval by the County Attorney's Office. Prepared By: Corinne Trtan, Project Manager, Public Utilities Planning and Project Management Department. Attachments: Attachment 1- Quote tabulation Attachment 2- PPMD Bid Analysis Attachment 3- Recommendation Letter Attachment 4- Work Order Packet Page -2703- 5/14/2013 16.C.8. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.C.16.C.8. Item Summary: Recommendation to approve a work order for $590,318.25 to Kyle Construction under Request for Quotation 08- 5011 -78 for Underground Utility Contracting Services for the Wastewater Pump Station 158.00 Rehabilitation Project, Project Numbers 70046 and 70051. Meeting Date: 5/14/2013 Prepared By Name: RaineyJenniferA Title: VALUE MISSING 4/19/2013 3:48:14 PM Approved By Name: HapkeMargie Title: Operations Analyst, Public Utilities Date: 4/19/2013 4:14:45 PM Name: ParkerNicole Title: Contracts Specialist,Purchasing & General Services Date: 4/22/2013 7:53:37 AM Name: Steve Messner Title: Plant Manager,Water Date: 4/22/2013 10:44:26 AM Name: WardKelsey Title: Manager - Contracts Administration,Purchasing & Ge Date: 4/22/2013 3:07:42 PM Name: JacobsSusan Title: Operations Analyst, Public Utilities Date: 4/22/2013 4:12:21 PM Name: JacobsSusan Title: Operations Analyst, Public Utilities Packet Page -2704- Date: 4/25/2013 2:57:37 PM Name: JohnssenBeth Date: 4/25/2013 8:18:45 PM Name: Joseph Bellone Title: Manager - Utility Billing & Cust Serv.,Utilities F Date: 4/26/2013 3:26:12 PM Name: ChmelikTom Title: Director, Public Utilities Engineering Date: 4/26/2013 4:36:48 PM Name: MarkiewiczJoanne Title: Manager - Purchasing Acquisition,Purchasing & Gene Date: 4/29/2013 1:19:35 PM Name: YilmazGeorge Title: Administrator, Public Utilities Date: 4/29/2013 3:45:05 PM Name: TeachScott Title: Deputy County Attomey,County Attorney Date: 4/30/2013 11:53:47 AM Name: KlatzkowJeff Title: County Attorney Date: 4/30/2013 2:21:51 PM Name: UsherSusan Title: Management/Budget Analyst, Senior,Office of Manage Date: 5/2/2013 2:35:18 PM Name: OchsLeo Title: County Manager Date: 5/2/2013 4:58:27 PM Packet Page -2705- 5/14/2013 16.C.8. 5/14/2013 16.C.8. Packet Page -2706- I g °c 4m F M u u o 4➢ T Y P Y P c n v y 3 i8 3 v,; m$ 3 (i tai pppp cogai y m` i S 3 ', ' 3 e_ a e i R e 2S m ycy 3 s , $ x =s- - 3 ag v « « «uUma uo0_ 0 'ooa g s :�o $$$$$$$$$$$$$$s$ $$$$$$ �° w$'a$'8 °s 3'8 9 89 a S$$$ 8 8 S 8 8$ 8 S$$ 8 8$$ o$$$$ 8 8 8 S$$ S k 8 k$$ 8$ 8 k$ 8$$ s� ,�ss�saaaa�ogsNg��Has�aats��as $ ksaists $$sts = « »» «« „ « »» « « .. « « » « »» « N 8S1588888B8U $o$S8S88l�88888$NNo9 $$ 9 688iS$ e$$88 888888888888888$$8888$$8888$88 8 88888 $$$8 -: ss$ N 9 N 'I � .. s$$$s$as$'ssa$$$$$s's$$s$a$$$k g ksS'ss's $$$$ o 88888885888 888888888888888 gig 88 9 $8888 8888 Lim kl,- 1 8 d 8 0 8 5 5 5 5 5$ 5 8 5 5 5 5 5 8 5 5 5 5 5 5 $ .� 8 $ 5 5 8 5 5 8 8 8 8 8 Packet Page -2706- I g °c 4m F M 5/14/2013 16.C.8. ■/ Packet Page -2 7 7 i f§ | | ! | :____�: ; ;_ : ; ;_ : : :■ - 5-H 9�� x ' ! , § ; \ ;` H ;.l�El - = ! !_ E,_„ � § | ; - ■,!. |�! • � W;N , � , ' |E; ! | | ; !! ! !"! .!!§, !!! . , u-� _ , , �) Q |£ \ � ; ; ; ; ;,, « ��..,�_ its ! � ; ■ � > � § §! ¥§ §§ �§ km §� §§ ; ; ;z§ | , ; s ■ ; „ ■■4,# . ;■, ;, ; ;;� ;, , : ; ; ■.,. ;. § s.. ■a ; ;.i ;, ; $ .!§!!! §§ )i §§§ §�� : ;; • � « , ; ; ; §. ; ;§ ;,� \ \(j/ { - ■ ■ ■ ■ ■a■ », �., : , � ._ ■ . ; : ;\§!!�! - § §§ §)r§!•� ! , ; s.a ; ;.E ; ■..,... ;;, 4 ' ! » ` # § „ §r■k§ ,■ • ■!) ; §•! § =n � ; , . ; . „ ■s,... ■a ;.l,l.; », ;; . i ■,.�,.. ; ■E�...,K,E ?� , � ) � ; G ; ■ � §)§!4 }) �) #§ ;,...,..,.. § § § §§ § § ■\ { ■ :��...,, �. Packet Page -2 7 7 i f§ | m oa CD p c d x n V z x o'o' C 5' ta S a o 0 0 0 0 CD 0 0 0 0 0 0 0 Q =- M + p p p O + �, D Q m = „v,* � p — � 6� a, v C y m m u+ C p� Q 0 m v+ fD = CL G1 Q a rD o Q Q m m o o C < W m G m Packet Page -2708- 5/14/2013 16.C.8. 1 rt _ t Irt O A� 0 00 f cn 0 N V 00 C V'1 r+ lu O� N N'I 00 O C m fD 3 E r+ 0 5/14/2013 16.C.8. 0 Stantec April 18, 2013 File: 177310517 Stantec Consulting Services Inc. 5172 Station Way Sarasota FL 34233 Tel: (941) 365 -5500 Fax: (941) 366 -1922 Collier County Public Utilities Division - Wastewater Program 3339 Tamiami Trail, East Building H, Suite 301 Naples, FL 34112 Attention: Corinne Trtan, Project Manager Reference: Request for Quote #08- 5011 -78 — Pump Station 158.00 Improvements Dear Corinne: Quotes for the Pump Station 158.00 Improvements, Quote # 08- 5011 -78 were opened at 3 :00 pm on April 12, 2013. Four (4) bids were received and subsequently tabulated by Stantec. The apparent low bidder was Kyle Construction with a bid of $ 590,318.25. The Engineer's Opinion of Probable Cost for the project was $444,896.00. The bids were tabulated and are provided as an attachment along with the Engineer's Opinion of Probable Cost. The bids were well above the estimate, but the grouping of the bids makes it appear the bids are valid and reasonable. Aside from the sometimes unpredictable nature of contractor bids, there are two issues that may partially explain the bid amounts. First, the number of construction projects within southwest Florida has increased in recent months, however many construction companies are still operating with fewer qualified employees. As a result, many contractors are stretching their resources to bid on additional work, which can higher bids. Secondly, the estimate for the Xylem diesel pump and fuel tank was based on a standard integral fuel tank and a standard sound enclosure. During the bid process, there were modifications to the diesel pump specifications which included custom fabrication for the tank and sound enclosure. This likely resulted in an increase to the vendor provided quote for the diesel pump during design. Based on our analysis of the bids and discussions with local vendors, we believe the bids are reasonable for the current market and suggest approval of the Kyle Construction bid proposal. Respectfully, STANTEC CONSULTING SERVICES INC. ,rte t _ Kelly Blak P.E. Project Manager Tel: (941) 225 -6175 Fax: (941) 366 -1922 kelly.blake@stantec.com Attachment: Bid Tabulation Packet Page -2709- Stank April 15, 2013 Corinne Trtan, Project Manager Page 2 of 2 5/14/2013 16.C.8. Reference: Request for Quote #08- 5011 -78 — Pump Station 158.00 Improvements c. Craig Pajer, PE Collier County Joe Greeley, PE Stantec dwm c. users\ cbiake1appdateUocal lmicrosoftlwindows \temporary intemet files lcontent.outlookton38hgzx \mwt - letter.doex Packet Page -2710- 5/14/2013 16.C.8. Packet Page -2711- i ox 3 �m ? I a I ;> la iR 6 A( 4 I�' I I O I" ���Sp• TIT i3 r O 2 2 s 9 O 1� m T � ; � 2- f) (m 10 E _ Io� o6a 9 14 p $ '1i i Q 'S T 9 [tug •'9 IA �- i� 2 Z� � g -� 2 T � � IF RI 1•'y 3 IN m b. ' CO (1 r 1 Im y 1 d gp Io ; i i 1 I,. r 1• i { I � {� �. I I I ,• � � !T. T T T 5 5 D M g D / D iD D ➢ D, 1 Iti , y y l y , "pop, - «Iwlw 8,8 8.8 8I818i8i$ 818;8 8i$18 8!8(0! ,° °e,o� S {S� °18181 m,$�818 i 818 8 S "S�SIS '8 $1818 gib 8 8 8 5 S 8 r,l Si Iglu S 81 IBIS I� I 818I8i�I81s I §�g a 8 mI 1810 I8 8Ig � " 1 8 { °I$ Ig R!818 818 8 91g Sl8 8 8 8 8 $i8 8i1S�$) { ISI i °IB.SIS!$i � 1 18':8 8 8 SsS $ � 251'1018 810 $183 81g , �s ° ml °gl$1 , °lols g�ss g o +° ° °is s� s gas s ors) I Islal I $Isla g sol i�;ai� Emlois i list, I B I° I11111014 bnl�iNlS 8iw 81 o1;!Nlo 81 { oI8I8,olol SIS 810 8� °�H�SS mlo 1 ' ° o m�y�8{o�8 S,o�oIS 8 e'I✓71SS 8�m, ° i�r oi$I 1 � 18 8 �o1�.881oo I mf818S I S8 8;8;818`8 8 8 S S i I° ( is 1 Oil j « ,w «i «, «I� «� I «I «Iw wi�• � I � i I« «, ' «i« «I w� «1 «`H 1 s (818 limit i Packet Page -2711- i ox 3 �m 5/14/2013 16.C.8. Packet Page -2712- T.1 M. a 0 MI. Ibl £_r' Ig i Z I' a rn °]�'i —j T Ll? za s. is & jr - 1w, iy PZ; P K K o< j lo, 91- 6 60 1 1 isi i s 8 sI8 '$ b.lgi9j. el ml '81's 8 !M .1.1. 6 g b 8 8'818. I-. 11-8 841 118A 819 ig gig '8 si I- t N'« -1 1 181--. ' 8 1.1, 'pig. '8 sj§j§ N 1. slilsib. g o 61 gig $'818,8 8198 .18 sl II I . . Uzi pI 3 91819131 El Am s o�sls�sl 6!916.191 .618 N�s N s It 8 N. . E 'm' i 6. b. 18 °s ,$I i 6. s° 1 6'. 1 5 N ,s g I g big 8 819 9 9 .1 8 81°16. g 9 iigll.�sls 8�81 8181 9 8 8 8 8 0 818 8 Packet Page -2712- WORK ORDEF/PURCHASEOR0ER Agreement for "Annual Underground Utility Contractors" -#08-5O11 Contract Date. March 11 2008 Fixed Term Contract Exmnes� March 10. 2014 (RFQ #08'5011-78) BCC approval Date May 142O13 This Work Order m for Underground Utility Construction services for work known as� Project Name PS 158.00 Rehabilitation Project No(a). 7D046,70051 The work is specified m the proposal page dated April 12, 2013 which is attached hereto and made a part of this Work Order. In accordance with Terms and Conditions ofthe Agreement referenced above and Request fo/ Quotation #08-5011-78 dated March 13 2013, as modified by Addendum 1 th,u 2. attached hereto part of this Work Order # (please fill out once rec*ived).s assigned to Kyle Construction. Inc. Scope of Work As detailed in the Quote Tabulation form and the following Existing va|vevauft vvetwe|} piping and pumps shall be removed The wet well shall be patched and coated New wet well pmmQ pumps guide bara brackets, f|oats, etc are proposed along with new above ground p/p/ng and valves, e|ectnco| upgrades are also included The Contractor is responsible for all required bypassing and shall provide power (o pump station throughout construction Task l From Item 1 through 8 O Quote - 8upp}v and install pumca mun,ro| pa-ie|s p,pmg m ,ne we, wy|/endaoovegroundando/kerneoessa/ymatene|otocompletefhevvorvas/ntended by1ne p|ans -Task 2, item 9 of Quote - Owner-directed Work for geological or Corrosion Unforeseen Conditions Schedule of Work. Complete work substantially 335 days after issuance of the Notice to Proceed, with an additional 30 dayato Final completion for a total of 365 days The Notice to Proceed is acoompanymg tn/s VVorhDrdsr |n Accordance with Numb*ed Paragraph Four of the Agreement the County will compensate the Firm with the s) [*]Negotiated Lump Sum TlLump Sum Plus Reimbursable Costs Time& KAa\ena| (established hourly rate- Schedule A) ElCos1 Pius Fixed Fee. as provided in the attached-� proposal Task 7 $ 551,318.25 (LS) Task Total Fee: $ 590,318i25 Prepared By" Corinne Trtan. Pro-ject Manager Date Planning & Project Management Department Approved By Craig Paj?f-,'\-PE. Pr6cipai Project Manager Date Planning %__E!)oject Management Department Authorized By "^"y="/e"^, rc Director Date Planning 8 Project, Management Department Packet Page -2713- 0 RFO#08-bO11-78 Page Approved By / 44 Stev6 Messner Interim Director Date Wastewater Department Approved BW hnoa Operations Manager Wastewater Department Authorized By- Dr. George Yilmaz, Administrator PbhcUNU Approveo By Nicofe Parker. Procuremen� Specialist Purchasing Departmentgf'11211JIS ATTEST Dwight Brock Clerk Deputy Clerk Approved asto Form and Legal Sufficiency 4eil;m* County Attorney , / Packet Page -1714- Date A) ate Date 0 BOARD OF COUNTY COMMISSIONERS Collier County Florida By Georgia H/Uer, Eoq Et ATTEST (Print Name!Titie) Cnanwoman '^. ~f