EXECUTIVE SUMMARY
This item requires that ex parte disclosure be provided by Commission members. Should a hearing
be held on this item, all participants are required to be sworn in. Recommendation to approve
extensions for completion of subdivision improvements associated with the Moorgate Point
subdivision (AR -7618) and Classics Plantation Estates, Phase Three subdivision (AR -7433)
pursuant to Section 10.02.05 B.11 of the Collier County Land Development Code.
OBJECTIVE: To approve extensions for the completion of subdivision improvements
associated with Moorgate Point and Classics Plantation Estates, Phase Three.
CONSIDERATIONS: On December 13, 2005, and January 24, 2006, the Board of County
Commissioners (Board) approved the final plats of Moorgate Point, and Classics Plantation
Estates, Phase Three respectively for recording. Section 10.02.04 B.3.b of the Land
Development Code requires that upon approval by the Board, a plat must be recorded within 18
months and the associated subdivision improvements must be completed within 36 months
unless an extension is formally requested and granted by the Engineering Services Department.
On March 6, 2006, the plat for Classics Plantation Estates, Phase Three was recorded in Plat
Book 45, Pages 28 through 33. On November 17, 2006 the plat for Moorgate Point was
Zn
recorded in Plat Book 47, Pages 64 through 67.
The developer requested and has been granted previous extensions for completion of the
improvements. The projects are both within the Lely Resort Planned Unit Development
(PUD), and both projects are being developed by Stock Development.
The developer failed to request an extension approval for Moorgate Point prior to December
13, 2012, and for Classics Plantation Estates, Phase Three prior to January 24, 2013. Had the
extension requests been submitted, the approvals of the requests would have been
perfunctory. Collier County has now received a request for extensions from December 13,
2012 through December 13, 2013, for Moorgate Point, and from January 24, 2013 through
January 24, 2014 for Classics Plantation Estates, Phase Three. The developer has paid the
appropriate fees for the one -year extensions. There are currently Performance Bonds in place
to guaranty the completion of the required subdivision improvements.
FISCAL IMPACT: The County will realize revenues as follows:
Fund: Growth Management Fund 131
Agency: County Manager
Cost Center: 138327 — Growth Management
Revenue generated by this project: Total: $300.00 Extension Fees
LEGAL CONSIDERATIONS: This item has been approved by the County Attorney's
Office, is legally sufficient, and requires a majority vote for approval. — ERP
Packet Page -1116-
5/14/2013 16.A.9.
GROWTH MANAGEMENT IMPACT: There is no growth management impact.
RECOMMENDATIONS:
1. That the Board accept the applicant's extension requests together with the appropriate
back fees.
2. Approve the extensions for Moorgate Point (AR -7618) and Classics Plantation Estates,
Phase Three (AR -7433) so that the developer may be in compliance with the requirements
of the Land Development Code.
Prepared by: John Houldsworth, Senior Site Plans Reviewer, Engineering Services, Growth
Management Division, Planning and Regulation
Attachment: Application Requests
Packet Page -1117-
5/14/2013 16.A.9.
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.16.A.16.A.9.
Item Summary: This item requires that ex parte disclosure be provided by Commission
members. Should a hearing be held on this item, all participants are required to be sworn in.
Recommendation to approve extensions for completion of subdivision improvements
associated with the Moorgate Point subdivision (AR -7618) and Classics Plantation Estates,
Phase Three subdivision (AR -7433) pursuant to Section 10.02.05 B.11 of the Collier County Land
Development Code.
Meeting Date: 5/14/2013
Prepared By
Name: HouldsworthJohn
Title: Site Plans Reviewer, Senior,Engineering & Environm
4/9/2013 8:12:09 AM
Approved By
Name: PuigJudy
Title: Operations Analyst, GMD P &R
Date: 4/25/2013 10:30:19 AM
Name: McKennaJack
Title: Manager - Engineering Review Services,Engineering & Environmental Services
Date: 4/25/2013 11:55:11 AM
Name: PepinEmily
Title: Assistant County Attorney, CAO Litigation
Date: 4/26/2013 9:42:51 AM
Name: MarcellaJeanne
Title: Executive Secretary,Transportation Planning
Date: 4/30/2013 8:17:05 AM
Name: KlatzkowJeff
Title: County Attorney
Date: 4/30/2013 10:17:57 AM
Packet Page -1118-
Name: FinnEd
Title: Senior Budget Analyst, OMB
Date: 4/30/2013 3:44:29 PM
Name: OchsLeo
Title: County Manager
Date: 5/2/2013 4:30:02 PM
Packet Page -1119-
5/14/2013 16.A.9.
5/14/2013 16.A.9.
•
DEVELOPMENT
March 27., 2013
John Houlswortb
Collier County Growth Management
2800 North Horseshoe Drive
Naples, FL 34104
Subject: Moorgate Point final subdivision acceptance
John.
Please accept this letter as a request for extension to complete the final subdivision improvements for
Moorgate Point (a, Lely Resort. To date. the project has received a Conditional Final Acceptance for all
paving & drainage subdivision improvements, and Final Acceptance for all water and sewer
improvements. We currently have four (4) vacant lots remaining in the community. We continue to
aggressively market the community and expect to reach buildout within 2-3 months and pursue Final
Acceptance shortly thereafter.
Please note that Collier County currently has 5103,895.25 in performance security posted for
infrastructure improvements, which are in excess of the actual cost to complete. I have enclosed the
required S 150.00 fee for the extension request. If you have any questions., please feel free to contact me.
Sincerely,
Keith 'elder
Director of Land Development
Enclosures
eci Chris Mitchell, Mitchell Engineering
Packet Page -1120-
5/14/2013 16.A.9.
SDEVELOPMENT
March 121 7. 201,3
John Houlsworth
Collier County Growth Management
2800 North Horseshoe Drive
Naples, FL 34104
Subject: Classics III final subdivision acceptance
John.,
Please accept this letter as a request for extension to complete the final subdivision improvements for
Classics Plantation Estates — Phase Ill. To date, the project has received a Conditional Final Acceptance
for all paving & drainage subdivision improvements, and Final Acceptance for all water and sewer
improvements. We currently have twelve (12) vacant lots remaining in the community. We continue to
aggressively market the community and expect to reach buildout within 9-12 months and pursue Final
Acceptance shortly thereafter.
Please note that Collier County currently has 5137,.997.00 in perfortnance security posted for
infrastructure improvements, which are in excess of the actual cost to complete. I have enclosed the
required $150.00 fee for the extension request. If you have any questions, please feel free to contact me.
Sincerely,
Keith 6'elder
Director of Land Development
Enclosures
cc: Chris Mitchell. Mitchell Engineering
Packet Page -1121-