Agenda 11/18/2014 Item # 16A 511/18/2014 16.A.5. EXECUTIVE SUMMARY Recommendation to approve final acceptance of the private roadway and drainage improvements for the final plat of Summit Place in Naples, Phase II (AR -6955) and authorize the acceptance of the plat dedications and release of the maintenance security (Performance Bond) in the amount of $182,800.58. OBJECTIVE: To have the Board of County Commissioners (Board) grant final approval of the improvements associated with the Summit Place in Naples Phase II plat, accept the plat dedications, and release the maintenance security in the amount of $182,800.58. CONSIDERATIONS: 1) On May 14, 2007, the Engineering Services Department granted preliminary acceptance of the roadway and drainage improvements in Summit Place in Naples, Phase II. 2) The roadway and drainage improvements will be maintained by the project's homeowners association. 3) The required improvements have been constructed - in accordance with the Land Development Code. The Engineering Services Department has inspected the improvements and is recommending final acceptance of the improvements. 4) A resolution for final acceptance has been prepared and approved by the County Attorney's Office. The resolution is a requirement of Section 10.02.05 C.1 of the Land Development Code. A copy of the document is attached. 5) The Summit Place PUD which encompasses Summit Place in Naples, Phase 11 has been found to be in substantial compliance. FISCAL IMPACT: The roadway and drainage improvements will be maintained by the project's homeowners association. The existing security in the amount of $182,800.58 will be released upon Board approval. The original security in the amount of $2,571,165.63 has been reduced to the current amount of $182,800.58 based on the previous work performed and completed and pursuant to the terms of the Construction and Maintenance Agreement dated April 25, 2006. GROWTH MANAGEMENT IMPACT: There is no growth management impact. LEGAL CONSIDERATIONS: This item has been approved as to form and legality, and requires a majority vote for Board approval. - SAS RECOMMENDATION: To have the Board accept final acceptance of the roadway and drainage improvements in Summit Place in Naples, Phase II Application Number AR -6955, and authorize; The Chairman to execute the attached resolution authorizing final acceptance of the improvements and plat dedications. 2. The Clerk of Courts to release of the maintenance security. Prepared By: John Houldsworth, Senior Site Plans Reviewer, Growth Management Division, Planning and Regulation Attachments: 1) Location Map, 2) Bond Basis and 3) Resolution Packet Page -954- 11/18/2014 16.A.5. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.A.16.A.5. Item Summary: Recommendation to approve final acceptance of the private roadway and drainage improvements for the final plat of Summit Place in Naples, Phase II (AR -6955) and authorize the acceptance of the plat dedications and release of the maintenance security (Performance Bond) in the amount of $182,800.58. Meeting Date: 11/18/2014 Prepared By Name: HouldsworthJohn Title: Site Plans Reviewer, Senior, Natural Resources 10/6/2014 2:47:53 PM Approved By Name: BeardLaurie Title: Planned Unit Development Coordinator, Transportation Planning Date: 10/7/2014 2:46:24 PM Name: PuigJudy Title: Operations Analyst, Community Development & Environmental Services Date: 10/14/2014 4:40:25 PM Name: McKennaJack Title: Manager - Engineering Review Services, Natural Resources Date: 10/23/2014 1:05:39 PM Name: StoneScott Title: Assistant County Attorney, CAO Land Use /Transportation Date: 10/28/2014 8:19:20 AM Name: Marcellaleanne Title: Executive Secretary, Transportation Planning Date: 11/3/2014 11:34:17 AM Name: KlatzkowJeff Title: County Attorney, Packet Page -955- 11/18/2014 16.A.5. Date: 11/3/2014 2:31:15 PM Name: IsacksonMark Title: Director -Corp Financial and Mngmt Svs, Office of Management & Budget Date: 1 l /4/2014 9:41:56 AM Name: FinnEd Title: Management/Budget Analyst, Senior, Transportation Engineering & Construction Management Date: 11/4/2014 12:50:56 PM Name: OchsLeo Title: County Manager, County Managers Office Date: 11/6/2014 3:45:03 PM Packet Page -956- 11/18/2014 16.A.5. wm Z 7 JF §/ � !§ § ui § m_j ( § p- ! , \ �)\ � `�4 | ..PLACE OR § :65 J ! § ■ » «2> « \2?/° / :�: | | f g N u ° ! ! \\ , G / E \ § 4 \ ! ! IL R §) ( - / | wm Z 7 JF racKe rage -9-57- � Q � W � CL Q � Z O Q U O J W } § ) z \ / � � !§ � .E § p- , �)\ � `�4 § :65 § % z | | f g N u \\ , G / !^ ! IL R §) | ( ; - ZEE _ H3 LNtro £ - _ f\ ; § ■ racKe rage -9-57- � Q � W � CL Q � Z O Q U O J W } § ) z \ / � � T)k NICIJisualiT D rion C D N S U L_-r [ N; G Civil Eng:irrc- -ring; _l L T 7.& JL Surveying & Mapping SU1MAUT :F'LA.CIE IN N.APLES MA,SE II PRI?LIh1I1�f.��RY' C►PT�1IG)�l IC)h :F')R,OI3A:EIL:E COST SUMMARY SANITARY SE.ViTIt POTABLE *W.ATER STORM DRAINAGE 11/18/2014 16.A.5. $293,389.75 $449,774.50 $397,214.20 PAVING $490,099.75 EARTH WORK $688,535.10 LANDSCAPE. $18,410.00 TOTAL $2,337,423.30 Contingence (110° 4, of 'CDta;l) Prices updated 03 -03 -06 Summit Phase 11 0:3.(G -06 OTIC IZEV 3 Packet Page -958- $2,571,165.63 6/9/2006 11/18/2014 16.A.5. JA""C ' ,Visun li € Lion CON S U I -T I N G lCivil. E price -ti:ng .L �. 7 '/.L AL Surveying 8: Mapping Fly l= ',LIIvIIrJA,IZ �' C)F'P�TI {)N OF E' R C)E ABLE COST Project: Summit Place Phase: ][I 01- 01'i(LU) ~i ~ Estimsited By: iKeuth Mohamed Checked By: Caro6inia Matiz -Partin SANITARY !i:EI71 ✓lER _ GESCRIT'NCION --- L _ _ _ UNIT OLANITIIYI— _ c�hT I TOTAL -_� — -�_Y�_ - -� 8" PVC Sanitary Sewer Main (0' -E' cut) LF 1,286 $27.1:5 — $34,914.90 8" PVC Sanitary Sever Main (6-8' cut) LF 1,140 $:33.10 $37,734.00 8' PVC Sanitary 'Sewer Main (8' -10' out) LF 538 $49.10 $26,415.80 8' PVC SaniUay ,Sewer Main (10' -12' cut) LF 543 $54.10 $29,376.30 4' diameter Manhole (0' - "6' cicpl.h) EA 9 $3,300.00 $29,700.00 4' diameter Manhole (6' - "8' depth) EA 8 $3,900.00 $31,200.00 4' diameter Manhole (8' -10' depth) EA 1 $4,800.00 $4,800.00 4' diameter Drop Manhole (8' -•] 0' depth) EA 1 $5,625.00 $5,625.00 4' diameter Manhole (10'••12' depth) 6A 2: $5,900.00 $11,800.00 Rcmove Plug and Connect existing; 8" :PVC S.a:nitary Sewer EA 3 $4,000.00 $12,000.00 6" PAC Sanitary Sewer Lateral LF 2,529 $13.75 $34,773.75 6 "Single Clean• -oul: EA 31 $275.00 $8,525.00 6" Dcuble Clean -gout EA 71 $27 5.00 $19,525.00 Television Insnection LS 1 57,000.00 $7,000.00 Sanitary Sewer Sub - Total $293,389.75 Summit Phase 11 03.03 -06 OPC FTIV3 6/9/2006 Packet Page -959- 11/18/2014 16.A.5. DIATAINC. u )Visualization C O N S ILI L_ T I iN (3 Civil Engineering .L t h h.L. .L Surveying &. Mapping ]PRFLITvI[r1A.R'C' ('-)PrN[OT� Or PROBABLE COST Project: Summit Place Phase 11 01-01M) (i ^ Estimated By: Keith Mohamed Checked By: Carolina Matiz -Pardo POTABLE `VirM' ER DESCRIPTION UNTF U �TITCT � TOTAL C O T 4" PVC Casing, 111' 3,181 57.00 $22,267.00 1 1/2" Water Service (Sch. 80) LF '3,181 $12:.50 $39,762.50 8" PVC Wate:rlvlain (C =900, Class 150, DR 18) LF 3,686 $31.50 $116,109.00 8" MY Water Main (C -900, Class 200, DR 14) LIT" 297 $30.00 $8,910.00 8" Gate Valve wI)ox EA 6 52.100.00 $12,600.00 1 1/2' Double Water Meter EA 74 S 1.750.00 $129,500.00 1 1/2' Single VVater Meter EA 3:5 $900.00 $31,500.00 Fire Hydrant and. Valve EA 14 $3,2.26.00 $45,164.00 Dead -End Fire :Hydrant EA 1 $3,2°*10.00 $3,250.00 Fire Hydrant w/ Temporary Bacterial Sample Point EA 2 $3,226.00 $6,452.00 Perm,ment Bacterial Satnpie Point EA 1 $1,1 "x'(1.00 $1,170.00 Reflective Pavement Marker ]EA l 'i $6.00 $90.00 Connect to ExistinglVaterMain IEP� 3 $11,000.00 $33,000.00 Potable Water Sub-Total $449,774.50 Summit Phase 11 03- 03 -06 0P'C FI V3 6/9/2006 Packet Page -960- 11/18/2014 16.A.5. IN C. Planni o� DIVA V isaal i:.i lion "`(7 \ S 1. ?i,'I` I'ti i ; Civil Eugincering L. 't IF 1.1. JL 5ur;e}ing & Nlappijw 1, _1. OPINION OF PROBABLE COST" Pr ijwl: Summit Place Plutee 11 01-01M.10 F.a hmatd By: Keith Muhamed Ch eekal By: Carolina Mlitit -Pardo 12" NUPE LF 269 $ i Z80 54,783.20 15" RCP LF 583 !63:.1)0 $18,656,00 18" RCP LF 875 S40.00 $35,00.0C 24" RCP LF 341 1552.0(1 $17,732.0C 30" RCP LF 1.072 S9C.00 $96,480.00 36" RCP LF 122 $1 D9.OD $13,2.98.00 42" RCP LF 560 $12:5. OD $70,000.00 2" dia Post Fence LF 120 512,00 $1,440. DO 18" Flared End EA 3 $2,75C.00 $8,2:i0.DO 24" Flared End EA 3 33,5M.00 $10,500 CO 30" Flared End E.A 3 (4,050.00 $12.15000 Grate Inlet (6'x Ei) EA 2 $2.25 -0.00 '4,500.00 Valley Sutter Inlet EA 19 $3,000.00 $57,OOD00 Throat Inlet (bottom) EA 1 $3,000.00 $3,000.00 Type ";C" Box EA 3 $1,100.00 $3,:300.00 Junction Box (4' x 4') EA 9 $2,800.0C $25,200.00 Jul letioI Box (5' x 5') EA 3 $2,E:90.(P0 $8,670.00 Outfall Structure 5A 1 $1 250.00 $1,21;C:00 Control Structure. EA 1 $6,000 CO $6,000.00 Storm Draiinage Sub= Colal $397,214.2:0 Summit Plus, II 03 -03 -G6 01'C REVS 6/9;2)06 Packet Page -961- Idisun� li:�ation C 0 N S,1L I "T"I Ni G Civil Engine.,--ring L r 1F'J- JL Si.irveying S, Mapping; PRELTn✓[I Q RY OPINION OF PrROBA.BL:EE CDDS , Project: Summit Place Phase 11 (11- 0150..10 w — — Estimated By:: Neith Mohamed Checked By: C;Qrolina Matiz -Pardo PAVING d, GR;A.DING 11/18/2014 16.A.5. -- — DE : ; ;C'RIF'TIO.Nf r UNIT QHJANTITY UNIT TOTAL — ------------------- - --- -- -- CO CT 2' Wiley Gutter 111? 7,990 .611.00 3' Valley Crossing; LF 65 :632.50 2' Type F Curb wid Gutter 1117 460 X621.00 1 1/2" Asphall.ic Concrete (Type 5 -111) S`.( 9,602 $6.50 8" Urnerock Base (L13R: 100'i Sl( 11, 1520 $9.75 4" Limerock Erase (1,1313. 100) SN 6,266 $7.50 12" Stabilized Subgrad.e: (L BR .40) SN' 12,479 $2.00 5' Concrete Sidewalk LF 8,055 $12.75 10' Curb Transition EA 2 $350.00 Saw -cut and Match Existing Pavement 1EA 3 $5,000.00 Saw -cut and Match Existing S.iclom a.lk EA 6 $2,500.00 Throat Inlet (top) F-A 1 :6850.00 Signing and Striping LS 1 $9,500.00 Paving and Grading Sub- Tol:al $87,890.00 $2,112.50 $9,660.00 $62,413.00 $112,320.0 0 S46,995.00, $24,958.OG $102,701.2.5 $700.00 $15,000.00 $15,000.00 $850.00 $9,500.00 $490,099.7!; Summit Phase 11 03- 03 -06) OPCC RE'N3 6/9/2006 Packet Page -962- Atl 1 "' VR "fill i ualiz:ation C (_) N ti t_ I' I N C' Civil Entzinecrin- _l IL ► rl. .i Siurs /c, im & Mapping FIRE71,11M]NARY OPITI ION OIL PROBABLE, C -'OST Project:Summit Place Phase If E :dimated By: Carolina Matiz -Pardo Checked By: Jamey Anderson F,ARTH WORIK 11/18/2014 16.A.5. --- -- - -r- I)ESCRI1PTIOi`1 - ~ -- - -r C11VIT QLJA1'1'i I ]f "Y C�NIT TOTAL -- - - -�_� COST' -- 4' Swale LF 2,874 $2.00 10' Berm 11IF 2..874 $3.00 Littoral Plantings SF 8.,632 $0.55 Excavation CY I10,511 $3.0.0 Einbmkment CY 110,511 $1.50 Impol Fill CY 4,378 $20.00 Cearing & Grubbinl; (medium) AC 23 $3,4:50.00 Silt Fence LF 3,472 $1.150 E'lorthwork Stub- Total $5,748.00 $8,622.00 $4,747.60 $331,533.00 $165,766.50 $87,560.00 $79,350.00 $5,208.00 $688,535.10 Surrrrnit Phrase 11 03- 03- 06'F'C F:EV3 6/9/2006 Packet Page -963- 11/18/2014 16.A.5. RESOLUTION NO. 14- A RESOLUTION OF THE BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA AUTHORIZING FINAL ACCEPTANCE OF CERTAIN ROADWAY AND DRAINAGE IMPROVEMENTS IN SUMMIT PLACE IN NAPLES, PHASE II, ACCORDING TO THE PLAT THEREOF RECORDED IN PLAT BOOK 46, PAGES 63 THROUGH 66; RELEASE OF THE MAINTENANCE SECURITY; AND ACCEPTANCE OF THE PLAT DEDICATIONS. WHEREAS, the Board of County Commissioners of Collier County, Florida, on April 25, 2006, approved the plat of Summit Place in Naples, Phase I1 for recording; and WHEREAS, the Developer has constructed and maintained the roadway and drainage improvements in accordance with the approved plans and specifications as required by the Land Development Code (Collier County Ordinance No. 04 -41, as amended); and WHEREAS, the Developer is requesting final acceptance of the roadway and drainage improvements and release of his maintenance security; and WIIEREAS, the Engineering Services Department has inspected the roadway and drainage improvements, and is recommending, acceptance of said facilities. NOW. THEREFORE. BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA, that final acceptance is hereby granted for those roadway and drainage improvements in Summit Place in Naples, Phase II, pursuant to the plat thereof recorded in Plat Book 46, pales 63 through 66, and the Clerk is hereby authorized to release the maintenance security. BE I1' FURTHER RESOLVED AND ORDERED that the roadway and drainage improvements within Summit Place in Naples. Phase II xvill be maintained privately in the future and will not be the responsibility of Collier County. This I"esolution adopted after motion, second and majority vote favoring same, this day of __ 2014. ATTEST: DVA'1GHT E. BROCK. CLERK Deputy Clerk BOARD OF COUNTY COMMISSIONERS COLLIER COUNTY. FLORIDA By: 1 o1'2 Packet Page -964- TOM HENNING, Chairman Approved as to form and legality: Scott A. Stone Assistant County Attorney C P`:I 4- EIS - 02707\2 5/41iy 2 of 2 Packet Page -965- 11/18/2014 16.A.5.