Agenda 10/28/2014 Item #11E10/28/2014 11. E. EXECUTIVE SUMMARY Recommendation to award Bid Number 14 -6330, "Master Pump Station 109 Improvements," to Douglas N. Higgins, Inc., in the amount of $1,596,937 under Master Pump Station Technical Support Project Number 70050. OBJECTIVE: To maintain reliable and sustainable wastewater service by rehabilitating Master Pump Station (MPS) 109. CONSIDERATIONS: The proposed scope of work under Project Number 70050, "Master Pump Station Technical Support," is consistent with the Capital Improvement Program (CIP) contained in the Water, Wastewater, Irrigation Quality Water, and Bulk Potable Water User Rate Study approved by the Board of County Commissioners (Board) on June 10, 2014, as Agenda Item I IC. Funding for Project Number 70050 is available in, and is consistent with, the FY2015 CIP Budget. MPS 109 is located on the Pelican Bay Utility Site at the southern end of Watergate Way. This is a critical pump station in the wastewater collection system and must be kept in operation at all times. This project will update the station to current utility standards and increase its efficiency and reliability, benefitting approximately 7,600 residential /commercial units in Pelican Bay, having a population of approximately 13,000. Improvements to MPS 109 include pump replacement, new piping, variable frequency drives, and electrical controls. The electrical controls will be housed in a new, prefabricated, climate controlled building to provide protection from the weather and extend equipment life. A diesel engine driven pump and standby diesel generator will increase station reliability by providing emergency pumping capability. Fencing and odor control are included to meet the county's standards of security and its good neighbor policy. Bid number 14 -6330 was advertised on August 5, 2014. Ninety -five prospective bidders downloaded bid packages. On September 8, 2014, the three sealed bids received for the construction of this project were opened. The bids are summarized below. VENDOR PROJECT COST Douglas N. Higgins $ 1,596,937.00 Quality Enterprises $ 1,597,053.10 Mitchell & Stark $ 1,799,000.00 Staff and the local project design engineer, AECOM, determined that the lowest bid is fair and reasonable, and recommend awarding the contract to Douglas N. Higgins, Inc. The bid is approximately 10 percent below the design engineer's opinion of cost of $1,77' ),280. The bid tabulation, analysis chart, engineer's letter of recommendation, and contract are attached (Attaclnnents 1, 2, 3 and 4, respectively). The bid specifications infonned the respondents that there may be unforeseen conditions associated with the project. The bid amount incorporates an allowance of $125,000 for owner - directed additional work including, but not limited to, modifications to existing piping, valves, electrical wiring and conduit. The price for any additional work will be negotiated prior to commencement in accordance with the county's Purchasing Ordinance and the terms of the agreement. Packet Page -5S8- 10/28/2014 11. E. FISCAL IMPACT: Funding is available in, and is consistent with, the FY2015 Capital Budget approved by the Board on September 18, 2014. The source of funding is the Wastewater User Fee Fund (414). Using today's dollars, the total cost to replace the equipment at the station is $1,596,937, with a life expectancy of 12 years for electrical, controls, pumps and mechanical equipment, generating an approximate annualized capital cost of $133,000. The operating budget impact of the completed project is reflected in the table below. The funding source will be user fees. Elements FY2015 FY2016* Cumulative FY2016 — FY2027 Capital Outlay $ 1,596,937 Total Operation and Maintenance $5,500 $66,000 Total Operating Costs $5,500 $66,000 Cost Savings ($12,700) ($152,000 Net Operating Effect $7,200 $86,000) Operating costs reflect an estimate of the additional funds needed in the annual operating budget for each fiscal year. The addition of the climate controlled electrical building and the diesel engine driven pump represent an annual cost increase of approximately $5,500, while the improved efficiency of the pumping system and the use of appropriately sized standby diesel generator provides an annual savings of approximately $12,700. The net result is a $7,200 estimated annual savings in operating cost. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval. —SRT GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. RECOMMENDATION: That the Board of County Commissioners, Ex- officio the Governing Board of the Collier County Water -Sewer District, award bid number 14 -6330 to Douglas N. Higgins, Inc., in the amount of $1,596,937 for the "Master Pump Station 109 Improvements "; and, authorize the Chairman to sign the attached agreement after final review and approval by the County Attorney's Office. Prepared By: Wayne M. Karlovich, Senior Project Manager. Public Utilities PPMD Attachments: Attachment I - Bid Tabulation Attachment 2- PPMD Bid Analysis Attachment 3- Engineer's Recommendation Letter Attachment 4- Contract (Due to the size of this document, a web link is provided for viewing: DN Higgins Contract A hard copy is also available at the County Manager's Office.) Packet Page -559- 10/28/2014 11. E. COLLIER COUNTY Board of County Commissioners Item Number: 11.11.E. Item Summary: Recommendation to award bid number 14 -6330, "Master Pump Station 109 Improvements," to Douglas N. Higgins, Inc., in the amount of $1,596,937 under Master Pump Station Technical Support Project Number 70050. Meeting Date: 10/28/2014 Prepared By Name: KarlovichWayne Title: Project Manager, Senior, Public Utilities Engineering 10/3/2014 1:39:42 PM Submitted by Title: Project Manager, Senior, Public Utilities Engineering Name: KarlovichWayne 10/3/2014 1:39:43 PM Approved By Name: Joseph Bellone Title: Director - Operations Support, Utilities Finance Operations Date: 10/7/2014 7:55:30 AM Name: HapkeMargie Title: Recycling Coordinator, Solid & Hazardous Waste Management Date: 10/7/2014 9:06:15 AM Name: JohnsonScott Title: Manager - Procurement, Purchasing & General Services Date: 10/7/2014 10:02:21 AM Name: JacobsSusan Title: Operations Analyst, Public Utilities Division Date: 10/7/2014 12:28:48 PM Packet Page -560- 10/28/2014 11. E. Name: NagySteve Title: Manager - Wastewater Collection, Wastewater Date: 10/7/2014 1:30:45 PM Name: HerreraSandra Title: Manager - Procurement, Purchasing & General Services Date: 10/7/2014 1:58:59 PM Name: MarkiewiczJoanne Title: Director - Purchasing/General Services, Purchasing & General Services Date: 10/9/2014 7:29:27 AM Name: JohnsonScott Title: Manager - Procurement, Purchasing & General Services Date: 10/9/2014 3:43:51 PM Name: ChmelikTom Title: Director - Public Utilities Engineering, Public Utilities Engineering Date: 10/10/2014 5:23:13 PM Name: PajerCraig Title: Project Manager, Principal, Public Utilities Engineering Date: 10/13/2014 4:03:07 PM Name: JohnssenBeth Title: Director - Wastewater, Wastewater Date: 10/13/2014 4:28:48 PM Name: TeachScott Title: Deputy County Attorney, County Attorney Date: 10/15/2014 11:46:32 AM Name: YilmazGeorge Title: Administrator - Public Utilities, Public Utilities Division Date: 10/16/2014 2:52:46 PM Name: KlatzkowJeff Title: County Attorney, Date: 10/16/2014 4:1 3:19 PM Name: UsherSusan Title: Management/Budget Analyst, Senior, Office of Management & Budget Date: 10/20/2014 10:19:29 AM Packet Page -561- 10/28/2014 11. E. Name: OchsLeo Title: County Manager, County Managers Office Date: 10/20/2014 12:08:00 PM Packet Page -562- 10/28/2014 11. E. ' O � vi `5xoO 0 0000 0 p O O o C: 6A � 6�9 69 69 69 6N9 � 69 in,�oo 0 0000 0 0 Xi..�: 7 �• O �D lD � M � N V?1 00 V1 C 00 h N L K 6NA 6A 4A 6A 6A 6NA iH y o � d Z y o � — m- o t a 0 �' =N 69 6A K fii 69 fA 69 � K C C d d O L C � Z .. O .a.6A 69 69 69 69 69 69 � 69 L 9 � Vi W o o Cl O 07 C o FL `m �Oy N � F'" CC W � ° • FE S a Z Fy�y � � 69 6A SMA 6�9 di tai 6A � fA N m 4 U W Z _ �� `�° a m m o an d biq G R O O v l0 �O 9 m J O y N H 3 Fr Us d `' °��n a� G v C C > d W � R Z eC C 9 tll CL C Packet Page -563- N E 0 � M � ,A O �✓ Q E Cr C n JOJ O .2 N a/.�.r LJ ` v V N � cc E m iz °- L N fcQ C v O 0 0 0 0 0 0 N IL w 0 Y > c V Co U :d CU -6 N- _ 0 °o LU -a Cu O U1 a-+ U 00 0 OI 0 } N W U m �..� � L C O YI m< o+ O 0+(L)=U O 0 0 0 0 0 0 0 N 10/28/2014 11. E. Cu O 0 0 0 0 0 0 ri iJ} Packet Page -564- u. c oo Z 0 .Q v c w N J Cu fd W L U Y L w on c w O 0 °o °o 00 0 0 n ri Cu O 0 0 0 0 0 0 ri iJ} Packet Page -564- u. c oo Z 0 .Q v c w N J Cu fd W L U Y L w on c w _ 10/28/2014 11.E. COMAECOM 239 278 7996 tel 4415 Metro Parkway, Ste 404 239 278 0913 fax Fort Myers, FL 33916 www.aecom com September 12, 2014 Mr. Wayne Karlovich, P.E. Project Manager Public Utilities Planning and Project Management RE: Collier County Master Pump Station 109 — Collier County Bid #14 -6330 Letter of Recommendation to Award Contract Dear Wayne: AECOM Technical Services, Inc. ( AECOM) has reviewed the apparent low bidder's (Douglas N. Higgins, Inc.) bid proposal for the Master Pump Station 109 Improvements. This bid was received by Collier County and publicly opened at 3:00 PM on September 8, 2014 at the County's Purchasing Department. The County's Purchasing Department reviewed the bid for completeness, bidder's responsiveness, and mathematical correctness. AECOM's review included a comparison of Douglas N. Higgins, Inc.'s bid proposal with other submitted bids and the Engineer's estimate. The purpose of Master Pump Station 109 Improvements is to replace the original pumps with new equipment. The project consists of replacing three existing submersible pumps with three new pumps, new backup diesel pump, new piping, new electrical building with VFD's and PLC, new backup diesel generator with fuel tank, and site work including a new driveway and drainage modifications. Three bids were received by Collier County. The bids and the Engineer's Opinion of Probable Construction Cost are summarized below: Bidder Total Bid Douglas N. Higgins, Inc. $1,596,937.00 Quality Enterprises USA, Inc. $1,597,053.10 Mitchell & Stark Construction Comr)anv. Inc. 1 $1,799,000.00 Engineer's Estimate 1 $1,773,280.06* ..upamea aiaizui4 Based upon the information provided to the County with the bid, and evaluation of the bids, AECOM recommends the award of the contract to Douglas N. Higgins, Inc. If you have any questions concerning this letter of recommendation, please do not hesitate to contact me directly at 239 -278 -7996. Sincerely, Dawn ':,t kiela, P. E. Project Manager Packet Page -565-