Agenda 09/09/2014 Item #16K3 9/9/2014 16.K.3.
EXECUTIVE SUMMARY,
Recommendation to approve filing a Second Appeal from the Federal Emergency Management Agency's
(FEMA) First Appeal level decision concerning the Hurricane Wilma (FEMA-1609-DR-FL) PW-2700 fund
deobligation in the amount of$11,172,272; the expenditure of additional funds for legal and engineering
expenses;and approve all necessary budget amendments.
OBJECTIVE: To obtain Board authorization to file a Second Appeal from FEMA's First Appeal level decision
that partially reinstated $1,853,755.68 of the $11,172,272.00 in deobligated funds; to expend additional legal and
engineering resources necessary to file the Second Appeal;and approve all necessary budget amendments.
CONSIDERATIONS: On August 1, 2014, Collier County received notice from the Florida Department of
Emergency Management ("FDEM")that the County's First Appeal to the $11,172,272 deobligation of Hurricane
Wilma-PW 2700 was approved in part and denied in part.See FEMA's August 1, 2012, Correspondence. FEMA
reinstated$1,853,755.68 in expenses for soft costs such as dune repairs, engineering and surveys as outlined in the
original Version 0 of PW 2700. However, FEMA failed to address the County's argument concerning the
application of additional sand quantities needed following the sand loss after Hurricanes Katrina and Wilma and
denied reinstatement for that portion of the deobligated funds. In addition, FEMA failed to include all of the
environmental monitoring costs required as part of the beach restoration project.
Outside counsel,Ernest Abbott with the law firm Baker Donelson,Bearman, Caldewll &Berkowitz,P.C.,believes
that there is a reasonable chance of receiving a significantly increased reimbursement of the remaining deobligated
funds and recommends filing the Second Appeal. See Mr.Abbott's Attached August 26,2014,Memorandum. It is
also Mr.Abbott's opinion that because the reinstatement of the $1,853,755.68 in deobligated funds was to correct a
FEMA error, those funds should not be in jeopardy by pursuing a Second Appeal. The legal costs to pursue the
$9.2 million by filing a Second Appeal is estimated to cost less than$50,000. The County must file its appeal with
FDEM no later than September 30,2014.
At Mr.Abbott's suggestion,the Department of Growth Management is also requesting authorization to allow a peer
' review be conducted on the original CP&E technical sand analysis with the objective of strengthening and
justifying the technical discussion. The estimated additional engineering costs are believed to be approximately
$36,000. County staff will work with the County Attorney's Office, outside legal counsel and the county's
consultants to integrate this additional analysis into a comprehensive appeal document.
FISCAL IMPACT: The Board approved initial funding in the amount of$100,000 for this matter on September
11, 2012. (Agenda Item 11H). Approximately $26,000 of the original $100,000 remains uncommitted. Staff is
anticipating approximately an additional $50,000 in legal costs and $36,000 in engineering expenses to finalize a
second appeal. The new funding of approximately$60,000 will initially be provided from the General Fund Other
G&A cost center (001-103010). Follow up action will be taken to present a funding request to the Tourist
Development Council recommending that the subject appeal costs be funded from TDC Beach Renourishment
Fund (195) consistent with previous appeal costs. The Board will subsequently be asked to approve shifting
funding to TDC Fund(195).
GROWTH MANAGEMENT IMPACT: There are no Growth Management Impacts from this action.
LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for
Board approval.—JAK
RECOMMENDATION: That the Board of County Commissioners approve filing a Second Appeal from the
Federal Emergency Management Agency's (FEMA) First Appeal level decision concerning the Hurricane Wilma
(FEMA-1609-DR-FL) PW-2700 fund deobligation in the amount of $11,172,272; authorize the additional
expenditure of up to $86,000 in legal and engineering expenses; and approve all necessary administrative/fmancial
activities and budget amendments.
Prepared by:Jeffrey A.Klatzkow,County Attorney
Attachments:(1)FEMA's August 1,2012 First Appeal Letter,and(2)Ernest Abbott Memorandum
Packet Page-3135-
9/9/2014 16.K.3.
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.16.K.16.K.3.
Item Summary: Recommendation to approve filing a Second Appeal from the Federal
Emergency Management Agency's (FEMA) First Appeal level decision concerning the Hurricane
Wilma (FEMA-1609-DR-FL) PW-2700 fund deobligation in the amount of$11,172,272;the
expenditure of additional funds for legal and engineering expenses; and approve all necessary
budget amendments.
Meeting Date: 9/9/2014
Prepared By
Name: CrotteauKathynell
Title: Legal Secretary,CAO Office Administration
8/28/2014 3:29:54 PM
Approved By
Name: TeachScott
Title: Deputy County Attorney, County Attorney
Date: 8/28/2014 4:01:17 PM
Name:MarcellaJeanne
Title: Executive Secretary, Transportation Planning
Date: 8/28/2014 4:37:51 PM
Name: FinnEd
Title:Management/Budget Analyst, Senior,Transportation Engineering&Construction Management
Date: 8/29/2014 10:26:36 AM
Name:KlatzkowJeff
Title: County Attorney,
Date: 8/29/2014 10:51:43 AM
Name: IsacksonMark
Title: Director-Corp Financial and Mngmt Svs,Office of Management&Budget
Date: 9/2/2014 8:57:50 AM
Name: OchsLeo
Packet Page-3136-
9/9/2014 16.K.3.
Title: County Manager, County Managers Office ,^
Date: 9/2/2014 9:17:22 AM
Packet Page-3137-
U.S.Jet;art:nieac 9/9/2014 16.K.3.
Region PI
3003 ChambleeThckcr R()ad
Atlanta,Ga 30341
,ze try4 1
.
;: ) FEMA
August 1,2014
Mr. Bryan Koon, Director
Florida Division of Emergency Management
2555 Shumard Oak Boulevard
Tallahassee, Florida 32399-2100
Attention: Steven Hyatt
Reference: FEMA-1609-DR-FL
Collier County
PA ID 021-99021-00
First Appeal, Project Worksheet 2700
Dear Mr. Koon:
This is in response to Collier County's (Subgrantee) first appeal of Project Worksheet(PW)
2700. The Subgrantee has appealed the Federal Emergency Management Agency's (FEMA)
disallowance of costs associated with renourishing sand on public beaches. The amount in
dispute is $11,095,283.52.
Background
High winds and strong wave action during FEMA-1609-DR-FL(Wilma) in October 2005 caused
erosion to nearly six miles of sand from Naples Beach. As a result of this damage, FEMA
obligated PW 2700 version 0 to renourish 58,641 cubic yards (CY) of disaster-related sand lost
on the county-maintained beach. The PW also included costs associated with dune repair,
mobilization, demobilization, engineering and surveys. The estimate for PW 2700 version 0 was
$3,381,940.54.
FEMA subsequently processed PW 2700 versions 1 and 2 which did not modify the scope of
work or related estimates, but revised the funding to account for the cost share increase granted
for the disaster declaration. At the Grantee's and Subgrantee's request, FEMA later obligated
PW 2700, version 3, on August,27, 2010,nearly five years after FEMA-1609-DR-FL (Wilma)
was declared. This version captured a pro-rated amount of the total sand renourishment
quantities that the Subgrantee attributes to FEMA-1609-DR-FL (Wilma). This increased the PW
funding from $3,381,940.54 to $12,868,465.94. In addition to the FEMA-1609-DR-FL (Wilma)
PW, the Grantee submitted final inspection PWs for FEMA-1393-DR-FL (Gabrielle) and
FEMA-1602-DR-FL (Katrina)which likewise requested costs at the pro-rated amount of the
1
wwwfema.gov
Packet Page-3138-
9/9/2014 16.K.3.
total renourishment project. FEMA denied the final inspection amount for FEMA-1393-DR-FL
(Gabrielle) and the Subgrantee appealed this denial.
Due to permit requirements causing delays in the FEMA-1393-DR-FL (Gabrielle)
renourishment, the Subgrantee performed a single beach renourishment project incorporating the
PWs from FEMA-1393-DR-FL (Gabrielle),FEMA-1602-DR-FL (Katrina) and FEMA-1609-
DR-FL (Wilma). Then, in draft final inspection reports, the Grantee pro-rated the costs across all
three disasters. As stated above, when the costs were presented to FEMA for reimbursement, the
cost overruns due to this pro-rated costs claimed for FEMA-1393-DR-FL (Gabrielle) were
denied. The Subgrantee appealed this decision and FEMA denied both the first and second
appeals.
As the re-nourishment was completed through a combination of PWs across all three disasters,
the second appeal also addressed all PWs associated with the renourishment project,to include
PW 2700 for FEMA-1609-DR-FL (Wilma). The second appeal decision stated that"Given that
the mainland and Marco Island renourishment projects included both eligible and ineligible
work, and the fact that this response only affects the PWs under FEMA-1393-DR-FL, Regional
PA staff should reexamine the costs funded by PWs under FEMA-1602-DR-FL and FEMA-
1609-DR-FL to deobligated duplicative environmental and turtle monitoring costs and to ensure
FEMA reimburses only eligible sand replacement costs."
In accordance with the second appeal decision's guidance, the Regional PA staff reviewed PW
2700, and in Version 61 disallowed $11,095,283.52 in costs, reducing the final cost to
$1,773,192.42 in June 2012. This deobligation was the result of adjusting the scope of work
back to the original 58,641 cubic yards (CY) of sand that was calculated in PW 2700 version 0
based upon pre- and post-storm surveys of Naples Beach. These surveys were conducted by the
Subgrantee's engineering firm, Coastal Planning & Engineering, Inc. (CPE). This deobligation
is the subject of this appeal.
FEMA's rationale for determining that the original sand volumes as captured in the original PW
versions were the eligible amounts of the disaster loss to be funded under the PW, and not the
pro-rated amounts presented by the Grantee in the final inspections, was explained in the second
appeal as follows:
There is too much uncertainty about typical erosion before, between and after the events
(Gabrielle, Katrina, and Wilma) for reliable use of this information to determine disaster
damage. The sand volumes calculated for the eligible scopes of work are based on
survey data that was available when the PWs were prepared and represent the most
reliable pre- and post-storm profile data. The Applicant has not demonstrated that a
survey of losses (from its consultant, Coastal Planning and Engineering (CPE)) over a
nearly six year period is more accurate than the (unit cost) estimates prepared for the
PWs.
' FEMA prepared PW 2700 versions 4 and 5 to capture administrative changes that did not modify the approved
scope of work or cost estimate.
2
Packet Page-3139-
9/9/2014 16.K.3.
Discussion
The Grantee's first appeal letter presents four separate issues; each will be discussed and
addressed separately.
Issue 1 —FEMA has Not Correctly Determined the Amount of Eligible Replacement Sand
In its appeal, the Subgrantee maintains that its consultant's calculations of sand loss already have
taken the placement of yearly maintenance sand into account, and that FEMA has erred in not
recognizing this fact. The Subgrantee maintains that the CPE engineering report presents
evidence that hidden damages were present on the beaches that were not discovered until the pre-
nourishment survey was done for the 2006 nourishment.
As discussed in the above-mentioned second appeal, sand volume losses are to be based on pre-
and post-storm surveys, as these surveys best represent the storm-related sand loss. FEMA
recalculated the original sand volume loss to Naples Beach using the recommended unit cost
method identified in the second appeal. The 58,641 CY loss, as identified in the approved PW
scope of work for Naples Beach,was multiplied by $30.2381 per CY which represents the actual
contract costs plus a unit cost for monitoring, resulting in the revised PW cost of$1,773,192.41.
The Subgrantee's argument that FEMA did not take into account maintenance sand does not
apply to this method of calculating the FEMA-eligible scope of work. FEMA's methods for
calculating eligible sand loss resulting from a disaster declaration, as confirmed by the FEMA-
1393-DR-FL (Gabrielle) second appeal response, is to calculate sand loss based upon the pre-
and post-storm profiles. The maintenance sand placed on the beach before the pre-storm profile
or after the post-storm profile has no bearing on the calculations of eligible sand loss as a result
of the damage event.
The engineering report provided by CPE dated October 15,2012 and revised on January 23,
2013, states that the increase in its sand loss calculations is due to hidden damages, as the post
storm survey measured the beach changes before full equilibration occurred. The claimed sand
loss measured by CPE in the pre-and post-disaster surveys for Wilma was 58, 641 CY. The sand
loss proposed in this report for FEMA-1609-DR-FL (Wilma) was 304,598 CY. However, the
sand loss claimed for FEMA-1393-DR-FL (Gabrielle) and FEMA-1602-DR-FL (Katrina) appear
to remain the same in the report produced after the second appeal response.
In addition, as stated in the second appeal decision for FEMA-1393-DR-FL (Gabrielle), "These
projects renourished the beaches to their design for the first time since original nourishment in
1996. While they did replace the eligible sand losses from the three disasters, they also replaced
sand eroded from the beaches before,between and after the declared events, as well as sand
placed on areas outside of the eligible projects." Therefore,the most reliable source of disaster
related damages are the pre- and post-disaster surveys.
Issue 2—FEMA has Not Afforded Proper Deference to the Subgrantee's Engineering Report
In its appeal,the Subgrantee states its consultant's beach engineering report satisfied, in part, the
environmental monitoring requirements imposed by the Florida Department of Environmental
3
Packet Page-3140-
9/9/2014 16.K.3.
Protection(FDEP). The report then became a part of the State's permit,thus entitled to a higher
degree of deference. FEMA,the Subgrantee claims, should be required to prove why the report
is wrong, rather than tasking the Subgrantee to prove why the report is true.
FEMA maintains that there is no conclusive evidence in the engineering report that the sand loss
is storm-related, and that the report raises no substantive new issues than what was addressed and
referred to in the previously discussed second appeal decision under FEMA-1393-DR-FL
(Gabrielle). A Subgrantee's engineering report used for the purposes of documenting
environmental monitoring compliance and obtaining permits, does not establish FEMA
eligibility, but rather documents the Subgrantees plans for re-nourishment and monitoring. In
addition,the documentation used to prepare the original PWs and establish the approved scope
of work, which is sand loss demonstrated through pre- and post-storm beach profiles, was also
provided by the Subgrantee's Engineering Reports.
Also, the Subgrantee's pre-nourishment survey of June 2006 extended out to the 400 foot
distance mark, while the November 2005 and all previous surveys extended out to the 800 foot
distance mark. This inconsistency in surveying has not been explained.
Issue 3 —FEMA is Improperly Holding the Subgrantee to the Initial Approved Scope Estimates
In its appeal,the Subgrantee presents information as to why it believes FEMA returned to the
original version 0 project costs and scope. One issue raised was that the PW stated that the
increased amount of sand would be ineligible because it represented an ineligible scope of work
change. When FEMA obligates a PW, it contains an approved Scope of Work for which the
Subgrantee can seek reimbursement of actual costs. Importantly,the approved scope of work is
not an estimate, but rather the cost to complete the approved scope of work is estimated. If, as
work progresses, a change in scope of work is needed,the Subgrantee must demonstrate that the
change is due to storm-related damages in order to make the work eligible for FEMA funding.
As such, changes in scope of work should be requested and evaluated by FEMA prior to the
work being done, so that eligibility can be determined and proper environmental compliance be
completed and documented. For this appeal, however,the issue is not necessarily the timing of
the request, but the fact that the work has not been demonstrated to be storm-related.
Inclusion of this ineligible sand in the original scope of work constitutes an ineligible scope of
work change.
Issue 4—Section 705(c) of the Stafford Act Precludes FEMA's Deobligations
Section 705(c) of the Stafford Act provides that a"State or local government shall not be liable
for reimbursement or any other penalty for any payment made under this Act if(1)the payment
was authorized by an approved agreement specifying the costs; (2)the costs were reasonable;
and (3) the purpose of the grant was accomplished." In its appeal, the Subgrantee asserts that the
Subgrantee met these three criteria.
FEMA obligated PW 2700 Version 3 for FEMA-1609-DR-FL (Wilma) on August 27, 2010, to
increase the PW funding from $3,381,940.54 to $12,868,475.94 as a result of the Subgrantee's
4
Packet Page-3141-
9/9/2014 16.K3.
method of pro-rating the project costs across the three disasters and its claim that there was an
increased sand loss due to hidden damages. The second appeal for FEMA-1393-DR-FL
(Gabrielle) was dated May 14, 2012,which required FEMA to revisit PW 2700 for FEMA-1609-
DR-FL (Wilma) and fund only the eligible sand loss resulting from the declared event as
documented by pre- and post-storm surveys. As a result of that review,FEMA completed the
deobligation action for FEMA-1609-DR-FL (Wilma) in PW 2700, in version 6 on June 21, 2012.
The increase in work is not eligible, which makes the costs for the ineligible work inherently not
reasonable. Section 705(c) of the Stafford Act is thus inapplicable.
Dune Repair, Mobilization and Demoblilization, Engineering and Survey Costs
FEMA has reviewed all the documentation provided with the appeal and our PW files. Based
upon the information,FEMA has determined that the pre- and post-storm surveys conducted by
the Subgrantee's engineering firm, CPE,best represent the storm-related sand losses eligible
under PW 2700. In reviewing PW 2700 version 6, FEMA reduced the eligible costs to include
the 58,641 CY in sand loss resulting from FEMA-1609-DR-FL (Wilma) and used the unit cost
identified in FEMA's second appeal response for FEMA-1393-DR-FL (Gabrielle), which is
$30.2381. The unit cost includes the contract costs for sand, as well as a unit cost to cover the
force account monitoring costs. The method for deriving this cost is described in the second
appeal for FEMA-1393-DR-FL (Gabrielle). The PW 2700 version 6 also disallowed the costs
for dune repair, mobilization and demoblilization, engineering and survey costs which had been
allowed in version 0 of PW 2700. As these costs were eligible, FEMA will reinstate these costs
as provided in version 0, as depicted below:
PW 2700 Collier County FEMA-1609-DR-FL
Item Measure Unit Unit Cost Total
Sand replacement CY 58641 $30.23812* $ 1,773,192.42
Dune repair LF 21850 $50 $ 1,092,500.00
Mob and de-mob LS 1 $506,273 $ 506,273.00
Engineering LS 1 $171,982.68 $ 171,982.68
Survey LS 1 $83,000 $ 83,000.00
Total $ 3,626,948.10
Conclusion
Based on all available information,the appeal is partially approved. FEMA will prepare a
version to PW 2700 to reinstate $1,853,755.68 in costs for dune restoration, engineering,
mobilization and demobilization and surveys at the original obligated amount.
The Subgrantee may appeal this determination to the Assistant Administrator,Recovery
Directorate, at FEMA Headquarters pursuant to 44 CFR § 206.206, Appeals. If the Subgrantee
elects to file such a second appeal, the appeal must: (1) contain documented justification
2 This unit cost was taken from FEMA's second appeal response for FEMA-1393-DR-FL(Gabrielle),which
included the force account monitoring costs into the unit cost. The number of units remains the same as PW 2700
version 0.
5
Packet Page-3142-
9/9/2014 16.K.3.
supporting the Subgrantee's position, (2) specify the monetary figure in dispute, and (3) cite the
provisions in federal law,regulation, or policy with which the Subgrantee believes the initial
action was inconsistent. A second appeal must be submitted to the Florida Division of
Emergency Management(FLDEM) by the Subgrantee within 60 days of the Subgrantee's receipt
of this letter. FLDEM transmittal of that appeal, with recommendation, is required to be
submitted to my office within 60 days of your receipt of the Subgrantee's letter. My office will
transmit the second appeal to FEMA headquarters.
If you have questions or need additional information,please contact Mr. Jesse F. Munoz, CEM,
Director, Recovery Division, at(770) 220-5300.
ely, e /
for
lur• A. tiro
Andrew V elasquez III
Acting Regional Administrator
6
Packet Page-3143-
9/9/2014 16.K.3.
BAI ER.,DONELSON !920 MASSACHUSETTS AVE,N.W.
SUITE 900
BEARMAN,CALDWELL&,BERKOWITZ, PC WASHINGTON,D.C.20001
PHONE: 202.508.3425
FAX: 202.222.2225
' 9@@LTTOBAKERDQN.ftSON.COM
www.bokerdonebon.com
ATTORNEY-CLIENT PRIVILEGED
MEMORANDUM
TO: Jeffrey A.Klatzkow
County Attorney
Collier County,Florida
FROM: Ernest B.Abbott
Of Counsel
Baker Donelson
DATE: August 26,2014
RE: Recommendation that Collier County File a Second Appeal of FEMA's
Disallowance of Reimbursement of Beach Restoration Costs
This memorandum summarizes my recommendation that Collier County file a"Second Appeal"
from FEMA's First Appeal Decision of August 1,2014 denying reimbursement of$9.2 million
of the cost incurred by Collier County to restore its engineered beaches after Hurricanes Katrina
and Wilma. The First Appeal did restore funding of$1.8 million of eligible soft costs(such as
engineering,survey,and dune repair). Note that,pursuant to FEMA's regulation governing
appeals submission,if the County accepts my recommendation to file a Second Appeal,this
complete package will need to be submitted to the Florida Department of Emergency
Management no later than September 30.
The primary rationale FEMA gave for disallowing$9.2 million was that FEMA concluded that
only 136,095 cubic yards of sand had been lost from the County's beaches after Hurricanes
Katrina and Wilma. This was the difference between a sand survey performed in 2004(the most
recent pre-Katina survey)and a sand survey performed in November 2005,and FEMA
concluded that"the most reliable source of disaster related damages are the pre-and post-disaster
surveys."
Collier County presented evidence in the First Appeal,and will submit additional engineering
evidence on Second Appeal,that the immediate post-Wilma survey had been performed before
the beach had recompressed after the disaster,and there are a number of surveys performed less
than 6 months after Wilma which measured 412,690 cubic yards of sand loss after Hurricanes
Katrina and Wilma. This additional measured sand loss accounts for$8.2 million of the disputed
Packet Page -3144-
9/9/2014 16.K.3.
MEMORANDUM
Collier County
August 26,2014
Page 2
costs. The remainder of the amount at issue is accounted by FEMA's failure to include all of the
environmental monitoring costs required as part of the beach restoration project.
We believe that,on Second Appeal,Collier County has a reasonable chance of receiving
significantly increased reimbursement.
• FEMA Region IV appeared not to have carefully examined all of the engineering
evidence provided by Collier County-and even invited the County to provide further
explanation of the difference sand surveys performed. Our experience on Second Appeal
is that FEMA reviews documentation submitted with far greater care.
• We understand that the County plans to provide FEMA with additional engineering
support,from engineers who had not been involved in the Project, demonstrating that the
sand loss suffered by the County was far larger than the amount approved by FEMA.
• The position taken by FEMA on the First Appeal provides no explanation as to how the
survey results in November 2005 were so dramatically different than those four months
later. We will demonstrate that there were no events between the two surveys that could
have accounted for the difference.
• The First Appeal decision's reinstatement of$1.8 million was explained as correction of a
FEMA error,since the$1.8 million in costs were clearly eligible under FEMA policies.
filing of an appeal should not jeopardize this recovery.
• FEMA has just implemented a new Public Assistance Appeals Branch within its
Headquarters office.This Branch is specifically tasked with review of FEMA's First
Appeal decisions and our experience has shown that they take this responsibility very
seriously. We have a good working relationship with the Branch Chief and would request
an in person discussion once the Second Appeal is filed.
We believe that the legal costs of preparing and filing a Second Appeal will cost less than
$50,000. The amount at issue is$9.2 million. Because the potential recovery on appeal dwarfs
the cost of pursuing an appeal,I would recommend that the County authorize the preparation and
filing of a Second Appeal in this matter.
Please do not hesitate to call if you have any questions.
Cc: Scott R.Teach,Deputy County Attorney
Gary McAlpin,Director,Coastal Zone Management
Packet Page-3145-