Agenda 09/09/2014 Item #16D 7 9/9/201416.D.7.
EXECUTIVE SUMMARY
Recommendation to approve execution of the 2013/2014 Federal Highway Administration Flexible Funds
grant award in the amount of$1,186,348 for the construction of improvements to the Collier Area Transit
Administration, Operations & Maintenance facility located at 8300 Radio Road and authorize a budget
amendment.
OBJECTIVE: To obtain grant funds for the construction of improvements to the Collier Area Transit
Administration,Operations&Maintenance facility located at 8300 Radio Road.
CONSIDERATION: On January 28, 2014 the Board approved Agenda Item 16D4 authorizing the
submittal of a grant application for the 2013/2014 Federal Highway Administration Flexible grant funds
in the amount of$1,186,348 for transit facility improvements located at 8300 Radio Road. The grant
requires a 20%match. Collier County received authorization from Florida Department of Transportation
(FDOT) on April 17, 2014 to use toll revenue credits in the amount of$296,587 as a soft match for the
grant.
The total estimated construction costs for phase 2 improvements to the CAT Administration, Operations
&Maintenance facility are$1,719,319. Phase 2 improvements includes,but is not limited to the addition
of a bus wash facility,passenger canopy and civil site work. Several grants are being utilized to fund this
project; the total amount of funding currently anticipated from various FTA grants (inclusive of this
application)is $1,869,240.00. Increased maintenance costs for the improvements are being considered as
part of the design process and will be provided prior to bid award.
On August 11, 2014,county staff received notification of award from the Federal Transit Administration
(FTA). Execution of the grant is processed through the FTA Transportation Electronic Award
Management System.
FISCAL IMPACT: A budget amendment is required in FY14 in the amount of$1,186,348 to recognize
the grant revenue funds to Collier Area Transit(CAT) Grant Fund(424), Project 33374. Collier County
has received approval from the Florida Department of Transportation for the use of toll revenue credits in
the amount of$296,587 as soft match in FY 14 Capital Grant Funds.
LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority
vote for Board approval.—SRT
GROWTH MANAGEMENT IMPACT: Transit capital and operations supports goals and objectives of
the Transportation Element of the Growth Management Plan.
RECOMMENDATION: That the Board of County Commissioners (1)approves execution of the grant
award for the 2013/2014 Federal Highway Administration Flexible Fund grant award in the amount of
$1,186,348 through the FTA Transportation Electronic Award Management System and(2)authorizes the
necessary budget amendment.
Prepared by:Trinity Scott,Public Transit Manager,Alternative Transportation Modes
Packet Page-1793-
9/9/2014 16.D.7.
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.16.D.16.D.7.
Item Summary: Recommendation to approve execution of the 2013/2014 Federal
Highway Administration Flexible Funds grant award in the amount of$1,186,348 for the
construction of improvements to the Collier Area Transit Administration, Operations &
Maintenance facility located at 8300 Radio Road and authorize a budget amendment.
Meeting Date: 9/9/2014
Prepared By
Name: Scott Trinity
Title: Manager-Public Transit,Alternative Transportation Modes
7/29/2014 9:56:33 AM
Submitted by
Title: Manager-Public Transit, Alternative Transportation Modes
Name: Scott Trinity
7/29/2014 9:56:34 AM
Approved By
Name: Scott Trinity
Title:Manager-Public Transit,Alternative Transportation Modes
Date: 8/13/2014 3:07:13 PM
Name: SotoCaroline
Title: Management/Budget Analyst,GMD Construction&Maintenance Admin
Date: 8/14/2014 3:31:48 PM
Name: TownsendAmanda
Title: Director-Operations Support,Public Services Division
Date: 8/22/2014 2:33:51 PM
Name: AlonsoHailey
Title: Operations Analyst,Public Services Division
Date: 8/25/2014 11:41:21 AM
Packet Page-1794-
9/9/2014 16.D.7.
Name: TeachScott
Title: Deputy County Attorney, County Attorney
Date: 8/25/2014 2:11:08 PM
Name: CarnellSteve
Title: Administrator-Public Services,Public Services Division
Date: 8/25/2014 5:09:22 PM
Name: OberrathKaren
Title:Accountant, Senior,Grants Management Office
Date: 8/26/2014 2:27:42 PM
Name: KlatzkowJeff
Title: County Attorney,
Date: 8/26/2014 3:45:46 PM
Name: StanleyTherese
Title: Manager-Grants Compliance, Grants Management Office
Date: 8/29/2014 12:16:41 PM
Name: KlatzkowJeff
Title: County Attorney, n
Date: 8/29/2014 3:45:22 PM
Name: OchsLeo
Title: County Manager,County Managers Office
Date: 8/30/2014 1:52:43 PM
Packet Page-1795-
View Print
9/9/2014 16.D.7.
DOT 0 FTA
U.S. Department of Transportation Federal Transit Administration
Application
Recipient ID: 1032
Recipient Name: COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
Project ID: :FL-95-X076-00
Budget Number: 1 - Budget Approved
Project Information: Collier Area Transit Capital Assistance J
Part 1: Recipient Information
Project Number: FL-95-X076-00
Recipient ID: t 1032
Recipient Name: COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
Address: :3301 TAMIAMI TRAIL EAST , NAPLES, FL 34112 4961
phone: (239) 213-5812(239) 213-5812*
Facsimile: (239) 659-5787
Union Information
Recipient ID: 1032
}
Union Name: i TRANSPORT WORKERS UNION, AFL-CIO
Address 1: 122 Dixie Lane
Address 2:
City: j Cocoa Beach, FL 32931
Contact Name: Kevin Smith
Telephone: (866) 795-4255(866) 795-4255V
Facsimile:
E-mail: jptwu500 @aol.com
Website:
Recipient ID: 4 1032
on Name: i.TRANSPORT WORKERS UNION, AFL-CIO
f ^�
t
dress 1: 122 Dixie Lane
`Address 2:
1
Packet Page-1796-
https://ftateamweb.fta.dot.gov/...cations/ViewPrint/ViewPrintRes.asp?GUID=PRODUCTION_ABOFB4A17A894FCE81FE07616E762BEC[8/29/2014 11:38:06 AM]
View Print
'City: Cocoa Beach, FL 32931 1 9/9/2014 16.D.7.
w Contact Name: :Kevin Smith
;Telephone:
N(866) 795-4255(866) 795-4255
• Facsimile: `(321) 784-8847V
E-mail: Kevin.Smith @SCLS-LLC.com — _
Website:
Part 2: Project Information
Project Type: Grant Gross Project
, Project Number: :FL-95-X076-00 Cost: $1,186,348
Project Description: Collier Area Transit Capital
Adjustment Amt: ` $0
..Assistance ,ITotal Eligible Cost: $1,186,3481
j Recipient Type: County Agency k Y Total FTA Amt: i $1,186,348
FTA Project Mgr: Chris White, ` Total State Amt: $0
404-865-5619404-865-561 9
m Total Local Amt: $0
Recipient Contact: Trinity Scott, 'Other Federal
239-252-5832239-252-5832 $0
s `Amt:
•
New/Amendment: New Special Cond Amt: : $0
Amend Reason: Initial Application
b ,
Special Condition: None Specified
Fed Dom Asst. #: 20507 S.C. Tgt. Date: None Specified
Sec. of Statute: 5307-3 S.C. Eff. Date: None Specified
State Appl. ID: None Specified Est. Oblig Date: None Specified
Start/End Date: Apr. 01, 2014- Dec. 31, 2015 i t Pre-Award "Yes
Recvd. By State: Jul. 11, 2014 Authority?:
EO 12372 Rev: , Applicable Fed. Debt No
— — ;;Authority?: i
' Review Date: None Specified ,
-- - —' Final Budget?: No
Planning Grant?: NO _M —...
Program Date
(STIP/UPWP/FTA Jan. 01, 2014
Prm Plan) :
Program Page: . 180
Application Type: Electronic
Supp. Agreement? No ,�,,..e...�,..,....�...�-_,,.�.._LL-.�..
Debt. Delinq. Details:
Urbanized Areas
_
UZA ID UZA Name ��..�.,�,.-,.
. 123610 BONITA SPRINGS, FL
Packet Page-1797-
https://ftateamweb.fta.dot.gov/...cations/ViewPrint/ViewPrintRes.asp?GUID=PRODUCTION_ABOFB4A 17A894FCE8I FE07616E762BEC[8/29/2014 11:38:06 AM]
view Print
9/9/2014 16.D.7.
Congressional Districts
/■te ID District Code District Official
12 Gus M Bilirakis
Project Details
These flex funds will be utilized for construction of a bus wash facility, canopy and civil site work required. This project is a
rehabilitation/renovation project for the Collier Area Transit Operations Administration and Maintenance Facility, an existing facility.
This facility was purchased by Collier County using local funds. The funds in this grant application will be used to complete this
phase of the project. Collier County will be using Toll Revenue Credits for the 20% match. A copy of the request to FDOT for use
of Toll Revenue Credits has been provided to FTA. The FDOT Toll Revenue Credit is for $296,587. Also, the final signed CE
concurrence letter from FTA has been attached for your use.
We anticipate awarding the bid by June 30, 2014 and finalizing construction by December 31, 2015. The following grants have
been committed to phase one of this project:
Preliminary Design & Engineering
FTA Section Fiscal Year Grant# ALI Description Amount
5309 Z003 FL 030264 11.31.01 Preliminary Design & Engineering $737,759
Phase One Construction
FTA Section Fiscal Year Grant# ALI Description Amount
5309 2009 FLO40117 11.44.03 Restrooms $109,375
5309 2008 FL040047 11.44.03 Sawtooth bus Bay, ADA restrooms &fueling island station $63,021.83
5309 2007 FL040033 11.44.03 Fuel Tank $238,000
5309 2006 FL040034 11.44.03 Fuel Tank $226,710
^� 2012 FL90X784 11.44.03 Oil Water Separator $130,000
2012 FL90X784 11.34.01 Bus Terminal $25,435
5307 2011 FL90X766 11.34.07 Lighting $30,472
5307 2011 FL90X766 11.34.07 Lighting $25,046
5307 2009 FL90X699 11.44.03 Saw tooth Bus Bay, ADA Restrooms $392,137
5339 2013 FL340004 11.44.03 Rehab/Renovate—Admin/Maint Facility $353,562
FHWA Flex 2013 FL95X069 11.44.03 Rehab/Renovate—Admin/Maint Facility $1,186,055
5307 2013 FL90X816 11.44.03 Rehab/Renovate—Admin/Maint Facility $607,810
TOTAL REVENUE $3,362,577.83
Engineer's Estimate $3,188,496.00
Construction Management & Inspection Services
FTA Section Fiscal Year Grant # ALI Description Amount
5309 2009 FL040117 11.71.04 Construction Management $120,000
Earmarks
No information found.
Security
No— We will not expend at least 1% of the 5307 funds in this grant application for security purposes.
ther, please describe below.
Packet Page -1798-
ittps://ftateamweb.fta.dot.gov/...cations/ViewPrint/ViewPrintRes.asp?GUID=PRODUCTION_ABOFB4A17A894FCE81FE07616E762BEC[8/29/2014 11:38:06 AM]
View Print
9/9/2014 16.D.7.
Part 3: Budget
Project Budget
t r Quantity FTA Amount s Tot. Elig. Cosh
SCOPE
114-00 BUS: SUPPORT EQUIP AND 0 $1,186,348.00[ $1,186,348.00
FACILITIES
ACTIVITY
11.44.03 REHAB/RENOVATE- 0 $1,186,348.00 $1,186,348.00
ADMIN/MAINT FACILITY
}
Estimated Total Eligible Cost: $1,186,348.00
Federal Share: $1,186,348.00 k
Local Share: $0.00
OTHER (Scopes and Activities not included in Project Budget Totals)
None
SOURCES OF FEDERAL FINANCIAL ASSISTANCE n
-----Accounting _�,........ _ Previously; Amendment's
UZA ID Classification FPC` Ey. SEC Approved Amount; Total
i 123610 2014.45.95.SX.2 00 2014 95 t $0.00 i $1,186,348 00 r $1,186,348.00
i
Total Previously Approved:[ $0.00
i.
rmx....rvn ...,
Total Amendment Amount:, $1,186,348.00
Total from all Funding Sources: $1,186,348.00
Alternative Fuel Codes
_ ,,
11.14.00 BUS: SUPPORT EQUIP AND FACILITIES Diesel Diesel Fuel
11.44.03 REHAB/RENOVATE - ADMIN/MAINT FACILITY --- Diesel Fuel
Extended Budget Descriptions
114-00 BUS: SUPPORT EQUIP AND FACILITIES 0= $1,186,348.00 $1,186,348.00 .
These flex funds will be utilized for construction of a bus wash facility, canopy and civil site work required. This project is a
rehabilitation/renovation project for the Collier Area Transit Operations Administration and Maintenance Facility, an existing
Packet Page-1799-
ttps://ftateamweb.fta.dot.gov/...cations/ViewPrintJViewPrintRes.asp?GUIID=PRODUCTJON_AB0FB4A 17A894FCE8I FE07616E762BEC[8/29/2014 11:38:06 AM]
View Print
9/9/2014 16.D.7.
facility. This facility was purchased by Collier County using local funds. The funds in this grant application wm VG UOVU
complete this phase of the project. The useful life range of the building improvements are 20 years, the useful life was based on }
industry standards.
44.03 REHAB/RENOVATE- ADMIN/MAINT FACILITY 1 0 $1,186,348.001 $1,186,348.00
These flex funds will be utilized for construction of a bus wash facility, canopy and civil site work required. This project is a
rehabilitation/renovation project for the Collier Area Transit Operations Administration and Maintenance Facility, an existing
facility. This facility was purchased by Collier County using local funds. The funds in this grant application will be used to
complete this phase of the project. The useful life range of the building improvements are 20 years, the useful life was based on
industry standards.
Changes since the Prior Budget
No information found.
Part 4. Milestones
11.44.03 REHAB/RENOVATE- ADMIN/MAINT 0 $1,186,348 $1,186,348
FACILITY
l .Milestone Description Est. Comp. Date
1. RFP/IFB Issued Apr. 01, 2014
The project will be bid following Collier County and Federal Transit
Administration procurement guidelines. The project will be bid following Collier
County and Federal Transit Adminsitration procurement guidelines. The
contract will be awarded to the vendor with the best value. The Bid is
expected to be awarded by July 1, 2014, and cosntruction is expected to be ,
F completed by December 2015.
2.;Contract Award Jul. 01, 2014
The project will be bid following Collier County and Federal Transit
Administration procurement guidelines. The project will be bid following Collier! 4
County and Federal Transit Adminsitration procurement guidelines. The
contract will be awarded to the vendor with the best value. The Bid is
expected to be awarded by July 1, 2014, and cosntruction is expected to be
completed by December 2015.
3. Contract Complete Dec. 31, 2015'
The project will be bid following Collier County and Federal Transit
Administration procurement guidelines. The project will be bid following Collier
County and Federal Transit Adminsitration procurement guidelines. The
contract will be awarded to the vendor with the best value. The Bid is
expected to be awarded by July 1, 2014, and cosntruction is expected to be
completed by December 2015.
pArt 5. Environmental Findings
114403 REHAB/RENOVATE- 0 $1,186,348 $1,186,348
ADMIN/MAINT FACILITY
Packet Page-1800-
https://ftateamweb.fta.dot.gov/...cations/ViewPrint/ViewPrintRes.asp?GUID=PRODUCTION_ABOFB4A17A894FCE81FE07616E762BEC[8/29/2014 11:38:06 AM]
View Print
9/9/2014 16.D.7.
Finding No. 1 - Class II(c)
C08- Maintenance, rehab, reconstruction of facilities
Maintenance, rehabilitation, and reconstruction of facilities that occupy substantially the same geographic footprint and do not
result in a change in functional use, such as: improvements to bridges, tunnels, storage yards, buildings, stations, and
terminals; construction of platform extensions, passing track, and retaining walls; and improvements to tracks and railbeds.
C09- Assembly or construction of facilities
Assembly or construction of facilities that is consistent with existing land use and zoning requirements (including floodplain
regulations) and uses primarily land disturbed for transportation use, such as: buildings and associated structures; bus
transfer stations or intermodal centers; busways and streetcar lines or other transit investments within areas of the right-of-
way occupied by the physical footprint of the existing facility or otherwise maintained or used for transportation operations;
and parking facilities.
C10- Joint development of facilities
Development of facilities for transit and non-transit purposes, located on, above, or adjacent to existing transit facilities, that
are not part of a larger transportation project and do not substantially enlarge such facilities, such as: police facilities, daycare
facilities, public service facilities, amenities, and commercial, retail, and residential development.
Part 6: Fleet Status
Fixed Route
n
Before Change After r
I. ,Active Fleet
A. Peak Requirement 17 - 0` 17
k B. Spares 1 6 i 01 6
f
C. Total (A+B) k__ 23 T 0 I 23
D. Spare Ratio (B/A) 35.29%i 0.00%I 35.29%
II Inactive Fleet # i
A. Other a 0 01 01
B. Pending Disposal I 0 I 0
., . r
.. .... .v ............ �a.nn..rnww.nr... s .r,+x�r..w.nr�v
.C. Total (A+B) p 0- 0 0
III. 'Total (I.0 and II.C) 23 t' 0 23
Part 8: Results of Reviews
The reviewer did not find any errors
Part 9: Agreement
UNITED STATES OF AMERICA
DEPARTMENT OF TRANSPORTATION
FEDERAL TRANSIT ADMINISTRATION
Packet Page-1801-
https://ftateamweb.fta.dot.gov/...cationsNiewPrintNiewPrintRes.asp?GUID=PRODUCTION ABOFB4A17A894FCE81FE07616E762BEC[8/29/2014 11:38:06 AM]
View Print
9/9/2014 16.D.7.
GRANT AGREEMENT
(FTA G-20, October 1, 2013)
9'the date the authorized U.S. Department of Transportation, Federal Transit Administration (FTA) official's electronic signature is
red for this Grant Agreement, FTA has Awarded Federal assistance in support of the Project described below. Upon
Execution of this Grant Agreement by the Grantee named below, the Grantee affirms this FTA Award, and enters into this Grant
Agreement with FTA. The following documents are incorporated by reference and made part of this Grant Agreement:
(1) "Federal Transit Administration Master Agreement," FTA MA(19), October 1, 2013,
http://www.fta.dot.gov/documents/20-Master.pdf
(2)The Certifications and Assurances applicable to the Project that the Grantee has selected and provided to FTA, and
(3)Any Award notification containing special conditions or requirements, if issued.
FTA OR THE FEDERAL GOVERNMENT MAY WITHDRAW ITS OBLIGATION TO PROVIDE FEDERAL ASSISTANCE IF THE
GRANTEE DOES NOT EXECUTE THIS GRANT AGREEMENT WITHIN 90 DAYS FOLLOWING THE DATE OF THIS FTA
AWARD SET FORTH HEREIN.
FTA AWARD
FTA hereby awards a Federal grant as follows:
Project No: FL-95-X076-00
Grantee: COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS
Citation of Statute(s) Authorizing Project:, 49 USC 5307 - Urbanized Area Formula (FHWA xfer FY 2007 fwd)
Estimated Total Eligible Cost (in U.S. Dollars): $1,186,348
Maximum Total FTA Amount Awarded (in U.S. Dollars): $1,186,348
1:aount of This FTA Award (in U.S. Dollars): $1,186,348
.mum Percentage(s) of FTA Participation:
Percentages of Federal participation are based on amounts included in the Approved Project Budget, modified as set forth in the
text following the Project Description.
U.S. Department of Labor Certification of Public Transportation Employee Protective Arrangements:
Original Project Certification Date: 7/31/2014
Project Description:
Collier Area Transit Capital Assistance
The Project Description includes information describing the Project within the Project Application submitted to FTA, and the
Approved Project Budget, modified by any additional statements displayed in this Grant Agreement, and, to the extent FTA
concurs, statements in other documents including Attachments entered into TEAM-Web.
Awarded By:
Yvette Taylor
Regional Administrator
FEDERAL TRANSIT ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
08/08/2014