Agenda 07/08/2014 Item #16C 47/8/2014 16.C.4. EXECUTIVE SUMMARY Recommendation to approve a time extension of 120 days to the final completion of Contract 12- 5931 with D.N. Higgins, Inc., Purchase Order 4500142945, for the Master Pumping Station 312 Rehabilitation project, under Project 72549, and authorize payment of the remaining balance of the contract for services rendered. OBJECTIVE: Approve a time extension of 120 days to the final completion of Purchase Order (PO) 4500142945 under Contract 12 -5931 with D.N. Higgins, Inc., (DNH) for the Master Pumping Station (MPS) 312 Rehabilitation Project, 72549. CONSIDERATIONS: The proposed scope of work for Project 72549, MPS 312 Rehabilitation, is consistent with the 2011 Wastewater CIP Update, Page 2 of 4, line 53, as identified in the 2011 User Fee Rate Study. On February 12, 2013, as Agenda Item I IA, the Board of County Commissioners awarded construction contract 12 -5931 to DNH for the MPS 312 rehabilitation project. The project had a notice to proceed date of March 28, 2013. The station has been in operation and was substantially complete as of March 6, 2014. After substantial completion is achieved, the contractor normally has until final completion to complete punch list items, clean up the site, provide record drawings, operation and maintenance manuals, and to provide release of liens and warranty certificates. Through a zero - dollar change letter, the original final completion date of March 27, 2014, was extended to April 24, 2014. On two occasions during progress meetings that were prior to the final completion date, the Public Utilities Division Project Manager requested the DNH Project Manager to submit a time extension request with supporting backup showing a direct impact to the critical path of the project. DNH did not submit the request until April 28, 2014, four days after the final completion date (April 24, 2014). DNH has requested a 120 -day time extension to the final completion date to accomplish the aforementioned tasks to reach final completion and to be able to receive final payment. Q. Grady Minor, the construction engineering and inspection firm, evaluated the request and provided a letter stating that the request is fair and reasonable. Staff agrees and recommends approval of the time extension. FISCAL IMPACT: Funding is available in the FY2014 Capital Budget approved by the Board on September 19, 2013. The source of funding is Wastewater User Fees Fund (414), Project 72549. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval. —SRT GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. RECOMMENDATION: That the Board of County Commissioners, Ex- officio the Governing Board of the Collier County Water -Sewer District, approve a time extension of 120 days to the final completion of contract 12 -5931, with D.N. Higgins, Inc., Purchase Order 4500142945, for the Master Pumping Station 312 Rehabilitation Project, under Project 72549; and, authorize payment of the remaining balance of the contract for services rendered. Packet Page -1042- 7/8/2014 16.C.4. Prepared By: Peter Schalt, PMP, Senior Project Manager, Planning and Project Management Department Attachments: Attachment 1- Change Order Attachment 2- Change Order Modification Form Attachment 3 -Letter from D.N. Higgins Attachment 4 -Letter from Q. Grady Minor Packet Page -1043- 7/8/2014 16.C.4. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.C.16.C.4. Item Summary: Recommendation to approve a time extension of 120 days to the final completion of Contract 12 -5931 with D.N. Higgins, Inc., Purchase Order 4500142945, for the Master Pumping Station 312 Rehabilitation project, under Project 72549, and authorize payment of the remaining balance of the contract for services rendered. Meeting Date: 7/8/2014 Prepared By Name: SchaltPeter Title: Project Manager, Senior, Public Utilities Engineering 6/12/2014 3:21:37 PM Approved By Name: JohnssenBeth Title: Director - Wastewater, Wastewater Date: 6/13/2014 1:45:58 PM Name: WardKelsey Title: Manager - Procurement, Purchasing & General Services Date: 6/13/2014 3:41:14 PM Name: MarkiewiczJoanne Title: Director - Purchasing /General Services, Purchasing & General Services Date: 6/13/2014 3:47:34 PM Name: JohnsonScott Title: Manager - Procurement, Purchasing & General Services Date: 6/13/2014 3:57:28 PM Name: BrilhartBrenda Title: Procurement Specialist, Purchasing & General Services Date: 6/16/2014 7:51:23 AM Name: Joseph Bellone Title: Director - Operations Support, Utilities Finance Operations Packet Page -1044- Date: 6/16/2014 8:54:31 AM 7/8/2014 16.C.4. Name: HapkeMargie Title: Recycling Coordinator, Solid & Hazardous Waste Management Date: 6/16/2014 9:48:15 AM Name: ChmelikTom Title: Director - Public Utilities Engineering, Public Utilities Engineering Date: 6/18/2014 5:17:05 PM Name: PajerCraig Title: Project Manager, Principal, Public Utilities Engineering Date: 6/23/2014 1:06:52 PM Name: TeachScott Title: Deputy County Attorney, County Attorney Date: 6/23/2014 1:35:58 PM Name: YilmazGeorge Title: Administrator - Public Utilities, Public Utilities Division Date: 6/23/2014 4:47:54 PM Name: KlatzkowJeff Title: County Attorney, Date: 6/26/2014 5:07:34 PM Name: UsherSusan Title: Management/Budget Analyst, Senior, Office of Management & Budget Date: 6/27/2014 1:02:23 PM Name: OchsLeo Title: County Manager, County Managers Office Date: 6/30/2014 8:57:02 PM Packet Page -1045- MCr o Ad;mIris}atve Servi,.-es E_ vision 7,uncisiraq ® Contract Change Request 7/8/2014 16.C.4. Purchasing Department Change Modification Form ❑ Work Order Modification Contract #: 12 -5931 Change #: 11`' PO/Work Order #: Project Name: MPS 312 Rehabilitation Current BCC Approved Amount $ 5,961,000.00 4500142945 Last BCC Approval Date; Agenda Item # Project #: 72549 Project Manager: Peter Department: PPMD Contractor /Firm Name: D. N. Higgins Dollar Amount of this Change $ Schalt, PIMP 0.00% Total Change from Original Amount Original Contract/Work Order Amount V $ 5,961,000.00 2/12/2013, 11A Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 5,961,000.00 2/12/2013, 11A Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount-/ $ 5,961,000.00 submitting for approval (this box must be initialed by Project Manager) SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 0.00 0.00% Total Change from Original Amount Revised Contract/Work Order Total $ 5,961,000.00 0.00% Change from Current BCC Approved Amount Cumulative Changes $ 0.00 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Original completion date: Last approved completion date: Revised completion date (includes this 3/27/2014 Z 4/24/2014 change): 8/22/2014 ,-' Number of days added: 120 with Each step on the contract modification checklist form has been reviewed prior to me this change order, 148 total since submitting for approval (this box must be initialed by Project Manager) NTP. ❑ Add new task(s) �� Change task(s) —T-a—Delete task(s) ® Other (specify): Add time 1. Provide a detailed and specific explanation of the requested change(s) to the task(s) and /or the additional days ^sided: This change order is to add 120 days to the last approved final completion date due to direct impacts to the critical :h of the project. This will allow the contractor sufficient time to finalize and close out the project. 4 2. Provide detailed rationale for the requested change: The time extension is to extend the final completion date of the contract due to direct impacts from unforeseen conditions to the critical path of the project. This will allow time for the contractor to finalize and close out the contract and for him to transmit the final deliverables to the County. 3. Provide explanation why change was not anticipated in original scope of work: The unforeseen conditions including the regulatory agency changing the material of the fuel piping after the project was awarded, and additional landscaping around the backflow device could not have been foreseen or anticipated until the project was commenced and underway. 4. Describe the impact if this change is not processed: The contractor could not finish the project properly, and the County would not receive the specified contract deliverables. Type of Change / Modification 1 Planned / Elective ❑ 2. Unforeseen conditions /circumstance ❑ 3. Quantity or price adjustment ❑ 4 Correction of error(s) 5. Value added ®6. Schedule adjustment Change Requested By • Contractor /Consultant ® Owner Usin De artment • Design Professional ❑ Regulatory Agency (specify): ❑ Other (specify): Purchasing Professional Participated in Negotiation of Change / Modification: ® Yes ❑ No Approved by: ° Date:,, "qme and Title: Tom`Chmelik, P.E., PMP, PPMD Director ` ;viewed by- ; - Date: I Procurement-Strategist's Name: Brenda Brilhart Packet Page -1046- Revised: 7126/13 1 7/8/2014 16.C.4. CHANGE ORDER CHANGE ORDER NO, i 1 CONTRACT NO. 12.5931 BCC Date: Agenda Item: TO: D. N, Higgins DATE: June 11, 2014 PROJECT NAME: MPS 312 Rehabilitation PROJECT NO.: 72549 Under our AGREEMENT dated February 12, 2013 You hereby are authorized and directed to make the following change(s) in accordance with terms and conditions of the Agreement: Add 120 days to final completion. (Please see attached Modification form and backup). Original Agreement Amount $5,96L000.0 Sum of Previous Changes $0 This Change Order Deduct $d Present Agreement Amount $5961,000.00 The time for completion shall be increased by 120 calendar days due to this Change Order. Accordingly, the Contract Time is now 513 calendar days. The substantial completion date is March 6, 2014 and the final completion date is August 22, 2014. Your acceptance of this Change Order shall constitute a modification to our Agreement and will be performed subject to all the same terms and conditions as contained in our Agreement indicated above, as fully as if the same were repeated in this acceptance. The adjustment, if any, to the Agreement shall constitute a full and final settlement of any and all claims of the Contractor arising out of or related to the change set forth herein, including claims for impact and delay costs. Prepared by: PL-L,. -1 Date: fa! 1 Peter S,ghalt, PMP, Senior Project Manager Approved By: _ Ug 4411 Oct rv't Dr id Schmitt, P.E. Vice President Q. Grady Minor Packet Page -1047- Contract N Brandy Bartolone, Regi D.N. Hins tq / 7KV, Approved by: f -� CHANGE OTME . No. 11 Page 7/8/2014 16.C.4. Date:^ Ta �-qn'elik, P.E., PW, PPMD Director )Approved by: f Date: G Date: e rI '—i`�` lose p ellone, Operations Director ,1 Approved by: Date: �. Dr. George Yilmaz, PhD, PUD Administrator Approved by: Date: Brenda Brilhart, Procurement Strategist Packet Page -1048- 7/8/2014 16.C.4. Civil Engineers * Land Surveyors e Planners • Landscape Architects June 11, 2014 Mr. Peter Schalt Collier County PPMD 3339 E. Tamiami Trail Naples, FL 34112 RE: MPS 312 Rehabilitation — Change Order For Time Extension — Final Completion Dear Mr. Schalt: We have reviewed the Time Extension request from D.H. Higgins on the MPS 312 Rehabilitation Project. The request is for a 120 day extension from April 24, 2014.,` The new final completion date will be August 22, 2014.- The additional time request contained in the letter is fair and reasonable, and does not affect the operation of the pumping station as it is now fully operational. If you have any questions please contact the undersigned V y truly yours, David W. Schn itt, P.E. DWS /jj O. Gra(ly iVlillol' & ii5\gg�ii4�� Allrii�d�V' neinecring\ PROJ- L' •NG \C \CCU131 \4RCDocs\O]Biddiag- Addenda- CUs- CoifrAL'S h��l�ft� t�l4�d�O�a '' 239-947-0375 3800 Via Del Rey EB 0005151 • L13 000515'1 - LC 26000266 Bonita 8prhigs, VL 34 134 mt'-W.gradylninor.coiil Packet Page -1049- 7/8/2014 16.C.4. June 11, 2014 Mr, Peter Schalt, PMP Senior Project Manager Collier County PPMD 3301 E. Tamiami Trail, Building H Naples, FL 34112 Re: MPS 312 Rehabilitation — Change Order Request, 120 -Day Time Extension for Final Completion Dear Mr. Schalt, This letter serves as a formal written request to follow -up our verbal request for a Final Completion Time Extension. We are requesting that the Final Completion date for the project be extended an additional 120 days from the previous Final Completion Date of April 24, 2014. The proposed Final Completion date will therefore be August 22, 2014. The additional time requested is associated with the tasks listed below and their associated durations, which directly impacted the critical path of the project. Task Duration Fuel Piping Coordination. 10 Days Preparing Change Order Proposals Following Substantial Completion 5 Days Project Management For Post Substantial Completion Change Orders 30 Days O &M Manual, Training Video, and Other Closeout Document Production 45 Da County Shutdown for Bypass Removal 30 Days Total 120 Days We appreciate your understanding in this matter. Yours Truly, �G Marc Lean, P.E. C: Brandy Bartolone Steven Martin, P.E., ABB David Schmitt, P.E., Q. Grady Minor File Packet Page -1050-