Agenda 06/10/2014 Item #16A 7 6/10/2014 16.A.7.
n
EXECUTIVE SUMMARY
Recommendation to approve a two year extension for completion of Site Development Plan (SDP)
improvements associated with Alden Woods (SDP AR-7819) pursuant to Section 10.02.03 H of the
Collier County Land Development Code.
OBJECTIVE: To have the Board of County Commissioners (Board) approve a two year
extension for the completion of Site Development Plan (SDP) improvements associated with
Alden Woods.
CONSIDERATIONS: On April 13, 2006, the Engineering Services Department approved the
Site Development Plan(SDP)Alden Woods. Section 10.02.03 H of the Land Development Code
requires that upon approval, an SDP must be completed within 36 months. The Code also allows
for 2,two year extensions which the developer has received. The Developer has already received
the maximum number of extensions allowed under the Code, and the project technically expired
on April 13,2013. As a result,the Board of County Commissioners must approve this additional
two-year extension request.
FISCAL IMPACT: The County will realize revenues as follows:
Fund: Growth Management Fund 131
Agency: County Manager
Cost Center: 138327--Land Development Services
Revenue generated by this project: Total: $150.00 Extension Fees
LEGAL CONSIDERATIONS: This item has been approved as to form and legality, and
requires a majority vote for Board approval.-SAS
GROWTH MANAGEMENT IMPACT: There is no growth management impact
associated with this Executive Summary.
RECOMMENDATIONS:
1. That the Board accepts the applicant's extension request together with the appropriate fees.
2. Approve a two year extension until April 13, 2015 for Alden Woods (SDP AR-7819) so that
the developer may be in compliance with the time limit requirements of the Land
Development Code.
Prepared by: John Houldsworth, Senior Site Plan Reviewer, Engineering Services, Growth
Management Division,Planning and Regulation
Attachment: Original Approval Letter
Packet Page-636-
6/10/2014 16.A.7.
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.A.5
Item Summary: Recommendation to approve a two year extension for completion of Site
Development Plan(SDP)improvements associated with Alden Woods(SDP AR-7819)pursuant to
Section 10.02.03 H of the Collier County Land Development Code.
Meeting Date: 6/10/2014
Prepared By
Name: houldsworth_j
Title: Site Plans Reviewer, Senior,Natural Resources
Approved By
Name: JackMcKenna
Title: Manager-Engineering Review Services,Engineering&Environmental Services
Date: 05/09/2014 11:20:31 AM
Name: puigj
Title: Operations Analyst,Community Development&Environmental Services
Date: 05/1 6/2014 02:30:39 PM
Name: scottstone
Title: Assistant County Attorney,CAO Land Use/Transportation
Date: 05/19/2014 09:56:29 AM
Name: marcellajeanne
Title: Executive Secretary, Transportation Planning
Date: 05/28/2014 07:50:31 AM
Name: markisackson
Title: Director-Corp Financial and Mngmt Svs, Office of Management&Budget
Date: 05/28/2014 08:50:53 AM
Name: klatzkowjeff
Title: County Attorney,
Date: 05/28/2014 03:15:36 PM
Packet Page-637-
6/10/2014 16.A.7.
Name: ochs 1
Title: County Manager, County Managers Office
Date: 05/29/2014 02:40:12 PM
n
Packet Page-638-
6/10/2014 16.A.7.
April 13, 2006
CHRISTOPHER MITCHELL, P.E.
WALDROP ENGINEERING, PA
10641 AIRPORT RD N SUITE 32
NAPLES FL 34109
(239)596-9191
Re: Final Site Development Plans Approval
SDP-AR-7819, ALDEN WOODS
Project Number: 2005020063
Dear Mr. Mitchell:
THIS IS YOUR PERMIT AND MUST BE POSTED ONSITE!
Engineering Services Department has reviewed the Final Site Development Plan for the
referenced project and has no objection to the construction of water, sewer, paving and drainage
aspects of the project subject to the following stipulations:
1. General Conditions
a) CHANGES IN USE AND/OR DESIGN OF THESE SITE AND ACHITECTURAL PLANS
AR.E NOT AUTHORIZED WITHOUT WRITTEN APPROVAL BY THE COUNTY.
CHANGES SHALL REQUIRE RE—REVIEW IN ACCORDANCE WITH ALL CURRENT
COUNTY CODES INCLUDING PARKING FACILITIES, UTILITIES, TRANSPORTATION
AND THE LIKE.
b) A preliminary inspection and approval of the infrastructure for multi-family residential must
be done by Engineer Inspections prior to any Certificate of Occupancy being granted.
c:) All PUD related stipulations shall apply to this project.
d) Permits from other agencies having jurisdiction over this project shall be obtained prior to
start of construction.
e) Please call Mr. Don Nobles at 403-2391 to schedule a pre—construction meeting a minimum
of 46 hours prior to start of construction.
f! This Final Site Development Plan is approved due to the issuance of a Certificate of Public
Facility Adequacy # 06-0128 with respect to Collier County Ordinance 93-82.
g) All construction activities permitted by this letter shall only occur during the following times:
Packet Page-639-
6/10/2014 16.A.7.
Page 2
6:30 A.M. to 7:00 P.M., Monday through Saturday; no work is permitted on Sundays and the
following holidays:
New Year's Day, Memorial Day, 4th of July, Labor Day, Thanksgiving Day, Christmas Day
I-1) The review and approval of these improvement plans does not authorize the construction of
required improvements, which are inconsistent with easement of record.
i; Upon completion of the infrastructure improvements associated with a site development
plan, and prior to the issuance of a certificate of occupancy, the engineer shall provide a
completion certificate as to the improvements, together with all applicable items referenced
in Section 3.2.6.5.3 of this code including electronic disk. Upon a satisfactory inspection of
the improvements, a certificate of occupancy may then be issued.
j;1 SIGNAGE RESTRICTIONS: Please be advised that any permanent sign (wall, ground,
monument, directory, etc.) requires a separate building permit and must meet the provisions
of the Collier County Land Development: Code, Section 5.06, acrd/or the applicable
provisions of the governing Planned Unit Development (PUD) document, regardless of any
sign placement, dimensions or color depicted on the site and/or architectural plans
approved by this letter.
2. Utility!
a) See attached Exhibit "A"
b) "APPROVAL OF THESE PLANS DOES NOT CONSTITUTE APPROVAL OF THE
METER SIZE. SIZING OF THE METER SHALL BE DONE WITH THE APPROVAL OF
PUBLIC UTILITIES ENGINEERING DIRECTOR OR HIS DESIGNEE, BASED ON
DOCUMENTATION RECEIVED FROM THE ENGINEERING OF RECORD. THE METER
DETAIL SHALL BE SUBMITTED TO ENGINEERING REVIEW SERVICE FOR
APPROVAL PRIOR TO INSATLLATION".
c:) No water or sewer utility construction shall commence until proper IDEP permits have been
obtained.
3. Subdivision
All work shall be in accordance with applicable Collier County ordinances and rules and
regulations of other entities having jurisdiction over the project.
4. Environmental
Site clearing is conditioned to the stipulations contained on the approved site plan.
Packet Page-640-
6/10/2014 16.A.7.
Page 3
5. Water Management
a) All work shall be in accordance with applicable State or Federal rules and regulations.
t) Work area shall be properly barricaded with hay bales and/or silt screens during the entire
time of construction, to prevent any siltation during construction.
c) Separate excavation permit must be obtained.
CI) The engineer of record, prior to issuance of a Certificate of Occupancy, shall provide
documentation from the stormwater maintenance entity that it has been provided
information on how the stormwater system works and their responsibility to maintain the
system.
II
e) This project was permitted by SFWMD.
fl Whether or not this project was permitted by SFWMD, dewatering shall not occur without a
dewatering permit from the South Florida Water Management District"
6. Addressing
F'ursuani: to Ordinance No. 99-.76, no proposed subdivision, street, building, condominium or
development may utilize the same name or a similar sounding name as any existing
subdivision, street, building, condominium or development, except that the major street within a
subdivision may utilize the name of the subdivision. Any changes to the project name shall be
reviewed and approved by Community Development and Environmental Services Addressing
Department.
7. Landscaping.
At the time of Preliminary Acceptance the Landscape Architect shall certify that he landscaping
has been installed in substantial accordance with the approved plans and specifications. The
certification shall be in a form approved by the County Manager or his designee.
8. Fire Protection.
a) Please note that prior to the accumulation of combustible building materials on site,
proposed fire hydrants must be operable with the minimum required fire flows and improved
stabilized emergency apparatus access ways (min. 14' wide) must be available to within
100' of the structures.
b) No fire appliances shall be obstructed, visually or functionally, by vegetation.
Additional Stipulations:
Packet Page-641-
6/10/2014 16.A.7.
Page 4
9.Dev Rev En 0 Mgmt
a Prior to issuance, of a Certificate of Occupancy, a Performance:/Maintenance Bond must be submitted
based on the estimated cost of the proposed paving and drainage improvements.
b. Prior to Excavation Permit issuance, a Performance Guarantee in the amount of$2.5,000 must be
submitted.
10. Dev Rev Eau Utilities
a. Preliminary and final water and sewer inspections shall be coordinated through Sherry Eaton with a 48
hour written noti fi cattion.
b. An on site pre construction meeting for water and/or sewer shall be held prior to construction. Contact
Wes Hill(x),213-2905.
See attached inspection checklist for SDP improvements.
(4) sets of approved plans and (3) sets of landscape plans are being returned herewith for your
use. Two copies of approved SDP shall be attached to each set of building plans submitted.
Two copies of the stamped approved Architectural Plans shall be submitted with the
Building Permit Application. If this is a simultaneous submittal it is the applicant's
responsibility to ,insert the approved architectural plans into the Building Department permit
set.
Be advised that this approval automatically expires twenty—four (24) months from the date of this
letter pursuant to Collier County Land Development Code Section 3.3.8.
Please call me if you have any questions or need any additional information.
Sincerely,
Thomas E. Kuck, P.E.
Engineering Services Director/
County Engineer
cc: Abe Skinner, Property Appraiser (w/attach.)
Don Nobles, Engineering Inspections Supervisor(w/attach.)
Ivette Monroig, Planning Tech.
HEIDI WILLIAMS, Project Planner
Customer Services/,Addressing Wallach.)
Sherry Eaton, Engineering Technician
Diane Deoss, D.O.R.
Jacquelyn DeSear, Operations Analyst., Public Utilities Engineering (wiattach.)
Wes Hill, Engineer
Fire Review
SDP-AR-7819, (wiattach.)
Engineering Reading File
Packet Page-642-