Agenda 06/10/2014 Item #16A 7 6/10/2014 16.A.7. n EXECUTIVE SUMMARY Recommendation to approve a two year extension for completion of Site Development Plan (SDP) improvements associated with Alden Woods (SDP AR-7819) pursuant to Section 10.02.03 H of the Collier County Land Development Code. OBJECTIVE: To have the Board of County Commissioners (Board) approve a two year extension for the completion of Site Development Plan (SDP) improvements associated with Alden Woods. CONSIDERATIONS: On April 13, 2006, the Engineering Services Department approved the Site Development Plan(SDP)Alden Woods. Section 10.02.03 H of the Land Development Code requires that upon approval, an SDP must be completed within 36 months. The Code also allows for 2,two year extensions which the developer has received. The Developer has already received the maximum number of extensions allowed under the Code, and the project technically expired on April 13,2013. As a result,the Board of County Commissioners must approve this additional two-year extension request. FISCAL IMPACT: The County will realize revenues as follows: Fund: Growth Management Fund 131 Agency: County Manager Cost Center: 138327--Land Development Services Revenue generated by this project: Total: $150.00 Extension Fees LEGAL CONSIDERATIONS: This item has been approved as to form and legality, and requires a majority vote for Board approval.-SAS GROWTH MANAGEMENT IMPACT: There is no growth management impact associated with this Executive Summary. RECOMMENDATIONS: 1. That the Board accepts the applicant's extension request together with the appropriate fees. 2. Approve a two year extension until April 13, 2015 for Alden Woods (SDP AR-7819) so that the developer may be in compliance with the time limit requirements of the Land Development Code. Prepared by: John Houldsworth, Senior Site Plan Reviewer, Engineering Services, Growth Management Division,Planning and Regulation Attachment: Original Approval Letter Packet Page-636- 6/10/2014 16.A.7. COLLIER COUNTY Board of County Commissioners Item Number: 16.A.5 Item Summary: Recommendation to approve a two year extension for completion of Site Development Plan(SDP)improvements associated with Alden Woods(SDP AR-7819)pursuant to Section 10.02.03 H of the Collier County Land Development Code. Meeting Date: 6/10/2014 Prepared By Name: houldsworth_j Title: Site Plans Reviewer, Senior,Natural Resources Approved By Name: JackMcKenna Title: Manager-Engineering Review Services,Engineering&Environmental Services Date: 05/09/2014 11:20:31 AM Name: puigj Title: Operations Analyst,Community Development&Environmental Services Date: 05/1 6/2014 02:30:39 PM Name: scottstone Title: Assistant County Attorney,CAO Land Use/Transportation Date: 05/19/2014 09:56:29 AM Name: marcellajeanne Title: Executive Secretary, Transportation Planning Date: 05/28/2014 07:50:31 AM Name: markisackson Title: Director-Corp Financial and Mngmt Svs, Office of Management&Budget Date: 05/28/2014 08:50:53 AM Name: klatzkowjeff Title: County Attorney, Date: 05/28/2014 03:15:36 PM Packet Page-637- 6/10/2014 16.A.7. Name: ochs 1 Title: County Manager, County Managers Office Date: 05/29/2014 02:40:12 PM n Packet Page-638- 6/10/2014 16.A.7. April 13, 2006 CHRISTOPHER MITCHELL, P.E. WALDROP ENGINEERING, PA 10641 AIRPORT RD N SUITE 32 NAPLES FL 34109 (239)596-9191 Re: Final Site Development Plans Approval SDP-AR-7819, ALDEN WOODS Project Number: 2005020063 Dear Mr. Mitchell: THIS IS YOUR PERMIT AND MUST BE POSTED ONSITE! Engineering Services Department has reviewed the Final Site Development Plan for the referenced project and has no objection to the construction of water, sewer, paving and drainage aspects of the project subject to the following stipulations: 1. General Conditions a) CHANGES IN USE AND/OR DESIGN OF THESE SITE AND ACHITECTURAL PLANS AR.E NOT AUTHORIZED WITHOUT WRITTEN APPROVAL BY THE COUNTY. CHANGES SHALL REQUIRE RE—REVIEW IN ACCORDANCE WITH ALL CURRENT COUNTY CODES INCLUDING PARKING FACILITIES, UTILITIES, TRANSPORTATION AND THE LIKE. b) A preliminary inspection and approval of the infrastructure for multi-family residential must be done by Engineer Inspections prior to any Certificate of Occupancy being granted. c:) All PUD related stipulations shall apply to this project. d) Permits from other agencies having jurisdiction over this project shall be obtained prior to start of construction. e) Please call Mr. Don Nobles at 403-2391 to schedule a pre—construction meeting a minimum of 46 hours prior to start of construction. f! This Final Site Development Plan is approved due to the issuance of a Certificate of Public Facility Adequacy # 06-0128 with respect to Collier County Ordinance 93-82. g) All construction activities permitted by this letter shall only occur during the following times: Packet Page-639- 6/10/2014 16.A.7. Page 2 6:30 A.M. to 7:00 P.M., Monday through Saturday; no work is permitted on Sundays and the following holidays: New Year's Day, Memorial Day, 4th of July, Labor Day, Thanksgiving Day, Christmas Day I-1) The review and approval of these improvement plans does not authorize the construction of required improvements, which are inconsistent with easement of record. i; Upon completion of the infrastructure improvements associated with a site development plan, and prior to the issuance of a certificate of occupancy, the engineer shall provide a completion certificate as to the improvements, together with all applicable items referenced in Section 3.2.6.5.3 of this code including electronic disk. Upon a satisfactory inspection of the improvements, a certificate of occupancy may then be issued. j;1 SIGNAGE RESTRICTIONS: Please be advised that any permanent sign (wall, ground, monument, directory, etc.) requires a separate building permit and must meet the provisions of the Collier County Land Development: Code, Section 5.06, acrd/or the applicable provisions of the governing Planned Unit Development (PUD) document, regardless of any sign placement, dimensions or color depicted on the site and/or architectural plans approved by this letter. 2. Utility! a) See attached Exhibit "A" b) "APPROVAL OF THESE PLANS DOES NOT CONSTITUTE APPROVAL OF THE METER SIZE. SIZING OF THE METER SHALL BE DONE WITH THE APPROVAL OF PUBLIC UTILITIES ENGINEERING DIRECTOR OR HIS DESIGNEE, BASED ON DOCUMENTATION RECEIVED FROM THE ENGINEERING OF RECORD. THE METER DETAIL SHALL BE SUBMITTED TO ENGINEERING REVIEW SERVICE FOR APPROVAL PRIOR TO INSATLLATION". c:) No water or sewer utility construction shall commence until proper IDEP permits have been obtained. 3. Subdivision All work shall be in accordance with applicable Collier County ordinances and rules and regulations of other entities having jurisdiction over the project. 4. Environmental Site clearing is conditioned to the stipulations contained on the approved site plan. Packet Page-640- 6/10/2014 16.A.7. Page 3 5. Water Management a) All work shall be in accordance with applicable State or Federal rules and regulations. t) Work area shall be properly barricaded with hay bales and/or silt screens during the entire time of construction, to prevent any siltation during construction. c) Separate excavation permit must be obtained. CI) The engineer of record, prior to issuance of a Certificate of Occupancy, shall provide documentation from the stormwater maintenance entity that it has been provided information on how the stormwater system works and their responsibility to maintain the system. II e) This project was permitted by SFWMD. fl Whether or not this project was permitted by SFWMD, dewatering shall not occur without a dewatering permit from the South Florida Water Management District" 6. Addressing F'ursuani: to Ordinance No. 99-.76, no proposed subdivision, street, building, condominium or development may utilize the same name or a similar sounding name as any existing subdivision, street, building, condominium or development, except that the major street within a subdivision may utilize the name of the subdivision. Any changes to the project name shall be reviewed and approved by Community Development and Environmental Services Addressing Department. 7. Landscaping. At the time of Preliminary Acceptance the Landscape Architect shall certify that he landscaping has been installed in substantial accordance with the approved plans and specifications. The certification shall be in a form approved by the County Manager or his designee. 8. Fire Protection. a) Please note that prior to the accumulation of combustible building materials on site, proposed fire hydrants must be operable with the minimum required fire flows and improved stabilized emergency apparatus access ways (min. 14' wide) must be available to within 100' of the structures. b) No fire appliances shall be obstructed, visually or functionally, by vegetation. Additional Stipulations: Packet Page-641- 6/10/2014 16.A.7. Page 4 9.Dev Rev En 0 Mgmt a Prior to issuance, of a Certificate of Occupancy, a Performance:/Maintenance Bond must be submitted based on the estimated cost of the proposed paving and drainage improvements. b. Prior to Excavation Permit issuance, a Performance Guarantee in the amount of$2.5,000 must be submitted. 10. Dev Rev Eau Utilities a. Preliminary and final water and sewer inspections shall be coordinated through Sherry Eaton with a 48 hour written noti fi cattion. b. An on site pre construction meeting for water and/or sewer shall be held prior to construction. Contact Wes Hill(x),213-2905. See attached inspection checklist for SDP improvements. (4) sets of approved plans and (3) sets of landscape plans are being returned herewith for your use. Two copies of approved SDP shall be attached to each set of building plans submitted. Two copies of the stamped approved Architectural Plans shall be submitted with the Building Permit Application. If this is a simultaneous submittal it is the applicant's responsibility to ,insert the approved architectural plans into the Building Department permit set. Be advised that this approval automatically expires twenty—four (24) months from the date of this letter pursuant to Collier County Land Development Code Section 3.3.8. Please call me if you have any questions or need any additional information. Sincerely, Thomas E. Kuck, P.E. Engineering Services Director/ County Engineer cc: Abe Skinner, Property Appraiser (w/attach.) Don Nobles, Engineering Inspections Supervisor(w/attach.) Ivette Monroig, Planning Tech. HEIDI WILLIAMS, Project Planner Customer Services/,Addressing Wallach.) Sherry Eaton, Engineering Technician Diane Deoss, D.O.R. Jacquelyn DeSear, Operations Analyst., Public Utilities Engineering (wiattach.) Wes Hill, Engineer Fire Review SDP-AR-7819, (wiattach.) Engineering Reading File Packet Page-642-