Agenda 05/27/2014 Item #16C2 5/27/2014 16.C.2. EXECUTIVE SUMMARY Recommendation to approve a work order for $472,333 to Douglas N. Higgins, Inc., under Request for Quotation #08-5011-115 for Underground Utility Contracting Services for the South County Water Reclamation Facility Proposed 30" and 24" Force Main and Master Pump Station 306 Force Main—Phase IV project,Project Number 70044. OBJECTIVE: Meet demand, stay in compliance, serve customers efficiently, and improve reliability by providing an alternative path for wastewater to flow from Master Pump Station (MPS) 302 to the South County Water Reclamation Facility (SCWRF). CONSIDERATIONS: The proposed scope of work for Project 70044 "Force Main Technical Support" is consistent with the 2010 Water Capital Improvement Project (CIP) Update, page 2 of 4, line 56, as identified in the 2011 User Fee Rate Study. Funding for project 70044 is available in and is consistent with the FY2014 CIP Budget. On September 11, 2012, the Board approved Contract #11-5782 for three design contracts for the Wastewater Basin Program under Agenda Item 11E. The MPS 306 Force Main project is one of many projects under design as part of the Wastewater Basin 306 Program. More construction projects are planned as the program continues and as funding becomes available. Wastewater MPS 306 is located near U.S. 41 and Thomasson Drive. Currently, MPS 306 discharges through a force main to MPS 302 located at the intersection of Rattlesnake Hammock Road and Santa Barbara Road. MPS 302 discharges through a 36-inch force main to the SCWRF. Approximately 80 percent of the south wastewater transmission system is conveyed through MPS 302 to the SCWRF. Currently, there is no alternative path for these flows to reach the SCWRF; therefore, the 36-inch force main cannot be shut down for preventative maintenance. Further, if the 36-inch force main were to fail, approximately 80 percent of the south transmission system would be out of service with a high potential for sanitary sewer overflows. To address these vulnerabilities, a new force main is under construction from MPS 306 to the SCWRF. This will provide an alternative path, allowing flow from MPS 302 to MPS 306 and then to the SCWRF. Attachment six shows the locations of the existing and proposed facilities. Under current flow conditions this project will directly benefit approximately 64,000 customers. Rapid land development in this area necessitates force main construction in phases, as easements can be acquired. This scope of work is Phase 4 of 7 required to construct the approximate 18,000-foot force main from MPS 306 to the SCWRF. Phase 4 is approximately 1,300 feet. Phase 1 (2,000 feet) was authorized by the Board on April 22, 2014 (Item 16C3). Phases 6 and 7, approximately 900 feet each, were constructed in November and December 2013. The remaining Phases 2 and 3 are planned to he constructed by the end of FY 2015. The county distributed Request for Quotation, "SCWRF Proposed 30" and 24" Force Main & MPS 306 Force Main — Phase III" (Attachment 2). on March 7, 2014, to the five vendors under Fixed-Term Underground Utilities Contract #08-5011. Four contractors submitted quotations by the March 24, 2014, deadline. The quotations are summarized below and in Attachment 1. Packet Page -815- 5/27/2014 16.C.2. VENDOR PROJECT COST Douglas N. Higgins $472,333.00 Quality Enterprises $ 541,420.00 Haskins, Inc. $ 715,000.00 Mitchell & Stark $ 825,000.00 Staff determined the lowest quote to be fair and reasonable and recommends awarding the project to Douglas N. Higgins, Inc., the lowest responsive and qualified vendor. The quote is $1 17,667 (20 percent) less than the engineer's cost opinion. The design professional, Hole Montes, Inc., recommends award to Douglas N. Higgins,Inc., in its letter dated March 26, 2014 (Attachment 4). Douglas N. Higgins, Inc. has a satisfactory performance and warranty record on previous, similar utility-related projects. The quote specifications informed the bidders there may be unforeseen conditions associated with the project. The quote amount incorporates an allowance of $55,000 for owner-directed additional work which includes, but is not limited to, unforeseen work and costs associated with existing underground piping, electrical wiring and conduits. The price for any additional work will be negotiated prior to commencement in accordance with the county's Purchasing Policy and the terms of the agreement. FISCAL IMPACT: Funding is available in, and is consistent with, the FY2014 Capital Budget approved by the Board on September 19, 2013. The source of funding is the Wastewater User Fee Fund (414). The project is expected to be complete by August 2014. There will be a minor increase in annual maintenance costs for the additional force main. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval.—SRT GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. RECOMMENDATION: That the Board of County Commissioners, Ex-officio the Governing Board of the Collier County Water-Sewer District, approve a Work Order for $472,333 to Douglas N. Higgins, Inc., under Request for Quotation #08-5011-115 for Underground Utility Contracting Services for the South County Water Reclamation Facility Proposed 30" and 24" Force Main and Master Pump Station 306 Force Main — Phase Ill project, Project Number 70044; and, authorize the Chairman to sign and execute the Work Order after final approval by the County Attorney's Office. Prepared By: Wayne M. Karlovich, Senior Project Manager,Public Utilities PPMD Attachments: Attachment 1-Quote Tabulation Attachment 2-Request for Quotes Attachment 3- PPMD Analysis of Quotes Attachment 4-Recommendation Letter Attachment 5- Work Order Attachment 6-Project Location Exhibit Packet Page -816- 5/27/2014 16.C.2. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.C.16.C.2. Item Summary: Recommendation to approve a work order for $472,333 to Douglas N. Higgins, Inc., under Request for Quotation #08-5011-115 for Underground Utility Contracting Services for the South County Water Reclamation Facility Proposed 30" and 24" Force Main and Master Pump Station 306 Force Main - Phase III project, Project Number 70044. Meeting Date: 5/27/2014 Prepared By Name: KarlovichWayne Title: Project Manager, Senior, Public Utilities Engineering 4/1 7/2014 1 2:35:06 PM Submitted by Title:Project Manager. Senior,Public Utilities Engineering Name: KarlovichWayne 4/17/2014 12:35:07 PM Approved By Name: NagySteve Title: Manager- Wastewater Collection, Wastewater Date: 4/18/2014 7:22:16 AM Name: HapkeMargie Title: Recycling Coordinator. Solid Waste Date: 4/18/2014 9:38:53 AM Name: JohnsonScott Title: Procurement Specialist,Purchasing& General Services Date: 4/18/2014 10:13:25 AM Name: JohnsonScott Title:Procurement Specialist. Purchasing&General Services Date: 4/18/2014 10:13:34 AM Packet Page -817- 5/27/2014 16.C.2. Name: BrilhartBrenda Title: Procurement Specialist,Purchasing& General Services Date: 4/21/2014 9:53:22 AM Name: JacobsSusan Title: Operations Analyst,Public Utilities Division Date: 4/22/2014 3:59:18 PM Name: ZautckeLaura Title: Management/Budget Analyst, Senior, Utilities Finance Operations Date: 4/24/2014 8:01:40 AM Name: JohnssenBeth Title: Director- Wastewater, Wastewater Date: 5/1/2014 11:12:16 AM Name: PajerCraig Title: Project Manager, Principal,Public Utilities Engineering Date: 5/1/2014 8:30:11 PM Name: ChmelikTom Title: Director-Public Utilities Engineering, Public Utilities Engineering Date: 5/9/2014 8:39:31 AM Name: TeachScott Title: Deputy County Attorney, County Attorney Date: 5/9/2014 2:04:44 PM Name: YilmazGeorge Title: Administrator-Public Utilities, Public Utilities Division Date: 5/12/2014 11:20:15 AM Name: KlatzkowJeff Title: County Attorney, Date: 5/14/2014 4:08:52 PM Name: UsherSusan Title: Management/Budget Analyst, Senior, Office of Management&Budget Date: 5/19/2014 11:56:05 AM Name: OchsLeo Title: County Manager, County Managers Office Date: 5/19/2014 12:29:32 PM Packet Page -818- 5/27/2014 16.C.2. Packet Page -819- 5/27/2014 16.C.2. QUOTE NO. 08-5011-115-30"&24"FORCE MAIN PHASE 1 -SOUTH COUNTY WATER RECLAMATION FACILITY &MPS 306 Forcemain Phase III DN Higgins Haskins Mitchell&Stark Quality Item Estimated No. Description Units Quantity Total Total Total Total 1 Perform all Contract Work described in the Lump Sum $417,333.00 $660,000.00 $770,000.00 $486,420.00 Contract Documents. — 2 Allowance Fund for Owners Use as Directed. This fund will be used only at the Owner's direction to accomplish work due to unforeseen conditions as specified in Section 01135. Inclusion of the Allowance Fund as part of the Contract Price is not a — guarantee that the Contractor will be paid any portion or the full amount of the Allowance Fund. Lump Sum $55,000.00 $55,000.00 $55,000.00 $55,000.00 $472,333.00 $715,000.00 $825,000.00 $541,420.00 Packet Page -820- 5/27/2014 16.C.2. Co l County Addrninisrattve Services Division Purchasing REQUEST FOR QUOTATIONS FOR MULTIPLE PROJECTS UNDER CONTRACT#08-5011 "Annual Contract for Underground Utilities" Date: March 10, 2014 From: Brenda Brilhart, Procurement Strategist 239-252-8446, Telephone Number brendabrilhart(c�colliergov.net To: Prospective Vendors Re: RFQ #08-5011-115 —SCWRF Proposed 30" and 24" Force Main — Phase III & MPS 306 Forcemain —Phase III ($590k) As provided in the referenced contract, the Collier County Purchasing Department is soliciting quotes for the referenced project. RFQ Due Date: 4:00 PM March 24, 2014 Non-Mandatory Pre-Quote Meeting 10:00 AM March 14, 2014 Purchasing Pre-Quote Meeting Location: 3327 Tamiami Trail East Naples, FL 34112 Q&A Deadline: 5:00 PM 3/18/14 Number of Days to Final Completion: 150 to Substantial, 30 to Final, Total 180 Plans and Specs: Included Liquidated Damages: $1,591 per day Payment & Performance Bonds Yes Direct Material Purchase No Your quotation response for this project is due no later than the date and time specified above. We will not accept any quotation responses later than the noted time and date. If your firm is unable to respond electronically, your quotation must be received in the office of the Purchasing Department at the above referenced address no later than the time and date specified. We look forward to your participation in this request for information/quotation process. Firm's Complete Legal Name Telephone Number/ Fax Number Signature Title Print Name Date C: Wayne Karlovich, Project Manager RFQ 08-5011 -115 1 Packet Page -821- ----- ---- tio ro ■ CU o as CI. t i i I I I co 1 CO I CL I of cr SI 0 LL 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 o o 0 o o o NJ rn Ln Lo tn- in- Packet Page -822- 5/27/2014 16.C.2. HOLE MONIES ENGINEERS•PJ NNERS•SURVEYORS 950 Encore Way•Naples.Florida 34110• Phone 239.254.2000•Fax:239.254.20099 March 26, 2014 Wayne Karlovich, P.E., Senior Project Manager Collier County Public Utilities 3339 Tamiami Trail East Suite 303 Naples FL 34112 RE: EVALUATION OF QUOTATIONS SCWRF 30" & 24" FORCE MAIN PHASE 1 & MPS 306 FORCE MAIN PHASE III HM File No. 2013.051 Dear Wayne, We have reviewed the four bids received by the County on the SCWRF 30" and 24" Force Main Phase 1, County Quote No. 08-5011-115. The four bidders and their quoted price are identified below as provided by the County Purchasing Department. The apparent low quote is from D.N. Higgins in the amount of$472,333.00. Bidder Bid ] Douglas N Higgins, Inc. $472,333.00 2 Quality Enterprises, Inc. $541,420.00 3 Haskins, Inc. $715,000.00 4 Mitchell & Stark Company, Inc. $825,000.00 D.N. Higgins, Inc. has successfully completed other construction projects for Collier County and is on the County's list of approved utility contractors. The engineer's estimate is $590,000. Therefore, we recommend award of this construction contract to D.N. Higgins in the amount of $472,333.00 subject to a final review by the Purchasing Department of the quotation documents. Please contact us if there are any questions about this quote evaluation. Thank you, HOLE MONTES, INC. / ;Jerry R. fareska, Ph.D., P.E., B.C.E.E. 'Associat'e/Environmental Engineering Manager JRT:dlh Ha2013\2013051\EN\C Correspondence0Cl Client CorrspondenceA20140325 WK SCWRF 30 Inch Force Main Award Recommendation Itr JRT.doc Packet Page -823- No;.-.)[es earl r,iyers -__- 5/27/2014 16.0.2. WORK ORDER/PURCHASE ORDER Contract 08-5011 "Annual Underground Utility Contractors" Contract Expiration Date: September 10, 2014 This Work Order is for professional underground utility construction services for work known as: Project Name: SCWRF Proposed 30" and 24" Force Main — Phase 1 & MPS 306 Forcemain—Phase III Project No: 70044.6.4 The work is specified in the proposal dated March 24, 2014 which is attached hereto and made a part of this Work Order. In accordance with Terms and Conditions of the Agreement referenced above, this Work Order/Purchase Order is assigned to: Douglas N. Higgins,Inc. Scope of Work: As detailed in the attached proposal and the following: * Task I Perform all Work as described in the Proposal * Task II Owner Directed Allowance Work Schedule of Work: Complete work within 180 days from the date of the Notice to Proceed which is accompanying this Work Order. The Consultant agrees that any Work Order that extends beyond the expiration date of Agreement 4 08-5011 will survive and remain subject to the terms and conditions of that Agreement until the completion or termination of this Work Order. Compensation: In accordance with the Agreement referenced above, the County will compensate the Firm in accordance with following method(s): ZNegotiated Lump Sum (NLS) (Lump Sum Plus Reimbursable Costs (LS+RC) ®Time & Material (T&M) (established hourly rate — Schedule A) n Cost Plus Fixed Fee (CPFF), as provided in the attached proposal. Task 1 $417,333.00 NLS Task II $55,000.00 T&M TOTAL FEE $472,333.00 ` PREPARED BY: V)St`11 Waynrlovich, Senior Project Manager Date J g APPROVED BY: Craig PajeAdat cipal P ject Manager Date APPROVED BY: f i !, / Torn Chmelik, PPMD Department Director Date 1 Page 1 of 2 b� Packet Page -824- 5/27/2014 16.C.2. APPROVED BY: A if-n-1-c Steve Nagy, Collecti s System Manager Date APPROVED B : < /7 Bet ohnsse , Wastewater Director Da e APPROVED BY: ^ -- - i l -, -- 4/_/' k N \ Dr. George Yilmaz, Public Utilities Administrator Date \ APPROVED BY: /1A914-4-` $renda Brilh. Procurement Strategist Date ATTEST: BOARD OF COUNTY COMMISSIONERS Dwight E. Brock, Clerk Collier County, Florida By: By: Deputy Clerk Tom Henning, Chairman ATTEST: D• _ . - :: , Bye )(i.,7nw1" <h-A.:1- By: _ _ 13 rna, L s .;i /45'.:s+ -Sec c<C49rLA9 B —r-, c,.-,- (Print Name/Title (Print Name/Title) (.- G /o..._,4) ter, 6K7 Approved as to Form and r.ci,t,y: 4 IC 44...... 1.--. Assistant-County Attorney Cllr"4t-1 Page 2 of 2 CIID Packet Page -825- 5/27/2014 16.C.2. Ter Comfy Administral>ive Services Division Purchasing REQUEST FOR QUOTATIONS FOR MULTIPLE PROJECTS UNDER CONTRACT#08-5011 "Annual Contract for Underground Utilities" Date: March 10, 2014 From: Brenda Brilhart, Procurement Strategist 239-252-8446,Telephone Number brendabrilhart(a�colliergov.net To: Prospective Vendors Re: RFQ#08-5011-115—SCWRF Proposed 30" and 24" Force Main—Phase III & MPS 306 Forcemain—Phase III ($590k) As provided in the referenced contract,the Collier County Purchasing Department is soliciting quotes for the referenced project. RFQ Due Date: 4:00 PM March 24, 2014 Non-Mandatory Pre-Quote Meeting 10:00 AM March :14, 2014. Purchasing Pre-Quote Meeting Location: 3327 Tamiami Trail East Naples, FL 34112 Q&A Deadline: 5:00 PM 3/18/14 Number of Days to Final Completion: 150 to Substantial, 30 to Final, Total 180 Plans and Specs: Included Liquidated Damages: $1,591 per day Payment& Performance Bonds Yes Direct Material Purchase No Your quotation response for this project is due no later than the date and time specified above. We will not accept any quotation responses later than the noted time and date. If your firm is unable to respond electronically, your quotation must be received in the office of the Purchasing Department at the above referenced address no later than the time and date specified. We look forward to your participation in this request for information/quotation process. Douglas N. Higgins. Inc. Firm's Complete-Legal-Name__ •- 74-3130/239-774-4266 Telap• Number/Fax Number Signatu - Vice President/Regional Mgr. Title I �//,`r Brandy Bartolone / l Print Name Date C: Wayne Karlovich, Project Manager RFQ 08-5011 -115 Packet Page-826- 5/27/2014 16.C.2. Colter County Email: evelyncolon @colliergov.net Telephone: (239) 252-2667 Administrative Services Division FAX: (239) 252-2810 Purchasing ADDENDUM '1 Memorandum Date: March 11, 2014 From: Brenda Brilhart, Procurement Strategist To: Interested Bidders Subject: Addendum#1 RFQ 06-5011-115—SCWRF Proposed 30" and 24" Force Main — Phase III & MPS 306 Forcemain—Phase III CHANGE: The pre-quote meeting scheduled for 10:00 AM March 14, 2014 will not be held. Place all project related questions on line at www.colliergov.net/bid If you require additional information contact me using the above contact information. cc: Wayne Karlovich, Project Manager Addenduml RFQ 08-5011-115 Packet Page-827- r_ - 5/27/2014 16.C.2. 761" County Email: evelyncolon @colliergov.net Telephone: (239) 252-2667 Administrative Services Division FAX: (239)252-2810 Purchasing ADDENDUM 2 Memorandum Date: March 11, 2014 From: Brenda Brilhart, Procurement Strategist To: Interested Bidders Subject: Addendum#2 RFQ 08-5011-115—SCWRF Proposed 30" and 24" Force Main— Phase III & MPS 306 Forcemain—Phase III CORRECTION: - - - : •- - --- - ' -= - - --- -- -Rat-be-held-, Pre Quote meeting will be held at 10:00 am March 14, 2014. If you require additional information contact me using the above contact information. cc: Wayne Karlovich, Project Manager Addendum 1 RFQ 08-5011-115 Packet Page -828- ra 5/27/2014 16.C.2. Colter County Email: brendabrilhart @colliergov.net Telephone: (239) 252-8446 Administrative Services Division FAX: (239) 252-6697 Purchasing ADDENDUM 3 Memorandum Date: March 19, 2014 From: Brenda Brilhart, Procurement Strategist To: Interested Bidders Subject: Addendum#3 RFQ 08-5011-115—SCWRF Proposed 30"and 24" Force Main— Phase III & MPS 306 Forcemain—Phase Ill CHANGE: DRAWINGS Hole Montes Drawing Sheets 7 and 12: Items to be Change:4"ARVs with flange connections and 4"piping,valves and fittings. Change to: 3" ARVs with threaded connections and 3" piping, valves and fittings. See attached Drawing Sheets 7 and 12. All Drawings: At each plug valve 24" and Larger add the following Note: Plug valves 24" and Larger shall be supported on a precast concrete slab placed under the valve to help distribute the total weight of the valve and reduce line sagging. FACT SHEET Under Scope of Work revise the second paragraph to read as follows: Collier County will be pre-purchasing piping, plug valves, and fittings, from Ferguson for use by the successful contractor. A list of county-supplied materials will be distributed with the bidding documents or in an addendum. Contractor shall provide all materials not included on the list. As indicated on the FACT SHEET, attached is the list of county-supplied materials. SPECIFICATIONS Add the following to Specification Section 330523.13 Horizontal Directional Drilling, 1.4— Submittals: F. Submit a horizontal directional drilling contingency plan and include a list of personnel to notify with emergency telephone numbers. The plan shall also include emergency contact information for other personnel, equipment, and materials needed but not maintained on the 1 Packet Page-829- - - 5/27/201416.0.2. project site. The contingency plan shall include the proposed measures employed for the condition when: 1. Spoils do not settle/separate with slurry separation equipment on site. 2. Drill steel/pipeline is unable to be advanced or retrieved with drill rig. 3. Drill tool lost in the hole. 4. The location control system fails to provide accurate information. Describe which operational parameters are observed/measured/recorded so that it can be determined if the above is occurring or has just occurred. 5. The installation forces start to move up rapidly and reasonable concern exists for completing construction. 6. A swivel breaks during carrier pipe installation.• 7. Inadvertent returns occur when under the crossing. Include measures to control turbidity and contain drilling fluid and surface returns in the waterway. 8. An inadvertent return occurs where slurry fails to return due to subsurface ground conditions, i.e., encountering a gravel bed that serves as an aquifer. 9. The pilot hole or ream intersects a subsurface interface and directional steering is unable to keep the drill path along the intended route. Describe which operational parameters are observed/measured/recorded so that it can be determined if the above is occurring or has just occurred. 10. Loss of directional steering information. Describe which operational parameters are observed/measured/recorded so that it can be determined if the above is occurring or has just occurred. 11. Loss of steering, inability to steer. Describe which operational parameters are observed/measured/recorded so that it can be determined if the above is occurring or has just occurred. ADD: the following to Specification Section 330523.13 Horizontal Directional Drilling: 3.7 ENVIRONMENTAL REQUIREMENTS A. Dispose of all drilling fluids and spoils in compliance with all relative environmental regulations, right-of-way and work space agreements, and permit requirements. B. The HDD operation shall be a closed loop slurry system maintained to eliminate the accidental discharge of water, drilling mud, or spoils. Provide equipment and procedures to maximize the recirculation of drilling mud and to minimize waste. C. All inadvertent returns to the surface shall be cleaned up upon discovery and before the end of the shift. The surface area shall be washed and returned to the original condition. If the amount of surface returns exceeds the capacity of the small sumps being used for 2 Packet Page -830- 5/27/2014 16.C.2. collecting and containing surface returns, drilling operations shall be discontinued. Drilling shall not resume until contingency plan is implemented. D. All construction-related activities involving fuels and lubricants, such as vehicle refueling and equipment maintenance including draining and pumping of lubricants, shall be conducted at a sufficient distance from the water channel to eliminate contamination in case of a spill. Double containment during fueling or greasing operations shall be implemented. E. Provide sanitation and garbage facilities on both sides of the crossing. Waste shall be collected and transported offsite for disposal. F. Damage to pond liner or bulging of the liner from inadvertent returns beneath the pond liner shall be repaired by Contractor at his expense. The work shall include at a minimum dewatering and isolating damaged area or bulge area with hydraulic dams, removal of the damaged or bulge portion of the liner, replacement of damage or bulge liner with a new 60 mil HDPE liner, spark test repair, and submit results to the County and the Engineer for approval. ADD the following to Specification Section 330502 High Density Polyethylene(HOPE) Pipe and Fittings, 3.2—Heat Fusion Joining: B. Use a data logging device with the pipe joining equipment to record fusion parameters of pressure,temperature, and time for each joint. If you require additional information contact me using the above contact information. cc: Wayne Karlovich, Project Manager Enc: 1 3 Packet Page -831- 5/27/2014 16.C.2. COLLIER COUNTY QUOTE NO. 08-5011-115 30" &24" FORCE MAIN PHASE 1 -SOUTH COUNTY WATER RECLAMATION FACILITY & MPS 306 Forcemain Phase Ill COLLIER COUNTY PUBLIC UTILITIES DIVISION Item Estimated No. Description Units Quantity Total 1 Perform all Contract Work described in the Contract Documents. — Lump Sum 417,333.00 2 Allowance Fund for Owners Use as Directed. This fund will be used only at the Owner's direction to accomplish work due to unforeseen conditions as specified in Section 01135. inclusion of the Allowance Fund as part of the Contract Price is not a — guarantee that the Contractor will be paid any portion or the full amount of the Allowance Fund. Lump Sum $55,000.00 TOTAL PRICE FOR ITEMS 1 AND 2 $ 472,333.00 Packet Page -832- 5/27/2014 16.C.2. QUOTE NO. 08-5011-115-30"&24"FORCE MAIN PHASE 1 -SOUTH COUNTY WATER RECLAMATION FACILITY &MPS 306 Forcemain Phase III (tern Estimated No. Description Units Quantity Total Total Total Total 1 Perform all Contract Work described in the Lump Sum $417,333.00 $660,000.00 $770,000.00 $486,420.00 Contract Documents. 2 Allowance Fund for Owners Use as Directed. This fund will be used only at the Owner's direction to accomplish work due to unforeseen conditions as specified in Section 01135. Inclusion of the Allowance Fund as part of the Contract Price is not a — guarantee that the Contractor will be paid any portion or the full amount of the Allowance Fund. Lump Sum $55,000.00 $55,000.00 $55,000.00 $55,000.00 $472,333.00 $715,000.00 $825,000.00 $541,420.00 Packet Page -833- 5/27/2014 16.C.2. ...._ - . ..- . , I 1 3: y'-, \ . , \ •• i A • t .... ■ sik •• -\ , ----5:--- - - _ ..- , -• - g -- 47+ >7 CL c: LLI Z =T: J_ • ' - - _ • - • 73 -`-7.E • I C ,13.1ri I •• I.... •,-: • C.^ (13 v 1 1 . ±: • - E -: • ' I L.. .0 ■ 4 - U. X -.. • "-- VD W y CD -,-. fel C c. 0 c„. ■••■ --u .4■1 (..) sa) 0 : n_ E rk,6- ,... _ - U • -,R fa U-I I . Z . ■ • . e • • c.. I * 4 • I I I •.. 1 I • .•:_- .= — .-- _ _ , ..„...- C) a..) = •— - -- C) E.) 7 0 13 0 cn N ca 0 m = - A .7'_. cn ■"," - 0L In -c";) .r ^ ci) = i 0 . L >•'' .,,, ,t -, 2 .2 - 0. 2 ■rrJ r■- Z., w Packet Page -834-