Agenda 03/25/2014 Item #16A16 3/25/2014 16.A.16. EXECUTIVE SUMMARY Recommendation to approve the short list of design professionals pursuant to RFP No. 14- 6190, "Golden Gate City Stormwater Drainage Improvement Project Engineering Design," Project Number 50129 and authorize staff to negotiate contracts with the top ranked firms for subsequent Board approval. OBJECTIVE: To obtain professional engineering services to upgrade the stormwater management system in Golden Gate City. CONSIDERATIONS: In 2010, Collier County Stormwater Section contracted for a Golden Gate City Stormwater System Inventory and Master Plan. This work inventoried the existing stormwater system and divided Golden Gate City into four quadrants of approximately one square mile each. Within these quadrants, the areas were further subdivided into sub-systems. The inventory analyzed the condition of the existing stormwater structures and pipes and made recommendations on a program to rehabilitate the existing stormwater system. Most of the system is more than 50 years old and has passed its useful lifespan and is now functionally obsolete. The Board of County Commissioners (Board) adopted the 2014 Capital Budget that identified the requirement for upgrading this stormwater system. This project is divided into a design component and a construction component. The design component is for an approximate ten (10) year time window at an approximate cost of$2 million. The construction component is a fifteen (15) to twenty (20) year time window at an approximate cost of $15 million. The individual designs will be done in stages so that there are several completed designs on the shelf at all times, shovel-ready for construction as construction funding becomes available. The designs will not become obsolete as there are no major permits required that can expire for the project. Also the engineering is based on a replacement design of the stormwater system that currently is in operation and will not become stale. A Request for Proposal (RFP) was solicited in order for the project's design to he in compliance with the applicable Consultants' Competitive Negotiations Act (CCNA) requirements. On November 20, 2013, RFP No. 14-6190, Golden Gate City Stormwater Drainage Improvement Project Engineering Design was posted. One thousand sin hundred and fifty (1.650) notices were sent out and seventy-eight (78) firms downloaded full document packages. Ten (10) responsive proposals were received on December 26, 2013. On February 5. 2013, a selection committee short-lisie our i,1) firms ias .d on an evaluatiGn their technical proposals. The selection commits e by consensus ranked the firms as shown eiow: Name of Firm Final Ranking Agnoli Barber and Brundage 1 Johnson Engineering � ----- ----- 2 CH2M Hill 3 RWA Consulting 4 Q. Grady Minor I 5 Hole Mantes 6 Packet Page -539- 3/25/2014 16.A.16. CDM Smith 7 Davidson Engineering 8 Conestoga Rovers 9 Decisive Pipeline 10 The top four firms are sufficiently familiar with the facilities and the scope of the project. They are qualified and have extensive experience both designing and inspecting projects similar to these facilities. Staff recommends approval of the final ranking and requests authorization to commence contract negotiations with the four highest ranked firms for this work. Additionally, the highest ranked firm will receive the work related to the quadrant of Golden Gate City that had the highest construction cost estimated value. The next highest firm will receive the work in the next quadrant that had the second highest value, and so on, for the remaining two firms. As such, Agnoli Barber and Brundage will design the Northwest Quadrant, Johnson Engineering will design the Northeast Quadrant, CH2M Hill will design the Southwest Quadrant, and RWA Consulting will design the Southeast Quadrant. RFP No. 14-6190 will provide professional engineering services to include a design phase, verification of equivalent capacity analysis phase, and post design services phase. The original Request for Proposal document is attached for reference of the detailed history and scope of the required professional services. FISCAL IMPACT: There is no fiscal impact at this time. Once negotiations are completed and approved, funding is available in the FY14 Capital budget to start the project. The source of funding for this project is a transfer from the Unincorporated General Fund 111 into the Stormwater Capital Projects Fund 325. The implementation of this multi-year project will be subject to funding availability. The replaced stormwater infrastructure will have a functional life span of fifty (50) years. The additional recurring cost for periodic inspection and cleaning of all the stormwater system on a three to five year basis is estimated to be $5,000 per cycle. LEGAL CONSIDERATIONS: This item has been reviewed by the County Attorney, is approved as to form and legality, and requires majority vote for approval. -JAK GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the viability of public facilities. RECOMMENDATION: To approve the short-list of RFP No, 14-6190 so that negotiations can begin with the four top-ranked firms. Following negotiations, this matter will be brought back to the Board to seek approval of the contracts with the selected design consultants. Prepared by: Joe Delate, PLA, Senior Project Manager, Transportation Engineering Department Attachments: (1) Request for Proposal; and (2) Final Ranking Packet Page-540- 3/25/2014 16.A.16. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.A.16.A.16. Item Summary: Recommendation to approve the short list of design professionals pursuant to RFP No. 14-6190, "Golden Gate City Stormwater Drainage Improvement Project Engineering Design," Project Number 50129 and authorize staff to negotiate contracts with the top ranked firms for subsequent Board approval. Meeting Date: 3/25/2014 Prepared By Name: DelateJoseph Title: Project Manager, Senior,Transportation Engineering&Construction Management 2/26/2014 3:03:54 PM Submitted by Title: Project Manager, Senior,Transportation Engineering&Construction Management Name: DelateJoseph 2/26/2014 3:03:55 PM Approved By Name: PutaansuuGary Title: Project Manager,Principal,Transportation Engineering&Construction Management Date: 2/27/2014 1:18:01 PM Name: TaylorLisa Title: Management/Budget Analyst,Transportation Administration Date: 2/27/2014 2:13:47 PM Name:AhmadJay Title: Director-Transportation Engineering,Transportation Engineering&Construction Management Date: 2/27/2014 2:58:02 PM Name: KearnsAllison Title: Manager Financial &Operational Support,Transportation Administration Date: 2/27/2014 4:48:45 PM Packet Page-541- 3/25/2014 16.A.16. Name: ShueGene Title: Director-Operations Support,Transportation Administration Date: 2/28/2014 8:54:45 AM Name: Evelyn Colon Title: Purchasing-Procurement Specialist Date: 2/28/2014 12:04:43 PM Name: LynchDiane Title: Supervisor-Operations,Road Maintenance Date: 2/28/2014 1:05:45 PM Name: JohnsonScott Title: Procurement Specialist,Purchasing&General Services Date: 3/1/2014 8:03:53 AM Name: MarkiewiczJoanne Title: Manager-Procurement, Purchasing&General Services Date: 3/4/2014 3:37:35 PM Name: TeachScott Title: Deputy County Attorney, County Attorney Date: 3/5/2014 11:39:18 AM Name: MarcellaJeanne Title: Executive Secretary, Transportation Planning Date: 3/11/2014 11:41:22 AM Name: KlatzkowJeff Title: County Attorney, Date: 3/14/2014 10:16:50 AM Name: UsherSusan Title: Management/Budget Analyst, Senior, Office of Management&Budget Date: 3/18/2014 1:57:27 PM Name: KlatzkowJeff Title: County Attorney, Date: 3/19/2014 9:17:14 AM Name: OchsLeo Title: County Manager, County Managers Office Date: 3/19/2014 11:13:20 AM Packet Page-542- 3/25/2014 16.A.16. Packet Page-543- 3/25/2014 16.A.16. REQUEST FOR PROPOSALS In accordance with Florida Statute 287.055, Consultants' Competitive Negotiation Act. Cliter COPLnty Administrative Services Division Purchasing COLLIER COUNTY BOARD OF COUNTY COMMISSIONERS CCNA Solicitation #14-6190 Golden Gate City Stormwater Drainage Improvement Project Engineering Design Evelyn Colon, Procurement Strategist 239-252-2667(Telephone) 239-252-2810(Fax) evelyncolon @colliergov.net(Email) This proposal solicitation document is prepared in a Microsoft Word format. Any alterations to this document made by the Consultant may be grounds for rejection of proposal, cancellation of any subsequent award, or any other legal remedies available to the Collier County Government. Purchasing Department.3327 Tamiami Trail East•Nap!es,Florida 34112-4901•wme.coliiergnv.net/purchasing CCNA(Revision 07012013) Packet Page-544- 3/25/2014 16.A.16. LEGAL NOTICE 3 EXHIBIT I: SCOPE OF WORK, SPECIFICATIONS AND RESPONSE FORMAT 4 EXHIBIT II: GENERAL RFP INSTRUCTIONS 13 EXHIBIT III: COLLIER COUNTY PURCHASE ORDER TERMS AND CONDITIONS 17 EXHIBIT IV: ADDITIONAL TERMS AND CONDITIONS FOR RFP 21 ATTACHMENT 1: CONSULTANT'S NON-RESPONSE STATEMENT 28 ATTACHMENT 2: CONSULTANT CHECK LIST 29 ATTACHMENT 3: CONFLICT OF INTEREST AFFIDAVIT 30 ATTACHMENT 4: CONSULTANT DECLARATION STATEMENT 31 ATTACHMENT 5: IMMIGRATION AFFIDAVIT CERTIFICATION 33 ATTACHMENT 6: CONSULTANT SUBSTITUTE W—9 34 ATTACHMENT 7: INSURANCE AND BONDING REQUIREMENTS 35 ATTACHMENT 8: REFERENCE QUESTIONNAIRE 37 #14-6190 npp_CCmATemp|ute 2 Packet Page -545- 3/25/2014 16.A.16. Colter County Administrative Services Division Purchasing Legal Notice Pursuant to approval by the County Manager, Sealed Proposals to provide Professional Engineering Design Services for Golden Gate City Stormwater Drainage Improvement Project Engineering Design will be received until 3:00 PM, Naples local time, on December 20th, 2013 at the Collier County Government, Purchasing Department, 3327 Tamiami Trail E, Naples, FL 34112. CCNA Solicitation # 14-6190 Golden Gate City Stormwater Drainage Improvement Project Engineering Design Services to be provided may include, but not be limited to the following: Develop the individual engineering designs for each quadrant and subsystem including, but not limited to, the following three (3) phases of work performed by the consultant: • Phase 1: Stormwater Replacement System Design • Phase 2: Equivalent Capacity Analysis • Phase 3: Post Design Services A non-mandatory pre-proposal conference will be held on December 4th, 2013, commencing promptly at 11:00 AM, and will be held in the Collier County Government, Purchasing Department, 3327 Tamiami Trail E, Naples, FL 34112 All statements should be made upon the official proposal form which must be obtained only on the Collier County Purchasing Department Online Bidding System website: vvww.collieroov.net/bid. Collier County does not discriminate based on age, race, color, sex, religion, national origin, disability or marital status. BOARD OF COUNTY COMMISSIONERS COLLIER COUNTY, FLORIDA, BY: /S/ Joanne Markiewicz Interim Purchasing & General Services Director This Public Notice was posted on the Collier County Purchasing Department website: www.colliercov.net/purchasinq and in the Lobby of Purchasing Building "G", Collier County Government Center on November 20th, 2013. #14-6190 RFP_CCNATemplate 3 Packet Page-546- 3/25/2014 16.A.16. Exhibit I: Scope of Work, Specifications and Response Format As requested by the Collier County Transportation Department (hereinafter, the "Department"), the Collier County Board of County Commissioners Purchasing Department (hereinafter, "County") has issued this Request for Proposal (hereinafter, "RFP") with the intent of obtaining proposals from interested and qualified Consultants in accordance with the terms, conditions and specifications stated or attached. The Consultant, at a minimum, must achieve the requirements of the Specifications or Scope of Work stated. The results of this solicitation may be used by other County departments once awarded according to the Board of County Commissioners Purchasing Policy. Brief Description of Purchase The selected consultant(s) shall perform comprehensive engineering designs of the County- owned stormwater system within the specified quadrant boundaries to establish the basis of design for system renovations. Upon completion of the comprehensive engineering designs, the selected consultant(s) will perform selective equivalent capacity analyses and construction- related support services. This solicitation anticipates the selection of four professional engineering firms to conduct the referenced professional services for four specific quadrant boundaries (one firm for each quadrant), namely, the following: 1) Northwest Golden Gate City; 2) Northeast Golden Gate City; 3) Southwest Golden Gate City; and 4) Southeast Golden Gate City. Assignment of each quadrant will be determined in order of final ranking, each firm will be assigned a quadrant according to size and scope complexity. Background In 2010, Collier County Transportation Division, Stormwater Department contracted for a Golden Gate City Stormwater System Inventory and Master Plan. This work inventoried the existing Stormwater facility and divided the four (4) square mile "City" (actually not a city, but part of Collier County) into four (4) quadrants of one (1) square mile each. These are the northwest, northeast, southwest and southeast quadrants, which are further divided by the Master Plan into subsystems. The Inventory analyzed the condition of the Stormwater structures and pipes. The Master Plan spelled out the orderly replacement of the existing Stormwater system with priorities for budget costs. No Stormwater modeling was done, as it was intended to be a rehabilitation/replacement program. The majority of the system is in fair to poor condition and is at the end of its useful life. Most of the existing underground piping is corrugated metal with concrete "pillbox" catch basins. The Transportation Engineering Department (TE) of the Growth Management Division has a program funded annually for the upgrading of the County's Stormwater System. The program areas are the four quadrants of Golden Gate City, which were originally constructed in the 1960's and are now functionally obsolete. Historically, TE's rehabilitation approach was to focus on critical facilities, upgrading the "worst first." The TE Department has identified a hierarchy of areas needing rehabilitation known as subsystems. In order to effectively and efficiently design rehabilitation projects, TE has decided #14-6190 RFP_CCNATemplate 4 Packet Page-547- 3/25/2014 16.A.16. to follow this hierarchy and design the projects based on condition relative to other County projects and adequate funding. Initially this program will focus on the improvements design and then the construction phases. Detailed Scope of Work The County is interested in contracting with the most qualified firms to design and implement the Work Program for the four initial distinct quadrants. Each subsystem within the individual quadrant shall include three general phases of work (as described below), and the contract will not be completed until the County has accepted final construction completion on each geographical area (quadrant). The work will include engineering design of the stormwater system and also may include surveying, lighting, sidewalks, and roadway improvements. The County reserves the right to select one (1), two (2) three (3) or four (4) firms to perform and coordinate all work in the geographical areas. Should the County decide to hire multiple consulting firms, it is expected that the selected firms will work cooperatively with the other firms to provide best value services to the Growth Management Division and will share "lessons learned" for the benefit of the County's taxpayers. Phase 1: Stormwater Replacement System Design The selected Consultant shall design the rehabilitation program, assist with bid process and recommend a Construction Contractor to execute the program within the quadrant; and • Prepare bid/quote documents for stormwater subsystem renovations; and • Observe and provide oversight. The following Phases are included as part of the scope of work. Phase 1.1 — Design Phase a. On the basis of the accepted Master Plan layout, Consultant will prepare preliminary and final drawings and specifications which provide the general scope, extent and character of the work to be furnished and performed by the Contractor. Consultant will prepare and submit drawings and specifications at the 60 and 100 percent complete stages for review and approval. An engineer's opinion of probable construction cost will accompany each submittal. Technical specifications will be based on the 16-Division format of the Construction Specifications Institute (CSI) in MS Word format. In addition to technical specifications, the selected Consultant will coordinate with County to develop necessary General Conditions, Supplemental Conditions, and Special Provisions Specifications will be developed specifically for the project being constructed. Standard Collier County Specifications may be used for reference but the selected Consultant shall not rely on them as a replacement for sound engineering judgment and responsibility. Documents shall include drawings and project specifications ready for bidding, consistent with Collier County standards, including the following: 1) Cover sheet, index and key map 2) Civil Site Plan #14-6190 RFP_CCNATemplate 5 Packet Page-548- 3/25/2014 16.A.16. 3) Civil Details b. Furnish copies of Contract Documents that include engineering drawings and specifications. Present and review them in person with the County at the 60 percent completion stage in the project and make appropriate changes. Phase 1.2 — Bidding and Award Phase (IF APPLICABLE) With the exception of the following, bid/quote services will be performed by the Collier County Purchasing Department. Consultant will assist the County with the following: a. Assist in preparing addenda, as required, to interpret, clarify, or expand the Bidding Documents. b. Consult with and advise the County as to the acceptability of the contractor and subcontractors, suppliers and other persons and organizations proposed by the Prime Contractor for those portions of the work as to which such acceptability is required by the Bidding Documents. c. Consult with the County concerning and determine the acceptability of substitute material and equipment proposed by the Contractor when substitution prior to the award of contracts is allowed by the Bidding Documents. d. Conduct a pre-bid/quote conference. e. Attend the bid opening, review bids, qualifications. f. Provide a recommendation of award. Phase 2: Equivalent Capacity Analysis Phase 2.1 —Verification of Equivalent Capacity In areas where existing easements do not provide adequate space between and adjacent to existing homes, the County may elect to facilitate rehabilitation of the stormwater piping system using an on-call contractor. This on-call contractor is able to clean, TV, and analyze the existing piping to determine its condition and whether it should be lined or repaired. This contractor is required to provide calculations that support the equivalent capacity of the piping. At that time, the County will require verification that the pipe to be lined meets the equivalent capacity of the existing pipe. This verification and analysis will be performed by the selected Consultant for that quadrant of the project. Phase 3— Post Design Services The selected Consultant shall be selectively involved in the construction process and shall interface with the County Construction Inspector and Project Manager. Phase 3.1 — Construction Observation and Documentation The selected Consultant (or activity observer) will provide the services outlined below. #14-6190 RFP CCNATemplate 6 Packet Page-549- 3/25/2014 16.A.16. Phase 3.2—Construction Progress Meetings The selected Consultant will attend on as-needed basis at the discretion of the County. Phase 3.3—Substantial Completion Inspections The selected Consultant will conduct substantial completion inspections when requested by the Construction Contractor, and the selected Consultant recommends that the work is sufficiently complete to warrant a substantial completion inspection. During the substantial completion inspection, the County's Construction Inspector will prepare a punch list of items requiring completion or correction to the satisfaction of the selected Consultant and the Project Manager. The County's Construction Inspector will be responsible for maintaining the punch list and issuing updates to the punch list on a weekly basis. The County's Construction Inspector will coordinate and participate in the final walk-through to ensure that the punch list items are completed to the satisfaction of the selected Consultant and the Project Manager. Phase 3.4— Final Completion Inspection Upon the request of the Construction Contractor and concurrence of the selected Consultant and the Project Manager, the County Construction Inspector will conduct final inspections of portions of the project as they are finished to determine if construction has been completed in accordance with the Contract Documents and the Construction Contractor has fulfilled all obligations therein. Based on the results of the final inspection, the selected Consultant, Project Manager, and the County Construction Inspector will judge the work complete or not complete. If the work is judged complete, the County Construction Inspector will issue a "notice of final acceptance and recommendation for final payment". If the work is judged not complete, the County Construction Inspector will issue written instructions to the Construction Contractor identifying the work judged not complete. Upon provision of evidence or assurance by the Construction Contractor that the deficiencies noted above have been corrected or completed, a second final inspection will be scheduled to verify that the outstanding issues have been resolved and the County Construction Inspector can issue a "notice of final acceptance and recommendation for final payment". All services related to the Final Completion Inspection shall be provided to the Project Manager of the Project. Phase 3.5— Final Construction Certification Upon issuance of a "notice of final acceptance and recommendation for final payment" the County Construction Inspector will request a signed and sealed certification by a licensed professional in responsible charge of the work, stating that the "Project has been completed by the Construction Contractor in accordance with the Plans and Specifications of the Contract Documents as amended by the Engineer of Record." All services related to the Final Construction Certification shall be provided to the Project Manager of the Project. Phase 3.6—Construction and Project Oversight 3.6.1. General Management and Oversight — The selected Consultant will provide support services customarily related to the construction of similar projects including, but not limited to: #14-6190 RFP_CCNATemplate 7 Packet Page-550- 3/25/2014 16.A.16. a. Participate in a pre-construction meeting with the Project Manager, selected Consultant, and the General Contractor. b. Participate in other meetings as described or implied herein on an as-needed basis. 3.6.2. Coordination of Shop Drawings, Contract Interpretations and Clarifications — The County Construction Inspector will coordinate with the selected Consultant regarding the issuance of interpretations and clarifications of Contract Documents during construction. The selected Consultant shall be responsible for technical review and decisions regarding interpretation and clarification of Contract Documents. The County Construction Inspector shall coordinate the selected Consultant's decisions and responses with the Construction Contractor. 3.6.3. As Constructed Field Drawings — The Construction Contractor shall maintain red pencil "mark-up" notations and sketches on full size construction plans that reflect the actual details of constructed facilities. These Constructed Field Drawings will be used by the County Construction Inspector to validate the "As Built" documentation provided by the Construction Contractor. The selected Consultant will review and approve the final "As-built" documents. Phase 3.7—Additional Services 3.7.1. Additional Services (only as authorized in writing) — in accordance with the contract or purchase order, in the event that other services may arise during the course of the work, but were not envisioned as part of the original or amended scope of work; selected Consultant shall submit a proposal to perform Additional Services prior to the performance of the work. The proposal shall include the specific services to be performed, time to complete, compensation, and an explanation as to why the services were not previously envisioned as part of the scope of work. The proposed Additional Services must be approved by the Project Manager in writing in advance of performance of said Additional Services. Failure to notify the Project Manager in writing of Additional Services shall be deemed a waiver of any claim by the selected Consultant that such services were Additional Services. Written authorization from the Project Manager will be required for any charges that exceed the predetermined upper limit. Term of Contract The term of this contract shall be for sixty (60) days following the final acceptance of the construction project associated with this agreement and no longer than fifteen (15) years, unless prior approval by the Board of County Commissioners. Surcharges will not be accepted in conjunction with this contract, and such charges should be incorporated into the pricing structure. The prices quoted on the Contractor's Proposal shall remain in effect for a period of five (5) years from the date of award by the Board of County Commissioners. Subsequently, at the discretion of the County and upon the written request of the Contractor at least thirty (30) days in advance, all prices may be adjusted on the anniversary date of the Agreement, based on the Consumer Price Index-South Region. #14-6190 RFP_CCNATemplate 8 Packet Page -551- 3/25/2014 16.A.16. Projected Solicitation Timetable The following projected timetable should be used as a working guide for planning purposes only. The County reserves the right to adjust this timetable as required during the course of the RFP process. Event Date Issue Solicitation Notice November 20, 2013 Last Date for Receipt of Written Questions December 10, 2013 @ 3:00 PM Non-mandatory pre-solicitation meeting December 4, 2013 @ 11:00 AM Addendum Issued Resulting from Written Questions or Pre-Proposal December 13, 2013 Conference Solicitation Deadline Date and Time December 20, 2013 @ 3:00 PM Anticipated Evaluation of Submittals January 2014 Anticipated Completion of Contract Negotiations February 2014 Anticipated Board of County Commissioner's Contract Approval Date March 2014 Response Format The Consultant understands and agrees to abide by all of the RFP specifications, provisions, terms and conditions of same, and all ordinances and policies of Collier County. The Consultant further agrees that if the contract is awarded the work will be performed in accordance with the provisions, terms and conditions of the contract. To facilitate the fair evaluation and comparison of proposals, all proposals must conform to the guidelines set forth in this RFP. Any portions of the proposal that do not comply with these guidelines must be so noted and explained in the Acceptance of Conditions section of the proposal. However, any proposal that contains such variances may be considered non-responsive. Proposals should be prepared simply and economically, providing a straightforward concise description of the Consultant's approach and ability to meet the County's needs, as stated in the RFP. All proposals should be presented as described in the RFP in PDF or Microsoft Word format with Tabs clearly marked. If applicable, the utilization of recycled paper for proposal submission is strongly encouraged. The items listed below are to be submitted with each proposal and submitted in the order shown. Each section should be clearly labeled, with pages numbered and separated by tabs. Failure by a Consultant to include all listed items may result in the rejection of its proposal. 1. Tab I, Cover Letter/ Management Summary In this tab, include: #14-6190 RFP_CCNATemplate 9 Packet Page-552- 3/25/2014 16.A.16. • In no more than two pages (executive summary), briefly describe the overall project approach and the firm's experience in providing the requested services as identified in this RFP. 2. Tab II, Project Understanding Approach (45 Points) In this tab, include: • Project Understanding - Describe the background of the project and the local circumstances driving the need for this program. • Key Issues - Describe the key issues anticipated for this project and summarize your approach to them and your experience dealing with similar issues on other projects. • Overall Approach - Present an overview of the your project approach and map the program process from beginning to end, including building public trust and maintaining public communications throughout the project. • Technical Approach - Provide a detailed step-by-step description of how you will work through this program development process. • Areas Requiring Special Consideration - Highlight how you will address project areas of broad importance to Collier County and its stakeholders. • Staffing and Location of Work - Show the depth of the team's resources and where the project will be managed. • Program Timeline - Describe the firm's timeline for completing the three phases of work in the Project. • Representative Projects - Provide a sample of a work product that is of similar nature to the County's scope of work contained in this RFP. 3. Tab III, Technical Team (35 Points) In this tab, include: • Provide an Organizational Chart of the Project Team (excluding Collier County staff) including subconsultants. • Provide Team Member Profiles - Provide resumes for all of the full time staff members assigned to the Collier County Golden Gate City Stormwater Drainage Improvement Project Engineering Design for all of the three phases of work; identify the specific staff assigned to each of the phases. • Provide the percentage of subconsultant percentages expected to use for the three phases and describe the discipline/work. 4. Tab IV, Location, Availability and Responsiveness (10 Points) The selected Consultant(s) will be required to interface with the Transportation Engineering staff on a daily or more frequent basis. Collier County has concluded that selecting a local (Collier and Lee Counties) consultant 1) is in its best interest to contain costs, 2) minimizes Phase completion time frames, and 3) results in higher quality of professional services due to their knowledge and understanding of local geography and topology. Illustrate how available and how responsive the selected Consultant's team members will be for this program. Firms having a local office (Collier and Lee Counties) will receive the maximum number of points (10). Firms having office their office located within 75 miles of the Collier #14-6190 RFP_CCNATemplate 10 Packet Page-553- 3/25/2014 16.A.16. County Government complex will receive 5 points. Firms having an office beyond 75 miles will not receive any points under this category. 5. Tab V, References—Completed and Returned (10 Points) In order for the Consultant to be awarded any points for this tab, the County requests that the Consultant submit five (5) completed reference forms from clients whose projects are of a similar nature to this solicitation as a part of their proposal. The County will only use the methodology calculations for the first five (5) references (only) submitted by the Consultant in their proposal. Prior to the Selection Committee reviewing proposals, the following methodology will be applied to each Consultant's information provided in this area: • The County will total each of the Consultant's five reference questionnaires and create a ranking from highest number of points to lowest number of points. References marked with an N/A (or similar notation will be given the score of zero (0)). Consultants who do not turn in reference forms will be counted as zero (0). • The greatest number of points allowed in this criterion will be awarded to the Consultant who has the highest score. • The next highest Consultant's number of points will be divided by the highest Consultant's points which will then be multiplied by criteria points to determine the Consultant's points awarded. Each subsequent Consultant's point score will be calculated in the same manner. • Points awarded will be extended to the whole number per Microsoft Excel. For illustrative purposes only, see chart for an example of how these points would be distributed among the five proposers. Consultant Total Consultant Name Points Awarded Reference Score Consultant ABC 445 20 Consultant DEF 435 19.6 Consultant GHI 425 19.1 Consultant JKL 385 17.3 Consultant MNO 385 17.3 Consultant PQR 250 11.2 Note:Sample chart reflects a 20 point reference criterion. The points awarded by Consultant will be distributed to the Selection Committee prior to their evaluation of the proposals. The Selection Committee will review the Consultant's proposal to ensure consistency and completion of all Phases in the RFP, and review the Points Awarded per Consultant. The Selection Committee may, at their sole discretion, contact references, and/or modify the reference points assigned after a thorough review of the proposal and prior to final ranking by the final Selection Committee. 6. Tab VI, Acceptance of Conditions #14-6190 RFP_CCNATemplate 11 Packet Page-554- 3/25/2014 16.A.16. Indicate any exceptions to the general terms and conditions of the RFP, and to insurance requirements or any other requirements listed in the RFP. If no exceptions are indicated in this tabbed section, it will be understood that no exceptions to these documents will be considered after the award, or if applicable, during negotiations. Exceptions taken by a Consultant may result in evaluation point deduction(s) and/or exclusion of proposal for Selection Committee consideration, depending on the extent of the exception(s). Such determination shall be at the sole discretion of the County and Selection Committee. 7. Tab VII, Required Form Submittals • Attachment 1: Consultant's Non-Response Statement • Attachment 2: Consultant Checklist • Attachment 3: Conflict of Interest Affidavit • Attachment 4: Consultant Declaration Form' • Attachment 5: Immigration Affidavit and company's E-Verify profile page and memorandum of understanding • Attachment 6: Consultant Substitute W-9 • Attachment 7: Insurance Requirements • Attachment 8: Reference Questionnaire • Other: License, Informational Materials, Signed Addenda #14-6190 RFP_CCNATemplate 12 Packet Page-555- 3/25/2014 16.A.16. Exhibit II: General RFP Instructions 1. Questions Direct questions related to this RFP to the Collier County Purchasing Department Online Bidding System website: www.colliergov.net/bid. Consultants must clearly understand that the only official answer or position of the County will be the one stated on the Collier County Purchasing Department Online Bidding System website. For general questions, please call the referenced Procurement Strategist noted on the cover page. 2. Pre-Proposal Conference The purpose of the pre-proposal conference is to allow an open forum for discussion and questioning with County staff regarding the RFP with all prospective Consultants having an equal opportunity to hear and participate. Oral questions will receive oral responses, neither of which will be official, nor become part of the RFP. Only written responses to written questions will be considered official, and will be included as part of the RFP as an addendum. All prospective Consultants are strongly encouraged to attend, as, this will usually be the only pre-proposal conference for this solicitation. If this pre-proposal conference is denoted as "mandatory", prospective Consultants must be present in order to submit a proposal response. 3. Compliance with the RFP Proposals must be in strict compliance with this RFP. Failure to comply with all provisions of the RFP may result in disqualification. 4. Ambiguity, Conflict, or Other Errors in the RFP It is the sole responsibility of the Consultant if the Consultant discovers any ambiguity, conflict, discrepancy, omission or other error in the RFP, to immediately notify the Procurement Strategist, noted herein, of such error in writing and request modification or clarification of the document prior to submitting the proposal. The Procurement Strategist will make modifications by issuing a written revision and will give written notice to all parties who have received this RFP from the Purchasing Department. 5. Proposal, Presentation, and Protest Costs The County will not be liable in any way for any costs incurred by any Consultant in the preparation of its proposal in response to this RFP, nor for the presentation of its proposal and/or participation in any discussions, negotiations, or, if applicable, any protest procedures. #14-6190 RFP_CCNATemplate 13 Packet Page-556- 3/25/2014 16.A.16. 6. Delivery of Proposals All proposals are to be delivered before 3:00PM, Naples local time, on or before December 20th, 2013 to: Collier County Government Purchasing Department 3327 Tamiami Trail E Naples FL 34112 Attn: Evelyn Colon, Procurement Strategist The County does not bear the responsibility for proposals delivered to the Purchasing Department past the stated date and/or time indicated, or to an incorrect address by Consultant's personnel or by the Consultant's outside carrier. However, the Purchasing/General Services Director, or designee, reserves the right to accept proposals received after the posted close time under the following conditions: • The tardy submission of the proposal is due to the following circumstances, which may include but not be limited to: late delivery by commercial carrier such as Fed Ex, UPS or courier where delivery was scheduled before the deadline. • The acceptance of said proposal does not afford any competing firm an unfair advantage in the selection process. Consultants must submit two (2) paper copy clearly labeled "Master," and six (6) compact disks (CD's) with one copy of the proposal on each CD in Word, Excel or PDF. List the Solicitation Number and Title on the outside of the box or envelope. 7. Validity of Proposals No proposal can be withdrawn after it is filed unless the Consultant makes their request in writing to the County prior to the time set for the closing of Proposals. All proposals shall be valid for a period of one hundred eighty (180) days from the submission date to accommodate evaluation and selection process. 8. Method of Source Selection The County is using the Competitive Sealed Proposals methodology of source selection for this procurement, as authorized by Ordinance Number 87-25, and Collier County Resolution Number 2007-340 establishing and adopting the Collier County Purchasing Policy. If the County receives proposals from less than three (3) firms, the Purchasing Director shall review all the facts and determine if it is in the best interest of the County to solicit additional proposals or request that the Selection Committee rank order the received proposals. The County may, as it deems necessary, conduct discussions with qualified Consultants determined to be in contention for being selected for award for the purpose of clarification to assure full understanding of, and responsiveness to solicitation requirements. #14-6190 RFP_CCNATemplate 14 Packet Page-557- 3/25/2014 16.A.16. 9. Evaluation of Proposals Collier County will evaluate and select these Services in accordance with Florida Statute 287.055, Consultants' Competitive Negotiation Act. The County's procedure for selecting is as follows: 1. The County Manager or designee shall appoint a Selection Committee to review all proposals submitted. 2. Request for Proposals issued. 3. Subsequent to the closing of proposals, the Procurement Strategist will review the proposals received and verify whether each proposal appears to be minimally responsive to the requirements of the published RFP. 4. Meetings will be open to the public and the Procurement Strategist will publicly post prior notice of such meeting in the lobby of the Purchasing Building. 5. The committee members will review each Proposal individually and score each proposal based on the evaluation criteria stated herein. 6. Prior to the first meeting of the selection committee, the Procurement Strategist will post a notice announcing the date, time and place of the first committee meeting. Said notice will be posted in the lobby of the Purchasing Building not less than three (3) working days prior to the meeting. The Procurement Strategist will also post prior notice of all subsequent committee meetings and will endeavor to post such notices at least one (1) day in advance of all subsequent meetings. 7. Collier County will consider all the material submitted by the Proposer and other information Collier County may obtain to determine whether the Proposer is capable of and has a history of successfully completing projects of this type, including, without limitation, additional information Collier County may request, interviews, or oral presentations. 8. The Selection Committee, as approved by the County Manager or designee, will review, evaluate and rank all responsive proposals received from Proposers responding to this RFP. The committee members will score each Proposal in accordance with the rating criteria set forth below and may, at their discretion, schedule presentations from any firms submitting a proposal. Consultant(s) shall have an opportunity to discuss their qualifications, approach to the project and ability to furnish services for the scope of work outlined in this solicitation during the publicly announced Selection Committee Meeting prior to the final ranking. This discussion does not preclude the County from having additional presentations by ranked firms at the County's sole discretion. 9. The Selection Committee will rank qualified firms in order of preference and by consensus using all information presented to the Committee, choose the top ranked firm and will subsequently enter into negotiations with the top ranked firm. Award of the contract is dependent upon the successful and full execution of a mutually agreed contract. 10. Negotiations shall begin with the top-ranked firm(s) in accordance with Florida Statute 287.055. 11. Upon the successful completion of negotiations, contracts will be presented to the Board of County Commissioners for approval. The County reserves the right to withdraw this RFP at any time and for any reason, and to issue such clarifications, modifications, addendums, and/or amendments as it may #14-6190 RFP_CCNATemplate 15 Packet Page-558- 3/25/2014 16.A.16. deem appropriate, including, but not limited, to requesting supplemental proposal information. Receipt of a proposal by the County or a submission of a proposal to the County offers no rights upon the Consultant nor obligates the County in any manner. Acceptance of the proposal does not guarantee issuance of any other governmental approvals. Proposals which include provisions requiring the granting of zoning variances may not be considered. 10. References The County reserves the right to contact any and all references submitted as a result of this solicitation. 11. Proposal Selection Committee and Evaluation Factors The County Manager or designee will appoint a Selection Committee to review all proposals submitted. The factors to be considered in the evaluation of proposal responses are listed below. Tab II, Project Understanding Approach 45 Tab III, Technical Team 35 Tab IV, Location, Availability and Responsiveness 10 Tab V, References 10 TOTAL 100 Points Tie Breaker: In the event of a tie, both in individual scoring and in final ranking, the firm with the lowest paid dollars by Collier County to the Consultant (as obtained from the County's financial system) within the last five (5) years will receive the higher individual ranking. This information will be based on information provided by the Consultant, subject to verification at the County's option. If there is a multiple firm tie in either individual scoring or final ranking, the firm with the lowest volume of work shall receive the higher ranking, the firm with the next lowest volume of work shall receive the next highest ranking and so on. 12. Acceptance or Rejection of Proposals The right is reserved by the County to waive any irregularities in any proposal, to reject any or all proposals, to re-solicit for proposals, if desired, and upon recommendation and justification by Collier County to accept the proposal which in the judgment of the County is deemed the most advantageous for the public and Collier County. Any proposal which is incomplete, conditional, obscure or which contains irregularities of any kind, may be cause for rejection. In the event of default of the successful Consultant, or their refusal to enter into the Collier County contract, the County reserves the right to accept the proposal of any other Consultant or to re-advertise using the same or revised documentation, at its sole discretion. #14-6190 RFP_CCNATemplate 16 Packet Page-559- 3/25/2014 16.A.16. Exhibit Ill: Collier County Purchase Order Terms and Conditions 1. Offer a) All goods are FOB destination and must This offer is subject to cancellation by the be suitably packed and prepared to COUNTY without notice if not accepted by secure the lowest transportation rates CONSULTANT within fourteen (14) days of and to comply with all carrier issuance. regulations. Risk of loss of any goods sold hereunder shall transfer to the 2. Acceptance and Confirmation COUNTY at the time and place of This Purchase Order (including all delivery; provided that risk of loss prior documents attached to or referenced to actual receipt of the goods by the therein) constitutes the entire agreement COUNTY nonetheless remain with between the parties, unless otherwise CONSULTANT. specifically noted by the COUNTY on the b) No charges will be paid by the COUNTY face of this Purchase Order. Each delivery for packing, crating or cartage unless of goods and/or services received by the otherwise specifically stated in this COUNTY from CONSULTANT shall be Purchase Order. Unless otherwise deemed to be upon the terms and conditions provided in Purchase Order, no invoices contained in this Purchase Order. shall be issued nor payments made prior to delivery. Unless freight and No additional terms may be added and other charges are itemized, any Purchase Order may not be changed except discount will be taken on the full amount by written instrument executed by the of invoice. COUNTY. CONSULTANT is deemed to be c) All shipments of goods scheduled on the on notice that the COUNTY objects to any same day via the same route must be additional or different terms and conditions consolidated. Each shipping container contained in any acknowledgment, invoice must be consecutively numbered and or other communication from marked to show this Purchase Order CONSULTANT, notwithstanding the number. The container and Purchase COUNTY'S acceptance or payment for any Order numbers must be indicated on bill delivery of goods and/or services, or any of lading. Packing slips must show similar act by CONSULTANT. Purchase Order number and must be included on each package of less than 3. Inspection container load (LCL) shipments and/or All goods and/or services delivered with each car load of equipment. The hereunder shall be received subject to the COUNTY reserves the right to refuse or COUNTY'S inspection and approval and return any shipment or equipment at payment therefore shall not constitute CONSULTANT'S expense that is not acceptance. All payments are subject to marked with Purchase Order numbers. adjustment for shortage or rejection. All CONSULTANT agrees to declare to the defective or nonconforming goods will be carrier the value of any shipment made returned pursuant to CONSULTANT'S under this Purchase Order and the full instruction at CONSULTANT'S expense. invoice value of such shipment. d) All invoices must contain the Purchase To the extent that a purchase order requires Order number and any other specific a series of performances by CONSULTANT, information as identified on the the COUNTY prospectively reserves the Purchase Order. Discounts of prompt right to cancel the entire remainder of the payment will be computed from the date Purchase Order if goods and/or services of receipt of goods or from date of provided early in the term of the Purchase receipt of invoices, whichever is later. Order are non-conforming or otherwise Payment will be made upon receipt of a rejected by the COUNTY. proper invoice and in compliance with Chapter 218, Fla. Stats., otherwise 4. Shipping and Invoices known as the "Local Government Prompt Payment Act," and, pursuant to #14-6190 RFP_CCNATemplate 17 Packet Page-560- 3/25/2014 16.A.16. the Board of County Commissioners Purchasing Policy. 8. Statutory Conformity 5. Time Is Of the Essence Goods and services provided pursuant to Time for delivery of goods or performance of this Purchase Order, and their production services under this Purchase Order is of the and transportation shall conform to all essence. Failure of CONSULTANT to meet applicable laws, including but not limited to delivery schedules or deliver within a the Occupational Health and Safety Act, the reasonable time, as interpreted by the Federal Transportation Act and the Fair COUNTY in its sole judgment, shall entitle Labor Standards Act, as well as any law or the COUNTY to seek all remedies available regulation noted on the face of the Purchase to it at law or in equity. CONSULTANT Order. agrees to reimburse the COUNTY for any expenses incurred in enforcing its rights. 9. Advertising CONSULTANT further agrees that No CONSULTANT providing goods and undiscovered delivery of nonconforming services to the COUNTY shall advertise the goods and/or services is not a waiver of the fact that it has contracted with the COUNTY COUNTY'S right to insist upon further for goods and/or services, or appropriate or compliance with all specifications. make use of the COUNTY'S name or other identifying marks or property without the 6. Changes prior written consent of the COUNTY'S The COUNTY may at any time and by Purchasing Department. written notice make changes to drawings and specifications, shipping instructions, 10. Indemnification quantities and delivery schedules within the CONSULTANT shall indemnify and hold general scope of this Purchase Order. harmless the COUNTY from any and all Should any such change increase or claims, including claims of negligence, costs decrease the cost of, or the time required for and expenses, including but not limited to performance of the Purchase Order, an attorneys' fees, arising from, caused by or equitable adjustment in the price and/or related to the injury or death of any person delivery schedule will be negotiated by the (including but not limited to employees and COUNTY and CONSULTANT. agents of CONSULTANT in the performance Notwithstanding the foregoing, of their duties or otherwise), or damage to CONSULTANT has an affirmative obligation property (including property of the COUNTY to give notice if the changes will decrease or other persons), which arise out of or are costs. Any claims for adjustment by incident to the goods and/or services to be CONSULTANT must be made within thirty provided hereunder. (30) days from the date the change is ordered or within such additional period of 11. Warranty of Non-Infringement time as may be agreed upon by the parties. CONSULTANT represents and warrants that all goods sold or services performed under 7. Warranties this Purchase Order are: a) in compliance CONSULTANT expressly warrants that the with applicable laws; b) do not infringe any goods and/or services covered by this patent, trademark, copyright or trade secret; Purchase Order will conform to the and c) do not constitute unfair competition. specifications, drawings, samples or other descriptions furnished or specified by the CONSULTANT shall indemnify and hold COUNTY, and will be of satisfactory material harmless the COUNTY from and against and quality production, free from defects and any and all claims, including claims of sufficient for the purpose intended. Goods negligence, costs and expense, including shall be delivered free from any security but not limited to attorneys' fees, which arise interest or other lien, encumbrance or claim from any claim, suit or proceeding alleging of any third party. These warranties shall that the COUNTY'S use of the goods and/or survive inspection, acceptance, passage of services provided under this Purchase Order title and payment by the COUNTY. are inconsistent with CONSULTANT'S #14-6190 RFP_CCNATemplate 18 Packet Page-561- 3/25/2014 16.A.16. representations and warranties in section 11 14. Force Majeure (a). Neither the COUNTY nor CONSULTANT shall be responsible for any delay or failure If any claim which arises from in performance resulting from any cause CONSULTANT'S breach of section 11 (a) beyond their control, including, but without has occurred, or is likely to occur, limitation to war, strikes, civil disturbances CONSULTANT may, at the COUNTY'S and acts of nature. When CONSULTANT option, procure for the COUNTY the right to has knowledge of any actual or potential continue using the goods or services, or force majeure or other conditions which will replace or modify the goods or services so delay or threatens to delay timely that they become non-infringing, (without performance of this Purchase Order, any material degradation in performance, CONSULTANT shall immediately give notice quality, functionality or additional cost to the thereof, including all relevant information COUNTY). with respects to what steps CONSULTANT is taking to complete delivery of the goods 12. Insurance Requirements and/or services to the COUNTY. The CONSULTANT, at its sole expense, shall provide commercial insurance of such 15. Assignment type and with such terms and limits as may CONSULTANT may not assign this be reasonably associated with the Purchase Purchase Order, nor any money due or to Order. Providing and maintaining adequate become due without the prior written insurance coverage is a material obligation consent of the COUNTY. Any assignment of the CONSULTANT. All insurance policies made without such consent shall be deemed shall be executed through insurers void. authorized or eligible to write policies in the State of Florida. 16. Taxes Goods and services procured subject to this 13. Compliance with Laws Purchase Order are exempt from Florida In fulfilling the terms of this Purchase Order, sales and use tax on real property, transient CONSULTANT agrees that it will comply rental property rented, tangible personal with all federal, state, and local laws, rules, purchased or rented, or services purchased codes, and ordinances that are applicable to (Florida Statutes, Chapter 212), and from the conduct of its business. By way of non- federal excise tax. exhaustive example, this shall include the American with Disabilities Act and all 17. Annual Appropriations prohibitions against discrimination on the The COUNTY'S performance and obligation basis of race, religion, sex creed, national to pay under this Purchase Order shall be origin, handicap, marital status, or veterans' contingent upon an annual appropriation of status. Further, CONSULTANT funds. acknowledges and without exception or stipulation shall be fully responsible for 18. Termination complying with the provisions of the This Purchase Order may be terminated at Immigration Reform and Control Act of 1986 any time by the COUNTY upon 30 days as located at 8 U.S.C. 1324, et seq. and prior written notice to the CONSULTANT. regulations relating thereto, as either may be This Purchase Order may be terminated amended. Failure by the awarded firm(s) to immediately by the COUNTY for breach by comply with the laws referenced herein shall CONSULTANT of the terms and conditions constitute a breach of the award agreement of this Purchase Order, provided that and the County shall have the discretion to COUNTY has provided CONSULTANT with unilaterally terminate said agreement notice of such breach and CONSULTANT immediately. Any breach of this provision has failed to cure within 10 days of receipt of may be regarded by the COUNTY as a such notice. material and substantial breach of the contract arising from this Purchase Order. 19. General #14-6190 RFP_CCNATemplate 19 Packet Page-562- 3/25/2014 16.A.16. a) This Purchase Order shall be governed for notice by written notice complying by the laws of the State of Florida. The with the requirements of this section. venue for any action brought to d) The CONSULTANT agrees to specifically enforce any of the terms and reimbursement of any travel expenses conditions of this Purchase Order shall that may be associated with this be the Twentieth Judicial Circuit in and Purchase Order in accordance with for Collier County, Florida Florida Statute Chapter 112.061, Per b) Failure of the COUNTY to act Diem and Travel Expenses for Public immediately in response to a breach of Officers, employees and authorized this Purchase Order by CONSULTANT persons. shall not constitute a waiver of breach. e) In the event of any conflict between or Waiver of the COUNTY by any default among the terms of any Contract by CONSULTANT hereunder shall not Documents related to this Purchase be deemed a waiver of any subsequent Order, the terms of the Contract default by CONSULTANT. Documents shall take precedence over c) All notices under this Purchase Order the terms of the Purchase Order. To the shall be sent to the respective extent any terms and /or conditions of addresses on the face page by certified this Purchase Order duplicate or overlap mail, return receipt requested, by the Terms and Conditions of the overnight courier service, or by personal Contract Documents, the provisions of delivery and will be deemed effective the Terms and/or Conditions that are upon receipt. Postage, delivery and most favorable to the County and/or other charges shall be paid by the provide the greatest protection to the sender. A party may change its address County shall govern. #14-6190 RFP_CCNATemplate 20 Packet Page-563- Exhibit IV: Additional Terms and Conditions for RFP 3/25/2014 16.A.16. 1. Insurance and Bonding Requirements The Consultant shall at its own expense, carry and maintain insurance coverage from responsible companies duly authorized to do business in the State of Florida as set forth in the Insurance and Bonding attachment of this solicitation. The Consultant shall procure and maintain property insurance upon the entire project, if required, to the full insurable value of the scope of work. The County and the Consultant waive against each other and the County's separate consultants, contractors, design consultant, subcontractors agents and employees of each and all of them, all damages covered by property insurance provided herein, except such rights as they may have to the proceeds of such insurance. The Consultant and County shall, where appropriate, require similar waivers of subrogation from the County's separate consultants, design consultants and subcontractors and shall require each of them to include similar waivers in their contracts. Collier County shall be responsible for purchasing and maintaining, its own liability insurance. Certificates issued as a result of the award of this solicitation must identify "For any and all work performed on behalf of Collier County." The General Liability Policy provided by Consultant to meet the requirements of this solicitation shall name Collier County, Florida, as an additional insured as to the operations of Consultant under this solicitation and shall contain a severability of interests provisions. Collier County Board of County Commissioners shall be named as the Certificate Holder. The Certificates of Insurance must state the Contract Number, or Project Number, or specific Project description, or must read: For any and all work performed on behalf of Collier County, the "Certificate Holder" should read as follows: Collier County Board of County Commissioners Naples, Florida The amounts and types of insurance coverage shall conform to the minimum requirements set forth in Insurance and Bonding attachment, with the use of Insurance Services Office (ISO) forms and endorsements or their equivalents. If Consultant has any self-insured retentions or deductibles under any of the below listed minimum required coverage, Consultant must identify on the Certificate of Insurance the nature and amount of such self- insured retentions or deductibles and provide satisfactory evidence of financial responsibility for such obligations. All self-insured retentions or deductibles will be Consultant's sole responsibility. Coverage(s) shall be maintained without interruption from the date of commencement of the Work until the date of completion and acceptance of the scope of work by the County or as specified in this solicitation, whichever is longer. The Consultant and/or its insurance carrier shall provide 30 days written notice to the County of policy cancellation or non-renewal on the part of the insurance carrier or the Consultant. The Consultant shall also notify the County, in a like manner, within twenty-four (24) hours after receipt, of any notices of expiration, cancellation, non-renewal or material change in coverage or limits received by Consultant from its insurer and nothing contained herein shall relieve Consultant of this requirement to provide notice. In the event of a reduction in the aggregate limit of any policy to be provided by Consultant #14-6190 RFP_CCNATemplate 21 Packet Page-564- hereunder, Consultant shall immediately take steps to have the aggregate limit ,3/25/2014 16.A:16. extent permitted under such policy. Should at any time the Consultant not maintain the insurance coverage(s) required herein, the County may terminate the Agreement or at its sole discretion shall be authorized to purchase such coverage(s) and charge the Consultant for such coverage(s) purchased. If Consultant fails to reimburse the County for such costs within thirty (30) days after demand, the County has the right to offset these costs from any amount due Consultant under this Agreement or any other agreement between the County and Consultant. The County shall be under no obligation to purchase such insurance, nor shall it be responsible for the coverage(s) purchased or the insurance company or companies used. The decision of the County to purchase such insurance coverage(s) shall in no way be construed to be a waiver of any of its rights under the Contract Documents. If the initial or any subsequently issued Certificate of Insurance expires prior to the completion of the scope of work, the Consultant shall furnish to the County renewal or replacement Certificate(s) of Insurance not later than ten (10) calendar days after the expiration date on the certificate. Failure of the Consultant to provide the County with such renewal certificate(s) shall be considered justification for the County to terminate any and all contracts. 2. Offer Extended to Other Governmental Entities Collier County encourages and agrees to the successful Consultant extending the pricing, terms and conditions of this solicitation or resultant contract to other governmental entities at the discretion of the successful Consultant. 3. Additional Items and/or Services Additional items and/or services may be added to the resultant contract, or purchase order, in compliance with the Purchasing Policy. 4. Use of Subcontractors Bidders on any service related project, including construction, must be qualified and directly responsible for 70% or more of the solicitation amount for said work. 5. County's Right to Inspect The County or its authorized Agent shall have the right to inspect the Consultant's facilities/project site during and after each work assignment the Consultant is performing. 6. Additional Terms and Conditions of Contract Collier County has developed standard contracts/agreements, approved by the Board of County Commissioners (BCC). The selected Consultant shall be required to sign a standard Collier County contract within twenty one (21) days of Notice of Selection for Award. The County reserves the right to include in any contract document such terms and conditions, as it deems necessary for the proper protection of the rights of Collier County. A sample copy of this contract is available upon request. The County will not be obligated to sign any contracts, maintenance and/or service agreements or other documents provided by the Consultant. 7. Public Records Compliance The Consultant/Contractor agrees to comply with the Florida Public Records Law Chapter 119 (including #14-6190 RFP_CCNATemplate 22 Packet Page-565- q § (a)-(d) ( )� 3/25/2014 16.A.16. specifically those contractual requirements at F.S. 119.0701(2) and 3 ', rules, regulations and requirements of any governmental agencies. 8. Payment Method Payments are made in accordance with the Local Government Prompt Payment Act, Chapter 218, Florida Statutes. Consultant/Contractor invoices must include: • Purchase Order Number; and • Description and quantities of the goods or services provided per instructions on the County's purchase order or contract. Invoices shall be sent to: Board of County Commissioners Clerk's Finance Department ATTN: Accounts Payable 3299 Tamiami Trail E Ste 700 Naples FL 34112 Or emailed to: bccapclerk(c�collierclerk.com. Collier County, in its sole discretion, will determine the method of payment for goods and/or services as part of this agreement. Payment methods include: • Traditional— payment by check, wire transfer or other cash equivalent. • Standard — payment by purchasing card. Collier County's Purchasing Card Program is supported by standard bank credit suppliers (i.e. VISA and MasterCard), and as such, is cognizant of the Rules for VISA Merchants and MasterCard Merchant Rules. The County may not accept any additional surcharges (credit card transaction fees) as a result of using the County's credit card for transactions relating to this solicitation. The County will entertain bids clearly stating pricing for standard payment methods. An additional separate discounted price for traditional payments may be provided at the initial bid submittal if it is clearly marked as an "Additional Cash Discount." Upon execution of the Contract and completion of each month's work, payment requests may be submitted to the Project Manager on a monthly basis by the Consultant/Contractor for services rendered for that prior month. Services beyond sixty (60) days from current monthly invoice will not be considered for payment without prior approval from the Project Manager. All invoices should be submitted within the fiscal year the work was performed. (County's fiscal year is October 1 - September 30.) Invoices submitted after the close of the fiscal year will not be accepted (or processed for payment) unless specifically authorized by the Project Manager. Payments will be made for articles and/or services furnished, delivered, and accepted, upon receipt and approval of invoices submitted on the date of services or within six (6) months after completion of contract. Any untimely submission of invoices beyond the specified deadline period is subject to non- payment under the legal doctrine of "laches" as untimely submitted. Time shall be deemed of the essence with respect to the timely submission of invoices under this agreement. In instances where the successful Consultant/Contractor may owe debts (including, but not limited to taxes or other fees) to Collier County and the Consultant/Contractor has not satisfied nor made arrangement to satisfy these debts, the County reserves the right to off-set the amount owed to the #14-6190 RFP_CCNATemplate 23 Packet Page-566- Count by applying the amount owed to the Consultant/Contractor for servic 3/25/2014 16.A.16. County Y ,,,.,...,,,..,., ,,, materials delivered in association with a contract. Invoices shall not reflect sales tax. After review and approval, the invoice will be transmitted to the Finance Division for payment. Payment will be made upon receipt of proper invoice and in compliance with Chapter 218 Florida Statutes, otherwise known as the "Local Government Prompt Payment Act." Collier County reserves the right to withhold and/or reduce an appropriate amount of any payment for work not performed or for unsatisfactory performance of Contractual requirements. 9. Environmental Health and Safety All Consultants and Sub Consultants performing service for Collier County are required and shall comply with all Occupational Safety and Health Administration (OSHA), State and County Safety and Occupational Health Standards and any other applicable rules and regulations. Consultants and Sub Consultants shall be responsible for the safety of their employees and any unsafe acts or conditions that may cause injury or damage to any persons or property within and around the work site. All firewall penetrations must be protected in order to meet Fire Codes. Collier County Government has authorized OSHA representatives to enter any Collier County facility, property and/or right-of-way for the purpose of inspection of any Consultant's work operations. This provision is non-negotiable by any department and/or Consultant. All new electrical installations shall incorporate NFPA 70E Short Circuit Protective Device Coordination and Arc Flash Studies where relevant as determined by the selected Consultant. All electrical installations shall be labeled with appropriate NFPA 70E arch flash boundary and PPE Protective labels. 10. Licenses The Consultant is required to possess the correct Business Tax Receipt, professional license, and any other authorizations necessary to carry out and perform the work required by the project pursuant to all applicable Federal, State and Local Law, Statute, Ordinances, and rules and regulations of any kind. Additionally, copies of the required licenses must be submitted with the proposal response indicating that the entity proposing, as well as the team assigned to the County account, is properly licensed to perform the activities or work included in the contract documents. Failure on the part of any Consultant to submit the required documentation may be grounds to deem Consultant non-responsive. A Consultant, with an office within Collier County is also required to have an occupational license. All State Certified contractors who may need to pull Collier County permits or call in inspections must complete a Collier County Contractor License registration form and submit the required fee. After registering the license/registration will need to be renewed thereafter to remain "active" in Collier County If you have questions regarding professional licenses contact the Contractor Licensing, Growth Management Division, Operations & Regulatory Management Department at (239) 252-2431, 252-2432 or 252-2909. Questions regarding required occupational licenses, please contact the Tax Collector's Office at (239) 252-2477. 11. Survivability Purchase Orders: The Consultant/Contractor/Vendor agrees that any Purchase Order that extends beyond the expiration date of the original Solicitation #14-6190 will survive and remain subject to the terms and conditions of that Agreement until the completion or termination of this Purchase Order. #14-6190 RFP_CCNATemplate 24 Packet Page-567- 3/25/2014 16.A.16. 12. Principals/Collusion By submission of this Proposal the undersigned, as Consultant, does declare that the only person or persons interested in this Proposal as principal or principals is/are named therein and that no person other than therein mentioned has any interest in this Proposal or in the contract to be entered into; that this Proposal is made without connection with any person, company or parties making a Proposal, and that it is in all respects fair and in good faith without collusion or fraud. 13. Relation of County It is the intent of the parties hereto that the Consultant shall be legally considered an independent Consultant, and that neither the Consultant nor their employees shall, under any circumstances, be considered employees or agents of the County, and that the County shall be at no time legally responsible for any negligence on the part of said Consultant, their employees or agents, resulting in either bodily or personal injury or property damage to any individual, firm, or corporation. 14. Termination Should the Consultant be found to have failed to perform his services in a manner satisfactory to the County, the County may terminate this Agreement immediately for cause; further the County may terminate this Agreement for convenience with a thirty (30) day written notice. The County shall be sole judge of non-performance. 15. Lobbying All firms are hereby placed on NOTICE that the Board of County Commissioners does not wish to be lobbied, either individually or collectively about a project for which a firm has submitted a Proposal. Firms and their agents are not to contact members of the County Commission for such purposes as meeting or introduction, luncheons, dinners, etc. During the process, from Proposal closing to final Board approval, no firm or their agent shall contact any other employee of Collier County in reference to this Proposal, with the exception of the Purchasing Director or his designee(s). Failure to abide by this provision may serve as grounds for disqualification for award of this contract to the firm. 16. Certificate of Authority to Conduct Business in the State of Florida (Florida Statute 607.1501) In order to be considered for award, firms must be registered with the Florida Department of State Divisions of Corporations in accordance with the requirements of Florida Statute 607.1501 and provide a certificate of authority (www.sunbiz.org/search.html) prior to execution of a contract. A copy of the document may be submitted with the solicitation response and the document number shall be identified. Firms who do not provide the certificate of authority at the time of response shall be required to provide same within five (5) days upon notification of selection for award. If the firm cannot provide the document within the referenced timeframe, the County reserves the right to award to another firm. 17. Single Proposal Each Consultant must submit, with their proposal, the required forms included in this RFP. Only one proposal from a legal entity as a primary will be considered. A legal entity that submits a proposal as a primary or as part of a partnership or joint venture submitting as primary may not then act as a sub- consultant to any other firm submitting under the same RFP. If a legal entity is not submitting as a primary or as part of a partnership or joint venture as a primary, that legal entity may act as a sub- #14-6190 RFP_CCNATemplate 25 Packet Page-568- 3/25/2014 16.A.16. consultant to any other firm or firms submitting under the same RFP. All submittu,.. requirement will be deemed non-responsive and rejected from further consideration. 18. Protest Procedures Any actual or prospective Consultant to a Request for Proposal, who is aggrieved with respect to the former, shall file a written protest with the Purchasing Director prior to the due date for acceptance of proposals. AU such protests must be filed with the Purchasing Director no later than 11:00 a.m. Collier County time on the final published date for the acceptance of the Request for Proposals. The Board of County Commissioners will make award of contract in public session. Award recommendations will be posted outside the offices of the Purchasing Department on Wednesdays and Thursdays. Any actual or prospective respondent who desires to formally protest the recommended contract award must file a notice of intent to protest with the Purchasing Director within two (2) calendar days (excluding weekends and County holidays) of the date that the recommended award is posted. Upon filing of said notice, the protesting party will have five (5) days to file a formal protest and will be given instructions as to the form and content requirements of the formal protest. A copy of the "Protest Policy" is available at the office of the Purchasing Director. 19. Public Entity Crime A person or affiliate who has been placed on the convicted Consultant list following a conviction for a public entity crime may not submit a bid, proposal, or reply on a contract to provide any goods or services to a public entity; may not submit a bid, proposal, or reply on a contract with a public entity for the const.uction or repair of a public building or public work; may not submit bids, proposals, or replies on leases of real property to a public entity; may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity; and may not transact business with any public entity in excess of the threshold amount provided in s. 287.017 for CATEGORY TWO for a period of 36 months following the date of being placed on the convicted consultant list. 20. Security and Background Checks If required, Consultant/ Contractor/ Proposer shall be responsible for the costs of providing background checks by the Collier County Facilities Management Department, and drug testing for all employees that shall provide services to the County under this Agreement. This may include, but not be limited to, checking federal, state and local law enforcement records, including a state and FBI fingerprint check, credit reports, education, residence and employment verifications and other related records. Consultant/Contractor shall be required to maintain records on each employee and make them available to the County for at least four (4) years. 21. Conflict of interest Consultant shall complete the Conflict of Interest Affidavit included as an attachment to this RFP documen . Disclosure of any potential or actual conflict of interest is subject to County staff review and does not in and of itself disqualify a firm from consideration. These disclosures are intended to identify and or preclude conflict of interest situations during contract selection and execution. 22. Prohibition of Gifts to County Employees No organization or individual shall offer or give, either directly or indirectly, any favor, gift, loan, fee, service or other item of value to any County employee, as set forth in Chapter 112, Part III, Florida Statutes, he current Collier County Ethics Ordinance and County Administrative Procedure 5311. Violation of this provision may result in one or more of the following consequences: a. Prohibition by the #14-6190 RFP_CCNATemplate 26 Packet Page-569- individual, firm, and/or any employee of the firm from contact with County staff for 3/25/2014 16.A.16. Y tYr r.,-.,,. — time; b. Prohibition by the individual and/or firm from doing business with the County for a specified period of time, including but not limited to: submitting bids, RFP, and/or quotes; and, c. immediate termination of any contract held by the individual and/or firm for cause. 23. Immigration Law Affidavit Certification Statutes and executive orders require employers to abide by the immigration laws of the United States and to employ only individuals who are eligible to work in the United States. The Employment Eligibility Verification System (E-Verify) operated by the Department of Homeland Security (DHS) in partnership with the Social Security Administration (SSA), provides an Internet-based means of verifying employment eligibility of workers in the United States; it is not a substitute for any other employment eligibility verification requirements. The program will be used for Collier County formal Invitations to Bid (ITB) and Request for Proposals (REP) including professional services and construction services. Exceptions to the program: • Commodity based procurement where no services are provided. • Where the requirement for the affidavit is waived by the Board of County Commissioners Consultants / Bidders are required to enroll in the E-Verify program, and provide acceptable evidence of their enrollment, at the time of the submission of the Consultant's/bidder's proposal. Acceptable evidence consists of a copy of the properly completed E-Verify Company Profile page or a copy of the fully executed E-Verify Memorandum of Understanding for the company. Consultants are also required to provide the Collier County Purchasing Department an executed affidavit certifying they shall comply with the E-Verify Program. The affidavit is attached to the solicitation documents. If the Bidder/Consultant does not comply with providing the acceptable E-Verify evidence and the executed affidavit the bidder's/Consultant's proposal may be deemed non-responsive. Additionally, Consultants shall require all subcontracted Consultants to use the E-Verify system for all purchases not covered under the "Exceptions to the program" clause above. For additional information regarding the Employment Eligibility Verification System (E-Verify) program visit the following website: http://www.dhs.gov/E-Verify. It shall be the Consultant's responsibility to familiarize themselves with all rules and regulations governing this program. Consultant acknowledges, and without exception or stipulation, any firm(s) receiving an award shall be fully responsible for complying with the provisions of the Immigration Reform and Control Act of 1986 as located at 8 U.S.C. 1324, et seq. and regulations relating thereto, as either may be amended and with the provisions contained within this affidavit. Failure by the awarded firm(s) to comply with the laws referenced herein or the provisions of this affidavit shall constitute a breach of the award agreement and the County shall have the discretion to unilaterally terminate said agreement immediately. #14-6190 RFP_CCNATemplate 27 Packet Page-570- 3/25/2014 16.A.16. air County Adrninistrahe Services DiVision Purchasing Attachment 1: Consultant's Non-Response Statement The sole intent of the Collier County Purchasing Department is to issue solicitations that are clear, concise and openly competitive. Therefore, we are interested in ascertaining reasons for prospective Consultants not wishing to respond to this solicitation. If your firm is not responding to this RFP, please indicate the reason(s) by checking the item(s) listed below and return this form via email or fax, noted on the cover page, or mail to Collier County Government, Purchasing Department, 3327 Tamiami Trail E, Naples, FL 34112. We are not responding to CCNA Solicitation #14-6190 Golden Gate City Stormwater Drainage Improvement Project Engineering Design for the following reason(s): ❑ Services requested not available through our company. ❑ Our firm could not meet specifications/scope of work. ❑ Specifications/scope of work not clearly understood or applicable (too vague, rigid, etc.) ❑ Project is too small. ❑ Insufficient time allowed for preparation of response. ❑ Incorrect address used. Please correct mailing address: ❑ Other reason(s): Name of Firm: Address: City, State, Zip: Telephone: Email: Representative Signature: Representative Name: Date #14-6190 RFP_CCNATemplate 28 Packet Page-571- 3/25/2014 16.A.16. Co itzt ier Copy Arin inistrati e Services Division Purchasing Attachment 2: Consultant Check List IMPORTANT: THIS SHEET MUST BE SIGNED. Please read carefully, sign in the spaces indicated and return with your Proposal. Consultant should check off each of the following items as the necessary action is completed: ❑ The Proposal has been signed. ❑ All applicable forms have been signed and included, along with licenses to complete the requirements of the project. ❑ Any addenda have been signed and included. ❑ The mailing envelope has been addressed to: Collier County Government Purchasing Department 3327 Tamiami Trail E Naples FL 34112 Attn: Evelyn Colon, Procurement Strategist CCNA Solicitation: #14-6190 Golden Gate City Stormwater Drainage Improvement Project Engineering Design ❑ The mailing envelope must be sealed and marked with Proposal Number, Proposal Title and Due Date. ❑ The Proposal will be mailed or delivered in time to be received no later than the specified due date and time. (Otherwise Proposal cannot be considered.) ALL COURIER-DELIVERED PROPOSALS MUST HAVE THE RFP NUMBER AND TITLE ON THE OUTSIDE OF THE COURIER PACKET. Name of Firm: Address: City, State, Zip: Telephone: Email: Representative Signature: Representative Name: Date #14-6190 RFP_CCNATemplate 29 Packet Page-572- 3/25/2014 16.A.16. Cofffer County Adrninisbafive services Division Purchasing Attachment 3: Conflict of Interest Affidavit By the signature below, the firm (employees, officers and/or agents) certifies, and hereby discloses, that, to the best of their knowledge and belief, all relevant facts concerning past, present, or currently planned interest or activity (financial, contractual, organizational, or otherwise) which relates to the proposed work; and bear on whether the firm (employees, officers and/or agents) has a possible conflict have been fully disclosed. Additionally, the firm (employees, officers and/or agents) agrees to immediately notify in writing the Purchasing/General Services Director, or designee, if any actual or potential conflict of interest arises during the contract and/or project duration. Firm: Signature and Date: Print Name Title of Signatory State of County of SUBSCRIBED AND SWORN to before me this day of , 20_, by , who is personally known to me to be the for the Firm, OR who produced the following identification: Notary Public My Commission Expires: #14-6190 RFP_CCNATemplate 30 Packet Page-573- 3/25/2014 16.A.16. /tat Co ler County Administrative Services Division Purchasing Attachment 4: Consultant Declaration Statement BOARD OF COUNTY COMMISSIONERS Collier County Government Complex Naples, Florida 34112 RE: CCNA Solicitation: #14-6190 Golden Gate City Stormwater Drainage Improvement Project Engineering Design Dear Commissioners: The undersigned, as Consultant declares that this proposal is made without connection or arrangement with any other person and this proposal is in every respect fair and made in good faith, without collusion or fraud. The Consultant agrees, if this proposal is accepted, to execute a Collier County document for the purpose of establishing a formal contractual relationship between the firm and Collier County, for the performance of all requirements to which the proposal pertains. The Consultant states that the proposal is based upon the proposal documents listed by the above referenced CCNA Solicitation. IN WITNESS WHEREOF, WE have hereunto subscribed our names on this day of 200_in the County of , in the State of Firm's Legal Name: Address: City, State, Zip Code: Florida Certificate of Authority Document Number Federal Tax Identification Number CCR# or CAGE Code Telephone: FAX: Signature by: (Typed and written) Title: #14-6190 RFP_CCNATemplate 31 Packet Page-574- Additional Contact Information 3/25/2014 16.A.16. Send payments to: (required if different from above) Company name used as payee Contact name: Title: Address: City, State,ZIP Telephone: FAX: Email: Office servicing Collier County to place orders (required if different from above) Contact name: Title: Address: City, State,ZIP Telephone: Email: #14-6190 RFP_CCNATemplate 32 Packet Page-575- 3/25/2014 16.A.16. cower County Administrative Services Division Purchasing Attachment 5: Immigration Affidavit Certification CCNA Solicitation: #14-6190 Golden Gate City Stormwater Drainage Improvement Project Engineering Design This Affidavit is required and should be signed, notarized by an authorized principal of the firm and submitted with formal Invitations to Bid (ITB's) and Request for Proposals (RFP) submittals. Further, Consultants / Bidders are required to enroll in the E-Verify program, and provide acceptable evidence of their enrollment, at the time of the submission of the Consultant's/bidder's proposal. Acceptable evidence consists of a copy of the properly completed E-Verify Company Profile page or a copy of the fully executed E-Verify Memorandum of Understanding for the company. Failure to include this Affidavit and acceptable evidence of enrollment in the E-Verifv program may deem the Consultant/Bidder's proposal as non-responsive. Collier County will not intentionally award County contracts to any Consultant who knowingly employs unauthorized alien workers, constituting a violation of the employment provision contained in 8 U.S.C. Section 1324 a(e) Section 274A(e) of the Immigration and Nationality Act("INA"). Collier County may consider the employment by any Consultant of unauthorized aliens a violation of Section 274A (e) of the INA. Such Violation by the recipient of the Employment Provisions contained in Section 274A(e) of the INA shall be grounds for unilateral termination of the contract by Collier County. Consultant attests that they are fully compliant with all applicable immigration laws (specifically to the 1986 Immigration Act and subsequent Amendment(s)) and agrees to comply with the provisions of the Memorandum of Understanding with E-Verify and to provide proof of enrollment in The Employment Eligibility Verification System (E-Verify), operated by the Department of Homeland Security in partnership with the Social Security Administration at the time of submission of the Consultant's/Bidder's proposal. Company Name Print Name Title Signature Date State of County of The foregoing instrument was signed and acknowledged before me this day of 20_, by who has produced as identification. (Print or Type Name) (Type of Identification and Number) Notary Public Signature Printed Name of Notary Public Notary Commission Number/Expiration The signee of this Affidavit guarantees, as evidenced by the sworn affidavit required herein, the truth and accuracy of this affidavit to interrogatories hereinafter made. #14-6190 RFP_CCNATemplate 33 Packet Page-576- 3/25/2014 16.A.16. cote-county Administrative Services Division Purchasing Attachment 6: Consultant Substitute W—9 Request for Taxpayer Identification Number and Certification In accordance with the Internal Revenue Service regulations, Collier County is required to collect the following information for tax reporting purposes from individuals and companies who do business with the County (including social security numbers if used by the individual or company for tax reporting purposes). Florida Statute 119.071(5) require that the county notify you in writing of the reason for collecting this information, which will be used for no other purpose than herein stated. Please complete all information that applies to your business and return with your quote or proposal. 1. General Information (provide all information) Taxpayer Name: (as shown on income tax return) Business Name: (if different from taxpayer name) Address City State Zip Telephone FAX Email Order Information Remit/Payment Information Address Address City State Zip City State Zip FAX FAX Email Email 2. Company Status (check only one) Individual/Sole Proprietor _Corporation _Partnership Tax Exempt (Federal income tax-exempt entity _Limited Liability Company under Internal Revenue Service guidelines IRC 501 (c) 3) Enter the tax classification (D=Disregarded Entity, C=Corporation, P=Partnership) 3. Taxpayer Identification Number(for tax reporting purposes only) Federal Tax Identification Number(TIN) (Consultants who do not have a TIN, will be required to provide a social security number prior to an award of the contract.) 4. Sign and Date Form: Certification: Under penalties of perjury, I certify that the information shown on this form is correct to my knowledge. Signature Date Title Phone Number #14-6190 RFP_CCNATemplate 34 Packet Page-577- 3/25/2014 16.A.16. Co er County Administrative Services Dion Purchasing Attachment 7: Insurance and Bonding Requirements Insurance/Bond Type Required Limits 1. ®Worker's Statutory Limits of Florida Statutes, Chapter 440 and all Federal Government Compensation Statutory Limits and Requirements 2. ® Employer's Liability $1,000,000 single limit per occurrence 3. ® Commercial General Bodily Injury and Property Damage Liability (Occurrence Form) patterned after the current $1,000,000 single limit per occurrence, $2,000,000 aggregate for Bodily Injury ISO form Liability and Property Damage Liability. This shall include Premises and Operations; Independent Contractors; Products and Completed Operations and Contractual Liability. 4. ® Indemnification To the maximum extent permitted by Florida law, the Consultant/Contractor shall indemnify and hold harmless Collier County, its officers and employees from any and all liabilities, damages, losses and costs, including, but not limited to, reasonable attorneys' fees and paralegals' fees, to the extent caused by the negligence, recklessness, or intentionally wrongful conduct of the Consultant/Contractor or anyone employed or utilized by the Consultant/Contractor in the performance of this Agreement. This indemnification obligation shall not be construed to negate, abridge or reduce any other rights or remedies which otherwise may be available to an indemnified party or person described in this paragraph. This section does not pertain to any incident arising from the sole negligence of Collier County. 4. ®Automobile Liability $500,000 Each Occurrence; Bodily Injury& Property Damage, Owned/Non-owned/Hired; Automobile Included 5. ❑ Other insurance as ❑Watercraft $ Per Occurrence noted: ❑ United States Longshoreman's and Harborworker's Act coverage shall be maintained where applicable to the completion of the work. $ Per Occurrence ❑ Maritime Coverage (Jones Act) shall be maintained where applicable to the completion of the work. $ Per Occurrence ❑Aircraft Liability coverage shall be carried in limits of not less than $5,000,000 each occurrence if applicable to the completion of the Services under this Agreement. $ Per Occurrence ❑ Pollution $, Per Occurrence #14-6190 RFP_CCNATemplate 35 Packet Page-578- 3/25/2014 16.A.16. ® Professional Liability $1,000,000 per claim and in the aggregate • $1,000,000 per claim and in the aggregate • $2,000,000 per claim and in the aggregate ❑ Project Professional Liability $ Per Occurrence ❑Valuable Papers Insurance $ Per Occurrence 6. ❑ Bid bond Shall be submitted with proposal response in the form of certified funds, cashiers' check or an irrevocable letter of credit, a cash bond posted with the County Clerk, or proposal bond in a sum equal to 5% of the cost proposal. All checks shall be made payable to the Collier County Board of County Commissioners on a bank or trust company located in the State of Florida and insured by the Federal Deposit Insurance Corporation. 7. ❑ Performance and For projects in excess of $200,000, bonds shall be submitted with the Payment Bonds executed contract by Proposers receiving award, and written for 100% of the Contract award amount, the cost borne by the Proposer receiving an award. The Performance and Payment Bonds shall be underwritten by a surety authorized to do business in the State of Florida and otherwise acceptable to Owner; provided, however, the surety shall be rated as "A-" or better as to general policy holders rating and Class V or higher rating as to financial size category and the amount required shall not exceed 5% of the reported policy holders' surplus, all as reported in the most current Best Key Rating Guide, published by A.M. Best Company, Inc. of 75 Fulton Street, New York, New York 10038. 8. ® Consultant shall ensure that all subcontractors comply with the same insurance requirements that he is required to meet. The same Consultant shall provide County with certificates of insurance meeting the required insurance provisions. 9. ® Collier County must be named as "ADDITIONAL INSURED" on the Insurance Certificate for Commercial General Liability where required. 10. ® The Certificate Holder shall be named as Collier County Board of County Commissioners, OR, Board of County Commissioners in Collier County, OR Collier County Government, OR Collier County (or Collier MPO). The Certificates of Insurance must state the Contract Number, or Project Number, or specific Project description, or must read: For any and all work performed on behalf of Collier County. 11. ® Thirty (30) Days Cancellation Notice required. Consultant's Insurance Statement We understand the insurance requirements of these specifications and that the evidence of insurability may be required within five (5) days of the award of this solicitation. Name of Firm Date Consultant Signature Print Name Insurance Agency Agent Name Telephone Number #14-6190 RFP_CCNATemplate 36 Packet Page-579- 3/25/2014 16.A.16. Caber County Administrative Servioas Dvision Purchasing Attachment 8: Reference Questionnaire Solicitation: #14-6190 Golden Gate City Stormwater Drainage Improvement Project Engineering Design Reference Questionnaire for: (Name of Company Requesting Reference Information) (Name of Individuals Requesting Reference Information) Name: Company: (Evaluator completing reference questionnaire) (Evaluator's Company completing reference) Email: , FAX: Telephone: Collier County is implementing a process that collects reference information on firms and their key personnel to be used in the selection of firms to perform this project. The Name of the Company listed in the Subject above has listed you as a client for which they have previously performed work. Please complete the survey. Please rate each criteria to the best of your knowledge on a scale of 1 to 10, with 10 representing that you were very satisifed (and would hire the firm/individual again) and 1 representing that you were very unsatisfied (and would never hire the firm/indivdival again). If you do not have sufficient knowledge of past performance in a particular area, leave it blank and the item or form will be scored "0." Project Description: Completion Date: Project Budget: Project Number of Days: Item Citeria Score 1 Ability to manage the project costs (minimize change orders to scope). 2 Ability to maintain project schedule (complete on-time or early). 3 Quality of work. 4 Quality of consultative advice provided on the project. 5 Professionalism and ability to manage personnel. 6 Close out project process (final product turnover; invoices; manuals or going forward documentation, etc.) 7 Ability to verbally communicate and document information clearly and succinctly. 8 Abiltity to manage risks and unexpected project circumstances. 9 Ability to follow County policies, procedures, rules, regulations, etc. 10 Overall comfort level with hiring the company in the future (customer satisfaction). TOTAL SCORE OF ALL ITEMS Please FAX this completed survey to: By #14-6190 RFP_CCNATemplate 37 Packet Page-580- 3/25/2014 16.A.16. c > ) 'co- w 46 ❑ ei a) MO •0 a L n. U) c 0 0 0 0 0 0 0 0 0 co d cu O O O O O O O 0 0 0 E 0 0 0 0 0 0 0 0 0 0 C 0 0 0 0 0 0 0 0 0 0 C i , N M In CO I's CO O O N li c o E a) Co. d' N CO CO N CO CO CO O p IO7 T- 4 4 4 lf) O T U a, co >.. co cu T a w L ❑ L c▪ts E L o a) Cl) E - a) Y- = ID .E U c c a) 5 N a) CO C •L co 0 CD co co C c L c > c a Z ` _ O -._tD)' g•=7 C w cm = C U) C N f' �! a' C U) a) _c LU f4 — t� ffi N r e O (B C = p >, C E c O a c C� CO O U 2 2 () u)) .> J ca � ti 0 U) "a a) cn Q L cn d G) co N Q C7 a) > C U `It< c e F- < -, U ct 0 2 0 ❑ U o 1- Packet Page -581-