Agenda 02/11/2014 Item #16E6 2/11/2014 16.E.6. EXECUTIVE SUMMARY Recommendation to retroactively approve change orders #1 and 2 to Contract 13-6084 for the Pelican Bay Crosswalk Construction project to Quality Enterprises USA, Inc. OBJECTIVE: The purpose for this project was to structurally restore and architecturally enhance the performance of the Pelican Bay crosswalks. BACKGROUND: On September 10, 2013 (Agenda Item 16F5), the Board of County Commissioners awarded contract 13-6084 for Pelican Bay Crosswalk Construction project to Quality Enterprises USA, Inc. The project cost was $191,638.87, and had an expected completion date by December 27, 2013. On December 23, 2013, change order #1 was presented to the Purchasing staff for an increase of an additional $20,384.76 and an additional twenty-one (21) days by the operating department for the project completion to be modified. These modifications resulted in a change order greater than ten (10) percent (the actual modification was 10.64%), and should have been "reported for approval" to the Board of County Commissioners prior to the execution of work. If approved by the Board, the contract would have been extended to January 17, 2014. On January 17, 2014, the Purchasing staff approved and issued change order#2, which extended the completion date by fourteen (14) days (in accordance with the Board's purchasing policy). The final completion date for the project was extended to January 31, 2014. The work performed by Quality Construction USA, Inc. under the original contract, and the two change orders were performed in the interest of saving time and money for the County. Staff and residents of Pelican Bay Community are satisfied with the work performed by the contractor. The Purchasing Director has reviewed change order procedures with the professional staff to ensure compliance with the Board's Purchasing Ordinance and respectfully requests the Board's retroactive approval of the two change orders. FISCAL IMPACT: Funding for this request is accounted for by Pelican Bay Services Division capital budgets. GROWTH MANAGEMENT IMPACT: There is no impact on the Growth Management Plan. Packet Page-815- 2/11/2014 16.E.6. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval.—SRT RECOMMENDATION: That the Board of County Commissioners retroactively approves change orders #1 and 2 to Contract 13-6084 for the Pelican Bay Crosswalk Construction project to Quality Enterprises USA, Inc. PREPARED BY: Kyle Lukasz, Manager, Pelican Bay Services Adam Northrup, Procurement Strategist, Purchasing Department Attachments: • Change Order#1 documentation • Change Order#2 documentation Packet Page -816- 2/11/2014 16.E.6. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.E.16.E.6. Item Summary: Recommendation to retroactively approve change orders#1 and 2 to Contract 13-6084 for the Pelican Bay Crosswalk Construction project to Quality Enterprises USA, Inc. Meeting Date: 2/11/2014 Prepared By Name:NorthrupAdam Title: Procurement Strategist, Purchasing 1/22/2014 4:18:00 PM Submitted by Title: Procurement Strategist, Purchasing Name:NorthrupAdam 1/22/2014 4:18:02 PM Approved By Name:NorthrupAdam Title: Procurement Strategist,Purchasing Date: 1/22/2014 4:35:15 PM Name: MarkiewiczJoanne Title: Manager-Purchasing Acquisition.Purchasing& Gene Date: 1/22/2014 4:35:22 PM Name: pochopinpat Title: Administrative Assistant,Facilities Management Date: 1/23/2014 10:50:21 AM Name: TeachScott Title: Deputy County Attorney,County Attorney Date: 1/24/2014 2:07:54 PM Packet Page-817- 2/11/2014 16.E.6. Name: PriceLen Title:Administrator, Administrative Services Date: 1/30/2014 9:20:52 AM Name: GreenwaldRandy Title: Management/Budget Analyst, Office of Management&Budget Date: 1/30/2014 4:31:50 PM Name: KlatzkowJeff Title: County Attorney, Date: 2/3/2014 3:19:46 PM Name: OchsLeo Title: County Manager, County Managers Office Date: 2/4/2014 11:15:05 AM Packet Page -818- 2/11/2014&);fter' Comfy Administrative S Services Division Purchasing Department et ,- Change Modification Form ® Contract Change Request ❑ Work Order Modification Contract#: 13-6084 Change#: 1 PO/Work Order#: Project Name: Pelican Bay Crosswalk 4500147541 Construction Projec:#: 50066 Project Manager: Kyle Department: Pelican Bay Contractor/Firm Name: Quality Lukasz Services Enterprises USA Inc. Original Contract/Work Order Amount $ 191,638.87 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 191,638.87c Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 191,638.67 SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 20,384.76 10.64% Total Change from Original Amount Revised Contract/Work Order Total $ 212,023.63 10.64% Change from Current BCC Approved Amount Cumula'ive Changes $ 20,384.76 10.64% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Origina completion date: Last approved completion date: I Revised completion date (includes this 12/27/2)13 12/27/2013 change): 01/17/2014 Numbe'of days added: 21 Each step on the contract modification checklist form has been reviewed prior to me submitting for approval KL (finis box must be initialed by Project Manager) ® Add new task(s) ® Change task(s) ® Delete task(s) ❑ Other(specify): 1. Prov de a detailed and specific explanation of the requested change(s)to the task(s) and/or the additional days added: Elevation of existing asphalt required the milling and repaving of 1,470 sq. ft. of asphalt and installing new road stripping.Also, due to alignments and grade issues 81' of additional sidewalk was required and 38'of sidewalk curbing removed with 6:1 slopping constructed. 2. Provide detailed rationale for the requested change: The milling, paving and re-stripping were required due to the existing road surfaces not being at the correct elevations which creates excessive bumps at the new crosswalks. Sidewalk additions and deletions were due to the realignment of one crosswalk due to stormdrain locations. Also, the elimination of sidewalk curbing is needed to create a better landscape grade to the adjoining property, 3. Provide explanation why change was not anticipated in original scope of work: Design survey work didn't require the elevations of all road surfaces so the difference between existing road elevation and crosswalk elevation was not discovered until construction. Realignment of one crosswalk was to improve safety with further setback from storm drain not anticipated from design surveys. The additional grading with elimination of sidewalk curbing was an esthetic issue that only appeared after crosswalk roadwork was performed. 4. Describe the impact if this change is not processed: If the milling and paving were not performed it would create an unsafe condition and the bumps created would not meet road design parameters. If the adjustment to sidewalks and curbing were not made it would create an unappealing condition when the brick paver crosswalks were to enhance the roadway conditions. Type of Change/Modification I ® 1. Planned/Elective ® 2. Unforeseen conditions/circumstance ❑ 3. Quantity or price adjustment ❑4. CoTection of error(s) 5. Value added ( ❑ 6. Schedule adjustment Change Requested By Contpctor/Consultant I ❑ Owner ® Using Department El Design Professional ❑ Regulatory Agency (specify): Other(specify): Revised:7/26/13 1 Packet Page -819- Purcha.ing Protessional articipated in Negotiation of Change/ Modification: ❑ Yes Ej No 2/11/2014 16.E.6. / Approv•d by: 2/_• Date: �� �,�,� Name .rid Title: Kyle Lukas +per. •• Review d by: Daie: z 3 Procur_ment Str.'-.'•is Name: Ada'gill•rttirup j Revised:7/26/13 2 Packet Page -820- 2/11/2014 16.E.6. CHAI9GE ORDirf, CHANGE 01WER NO. 1 CONTRACT NO. 13-6084 BCC Date: 09/10/2013 Agenda Item: 16-F-5 TO: Ouaiity Enterprises USA Inc. 3894 Mannis Dr. Na.ples, FL 33114 DATE: 17/20/2013 PROJECT NAME:Pelican Bay Crosswalk Construction PRalECT NO.: 50066 Under our AGREEMENT dated September 10,2013 You hereby are authorized and directed to make the following change(s) in accordance with term and conditions of the Agreement: Mill, nave and stripe areas 1,470 S . :ft. of pavement adjacent to crosswalks. Also, add 81 ft.. of sidewalk and eliminate 38 I-1. of sidewalk curbing and instead reslopping area, FOR THE Additive Sum of: $20,384.76;Twenty Thousand Three Hundred and Eighty Four Dollars and Seventy Six Cents. Original Agreement Amount $191,638.87 sum urPt.evions Changes 1; 0 This Change Order 20,384.76. Present Ageement Amount $212,02163 The time for completion shall be increaser,1 by 21 calendar days 013e to this Change Order. Accordingly, the Contract Time is now 96 calendar days. The substantial completion data is December 12. 2013 and the final completion date is January 17.. 2014. Your acceptance of this Change Order shall consdkutt-:a modification to our Agreement and will be performed subject to all the same terms and conditions as contained in our Agreement indicated above,as fully as if the same were repeated in this acceptance. The adjustment, if any, to the Agreement shall constitute a full and final settlement of any and all claims of the Contractor arising out of or related to the change set forth herein. includinv claims for impact a. _ielay costs. paced by Iyle Luasz, froleces.ger Pelican Bay Approved By: T, _____ Date: ' ____ Jigickr,Design Professional Agnoli Barber and Brundage . . Packet Page-821- 2/11/2014 16.E.6. kccepted by: .--• Date: - Loirlal.rudit5;-.ciiec President Quality Enterprises LISA 1 Approved by: Date: Neil Dorr'il, trator. Pelican 13..; -a—ices Di vi - Or — Approved by: Adam •lortIrrup,Procurement Date: 24-3 Packet Page-822- 2/11/2014 16.E.6. Accepted by:— Dxte:___________ Lou Gaudio, Quality Etticfprisps1J§—ki,pc, Approved by: Dxte: Nail AorrirAkimiriisril.gor ervices Division Approved by: Do/e: Adam Northrup, Prncnrenent6u-Mqg:tat --- • Packet Page-823- --- 1 2/11/2014 1� �� � / ^~ . .'~-~ . . 16.E.6. �� |eliou»BuySmrvice*Qivisinn :01 Laurel Oak Drive#302 'aples,FL 34108 . aoxuryI7' 20|4 ou Gaudio, Vice President I:oolity Enterprises USA mc, ^994 Mannis Dr. � auks, FL@3Il4 ^E: Zero Dollar Contract Change Notification#2 Contract#l8-6O84 Pelican Bay Crmss.alk [nnstrnctipn Project#5006G Purchase Order#450Ol4754l I ear Mr. Gaudio: v copy of this letter, the above referenced work order is being issued a zero dollar( O.O0) change as ' 6inutedbe]on,: El The above referenced purchase order time is hereby extended by 14 calendar days. The previous total .umber of project completion days was 96 calendar days. The now final completion date shall be on or ,-fore January DI,80I4. � �,^ ~v extending this work order, the County is not relieving your firm of its obligations to perform work in a 1 zuo1y and satisfactory manner or any consequences resulting from failing to do so. Collier County hereby r,serves all legal /zgbro, including, but not limited ro, rights to tercnjoate, suspend or elect any other a oropriate course(s)of action should circumstances warrant with regard to the referenced work order. 11Addidouul Staffing Categories Professional Position(s) Hourly Rate(s) | JDraw against Allowance (specify allowance item and identify specific terns and uantiries) I Other: Specify (minor adjustments/c1arjficatins to scope. cxiStflg task aflocatwn and quantity a justments, re-allocation of dollar amounts between existing tasks andor clanfication of existing ta=ku) - /' 8i '� lz. / '' 1'-�~.~~-~--- .'� - 6 )yie Luicaez • Northrup, w/v,»l:- '>•• ••-'`r--'.3."'J'.-7 -/ - �--- �u�� ' / ' / ��-u�� ~-- / / / 'C Bonnie Baer, Clerk's Finance Division �- Packet Page-824- _��