Agenda 01/14/2014 Item # 16B3 1/14/2014 16.B.3. EXECUTIVE SUMMARY Recommendation that the Board of County Commissioners, as the Community Redevelopment Agency(CRA), approve a time extension Change Order#2 to a Work Order issued under Contract #09-5262-CI between the Collier County Community Redevelopment Agency (CRA) and Agnoli, Barber & Brundage (ABB) for Design Services associated with the Colorado Avenue Improvement Project in Immokalee. OBJECTIVE: To extend the project completion date set forth in Contract No. 09-5262 between the CRA and ABB for Design Services associated with the Colorado Avenue Improvement Project in Immokalee. CONSIDERATIONS: On March 9, 2010, agenda item #10C, the BCC voted to award request-for- proposal#09-5262, Engineering Services for Collier County, with ABB identified as the top ranked Civil Engineering(CI) firm. On February 8, 2013, CRA staff issued a work order and Notice-to-Proceed to ABB stipulating a total performance period of 330 days with a completion date of December 31, 2013. Zero Dollar Contract Change Notification,Change#01extended the performance period by 35 days to February 4,2014. The proposed Change order#2 will add an additional 320 days, further extending the performance period to December 21, 2014. This design services work order is related to a grant-funded construction project for which staff will require construction administration services from ABB during construction. Although the future construction contract will be grant-funded, this ABB professional services work order is being funded entirely by Immokalee MSTU Fund 162. This new expiration date will match the amended disaster recovery construction grant expiration date, which is currently under consideration by the Florida Department of Economic Opportunity(DEO). FISCAL IMPACT: This change is limited to a time extension only. This item has no fiscal impact. Although the future construction contract will be grant-funded, this ABB professional services work order is being funded entirely by Immokalee MSTU Fund 162. GROWTH MANAGEMENT IMPACT: Redevelopment efforts along Colorado Avenue further the programs and projects within the budgetary and policy guidance and directives of the CRA and the Board of County Commissioners in furtherance of Policy 4.2 of the Future Land Use Element of the Growth Management Plan which reads as follows: "The Immokalee Area Master Plan addresses conservation, future land use, population, recreation, transportation, housing, and the local economy. Major purposes of the Master Plan are coordination of land uses and transportation planning, redevelopment or renewal of blighted areas and the promotion of economic development." LEGAL CONSIDERATIONS: This item has been approved for form and legality and requires a majority vote. -JAB RECOMMENDATION: That the Board of County Commissioners approves the attached Change Order No. 2 for Contract No. 12-5262 for Design Services associated with the Colorado Avenue Improvement Project in Immokalee. Prepared By: Bradley Muckel,Executive Director(interim),CRA-Immokalee Attachments: 1) ABB Work Order, 2) ABB Notice to Proceed, 3) Change Order No. 1, 4) Proposed Change Order No. 2 Packet Page-836- 1/14/2014 16.B.3. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.B.16.B.3. Item Summary: Recommendation that the Board of County Commissioners, as the Community Redevelopment Agency (CRA), approve a time extension Change Order#2 to a Work Order issued off Contract#09-5262-CI between the Collier County Community Redevelopment Agency (CRA) and Agnoli, Barber& Brundage (ABB) for Design Services associated with the Colorado Avenue Improvement Project in Immokalee. Meeting Date: 1/14/2014 Prepared By Name: MuckelBradley Title: Project Manager, 1/2/2014 9:44:06 AM Submitted by Title: Project Manager, Name: MuckelBradley 1/2/2014 9:44:07 AM Approved By Name: MarkiewiczJoanne Title: Manager-Purchasing Acquisition,Purchasing& Gene Date: 1/8/2014 6:32:12 AM Name: MarkiewiczJoanne Title: Manager-Purchasing Acquisition,Purchasing&Gene Date: 1/8/2014 6:32:19 AM Name: Evelyn Colon Title: Purchasing-Procurement Specialist Date: 1/8/2014 8:09:03 AM Name: BelpedioJennifer Title: Assistant County Attorney,County Attorney Packet Page-837- 1/14/2014 16.B.3. Date: 1/8/2014 11:04:20 AM Name: KlatzkowJeff Title: County Attorney Date: 1/8/2014 11:20:33 AM Name: FinnEd Title: Senior Budget Analyst, OMB Date: 1/8/2014 12:58:53 PM Name: OchsLeo Title: County Manager Date: 1/8/2014 1:23:36 PM Packet Page-838- 1/14/2014 16.B.3. WORK ORDER Agreement for Fixed Term Professional Engineering Services Contract#09-5262 This Work Order is for professional engineering services for work known as: Colorado Avenue and South Fifth Street Improvements: Design. Bid Services and Construction Administration The work is specified in the Agnoli, Barber & Brundage (ABB) proposal dated January 29, 2013, which is attached hereto as "Exhibit A" and made a part of this Work Order. In accordance with the Terms and Conditions of the Agreement referenced above, this work order is assigned to ABB. Scope of Work: The work is specified in the Agnoli, Barber & Brundage (ABB) proposal dated January 29, 2013, which is attached hereto as "Exhibit A" and made a part of this Work Order. Task 1:Data Collection,Site Survey and Geotechnical Exploration$25,630.00 Task 2:Preliminary(30%)Design Document$20,945.00 Task 3:Develop(60%)Design Documents$20,278.00 Task 4:Pre-Final(90%)Design Documents$18,658.00 Task 5:Final(100%)Design Documents$6,660.00 Task 6:Permitting Services$9,840.00 Task 7:Bidding and Construction Administration Services$22,465.00 Task 8:Additional Meetings,Project Management and Quality Control$12,250.00 Schedule of Work: Tasks 1-5 are to be completed by June 28, 2013. All other tasks are to be complete by December 31, 2013. All work shall be complete within 330 days from receipt of the Notice-to-Proceed authorizing start of work. Compensation: In accordance with Article Five of the Agreement, the County will compensate the Firm in accordance with the established hourly rate(s) as enumerated in Schedule "B" of the base Agreement #09-5262. Not-to-Exceed amounts for each of the eight tasks are shown below. Task No. Description Hours Value$ 1 Data Collection,Survey and Geotech 126 25,630 2 Preliminary Design-30% 173 20,945 3 Developed Design-60% 174 20,278 4 Pre-Final Design-90% 162 18,658 5 Final Design-100% 52 6,660 6 Permitting 12 9,840 7 Bidding and Construction Assistance 170 22,465 8 Meetings,Project Management and Quality Control 88 12,250 TOTAL TASK AUTHORIZATION 1,016 136,725 Any change within monetary authority of this Work Order made subsequent to final department approval will be considered an additional service and charged according to Schedule "B" of the base Agreement#09-5262. Prepared By: Bradl-y Muckel, CRA PM 2/5/13 N Titl ,mil Date Authorized By: ,,,, i //' _ Cliennttnepartmen / ector Date Accepted By: 'Ag "•li, :arber�r�Dgdage, Inc. (Coa yT lam •thorized Co .any Officer , trot.e l : c 4 'i Ic'r ,S. 22'Jc- . Print Name &Title - Date • Packet Page-839- 1/14/2014 16.B.3. fr 4 o ie-r County Administrative Services Division Purchasing Friday, February 8, 2013 Mr. Ted Tryka Agnoli, Barber& Brundage, Inc. (ABB) 7400 Tamiami Trail North Naples, FL 34108 RE: NOTICE-TO-PROCEED FOR: Colorado Avenue and South Fifth Street Improvements Contract No. 09-5262 CI Purchase Order No. 4500142329 Dear Mr. Tryka: This letter serves as Collier County's official NOTICE TO PROCEED (NTP) for your company to commence with the items identified on purchase order #4500142329 which is based on ABB proposal dated 1/29/13, attached hereto as"Exhibit A". Commencement date for the services associated herewith shall be considered to be Tuesday, February 5, 2013. Substantial and final completion of all work shall be considered to be Tuesday, December 31, 3013. No work is authorized after the final completion date herein unless the time of the contract/work order is extended on or before the final completion date. Invoices for unauthorized work will not be paid. This NTP is limited to the scope of work identified in the attached ABB proposal identifying a total price not-to-exceed $136,725.00. The purchase order number is shown above and a copy of the purchase order is enclosed. Please include the purchase order number and contract number on each invoice to facilitate the payment process. If you have any questions, please feel free to contact me at 239.867.4121. Sincerely, Bradley Muckel Principal Project Manager Collier County Community Redevelopment Agency(CRA)- lmmokalee Cc: Christie Betancourt, Administrative Assistant, Immokalee CRA ABB—"Colorado Avenue" Master File Purchasing Departren°•3327 Tarniami Trail East•Naples.Florida 341'2-4901 •WW1 colfiergov.netlpurchasing Packet Page -840- 1/14/2014 16.B.3. ier County Purchasing Department Administrative Services Division Change Modification Form Purchasing ❑Contract Change Request ®Work Order Modification Contract#: 09- Mod#:02 PO/Work Order#: Project Name: County-Wide 5262-CI 4500142329 Engineering Services: Colorado Avenue Drainage/Sidewalk Improvements Project#: Project Manager: Department: Immokalee Contractor/Firm Name:Agnoli, Barber 4500142329 Bradley Muckel CRA &Brundage, Inc. (ABB) Original Contract/Work Order Amount $ 136,725.00 Original BCC Approval Date;Agenda Item# Current BCC Approved Amount Last BCC Approval Date;Agenda Item# Current ContractNVork Order Amount $ 136,725.00 3/8/2014 SAP Contract Expiration Date(Master) Dollar Amount of this Change $0.00 0.00% Total Change from Original Amount Revised Contract/Work Order Total $136,725.00 #DIV/Ol Change from Current BCC Approved Amount Cumulative Changes $0.00 0.00% Change from Current Amount Completion Date,Description of the Task(s)Change, and Rationale for the Change Original notice to proceed Last approved completion date: Revised completion date(includes this completion date: 12/31/13 02/04/14 change): 12/21/14 Number of days added(if Explain why additional days are needed (detailed/specific): extension,must attach current insurance certificate(s)from SIRE Due to heavy flooding over the project area, the site survey and design components of or obtain from vendor): 320 days the work order have taken longer than originally anticipated. Since the work order also includes a task for bidding and construction administration services,the performance period will need to be extended to coincide with the general contractor's performance period. In addition,construction of this project is being funded through a disaster recovery grant. Although the design for this project is now 100%complete,we can't begin the solicitation process for a general contractor until the environmental assessment identified in our grant agreement has been completed.The environmental assessment will be completed by the end of February-2014. ❑Add new task(s) ❑Change task(s) ❑ Delete task(s) ®Other(specify): Extension of performance period. 1. Provide a detailed and specific explanation of the requested change(s)to the task(s):The completion date is being extended from 2/4/14 to 12/21/14 so that the consultant can provide bidding and construction administration services, identified as Task 6 in their contract. 2. Provide detailed rationale for the requested change:The Engineer of Record for this project at ABB has been hired to provide certain construction administration services during the course of construction to include shop drawing reviews, contractor invoice review/approvals, periodic interpretation requests, as well as other miscellaneous services identified in ABB proposal dated 1/29/13.The construction period for this project will occur in the spring of 2014.Therefore, the subject ABB work order needs to be extended to accommodate the construction period. 3. Provide explanation why change was not anticipated in original scope of work: Due to heavy flooding that occurred over the project area in the summer of 2013,the surveying component of this work order could not be conducted as originally scheduled.The project had to be put on hold while the survey crews waited for the flood waters to subside.This postponed the completion of construction drawings. There have also been administrative delays in getting the grant-funded construction agreement and related SAP budget approved and activated. Revised:7/27/11 1 Packet Page-841- 1/14/2014 16.B.3. 4. Describe the impact if this change is not processed:The services of the Engineer of Record for the project ! would not be retained to perform shop drawing reviews, invoice review/approvals, periodic interpretation requests from the ■ GC during construction,as well as other engineering services. Type of Change I Modification ❑ 1. Planned/Elective ❑2. Unforeseen conditions/circumstance ❑3.Quantity or price adjustment 4. Correction of error(s) ❑5.Value added ®6. Schedule adjustment . , Change Requested By RContractor/Consultant ®Owner ❑ Using Department Design Professional O Regulatory Agency(specify): ❑Other(specify): Purchasing Professional Participated in Negotiation of Change!Modification: ❑ Yes ►Z� No Approved by: ��'''" �� Date: / 6• / Name and Title: r ey Muckel, CRA Executive Director(Interim) Reviewed by: Date: ' / /q ent Strs�Nar► : Eve n Colon ` • Procurement Y Revised:7/27/11 2 Packet Page -842- 1/14/2014 16.B.3. CHANGE ORDER#02 TO WORK ORDER Agreement for Fixed Tenn Professional Engineering Services Contract#09-5262 TO: Agnoli, Barber& Brundage, Inc. (ABB) 7400 Tamiami Trail North, Suite 200 Naples,FL 34108 239.597.3111 FROM: Immokalee CRA 750 South Fifth Street Immokalee,Florida 34142 Re:Engineering Services—Colorado Avenue Stormwater/Sidewalk Improvement Project PO Date: 02/08/2013 Work Order/Purchase Order#4500142329 Change Order#2 Notice to Proceed Date: 02/08/2013 Change Order Description: This change is limited to a performance period extension of 320 days. The NTP is dated 02/05/13.The current end date is 2/4/13. The new completion date is 12/21/14. Original work order amount $136,725.00 Sum of Previous Changes ..$0.00 This Change Order No. 2 Amount(add or subtract) $0.00 Revised Agreement Amount $136,725.00 Original work order time in calendar days 329 days Adjusted number of calendar days due to previous change orders ..35 days This change order adjusted time is 320 days Revised Contract Time in working days 685 days Original Notice to Proceed date February 5,2013 Completion date based on original contract time December 31,2013 Completion date based on Change Letter#01 February 4,2014 Revised completion date due to Change Order#02 December 21,2014 Your acceptance of this change order shall constitute a modification to the aforementioned Work Order and will be performed subject to all the same terms and conditions as contained in said Work Order, as fully as if the same were restated in this acceptance. The adjustment to this Agreement shall constitute a full and final settlement of any and all claims arising out of,or related to,the change set forth herein,including claims for impact and delay costs. Packet Page-843- 1/14/2014 16.B.3. Change Order No.2 Page`2 to this Agreement shall constitute a full and final settlement of any and all claims arising out of,or related to,the change set forth herein,including claims for impact and delay costs. �i Requested by 3 'L- �-�'" Date: (a•3 I-i 3 Bradley uckel,Interim Executive Director-Immokalee CRA Approved by: f P - roc_ Date: 1'2- - -/3 Evelyn Colon, rocurement Strategist ATTEST: BOARD OF COUNTY COMMISSIONERS Dwight E.Brock,Clerk Collier County,Florida By: By: Deputy Clerk Comm.Tom Henning Chairwoman Chairman rk By: Agr[o arber :m,11 Uo,p 1�llGk , JNJG41 V. P By: w ' ,' P //I4 (Witness One Name/Title) (Name and TOW By: (12---- 6?------, idreA, , deeSin ,, llw (Witness Two Name/Title) / I i Approved as to Form and Legality: Assistant County Attorney 9Q.P I 1 1 I • ¢, v Packet Page -844-