Loading...
Agenda 01/14/2014 Item # 16A 5 1/14/2014 16.A.5. EXECUTIVE SUMMARY Recommendation to approve Change Order No. 1 to Contract#09-5262CI in the amount of $10,850 with CardnoTBE, for "Independent Peer Review for the Chokoloskee Bridge Replacement" over Chokoloskee Bay for Project No. 66066.9.2 OBJECTIVE: Change Order No. 1 is required to provide reevaluation and consultation of the revised 60% Phase design engineering drawings and specifications being done by TY Lin International under contract#11-5639. CONSIDERATIONS: On September 10, 2013, the Board of County Commissioners (Board) approved Change Order No. 1 to Contract #11-5639 with TY Lin International under Item 11G. That approval authorized a design change in the bridge height by an additional 3 feet, the realignment of the existing parking areas and better access to the water. The Change Order also authorized an extension to the project's design schedule to January 20, 2016. The design is currently at the 60%Phase. CardnoTBE is currently under contract (#09-5262 CI) to provide independent peer review and consultation of the project's engineering drawing and specifications to insure their accuracy and to resolve any constructability concerns. This contract was suspended on September 10, 2013, due to the redesign. The purpose of the current Change Order No. 1 (Contract#09-5262CI) is to extend the contract time of the peer review process through to the 90% design phase and to fund the peer review of the modified 60% engineering documents. FISCAL IMPACT: Funds in the amount of$10,850.00 are available in gas taxes. The original Work Order Amount was $24,880.00. This Change Order No. 1 will be a 43.61% increase over the original fee, which would bring the total contract amount to $35,730.00, if approved. The engineer's estimate to replace the asset is at $4,436,527 and it will have an expected useful life of 100 years. Given the lifecycle costs of a bridge, projected maintenance costs are anticipated to be minimal for the first five to seven years in service. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires a majority vote for Board approval.—SRT GROWTH MANAGEMENT IMPACT: There is no impact to the Growth Management Plan related to this action. RECOMMENDATION: That the Board: 1. Approves the Change Order No. 1 to Contract 09-5262CI with CardnoTBE, and 2. Authorizes its Chair to execute the attached Change Order No. 1, following final County Attorney review. Prepared By: Marlene Messam, P.E., Senior Project Manager Attachments: 1) Scope and Fee Proposal for revised evaluation; 2) Change Order to Contract (09-5262 CI); 3) Modification#3 to Contract(09-5262 CI) Packet Page -439- 1/14/2014 16.A.5. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.A.16.A.5. Item Summary: Recommendation to approve Change Order No. 1 to Contract#09-5262CI in the amount of$10,850 with CardnoTBE,for "Independent Peer Review for the Chokoloskee Bridge Replacement" over Chokoloskee Bay for Project No. 66066.9.2 Meeting Date: 1/14/2014 Prepared By Name: MessamMarlene Title: Project Manager, Senior,Transportation Engineering 12/6/2013 4:02:26 PM Submitted by Title: Project Manager, Senior,Transportation Engineering Name: MessamMarlene 12/6/2013 4:02:28 PM Approved By Name: AhmadJay Title: Director-Transportation Engineering,Transportation Engineering&Construction Management Date: 12/20/2013 7:15:25 AM Name: LynchDiane Title: Administrative Assistant Date: 12/20/2013 8:36:46 AM Name: TaylorLisa Title: Management/Budget Analyst,Transportation Administr Date: 12/20/2013 9:46:33 AM Name: ShueGene Date: 12/20/2013 10:59:37 AM Name: LynchDiane Packet Page -440- 1/14/2014 16.A.5. Title: Administrative Assistant Date: 12/20/2013 11:00:41 AM Name: ShueGene Date: 12/20/2013 2:39:20 PM Name: PutaansuuGary Title: Project Manager,Principal,Transportation Engineer Date: 12/22/2013 10:29:24 AM Name: LynchDiane Title: Administrative Assistant Date: 12/23/2013 10:03:45 AM Name: MarkiewiczJoanne Title: Manager-Purchasing Acquisition,Purchasing&Gene Date: 12/23/2013 10:15:25 AM Name: LynchDiane Title: Administrative Assistant Date: 12/23/2013 10:54:44 AM Name: CummingsRhonda Title: Contracts Specialist,Purchasing&General Services Date: 12/23/2013 11:10:01 AM Name: LynchDiane Title: Administrative Assistant Date: 12/23/2013 11:33:20 AM Name: MarcellaJeanne Title: Executive Secretary,Transportation Planning Date: 12/26/2013 2:00:15 PM Name: TeachScott Title: Deputy County Attorney,County Attorney Date: 12/27/2013 8:39:28 AM Name: KlatzkowJeff Title: County Attorney Date: 1/6/2014 9:22:09 AM Name: UsherSusan Title: Management/Budget Analyst, Senior,Office of Manage Packet Page -441- 1/14/2014 16.A.5. Date: 1/6/2014 4:23:07 PM Name: OchsLeo Title: County Manager Date: 1/7/2014 9:28:59 AM Packet Page -442- 1/14/2014 16.A.5. 1/4124 Cardno Scope of Services Independent Peer Review Services for Chokoloskee Bridge (030161) Replacement 60% Resubmittal Change Order for Constructability Review Collier County Project Number: 66066 Packet Page -443- 1/14/2014 16.A.5. Scope of Services: Independent Peer Review for Chokoloskee Bridge(030161)Replacement 60%Resubmittal Change Oder for Constructability Review "Independent Peer Review Services for Chokoloskee Bridge Replacement" 1) SCOPE STATEMENT This scope of services is for the independent peer review and consultation on all design engineering drawings and specifications done by others to insure their accuracy and to resolve issues of concern with constructability, relevant codes, including County, FDOT and AASHTO standards, specifications, and recognized engineering practices. The objective is to avoid major changes during construction. As part of the independent peer review services the CONSULTANT will include but not be limited to the independent confirmation of the following: 1. Compatibility of bridge geometry with roadway geometrics including typical sections, horizontal alignment, and vertical alignment. 2. Compatibility of construction phasing with Traffic Control Plans. 3. Potential Conflicts with underground and overhead utilities. 4. Compliance with County, FDOT and other agency design requirements. 5. Conformity to County and FDOT Standards. 6. Structural Analysis Methodology and assumptions. 7. Completeness and accuracy of bridge and roadway plans. 8. Constructability issues. 2) PURPOSE The purpose of this Exhibit is to describe the scope of work and the responsibilities of the CONSULTANT and the COUNTY in connection with the preparation of reports based on the review of the construction documents and calculations provided during the resubmittal of the 60% design phases of the Chokoloskee Bridge Replacement, herein called the Project. 3) SCOPE OF SERVICES A. Proiect Description: The principal intent of the Project is to replace the existing functionally obsolete bridge (030161) located 5.4 miles south of US41 and on CR 29 (Copeland Avenue) over the Chokoloskee Bay in Collier County, Florida. The existing bridge has been deemed scour susceptible and was constructed in 1955. The replacement bridge will have two lanes with bike lanes/shoulder on each side and sidewalks. The 60% Phase was resubmitted based on feedback from the public information meeting. The changes include: the bridge was made higher and substructures redesign. 2 Packet Page -444- 1/14/2014 16.A.5. Scope of Services: Independent Peer Review for Chokoloskee Bridge(030161)Replacement 60% Resubmittal Change Oder for Constructability Review B. Project Tasks: This scope of work will cover the following tasks: Task 1R: Provide constructability review of the Project at the end of the 60% design Phase. This includes the review of the roadway and structural plans, design, design studies, design calculations for the items that have changed as a result of the 60% resubmittal and verification of incorporation of the original review comments. The constructability review should concentrate on the ability of specific details to be constructed within the requirements of the plans and to propose better details if possible. Task 2R: Prepare a detailed set of constructability review comments based on the work performed under Task 1R. Task 5R: Meeting and or coordination with the County and the Project designers C. Project Design Assumptions: All standards will be prepared in following formats: Design Specification: AASHTO LRFD Bridge Design Specifications—4th Edition CADD Platform: Bentley Microstation V8 Specifications: Collier County Specification Format prepared in WORD All design calculations used for the development of standards are cataloged in the project calculation book and will be made available to the reviewer. D. Work Plan: The Independent Design Peer Review for Constructability Review Check involves the following activities: I. Structural, constructability review of the Project Provide complete comments on the following bridge elements as detailed in the plans. i. Review the structural plans and insure that they are constructible, consistent, clear and complete. ii. Provide check of quantity calculations and cost estimate and provide guidance as required. II. Provide review of the supplemental roadway plans i. Review the roadway plans for completeness, constructability. ii. Provide check of quantity calculations and cost estimate and provide guidance as required. 3 Packet Page-445- 1/14/2014 16.A.5. Scope of Services: Independent Peer Review for Chokoloskee Bridge(030161)Replacement 60% Resubmittal Change Oder for Constructability Review III. Meetings! Coordination i. The Consultant shall attend one review meetings with County staff and design consultant. The meeting will occur at the end of Task 2R after the submittal of the constructability review comment documents for the purpose of discussing the comments. E. Deliverables: Consultant will furnish documents as required by the County to adequately address the independent design peer review check comments. The CONSULTANT shall provide the County copies of the documents for distribution, as follows: Constructability (60%) review comments 2 sets 8.5" x 11" bound 4) OMPENSATION The fee for this project will be a negotiated lump sum basis for all Tasks in accordance with the AGREEMENT FOR PROFESSIONAL SERVICES as detailed in Attachment 1. 4 Packet Page-446- 1/14/2014 16.A.5. Attachment I Car drT+o Task Assignment Breakdown TBE Project Name:Chokoloskee Bridge Replacement Independent Peer Review/Re-Submittal 60%Constructability Review Project Number:66066 Contract Number:09-5262 CL Task Description _ Structural Sr. oadway Environmental f Total (Engineer Engineer Specialist / Clerical Hours Total Fee $155.00 y'w'-$T55A0 $115.00 $60.00 1R ?Constructability Review at 60% Design Phase ,Structures 32 32 $4,960 Roadway/Drainage/Hydraulics 20_T 20 $3,100 Task 1R Subtotal 32 20 52 $8,060 2R Constructability Deliverables Structural Review Comments 8 8 $1,240 • Roadway Review Comments _ 6 6 $930 Task 2R Subtotal I 8 6 14 $2,170 SR Meetings/Coordination / 4 $620 60%Constructability Review Meeting 2 2 I -� 4 $620 ►' _-...__..._.__ --.._..............-- -- -..........- Task SR Subtotal 2 2 /' 1, _...._— is 0 � 70 $10,850 Project Grand Total 42 28 8 0 Packet Page-447- 1/14/2014 16.A.5. Cotner County Purchasing Department Adrrtinistfative Services Division Change Modification Form Purchasing ❑ Contract Change Request ®Work Order Modification Contract#: 09- Change#: 1 PO/Work Order#: Project Name: Independent Peer Review 5262CI Bridge — 4500138762 for Chokoloskee Bridge Replacement Project#:66066.9 Project Manager. Department:Transp. Engr. Contractor/Firm Name: CardnoTBE Marlene Messam Original Contract/Work Order Amount $ /24,880.00 n/a Original BCC Approval Date;Agenda Item it Current BCC Approved Amount $ 24,880.06 n/a Last BCC Approval Date; Agenda Item# Current Contract/Work Order Amount $ 24,880.00 SAP Contract Expiration Date(Master) Dollar Amount of this Change $ 10,850.00 43.61% Total Change from Original Amount Revised Contract/Work Order Total $ ,/ 35,730.00 43.61% Change from Current BCC Approved Amount Cumulative Changes $ 10,850.00 43.61% Change from Current Amount Completion Date,Description of the Task(s)Change,and Rationale for the Change Original completion date: Last approved completion date: Revised completion date(includes this . 8/25/2013 / 12/22/2013 change):7/21/2014 Number of days added:330 /Each step on the contract modification checklist form has been reviewed prior to me . ✓ submitting for approval M.A.M.(this box must be initialed by Project Manager) ❑Add new task(s) ®Change task(s) ❑Delete task(s) ®Other(specify): Redo Task#1 1.Provide a detailed and specific explanation of the requested change(s)to the task(s)and/or the additional days added:The 60%Phase of the Chokoloskee Bridge Replacement is being redesigned by the Primary Consultant TYLIN under contract#11-5639.This redesign was approved by the BCC on 09/10/2013 by change order No. 1 (Item No.11 G).As a result of the redesign, CardnoTBE contract#09-5262CI(Bridge)was suspended on 09/10/2013.This change order seeks to reinstate the contract by adjusting time and provides a fee increase to redo the independent peer review of the redesigned 60%plans. 2.Provide detailed rationale for the requested change:The services of CardnoTBE are needed to provide independent peer review of the design documents and calculations because the evaluation and analysis of bridge structures are not available in house and the County typically utilizes the services of consultant to provide these services.Since the redesign of the 60%phase will result in a significant change in the project,a second independent peer review became necessary. 3.Provide explanation why change was not anticipated in original scope of work:The Chokoloskee Bridge Replacement 60% Phase redesign was as a result of public feedback and was approved by the Board.These events could not have been anticipated; therefore, no provision was made in the original scope for a second independent peer review of the 60%design phase. 4.Describe the impact if this change is not processed:In house staff is not able to provide the level of structural analysis and evaluation that is required for public, health, and safety. If this change order is not approved, the County would not be providing due diligence in ensuring the public benefits. Type of Change/Modification ❑ 1. Planned/Elective 2. Unforeseen conditions/circumstance ❑3.Quantity or price adjustment l 4.Correction of error(s) 0 5.Value added El 6. Schedule adjustment Change Requested By ❑Contractor/Consultant n Owner Using Department Revised:7126/13 1 i Packet Page -448- - 1/14/2014 16.A.5. ❑ Design Professional ❑Regulatory Agency(specify): []Other(specify): Purchasing Pro - •nal Participat=• in Negotiation of Change I Modification: [J Yes ❑ No r ... ,4.. Approved by: ' I t #/ 4 r Date: a-// '"I Name and Title:0 rte'ne;Messaj , P.E., Sr ,"roject Manager Reviewed by: Q / ,-f Date: ft)7.:9 „,i) Procurement Strategist's Name:Evelyn Colon Revised:7/26/13 2 Packet Page -449- 1/14/2014 16.A.5. CHANGE ORDER TO WORKORDER TO:CardnoTBE FROM: Transportation Engineering 22 Sarasota Center Blvd. 2885 South Horseshoe Drive, Sarasota,Florida 34240 Naples,FL 34104 Project Name:Independent Peer Review for Chokoloskee Bridge Replacement Project Number:66066.9 .2 Work Order Date: 10/29/2012 Work Order/Purchase Order No.:4500138762 Change No.: 1 Date: 12/4/2013 Change Order Description: This change order is to: Change time and Change price_ See the attached Scope and fee proposal Original agreement amount $24,880.00 Sum of Previous Changes ..$0.00 This Change Order No. 1 Amount(add) $10.850.00 Revised Agreement Amount $35,730.00 Original contract time in calendar days 300 days Adjusted number of calendar days due to previous change orders .0 days This change order adjusted time is 330 days ,gi t4,A -M Revised Contract Time in working days days Original Notice to Proceed date 10/29/2012 1 Completion date based on original contract time 08/25/2013 d Revised completion date due to change order(s) 07/21/2014 1,/ • Your acceptance of this change order shall constitute a modification to our Agreement and will be performed subject to all the same terms and conditions as contained in said Agreement indicated above, as fully as if the same were repeated in this acceptance. The adjustment,to this Agreement shall constitute a full and final settlement of any and all claims arising out of,or related to,the change set forth herein,including claims for impact and delay costs. Accepted: January 14,2014 ATTEST: OWNER: BOARD OF COUNTY COMMISSIONERS COLLIER COUNTY,FLORIDA Dwight E.Brock,Clerk By Georgia A.Hiller,Esq.,Chairwoman (3) Packet Page -450- 1/14/2014 16.A.5. Change Order No. Page 2 CONTRACTOR: 61 CardnoTBE_ ( / t. /1, , . , /'� D n I. lene M :•:7,7.E.,Project Manager By: P er Nikolov,P.E.,Sr.Vice President DEP• •TMENT DIRECTOR �-C -4. ([[ ' 1= _ u r By: `A. Co . . .r First Witness "" , ! /i 2- i 3 rn r*rte. 0, rfcc -- 1U P I 1 Type/print witness name ij C/ /�` l�.;(1e1.1� ,,� ,r� IVISIa. t "1/00100e e ' TOR Con r Second.Witness ..A B� —� ��ra 1 Z 4 d' ,, gip , I l t.1 1 tier"��'r`, i� '`') Nick Canal•■1 i•r I - Type/print witness name PRt (_REMENT STRATEGIST 1 f j �f By: L`t f J t Yom' 1 )t 4 0 l 12) Evelyn Colon Approved as to form and legality: f1 Deputy County Attorney 0 4:11, Packet Page -451-