EXECUTIVE SUMMARY
Recommendation to approve Change Order #1 to Contract 14-6255R with BSSW Architects, Inc.
for Collier County Sheriff Office (CCSO) requested scope additions to the new Orangetree
Substation.
OBJECTIVE: To update the design of the new Orangetree Substation to account for the present
and future facility needs identified by the CCSO during the preliminary conceptual development
phase of the current scope of work.
CONSIDERATIONS: The Board approved the current design contract at the July 8, 2014,
BCC meeting under item 16E8. The approved project design scope was based on a 2006 concept
plan to move the CCSO's personnel out of an existing double wide trailer located on the
Corkscrew Elementary School grounds and to provide a 6,000 sq. ft. building to accommodate
them in a proper substation facility. The 2006 project was postponed during the recent recession
due to budget restraints.
During the current conceptual design phase involving many meetings with the CCSO operational
personnel, the CCSO determined that the facility would need to be larger based on growth that
has occurred in the area served by this substation during the intervening eight (8) years,
recognition of the CCSO's current law enforcement strategies, and taking into account the
anticipated future growth in the area. The proposed facility needs to accommodate the planned
additional personnel to cover investigations and patrol, more flexible storage and office space for
future needs, and storage of the Mutual Aid Dispatch — Interoperable Communication Unit
(MAD-ICU) vehicle in an air conditioned garage. This increase in the facility configuration will
result in more Architectural, Engineering and Site Development design plans. The building will
increase from the original 6,000 sq.ft. to a total of 8,486 sq.ft., a 41% increase to the size of the
facility from the original design concept.
FISCAL IMPACT: Funds in the amount of $49,000 for this increased design cost as well as
$851,000 for the additional construction cost have been budgeted in the FY2016 budget within
Impact Fee Fund 385.
GROWTH MANAGEMENT IMPACT: There are no Growth Management Impacts associated with
this action.
LEGAL CONSIDERATIONS: This item has been approved as to form and legality and requires a
majority vote for Board action. -CMG
RECOMMENDATION: That the Board approves Change Order #1 to Contract 14-6255R with BSSW
Architects, Inc., for the CCSO requested scope additions to the new Orangetree Substation in the amount
of$49,000.
Prepared by: Hank Jones,Principal Project Manager, Facilities Management Division
Attachments: Change Order#1
Packet Page -1296-
11/10/2015 16.E.1 .
Packet Page-1297-
11/10/2015 16.E.1 .
COLILIER COUNTY
Board of County Commissioners
Item Number: 16.16.E.16.E.1.
Item Summary: Recommendation to approve Change Order#1 to Contract 14-6255R with
BSSW Architects, Inc. for Collier County Sheriff Office (CCSO) requested scope additions to the
new Orangetree Substation.
Meeting Date: 11/10/2015
Prepared By
Name: JonesHank
Title: Project Manager, Principal, Administrative Services Department
10/7/2015 3:59:19 PM
Submitted by
Title:Project Manager, Principal, Administrative Services Department
Name: JonesHank
10/7/2015 3:59:20 PM
Approved By
Name: pochopinpat
Title: Operations Coordinator, Administrative Services Department
Date: 10/9/2015 11:04:11 AM
Name: MarkiewiczJoanne
Title: Division Director-Procurement Services,Procurement Services
Date: 10/12/2015 9:59:55 AM
Name: LinguidiDennis
Title: Division Director-Facilities Mgrnt,Facilities Management
Date: 10/13/2015 5:07:13 PM
Name: JohnsonScott
Title: Manager-Procurement, Procurement Services
Date: 10/14/2015 9:20:09 PM
Packet Page-1298-
11/10/2015 16.E.1 .
Name: JohnsonScott
Title: Manager-Procurement,Procurement Services
Date: 10/14/2015 9:20:44 PM
Name: CummingsRhonda
Title: Procurement Specialist,Procurement Services
Date: 10/19/2015 12:45:46 PM
Name: CummingsRhonda
Title: Procurement Specialist, Procurement Services
Date: 10/19/2015 12:45:54 PM
Name: GreeneColleen
Title: Assistant County Attorney, CAO General Services
Date: 10/22/2015 12:02:06 PM
Name: PriceLen
Title: Department Head-Administrative Svc, Administrative Services Department
Date: 10/22/2015 1:18:17 PM
Name: GreeneColleen
Title: Assistant County Attorney, CAO General Services
Date: 10/22/2015 1:37:07 PM
Name: KlatzkowJeff
Title: County Attorney,
Date: 10/28/2015 11:08:58 AM
Name: WellsLaura
Title: Management/Budget Analyst, Senior, Office of Management& Budget
Date: 10/29/2015 10:07:21 AM
Name: CasalanguidaNick
Title: Deputy County Manager, County Managers Office
Date: 10/30/2015 9:22:58 AM
Packet Page-1299-
11/10/2015 16.E.1 .
Procure nt Services
1.---- m. . , Change Order Form
``il Contract Modification 0 Work Order Modification 0 Amendment
Contract#: 14-6255R Change#: 1 Purchase Order#: 4500152058 Project#: 52011
. f
Contractor/Firm Name: BSSW Architects,Inc. Contract/Project: CCSO Orange Tree Sub-Station)
Project Manager Name: Robert Fuentes/Hank Jones Division Name: Facilities Management
Original Contract/Work Order Amount $: . 220,700.00 7/08/14 16E8 Original BCC Approval Date;Agenda Item#
Current BCC Approved Amount . :$' 220,700.00 7/08/14 16E8 Last BCC Approval Date;Agenda Item#
Current Contract/Work Order Amount $; 220,700.00 5116/2016 SAP Contract Expiration Date(Master)
Dollar Amount of this Change $• 49,000.00 22.20% Total Change from Original A.mount
Revised Contract/Work Order Total $ 269,700.00 22.20% Change from Current BCC Approved Amount
Cumulative Changes $ 49,000.00 22.20% Change from Current Amount
.
.. i Completion Date,De4ription of the Task(s)Change,and Rationale forthe Change t
Notice to Proceed 8/05/2014 Original 5/16/2016 Last Approved 5/16/2016 Revised Date 1/21/2017
Date , Completion Date Date (Includes this charge)
#of Days Added 250 Select Tasks 0 Add new task(s) 0 Delete task(s) 0 Change task(s) d Other(see below)
Provide a response to the following:1.)detailed and specific explanation/rationale of the requested change(s)tin:the task(s)and 1 or
the additional days added(if requested);2.)why this change was not Included in the original contract;and,3.) 4E/scribe the impact if
this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed..
1- Original project design scope was based on an eight(8)year old concept scope to provide a 6,000 sq.ft building to
accommodate Collier County Sherriffs personnel in a proper building and move them out of an existing double wide trailer
located on the Corkscrew Elementary School grounds.During the current preliminary design phase,the CCSO determined
that the facility would need to be larger based on the developmental growth in the area served during the intervening eight(8)
years;and recognizing the CCSO's current law enforcement strategies. The larger facility needs to accommodate additional
personnel to cover investigations and patrol,storage of the MADIOCU vehicle in an air condition garage with more flexible
storage and office space.This increase in the facility configuration will result in more Architectural, Engineering and Site
Development design plans. The building will increase to a total of 8,486 sq.ft,a 41%increase from original design concept,
2- This change was not anticipated due to the fact that this project was previously conceived during Fiscal 20061 007,but was
cancelled due to the economy and funding issues,and was based on a concept for only providing a maximum space of 6,000
sq.ft.
3- If the change order is not approved,the CCSO substation will have to be scaled back to the 2007 concept sixeitof only 6,000
sq.ft.,and will be inadequate for ttie CCSO current requirements and have no room for expansion in the future. The result will
be a subsequent,future project for additions to the building and site the cost of which will far exceed the amount of this
change order. Additionally,the construction costs of the inevitable additions will be costlier due to inflationaryiconstruction
costs. ,d.,t} -,,
f'' .,,; ` / rti
Prepared by d' °' %±. 4 Date: :ve.f
/ Robert Fuentes Project Manager,Facilities`fac„ ment Division
Acceptance of this Change Order shaft constitute a modificatiorkloiriontract I work order identified above and will be subject to all the same
terms and conditions as contained iri'the contract/work order indicated above,as fully as if the same were stated in this'' ceptance. The
adjustment,if any,to the Contract shall constitute a full and final settlement of any and all claims of the Contractor i Vend /Consultant/
Design Professional arising out of or related to the change set forth herein,including claims for impact and delay costs. • i
Accepted by: Date:
__SSS_W Archiects,lnc.
11 - es--',:x._. ,u_ _ g r, '+=r-�.j , q C� i 1 •,,- ffi''�'• Date !t ' -''
Approved by 1 ._.. ;,. .'
( esigr,►Professio l and Marne of Finn,if project applicable) i f
/ / r
'proved by-r` ,i s, -L-^;; Y,.,.- ( 1:1!i<`LL ,—,--<`W Date: 1 I . l
: I
!
(Pro i rement Professional)
I
• (Divisions who may require additional Signatures may include on separate sheet.)
Revised'10/21/2014
Packet Page-1300- i i
11/10/2015 16.E.1 .
CHANGE ORDER#1
Exhibit A
Architecture and Engineering Services for Sherriffs Office at EMS-12 Orange Tree
Contract#14-6255R
A. Summary of Work:
1. Background:
BSSW Architects Inc. was retained to develop a program, and building design for the existing and future needs of the
Collier County Sheriffs Office at Orange Tree in an approximately 6000 square foot addition to the current EMS 12 facility
or a freestanding structure.
Through the preliminary design process it was determined that a free standing facility would be most economical and better
serve the needs of the CCSO. With that decision, and the additional flexibility that an independent structure afforded, the
CCSO would like to increase the scope of the project to include expanded work areas and offices, equipment storage area
and a conditioned garage for the MADIOCU vehicle. Outdoor door service areas are also desired for a patrol car wash-
down, expanded service equipment yard, secure parking area and a concrete pad for the Portable Mutual Aid Tower(MAT).
Additional work will also include alternate design for fire service as originally planned connection to the county facility will
not be available.
These items will increase the scope of Site Design and Building Design and associated Engineering services for this
project. The original building program defined by the contract was "approximately 6000" square feet. The final building
design, with the additional desired program areas, will be approximately 8,486 square feet, a 41% increase in the building
size.
We therefore are requesting additional fees for the increased effort needed within all professional disciplines for the project.
All other provisions of the original referenced contract remain unchanged.
2. Additional Professional Architecture and Engineering Fees for this Change Order:
Task 1:Preliminary Site Design and Building Design
• Architectural Design and Civil Site design
Increase scope in final Site Design for bidding
and construction documents. $ 7,000.00
Task 2: Design
• Arch, MEP, FP, Civil& Landscape Design
increase in scope for final Building Design
for bidding and Construction Documents. 37,000.00
1500 JAC .oN ST ;,:200 FOOT IUIYFRS FL 33901 HO CE! FRAAAL.A\1dl1E NAPLES FL 34102
PH 239.2 8 3338 OX: 239.275 5353 HI 239.63113 3103
C /A 1 1 0 1 4 AND PERI— ORM N C F I i,! C; ! L : e:. t: t,' . , C a C F<' : ; i r. 1!.
Packet Page-1301-
11/10/2015 16.E.1.
CHANGE ORDER#1
"rch tecture and Engineering Services for Sheriffs Office at EMS-12 Orgnge Tree
treet#14-52558
Task 3: Building Permit Submittal
No change 0.00
Task 4: Bidding Support
Increase scope of services 750.00
Task 5: Post Design and Construction Admin.Services
• Arch,MEP, FP,&Landscape
Increase scope of services 4,250.00
Total additional professional fees this change order $ 49,000.00
Fee Summary:
Original Contract Sum: $220.700.00
Total Contract Sum with Change Order 1 $269,700.00
Packet Page -1302-
11/10/2015 16.E.1 .
Send all Invoices to:
Collier County Board of County Commissioners `,t Collier County Board of County Commissioners
Purchasing Department t
� Attn:Accounts Payable
Phone:239-252-8407 : '= 3299 Tamiami Tr!E Ste 700
Fax: 239-732-0844 ;; Naples FL 34112-5749
Tax Exempt:85-8015966531C-1 OR email to:bccapclerk @collierclerk.com
Purchase Order number must appear on all related
correspondence,shipping papers and invoices:
vendor# 108712 .Purchaselorder„ a-`
BSSW ARCHITECTS INC
Po Number 4500152058 Dare 08/04/2014
1500 JACKSON ST,STE 200 contact Person County Capital Pro
FT MYERS FL 33901
Please deliver to:
FACILITIES MANAGEMENT Delivery Date: 02/09/2017
3335 TAMIAMI TRL E, STE 101
NAPLES FL 34112-5356
Terms of Payment Net 30 Days Currency USD
Item �'. -"'"r`:. - ,, ..,.. . Order;Q '�'Unit- ..,Price Per Unit 6
Material Description ty �r Net Yalul:
00010 SUBSTATION @ EMS-12 ORANGETREE CCSO 173,000 each 1.00 173,000.00
Release order against contract 4600003784 Item 00010
00020 SUBSTATION @ EMS-12 ORANGETREE CCSO 47,700 each 1.00 47,700.00
Release order against contract 4600003784 Item 00010
Total net vatue excl.tax USD 220,700.00
VENDOR Terms and Conditions
The VENDOR agrees to comply with all Purchase Order Terms and Conditions as outlined on the Collier County Purchasing Internet site:
http://www.colliergov.net/Index.aspx?page=762(revision date 01/22/2008),including delivery and payment terms.Further the VENDOR agrees to:
1. Provide goods and services outlined in this Purchase Order with the prices,terms,delivery method and
specifications listed above.
2. Notify department Immediately if order fulfillment cannot occur as specified.
3. Send all invoices to:
Collier County Board of County Commissioners
Attn:Accounts Payable
3299 Tamiami Tr!E Ste 700
Naples FL 34112-5749
OR email to:bccapclerk@collierclerk.com
The Purchase Order is authorized under direction of Collier County Board of County Commissioners by:
Joanne Markiewicz,General Services/Purchasing Director
Prtnted 08/05/2014 @ 07:2127 385-120433-752200.52011.1 Page I of 1
Packet Page -1303-
'�
11/10/2015 16.E.1.
CO ier County
Administrative Services Division
August 5, 2014 Facilities Management
Mr. Dan Summers AlA
BSSW Architects, Inc.
1500 Jackson St., Suite 200
Ft. Myers, Fl. 33901
RE: NOTICE-TO-PROCEED FOR
Professional Architectural Services for the Orange Tree Collier County Sheriffs
Sub-Station.
RFP-1462-55R July 8, 2014 16E8
Purchase Order No. 4500152058
Collier County Project No.52011
Dear Mr. Summers:
This letter serves as Collier County's official NOTICE TO PROCEED (NTP) to your
Company to commence with the above referenced project. This NTP is issued pursuant
to Contract #RFP-1462-55R. The purchase order number is shown above and a copy
of the P.O. is enclosed.
This NTP is limited to All Tasks of the scope of work for: Professional Architectural
Services including, Programming, Architectural Drawings, Construction Documents,
Bidding, Construction Administration and Close out Documents for the Negotiated Sum
Not to exceed price of $ 220,700.00. Please include the purchase order number,
contract number and project number on each invoice to facilitate the payment process.
Commencement date for the services associated herewith shall be considered to be
August 5, 2014. Final completion of all work shall be considered to be May 16, 2016,
for a total of 650 days. No work is authorized after the final completion date herein
unless the time of the contract/work order is extended on or before the final completion
date. Invoices for unauthorized work will not be paid.
If you ha any questions, please contact me.
Sincer,,y)
ly,
r y. 71
. .
Robert Fuentes /
Project Mana er
I
Department of Facilities Management•3335 Tamiami Trail East,Suite 101 •Naples,Florida 34112-5356•239-252-8380•FAX 239-793-3795
Packet Page-1304-
Dineen rinlivnr fn.
11/10/2015 16.E.1 .
EXECUTIVE SUMMARY
Recommendation to approve award of contract 14-6255R CCSO Substation at
EMS-12 Orange Tree to BSSW Architects Inc. for professional engineering
services, approve an associated budget amendment, and authorize the Chairman
to execute the approved contract.
OBJECTIVE: To provide for professional engineering services for the design and construction
of the Orange Tree Sheriff's Substation.
CONSIDERATIONS: On 6/24/2014, the BCC approved the ranking and authorized staff to
negotiate a contract with the top ranked firm.
Pursuant to the Competitive Consultant's Negotiation Act, Florida Statute Section 287.055, staff
has negotiated and reached agreement with the top ranked firm, BSSW Architects Inc. for a
T&M-not to exceed amount of$220,700 for all professional services, design thru construction.
FISCAL IMPACT: The Source of funds is the Law Enforcement Impact Fee, Fund 385, Project
52011. That project currently has $50,000 available, and a Budget Amendment transferring the
additional amount required of $173,000 is attached. The remaining funds required for physical
construction of the project are included in the FY2015 Budget Submission.
GROWTH MANAGEMENT IMPACT: There is no impact to the Growth Management Plan
related to this action.
LEGAL CONSIDERATIONS: This item has been approved as to form and legality and requires
majority vote for approval. - CMG
RECOMMENDATION: That the Board of County Commissioners authorizes the Chairman to
execute the County Attorney approved contract 14-6255R and approve the required Budget
Amendment.
PREPARED BY: Hank Jones, Principal Project Manager, Facilities Management
Packet Page-1305-