Agenda 04/06/2004 Wr
Joint BCC and City of Naples Workshop
9:00 a.m., April 6, 2004
Collier County Board of County Commissioners Boardroom
3301 East Tamiami Trail
Naples, FL 34112
1. Update on Golden Gate Parkway/Airport-Pulling Road
Intersection Improvements
2. City of Naples Comprehensive Plan Amendment
3. Annexation Policy
4. Waterside Shops and other Commercial Interests
5. Second Gordon River Bridge Options
6. FEMA FIRM Negotiations
EXECUTIVE SUMMARY
A REVIEW OF ALL FEASIBLE PLANNING & DESIGN ALTERNATIVES
(CONVENTIONAL & UNCONVENTIONAL) FOR INTERSECTION IMPROVEMENTS
AT AIRPORT-PULLING ROAD/GOLDEN GATE PARKWAY AND THEIR IMPACT ON
ALL OTHER MAJOR INTERSECTIONS ALONG THE GOLDEN GATE PARKWAY
CORRIDOR. A GRADE SEPARATED OVERPASS IS THE ONLY ALTERNATIVE
ACHIEVING AN ADEQUATE LEVEL OF SERVICE IN 2025 WHILE PROVIDING THE
MOST COST EFFECTIVE, LONG-TERM BENEFIT TO TAXPAYERS.
OBJECTIVE: To present comprehensive data, analysis and information to the Board of County
Commissioners, Naples City Council, and Collier County citizens regarding various improvements
to the Airport-Pulling Road/Golden Gate Parkway intersection resulting from extensive study by
staff and five professional consulting firms. All conclude that a grade separated overpass is the only
alternative achieving an adequate level of service in 2025 while providing the most cost effective,
long-term benefit to taxpayers.
CONSIDERATION: Collier County is approaching the completion of a $1.8 million design effort
that will substantially address existing transportations deficiencies at the intersection of Airport-
Pulling Road and Golden Gate Parkway, and more importantly, accommodate transportation needs
well into the future. This $1.8 million design cost does not include an additional $435,000 the
County has already spent on supplemental studies, analysis and reports considering alternative
improvements and impacts along the corridor. The design effort to date is in accordance with a
decade of extensive planning and preparation by City and County officials. The project, a grade
separated overpass, is one critical step in a series of improvements to occur along the Golden Gate
Parkway corridor. Such improvements include the 6-lane expansion currently under construction,
the 1-75 interchange to be completed in 2007, and the Goodlette-Frm~ Road improvements to begin
early in 2005.
In reviewing a decade of plmming, this project is specifically called out within the Halstatt (Grey
Oaks, Estuary & Naples Grande) Development of Regional Impacts (DRI)/PUD, which was
approved under an Interlocal Agreement between the City and the County in 1990. This
development was required to reserve the rights-of-way for an overpass with Golden Gate Parkway
to fly over Airport Road. An overpass was identified as a need in the Metropolitan Plarming
Organization's (MPO's) Long Range Transportation Plan since 1993. The project was also
identified in the County's Transportation 5-Year Funded Work Program since 2001. In 2002, the
County received notice that it was the recipient of $7.45 million in grant funding from the State of
Florida (TOPS Grant) specifically for the proposed improvements to the Parkway which included an
overpass to handle the traffic increase fi'om the new 1-75 interchange. As part of the overall corridor
study, as well as concerns expressed by the City of Naples, the County advanced improvements to
Goodlette-Frank Road in its 2002 update to the 5-Year Transportation Work Program.
To evaluate all conventional and unconventional alternatives to
improve the intersection and corridor, the County has worked
with five different professional consulting firms; and the City has
worked with one firm. Kimley-Horn's first study looked at
improvements to several intersections throughout the County and
evaluated those intersections against several criteria including
existing and future traffic conditions, activity centers, whether the
roadways are evacuation routes, and parallel roadway options.
The Grade Separation Study indicated that even with at-grade
intersection improvements this intersection would fail from a
level of service standpoint, which would cause a severe delay to
the transportation system. Even if at-grade improvements were
designed to include free flow rights and triple lefts along with six
through lanes for each approach, the intersection still fails to
operate at an acceptable level-of-service (LOS) in 2025.
Additional analysis in the report was undertaken to estimate the user benefits of an Overpass at this
location. It is estimated that over 550,000 hours of delay per year could be saved based on 2025
traffic conditions at a cost savings of $2.9 million. In addition the overpass is projected to reduce
traffic crashes and save motorists approximately $130,000 per year.
Subsequent to Kimley-Horn's study of conventional, at-grade
improvements, Kimley Horn prepared a Teclmical Memorandum in
2001, which reviewed the types of overpass structures that could
operate most efficiently and at the greatest level of safety. Structures
that were considered include diamond, cloverleaf, trumpet and single
point urban interchanges (SPUI). In summary, Kimley-Horn states,
"the combination of relatively high capacity and low right-of-way
costs makes the SPUI an ideal candidate for urban arterials".
The need for a grade separated overpass at Airport Pulling Road and
Golden Gate Parkway was further evaluated under a contract with
RWA Consultants who were tasked with the refinement of design
traffic movements to develop an overpass concept within reserved
rights-of-ways. RWA was also
charged with coordinating
public involvement activities to develop a concept that would be
consistent with the expectations of quality as characterized by
the community. County staff and RWA met with the Board of
County Commissioners (BCC), the Naples City Council on
February 6, 2002, Bear's Paw on April 4, 2002 and held
Countywide public meetings on February 11, 2002 and March
4, 2002 to present the conceptual plan and gain input into the
design of this project. This concept plan was finalized in
February of 2002 and it included almost $4 million in
architectural and landscaping features to establish a more
human scale to the structure and to serve as the gateway into the
City of Naples. On May 14, 2002, County staff received
authorization from the BCC to begin design and engineering
with RWA based on the work accomplished tln'ough the conceptual design study.
2
In late 2002, the City of Naples asked Kimley-Horn to look at the traffic impacts associated with the
future interchange and overpass. This study was undertaken to determine the traffic conditions at the
intersections of Airport Pulling Road and Goodlette Frank Road. The results again indicated that the
intersection at Airport Pulling Road fails in 2025 during both AM and PM peak hour conditions even
with the best conventional at-grade solutions. With an overpass, the intersection would operate at an
acceptable LOS for peak hour conditions in 2025. Kimley-Hom also determined that the
intersection at Goodlette Frm~k Road is projected to fail for both the AM and PM peak hours with at-
grade improvements within the existing right-of-way in 2025. It should also be noted that the
intersection operates at a LOS F for the peak hour conditions today in this analysis and is projected
to fail with or without the overpass at Airport-Pulling Road. At the January 7, 2003 City/County
joint workshop, Kimley-Horn confirmed the need for an overpass at Airport-Pulling Road and
concluded the need for an overpass at Goodlette-Frm~ Road. However, they assumed that they
would have to stay within the current ROW. County staff stated that because the primary movements
are turning movements (unlike Golden Gate Pkwy. at Airport) the intersection should be able to be
addressed with at-grade improvements. Subsequently, the County and City have been cooperatively
working with American Consulting Engineers (ACE) to design improvements to the intersection at
Goodlette-Frank Road (as well as that segment of Goodlette-Frank Road between the Parkway and
Pine Ridge Road). The current design creatively calls for improvements that bypass westbound right
turns outside the existing right-of-way. The design is quickly approaching 30% complete and will
provide for an acceptable level of service today and through 2025.
Kimley-Horn's study utilized the MPO's 2025 traffic model, which includes two Gordon River
Bridges. Subsequent to the City/County workshop, Kimley-Horn was asked by the City to remove
the bridges from the model and determine the impacts along the corridor. Kimley-Horn concluded
that without the bridges, delay and extended queue lengths already experienced along the con'idor
would increase considerably. At a City Council Meeting, these results were discussed and concerns
were raised with the Overpass.
Later, in response to issues raised by the City at an MPO
meeting about the beneficial impacts of building one or two
additional bridge crossings across the Gordon River, the
County hired the TBE Group to prepare a detailed analysis
of the costs and traffic impacts of additional bridges,
particularly as they provide relief to Golden Gate Parkway.
In building two bridges, different scenarios were developed
to maximize diversion from Golden Gate Parkway. In
summary, the cost to establish a single bridge crossing is
estimated at $75 million. The cost to establish two bridge
crossings is estimated at $90 million. These estimates are
attributed to the acquisition of right-of-way, design,
engineering, construction, and inspection associated with
the proposed bridges and roads leading to the bridges. TBE
concluded that the bridges would improve the operation of
the network, with primary relief to Radio Road and Davis
Boulevard rather than Golden Gate Parkway.
FINAL REPORT
In November 2003, the County comracted with Parsons
Brinkerhoff Quade & Douglas (Parsons), a transportation
firm identified by the City as uniquely qualified in
evaluating unconventional intersection designs. Parsons
visited the area and reviewed prior studies and data. They
quickly discounted previously considered unconventional
approaches such as round-a-bouts, jug-handles, continuous
flow intersections and quadrant roadways because of the
volume of traffic seen at this intersection and right-of-way
constraints. Parsons found that only grade separation would
meet the 20-yem' design needs (see Figure 1 below).
However, Parsons did recommend a split intersection /
median u-turn concept as a possible interim solution (see
Figure 2 attached). Parsons proposed that this
unconventional concept could likely fit within the dedicated
right-of-way for an ultimate overpass. Parson also estimates
that grade separation would be needed between 2010 and
2015; the earlier date likely if the corridor experiences a 2% a year growth rate which Parsons
raised as a likely probability based on historical growth along the corridor. They noted that a
split intersection design has been
used as a temporary measure during
interchange construction in the U. S., but
there is presently no known longstanding
specific application. In whichever year
grade separation becomes necessary, it is
estimated that $3.5 million worth of
construction associated with the
unconventional design would be disrupted
and/or removed as part of an overpass
construction. The unconventional nature of
Figure 1:2025 Volume-to-Capacity Analysis Results
2025 PM
INTERSECTION DESIGN Volume-to-
Capacity Ratio
Conventional Intersection 1.42
single P0in~ OverpaSs(planned) 0:85
Median U-Turn (crossovers only on GGP) 1.21
Continuous Flow Intersection 1.05
Split Intersection (with median crossovers) 1.11
Echelon Interchange (grade s eparafi0n) 0:98
V/C Ratio above 1.0 = greater delay and longer peak volume time,
such a design requires significant driver acclamation, education and special law enforcement.
Lastly, the County has been working with Post Buckley Shuh and Jernigan (PBS&J), another
leading transportation consulting firm, to evaluate future traffic conditions along Golden Gate
Parkway from Santa Barbara Boulevard to U.S. 41. Two specific assignments were given. The
first included the evaluation of different build scenarios for the Golden Gate Parkway
intersections with Goodlette-Frank Road mad Airport-Pulling Road in 2005 and 2025. The
second assigmnent focused on the evaluation of different traffic scenarios due to the
implementation of a second Gordon River bridge crossing. PBS&J's results are best surnmarized
in Tables 1 and 2. Findings from the first assignment as depicted in Table 1 revealed the
following:
· Operations at US 41 and at Santa Barbara Boulevard are relatively unaffected by the specific
improvement decision at the Airport Road and Golden Gate Parkway intersection or by the
possible addition of two Gordon River Bridges
· The addition if two Gordon River Bridges will slightly reduce delay at Goodlette Frank
Road, but add more delay at Livingston Road regardless of the specific improvement
decision at the Airport Road and Golden Gate Parkway intersection
Given that all Airport Road at Golden Gate Parkway intersection alternatives, when
optimized, do not significantly impact other intersections along the corridor, Table 1 below
provides the best tool to evaluate the corridor operations and cost of the Airport Road at
Golden Gate Parkway improvement options.
· An overpass at Airport-Pulling Road provides significm~t benefit to the operation of the
intersection well into the future;
· Alternative improvements, such as a westbound bypass, at the intersection of Goodlette-
Frank Road significantly improve the operation of the intersection.
· In 2005, the signalized intersections within the study co~Tidor are expected to operate better
than a LOS 'D', with the proposed improvements;
In 2025, the following intersections along the Parkway are
expected to operate below LOS 'D' with the proposed
improvements: Goodlette-Frank, Livingston, Santa
Barbara (which is policy constrained). However, only
Santa Barbm'a will operate below a LOS E (the county's
minimum standard) for portions of the day.
Findings from the second assignment as depicted in Table
2 revealed that an overpass at Airport-Pulling Road, along
with a second Gordon River bridge crossing, provides the
greatest savings in travel time, delay and fi.~el consumption
along the Parkway corridor when compared to all other
alternatives. The alternative of best conventional at-grade
improvements, without a second Gordon River bridge
crossing, is used as the baseline by which other
alternatives are gauged. The baseline alternative has a cost
of approximately $12 million. Other alternatives that were
considered include:
1. An overpass without additional Gordon River bridge crossings;
2. At-grade improvements at Airport-Pulling Road with two Gordon River bridge crossings;
3. An overpass with two Gordon River bridge crossings;
4. Split intersection / median U-turn concept without additional Gordon River bridge
crossings;
5. Split intersection / median U-turn concept with two Gordon River bridge crossings.
The PBS&J findings confirm the results of all prior studies that the only conventional or
unconventional improvement that meets the needs in 2025 is grade separation. Their emalysis
showed that the overpass does not adversely impact the other intersections along the corridor and
that the overpass, even without two new bridges, provides for nearly a 20% reduction in travel time
over the entire corridor. Even with 4-1anes on a north Gordon River bridge crossing and 2-lanes on a
south bridge crossing, the addition of two new bridges does not provide sufficient relief to Golden
Gate Parkway traffic to eliminate the need for grade separation. Lastly, they found that the split
intersection with median u-turns would initially provide better operations than at-grade conventional
improvements, but would actually operate less effectively than conventional at-grade intersection
improvements in 2025. Neither the split intersection nor the conventional at-grade improvements,
even when combined with the additional bridges, would meet the 2025 traffic at an acceptable LOS.
FISCAL IMPACT: The Overpass is estimated to cost $27.2 million, which is to be funded by Gas
Taxes, Impact Fees and a portion of the TOPS grant.
GROWTH MANAGEMENT: The design, construction, and all-inclusive detail analysis of a
grade separated overpass is consistent with the Growth Management Plan and the MPO's Cost
Feasible Plan.
RECOMMENDATION: To recognize that an exhaustive analysis of all conventional and
unconventional improvements concludes that a grade separated overpass is the only alternative
achieving an adequate level of service in 2025. Secondly, to recognize that irnplementation of a
split intersection with median u-turns would only address deficiencies for a short duration even if
additional bridges were constructed and, therefore, construction of an overpass at the outset would
deliver the most cost effective solution meeting the long-term needs of the entire county with the
least construction disruption. And lastly to recognize that the current overpass design includes $4
million in aesthetic enhancements to maintain community character.
Prepared by:
Gregg R. Strakaluse, P.E.
Director, Engineering & Construction Management
Date:
Reviewed by:
Don Scott, AICP
Director, Transportation Planning
Date:
Reviewed mid Approved by:
Norman Feder, AICP
Transportation Administrator
Date: