Agenda 07/07/2015 Item #16E97/7/2015 16.E.9. EXECUTIVE SUMMARY Recommendation to accept and ratify reports for staff - approved change orders, changes to work orders, and surplus credit. OBJECTIVE: To provide the Board with visibility of administrative change orders and changes to work orders and promote accountability in the use of staff authority. CONSIDERATIONS: In accordance with the Purchasing Ordinance 2013 -69, approved by the Board on December 10, 2013 as agenda item 17.J, staff reports administrative changes to Board - approved contracts of not greater than 10 percent of the current Board approved amount, changes to Work Orders issued under CCNA Contracts that are less than or equal to $200,000, and changes to work orders for all other contracts that are not greater than 10 percent of the current Board approved amount. The attached monthly reports of Administrative Change Orders and Administrative Changes to Work Orders cover the period of May 19, 2015 to June 15, 2015. Staff is reporting revenue generated from the on -line auction of I- Phones that was authorized on October 28, 2014 (Agenda Item 16 E1). The I- Phones were auctioned in three separate batches so not to flood the market and receive the best revenue available. The final batch closed on May 29, 2015 and generated the following in gross revenue of $9,774.99, the auctioneer's commission of $782.00 (8 %) was deducted from the gross revenue resulting in $8,992.99 in revenues to the general fund. FISCAL IMPACT: The net total for 11 changes to contracts is $199,121.89. The net total for 6 changes to work orders is $389.25. The net revenue generated from the on -line auction sale is $8,992.99. LEGAL CONSIDERATIONS: This item raises no legal issues and requires majority vote for approval. -JAK GROWTH MANAGEMENT IMPACT: There is no Growth Management Impact associated with this action. RECOMMENDATION: That the Board of County Commissioners accepts and ratifies the Administrative Change Order Report and Administrative Changes to Work Order Report, and recognizes and accepts the surplus report and the net revenue generated by the on -line auction. PREPARED BY: Diana De Leon, CPPB, Contracts Technician, Procurement Services Division Attachments: • Change Order Report and backup • Changes to Work Order Report and backup • Surplus Report Packet Page -2032- 7/7/2015 16.E.9. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.E.16.E.9. Item Summary: Recommendation to accept and ratify reports for staff - approved change orders, changes to work orders, and surplus credit. Meeting Date: 7/7/2015 Prepared By Name: DeLeonDiana Title: Contracts Technician, Administrative Services Department 6/19/2015 12:33:59 PM Submitted by Title: Contracts Technician, Administrative Services Department Name: DeLeonDiana 6/19/2015 12:34:00 PM Approved By Name: DeLeonDiana Title: Contracts Technician, Administrative Services Department Date: 6/19/2015 12:46:27 PM Name: pochopinpat Title: Administrative Assistant, Administrative Services Department Date: 6/19/2015 12:51:41 PM Name: NorthrupAdam Title: Procurement Specialist, Administrative Services Department Date: 6/19/2015 12:58:19 PM Name: Markiewiczloanne Title: Division Director - Purchasing & Gen Svc, Administrative Services Department Date: 6/19/2015 1:22:43 PM Name: PriceLen Packet Page -2033- 7/7/2015 16.E.9. Title: Department Head - Administrative Svc, Administrative Services Department Date: 6/22/2015 6:21:36 PM Name: IsacksonMark Title: Division Director - Corp Fin & Mgmt Svc, Office'of Management & Budget Date: 6/23/2015 11:47:07 AM Name: KlatzkowJeff Title: County Attorney, Date: 6/24/2015 1:35:10 PM Name: CasalanguidaNick Title: Deputy County Manager, County Managers Office Date: 6/26/2015 3:02:40 PM Packet Page -2034- .n w � m N C n 0 m 3 o n ' L U CL E U Q e O m c w m o� o y c m m i m r m U U N Q] e r C 'A ` 7 O M V E Q w y C � y � 0 L O E U w a d � C O a ° E U U w U F m O CL w � c � C U 0 O 07 ` E 0 O O Q Ow U U w p W Q = U O O U) m o a Z O Qw Q F C m c � o � '> O o a O Z C m C ZZZ,Zi U y o a°i @ c i 0 >a`uL.>o U) d � f6 � 0 3 U 0 IL` m Z 0 0 N 0 o 3 p U 3 0 C n @ In > o 0 c�c' o m a a � 0 Co m L o O ° c C ° c o @ OU Q N O L D c O C 0 N O O m W G fA O m M �p N _ C C m � p m a ° O Co U o L Cl U N ry O O U d O T C o w W v T (h w L N N :E; o L _01 N L F pcp U N C E C O fA LO O N o o N Oi a m N N a cCo Cn a� L N E o O O C w O a C U U m = O- > O o N N m O 0 N m m C o ° 0 m a C m 0 w m O d o U c > N N `@ 6 cci a C`n U C ° w o a m O ° a U N m o y a E C, w m U') 3 N pen O .L U 0 o a Q o N O me U Z a E m O C m 'o U O C c O i» o >- C U ° U U cm o .o v fA 2 U O M L ; C w N rn� C ~ rn $ o C 3 N ° ° ) O p O C o 7 m y o U Y N > N p p fR y w >O Co E N U w ° c m m N w o o O C O Y U N O ni C> m N N o U y m q N C N ° E - a W ° a m m a N m m N CL a) Z Z c0 v O m c C T C _ _ ,.C-_ U m 7 Y m O N N > w p N C 'D c w � c E N C c rz o m _ o ° m E 0 E ~ c 0 U E '2 m N o E >_ Q xl co N .9 - (U O °_ E C m m U 'c r E m O c w N m L D m C N 0 L 0 m E E c c `o 'OL o r o U) 3 C m E m U c O o o y U w m o m m L 0 Cri O 3 m y °o m LL M a y m m U_ (c 2Qm m E m o N EocNO co a O ¢`z�� x ° N 0 E Q (U N a °- U d @ L) N m D N 7 a� u) C CT C C O U> U m +� N > OU L E @ U L m N N N m m m U w@ U M'o c = O H mm° c m E 3 °° a� rnc0 0o a, o Cu m 3 m o M c', o Nom m'Cn� m m T mQ °LC U Y COO �UO> H a� CAZ�U� H W m _ C y N Cn Z d m rnE md� m d - m E N w V N a Q v y ° U ai ° y N U (n m ; 7 d U _y � m a N Z � .N 8 N d > 0 m O 0 ° O �n M N 0 3 3c 0 m 3 > `o O o N N 7 E L m fU6 U C/) N a � 0 Co m L o O c! C ° L U x N C U Q � 'z L o0 C 0 0 m o O U Y W G 7. O 2 M �p N _ C C m O U m a ° E >o Co o a Cl N fV ti O O > ai T � w W v T (h w L L _01 N L F L x x E .0 m Q LO O N o o a m Oi a m O w Cn a� L N E o O C w @ C O m = - > C c m N N m 2 N m m O C o m a c °° m O d O v > N N m � cci a C`n U U m ° w o a M 69 O ° a N N m o y a E C, w cc w U') N .L O u a 0 L m o me O o c O C 'o U O L U m C_ >- C M ° U cm o .o v fA O M - U w N rn� C c U ° a y O N O C o 7 N U O (A U (IS C N y 6 Co E N U w m m C w O m U E Y U ni C> C w U y q N C N ° E - a ° a m m H m m N CL a) Z Z c0 v O C _ _ m N m U U U N C O m N n E 0 C j ° N o E >_ N c a xl a - °_ E U w m U 'c > m c w lz N C N 0 L Cu E ma U m 'OL y o a o N m T E U M m m 0 Cri O Xk N .N OU w y E m U LL M a y 'O N m N e d > r a C 2Qm m E m o N EocNO co a m c� ¢`z�� 0 E I°- L) C d - N n N m = C n m N n � N m CI C m m U -- o m U ED o p o N o a m j m M W V o 7 O m O v Packet Page -2035- 7/7/2015 16.E.9. 0 0 0 O O Q Z 0 Q `z C ° 3c 0 3 `o O N N 7 E L fU6 U C/) N _Q Z U ' CL m 50 a_ o L U x N w 'O o Q a 'z o0 0 m U Y m 3 (U N O _ C C O U m a ° E >o Co o a O = CT > ai w T W v T m a o -6 O (U N L n L E .0 m o m m E U- 16 m o N Cn a� m E o 7 Kl ° N 'a w C p m = - > C c m N N m CL N m m CxaQC° m a m m QZ L 0 UQ O I- mY > O m � L @ U C`n U m c ° w U C O m ` N C O 'co o y a E 2 � M U') O u a 'w = v N Cn a r U a E v M > > E Q Cl) a Z v `mE wm o O m 0 o G Cu (D � m c y R o o L L U ) O U m y C u 0 o M U 3 N O � U ,O > c E O Q w d C O) y C O era E o O UOQ u°9 O � w �(OQp 'RO a, > > C O O O LO a U C C OU 7 Q Q C R L) V w LO M9 = aa) F. m C a o d w Of � C U 3 o o w a) O E R p O o Q U U w m w CD 0 0 w z Q O E o 2 U > y o < m U O O R E E m¢ O 40 rn Z Co 69 p N R CL p O o �_ m 11-0 z O a o rn U y U @ Co > O ii U d o o NQ Y R U @ M a V >. O N C Z lyp Q c O y y o a a E R O a O R Z Z Zk �i ° 00 d r C a) O C N In Co CI O m Q d O L O � a U p N L 0 Cu C%i Lo �' C o LO U N N Of n '0) �) L Q O 69 C O Ir N LL 2 o co m a c E o ` R � G eA m Z ° C R t O m m O 7/7/2015 16.E.9. Packet Page -2036- y 0 C 0 m o 0 ooi °o m o O y O Ci M U 3 (V U ,O O C Z U R O O � �(OQp 'RO Cu C C C 2 a) .0 U C C OU C R e 8 = aa) E m C a o 0) o L o E R Cl) L E 0 0 0 o O E o o > E C R E n> n•- m Co p N R CL O o �_ m O a o U c Co o C o o NQ R o Cu a rn o c (0 o a a E �i ° Q aOi ° Cu C%i Lo �' C o LO U N N Of n C 2 69 =5 2 o co c E .1i y ` R � G eA C U O L O O N R O a) n O N y C Co z y (a C n D O N a) °° E O M — O L o U E= C Lo o ° y 0 3 w w d C `o ri n S o u9 3 a) a Co v > g Q Co N N 69 EO U L o N N o a @ a) U R ° R o ° N d O y U a) O. p N fa p LR-. CM •O o CL a 'O Co Ol y M C p a O H C R Q Z LD LO O a) m y L .L... Cl) V O w O) C C a) C a) V1 L D r» moo i» a) m m E 69 ° d R — a) R y N R 7 fa y T 7 Cu m o° O E aa)) a�Ei 3 a�� o N .a EL E w UU L C O) °O .0 N Y L U N L a) M a c 7 o y m Z ~ O r C; N to y y �,°j a) R O y y C Cl O) L — C` m O a) O V M 6 N V R N a) C y N ° y Mn Eu o Y m 3 0 � m E i @ o ? °o o U o E ti N ? o o o 0 o LO R a _ O O to a) N E C O EA d) m w am) J L 69 a) @ p s E> CO 0 0 o N d o a� L _ E 0 0 0 °ro o o o � m Cr O�� w e m e c U v � rc 0 tf6- O w p M o a) o. , -� - . -Ra = F W a 5 y@ 0 L c m C to S a) a) a) w �° c o O) R C a) O F U) 3 0 N c U M N H U a Z m .Q L C J a 0^ lL I y fya 3 3 9) y C) C,- m 3 ° '0 o 8 o a a y o y.o LR. •= _ o �. O nO R "O y m O a) C ya R d ai R y ° m O CD a) R v a a yy R> 7 y 3 m T w w C L m U J c J m e C O C Co 3 a R a) a N L to am Ce v m o m E c 0 Lo. a c c ;U m 0 y E R o 3 E aU o ~ m U- C C U — E O Y N a7 a) U X fA y o° O R O R to a� o y O a y C a a) N 3 C Y M U U y 0 C C o c O oXo C y@ U CL 0 R a) O O a > > o 7" U o a C U o = @ o c o y E L) L y Q v = o O R i c U m o E m m o m a° `O O °-� 'j Xkm E.0 aU N a) N N XkU aI N Z �N CD o m as m O c a@ E o m o .� o C> 0 m CD rni a Q a `b 2 C o ,No ? m .or-) M 2 a :� C x o(D a) m '� 9 x a`) c c`"o mom Cn Q� m a> '� Q O O (Ca S @ m` r L a) QM�UO O F- y R O :z (o L a) UO O N a I-D O L O UZ 02 0 7 F- 0.L Q) L O a) O U C y` LO a7 ~ IM -° d E -° Of O` m � a) U y N U U C p m L C L) �_ W L R U W L) 0= V t C U L O ° a) U O L = O O a) N fD y c0 m ° O m M Z L - a y C -° v a) m °N a y > n m d i i` V x > C o ° > ai Cu O m O F a) O o O c °) Packet Page -2036- in w c m s� and N C ° r U a E U E m a N d) m m c y y � o) m c v U H O m to O > c E Cu O Q U �q y C tm 3 O t O E U a N a > c 0 m a o a �aQ U U w U � m 0 O CL w Cr LU � c v O a 0 0 O O a Ow U U w U' ul 7 Q Co Z_ Q Lo 4 C d C U >O O 0 U E m Qa a w m c � O V y d �> O � d d Z y c a m d E z z° S 2 aU c a > n U U a w a � O V O n. E Z 0 rn � o ,o =3 3 C N '- C p O C ay m o m 3 o CD p Lo >_ 3 a m m U m O (D 0) m E _ O O 0) ° CO .Y 69 m 3 c N m M O_ N M ti ° �° m m O w U U m m N C E O m ° o mD w Co > m w 0 0 M N > ° ° t0 C .0 � N @ N C� (0 O N N m 0) _ C_ m O � � N N m r U N 00 o aa) M N fA .O N O @ m O Y m U 3 � 4 0` E a' o E m X 0] c _ Y 0) 0 C Mn C X O N — O m C U N N X O C N ED N > C O Cl E E Y a o c N a>i > m m Q E m ° o L � o) m t m 6 `O a Co a� UU FO- � a ci °) L a c o nom ma 0 o p in C y U > c O ° m CR r ci rn w i v c O U d O) C r U O F Packet Page -2037- 7/7/2015 16.E.9. 0 w o m N r d T E � E N Z m E C U U m s N } (v �d9 0 m m L) CO e V Y CO v E $ N 0 co a) 1 a e A 0 U C S y O 0 > x E O a O d c CD 0 0 Y E L Q U ?� r► d � 9 C CD 0 o 7 E Vow > `s v E U m as a Y d C R � � O o � � w c 6 N , '> o 0 a` CI R x X w O U z W O C Z O O � U A O C fyC U � Z Z Z 2 O U Cf O) c r 0 C C L > a U a A U1 0 7 °= o o a. = Z 0 co co N N °o C) °o C O ti i» a Z N m EA x d U LL 0 CL CL L U U) m m O N N V c L O � U fC LO m C O 0 E U m r a) a O U — w 0 O °c o U * C C) (C M ma > OCDC)cv0 r i�5 U o w C) 0 0 OJ a0) E 0 m N c N m N o) L U C) H N N o ° F a N « C) 0 a O C CS W L c U O o UUC m �+ C7 N > 0 O 0 0 0 0 O 0 of co 60 0 fA m co Z Oi CD 6s a 2 a CD N O N O N r ao L O (D U LO `m A � O) C O 0 3� Cl U U M ° ,c�m�ami M o m O m 0 C Qr,- Uma LO CL m = O Cn N Y co F- 0 0 C6 vi 2 U O N 0 CD C) C L U O 2 C) 0P 0 O 0 0 O 0 0 0 M °o ci 4.9 O M 69 g Z O M 69 °C E a° c ma d N O` Lm) m c LO M O m N 0 V m (O O) o LO Cl) Co L C CJ V m a`) Y O C m F E E 3 ° o m `o « L O o O U O C7 M > O C c c @ N 0 0 a) N (A UO .N- O M C) Y T Cn O E O c O L O O i� O r� U f CO F- S N Cf : � C C 3 l6 L 47 V C) C 0 O CD CO m m o CO o icket Page -2038- 0 O o !� C 7 N O U L 0 a O C O f0 o S d 9. U c o @ O T 0 � C n � 69 O m L N m 0 0 0 O Y O 'C O N O « O � N � a w 0 m 3 N a C z •° c m O O d O N 0 vi ° O lC N C m o w U) U y C 0 c N L N H Q 0 O N O Y O 3 s m O O O N LO N T )N "t 0 L O ` O m _ CD a � d' N m N C) O M d m Y C ) f0 L � ° 6 0 C ° N C C_ Z 0 'm 1 11 c m N J O m 32 N N> >: L O > O O 1- m` U C7 O F _o m O1 N C � Q7 LO V N O `p C) CS o w 0 N U > I a ow 7/7/2015 16.E.9. 0 co c co C3 U C C) m m U 0 t0 0 � N u? C) C) w a L O f- Y 0 3 LO °o v O M N O � N 0 69 LO 69 O c N O O N n E C m � m O] C u7 C) C N fA y m N Z C) U)m (V C L m � U O U C) N 2 co l 64 c ° 0 U 0 0 0 LO N m (V @ rn m�cq d t9 � m C � t0 @ Om N C) m CN m O N w to Ff3 C C) `0 E 7 C 7 p Q E2 C7 �p O N C 0 Q @ c N U) N O O V (0 7 U r 0 O C U U CD Cl N « N N d O O 0 � L Y N _ O � L) O m CS m F a _ m N N m j '00 O LU c ca C O m a m c ° m ° E a C C7 0 Y 0 O a m N a c m U o Z U c c o 0 ots °D m rn •y E a L) UFO 0-C O d C � O C c � U U X a o(D Z c O a C1 0 « >o o Packet Page -2039- 7/7/2015 16.E.9. m � 0 o N U D O m C C_ @ m C y` a O L c 0 m m e m o U E o 0 ° 0 a U O` N U 0] O C O d ° O U O y 0 O >YE o Lf m m Q 8 N Lo O o y C 3 a o N f1Y o> O o x E $ o c N o°'o d p c O o c d 0 c E o t C v Y U W o c vi o, .N F- @ O m a o c w U > o Q o E �m °' z o. Q Q w m O Y I m y O O O m0 o Q 2 � m U C `po°Eo Q a: d rnU a) a) o Co ` CM c o @ c o z y? m a- 6 a v c d U m D o m X 30 W U N 72 O z 2 m O 0 z 0 V 0 m N (Dvao O 3 ` d � L @ Y C N U U i v m y @ O Of o LO N tA C N N - N U p m C d d C J m 7 N L N O O U C4v y rnd>, .L 'O N C Gl c d C p C 'O p GI >aUa - °,nUgcn lo-m O Y io C o� a O �+ c c in t f0 d D d o W to w U E O > a = z co O N F Packet Page -2039- 7/7/2015 16.E.9. 7/7/2015 16.E.9. M yGy:':� M Ir1 Lh t7 (7 r yyyy G $ N 6) (p Q a v, m I � �`�• w w w w w wi o ! 0 0 0 0 0 0 rn m m I rn m -'. IA f' N g m (o (!7 N N (n N w O O O i0 O 10 >1011- N Z IK ID: FIW Ulu U; y i z w U,IO fIZIW :Z ..� ... id ito wW�IW d N a N ''., c c c C C It = CL W y 'I> o� m w , 21 0 m `m - Im o U I, i0 z u7 w w w w 1w he Z 0 0 z 0 l0 10 0 a s a a a a la �w ¢z ' i w �I 0 I 'n U i i(n I(n 1. w 0 0 10 10 O oe I0 W I� 10 la w > > > > > M Q O (6 mnl� Q Co (n m V D m O N N 6R7 In C7 (+1 (+1 (O Q M C'J Q Q Q Q Q Q O 6 Ld N O> (O lh f7 f�J (7 In Q OI - MQ(hM (O(pp (O(ppp MC'1mm mmC m C n Q O :.0 M N Oi !D l+] � �Nnm _ 010�0� Nt")ee�� OWN 'V Q M m m M M m M Q Q Q Q Q Q m m O D NI�QN O> 6 (M O M NO NAM N L DM (n w NNm N' � M �m CON'I O. O wNM D Z M W D(DnaD Z M wm m00 'w:; N m m Z wQ wON -i W ;, M 0 wto Q.- = N M Q in M 0 (D ,f N O I0 = Z (D n m M M Q Q Z Q Q Q t:O GD 10N N dI: T. Z Q 0O Z M M M 0O- ¢I Oi a M (.I M M a n(n Q Q a . M Packet Page -2040- 1 I 7/7/2015 16.E.9. corw cout,,tv Procurement Services .� Change Order Fora! ig Contract Modification (] Work Order Modification ❑ Amendment Contract M 13 8085 Change #: EEI Purchase Order #: 4500151387 1 Project #: 88088.11 Contractor /Firm Name: Fyisinger Campo & Associates, Corp Project Name: 0i1pe °r tl Ri1is° 6ervkoe for venoerau Dnve sr doe rterphcemee4. Anthony 0. Stolts, P.E. =owthnagement Department Project Manager Name: Department: Original Contract'Work Order Amount $ 674;270.29 5- 27- 14;18A17 Original BCC Approval Date; Agenda Item ## Current BCC Approved Amount it",' 70. ZJ !W N/A Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 674,270.29 6/21!2015 SAP Contract Expiration Date (Master) Dollar Amount of this Change 0 0.00% Total Change from Original Amount Revised Contract/Work Order Total S 674,270.29 #YAL-AiEl Change from Current BCC Approved Amount Cumulative Changes I $ 0 001 0.009 /a Change from Current Amount I Completion Date, Description of the Task(s) Change, and Ratlonsis for the Change I Notice to Proased 07/01/2014 Original 06/212015 Last Approved 06/21/2015 Revised Date 02/05/2018 Date Completion Date Date Includes this change) # of Days Added 860 Select Tasks ❑ Add new tasks) ❑ Delete task(s) ❑ Change tasks) ® Outer (see belovt) Provide a response to the following: 1.) detailed and specific explanation /rationale of the requested change($) to the task(s) and I or the additional days added (if requested); 2.) why this change was not Included In the original contract; and, 3,) describe the Impact If this chance Is not processed. Attach additional information from the Design Professional and/or Contractor it needed. 1.) This was a planned extension of time. (See Attached Letter Dated May 19, 2015 from Kisinger Campo & Associates for details.) 2.) This change was anticipated in the original contract 3.) The consultant will not be able to provide the services defined in the approved contract. Prepared by: i!sil —y'r+ Date: Zui - os- Z/ Anth Its, P.E., Senior Project Manager, Transportation Engineering Division Acceptance of this Change Order shall constitute a modification to contract / work order Identified above and will be subject to all the same terms and conditions as contained In the contract / work order indicated above, as fully as 0 the name were stated In this acceptance. The sd)ustmont, If any, to the Contract shall constitute a full and Anal settlement of any and all claims of the Contractor / Vendor I Consultant I Design Professional arisjng out of Qr related to the change act forth herein, Including claims for Impact and delay costs, Accepted by: Date:Z/ Paul Foley' Pr den Kiaing po & Associates, Corp. Approved by: �21 Approved f E t Date: .1ay.J,t P1 fw , Director, T po tion E gineering Division (Vick Casale ida, puty County Manager J % _. Approved by: Date: j �C/ S r.._,..- _�_- n - -- - -a h- _- 1 -1. -1 (Divisions who may require additional signatures may Include on separate sheet.) Revised: 10/2812014 Packet Page -2041- F 7/7/2015 16.E.9. KISINGER CAMPO May 19, 2015 Mr. Anthony Stolts, P.E. Senior Project Manager Collier County Growth Management Division Transportation Engineering Department 2885 South Horseshoe Drive Naples, FL 34104 Re: Contract No. 13 -6085 Design and Related Services for Vanderbilt Drive Bridge Replacements Request for Time Extension Dear Mr. Stolts: As specified In the original Notice to Proceed letter dated June 30, 2014 for the subject contract between Collier County and Kisinger Campo and Associates Corp. (KCA), final completion of all work shall be before June 21, 2015. Included in the scope of work are Post - Design Services (PDS) that will be performed during construction procurement and the project construction phase. It was decided during design contract negotiations that a contract extension would be required in order to utilize the PDS task, and the amou nt of time allocated for the PDS phase was 'To Be Determined" as specified on Schedule C of the contract. This decision was based on the need to present general construction methods and traffic control concepts to the local public during the design phase, and solicit comments to gauge public acceptance, thereby enabling a more accurate estimate of the construction duration and PDS. Therefore, based on the time needed to receive final permits, complete right -of -way certifications, procure a contractor, and complete construction, KCA requests the subject contract be extended an additional 960 calendar days from the end of the current contract completion date. Please note that a change in the compensation amount for PDS is not being requested at this time. if you have any questions, please contact me or KCA's deputy project manager, Chris Meares, at (813) 871- 5331 or at Chris.Meares@kisineercamoo.com. Sincerely, &44�- Paul G. Foley, P.E„ President 701 North Franklin Street, Suite 400 1 Tampa. floilda 31602 1 , ' 813 871 5331 • 813 871 513S I . Packet Page -2042- 7/7/2015 16.E.9. Contract # 13 -6085 "Design and Related Services for Vanderbilt Drive Bridge Replacements" PROFESSIONAL SERVICES AGREEMENT THIS AGREEMENT is made and entered into this Q74", day of , 2014 by and between the Board of County Commissioners for Collier County, krida, a political subdivision of the State of Florida (hereinafter referred to as the "COUNTY" or "OWNER ") and Kisinger Campo & Associates, Corp., authorized to do business in the State of Florida, whose business address is One Tampa City Center, 201 North Franklin Street, Suite 400, Tampa, FL 33602 (hereinafter referred to as the "CONSULTANT'). WITNESSETH: WHEREAS, the OWNER desires to obtain the professional Consulting services of the CONSULTANT for Design and Related Services concerning Vanderbilt Drive Bridge Replacements (hereinafter referred to as the "Project "), said services being more fully described in Schedule A, "Scope of Services ", which is attached hereto and incorporated herein; WHEREAS, the CONSULTANT has submitted a proposal for provision of those services; and WHEREAS, the CONSULTANT represents that it has expertise in the type of professional services that will be required for the Project. NOW, THEREFORE, in consideration of the mutual covenants and provisions contained herein, the parties hereto agree as follows: Packet Page -2043- 7/7/2015 16.E.9. !,, SCHEDULE C PROJECT MILESTONE SCHEDULE Schedule is based on the number of calendar days from issuance of Notice to Proceed. PHASE CUMULATIVE ni IPATIMI r11 IPATInKl* 1. 30% SUBMITTAL 2. 60% SUBMITTAL 3. 90% SUBMITTAL 4. 100% SUBMITTAL 5. FINAL SUBMITTAL 6. POST DESIGN SERVICES 162 162 72 234 57 291 44 335 20 355 TBD TBD * Includes 21 day phase submittal review time. END OF SCHEDULE C C-1 Packet Page -2044- �^'� 7/7/2015 16.E.9. "+.,.. -0 Tom' CO my Procuiv.,,,,riv,%,,i Change Order Form ® Contract Modification ❑ Work Order Modification ❑ Amendment Contract #: 15 -6378 Change #: I 1 Purchase Order #: 4500159051 I Project M NA r I Contractor /Firm Name: Shadow Transit Services Contract/Project: Jevun Lisa Marciano Project Manager Name: J 9 —� Division Name: L Naples Depot Museum Original Contract/Work Order Amount $ 116,000.00 4/14/15; 16D3 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 116,000.00 4/14/15; 16D3 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 116,000.00 5/31/2016 SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 6,450.00 5.56% Total Change from Original Amount Revised Contract /Work Order Total $ 122,450.001 5.56% Change from Current BCC Approved Amount Cumulative Changes $ 6,450.00 5.56% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed 06/01/2015 Original 05131/1 Last Approved 05/31/1 Revised Date NA Date Completion Date Date _(Includes this change) # of Days Added = Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other (see below) Provide a response to the following: 1.) detailed and specific explanation /rationale of the requested change(s) to the task(s) and / or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and /or Contractor if needed. 1. The contract was written and approved for $122,450.00, but the title of the executive summary was changed to state "contract amount $116,000 ". We believe this problem was due to confusion with a statement in the FISCAL IMPACT section. 2. The Executive Summary was originally written correctly, but a change by someone in the Sire approval stream caused this issue. 3. If this change is not processed, the full contract cannot be completed and /or paid for. Prepared by: a Jv�r.k� JJ )' (Project Manager Name and Division) Li�I C J)C1, �I ( P i4UJLilGI it Date: 1 UVl r Z �I Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same terms and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant / Design Professional a ng out of or related to the change set forth herein, including claims for impact and delay costs. Accepted by: 6 Date: (Conifa for ! Ve o Consultant / Design Professional and Name of Firm, if project applicable) Approved by: Approved by: and Name (Procured>ient Profess (Divisions who may require additional signatures may include on separate sheet.) Packet Page -2045- Date: f f Date: (� / t Revised: 10/2812014 7/7/2015 16.E.9. EXECUTIVE SUMMARY Recotnmenda nn fora d FP No 15 6378 Na les De of Museum 1.94 7 Budd Tavern ain Car �" ....€Sado _ 'I'._a „� Services in ne amount of-116 0,00: OBJECTIVE: To uphold the mission of Collier County Museums by preserving, displaying and enhancing the safety of historical items and to offset operating expenses for the County Museums through providing an updated venue for revenue generation. CONSIDERATIONS: In 2004, Collier County entered into a long term lease with Southwest Heritage Inc, to restore the old Naples Train Depot and convert the building along with three historic train cars into an additional museum in the Collier County Museum system. The Museum opened in January 2011. One of the historic cars is the 1947 Budd Tavern observation car, which was brought to the Naples Depot in 1978. Since that time, no major upgrades have been performed on the train car to prevent or decrease deterioration. While the Naples Depot staff has used stopgap measures to keep the train car safe for visitation, it has come to a point where the train can no longer be kept open for museum visitors if a permanent solution is not instituted. This project will remove all of the 1970's themed items, replace broken windows and seals, remove molded carpet and wood and restore the car to its original 1947 appearance. This project will help preserve the historical Tavern Train Car, create a safe environment for visitors to experience its history, and create a prospective venue for rental opportunities. Request for Proposal 15 -6378 Naples Depot Museum 1947 Budd Tavern Train Car Restoration was publicly advertised on November 21, 2014. Email notices were sent to seven hundred fifty eight (758) firms, including notices to restoration companies; forty nine (49) firms requested full solicitation packages. Three firms submitted information including: one (1) firm who indicated they were not interested; one (1) firm (Wasatch Railroad Contractors) who submitted a letter of interest but declined to submit a formal proposal and, therefore declared non- responsive; and one (1) firm (Shadow Transit Service, Inc.) who was presented to the selection committee for evaluation purposes. A selection committee met on January 29, 2015 to discuss and review the proposal. By consensus of the members, Shadow Transit Service, Inc. was recommended as the firm who could complete the County's scope of work. Staff has negotiated the final contract which has been reviewed by the County Attorney's Office, and recommends an award to Shadow Transit Services, Inc. FISCAL IMPACT funds in the amount of $116,000 are. available, in Museum Capital Club Car RestoratioriFund "j374):in reject No. 50502. Staff ha"s prepared a budget amendment moving $12,500 from Museum Capital IIurncane Protection Fund (314) to Project No. 50502 (Club Car Restoration) as a contingency in order to cover the proposal cost of $122,450, creating a total of $128,500. GROWTH MANAGEMENT IMPACT: None LEGAL CONSIDERATIONS• This item has been approved as to form and legality and requires majority vote for approval. - CMG RECOMMENDATION: That the Board of County Commissioners awards RFP No. #15 -6378 Naples Depot Museum 1947 Budd Tavern Train Car Restoration to Shadow Transit Service, Inc.; authorizes the Chairman to execute a County Attorney approved contract; and authorizes the necessary budget amendment. Prepared By: Lisa Marciano, Manager, Museum Packet Page -2046- 7/7/2015 16.E.9. E=xhibit B Price Schedule DESCRIPTION ., m ,. LUMP SUM FEE , .- . 1. Remove and replace all windows and gaskets. $9,800.00 2. Chase all roof leaks and repair as needed. $2,100.00 3. Replace A/C units and upgrade system, $8,400.00 4. Replace rotten plywood floors in car. $5,800.00 5. Replace all water damaged window sills. $5,800.00 6. Repair /Replace all damaged window shades. $5,500.00 7. Strip contact paper and carpet from walls. $4,300.00 8. Remove ceiling egg grates in Observation end of $2,600.00 car. 9. Remove wall panels in Observation end. $2,600.00 10. Replace all degraded wall panels and replace all $5,200.00 insulation where accessible. 11. Repaint interior of car circa 1947 including ceiling. $7,100.00 12. Replace floor covering with 100% nylon carpeting in Observation Lounge and Linoleum in the $7,900.00 Tavern end. 13. Replace light lenses in Tavern end with original $10,600.00 and repair /service light fixtures. 14. Service /repair electrical /lighting system. $2,100.00 15. Re- upholster Tavern seating consistent with the $7,500.00 1947 original seating. 16. Replace Tavern section table tops. $3,600.00 17.Acid wash car exterior, $700.00 18, Replace car end diaphragm bellows. $1,450.00 19. Purchase and install 12 ea. Lounge chairs. $9,200.00 20. Purchase and install window side curtains for $2,300.00 Observation and Tavern sections. 21. Build and install historically accurate desk in $3,350.00 Observation Lounge against bulkhead. 22. Have mirrors behind bar etched with proper period $700.00 design. 23. Service and install components for electro- $1,850.00 mechanical refrigeration in bar area. 24. Research, replicate, and install interior artwork as $12,000.00 found in original 1947 construction. Lump Sum Total $122,450.00 Page -12- Packet Page -2047- CotE7rr Cas4nLy AdnuNstabve Services Nisnn FiacurC�rn I5crr Contract Modification ❑ Work Order Modification Amendment 7/7/2015 16.E.9. Procurement Services Change Carder Form Contract #: 14 6237 Change #: = Purchase Order #: 4500156973 Project #: L Contractor /Firm Name: AMEC Foster Wheeler Enviro & Infr Project Name: - BvlorackrAvenue im }Drovements Project Manager Name; Bradley Muckel Department: Immokalee CRA Original Contract/Work Order Amount $ 43,442.00 1113/15; 16.B.2 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 43,442.00 1/13/15; 16.13.2 Last BCC Approval Date; Agenda Item # Current ContractfWork Order Amount $ 43,442.00 {> ` 10 I / f# SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 0-00 0.00% Total Change from Original Amount Revised Contract/Work Order Total $ 43,442.00 0.00% Change from Current BCC Approved Amount Cumulative Changes $ 0.00 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed 1/30/15 Original 6130115 Last Approved 6130115 Revised Date 8/29/2015 Date Completion Date Date (Includes this change) # of Days Added 60 Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other (see below) Provide a response to the following: 1.) detailed and specific explanation /rationale of the requested change(s) to the task(&) and / or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and /or Contractor if needed. Purpose Extend completion date of this GEE contract to coincide with the completion date of the related construction contract for Quality Enterprises 14 -6236. Impact if this change is not processed The construction engineering inspection (CEI) firm would not be available to perform CEI services at the end of this construction project. Field supervision, testing, as -built review and daily reports would all need to be performed by CRA staff. Prepared by: (Project Manager Name and Date: 6/1/15 Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same terms and conditions as contained in the contract/ work order indicated above, as fully as if the same were stated in this acceptance, The adjustment, if any, to the Contract shall constitute a full and final settlement o any and all claims `the Contractor/ Vendor/ Consultant/ Design Professional arising out of or related to the change set f rth herein, I ^luding cla s f ipact and delay costs. Accepted by: Nestor Fernandez- AmecFW Date: 611115 (Contractor / Vendor / Consultant / Design' :-ofessional ay6 Pame of Firm, if project applicable) Approved by: (Design P Approved by: (Prdcurea ional and Name of Firm, if project applicable) (Divisions who may require additional signatures may include on separate sheet.) Packet Page -2048- Date: Date: rte- Z - Revised: 10/28/2014 Gotfier- copy katnin:stratiw Servces D mszon - �'rogifem 1 -1CM=l 7/7/2015 16.E.9. Procurement Services Change Order Form E Contract Modification ❑ Work Order Modification ❑ Amendment Contract #: 14 -6224 Change #: = Purchase Order #: 450015156/ Project #: 35027 Contractor /Firm Name: Compass Construction Project Name: CAT Passenger Transfer Facility Improvements Bryan Vehovec De artment: Public Tran Project Manager Marne P sit &Neighborhood Enhancement : Original Contract/Work Order Amount $ 3,721,994.00 3/25/14 11.13 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 3,721,994.00 3/25/14 11.13 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 3,721,994.00 11/2712015 SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 50,159.05 1.35% Total Change from Original Amount Revised Contract!Work Order Total $ 3,772,153.05 1.35% Change from Current BCC Approved Amount Cumulative Changes $ 50 1 r)q nr;l 1.35% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed 8/26/14 Original 9/20/15 Last Approved 9/20/15 Revised Date 11!27/15 Date Completion Date Date (Includes this change) # of Days Added 68 .M Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) E Other (see below) Provide a response to the following: 1.) detailed and specific explanation /rationale of the requested change(s) to the task(s) and / or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and /or Contractor if needed. Aqq��- 1. This change addresses items that wereincluded in original contract scope by designer. The Proposed changes will result in value added enhancements. This includes the addition of acoustical canopies in the Administration building lobby and value added changes to the site pavement. 2. The Contractor will not be able to complete the project as other items in the contract scope are dependant upon these changes being completed. on date will be modified to match what is listed in the Notice to Proceed. Completion date nor add time to the contract. 4. This change includes a request for a time extension of 68 calendar days to be added to the contract time due to various delays that were encountered. The new Final Competion date will be November 27, 2015. Prepared by: Bryan Vehovec, Project Manager - Public Transit & Neighborhood Enhancement Date: Cel _1_12 d' Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same terms and conditions as contained in the contract / work order indicated above, as fully as if.the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant / Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs. Accepted by: _ ` Date: 6/01/2015 Compass Construction Approved by: pproved by: Audie Robinson, Project Manager Atkins Procurement Professional ' (Divisions who may require additional signatures may include on separate sheet.) Packet Page -2049- Date: 6/01/2015 Date: Cl�' 714 - ( Revised: 10/28/2014 Approved by: Approved by: Michelle Arnold, Director— Public Transit & Neighborhood Enhancement (Divisions who may require additional signatures may include on separate sheet.) Packet Page -2050- 7/7/2015 16.E.9. Date: 6 ` Z' %S Revised: 10/2812014 14 -6224 CAT Transfer Station Facility Improvements CHANGE ORDER #3 Description Admin Acoustical Canopies Admin Relocated Elect CO Electric Public Restroom $ 45,910.00 $ $ 757.00 $ $ 690.80 $ $ 585.20 $ $ 1,825.00 $ Change Order #1- Credit to Allowance Line Item #1070 Change Order #2 - Credit to Allowance Line Item #1070 Total Change Order #3 Change Order #1 & 2 Credit NET CHANGE 7/7/2015 16.E.9. Markup TOTAL 2,295.50 $ 48,205.50 37.85 $ 794.85 34.54 $ 725.34 29.26 $ 614.46 91.25 $ 1,916.25 TOTAL $ 52,256.40 Change Order #3 $ 50,159.05 Difference $ (2,097.35) $ (1,152.44) i $ (944.91) $ (2,097.35) j Packet Page -2051- I i $ 52,256.40 $ (2,097.35) i I $ 50,159.05 7/7/2015 16.E.9. BrilhartBrenda Prom: VehovecBr yal l Sent: Wednesday, June 17, 2015 4:23 PM To: ArnoldMichelle Cc: BrilhartBrenda Subject: Change Order #3 After reviewing the items of the change order, I would say that; The Civil /Site work change was a combination of unforeseen /unaccounted for during the design phase and a value added enhancement due to it having multiple items associated with it. The electrical relocation change was unforeseen /unaccounted for during the design phase. The sound panels addition was planned to be installed by this Dept. but not included in the design at time of bid so they would be considered a value added enhancement. Bryan Vehovec, ProjectManager Collier County Public Transit & Neighborhood Enhancement Bryan Vero vecr0,colliere-o v net (239) 537- 0716moMe (239) 252 -4994 office Under Florida Law, e-mail addresses are public records. if you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact this office by telephone or in writing. Packet Page -2052- CRMPass nstruction, Inc. ,9X& awa Of �_rce Clue, Bryan: May 28, 2015 Collier County Public Transit & Neighborhood Enhancement 3299 Tamiami Trail. East Naples, FL 34112 -4901 Attention: Bryan Vehovec RE: Facility Improvements 8300 Radio Road Time Extension 7/7/2015 16.E.9. In light of many issues that have been experienced during the course of construction so far as documented in our regular project meetings, the overall project schedule has been impacted to a point that is unrecoverable. This letter is meant to serve as our formal request that an additional sixty -eight (68) calendar days be added to the contract time for these related delays. Some of the significant issues which have contributed to the delays include but are not limited to the following: - Lake excavation was slowed due to a lack of permit allowing for spoils to be hauled offsite. This was not common knowledge at the time of bidding and /or contract award and was not anticipated. Stockpiles were maintained onsite and stacked vertically which greatly impacted maneuverability onsite, water retention related to dewatering and progress on utility installation and earthwork activities. This had an overall impact of thirty (30) days to the project schedule. Contaminated soil was found in the East and West berms which was required. to be sampled, analyzed, removed and replaced which had an impact to the schedule of six (6) days. The coordination of the fuel building permits required significant effort above and beyond what was identified within the original contract documents. Compass was originally required to contract with a fueling equipment company to finalize the equipment design and permitting, but the original building permit documents as submitted by the architect were not presented in a format deemed acceptable by Collier County Growth Management. This required numerous meetings additional documentation and simultaneous submission of the various components including the metal building, fuel canopy and fuel equipment. This initially backed up the fuel station scope of work to occur later in the schedule but follow the same general timetable. Later, due to prolonged coordination 824 Lafayette St. * Cope Coral, FL 33904 -9031 * Phone: 239- 542 -7118 * Fax: 239 - 542 -8648 www.comr>assconstruction.com * State- Certified General Contractor * License Number CG CO25919 Packet Page -2053- 7/7/2015 16.E.9. efforts and general scope changes the flow of work between the canopy and building were impacted by a total of thirty (30) days. - The existing water main on Radio Road was found to be in a different location that shown on the contract documents and required the location of the new tie -in to be relocated at the direction of Collier County Utilities. Additionally the existing 16" main was in fact a 12" main, and the materials ordered for the original scope had to be replaced prior to commencing with the tie -in. These items had an impact of three (3) days to the project schedule. - The primary service conduits and transformer pad were not in the FPL scope of work to Collier County, and we were required to install the conduits and pad for the installation of FPL's scope of work. This had an impact of four (4) days to the overall project schedule. - The existing building foundations in the administration building restrooms were in conflict with the new work and required modifications to tie -in the new and existing work. This had an impact of five (5) days to the overall project schedule. - The existing water service to feed the administration building was found to be a 1." line vs. the required 2" service. This required an additional water service to be run to the administration building which included excavation, piping and patching. This had an overall impact to the schedule of three (3) days. - The existing sewer lateral at the administration building was found to be 4" line vs. the required 6" line and the cleanout elevation would not allow for the new tie -in to occur within the design parameters. We were required to cap and grout the existing 4" service and run a new 6" service back to the lift station and tie into the structure of the lift station itself. This had and overall impact to the schedule of four (4) days. As we have discussed throughout the course of construction our objective has always been to keep the project moving forward as issues have arisen, discuss the setbacks during our project meetings and look for opportunities to gain back any lost time. Now that we have reached most of our significant milestones we will endeavor to gain back some of the delay prior to project completion. Sincerely, COMPASS CONSTRUCTION, INC Doug Oliver Vice President 824 Lafayette St, * Cape Coral, FL 33904 -9031 * Phone: 239 - 542 -7118 * Fax: 239 - 542 -8648 2 www.compossconstruction.com * State - Certified General Contractor * License Number CG 0025919 Packet Page -2054- 7/7/2015 16.E.9. #VALUEt I Change from Currant Amount Completion Da*11ascription.ofthe Task(s) Change,:and Rationalefcrthe Change Notice to Process N/A Original N/A Last Approved NIA Revised Data WA Date Completion Data Date (tridudas this ehenpe) A of Days Added 1•UA Select Tasks ' ❑ Add new task(*) ❑ Delete tasks) ❑ Change task(*) ® Other (see below) Provide a response to the following: 1.) detailed and specific explanation/rationale of the requested change(*) to the task(s) and / or the additional days added (If requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact If this change Is not processed. Attach additional Information from the Design Professional ardor Contractor if needed. 1.) Additional line items to be added to laid #14 -6232 as authodeed by Exhibit IV, Item 1 of the solicitation, Thane unit priced items are required for incidental work during certain projects that have features not typical of the majority of roadways. (e.g. paver crosswalks and protection thereof, replacing worn out limbers or broken retaining blacks along pathways, other work in the performance of roadway paving maintenance) 2.) The need for these additional unit priced items were not anticipated at the time of the bid. 3.) If these additional unit priced items are not added to the contract, projects wl be Impacted by causing delays or even bringing them to a standstill. Prepared by' ` LA ` Date: 2z 4 Zd gar Name and n) Accsptance of C ge Order shalt can ute a modification to contract /work order identified above and will be n4act to all the same terms and cond ns as contained in the contract I work order indicated above, as fully as If the same were slated in this acceptance. The adjuslmerit, if any to the Contract shall corAfkda and final settlement of any and all claims of the Confr-dctor / Vendor / Consultant / Design Pro" l arising out o or re =thea=ge sat forth hherein, inclutd' iN claims for impact aril delay coats. Accapted 4- � ` "' Date: f� or / Vand1or /1 Consultant I Design Protessional and Name of Fi0n, if project applicable) Approved by: l 1 A Date: (Dp gn Profes.sioni&l and blprnq of Firm, if project applicable) Approved by: I Gtr i Cl(`!.� 1- Date; �^ . Packet Page -2055- lcz i C Procurement Services Change Order Form XContract Modification ❑ Work Order Modification ❑ Amendment Contract #., 148232 Change It: = Purchase Order 0: 1 WA Project # A ContractorlFirm Name: Ajax Paving Industries of Florida, LLC project Nama: Asphalt, Milling & Related items Project Manager Name• JR Gorentz --7 Department I Growth Management Department — Road "nt� Original ContracUWork Order Amount NIA 5- 13- 14,11.D Original BCC Approval Date; Agenda item # Current BCC Approved Amount NIA 5- 13- 14;11.D Last BCC Approval Date; Agenda Item Current ContractlWork Order Amount N/A 5112120 #6 SAP Contract Expiration Data (Master) hfrom ReIvised ContradNVorkhOrder Total S 0.00 #VALUEi Change Current BCCIApproved Amount #VALUEt I Change from Currant Amount Completion Da*11ascription.ofthe Task(s) Change,:and Rationalefcrthe Change Notice to Process N/A Original N/A Last Approved NIA Revised Data WA Date Completion Data Date (tridudas this ehenpe) A of Days Added 1•UA Select Tasks ' ❑ Add new task(*) ❑ Delete tasks) ❑ Change task(*) ® Other (see below) Provide a response to the following: 1.) detailed and specific explanation/rationale of the requested change(*) to the task(s) and / or the additional days added (If requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact If this change Is not processed. Attach additional Information from the Design Professional ardor Contractor if needed. 1.) Additional line items to be added to laid #14 -6232 as authodeed by Exhibit IV, Item 1 of the solicitation, Thane unit priced items are required for incidental work during certain projects that have features not typical of the majority of roadways. (e.g. paver crosswalks and protection thereof, replacing worn out limbers or broken retaining blacks along pathways, other work in the performance of roadway paving maintenance) 2.) The need for these additional unit priced items were not anticipated at the time of the bid. 3.) If these additional unit priced items are not added to the contract, projects wl be Impacted by causing delays or even bringing them to a standstill. Prepared by' ` LA ` Date: 2z 4 Zd gar Name and n) Accsptance of C ge Order shalt can ute a modification to contract /work order identified above and will be n4act to all the same terms and cond ns as contained in the contract I work order indicated above, as fully as If the same were slated in this acceptance. The adjuslmerit, if any to the Contract shall corAfkda and final settlement of any and all claims of the Confr-dctor / Vendor / Consultant / Design Pro" l arising out o or re =thea=ge sat forth hherein, inclutd' iN claims for impact aril delay coats. Accapted 4- � ` "' Date: f� or / Vand1or /1 Consultant I Design Protessional and Name of Fi0n, if project applicable) Approved by: l 1 A Date: (Dp gn Profes.sioni&l and blprnq of Firm, if project applicable) Approved by: I Gtr i Cl(`!.� 1- Date; �^ . Packet Page -2055- an-- 7/7/2015 16. E.9. 14 -6232 Asphalt, Milling & Related Items Prafarrari KAntcrinlc 1— Additional Pricing and Mark Up Position Hourly Rate Superintendent $ 51.80 Foreman $ 44.15 Operator Laborer $ 25.16 $ 21.46 Percentage Material Mark Up % 10% Materials will require that invoices be submitted and the markup only applies to the price of the materials, no mark up for shipping or taxes. Packet Page -2056- 7/7/2015 16.E.9. Ajax Paving Industries of Florida. LLC EXHIBIT "B" PRICE SCHEDULE �i Page 1 of 3 Packet Page -2057- /7/2015 16.E.9. Ajax Paving Industries of Plorida, LLC Page 2 of 3 Packet Page -2058- Yards 7/7/2015 16.E.9. -. U .Ajax Paving Industries of* Florida, LLC Section B: The Following Items are not Inciuded in Aword Toto . Price Adjustment forAsphalt & Related Items: ITEM — ;DESCRIPTION QTY UNIT UNIT PRIM 113 RC - 70 1 Gal $4.00 114 RC -250 1 Gal S4.D0 115 SS -1 or SS -1H 1 Gal $4.00 116 AE - 60 1 Gal $4.00 117 AE - 90 1 Gal $4.00 118 AE - 150 1 Gal Sit= 119 AE - 200 1 Gal 54.00 120 EPR -1 1 Gal 54.00 121 RA - 500 1 Gal 54.00 122 RS -1h RS -2 CRS - Sh, CRS -2 1 Gal $4.00 123 NTSS - ihm 1 Gal $4.00 124 Other write In Trackless Tack Gal 54.00 125 Other -it. In Gal 126 Other write In Gal 127 Shoulder Ground-in Rumble Strip Placement (longitudinal Cut) Continuous I Mlle $8,500.00 128 Shoulder Ground -In Rumble Strip Placement (Longitudinal Cut), Skip Array 1 Mlle $8,500.00 129 Shoulder Ground -In Rumble Strip Placement (Transverse Cut) Continuous 1 Mlle $8.500.00 130 Shoulder Ground -in Rumble Stop Placement (Transverse Cut) Skip Array 1 Mlle $8,500.00 131 Asphalt Curb 1 LF $8.00 132 Shoulder Widening/Base Preparation a Inch compacted depth) 1 SY $30.00 133 Shoulder Widening /Base Preparation 112 inch compacted depth) 1 SY $35.00 134 Miscellaneous Base Work Preparation (4 inch compacted depth) 1 SY $10.00 135 Miscellaneous Base Work Preparation (6 Inch compacted depth) i SY $20.00 136 Miscellaneous Base Work Preparation IS inch compacted depth) 1 SY $30.00 137 Miscellaneous Base Work Preparation (12 Inch compacted depth) 1 SY $35.00 138 Swale rework (6 feet wide, 3 foot deep) Includes material disposal 1 LF 55.00 139 Swale rework (6 feet wide, 2 foot deep) Includes material dimpowl 1 LF $3.00 140 Sod laid In place Bahia 1 SF 516.00 141 Sod laid in place Flortan 1 SF 536.00 142 lWater when requested separate from other Items 1 Gal 51.00 143 S4 As hat ickup I Ton 560.00 144 8.111 Asphalt Pick up 1 Ton $65,00 145 spa Patch (1 42 inch asp a op tri) (Lut out old ana install compac, includes material disposal and 8" base work 1 SY $75.00 ProlTip'tPaymentTerm# =N'Aa 96. 'N A Days NAt _3dDeysar' i x _ . •., Page 3 of 3 Packet Page -2059- 7/7/2015 16.E.9. "A COLLIER COUNTY FACILITIES MANAGEMENT 3301 Tamiami Trail East . Building W . Naples, Florida 34112 . (239) 252 -8380 . Fax (239) 252 -3795 www.colliergov.net June 5, 2015 To: Mr. Mark W. Minor, P.E. Q Grady Minor & Associates, PA 3800 Via del Rey Bonita Springs, FI 34134 -7569 Re: Zero Dollar Contract Change Notification Change Order # 6 Contract: No. 12 -5868 Project No. 80065, Gordon River Greenway Park Purchase Order No. 45 - 140508 Dear Mr. Minor: By copy of this letter, the above referenced work order is being issued a zero dollar ($0.00) change as indicated below: ® Available funds are to be relocated between tasks as follows: Move funds from tasks: No Description Amount III Environmental Reports $ 1 6,792.50 Total $ 16,792.50 Move funds to tasks: No. Description Amount ($) 1.4 Request for Information $ 5,000.00 1.6 Detailed Observations $ 6,792.50 1.8. Work Directives / ... $ 5,000.00 Total $16, 792.50 By changing this contract, the County is not relieving your firm of its obligations to perform work in a timely and satisfactory manner or any consequences resulting from failing to do so. Collier County hereby reserves all legal rights, including, but not limited to, rights to terminate, suspend or elect any other appropriate course(s) of action should circumstances warrant with regard to the referenced work order. Sincerely, Claude H. Nesbitt Project Manager --; Rhonda Cummings =Pi of remer to 'S1; Purcha ing Department Approval:'" Date: Packet Page -2060- 7/7/2015 16.E.9. Co Coin` Procurement Services adrrunsaati�eseSemcmndsia, Change Order Form Proauemmi Services ® Contract Modification ❑ Work Order Modification ❑ Amendment Contract #: 11 -5621 Change #: = Purchase Order #: 4500133227 Project #: 35010 Contractor /Firm Name: Atkins North America Project Name: Design Services for CAT Transfer Facility Project Manager Name: Brandy Otero Department: Public Transit & Neighborhood Enhancement Original Contract/Work Order Amount $ 502,451.20 9/13/11 16A24 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 552,301.20 7/9/13 16D4 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 552,301.20 9/24/2015 SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 0.00 9.92% Total Change from Original Amount Revised Contract/Work Order Total $ 552 301.20 0.00% Change from Current BCC Approved Amount Cumulative Changes $ 49.850-001 0.00% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed 11/28/2011 Original 3/22/13 Last Approved 9!24/15 Revised Date 12/31/16 Date Completion Date Date (Includes this change) # of Days Added 1-%(0 Y Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other (see below) Provide a response to the following: 1.) detailed and specific explanation /rationale of the requested change(s) to the task(s) and / or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and /or Contractor if needed. 1) This change order is necessary to allow time for Task 4, (Construction phase services) during Phase II construction at Radio Road. 2) At time of contract award, there was not sufficient funds to construct all phases of this project, so task 4 construction services was only anticipated to be for the length of phase I construction. Funding has now been secured for Phase II construction, and staff is requesting that time be added to this contract to allow for construction services during phase II of the project. 3) It this change order is not processed, the consultant will not able to provide construction services for Phase 11. Prepared by: Public Transit & Neighborhood Enhancement Division Date: Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same terms and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant / Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs. Accepted by: Approved by: `reproved by: AT" C N CRT'►} fYi�L4 Date: l,5' / Design Professional and Name of Finn, if project applicable) Michelle Arnold, Director Brilhart, ProcuKement Strategist (Divisions who may require additional signatures may include on separate sheet.) Packet Page -2061- Date: �y Date: Revised: 10/28/2014 C 7/7/2015 16.E.9. SCHEDULE C PROJECT MILESTONE SCHEDULE - Project time to begin after issuance of Notice to Proceed ^ -1 Packet Page -2062- Schedule . Calendar Task Description Days {1 pD xwm��l L� * ' : eah'eIY�E "� t1P'� "* !�2 u�' P I:,:�.,,:TM,+t°.;; In.P�r.�7r`xair�la9 r.LlMill7iih _.�__ .eel. I :.,,x�'' 1 Programming/Design Charette Meetings Overall Site) 60 ` -I ��' �� Milli 117 ���;II r.J _.H_W:_..IE.�a9I„vl.. �'"a=a c" I S�� e:�A9 pp ppi�m }�A ec�+� x�JJEntertn , _aw 1 "ll'. aL�"7tE1__ - -. i , IM�IY Ill�i I - Final Design (60 Percent —100 Percent), Bid Phase 3 Services 120 Ilisl hr+All >� .�,..�I,ryy, .:..:f��C.r1��ItL"#��f �i�� F , , .,t�1lf 1���,y�ildl„ vl,�ly 1 II ♦I n ...�'. ��. :,:, ., �t7i:,, ..�" 5 Expenses 0 ^ -1 Packet Page -2062- c, cam' Fdmcrtspefie ser� �e„enc sautes j!�, Contract Modification ❑ Work Order Modification ❑ Amendment Contract #: 14 16289 Change #: Purchase Order #: Contractor/Finn Name: AJ Paving Industries of Florida, LLC Project Manager Name: Joseph F. Delate ungmai uontract/Work Order Amount Current BCC Approved Amount Current Contract/Work Order Amount _ Dollar Amount of this Change Revised Contract(Work Order Total Cumulative Chanoes 7/7/2015 16.E.9. a Procurement Services Change Order Form 4500157662 Project #: 60040 Design -Build Gold Project Name: en Gate Boulevard 4 -Lane Transportation Engineering Division, Growth Department Management Department 2124115; 11A Original BCC Approval Date; Agenda Item # 2/24115: 11A Last BCC Approval Date; Agenda Item # 5/1512017 SAP Contract Expiration Date (Master) 0.39 °10 Total Change from Original Amount 0.39% Change from Current BCC Approved Amount 0.39% Change from Current Amount CompletionaDate, Description of the Task(s) Change and Rationale for the Change Notice to Proceed 4/1/15 Original Last Approved 5/15117 Revised Date 5/15/17 Date Completion Date Date N/A (Includes this change) # of Days Added —J Select Tasks ® Add new task(s) ❑ Delete task(s) ❑ s Change task (s) () ❑Other (see below) Provide a response to the following: 1.) detailed and specific explanationlrationale of the requested change(s) to the task(s) and / or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Contractor if needed. The design and construction of Golden Gate Boulevard 4- laning east of Wilson Boulevard requires the acquisition of right - of-way (ROW) for the roadway improvements. One such affected property is the Sanchez parcel, located at 170 Golden Gate Boulevard East, which has improvements that are in conflict with the Proposed construction. In order to acquire this property, a cure plan was created to mitigate the impacts of the widened roadway and to restore the property to its original condition. This change was not anticipated in the original contract because the property has improvements that are in conflict with the design, and there was no way of knowing these existed until crews were on site. This change order is critical to this construction project and will cause delays if not implemented in a timely manner. The costs have been vetted with staff, negotiated with the contractor and fully encompass all work necessary to make the Sanchez's whole. See attached memo for additional information. PREPARED BY: Jose¢h F. Delate, PLA, ASLA, Senior Project Manager Transportation Engineering Division, Growth Management Department ! ' 1 Date Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same terns and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full znd final settlement of any and all claims of the Contractor / Vendor / Consultant ! Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs. (Divisions who may require additional signatures may include on separate sheet.) Revised: 1012af2014 Packet Page -2063- ACCEPTi p BY .'I 7/7/2015 16.E.9. Andy DeCreene, Area Manager, Ajax Paving Industries of Florida, LLC APPROVED BY; sRtA6 r_q,2 Cary Putaansuu, P.E., Principal Project Manager Transportation Engineering Division APPROVED BY: %ray, Tran APPROVED E.; Director Z Engineering Division Deputy County Manager r APPROVED BY_ Evelyn Collin, curement Strategist Purchasing Division 911.5- (�5 l�s Date Z10/ Is' Date Date Date (Division6 who may require additional signatures may Include on separate sheet.) Revised; 10/26/2014 Packet Page -2064- 0)117ey County Gna,tvt~ MC-U-10—U-11 lualt Depa triient Transportation Engineering Division Date: June 11, 2015 To: From: Subject: MEMORANDUM 7/7/2015 16.L.9. File- Design -Build Golden Gate Boulevard 4 -Lane, East of Wilson Boulevard, Change Order # 1, Project # 60040 Joseph F. Delate, PLA, ASLA; Senior Project Manager Collier County Transportation Division Emily R. Pepin, Assistant County Attorney Collier County Attorney's Office Back -up Memo for Change Order #1 Golden Gate Boulevard 4- Laning, East of Wilson Boulevard, Project Parcel 141 (Sanchez - owner) is located at 170 Golden Gate Boulevard East on the south side of Golden Gate Boulevard between Wilson Boulevard and 2nd St. SE. The parent tract of this parcel is improved with a single - family home with an existing front yard set -back from Golden Gate Boulevard of only 75 feet. The necessary right -of -way (ROW) acquisition for this project reduces the set -back to 30 feet, significantly impacting the functionality of this parcel's driveway, septic system and drainfield. In most instances, the property owner is compensated for these impacts with funds sufficient for them to implement a cure to fix the issue. Many times the property owners elect to keep the monies awarded and not implement the proscribed cures, since in most circumstances these impacts and cures do not materially impact the habitability of the,,property by the owner. In this case, however, the impacts are so severe that the home would be hendered uninhabitable if not implemented. Collier County ROW Section has had recent experience in which agreed/settled cures were not implemented by property owners causing delays /confusion upon the commencement of road construction and hardship to the property owners who had otherwise spent the allocated funds or no longer had the time to implement the cures. In an effort to avoid these problems and to save money on possible litigation, County ROW staff pro- actively approached the property owner in an effort to coordinate a cure as part of an overall settlement of the parcel. The owner was receptive and cooperative. Through discussions with engineering and construction experts, it was determined that the only feasible cure would require re- configuration of the driveway in a way that would allow the property owner to utilize a portion of the proposed roadway easement and a re- alignment of the existing drainfield and septic tank within the reduced confines of the front -yard setback. This agreed upon cure evolved over several months and involved lengthy negotiations with the property owner. Given that some of this curative work was going to take place within the new ROW (which would have to be coordinated with Tra'tsporlafion Engineering Division - 2885 South Horseshoe Drive - Naples, Florida 34104.239- 252 -8182 • www.coliiergov.net Packet Page -2065- 7/7/2015 16. E.9. the roadway Contractor), the complementary nature of some the work involved (grading, paving, gravity wall), and the narrow window of time available to implement the cure, it was determined that the most effective method to implement the cure would be for the County to directly oversee and pay for the cure by utilizing the services of the prospective roadway Contractor who is willing and able to take on these tasks. This specific curative proposal evolved over time and the final decision to utilize the roadway Contractor for this work took place after the Request for Proposal (RFP) for the roadway project itself was solicited, and was not included in the roadway Contractor's original contracted scope of work. While the construction costs for the roadway project are increased by directly implementing the cure, it is more economical for the County to perform the work with our roadway Contractor by avoiding litigation related costs (attorney fees, expert fees, engineering reports and studies, settlement premiums) and will be possible to avoid paying the property owner indirect construction costs to implement the cure. Moreover, the County will have assurance that the curative work is completed in a timely manner, without interference to the roadway Contractor's work, while avoiding any possible claims. The County also would avoid the risk that no cure is implemented and the home becomes uninhabitable. The Change Order 41 proposal from Ajax Paving (roadway Contractor) for this cure encompasses the surveying, geo- technical, design, permitting, project management, construction, inspection and certification of a new on -site waste disposal system (septic tank and drainfield), removal of the existing on -site waste disposal system and usage/ maintenance of the existing system as a temporary disposal system during this construction, FDOT index retaining wall with residential finishes, concrete hammerhead driveway to allow the property owner to exit their property onto the new highway, and final grading, sodding, and mowing. The total cost for this Change Order #1 is $75,085.78 which has been negotiated with the Contractor from an original price of approximately $125,000. The pricing has been reviewed by staff, analyzed and approved by a staff Professional Engineer (see attached memo), and vetted with multiple levels of County government, including the County Attorney's Office. It is customary for work to be added to County construction projects to accommodate changes in the field, such as this, and a Change Order is the appropriate mechanism to procure this type of work. Packet Page -2066- Copier County 7/7/2015 16.E.9. Procurement Services Change Order Form ® Contract Modification ❑ Work Order Modification ❑ Amendment Contract #: 15 6370 Change #: = Purchase Order #: N/A Project #: N/A Contractor /Firm Name: Contemporary Controls & Communictionsinc. Project Name: Motorola Centeral Control Irrigation Supplies & Services Project Manager Name: Pamela Lulich Department: County- wide Bid # 15 -6370 Original Contract/Work Order Amount WA 2/10115;16A9 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount N/A 2/10115;16A9 Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount N/A 2/9 /2016 SAP Contract Expiration Date (Master) Dollar Amount of this Change N/A #VALUE! Total Change from Original Amount Revised Contract/Work Order Total $ 0.00 #VALUE! Change from Current BCC Approved Amount _... Cumulative Changes #VALUE! #VALUE! Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed N!A Original N/H Last Approved N/A Revised Date N/A Date Completion Date Date (Includes this change) # of Days Added N/A Select Tasks ® Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other (see below) Provide a response to the following: 1.) detailed and specific explanation /rationale of the requested change(s) to the task(s) and / or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed. 1.) Additional line items to be added to the Bid # 15 -6370 as authorized by Exhibit IV, item 1 of the solicitation. The items are needed for incidental work that will be needed to upgrade communication changes in the conversion from unsupported Windows XP to supported VVindows7. REPAIR: MLB -8 -AC MOTOROLA 8 STATION AC LIGHTNING BOARD S73.15 REPAIR: MLB -I2 -AC MOTOROLA 12 STATION AC LIGHTNING BOARD S85.63 MLB -I2 -AC MOTOROLA 12 STATION AC LIGHTNING BOARD S378 -00 2.) The additional separated items were not anticipated at the time of the bid. These are parts of the bid items that are approved on the Bid but not itemized. Adding items to the bid sheet as separate parts are due to the need for repair or replacement of a single part over time or usage. These components are existing in the field and are valuable. They are part of the overall Motorola onsite controller package and have been for years. They are surge protectors that protect the equipment from power surges coming in from the field and they also provide a secondary way of opening the irrigation field valve for manual tests. 3.)Some new additional items are added to the bid because of an oversight of future work needed by the contractor. Prepared by: Lulich, Landscape Operations Manager, Road Maintenance Division) Date: 7// �J Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same terms and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of�he Contractor / Vendor / Consultant / Design Professional arising o:ti�f or relate tithe change set forth herein, including claims for imp dt and delay costs. Accepted by:— Approved by: (Procurement & Communication, Inc. ) 1 (Divisions who may require additional signatures may include on separate sheet.) Packet Page -2067- Date: Date: / 7/7/2015 16.E.9. 15 -6370, Motorola Central Control Irrigation Supplies & Services ITEM DESCRIPTION NON BID ITEMS AMOUNT REPAIR: MLB -8 -AC MOTOROLA 8 STATION AC LIGHTNING BOARD $73.15 REPAIR: MLB -I2 -AC MOTOROLA 12 STATION AC LIGHTNING BOARD $85.63 MLB -I2 -AC MOTOROLA 12 STATION AC LIGHTNING BOARD $378.00 Packet Page -2068- 7/7/2015 16.E.9.", Exhibit IV: Additional ITB Terms and Conditions 1. Additional Items and /or Services a 4 Additional items and / or services may be added to the resultant contract, or purchase order, in compliance with the Purchasing Ordinance. 'Conflict of Interest Vendor shall provide a list of any businesses and /or organizations to which the firm has any affiliation or obligations within the past five (5) years; whether paid or donated, which could be construed by the County as a conflict of interest. Disclosure of any potential or actual conflict of interest is subject to County staff review and does not in and of itself disqualify a firm from consideration. These disclosures are intended to identify and or preclude conflict of interest situations during contract selection and execution. 3. Vendor Performance Evaluation Collier County has implemented a Vendor Performance Evaluation System for all contracts awarded in excess of $25,000. To this end, vendors will be evaluated on their performance upon completion /termination of agreement. 4. Use of Subcontractors Bidders on any service related project, including construction, must be qualified and directly responsible for 49% or more of the solicitation amount for said work. 6. Deductions for Non - Performance The County reserves the right to deduct a portion of any invoice for goods not delivered, or services not performed in accordance with requirements, including required timeframe. The County may also deduct, or chargeback the Vendor the costs necessary to correct the deficiencies directly related to the Vendor's non - performance. 5. Offer Extended to Other Governmental Entities Collier County encourages and agrees to the successful vendor extending the pricing, terms and conditions of this solicitation or resultant contract to other governmental entities at the discretion of the successful vendor. 6. Environmental Health and Safety All Vendors and Sub vendors performing service for Collier County are required and shall comply with all Occupational Safety and Health Administration (OSHA), State and County Safety and Occupational Health Standards and any other applicable rules and regulations. Vendors and Sub vendors shall be responsible for the safety of their employees and any unsafe acts or conditions that may cause injury or damage to any persons or property within and around the work site. All firewall penetrations must be protected in order to meet Fire Codes. Collier County Government has authorized OSHA representatives to enter any Collier County facility, property and /or right -of -way for the purpose of inspection of any Vendor's work operations. This provision is non - negotiable by any department and /or Vendor. #15 -6370 15 Packet Page -2069- jam��; 7/7/2015 16.E.9. wlerco- pt'rn—'Y Procurement bervices AdminisniJveSeNcesDMsion Change Order Form Procurement Senuces [0 Contract Modification ❑ Work Order Modification ❑ Amendment Contract #: 13 -6137 Change #: LEI Purchase Order #: 45001478341 Project #: 51031 Contractor /Firm Name: FDeAngelis Dimond Construction Project Name: J -1 HVAC Systems Replacement Project Manager Name: Robert Fuentes Department: Facilities Management Original Contract/Work Order Amount $ 5,182;845.00 9 -24 -13 # 11'F Original BCC Approval Date; Agenda Item # Current BCC Approved Amount '$ . T6tv9I�Z"i.2o _4 -ZI-IS Nr z- Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 4.;747;022:53 f SAP Contract Expiration Date (Master) Dollar Amount of this Change "'$ 48,683.67 -7.47% Total Change from Original Amount Revised Contract/Work Order Total E$4j,719.5,706.2dO .071 Change from Current BCC Approved Amount Cumulative Changes 7,138.80 1.03% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed 10 -31 -2013 Original 2 -11 -2016 Last Approved 2 -11 -2016 Revised Date 2 -11 -2016 Date Completion Date Date (includes this change) # of Days Added 0 Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ❑ Other (see below) Provide a response to the following: 1.) detailed and specific explanationirationaie of the requested change(s) to the task(s) and / or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and /or Contractor if needed. The additional work in WD # 12 includes numerous non - compliant electrical issues that were hidden from view due to a secure ceiling in hallways and holding cell areas. Most of the work is needed to comply with new electrical, fire and mechanical codes that are in effect and were not when Building was built in 1984. Various items in this change were requested by Jail Staff and AHJ to comply with life safety. Change was not anticipated and not included due constraint in the building type (jail) accessibility of areas and other security concerns in an occupied building. Additional 34 Fire Dampers were installed for Fire Compliancy per Fire Marshall and NFPA. Chases between cells needed major repairs to water lines that were rusted and broken. If this change is not approved the whole project will stop and it will create a problem when moving inmates from one area affected area to another one. See additional Back up attached on WD # 12. 1 Prepared by: Robert Fuentes, Project Manager Facility Management Department / ! / ��e- 5- .94-20 -15- (Project Manager Name and Department) % r, Acceptance of this Change Order shall constitute a modification to contract /work o'��er identife above and will be subject to all the same terms and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the tract shall constitute a full and final settlement of any and all claims'of the Contractor / Vendor / Consultant / Design Profession o rising t of or related to the change set forth herein, including claims for jmpact and delay costs. Accepted by: Date: r 1 / Consultant / Design Professional and Name of Firm, if project applicable) / Approved by: '5 <-efl 54:nurvt0( pg4g Date: (Design Professional and Name of Firm, if project applicable) Approved by: rement P Date: & — (Divisions who may require � Packet Page - 2070 -:lude on separate sheet.) Revised: 10128/2014 C�a� {ie-r Gr ou�axy Admindstrabve Services avisian Procurement Serv=s 7/7/2015 16.E.9. ProCLi . UlV1c.c> Change Order Form YContract Modification ❑ Work Order Modification ❑ Amendment - ontract #: 13 -6137 Change #: li4_] Purchase Order #: 1 4500147834 I Project #: 51031 Contractor /Firm Name: FDeAngelis Dimond Construction Project Name: J -1 HVAC Systems Replacement Project Manager Name: Robert Fuentes -] Department: Facilities Management Original Contract/Work Order Amount $ 5,182,845.00 9 -24-13 # 11 F Original BCC Approval Date; Agenda Item # Current BCC Approved Amount 9 2 4 -4;#44F Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount "'°-2 ; SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 48,683.67 -11 s7ya Total Change from Original Amount Revised Contract/Work Order Total — 11.57.70 Change from Current BCC Approved Amount Cumulative Changes $ ) - 4-a7-04 Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed 10 -31 -2013 Original 2 -11 -2016 Last Approved 2 -11 -2016 Revised Date 2- 11 -2Q16 Date I I Completion Date Date (Includes this change) # of Days Added 0 Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ❑ Other (see below) Provide a response to the following: 1.) detailed and specific explanation /rationale of the requested change(s) to the task(s) and / or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and /or Contractor if needed. The additional work in WD # 12 includes numerous non - compliant electrical issues that were hidden from view due to a secure ceiling in hallways and holding cell areas. Most of the work is needed to comply with new electrical, fire and mechanical codes that are in effect and were not when Building was built in 1984. Various items in this change were requested by Jail Staff and AHJ to comply with life safety. Change was not anticipated and not included due constraint in the building type (jail) accessibility of areas and other security concerns in an occupied building. Additional 34 Fire Dampers were installed for Fire Compliancy per Fire Marshall and NFPA. Chases between cells needed major repairs to water lines that were rusted and broken. If this change is not approved the whole project will stop and it will create a problem when moving inmates from one area affected area to another one. See additional Back up attached on WD # 12. Prepared by: Robert Fuentes, Project Manager Facility Management: Department ,— Date: 5 -14 -2015 (Project Manager Name and Department) Acceptance of this Change Order shall constitute a modifi b n to contract /work order identified above and will be subject to all the same terms and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if , to ttie Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant / Design Prof ssional ari ing out of or related to the change set forth herein, includiinng claims for impact and delay costs. Accepted b E�,`%C /�ill l c ? c ZJrCIS %' /�1�/ Date: //y Contractor / Vendor / Consultant / Design Professional and Name of Firm, if project applicable) Approved by: 41,,.2 �,�� --�" Date: (Design Professio nal and Name of Firm, if project applicable) Approved by: Date: (Procurement Professional (Divisions who may require; ' ' .lude on separate sheet.) Packet Page -2071- Revised: 10/28/2014 7/7/2015 16.E.9. Facilities Management Department WORK DIRECTIVE CHANGE PROJECT NAME: J -1 HVAC System Upgrades DATE OF ISSUANCE: 5/07/2015 OWNER: Collier County Board of Commissioners CONTRACTOR: DeAngelis Diamond Construction CHANGE # 12 EFFECTIVE DATE: 5/07/2015 PROJECT #: 51031 PO #4500147834 ENGINEER: H2 Engineering You are directed to proceed promptly with the following change(s): Description: Provide the following changes on certain non - conforming and code related issues in Phase II. CR -50 Additional electrical work needed and was not anticipated during demolition and new installation on corridor 3 & 4; 1- Relocate VFD from wall that was shown to be installing per drawings (E 10213) to different location in the wall. 2- Strap up all low voltage wiring in hallways to prevent damage during ceiling demolition. 3- Re- install two (2) lights that were taken down to install new duct work in boiler room. 4- Trace and repair electrical conduit leaking rain water from core drilling to mechanical room corridor 5. 5- Re- traced lighting issue in POD 2 due to low voltage issues with Integrator system. 6- Pod 2 address punch items that failed during test and re -work duct detectors per Fire Dept., request. 7- Remove and re- install 5 casket styles light that were in the way for the installation of high mounted fire dampers in POD4 A, B &D. 8- Clean out exhaust fan chases in Pods 3 &4 for new F/A smoke detectors. 9- Install conduits and boxes in Pods 3/4 for roof chase F/A smoke detectors. 10- Install rigid EMT to supply RTU 3/4 feed. Existing had to be cut and abandoned due to unit was sitting on top of electrical conduit. 11- Relocate existing corridor 3/4 conduits, to accessible locations per electrical inspector, also separate conduit for F/A per Fire inspector request. 12- Relocate electrical conduits in phone room behind 4 corners to accommodate A/C return grill for corridor 3/4. 13- Install conduit in ductwork for F/A low flow smoke detectors in control room 3/4. 14- Fire alarm conduit marking and identification requested by ENFD even this is not part of NFPA. 15- Install new contactors for corridor and PODS 3/4 fire dampers to avoid overloads. 16- Furnish and install two (2) new wall pack lights for additional lighting in Floor care room. 17- Install wall pack light to replace wedge florescent fixture in AHU -6. $18,541.95. CR -51 Install high ceiling conduits for Fire Dampers and Smoke dampers in pods 3/4. Add conduit and boxes to accommodate 480Volt purge fans on F/A system. $3,121.65. CR -52 Provide additional access panels in the secure acoustical ceiling in hall ways 3/4 per Maintenance personnel request. $2,604.00. Packet Page -2072- 05105115 8:05 AM 7/7/2015 16.E.9. CR -53 Core drill and install additional smoke dampers to the communications room per requirement base on H2Engineering submission, and add additional 34 fire dampers to meet fire code these were located in the corridor areas. e "n c`c c ,310,555.6`5. CR -54 Remove and replace (18) 4" in plumbing chase to accommodate the installation of duct work. $ 1,477.75. CR -55 During the layout for the installation of TRU 6 -7 it was determined that the unit would be close to the edge of the parapet wall on the roof causing a safety concern to avoid any safety issues an aluminum railing is been erected to the edge of the wall for a total of 63 linear feet. $6,562.50. CR- 56 Purchase paint for Inmate labor to paint corridors 3 &4 and PODS # A,B,C PODS # A,B.C, thus reducing labor costs on having painting contractor due the work. $3,454.04. CR- 57 Repair numerous plumbing issues in PODS 3& 4 and refitting (4) hung wash basins in cells. $2,026.17. CR -58 Replace existing 40OW wall pack light that was inoperable in POD 3A. $339.96. Purpose of Work Directive: Less disruption in the Jail operations and to ensure proper operations of other infrastructures and in most cases was requiring by newer electrical and fire codes. Attachments: Change request from contractor with back up documents from subcontractor. If a claim is made that the above change(s) have affected Contract Price or Contract Times any claim for a Change Order based thereon will involve one or more of the following methods of determining the effect of the changes(s). Method of determining change in Contract Price: Method of determining change in Contract Times: ❑ Unit Prices N. Contractor's records ® Lump Sum Engineer's record ❑ Other ❑ Other Total Work Directive # 12 $48,683.67 Contract time increase or decrease by (0) calendar days. F i AUTHORIZED: a { l/ v ,d By: DeAngelis Diamond Construction Owner's`Representative Packet Page -2073- 05/05/15 8:05 AM To: Robert Fuentes - CCDF Collier County 3335 Tamiami Trail East Naples, FL 34112 Ph: 239-252-8380 Description: Additional electrical work 7/7/2015 16.E.9. DEAI-,iGELIS DlAmo�-jD C 0 N ST P. U C T 1 0 N,! N C. Change Request Number: 50 Date: 417115 Job: 13-021 Collier County J-1 HVAC System We are pleased to offer this proposal to make the following changes: To additional electrical work, to rectify non-conforming and meet code, repair previously damaged, add new, additional work all per attached work sheets, by Community. 16-001 Electric 17,659.00 Subtotal 17,659.00 Fee 882.95 The total amount to provide this work is $18,541.95 11 this is acceptable, sign and return via fax (239-594-1995) or email. Please provide apprcval at your earliest convenience. Only the work specifically outlined in this proposal is included. If you have any questions, or comments, feel free to contact me at 239-594-1994. Submitted by: Nic Kieft Approved by: DeAngelis Diamond Construction Date: Cc: Scott Craig PE (H2 Engineering, Inc.) 663$ WILLO' PARK DRIVE. NIMPILES, FL 34109 1 7309 IMERCHANIT COURT. SUITE B. SAP'1kS(DTA. FL 34240 \1 F L E S: 2 3 9. 5 1 4. 19 1 4 1 S A M S 0 9 4 1. 8 8. 6 9 9 D I L A N G E L I S D 1AMON D.MA Packet Page -2074- L(I W-1 DI- ANT GF1,1S DIAmc)N,D C0 NSTP U C T 10N.i NC Change Request To: Robert Fuentes - CCDF Collier County 3335 Tamiami Trail East Naples, FL 34112 Ph: 239 - 252 -8380 Description: Additional electrical work for Fire Alarm 7/7/2015 16.E.9. Number: 51 Date: 417/15 Job: 13 -021 Collier County J -1 HVAC System We are pleased to offer this proposal to make the following changes: To install additional conduit, boxes and fittings to allow the installation of low flow duct detectors to all pass through Fire /Smoke Dampers, Pods 3 & 4. (Per engineer and ENFD) Adding conduit and boxes so that Purge fans coudl be added to FA system. 16 -001 Electric (50) 1,859.00 16 -001 Electric (52) 1,114.00 Subtotal 2, 973.00 Fee 148.65 The total amount to provide this work is $3,121.65 If this is acceptable, sign and return via fax (239- 594 -1995) or email. Please provide approval at your earliest convenience. Only the work specifically outlined in this proposal is included. If you have any questions, or comments, feel free to contact me at 239 - 594 -1994. Submitted by: Nic Kieft Approved by: DeAngelis Diamond Construction Date: Cc: 6635 WILLOW PARE: DRIVE, NAPLES, FL 34109 ( 7309 MERCHANT COURT, SUITE h, SARASOTA. FL 34240 NAPLES: 239.594.1994 1 SARASOTA: 941.388.6997 DEANGELISDIAMOND.COM Packet Page -207S- 7/7/2015 16.E.9. DEANGELIS DIAMOND CONSTRUCTION.] NC Change Request To: Robert Fuentes - CCDF Number: 52 Collier County Date: 4/8/15 3335 Tamiami Trail East Job: 13 -021 Collier County J -1 HVAC System Naples, FL 34112 Ph: 239 - 252 -8380 Description: Access panels We are pleased to offer this proposal to make the following changes: To provide 62 security acccess panels as required by Facilities Management. 09 -130 Acoustical Ceilings 2,480.00 Subtotal 2,480.00 Fee 124.00 The total amount to provide this work is $2,604.00 Please note that DeAngelis Diamond Construction will require an extra 0 days. If this is acceptable, sign and return via fax (239- 594 -1995) or email. Please provide approval at your earliest convenience. Only the work specifically outlined in this proposal is included. If you have any questions, or comments, feel free to contact me at 239 - 594 -1994. Submitted by: Nic Kieft Approved by: DeAngelis Diamond Construction Date: Cc: Scott Craig PE (1-12 Engineering, Inc.) 6635 WILLOW PARK DRIVE, NAPLES, FL 34109 1 7309 MERCHANT COURT, SUITE B, SARASOTA, FL 34240 NAPLES: 239.594.1994 1 SARASOTA: 941.388.6997 DEANGELISDIAMOND.COM Packet Page -2076- 7/7/2015 16.E.9. L("'� DFANGEt_IS MAMC)ND C O N S T R U C 1 1 0 N I N C Change Request To: Robert Fuentes - CCDF Number: 53 Collier County Date: 4/8115 3335 Tamiami Trail East Job: 13 -021 Collier County J -1 HVAC System Naples, FL 34112 Ph: 239 - 252 -8380 Description: HVAC grills and dampers We are pleased to offer this proposal to make the following changes: To core drill and install grills, with fire smoke dampers to the communications room and TV room, per requirement of the Engineer. To furnish and install 34 added fire dampers, required to meet fire code, to contracted smoke dampers located in corridor walls. 15 -500 HVAC (Grills) 3,888.00 15 -500 HVAC (Smoke dampers) 6,165.00 Subtotal 10,053.00 Fee 502.65 The total amount to provide this work is $10,555.65 If this is acceptable, sign and return via fax (239 - 594 -1995) or email. Please provide approval at your earliest convenience. Only the work specifically outlined in this proposal is included. If you have any questions, or comments, feel free to contact me at 239 - 594 -1994. Submitted by: Nic Kieft .Approved by: DeAngelis Diamond Construction Date: Cc: Scott Craig PE (H2 Engineering, Inc.) 6635 WILLOW PARK DRIVE, NAPLES, FL 34109 1 7309 MERCHANT COURT SUITE B, SARASOTA, FL 34240 NAPLES: 239.594.1994 1 SARASOTA: 941.388.6997 DFANGELISDIAMOND.COM Packet Page -2077- 7/7/2015 16.E.9. DEANGELIS DIAN-IoNU C0NS"T RUCT10N.INC. Change Request To: Robert Fuentes - CCDF Number: 54 Collier County Date: 4/8/15 3335 Tamiami Trail East Jab: 13 -021 Collier County J -1 HVAC System Naples, FL 34112 Ph: 239 - 252 -8380 Description: Plumbing We are pleased to offer this proposal to make the following changes: To the removal and replacement of various 4" waste pipes to facilitate the installtion of duct work in chases. 15 -400 Plumbing 1,407.38 Subtotal 1,407.38 Fee 70.37 The total amount to provide this work is $1,477.75 Please note that DeAngelis Diamond Construction will require an extra 0 days. If this is acceptable, sign and return via fax (239- 594 -1995) or email. Please provide approval at your earliest convenience. Only the work specifically outlined in this proposal is included. If you have any questions, or comments, feel free to contact me at 239 - 594 -1994. Submitted by: Nic Kieft Approved by: DeAngelis Diamond Construction Date: Cc: Scott Craig PE (H2 Engineering, Inc.) 6635 WILLOW PARK DRIVE, NAPLES, FL 34109 1 7309 MERCHANT COURT. SUITE 6, SARASOTA, FL 34240 NAPLES: 239,594,1994 I SARASOTA: 941.388.6997 DEANGELISDIAMOND.COM Packet Page -2078- 7/7/2015 16.E.9. I �� DFAI',Gf:LIS DIAN40ND C 0 N S T It U C T 1 0 N. I NC Change Request To: Robert Fuentes - CCDF Number: 55 Collier County Date: 4/27/15 3335 Tamiami Trail East Job: 13 -021 Collier County J -1 HVAC System Naples, FL 34112 Ph: 239-252-8380 Description: Safety railings We are pleased to offer this proposal to make the following changes: To provide 63 linear feet of mill finish aluminum railings located on parapet adjacent to RTU 6 -7. 05 -720 Railings: Exterior 6,250.00 Subtotal 6,250.00 Fee 312.50 The total amount to provide this work is $6,562.50 Please note that DeAngelis Diamond Construction will require an extra 0 days. If this is acceptable, sign and return via fax (239- 594 -1995) or email. Please provide approval at your earliest convenience. Only the work specifically outlined in this proposal is included. If you have any questions, or comments, feel free to contact me at 239 -594 -1994. Submitted by: Nic Kieft Approved by: DeAngelis Diamond Construction Date: Cc: Scott Craig PE (1-12 Engineering, Inc.) 6635 WILLOW PARK DRIVE, NAPLES, FL 34109 1 7309 MERCHANT COURT, SUITE B, SARASOTA, FL 34240 NAPLES: 239.594.1994 1 SARASOTA: 941.388.6991 DEANGELISDIAMOND.COM Packet Page -2079- 7/7/2015 16.E.9. LC i)LAI~IGEi_is DiAnitc-. .)ND C0N'5TRUCI 10N.I NC Change Request To: Robert Fuentes - CCDF Number: 56 Collier County Date: 4127/15 3335 Tamiami Trail East Job: 13 -021 Collier County J -1 HVAC System Naples, FL 34112 Ph: 239-252-8380 Description: Paint We are pleased to offer this proposal to make the following changes: To furnish only Sherwin Williams paint, Snowbound and Collier Biege paint, for Pods 3-4 & Corridor. 09 -400 Sherwin Williams 3,289.56 Subtotal 3,289.56 Fee 164.48 The total amount to provide this work is $3,454.04 Please note that DeAngelis Diamond Construction will require an extra 0 days. If this is acceptable, sign and return via fax (239- 594 -1995) or email. Please provide approval at your earliest convenience. Only the work specifically outlined in this proposal is included. If you have any questions, or comments, feel free to contact me at 239 - 594 -1994. Submitted by: Nic Kieft Approved by: DeAngelis Diamond Construction Date: Cc: Scott Craig PE (1-12 Engineering, Inc.) 6635 WILLOW PARR DRIVE, NAPLES, FL 34109 1 7309 MERCHANT COURT, SUITE 6, SARASOTA, FL 34240 NAPLES: 239.594.1994 1 SARASOTA: 941.388.6997 DEANGELISDIAMOND.COM Packet Page -2080- To: Robert Fuentes - CCDF Collier County 3335 Tamiami Trail East Naples, FL 34112 Ph: 239 -252 -8380 Description: Plumbing repairs 7/7/2015 16.E.9. µ DEANGELIS DiAIvIL0 ID c r� s -rr.uc -r 1 0 N. � Change Request Number: 57 Date: 4127115 .fob: 13 -021 Collier County J -1 HVAC System We are pleased to offer this proposal to make the following changes: To carry out various repairs and replacement to plumbing in chases, pods 3 & 4. Work included refitting 4 wall hung wash basins. 15 -400 Plumbina 1,929.69 S u btotal 1,929.69 The total amount to provide this work is Fee 96.48 $2,026.17 If this is acceptable, sign and return via fax (239- 594 -1995) or email. Please provide approval at your earliest convenience. Only the work specifically outlined in this proposal is included. If you have any questions, or comments, feel free to contact me at 239 - 594 -1994. Submitted by: Nic Kieft DeAngelis Diamond Construction Cc: Scott Craig PE (H2 Engineering, Inc.) Approved by: Date: 6635 lh`f LLO�Y PARK DRIVE, NAPLES. rL 34109 ! 7301) MERC -RANT COURT. SUITE 6, SARASOTA. FL 34240 l`JA[' LES: 239.594;.] ;'W 1 SAPASOTYc'M1.388.6997 DE, AINGEL iSDfA;iMON1D.CO"t Packet Page -2081- 7/7/2015 16.E.9. .. TV"::r � r n 4.f c A f � G E 'L ! �, LJ ! \ 71't l_i 1V C} CONSTRUCT I ON.I N G Change Request To: Robert Fuentes - CCDF Number: 58 Collier County Date: 4/27/15 3335 Tamiami Trail East Job: 13 -021 Collier County J -1 HVAC System Naples, FL 34112 Ph: 239 -252 -8380 Description: Interior flood light We are pleased to offer this proposal to make the following changes: To supply only 400 W wall pack, to replace exisiting, found broken, Pod 3A 13 -999 Miscellaneous 323.77 Subtotal 323.77 Fee 16.19 The total amount to provide this work is $339.96 Please note that DeAngelis Diamond Construction will require an extra 0 days. If this is acceptable, sign and return via fax (239- 594 -1995) or email. Please provide approval at your earliest convenience. Only the work specifically outlined in this proposal is included. If you have any questions, or comments, feel free to contact me at 239 - 594 -1994. Submitted by: Nic Kieft Approved by: DeAngelis Diamond Construction Date: Cc: Scott Craig PE (1-12 Engineering, Inc.) 6635 WILLOW PARK DRIVE, NAPLES, FL 34109 1 7309 MERCHANT COURT, SUITE G, SARASOTA, FL 34240 NAPLES: 239.594.1994 1 SARASOTA: 941.388.6997 DEANGELISDIAMOND.COM Packet Page -2082- v- �drr NSbd a vB Serdces Divisrn Proax[rtv11f services 7/7/2015 16.E.9. Procurement Services Change Order Form FJ Contract Modification EJ Work Girder Modification ❑ Amendment Contract #: 14-8251 Change #: 01 Purchase Order #: 4500156702 Project #: - - Contractor /Firm Name: Marquee Development, inc. I Project Name: Colorado Avenue Improvements Project Manager Name: Bradley Muckei Department: Immokaiee CRA ......_...__ Original Contract/Work Order Amount $ 368,176.50 12/.9/14 ::163.1 Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 368,176.50 12/9/14,, 16.B:1 Last BCC Approval Date; Agenda Item # Current Contract/Work•Order Amount $ 368,176;50 +$1,500.00 SAP Contract Expiration Date (Master) Dollar Amount of this Change $ 18,743.39 5.09% Total Change from Original Amount Revised Contract/Work Order Total $ 386 919.89 5.09% Change from Current BCC Approved Amount Cumulative Changes $ 1.8,743 191 5.09% Change from Current Amount Completion Date, Description of the Task(s) Change, and Rationale for the Change Notice to Proceed 1131/15 Original 6130115 Last Approved 6/30/15 Revised Date 7/30/15 Date Completion Date Date (Includes this change; # of Days Added 30 Select Tasks .0 Add new tasks) ® Delete task (s) () ❑Change task(s) 71 Other (see below) Provide a response to the following: 1.) detailed and specific explanation /rationale of the requested change(s) to the task(s) and / or the additional days added (if requested); 2.) why this change was not included in the original contact; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and /or Contractor if needed. Field Chancre #1: Grading Changes (Owner Request) in order to avoid stormwater accumulation along right -of -way areas, staff is requesting that the contractor perform embankment and excavation work in all right -of -way areas, creating drainage swales. This will require the filling in of low areas with off -site fill and cutting down high areas in order to maintain positive water flow to new drainage structures. The unit prices below were taken from recent County contract 14 -6237 for similar work. A 30 -day extension has been requested by the contractor to perform this work. Thi s work wa i oc included inothe,griginal schedule of values because the drainage issues were not known E"rn menrt Cut'ic ar s @ $29.41/CY = $9,'32.95 Excavation (cut) high areas: 368.20 Cubic Yards @ $34.09 /CY = $12.551.94 Field Change #2: Driveway Apron Changes (Contractor Request) Rebuild two commercial driveway aprons at station 96 +00 with concrete instead of depicted asphalt. Revised quantities are as follows: • The removal of the asphalt driveways result in a deduction of: item 12 Optional Base Group 6 (8" Limerock) -255 SY @ $20.50 = - $5,227.50 Item 13 Superpave A.C. (2 ") -31.0 TN @ $450 = - $13,950.00 • Replacing it with concrete results in an addition of: Item 15 Class I Concrete Driveways (6" Thick) +255 SY @ $38.00 = $9,690.00 Field Chancre 43: Side Penetrations into Existing Boxes (Contractor Request) 2 ea. @ $750.00 = $1500.00 Chanoe Add I Deduct Net Change I Embankment +$9,732.95 Excavation +$12,551,94 Side Penetration into Existing Structure +$1,500.00 Add concrete commercial driveways (255 5 +$9,690.00 5% Proiect Concrete Quantity Contingency (1 17 SY) +4,446.00 j Deduct Commercial As halt Driveways - $19,177.50 Totals: +$37;920.89 - $19177.50 +,18.74:3.39 Impact if this change is not processed Fiscal: The ad altematerwork would not be completed. Time: The contractor would not be able to complete the base scope of work. (Divisions who may require additional signatures may include on separate sheet,) Revised: 10PH120! a Packet Page -2083- 7/7/2015 16.E.9. ' rC l Prepared by: Bradley Muckel — Immokalee CRA '-CT J.. -�'( Date: June 12. 2015 (Project Manager Name and Deparfinent) i Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same terms and conditions as contained in the contract/ work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contra II constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant / Design Professional arising o or r ted to the a set forth herein, including claims for impact and delay costs; Accepted by: -- Date: (Cunt r / Vendor / Consultant / Design Professional and Name of Firm, if project applicable) Approved by: --f4'p F— AP Ai+o.L! r Date: (c ^/. - /.S Approved by: (Design Professional and am�ffl , i f project applicable) Date: 6 Professional (Divisions who may require additional signatures may include on separate sheet.) Packet Page -2084- Revised: 10/28/2014 fier county Pnx- erreru se ws 7/7/2015 16.E.9.,,. PROCESSED BY° Procurement Services iJSB TajribC Change Order Form ❑ Contract Modification ® Work Order Modification ❑ Amendment Contract #: 13 6164 Change #: IE71 Purchase Order #: 45- 150429 Project #: 60123 Q Grad Minor 128`" Ave SE Crossing Replacement Contractor /Firm Name: y Project Name Shane Cox Capital Project Planning, Impact Fees & Program Project Manager Name: Department Management Division Original Contract/Work Order Amount$r g'gce0i�'r� Original BCC Approval Date; Agenda Item # Current BCC Approved Amount 3 k 4 0 A Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount "$., a� 3/18/2019' SAP Contract Expiration Date (Master) Dollar Amount of this Change '$�;;;) 22.88% Total Change from Original Amount Revised ContractfWork Order Total $ 21,891.00 #WA 'Change from Current BCC Approved Amount Cumulative Changes $ 4,076.00 22.880% Change from Current Amount Completion Date, Description of the Task,(s) Change, and Rationale for the Change Notice to Proceed 21APR'14 Original 17JAN'15 Last Approved 08SEP'15 Revised Date 085EP'15 ►/ Date Completion rate QatP_ llnrinrloe 4hic 'h.-I # of Days Added 0 7/Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other (see below) Provide a response to the following: 1.) detailed and specific explanation /rationale of the requested change(s) to the task(s) and / or the additional days added (if requested); 2.) why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed. 1) We wish to add a $4,076 increase to the work order, for the 'on -call assistance during construction' budget. This figure ($4,076) is not 22.88 % of the total design fees. It is only 22.88% of this individual work order. This work order is the second of two work orders with Q Grady Minor Inc for this project design. A second W.O. was created when old Engineering Services Contract 09 -5262 expired and was replaced with the current contract, 13 -6164. Of the total design costs to this firm for this project, the requested change represents approximately 4.8 %. 2) The oncall services during construction were estimated when the designer prepared the work order scope early on in the design process. Some of the issues raised, and questions asked, .by the contractor were more involved and lengthier than anticipated compared to the designer's previous experience with this type of project. 3) If this change is not processed, the necessary 'Engineer of Record' assistance during construction could not be accomplished to the end of the construction period. This work is Time & Materials, so only the portion of the budget that is needed will be used. Prepared by: 5ttane Cox PE, Sr Project. Manager Capital Project Planning, Impact Fees & Program Management Division i Date: 1 Acceptance of this Change Order shall constitute a modification to contract / work order identified above and will be subject to all the same terms and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant ! Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs. (Divisions who may require additional signatures may include an separate sheet.) Revised: 10128/2014 Packet Page -2085- Accepted by: 7/7/2015 16.E.9.- N (Mark Minor, President, Q Grady Minor Associates) Date: K 1 c APPROVED BY: r , rJ_ j Gerald N Kurtz PE, Principal roject Manager Date Capital Project Planning, Impact Fees & Program Management Division APPROVED BY: Amy Patterson, ision Director Capital Project Planning, Impact Fees & Program Management Division APPROVED B '` sal guida Dep ty County Man er APPROVED BY: Evelyn Colon, Procurement Strategist Purchasing Division ,S tY lr Date Date Date (Divisions who may require additional signatures may include on separate sheet.) Revised. 1028/2014 Packet Page -2086- 7/7/7ni F 1 F F A— IN Vic# 7�r C ;0un ty Public Utilities Division May 14, 2015 Planning & Project Management Mr. Ron Cavalieri, P.E. AECOM Technical Services, Inc. 4415 Metro Parkway, Suite 404 Fort Myers, FL 33916 RE: Zero Dollar Contract Change Notification # 1 Contract No. 13- 6164 -SC Purchase Order No. 4500152062 Collier County Project No. 71055.34 Barefoot Beach WQ Monitoring Panel Replacement Dear Mr. Cavalieri: By copy of this letter, the above referenced contract is being issued a zero dollar ($0.00) change as indicated below: MThe above referenced contract time is hereby extended by 60 calendar days. The previous total number of project completion days was 300 days. The previous final completion date was June 7, 2015. The new final completion date shall be on or before August 6, 2015. Note: Time extensions cannot exceed 20% By extending this contract, the County is not relieving your firm of its obligations to perform work in a timely and satisfactory manner or any consequences resulting from failing to do so, Collier County hereby reserves all legal rights, including, but not limited to, rights to terminate, suspend or elect any other appropriate course(s) of action should circumstances warrant with regard to the referenced contract. ®Other. Re- allocation of dollar amounts between existing tasks. Reallocate $13,900 from Task IV — Construction Phase Basic Services to Task(�Design Phase Services (see table below). Sincerely, Alicia Abbott Project Manager Swain Nall, Pro�6rem trategist, Purchasing Department /,/;' Approval- rim Date: C: Robin Sheiey, Clerk's Finance Division Oscar Martinez, P.E., Interim Principal Projeq_Manager Pianrir�g & Prnje-et Mat - iaaemaruiepamient • 3339 Tamiarri Trail East; Suite 303 • Naples, Florida 34112 -5361. 239 - 252 -4255 • FAX 239. 252-5378 Packet Page -2087- Original WO Amount Task 1 $ 3,680 Task 11 25,970 Task III 2,960 Task IV 16,129 Total $48.739.00 Reallocation Revised WO Amount $ 0.00 $ 3,680.00 13,900 39,870.00 0.00 2,960.00 (13,900) 2,229.00 0.00 $48,739.00 Packet Page -2088- p 7/7/2015 16.E.9. 7/7/2015 16.E.9.- 3} a-r.t Cower oum Public Utilities Division May 14 2015 Planning & Project Management Mr. Craig Fuller, P.E. URS Corporation 4415 Metro Parkway, Suite 404212 East Main Street Bartow, FL 33830 RE: Zero Dollar Contract Change Notification # 1 Contract No. 13 -6164 Purchase Order No. 4500151853 Collier County Project No. 70103 Immokalee Rd. Chloramine Booster Station Dear Mr. Cavalieri: By copy of this letter, the above referenced contract is being issued a zero dollar ($0.00) change as indicated below: rzo ®The above referenced contract time is hereby extended by.-3 calendar days. The previous total number of project completion days was 365 days. The previous final completion date was June 7, 2015. The new final completion date shall be on or before October 5, 2015. Note: Time extensions cannot exceed 20% By extending this contract, the County is not relieving your firm of its obligations to perform work in a timely and satisfactory manner or any consequences resulting from failing to do so. Collier County hereby reserves all legal rights, including, but not limited to, rights to,:crminate, suspend or elect any other appropriate course(s) of action should circumstances warrant with regard to the referenced contract. ®Other: Re- allocation of dollar amounts between existing tasks. Reallocate $3,500 from Task II - (Bidding /Construction Services), and $2,500 from Task III (Public Involvement), to add a total of $6,000 to Task I (Design Phase Services). Sincerely, Alicia Abbott Project Manager Swain Hall, Prop rement s ategist, Purchasing Department Approval: �i /il G i % Date: � �l C: Robin Sheley, Clerk's Finance Division Oscar Martinez, P.E., Interim Principal Project Manager Planing Precut I siren €O a vrent 3319 T.aMiaMi Trail East, Suits 303 Nap3es, F1ori�a 2411,2-5361-239-252-4285 • FAX 239 - 2552-5378 Packet Page -2089- 7/7/2015 16.E.9.- 0 May 8, 2015 Mrs. Alicia Abbott Project Manager Public Utilities Planning & Project Management Department 3339 East Tamiami Trail, Suite 303 Naples, Florida 34112 Re: Immokalee Road Chloramine Booster Station Contract 13- 6164 -PU Work Order /Purchase Order No. 4500151853 Reallocation of Funds Dear Mrs. Abbott: The above named project has permitting associated with it. Additional permitting services were required, requiring additional design services to accompany the permits. We foresee the additional services required totaling approximately $6,000. Below is a request to reallocate funding from differing tasks to the permitting task. The following is a tabulated reallocation with the same values shown in the Project 4500151853's Monthly Status Report. Task Description Original Contract Amount Task Reallocations Adjusted Task Amounts Dollar Amount Remaining 00010 Permitting $ 6,393.00 $ 6,000.00 $ 12.393.00 $ 6,661.13 00020 Bidding/Construction Services $ 28,484.00 $ 3,500.00 $ 24,984.00 $ 19,452.00 00030 Public Involwment $ 5,704.00 $ (2,500.00 $ 3,204.00 $ 3,204.00 00040 Reimbursables $ 750.00 $ - $ 750.00 $ 44.52 Totals: $ 41,331.00 $ - $ 41,331.00 $ 29.361.65 The function of this letter is to request the reallocation of $6,000.00 from Task 2 ($3,500) and Task 3 ($2,500) to Task 1 of the project. ENGINEER: f� -�` �/ ' Date:- 5/8/15 Craig Fuller, P.E. Project Manager URS Corporation 212 East Main Street Bartow, FL 33830 Tel: 863.519.9504 Fax: 863.519.9403 Packet Page -2090- 7/7/2015 16.E.9. T Procurement Services Change Order Form 0 Contract Modification ® Work Order Modification Amendment Contract #: 13$164 -ST Change M 001 Purchase Order #: 4500152540 i Project #: j N/A j Contractor/Firm Name; TY ln Intem— atonai � omr�wurnwrfOa� uo. nngw.ao..w..wa.. aoFw� Project Name: Project Manager Name Anthony D Stotts. P, E, Department: j Growth Management Department Original ContracMork Order Amount $ 97,770.00 N/A Original BCC Approval Date; Agenda Item # Current BCC Approved Amount N/A N/A Last BCC Approval Date; Agenda Item # Current ContracVWork Order Amount $ 97,770.00 SAP Contract Expiration Date (Master) Dollar Amount of this Change S 0.00 0.00% Total Change from Original Amount Revised ContracUWork Order Total S 97,770.00 #VALUE! Change from Current BCC Approved Amount Cumulative Changes $ 0.00 0.00% Change from Current Amount A Compielbn Date, Description of the Tesk(s) Change, and Rationale for the Change Notice to Proceed 09!10!2014 Original 07/0712015 Last Approve R evised Date 2/31/2015 Data Completion Data Date (includes this change. 9 of Days Added 177 Select Tasks ❑ Add new task(&) ❑ Delete task( &) ❑ Change task(s) ® Other (see wow) Provide a response to the following: 1.) detailed and specific explanation /rationale of the requested change(s) to the task(*) and / or the additional days added (if requested), 2.) why this change was not included in the original contract, and, 3.) describe the impact if this change Is not processed. Attach additional information from the Design Professional and/or Contractor if needed. 1.) Additional time is required to execute the bridge repairs. 2.) More time was required to coordinate efforts between divisions prior to commencing the repairs than was originally anticipated. 3.) The consultant's services are necessary during the repair and will not be available K this change is not prooessed. Prepared by r � � y `� Date. W47 __0_& - AnthonF:Stetts, P.E., Senior Project Manager, Transportation Engineenng Division Acceptance of this Change Order shall con4titult a modification to contract / work order identified above and will be subject to alt the same terms and conditions as. cro- riat,,,ed In the C�,tract / work order Indicated above, as fully as if the same were stated in this ac:aptance- The adjustment if arty; 16 the Conlra�( shall t:orlsHute a full and final settlement of any and all ciaims of the Contractor I Vendor I Consultant Design Pr4texir jonal arising out or re:att+d to the change set forth herein, including claims for impact and delay casts. Accepted by: Date: r?� cs molor P.E., Vl# Pr ideal, T Y. Lin Enter do aI i -- r^ Approved by: Date Approved by �' • �vrr'c� Date Travi `,ossard, Dir c(or, Ro d tgainten�pce ! an (k Ca aru�+ a, Deputy Couwy.Manaq -r Approved by —G _ -. —� I- _. - Date J �� Evelyn olon. Procur ant Specialist (Divisions who may require additiona' s,gnatures may include on separate sheet) Revised 1012132014 Packet Page -2091- -- 7/7/2015 16.E.9. C10 per unt GrDAtth Management Departrnent Transportation Engineering Division June 09, 201 a Dick Casalanguida. Deputy County Manager Growth Management Department 2885 South Horseshoe Drive Naples. Florida 34104 RE: Golden Gate Parkway (CR886) at Airport Pulling, Road Overpass Maintenance Repair BRIDGE NO. 034134 Contract No. 13- 6164 -ST Road Maintenance Bridge Repair Project Dear Mr. Casalanautda: The following Fork Order Modification (-,(-()0 1) extends the engineering consultants' work order time on the Golder date Parkway (CP,886) at Airport Pulling Road Overpass Maintenance Repair project by x''77 Days. More internal coordination time was required than w =as originally anticipated. Repair documents are now complete and %kill be released for contractor quotes soon. If'you have any questions. please contact me. SincerelN, AnTliony O lts, P.E. Sr. Project Manager Tra vorta6on ErgrieeriU Umsion • 2885 South Horseshoe dove - Naples, Ronda 34104.239- 252 -8182 - www.cuitergov.net Packet Page -2092- Aomfngar+e seMOes DiWdon woar�mres.Mooa 7/7/2015 16.E.9. ��FTrascure en ervfces rder Form ❑ Contract Modification ® Work Order Modification Amendment Contract #: 13 6164 Change #: = Purchase Order#: 45x0151661 Project #: 511Q1 Contractor/Firm Name: Johnson Engineering Project LASiP t Cope Ln, Crews Rd, Sandy Ln. Name: Shane Cox Capital Project Planning, Impact Fees & Program Project Manager Name: Department Management Division IOriginal Contract/Work Order Amount MIA; Original BCC Approval Date; Agenda Ibem #! Current BCC Approved Amount #WA NIA: Mast BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ ,506;00; 3/1812019; ;SAP Contract Expiration Data (Masser) Dollar Amount of this Change ':$..::;:'_;'::;':;:30:00 0.00% 'Total Change from Original Amount Revised Contract/Work Order Total $ 56,506.00 #WA "Change from Current BCC Approved Amount Cumulative Changes $ 0,001 0.00% ! Change from Current Amount Completion Date, Description of the Tasks) Change, and Rationale for the Change Notice to Proceed 15JUL'14 v Original "15JUL'15 Last Approved 15JUL'i5 Revised Date 15JAN'17 Date Completion Date Date (Indudes this change) # of Days Added 550 `` Select Tasks ❑ Add new task(s) ❑ Delete tesk(s) ❑ Change task(s) ® Other (see below) Provide a response to the foltowving: Z.) detailed and specific explanationlrationale of the requested change($) to the task {s) and / or the additional days added (if requested); 2) why this change was not included In the original contract; and. 3.) describe the Impact if this change is not processed. Attach additional information from the Design Professional and/or Contractor ff needed. 1) We wish to add 550 days to the work order. Consiruc Wn will not start until dry season of 2016 and the design consultant will be needed during construction to approve shop drawings and submittals, clarify plans, and other possible assistance duties. 2) The extended time Is an unforeseen situation of this work. This segment of LASIP had a significant number of real property parcels (easements) Involved with the project and the process has taken much longer than expected. Therefore we had to delay starting construction this year. Since Stormwater Management projects, with few exceptions, can only be done in dry season, construction will have to wait until early calendar year 2016. 3) If this change Is not processed, the design consultant would not be under contract to assist with construction activities like shop drawing approval and plan does clarification, it is essential they be avaliable during this time. Prepared by: Shane Cox PE, Sr Project Mana Capital Project Planning, Impact $ Program Management Division Date: Acceptance of this Change Order shall constitute a modification to contract 1 work order identified above and will be subject to all the same terms and conditions as contained in the contract / work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any, to the Contract shall constitute a full and final settlement of any and all claims of the Contractor / Vendor / Consultant! Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs, (Divisions who may require additional signatures may Inctude on separate sheet_) Revised: 1012er2M4 Packet Page -2094- 1 7/7/2015 16.E.9.:' 'Accepted by: Date: 6 a- IL If Kevin Winter, Board Chair Johnson Engineering, inc APPROVED BY: Gerald N Kurtz PE, Principal Project Manager Date Capital Project Planning, Impact Fees & Program Management Division 1-5 APPROVED BY: Amy Patterspii-, /Division Director Date Capital Project'Planning, Impact Fees & Program Management Division APPROVED BY: 'a Date Deputy County Manager.,; ---, APPROVED BY: -Evelyn Col&n,-P� urement Strategist Date Purchasing Division (Divisions who may require additional signatures may include on separate sheet.) Revised: 10128=14 Packet Page -2095-