Agenda 07/07/2015 Item #16A237/7/2015 16.A.23.
EXECUTIVE SUMMARY
Recommendation to approve Change Order No. 1 to Work Order/Purchase Order No. 4500157798
with Humiston & Moore Engineers for Collier County Beaches and Inlets Annual Monitoring for
2015 under Contract No. 13- 6164 -CZ, authorize the County Manager or his designee to execute the
Change Order for a time extension of 138 days, and makes a finding that this item promotes
tourism.
OBJECTIVE: To extend work order /purchase order No. 4500157798 an additional 138 days to
complete surveys for Wiggins, Doctors Pass and South Marco.
CONSIDERATIONS: The Coastal Zone Management (CZM) department is tasked with the
maintenance and monitoring of over thirty (30) miles of coastline, beaches, estuaries, channels,
and bays. CZM has specific goals, objectives, and criteria to meet as identified within the
Collier County Growth Management Plan, Land Development Code, and the Codes of Laws and
Ordinances regarding the county's coastal aquatic resources. In order to meet these goals and
objectives, CZM has been charged with a variety of programs including the implementation of
beach re- nourishment and dredging projects, the artificial reef program, derelict vessel program,
waterways marker program, as well as any related operations that are required to maintain the
health, aesthetics, and safety of the county's coastal waterways and communities.
Yearly physical monitoring of the beaches and inlets is required by FDEP permit. Results of this
report are used to evaluate, recommend and prioritize annual beach segment renourishment. The
BCC approved the work order for this project on March 10, 2015 for a not to exceed amount of
$163,795. At the time of the original contract surveys were not yet scheduled. The surveys have
now been scheduled for late August when the Gulf is calmest. Additional time will be needed in
order to complete the surveys and related reports.
FISCAL IMPACT: Funds have been budgeted and approved for this activity in FY 2014/15
fund 195 Tourist Development Tax. This change order is for time only, no additional funding is
required.
FDEP cost share funding may be requested at a future date to reimburse Collier County for a
portion of the completed work.
GROWTH MANAGEMENT IMPACT: There is no impact to the Growth Management Plan
related to this action.
ADVISORY COMMITTEE RECOMMENDATIONS: At the Tourist Development Council
and the Coastal Advisory Committee meetings on February 23, 2015 both committees
unanimously recommended this item for approval by a 6 to 0 vote.
LEGAL CONSIDERATIONS: This item has been approved as to form and legality and
requires majority vote for approval. - CMG
Packet Page -1067-
7/7/2015 16.A.23.
RECOMMENDATIQN: To approve Change Order No. l to Work Order/Purchase Order No.
4500157798 with Humiston & Moore Engineers for Collier County Beaches and Inlets Annual
Monitoring for 2015 under Contract No. 13- 6164 -CZ, authorize the County Manager or his
designee to execute the Change Order for a time extension of 138 days, and make a finding that
this item promotes tourism.
Prepared By: J. Gary McAlpin, P.E., Coastal Zone Management, Natural Resources Department
Attachments: 1) Change Order No. 1
Packet Page -1068-
7/7/2015 16.A.23.
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.16.A.16.A.23.
Item Summary: Recommendation to approve Change Order No. 1 to Work
Order /Purchase Order No. 4500157798 with Humiston & Moore Engineers for Collier County
Beaches and Inlets Annual Monitoring for 2015 under Contract No. 13- 6164 -CZ, authorize the
County Manager or his designee to execute the Change Order for a time extension of 138 days,
and makes a finding that this item promotes tourism.
Meeting Date: 7/7/2015
Prepared By
Name: HambrightGail
Title: Accountant, Growth Management Department
6/29/2015 10:07:38 AM
Submitted by
Title: Accountant, Growth Management Department
Name: HambrightGail
6/29/2015 10:07:40 AM
Approved By
Name: McAlpinGary
Title: Manager - Coastal Management Programs, Growth Management Department
Date: 6/29/2015 10:27:57 AM
Name: KearnsAllison
Title: Manager Financial & Operational Support, Growth Management Department
Date: 6/29/2015 10:44:07 AM
Name: Tara Castillo
Title: ManagementBudget Analyst, Growth Management Department
Date: 6/29/2015 10:44:21 AM
Name: PattersonAmy
Title: Manager - Impact Fees & EDC, Growth Management Department
Packet Page -1069-
7/7/2015 16.A.23.
Date: 6/29/2015 10:59:56 AM
?game: MarkiewiczJoanne
Title: Division Director - Purchasing & Gen Svc, Administrative Services Department
Date: 6/29/2015 11:06:43 AM
Name: PuigJudy
Title: Operations Analyst, Growth Management Department
Date: 6/29/2015 11:14:35 AM
Name: JohnsonScott
Title: Manager - Procurement, Administrative Services Department
Date: 6/29/2015 11:28:30 AM
Name: OberrathKaren
Title: Accountant, Senior, Grants Management Office
Date: 6/29/2015 12:16:33 PM
Name: CasalanguidaNick
Title: Deputy County Manager, County Managers Office
Date: 6/29/2015 12:34:14 PM
Name: GreeneColleen
Title: Assistant County Attorney, CAO General Services
Date: 6/29/2015 1:16:13 PM
Name: KlatzkowJeff
Title: County Attorney,
Date: 6/29/2015 1:25:20 PM
Name: StanleyTherese
Title: Manager - Grants Compliance, Grants Management Office
Date: 6/29/2015 2:20:46 PM
Name: FinnEd
Title: Management/Budget Analyst, Senior, Office of Management & Budget
Date: 6/29/2015 4:15:53 PM
Name: CasalanguidaNick
Title: Deputy County Manager, County Managers Office
Date: 6/29/2015 4:27:14 PM
Packet Page -1070-
isr cownw
,�ara++.w•g•�»
[I Comsat mwmc~ CM V#Wk Order ModNtcatlen
0 Amsrdmarrt
=7 Pre)Wt* 1�6 -o069d
46.1li77g9
Beach tAnno&.,W
Comsat ds 1 1341b�t -�:Z +Os 1 purchase OrOsrI
Conhsetormwh Name: Humisbn 5 Moore Engineers 7
Project Manager Nsnrrr• J Gary Mc•Upin
Current Bcc Approved Amount
Current ContVCMork Order Amount
Dour Amount of this Change
Revised ContrwMot* order TOW
7/7/2015 16.A.23.
proourwaem servlcas
Change Order Form
projrct Nwaa: �,�re'ISplas
Coastal Zwo Management
Dep+ertmsrt'
3M0/15 18A16 Original BCC Approval Doha; Apathds item
3110/'t s 11 SA10 Last B= Approvvd DS%; A9W d' lw" *
31=019 SAP Contra ExpWon Der (040001
0.S TOW Charge bom Ori * Amount
0. Chwp from Current BCC Approved Amount
n charms from Cument Amount
r.�.drhm Dana. Dseofipdon of the Tsskts) CfMege. ee±d r4Mlorrals far Mar Change
Wodce to Provee�
Dow
F138
Original 104WIG Last Apprevad 19/1UZD15 Rwleed Dale
Completion Date Dab (MdWft NO onwp)
1TJ901Zg18
R of Days Ikfded Select Twks 0 Add new bslgs) 0 Delete taskis) 0 Charge VOW) C1 OMW (ass We"
d the requested tdrahgsts)10 00 faNds) and f or
Provide a real to the tblloering: 1.) detailed and epealNc 100111raat; era, i.) dsaor =�e � *
the addltlarwt days added (H regrrssbdk Z.) who► this change woe not included M fire h CorMrsrxor rrssdad
this change le not Wooessed. Attach addalonai Wwff Uon nom the Design Prvl WWW
1.) detailed and specific W#AnstieNmdcnale of the requesbd charrge(s) le the fb tsslh u � 00 � Is the o�tlas+I
requested); Surryrs for V"gpina. Doctors Pass and South Marco setwhiuled for August
2.) why this change was not included In the OAGW d contract. Surveys were not yet scheduled at the 1Mree of the OrIplrMt
cmntrect
3.) dascdbq the Impact if this change Is not processed No innpact ttMN Mh o w® redlroe
mobWlsatIM most and prvvda savings m tna County. ` j
!Tj
Prepared by:
o.le: � L ;/j 5 -
�--' '�- -r-- -. • - - - -- r - b as flee acme
Aomponce of this Change Order shall owu t11vee a naclhxt0n b ronWO /worm order WentMied were staled in aooapftnw. The
ismw and can wkm as contained in the corWat2 I work order in*cMd above, as fuYy
ad)uebnent, 9 any, to to Contract shah constitute a fug and ** Nownerd of ant► and an clews of the Card's "WC i Vendor ! Conudterd !
Design Prafassi=d arising out of or related b the chaps set forth herein, ia$ng dsims for krnpeot and decay oosb
Dear. d Y2 -15
AccePbd try: — Tc -
M A. Dabeas, PhD., P.E..
/ Nick Casalanguida tee: 6- ?6 -1.5
Approved by Dste� /�APprowd by: ►Hdc Caealengu DIPsr Head i Dsis+<f} `
Amy P ran, Dhdsian Director Cozy
Data: -
Approved nail: Adam t ProisasIons!
tJorMnruP. Procurer'ren
(Diriaw s whc may ie Wit DOW" 944 aUx" MW frdtda an separe o onset.) ROrh: f OfYW4
I
Packet Page -1071-
7/7/2015 16.A.23.
HUMISTQN
-r liROiJRE
ENGINEERS
COASTAL
ENGINEERING DESIGN
AND tERMiTTING
June 18, 2415
Gary McAlpin
Collier County Coastal Zone Management
2800 Horseshoe Drive
Naples, FL 34104
REF: Contract 13- 6164 -CZ
Change Order request No. 1
Purchase Order 45- 157798
Dear Gary:
This is written request for a 138 day additional time to be added to The County /Naples
Beach Monitoring project purchase order 45- 157798.
Combining the surveys to be completed at one time, in August, will reduce costs and
provide savings to the County. The reports are due 90 days after the survey date;
extending the contract until the end of the year will provide sufficient time to complete
the required reports.
Sincerely yours,
HUMISTON & MOORE ENGINEERS
Brett D. Moore, P.E.
President
Packet Page -1072-
6619 STRAND COURT
NAPLES.FLONIOA 31110
FAX 2.19 sk 9045
Dear Gary:
This is written request for a 138 day additional time to be added to The County /Naples
Beach Monitoring project purchase order 45- 157798.
Combining the surveys to be completed at one time, in August, will reduce costs and
provide savings to the County. The reports are due 90 days after the survey date;
extending the contract until the end of the year will provide sufficient time to complete
the required reports.