Agenda 07/07/2015 Item #11C_/*-�N
7/7/2015 11.C.
EXECUTIVE SUMMARY
Recommendation to award bid number 15 -4561, "Master Pump Station 306 Force Main Phase II,»
to Bonness, Inc., for $1,107,858.57 under Force Main Technical Support Project Number 70044.
OBJECTIVE: To meet the demand, stay in compliance and serve customers efficiently by providing an
alternative path for wastewater to flow from Master Pump Station (MPS) 302 to the South County Water
Reclamation Facility (SCWRF).
CONSIDERATIONS: The proposed scope of work under Project Number 70044, "Force Main
Technical Support," is consistent with the Capital Improvement Program (CIP) contained in the Water,
Wastewater, Irrigation Quality Water, and Bulk Potable Water User Rate Study approved by the Board of
County Commissioners (Board) on June 10, 2014, as Agenda Item I IC. Funding for Project Number
70044 is available in, and is consistent with, the FY2015 CIP Budget.
Wastewater MPS 306 is located near U.S. 41 and Thomasson Drive. Currently, MPS 306 discharges
through a force main to MPS 302 located at the intersection of Rattlesnake Hammock Road and Santa
Barbara Road. MPS 302 discharges through a 36 -inch force main to the SCWRF. Approximately 80
percent of the south wastewater transmission system is conveyed through MPS 302 to the SCWRF.
Currently, there is no alternative path for these flows to reach the SCWRF; therefore, the 36 -inch force
main cannot be shut down for preventative maintenance. Further, if the 36 -inch force main were to fail,
approximately 80 percent of the south transmission system would be out of service with a high potential
for sanitary sewer overflows. To address these vulnerabilities a new force main is being constructed from
MPS 306 to the SCWRF. This will provide an alternative path that will allow flow from MPS 302 to be
routed through MPS 306 and then to the SCWRF. Attachment 5 shows the location of the existing and
proposed facilities. This project was designed under the Wastewater Basin Program.
Rapid development in this area necessitated that the force main be constructed in phases as easements
were acquired. This scope of work is Phase two of the seven phases required to construct the
approximate 3.4 mile force main from MPS 306 to the SCWRF. Progress is shown in the table below:
Phase
Approximate Length
Planned Completion
I
0.5 miles
Complete
H
1.1 miles
End of FY2016
III
0.8 miles
End of FY2016
IV
0.2 miles
Complete
V
0.4 miles
Complete
VI
0.1 miles
Complete
VII
0.2 miles
Complete
Bid number 15 -4561 was advertised on April 24, 2015, with 66 prospective bidders downloading bid
packages. On May 27, 2015, the ten sealed bids received were opened. The bids are summarized below.
VENDOR
PROJECT COST
Bonness
$1,107,858.57
Quality Enterprises
$ 1,109,060.80
Mitchell & Stark
$1,111,915.00
Southwest Utility Systems
$ 1,137,600.00
Packet Page -601-
91- Melmiitel
T B Landmark Construction
$1,173,755.00
Douglas N. Higgins
$1,178,000.00
Guymann
$1,229,171.00
Andrew Sitework
$ 1,382,634.50
Coastal Concrete
$1,464,459.50
Metro Equipment Service
$1,496,200.00
Staff and the local project design engineer, AECOM Technical Services, Inc., determined that the
lowest bid is fair and reasonable and recommends awarding the contract to Bonness, Inc. The bid is
approximately 11 percent below the design engineer's $1,250,000 opinion of cost. The bid tabulation,
analysis chart, engineer's letter of recommendation, and contract are Attachments 1, 2, 3 and 4,
respectively.
The bid specifications informed the bidders that there may be unforeseen conditions associated with the
project. The bid amount incorporates an allowance of $50,000 for owner - directed additional work. The
price for any additional work will be negotiated prior to commencement in accordance with the county's
Purchasing Ordinance and the terms of the agreement.
FISCAL IMPACT: Funding is available in, and is consistent with, the FY2015 Capital Budget approved
by the Board on September 18, 2014. The source of funding is the Wastewater User Fee Fund (414). The
project is expected to be completed by July 2016. There will be an increase in annual maintenance costs
for the additional force main that is included in the operational budget.
LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote
for Board approval. —SRT
GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan
standards to ensure the adequacy and availability of viable public facilities.
RECOMMENDATION: That the Board of County Commissioners, Ex- officio the Governing Board of
the Collier County Water -Sewer District, award bid number 15 -4561 to Bonness, Inc., in the amount of
$1,107,858.57 for the "Master Pump Station 306 Force Main Phase H "; and, authorize the Chairman to
sign and execute the attached agreement after final review and approval by the County Attorney's Office.
Prepared By: Wayne M. Karlovich, Senior Project Manager, Public Utilities PPMD
Attachments:
Attachment 1- Bid Tabulation
Attachment 2- PPMD Bid Analysis
Attachment 3- Recommendation Letter
Attachment 4- Contract (Due to the size of the contract, a web link is provided for viewing:
httn: / /www.collierL,ov. net/ ftn/ A2endaJulvO7l5 /PubUtilitiesBonnessContract.t)df
A hard copy is also available at the County Manager's Office.)
Attachment 5- Project Location Exhibit
Packet Page -602-
A
7/7/2015 11.C.
COLLIER COUNTY
Board of County Commissioners
Item Number: 11.11.C.
Item Summary: Recommendation to award bid number 15 -4561, "Master Pump Station
306 Force Main Phase 2," to Bonness, Inc., for $1,107,858.57 under Force Main Technical
Support Project Number 70044.
Meeting Date: 7/7/2015
Prepared By
Name: KarlovichWayne
Title: Project Manager, Senior, Public Utilities Department
6/15/2015 9:38:59 AM
Submitted by
n Title: Project Manager, Senior, Public Utilities Department
Name: KarlovichWayne
6/15/2015 9:39:00 AM
n
Approved By
Name: NagySteve
Title: Manager - Wastewater Collection, Public Utilities Department
Date: 6/15/2015 10:53:29 AM
Name: JohnssenBeth
Title: Division Director - Wastewater, Public Utilities Department
Date: 6/15/2015 12:44:06 PM
Name: HapkeMargie
Title: Recycling Coordinator, Public Utilities Department
Date: 6/16/2015 8:29:01 AM
Name: ChmelikTom
Title: Division Director - Public Utilities Eng, Public Utilities Department
Date: 6/16/2015 11:47:22 AM
Packet Page -603-
7/7/2015 11.C.
Name: Joseph Bellone
Title: Division Director - Operations Support, Public Utilities Department
Date: 6/16/201511:50:41 AM
Name: PajerCraig
Title: Project Manager, Principal, Public Utilities Department
Date: 6/16/2015 4:15:59 PM
Name: JacobsSusan
Title: Operations Analyst, Public Utilities Department
Date: 6/16/2015 8:29:31 PM
Name: MarkiewiczJoanne
Title: Division Director - Purchasing & Gen Svc, Administrative Services Department
Date: 6/17/2015 8:04:46 PM
Name: HallSwainson
Title: Procurement Specialist, Administrative Services Department
Date: 6/19/2015 9:27:02 AM
Name: YilmazGeorge
Title: Department Head - Public Utilities, Public Utilities Department
Date: 6/19/2015 10:06:56 AM
Name: TeachScott
Title: Deputy County Attorney, County Attorney
Date: 6/22/2015 2:01:06 PM
Name: KlatzkowJeff
Title: County Attorney,
Date: 6/24/2015 2:47:09 PM
Name: UsherSusan
Title: Management/Budget Analyst, Senior, Office of Management & Budget
Date: 6/26/2015 2:53:28 PM
Name: CasalanguidaNick
Title: Deputy County Manager, County Managers Office
Date: 6/26/2015 3:17:55 PM
Packet Page -604-
Project Manager \1 tions Sent: 1996
Wayne Karlovich, �rojecl Manager, PPMD / Downloaded: 67
Submittals: 10
MPS 706 Force Main
PHASE II
COLLIER COUNTY PROJECT
Bid Tabulation
Wednesday, May 27, 2015
..1 „: �i. „ . . , i :�. . >..:.:.,::: „,: : .
... .. R. � ». G <:
fi.a�S� . r. ' , . .,.m:3� e`.t_ . .
t S ir Pr
, 5 ., ,&_� q,. ? ,h .b .r
.=n,.t,`: rL , .P ,=,...r . Ly .
'�. ? � . .x, ,ig K sr.L 3 4 f
�J I{
tS k., ., .,✓.v-
KEk 5
. s ,y. :
.-.:..
. :�,
I .a x ,.a .
.. e °'..
E .} . ,
,.7i. . . s :- , ._., .{a:.�a, , ;. 3
: -.
„. x., i.,..x:_.
il I
.,,
,
a^�i t.,.i . � § # _U �,u1.55G
,_ '�E ,n.1 4. �, d e.P ,x .r*r v, .p, � �r�
t,V
.S.l,,�t._ a _. . n4 .l x
,.. � , -. . .ft. e IIV .��
. G . . ` . . 1 t"tr l�><fo�
., t
..,.
b
'a
._.. .. �r�n
. 4,�. L S• t�w d �'Sn ' . i:,I3,: -. u ; . al.�iaN�tr
t: .
"i � .
.[d .'
._:..
t .}z¢ . a.; �
,
: q , ; ,f
t x -
R
�,g
� �J.� � �a',':., . . . 3.Ey< x . ��>s�r"..E�N. , �
,
°. i''&
a ss . ,,,:y° „.
S n { c
= C s
!s
Y : r ,.➢� !
O,
11
ti .
�k
1
^. v�. °.
.a._. ;
.� &; 3
�
• T .. a ...-
� � �F . J .:;, .. — `a
:.,
�r„�, �y ..
,
t 5
, .
;..s
.- w ,L'� e .
".
.
- .:. x..,
„
ITEM
,.,..r.... ,. .,. , :,r.... t ...:: -:..,� .....,.
>..,..:
�...�'zn.'.-',
,- ........
..._...... _..
OUANTif
..a.. � .KZ
. +.
L _:r ...
bEb
li' -=f
-P NIT
EFL U
�-c , - -: 4
.z 1 Jf7E b fl >.
E N
_a.
17,
:.. •,�
„
...
P.E c
5 ENb bf'E
UNII
tiEcT �D ws
.r...,,
,EXTEN, -:
,.,
_
o-,s�.
d:.
[°5�
+#....... ,... 5.. {,
x '11r:t^a
�' +w
q,.M1 13x., '?...
lraJ�W� ib�"::.a
Yai:IF9.
1
Mobilization/Demobilization
LS
1
$36,992.07
$36,992.07
-----------
$71,817.50
--------
$71,817.50
------------
$115,000.00
---------
$115,000.00
------------
$100,000.00
-------------------------------
$100,000.00
$52,800.00
$52,800.00
-------------
--------
2
---- -- ---- ----- --- --- ------ -- --- - --
Maintenance of Traffic
- - --- --
LS
-- - - - - --
1
--------
$29,105.40
$29,105.40
-- -- -- -----
$13,685.00
- -------
$13,685.00
--- - ---
$6,250.00
$6,250.00
$15,000.00
$15,000.00
$10,000.00
$10,000.00
---------------------------------------------------
3
Project Signs
LS
------ --
1
- -- --- --
$555.61
$555.61
$862.50
$862.50
$1,500.00
$1,500.00
$1,000.00
$1,000.00
$1,410.00
$1,410.00
------
4
---- ----- --- --------- --- --- -- --- --'
Clearing and Grubbing
----- --
LS
- -- --- --
1
- -- -----
$22,871.59
$22,871.59
$54,625.00
$54,625.00
$26,000.00
$26,000.00
$75,000.00
$75,000.00
$20,000.00
$20,000.00
- - -- --
5
---- -- --- --- --- --- --- ------ -- --- ---
Install 30” Pipe, Adapters, and Fittings by Open -Cut
-- — -- — -
LF
- -- -- - --
3,490
- -- --- --
$87.45
--- --
$305,200.50
$87.77
--------
$306,317.30
-------------------------------------------
$68.00
$237,320.00
$65.00
$226,850.00
---------------------
$78.00
$272,220.00
------------
- -- - --
6
---- -- ---- --- -- --- --- ---- -- -- --- ---
Install 30" Pipe by Horizontal Directional Drilling
-- --- --
LF
- - - - -- --
2,485
- -- --- --
$241.84
- - --
-----------
$600,972.40
-----------
$236.90
--------
$588,696.50
--------------------------------------------
$257.00
$638,645.00
$250.00
$621,250.00
--------------------
$277.00
$688,345.00
— -- — — -- — --
---------------------------------------------------
7
Install Plug Valves
EA
- -- --- --
5
- -- -
$6,155.49
$30,777.45
$1,725.00
--------
$8,625.00
------------
$3,000.00
---------
$15,000.00
----------------------
$4,500.00
$22,500.00
---------------------
$6,800.00
$34,000.00
------------
---------------------------------------------------
0 8
Install Air Release Valve Assembly
EA
- -- -----
5
- -------
$3,222.29
-----------
$16,111.45
$1,495.00
$7,475.00
$3,000.00
$15,000.00
$2,500.00
$12,500.00
$6,800.00
$34,000.00
W------------------------------------------------
- -- -- - --
-- - --- --
- --- -- -- - --
-- - - - - --
-- --- - - -- --
-- --- --
---- - - - - --
--- -- ----
---------------------
- --- -- --- - --
N 9
Pavement Replacement
SY—
90
$16969
$15- 272
$77
$6,957.00
$80.00
$7-200.00
$15000
$13,500.00
$122.00
$10,980.00
— - - - - --
—
-10
--
-30
—
— —
—
`—
--
— — — —
— — —
— — — —
10
iu
Owner Directed Allowance
TM
1
$50,000.00
$50,000.00
$50,000.00
$50,000.00
$50,000.00
$50,000.00
$50,000.00
$50,000.00
$50,000.00
$50,000.00
Total Bid
57,107,858 57
Totaf 060 80btal
d 4 �
Sid �tt��9i5 00
Toai �idj
;1,�37r�300 Ob
}
Total 5 rW{
#i, X3,355.00
,6f�,
lT E Verify
Yes
Yes
Yes
Yes
Yes
O Florida Division of Corporations
Yes
Yes
Yes
Yes
Yes
{ Material Manufacturers
Yes
Yes
Yes
Yes
Yes
List of Major Subcontractors
Yes
Yes
Yes
Yes
Yes
Statement of Experience
Yes
Yes
Yes
Yes
Yes
Trench Safety Act
Yes
Yes
Yes
Yes
Yes
Local Preference
Yes
Yes
Yes
Yes
Yes
Immigration Law Affidavit Certification
Yes
No
Yes
Yes
Yes
Substitute W -9
Yes
Yes
Yes
Yes
Yes
Bid Bond
Yes
Yes
Yes
Yes
Yes
Bidders Check List
Yes
Yes
Yes
Yes
Yes
Insurance Certificate
Yes
Yes
No
No
No
N
O
AE
= . ,
:.::
r taDougias tJ
Higgins; lnc.
_.; i , ., tYs..
...
GUymahn Construction:df,��
_
r 4' . •( �i.
s, '.M; .
; MdreNr Sitd dr�L UP,
.i '1 FJ . 6 ,, : d ryry GdiAi �fl Cts
CdUs�ai Cdrii rata Prdliuc LLC
is
,. ,
.1. .F J
etro .ui41
111 Eq..lpm
.i r '•
a I }ivi�li c''
nS In
' ^
X
r
� 45•f°
�4
-
o i
,
h
'
?a a,. ..R �::,
ITEM NC1 : IT I)SCI2IPTION UNITS+
_
N
�UAWTITY
pER UNIT"
;... ,.;
" EXTENDED
p '
ER UNIT'
.,'''mot
f
'T'EI(TENbED'�r`
,� r 1
-P €I2 UNIT' �E�CIENDEDSr.
Yn� x
`rPE s E
k UNIT XTENDED
:PEt�UNI'1��
EXTENDED.
---_- — ..�- _- -- `+,------------ - - - -�- -• --
-- - - - --
- -_ - - - --
—
__r�-= --
-- --- =--�•-
_,
- �...
- i4ts$57,530.00
y
�-
1 Mobilization /Demobilization LS
-----------------------------
t
- -- --- --
$47,137.00
- -- -- - --
$47,137.00
$72,831.00
$72,831.00
$57,530.00
___ ......= —y -`yam - --
$85,000.00 $85,000.00
- - -`V•
$190,000.00
— -` --
$190,000.00
2 Maintenance of Traffic LS
-- — -- — -- — -- — -- — -- - - — -- — -
1
- - - - -- --
$2,608.00
- -- --- --
- --- -- - -- --
$2,608.00
-
- - - --- --
$13,280.00
- --- -- --- - --
$13.280.00
-- - - - --- ---- - --- - - -
$7,320.00 $7,320.00
-- — -- — -- — -- --- -- - ---
$35,000.00 $35.000.00
- -- --- --
$25,000.00
- --- -- - -- - --
$25,000.00
— '
3 Project Signs LS
9
------------------------------------ -- --- --
1
- ----- --
$555.00
- -- -----
--- -- --- --
$555.00
- - - - - ---
$1,000.00
-- -- -- - - - ---
$1,000.00
$854.00 $854.00
--- -- ---- -- --- -- ----
$7,500.00 $7,500.00
- -- --- --
$1,000.00
- --- -- - - - - --
$1,000.00
4 Clearing and Grubbing LS
------------------------------------ - - -----
1
- - - --- --
$51,625.00
- - - --- --
- --- -- --- --
$51,625.00
--
- ----- --
$43,000.00
- --- -- -- - --
$43,000.00
-- - -- --- - ----------
$42,700.00 $42,700.00
----- ---- ------- ----
$15,000.00 $15,000.00
------ --
$20,000.00
------ --- ---
$20,000.00
5 Install 30" Pipe, Adapters, and Fittings by Open -Cut LF
— — —
3,490
— —
$106 00
—
--- - --- --
$36994000
-----------
- -- - - - --
$123 -35
-- -- -- - - - ---
$430,491.50
-- ---- -- --- -- -- - - --
$120.60 $420.894.00
--- - - - --- ---------------------
$111.30 $386,437.00
$120.00
---- -- - - - - --
$418,800.00
6 Install 30" Pipe by Horizontal Directional Drilling LF
--------------------------------------------------- -- --- --
2,485
- -- --- --
$255.00
- -- - --
$633,675.00
—
$226.60
— —
$563,101.00
—
$296.90 $737,796.50
— —
$348.50 $866,022.50
—
$310.00
— —
$770,350.00
7 Install Plug Valves EA
---------------------------------------------------
5
-----------------
--
$1,469.00
- ---- - -- - --
$7,345.00
- ----
- -- --- --
$6,005.00
- --- -- --- ---
$30,025.00
--------------------------------
$6.179.00 $30.895.00
---------------------
$2,400.00 $12,000.00
$1,000 -00
- --- -- --- ---
$5,000.00
— 8 Install Air Release Valve Assembly EA
- ---- -- ---- - --- --- - - — -- — -
5
- -- -- - --
$1,313.00
- - - ---
- --- --
$6,565.00
- - - - -- --
$4,175.00
- --- -- - - - ---
$20,875.00
-- - -- - -- --- -- -- - ---
$4,175.00 $20,875.00
- -- -- ---- ---------------------
$200.00 $1,000.00
$1,500.00
------ - - - ---
$7,500.00
9 Pavement Replacement SY
-- — -- — -- — -- — -- -- — -- — -
90
-----------------
--
$95.00
-- -- -- --- --
$8,550.00
- - - --- --
$50.75
- ----- --- - --
$4,567.50
-- — - - — -- - - - -- — -- — --
$153.00 $13,770.00
--- -- ---- --- -- -- --- --
$50.00 $4,500.00
-- - - - - --
$95.00
- --- -- --- ---
$8,550 -00
10 Owner Directed Allowance TM
1
$50,000.00
- --- -- --- --
$50,000.00
- -- --- --
$50,000.00
- --- -- ------
$50,000.00
-- -- - --- ----- -- - ---
$50,000.00 $50,000.00
--- -- ---- ----- - - ----
$50,000.00 $50,000.00
--'--- --
$50,000.00
- --- -- --- ---
$50,000.00
;Total Bid .;' $1,178,000,00
.. Total Bid „ : ° $1,229171 00
a Total Bid j1,S8 834 80
r Total) Bid: $�,48d459.60
R° TotalBil �1id9,8,200.00
E Verify
Yes
Yes
„ff
No
No
No
Florida Division of Corporations
Yes
Yes
Yes
No
Yes
n Material Manufacturers
Yes
Yes
Yes
Yes
Yes
List of Major Subcontractors
Yes
Yes
Yes
Yes
Yes
(D
ry Statement of Experience
Yes
Yes
Yes
Yes
Yes
Trench Safety Act
Yes
Yes
Yes
Yes
Yes
!]! Local Preference
Yes
Yes
Yes
Yes
Yes
Immigration Law Affidavit Certification
Yes
Yes
Yes
Yes
Yes
Substitute W -9
Yes
Yes
Yes
Yes
Yes
t7l Bid Bond
Yes
Yes
Yes
Yes
Yes
0 Bidders Check List
Yes
Yes
Yes
Yes
Yes
, Insurance Certificate
Yes
No
Yes
No
Yes
Opened By: Swainson Hall, Procurement Strategist
Witnessed By: Evelyn Colon, Procurement Strategist
—4
N
O
Cn
AE
v
m
v
m
rn
0
Bid Results of RFQ 15 -4561
(Master Pump Station 306 Force Main Phase 2)
$1,600,000.00
.................................................................... ............................... KEY:
$1,400,000.00 -
--- - - - - - - - - - - - - - - - - - - - - - - -
Dashed Green -
AVERAGE BID
$1,200,000.00 -- - - - - - -- - - - — Dashed black -
+/ -1 std dev
— — — — — — — — — — — — of avg bid
$1,000,000.00 —
Dotted red-
+/- 20% of eng
estimate for
$800,000.00 — horizontal
construction
$600,000.00
$400,000.00
$200,000.00
$0.00
�c 00 �etQ ��4r Jtir aca �`QO JAS 92 CpC
Al
y
N
O
U7
w
7/7/2015 11.C.
•
June 10, 2015
AECOM 239 - 278 -7996 tel
4415 Metro Parkway Ste. 404 239 - 278 -0913 fax
Fort Myers, FL 33916
www.aecom.com
Mr. Wayne Karlovich, P. E.
Senior Project Manager
Public Utilities Planning and Project Management
RE: MPS 306 Force Main Phase II - Collier County Solicitation #15 -6451
Letter of Recommendation to Award Contract
Mr. Karlovich,
Pursuant to your request, AECOM Technical Services, Inc. has reviewed
the apparent low bidder's (Bonness Inc.) bid proposal for the MPS 306 Force
Main Phase II project. This bid was received by Collier County and opened at
3:00 PM on May 27, 2015, at the County's Purchasing Department located at
3327 Tamiami Trail East, Naples, FL 34112. The County's Purchasing
Department reviewed the bid for completeness, bidder's responsiveness, and
mathematical correctness. AECOM's review included a comparison of
Bonness Inc.'s bid proposal with other submitted bids and the Engineers
estimate. AECOM also confirmed successful similar assignments with the
references Bonness Inc. provided in their proposal.
Ten bids were received by the County from General Contractors. The bids and
the Engineer's Opinion of Probable Construction Cost are summarized below:
Bidder
Base Bid
Bonness Inc.
$1,107,858.57
Quality Enterprises USA, Inc.
$1,109,060.80
Mitchell & Stark Construction Company, Inc.
$1,111,915.00
Southwest Utility Systems, Inc.
$1,167,600.00
B Landmark Construction, Inc.
$1,173,755.00
Dou as N. Higgins, Inc.
$1,178,000.00
Gu mann Construction of FL
$1,229,171.00
Andrew Sitework LLC
$1,382,634.50
Coastal Concrete Products LLC
$1,464,459.50
Metro E_ ui ment Service, Inc.
Engineer's Estimate
$1,496.200.00
$1,250,000.00
Based upon the information provided to the County with the bid, and
evaluation of the bids, AECOM recommends the award of the contract to
Bonness Inc. in the amount of $1,107,858.57.
Packet Page -608-
7/7/2015 11.C.
We appreciate the opportunity to assist the County on this important project.
If you have any questions or if you require any additional information, please
do not hesitate to contact me directly at 239 - 278 -7996.
Sincerely,
AECOM Technical Services, Inc.
a
Donovan S. Bramlett, P.E.
Project Manager
Packet Page -609-
C
7i
U.
O x
ko Lu
LM
E
sa
re 0 w.
2
k-
u
CD
Ln Z:
LU
Lj
Zzr
-6
Barn Rd�
Z E
o, A CAr P-
�vj 11
Ut
`pr:...
le
-JW
�il 4�
RE
ifii
ti
IA
0
0 a.
of
Packet Page -610-
7/7/2015 11.C.
O
v
0
o
a)
E
�
a
a)
5u,
7/7/2015 11.C.