Loading...
Agenda 05/12/2015 Item #16C1EXECUTIVE SUMMARY Recommendation to approve a $365,690.30 work order to Quality Enterprises USA, Inc., under Request for Quotation 14-6213-20 for Underground Utility Contracting Services for the Bluebill Avenue Forcemain Replacement, Project Number 70044. OBJECTIVE: To bring outdated utility infrastructure into compliance with current standards while meeting the demand for service, protecting public health and safety, and providing proactive environmental protections. CONSIDERATIONS: On June 10, 2014, as Agenda Item 11C, the Board of County Commissioners (Board) approved the Water, Wastewater, Irrigation Quality Water, and Bulk Potable Water User Rate Study. The proposed scope of work is consistent with Project 70044, “Forcemain Transmission System TSP,” on page 3-186, line 74 of the user rate study. Funding for project 70044 is available in and is consistent with the FY2015 CIP Budget. The purpose of this project is to proactively replace critical infrastructure that is aging to prevent an accidental wastewater discharge. The Bluebill Avenue force main is an approximately 40-year-old subaqueous (underwater) crossing made of iron pipe. This force main provides wastewater service to all entities west of the Vanderbilt Channel. The condition of this asset is defined as “Red: Level 3 – Risked Compliance” as reported to the Board at the October 1, 2013, Asset Assessment and Management Workshop. This project was designed under the Wastewater Basin Program. The scope of work includes a replacement HDPE force main directionally drilled under the Vanderbilt Channel. The Public Utilities Department coordinated with the Vanderbilt Beach Beautification Municipal Service Taxing Unit to minimize disruption to the ar ea and its residents, and to optimize other underground utility work. The Procurement Services Division electronically distributed Request for Quotation 14-6213-20, Bluebill Avenue Force Main, on February 25, 2015, to the six vendors under the Fixed-Term Underground Utilities Contract No. 14-6213. Five of the vendors submitted quotations by the March 20, 2015, deadline. The quotations are summarized below. VENDOR QUOTE Quality Enterprises $ 365,690.30 Mitchell & Stark $ 376,545.00 Douglas N Higgins $ 406,818.80 Haskins, Inc. $ 461,612.00 Southwest Utility Systems, Inc. $ 530,264.00 Kyle Construction Did Not Quote The engineer’s opinion of probable construction cost is $455,218. Staff reviewed the quotations and determined Quality Enterprises USA, Inc., to be the lowest qualified and responsive bidder at approximately 20 percent below the engineer’s cost opinion. The quote tabulation and graph are Attachments 1 and 2, respectively. The Procurement Services Division concluded that bidding was competitive and representative of market conditions. The project design professional for the Wastewater Packet Page -697- 5/12/2015 16.C.1. 101 Basin, CDM Smith, Inc., also recommends award of this work order to Quality Enterprises USA, Inc., per the attached letter dated April 8, 2015 (Attachment 3). Quality Enterprises USA, Inc. has a satisfactory performance and warranty record on other similar county utility-related construction projects. The bid specifications informed the bidders there may be unforeseen conditions associated with the project. The project cost includes an allowance of $55,000 for owner- directed work due to unforeseen corrosive or geological conditions that include, but are not limited to, repairs due to structural deterioration, and/or replacement of defective mechanical equipment and deficient electrical components. Subject to the Purchasing Ordinance, staff will negotiate a price for any additional work due to unforeseen conditions prior to the start of any such work. FISCAL IMPACT: Funding is available in, and is consistent with, the FY2015 Capital Budget approved by the Board on September 18, 2014. The source of funding is the Wastewater User Fee Fund (414). The total capital cost to implement Project 70044, Bluebill Avenue Force Main, is $365,690.30. This asset is a direct replacement; therefore, operational costs are not expected to change. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval.—SRT GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan standards to ensure the adequacy and availability of viable public facilities. RECOMMENDATION: That the Board of County Commissioners, Ex-officio Governing Board of the Collier County Water-Sewer District, approve a $365,690.30 work order under Request For Quotation 14-6213-20 to Quality Enterprises USA, Inc.; and, authorize the Chairman to sign and execute the work order after approval by the County Attorney’s Office. Prepared By: Corinne Trtan, Project Manager, Planning and Project Management Division. Attachments: Attachment 1- Quote tabulation Attachment 2- PPMD Quote Analysis Attachment 3- Recommendation Letter Attachment 4- Work Order Packet Page -698- 5/12/2015 16.C.1. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.C.16.C.1. Item Summary: Recommendation to approve a $365,690.30 work order to Quality Enterprises USA, Inc., under Request for Quotation 14-6213-20 for Underground Utility Contracting Services for the Bluebill Avenue Forcemain Replacement, Project Number 70044. Meeting Date: 5/12/2015 Prepared By Name: TrtanCorinne Title: Project Manager, Public Utilities Engineering 4/15/2015 1:58:13 PM Submitted by Title: Project Manager, Public Utilities Engineering Name: TrtanCorinne 4/15/2015 1:58:14 PM Approved By Name: Joseph Bellone Title: Division Director - Operations Support, Utilities Finance Operations Date: 4/15/2015 3:12:35 PM Name: HapkeMargie Title: Recycling Coordinator, Solid & Hazardous Waste Management Date: 4/15/2015 3:37:24 PM Name: NagySteve Title: Manager - Wastewater Collection, Wastewater Date: 4/16/2015 1:51:59 PM Name: ChmelikTom Title: Division Director - Public Utilities Eng, Public Utilities Engineering Date: 4/16/2015 5:17:41 PM Packet Page -699- 5/12/2015 16.C.1. Name: JohnssenBeth Title: Division Director - Wastewater, Wastewater Date: 4/17/2015 9:41:18 AM Name: MarkiewiczJoanne Title: Division Director - Purchasing & Gen Svc, Purchasing & General Services Date: 4/20/2015 7:23:30 AM Name: HallSwainson Title: Procurement Specialist, Purchasing & General Services Date: 4/20/2015 2:10:00 PM Name: PajerCraig Title: Project Manager, Principal, Public Utilities Engineering Date: 4/20/2015 3:15:07 PM Name: TeachScott Title: Deputy County Attorney, County Attorney Date: 4/21/2015 8:18:43 AM Name: YilmazGeorge Title: Department Head - Public Utilities, Public Utilities Department Date: 4/23/2015 1:01:13 PM Name: KlatzkowJeff Title: County Attorney, Date: 4/29/2015 3:50:05 PM Name: UsherSusan Title: Management/Budget Analyst, Senior, Office of Management & Budget Date: 5/4/2015 11:09:03 AM Name: CasalanguidaNick Title: Deputy County Manager, County Managers Office Date: 5/4/2015 11:41:48 AM Packet Page -700- 5/12/2015 16.C.1. Item Description Unit Estimated Quantity Cost Amount Cost Amount Cost Amount Cost Amount Cost Amount Schedule 1: General 1.1 Mobilization/Demobilization Lump Sum 1 $4,980.00 $4,980.00 $11,000.00 $11,000.00 $16,000.00 $16,000.00 $40,000.00 $40,000.00 $50,000.00 $50,000.00 1.2 Performance and Payment Bond Premium Lump Sum 1 $4,692.00 $4,692.00 $4,000.00 $4,000.00 $5,000.00 $5,000.00 $10,000.00 $10,000.00 $10,000.00 $10,000.00 1.3 Indemnification Lump Sum 1 $300.00 $300.00 $100.00 $100.00 $100.00 $100.00 $2,000.00 $2,000.00 $5,000.00 $5,000.00 Schedule 2: Wastewater Forcemain 2.1 Install Ductile Iron (DI) Wastewater Force Main and Fittings LF 55 $130.90 $7,199.50 $100.00 $5,500.00 $300.00 $16,500.00 $230.00 $12,650.00 $600.00 $33,000.00 2.2 Furnish and Install 12" Line Stops EA 2 $5,700.00 $11,400.00 $14,000.00 $28,000.00 $11,000.00 $22,000.00 $6,000.00 $12,000.00 $15,000.00 $30,000.00 2.2 Furnish and Install 12" Tapping Valve and Sleeve EA 2 $3,570.00 $7,140.00 $4,800.00 $9,600.00 $3,300.00 $6,600.00 $2,500.00 $5,000.00 $8,500.00 $17,000.00 2.3 Install Air Release Valves EA 2 $1,200.00 $2,400.00 $2,500.00 $5,000.00 $1,500.00 $3,000.00 $2,000.00 $4,000.00 $2,500.00 $5,000.00 2.4 906 LF Horizontal Directional Drill (from Station 12+47 to Station 21+53)Lump Sum 1 $227,640.00 $227,640.00 $220,000.00 $220,000.00 $240,000.00 $240,000.00 $185,000.00 $185,000.00 $250,000.00 $250,000.00 2.5 Furnish Asphalt for 1-inch Overlay SF 15,132 $1.90 $28,750.80 $1.10 $16,645.20 $0.90 $13,618.80 $3.50 $52,962.00 $2.00 $30,264.00 2.6 Miscellaneous Work and Cleanup Lump Sum 1 $6,900.00 $6,900.00 $15,000.00 $15,000.00 $18,000.00 $18,000.00 $65,000.00 $65,000.00 $15,000.00 $15,000.00 2.7 Excavation Below Normal Grade and Bedding Rock CY 100 $60.00 $6,000.00 $12.00 $1,200.00 $50.00 $5,000.00 $55.00 $5,500.00 $50.00 $5,000.00 Schedule 3: Environmental 3.1 Wetland Erosion Control and Prevention Barriers Lump Sum 1 $1,785.00 $1,785.00 $3,500.00 $3,500.00 $3,000.00 $3,000.00 $10,000.00 $10,000.00 $20,000.00 $20,000.00 3.2 Tree and Inlet Protection Lump Sum 1 $1,503.00 $1,503.00 $2,000.00 $2,000.00 $3,000.00 $3,000.00 $2,500.00 $2,500.00 $5,000.00 $5,000.00 Schedule 4: Allowances 4.1 Materials Testing Allowance T&M 1 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 4.2 Extra Work (Project Allowance)T&M 1 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $365,690.30 $376,545.20 $406,818.80 $461,612.00 $530,264.00 1. Kyle Construction Inc Collier County Basin 101 - Bluebill Ave Bridge Force Main Design Quote Schedule (Installation Only) Douglas N. Higgins, Inc. Were there any Contractors who did not submit any quotes? TOTAL BID PRICE FOR PROJECT Haskins Inc. Mitchell & Stark Construction Company, Inc. Quality Enterprises USA, Inc. Southwest Utility Systems, Inc. Pa c k e t P a g e - 7 0 1 - 5 / 1 2 / 2 0 1 5 1 6 . C . 1 . $3 0 0 , 0 0 0 $4 0 0 , 0 0 0 $5 0 0 , 0 0 0 $6 0 0 , 0 0 0 RF Q  Re s u l t s  fo r  Bl u e b i l l  Av e .  Fo r c e m a i n  Re p l a c e m e n t  Pr o j e c t KEY:DashedGreen ‐AVERAGE  BID Dashed  black ‐+/‐1  std  dev of  avgbid Dottedred ‐+/‐20% of  eng estimate  for horizontal $0 $1 0 0 , 0 0 0 $2 0 0 , 0 0 0 En g  Es t Q u a l i t y  En t e r p r i s e s M i t c h e l l  & St a r k D N  Hi g g i n s ,  In c . H a s k i n s  In c . S o u t h w e s t  Ut i l i t y   Sy s t e m s ,  In c . construction Packet Page -702- 5/12/2015 16.C.1. 2180 W. First Street Suite 400 Fort Myers, Florida 33901 tel: 239 938-9600 fax: 239 339-6418 April 8, 2015 Craig Pajer, P.E. Principal Project Manager Public Utilities Planning and Project Management Department 3339 Tamiami Trail East, Suite 303 Naples, FL 34112 Subject: Basin 101 – Bluebill Ave. Bridge Force Main RFQ No. 14-6213-20 Low Quote Evaluation – Recommendation for Contract Award Dear Mr. Pajer: On March 20, 2015, quotes were received by Collier County for the Bluebill Ave. Force Main project (RFQ No. 14-6213). Five quotes were received. The apparent low quote was submitted by Quality Enterprises USA, Inc. in the amount of $365,690.30 for Quote Items 1 through 4, including the identified project allowances. This is approximately twenty percent less than CDM Smith’s opinion of probable construction cost of $455,218. The other four quotes were submitted by Mitchell & Stark Construction Company, Inc. ($376,545.20), Douglas N. Higgins, Inc. ($406,818.80), Haskins Inc. ($461,612.00), and Southwest Utility Systems, Inc. ($530,264.00). The quote tabulation summary is attached. CDM Smith has reviewed the quote submitted. The price appears reasonable to properly complete the work. Quality Enterprises USA, Inc. is on the County’s Annual Contract for Underground Utility Contracting Services and as such should be qualified to properly perform the work on this project. In summary, CDM Smith believes that Quality Enterprises USA, Inc. is the lowest, responsive, responsible quoting firm and is qualified to perform the construction of the Bluebill Ave. Forcemain project. CDM Smith recommends that Collier County award the project for the total quote for Items 1 through 4 including the project allowance. Please do not hesitate to call if you have any questions or wish to discuss the quote further. Respectfully, Jason A. Sciandra, P.E. Senior Project Manager CDM Smith Inc. Attachment Packet Page -703- 5/12/2015 16.C.1. Item Description Unit Estimated Quantity Cost Amount Cost Amount Cost Amount Cost Amount Cost Amount Schedule 1: General 1.1 Mobilization/Demobilization Lump Sum 1 $4,980.00 $4,980.00 $11,000.00 $11,000.00 $16,000.00 $16,000.00 $40,000.00 $40,000.00 $50,000.00 $50,000.00 1.2 Performance and Payment Bond Premium Lump Sum 1 $4,692.00 $4,692.00 $4,000.00 $4,000.00 $5,000.00 $5,000.00 $10,000.00 $10,000.00 $10,000.00 $10,000.00 1.3 Indemnification Lump Sum 1 $300.00 $300.00 $100.00 $100.00 $100.00 $100.00 $2,000.00 $2,000.00 $5,000.00 $5,000.00 Schedule 2: Wastewater Forcemain 2.1 Install Ductile Iron (DI) Wastewater Force Main and Fittings LF 55 $130.90 $7,199.50 $100.00 $5,500.00 $300.00 $16,500.00 $230.00 $12,650.00 $600.00 $33,000.00 2.2 Furnish and Install 12" Line Stops EA 2 $5,700.00 $11,400.00 $14,000.00 $28,000.00 $11,000.00 $22,000.00 $6,000.00 $12,000.00 $15,000.00 $30,000.00 2.2 Furnish and Install 12" Tapping Valve and Sleeve EA 2 $3,570.00 $7,140.00 $4,800.00 $9,600.00 $3,300.00 $6,600.00 $2,500.00 $5,000.00 $8,500.00 $17,000.00 2.3 Install Air Release Valves EA 2 $1,200.00 $2,400.00 $2,500.00 $5,000.00 $1,500.00 $3,000.00 $2,000.00 $4,000.00 $2,500.00 $5,000.00 2.4 906 LF Horizontal Directional Drill (from Station 12+47 to Station 21+53)Lump Sum 1 $227,640.00 $227,640.00 $220,000.00 $220,000.00 $240,000.00 $240,000.00 $185,000.00 $185,000.00 $250,000.00 $250,000.00 2.5 Furnish Asphalt for 1-inch Overlay SF 15,132 $1.90 $28,750.80 $1.10 $16,645.20 $0.90 $13,618.80 $3.50 $52,962.00 $2.00 $30,264.00 2.6 Miscellaneous Work and Cleanup Lump Sum 1 $6,900.00 $6,900.00 $15,000.00 $15,000.00 $18,000.00 $18,000.00 $65,000.00 $65,000.00 $15,000.00 $15,000.00 2.7 Excavation Below Normal Grade and Bedding Rock CY 100 $60.00 $6,000.00 $12.00 $1,200.00 $50.00 $5,000.00 $55.00 $5,500.00 $50.00 $5,000.00 Schedule 3: Environmental 3.1 Wetland Erosion Control and Prevention Barriers Lump Sum 1 $1,785.00 $1,785.00 $3,500.00 $3,500.00 $3,000.00 $3,000.00 $10,000.00 $10,000.00 $20,000.00 $20,000.00 3.2 Tree and Inlet Protection Lump Sum 1 $1,503.00 $1,503.00 $2,000.00 $2,000.00 $3,000.00 $3,000.00 $2,500.00 $2,500.00 $5,000.00 $5,000.00 Schedule 4: Allowances 4.1 Materials Testing Allowance Lump Sum 1 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 $5,000.00 4.2 Extra Work (Project Allowance)Lump Sum 1 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $365,690.30 $376,545.20 $406,818.80 $461,612.00 $530,264.00 Haskins Inc. Mitchell & Stark Construction Company, Inc. Quality Enterprises USA, Inc. Southwest Utility Systems, Inc. Collier County Basin 101 - Bluebill Ave Bridge Force Main Design Quote Schedule (Installation Only) Douglas N. Higgins, Inc. TOTAL BID PRICE FOR PROJECT Pa c k e t P a g e - 7 0 4 - 5 / 1 2 / 2 0 1 5 1 6 . C . 1 . Packet Page -705- 5/12/2015 16.C.1. Packet Page -706- 5/12/2015 16.C.1. Packet Page -707- 5/12/2015 16.C.1. Packet Page -708- 5/12/2015 16.C.1. Packet Page -709- 5/12/2015 16.C.1. Packet Page -710- 5/12/2015 16.C.1.