Agenda 04/28/2015 Item #16E2 4/28/2015 16.E.2. EXECUTIVE SUMMARY Recommendation to approve Change Order#12 in the amount of$114,853.20 to Deangelis Diamond Construction on Contract 13-6137, Collier County J-1 HVAC System Replacement, and authorize the necessary Budget Amendment to install security related devices in the J-1 Section of the Naples Jail. OBJECTIVE: To increase the security and safety for inmates in the J-1 Section of the Naples Jail in accordance with the recommendations of a technical resource working in conjunction with the National Institute of Corrections(NIC), Department of Justice. CONSIDERATIONS: The Division of Facilities Management is responsible for the maintenance, repair, capital replacement, and construction of over 900 County structures, including the Naples Jail Facility which houses Collier County Sheriff's Office inmates. The upgrading of Heating, Ventilation, and Air-Conditioning (HVAC) systems in the J-1 Section of the Naples Jail Center is a five million six hundred thousand dollar ($5,600,000); four (4) year project contracted with Deangelis Diamond Construction (DDC)and is currently in its final year of completion. On July 10, 2014, a technical resource, working in conjunction with the Sherriff s Office and the Department of Justice's National Institute of Correction (NIC), provided recommendations for the Naples Jail Facility, which if performed, would increase the security and safety of inmates held in 312 individual holding cells. A specific safety and security recommendation requires the customization of each individual holding cell. The method and installation procedure for this customization was developed and tested in one (1) individual holding cell by Corrections Staff and DDC, and has been approved by the Sheriffs Office Corrections Staff as an appropriate modification in accordance with the recommendation identified in the NIC Technical Assistance Report. This type of work requires that inmate pods be vacant while the work is performed. DDC is currently working in vacant Jail Pods 3 and 4 and will be starting the final two Jail Pods in April which will be vacated at that time. Staff is recommending this change order and upgrade in the amount of one hundred fourteen thousand eight hundred fifty three dollars and twenty ($114,853.20) be issued to DDC to complete the customization of the entire 312 individual cells to comply with the NIC Technical Assistance Report recommendations based on the following: - The contractor's personnel developed the specific installation procedure for the customization of the individual cells to work in conjunction with the upgraded HVAC system; • The contractor is currently working in the jail and has qualified personnel who are experienced at working inside the jail and its environment; • The contractor has already completed the process of having its personnel obtain the required Correctional Security clearances; - Since the contractor will be working in the vacated Jail Pods 5 and 6, they can customize those two pods while completing the final phase of the HVAC project, a three (3) month schedule savings over mobilizing another contractor after the HVAC project is completed; and • The installation of the customization in the other, previously HVAC upgraded Pods 1, 2, 3, & 4; will require significant cooperation and coordination between the Correctional Staff and the contractor, a relationship that has been highly successful with DDC. This item and Staffs recommendation has been reviewed by the Chief of Corrections and is fully supported. Packet Page -1817- 4/28/2015 16.E.2. The details of this project are exempt from Florida's Public Records Law as provided for in Section 119.07 and Section 281.301, Florida Statutes. FISCAL IMPACT: A Budget Amendment in the amount of $114,853.20 is required to transfer funds from County-wide Capital Project Fund 301 Reserves to increase Naples Jail Project 52008. J,EGAL CONSIDERATIONS: This item has been approved as to form and legality and requires majority vote for approval.—CMG GROWTAMANAGEMENTIMPACT: There is no impact to the Growth Management Plan related to this action. RECOMMENDATION: That the Board of County Commissioners approves Change Order #12 in the amount of $114,853.20 to Deangelis Diamond on contract 13-6137 Collier County J1 HVAC System Replacement and authorizes the necessary Budget Amendment to install security related devices in the J-1 Section of the Naples Jail. Prepared By: Dennis Linguidi,CFM,Interim Director,Facilities Management Division Reviewed By: Chris Roberts, Chief of Corrections, Collier County Sheriff's Office Reviewed By: Hank Jones,P.E.,Principle Project Manager,Facilities Management Division Attachments: • Change order proposal • Contract Change Order Form Packet Page -1818- 4/28/2015 16.E.2. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.E.16.E.2. Item Summary: Recommendation to approve Change Order#12 in the amount of $114,853.20 to Deangelis Diamond Construction on Contract 13-6137, Collier County J-1 HVAC System Replacement, and authorize the necessary Budget Amendment to install security related devices in the J-1 Section of the Naples Jail. Meeting Date: 4/28/2015 Prepared By Name: LinguidiDennis Title: Manager-Facilities, Facilities Management 4/3/2015 10:08:37 AM Submitted by Title: Manager-Facilities,Facilities Management Name: LinguidiDennis 4/3/2015 10:08:38 AM Approved By Name: JonesHank Title: Project Manager,Principal,Facilities Management Date: 4/9/2015 3:32:31 PM Name: CummingsRhonda Title: Procurement Specialist,Purchasing&General Services Date: 4/10/2015 3:31:56 PM Name: MarkiewiczJoanne Title: Division Director-Purchasing&Gen Svc, Purchasing&General Services Date: 4/13/2015 12:39:28 PM Name: HerreraSandra Title: Manager-Procurement, Purchasing&General Services Date: 4/14/2015 7:31:52 AM Packet Page-1819- 4/28/2015 16.E.2. Name: JohnsonScott Title:Manager-Procurement, Purchasing&General Services Date: 4/14/2015 7:56:52 AM Name: PriceLen Title: Department Head -Administrative Svc, Administrative Services Department Date: 4/14/2015 2:27:57 PM Name: GreeneColleen Title:Assistant County Attorney, CAO General Services Date: 4/14/2015 2:31:23 PM Name: KlatzkowJeff Title: County Attorney, Date: 4/14/2015 3:01:42 PM Name: UsherSusan Title: Management/Budget Analyst, Senior, Office of Management&Budget Date: 4/16/2015 8:31:50 AM Name: UsherSusan Title: Management/Budget Analyst, Senior, Office of Management&Budget Date: 4/16/2015 8:31:59 AM Name: CasalanguidaNick Title:Deputy County Manager, County Managers Office Date: 4/16/2015 3:17:13 PM Packet Page -1820- 4/28/2015 16.E.2. • DEANGELIS DIAMOND C ONSTRUCTI ON. I N C. Change Request I To: Robert Fuentes-CCDF Number. 39 Collier County Date: 2/2/15 3335 Tamiami Trail East Job: 13-021 Collier County J-1 HVAC System Naples, FL 34112 Ph: 239-252-8380 Description: 1 j We are pleased to offer this proposal to make the following changes: To furnish and install 616 Kees security,40.41per the attached proposal by B&I Contractors. 15-500 HVAC 109,384.00 Subtotal 109,384.00 Fee 5,469.20 The total amount to provide this work is $114,853.20 Please note that DeAngelis Diamond Construction will require an extra 30 days. If this is acceptable,sign and return via fax(239-594-1995)or email. Please provide approval at your earliest convenience. Only the work specifically outlined in this proposal is included. If you have any questions, or comments,feel free to contact me at 239-594-1994. Submitted by: Nic Kieft Approved by: DeAngelis Diamond Construction Date: Cc: Scott Craig PE(H2 Engineering, Inc.) 6635 WILLOW PARK DRIVE, NAPLES, FL 34109 1 7309 MERCHANT COURT, SUITE B, SARASOTA, FL 34240 NAPLES:239.594.1994 I SARASOTA:941.388.6997 DEANGELISDIAMOND.COM Packet Page -1821- 4/28/2015 16.E.2. Caner G®tf e .1 Procurement Services Change Order Form El Contract Modification ❑ Work Order Modification ❑Amendment Contract#: 13-6137 Change#: 12 I Purchase Order#: 1 4500147834 Project#: 51031 Contractor/Firm Name: DeAngelis Diamond Construction Co. Project Name: J-1 HVAC Replacement Project Manager Name: Robert Fuentes Department: Facilities Management Division Original Contract/Work Order Amount $ 5,182,845.00 9-24-13#11F Original BCC Approval Date; Agenda Item # Current BCC Approved Amount $ 4,583,414.00 9-24-13#11F Last BCC Approval Date; Agenda Item # Current Contract/Work Order Amount $ 4,583,414.00 4/9/2016 SAP Contract Expiration Date(Master) Dollar Amount of this Change $ 114,853.20 -9.35% Total Change from Original Amount Revised Contract/Work Order Total $ 4,698,267.20 2.51% Change from Current BCC Approved Amount Cumulative Changes $ (484,577.80) 2.51% Change from Current Amount Completion Date, Description of the Task(s)Change, and Rationale for the Change Notice to Proceed 10-31-2013 Original 2-11-2016 Last Approved 2-11-2016 Revised Date 2-11-2016 Date Completion Date Date (Includes this change) #of Days Added 0 Select Tasks ❑Add new task(s) ❑ Delete task(s) ❑ Change task(s) ❑ Other(see below) Provide a response to the following: 1.)detailed and specific explanation/rationale of the requested change(s)to the task(s)and/or the additional days added (if requested); 2.)why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed. After the award of this contract the CCSO requested a specific safety and security modification to portions of the HVAC duct system. This specific safety and security recommendation requires the customization of each individual holding cell.The method of installation procedure for this customization was developed and tested in one(1) individual holding cell by Corrections Staff and DeAngelis Diamond Construction (DDC)and has been approved by the Sheriffs Corrections Staff as an appropriate modification to the recommendation identified in the NIC Technical Assistance Report. Staff is recommending this change order and upgrade in the amount of one hundred fourteen thousand fifty three dollars and twenty cents, ($114,853.20) be issued to DDC to complete the customization of the entire 312 individual cells to comply with the NIC Technical Assistance Report recommendation based on the following: • The contractor's personnel developed the specific installation procedure for customization of the individual cells to work in conjunction with the upgraded HVAC system; • The contractor has already completed the process of having personnel obtain the required Correctional Security clearances; • Since the contractor will be working in the vacated Pods 6 and 7,they can customize those two pods while completing the final phase of the HVAC project, a three(3)month schedule savings over mobilizing another contractor after the HVAC project is completed; and coordination between Correctional Staff and the contractor, a relationship that has been highly successful with DDC. Prepared by Robert Fuentes, Project Manager,and Facilities Management Division Date:4-6-2015 k `. < (Project Manager Name and Department) a.� r ` Acceptance of this Change Order shall constitute a modification to contract/work order identified above and will be;subject to all the same terms and conditions as containedj'n the contract/work order indicated above,as fully as if the same were stated in this acceptance. The adjustment, if any to the Contract shall constitute a full and final settlement of any and all claims of the Contractor/Vendor/Consultant/ Design Professional arising orirfelated to the change set forth herein, including claims for impact and delay costs. are Accepted by: i' '17/,-,:zs-/-f" C/P`e} f ', ...t6 1-1, °0-zi Date: — / (Corttracto-1 Vendor/Consultant/Design Professional and Name of Firm, if project applicable) Approved by: Date: (Design/P efessionaj"nd Name-of Firm,if project applicable) , / Approved by : /`� `'1,r ";6� 4e / /-144-1.4, Date: t ' % "} (Proc sent Prof&s ibn'a'I � (Divisions who may require Packet Page -1822-iclude on separate sheet.) Revised: 10/28/2014 � ��� 4/28/2015 16.E.2. X05" , di gt.irt DEANGELIS DIAMOND CONSTRUCTION, INC Change Request I To: Robert Fuentes-CCDF Number: 39 Collier County Date: 2/2/15 3335 Tamiami Trail East Job: 13-021 Collier County J-1 HVAC System Naples, FL 34112 Ph:239-252-8380 Description: Anti-suicide grills We are pleased to offer this proposal to make the following changes: To furnish and install 616 Kees security grills per the attached proposal by B&I Contractors. 15-500 HVAC 109,384.00 Subtotal 109,384.00 Fee 5,469.20 The total amount to provide this work is $114,853.20 Please note that DeAngelis Diamond Construction will require an extra 30 days. If this is acceptable,sign and return via fax(239-594-1995)or email. Please provide approval at your earliest convenience. Only the work specifically outlined in this proposal is included. If you have any questions, or comments,feel free to contact me at 239-594-1994. Submitted by: Nic Kieft Approved by: DeAngelis Diamond Construction Date: Cc: Scott Craig PE(H2 Engineering, Inc.) 6635 WILLOW PARK DRIVE, NAPLES, FL 34109 I 7309 MERCHANT COURT, SUITE B, SARASOTA, FL 34240 NAPLES: 239.594.1994 I SARA Packet Page -1823-IEANGELISDIAMOND.COM Change Order Request 4/28/2015 16.E.2. Established 1960 Employee Owned C.O.R.# 2465-0011 B&I=,Contr. ors Inc. G.C. # . Mechanical•Service Electrical•Plumbing °".rrete °° Date: 1/28/2015 Celebrating 50 rears.1960-2010 Project Name: Collier County Correctional Facility J-1 HVAC Renovation Project#: 2465 To: DeAngelis Diamond Construction, Inc. From: B&I Contractors, Inc. Attn: Nicholas Kieft sharedl sharedl 6635 Willow Park Drive 2701 Prince Street Fort Myers, FL 33916-5529 Naples, FL 34109 Phone: (239)594-1994 Fax: (239)594-1995 Phone: (239)332-4646 Fax: (239)332-5928 We hereby propose to make the following changes: Anti-suicicde Cell Grilles Proposal to provide anti-suicide grilles for jail cells in pods 2-7. Scope of work as follows: 1. Prepare existing grilles for installation of new maximum security grilles(remove center of grille and prepare face for welding). 2. Provide(616)6" Kees security grilles(face plate only)to match the grilles provided under the J-1 Renovation project for the shower rooms. 3. Installation of grilles(welded to existing with continuous weld around perimeter). 4. Painting of grilles by others. Change Order Price $109,384.00 This price is good for 5 days. If conditions change,this price is void. We are requesting a time extension of 5 days in conjunction with this change. sharedl sharedl 1/28/2015 Author Date Sent 0 Accepted The above prices and specifications of this Change Order request are satisfactory and are hereby accepted. All work to be performed under same terms and conditions as specified in original contract unless otherwise specified. Authorized Signature Date of Acceptance Packet Page -1824- Page 1 of 2 Change Order Request 4/28/2015 16.E.2. EsteblIshed 1960 -. Employee Owned C.O.R.# 2465-0011 B&I Contr , ors Inc. Mechanical•SCNIce Electrical•PWmbing G.C. # 'ro Pr.i.do Date: 1/28/2015 Celebrating i0 mars 1960-2010 Project Name: Collier County Correctional Facility J-1 HVAC Renovation Project#: 2465 Labor Markup (Labor Type I Man HrsI !±I Burden Fringe_ TotalTaxi Sub Total % I Amount r Total Labor) Foreman 770.00 $53.50 $0.00 $0.00 $0.00 $41,195.00 0.00% $0.00 $41,195.00 Journeyman 770.00 $45.00 $0.00 $0.00 $0.00 $34,650.00 0.00% $0.00 $34,650.00 Sub Total $0.00 $75,845.00 $0.00 $75,845.00 Grand Total $0.00 $75,845.00 $0.00 $75,845.00 Materials Markup I'-'Materials I Quantity( Cost TotalTaxl Sub Total %- . Amount Total Materials Grilles 616.00 $23.00 $850.08 $15,018.08 0.00% $0.00 $15,018.08 Welding Supplies 1.00 $500.00 $30.00 $530.00 0.00% $0.00 $530.00 Sub Total $880.08 $15,548.08 $0.00 $15,548.08 Grand Total $880.08 $15,548.08 $0.00 $15,548.08 Total $91,393.08 Overhead $9,139.31 Profit $5,026.62 Warranty $2,741.79 Bond $1,083.01 Total $109,384.00 Packet Page -1825- Page 2 of 2