Agenda 03/24/2015 Item #16A12 3/24/2015 16.A.12.
EXECUTIVE SUMMARY
Recommendation to award ITB #15-6393 for the Traffic Signal Upgrade at the intersection
of Golden Gate Parkway and Tropicana boulevard to Highway Safety Devices, Inc., in the
amount of$479,967.30 for Project#60172.
OBJECTIVE: The purpose of the project is to upgrade the existing span wire traffic signal
installation to a steel mast arm assembly at the intersection of Golden Gate Parkway and
Tropicana Boulevard.
CONSIDERATIONS: Span wire traffic signals within ten miles of the coastline are subject to
damage by high winds and possible complete destruction during a hurricane. Replacement of
this existing span wire traffic signal with a steel mast arm assembly will result in a more secure
traffic control installation during inclement weather. Signal upgrades will also be included with
this work. The Engineer's Opinion of Probable Cost for this improvement was $455,756.79.
On December 19, 2014, notices were sent to 2,280 prospective bidders and 49 bid packages were
downloaded for ITB #15-6393, Traffic Signal Upgrade at the intersection of Golden Gate
Parkway and Tropicana Boulevard. A pre-bid meeting was held on January 6, 2015. Bids were
opened on January 20, 2015, and staff evaluated the three submittals listed below:
Highway Safety Devices, Inc. $479,967.30
American Lighting and Signalization, Inc. $619,538.00
OnPower Services, LLC (Non-Responsive) Non-responsive
OnPower Services, LLC, was deemed non-responsive as the contractor did not provide itemized
unit prices or alternate pricing; therefore, the bid was disqualified. American Lighting and
Signalization, Inc.'s bid was $139,570.70 greater than Highway Safety Devices, Inc. for the
painted mast arm assemblies.
The Highway Safety Devices, Inc. bid was 5.04% above the Engineers Opinion of Probable
Cost. Following review, staff recommends awarding ITB #15-6393 to Highway Safety Devices,
Inc., as the lowest, qualified and responsive bidder. The mast arm assemblies shall be painted
per Board of County Commissioners' (Board) direction as noted from the February 10, 2015,
Board meeting.
FISCAL IMPACT: Funds in the amount of$479,967.30 are available in the Traffic Operations
Intersection Enhancement Project(#60172). Source of funds is Gas Tax.
The Traffic Operations Section currently utilizes funding of approximately $600,000 to maintain
205 signalized intersections (an estimated $3,000 annual maintenance cost per intersection). The
upgrade of this intersection should not impact ongoing maintenance costs, as this intersection is
not incremental to the county network, but rather a safety enhancement.
LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires
majority vote for Board approval.—SRT
Packet Page-511-
3/24/2015 16.A.12.
GROWTH MANAGEMENT IMPACT: There is no growth management impact associated
with this Executive Summary.
RECOMMENDATION: That the Board award ITB #15-6393, Traffic Signal Upgrade at the
intersection of Golden Gate Parkway and Tropicana Boulevard to Highway Safety Devices, Inc.,
in the amount of $479,967.30 and authorize the Chairman to execute the attached agreement
after final review by the County Attorney's Office.
Prepared by: John W. Miller, Project Manager, Traffic Operations Division, Growth
Management Department
Attachments: 1)Bid Tabulation; and 2) 15-6393 Contract
http://www.colliergov.net/ftp/AaendaNar2514/GrowthMamt/15-6393contractcAoApproved.pdf
Packet Page-512-
3/24/2015 16.A.12.
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.16.A.16.A.12.
Item Summary: Recommendation to award ITB#15-6393 for the Traffic Signal Upgrade at
the intersection of Golden Gate Parkway and Tropicana Boulevard to Highway Safety Devices,
Inc., in the amount of$479,967.30 for Project#60172.
Meeting Date: 3/24/2015
Prepared By
Name: MillerJohn
Title:Project Manager, Traffic Operations
2/26/2015 8:59:35 AM
Submitted by
Title: Project Manager, Traffic Operations
Name: MillerJohn
2/26/2015 8:59:36 AM
Approved By
Name:NauthRookmin
Title: Management/Budget Analyst,Transportation Administration
Date: 2/26/2015 10:40:53 AM
Name: BathonDale
Title:Project Manager, Principal,Transportation Engineering&Construction Management
Date: 2/27/2015 5:47:01 AM
Name: LynchDiane
Title: Supervisor-Operations, Road Maintenance
Date: 2/27/2015 8:53:56 AM
Name: EvelynColon
Title: Purchasing-Procurement Specialist
Date: 2/27/2015 9:13:53 AM
Packet Page -513-
3/24/2015 16.A.12.
Name: KearnsAllison
Title: Manager Financial &Operational Support, Transportation Administration
Date: 3/3/2015 12:53:04 PM
Name: MarkiewiczJoanne
Title: Division Director-Purchasing& Gen Svc, Purchasing& General Services
Date: 3/3/2015 1:40:05 PM
Name: AhmadJay
Title: Division Director-Transportation Eng, Transportation Engineering&Construction Management
Date: 3/3/2015 2:52:10 PM
Name: KhawajaAnthony
Title: Chief Engineer-Traffic Operations, Traffic Operations
Date: 3/4/2015 5:29:38 PM
Name: JohnsonScott
Title: Manager-Procurement, Purchasing&General Services
Date: 3/6/2015 11:07:47 AM
Name: HerreraSandra
Title: Manager-Procurement,Purchasing&General Services
Date: 3/10/2015 11:40:39 AM
Name: TeachScott
Title: Deputy County Attorney, County Attomey
Date: 3/10/2015 4:51:45 PM
Name: LynchDiane
Title: Supervisor-Operations, Road Maintenance
Date: 3/10/2015 4:59:40 PM
Name: MarcellaJeanne
Title: Executive Secretary, Transportation Planning
Date: 3/11/2015 2:16:18 PM
Name: TeachScott
Title: Deputy County Attorney, County Attorney
Date: 3/16/2015 11:34:27 AM
Name: KlatzkowJeff
Title: County Attorney,
Date: 3/16/2015 12:59:28 PM
Packet Page -514-
3/24/2015 16.A.12.
Name: UsherSusan
Title: Management/Budget Analyst, Senior, Office of Management&Budget
Date: 3/16/2015 3:51:38 PM
Name: OchsLeo
Title: County Manager, County Managers Office
Date: 3/17/2015 9:44:40 AM
Packet Page -515-
John Mliler,eloped Manager 3/24/2015 16.A.12.
Submittals..3
15-6393,Golden Gate Parkway at Tropicana Boulevard Traffic Signal Upgrades
I American Lighting and Highway Safety Devices,inc I OnPower Services,LLC I
Signalization,Inc (Non-Responsive)
LINE NO.ITEM NO. DESCRIPTION QTY UNIT UNIT PRICE TOTAL UNIT PRICE TOTAL is 'UNIT PRICE -TOTALS
101-1 MOBILIZATION 1 LS S 80.000.00 $ 80.00U.00 S 45,00000 5 45.111011 t, _.
2 102-1 MAINTENANCE OF TRAFFIC I IS S 40,000.00 $ 4)1.000.00 $ 25,111111,00 $
3 110-1-1 CI FARING AND GRIR3BING 1 US S 55010.00 $ 55,01)0.00 S 1.550 00 A
72)1-0 EMBANKMENT 51 C.Y S 3000 S 1.53000 $ 33.00 S
327-711-1 MILLING EXISTING ASPIIAI.TIC PAVEMENT 1761 SY S 1100 S 19,37100 S 000 S
334-1-13 S111'ERPAVE:ASPHALTIC CONCRETE(A C.SP 95)(TRAFFIC C) 100 TN 5 60(1011 S 90,000.00 S 330.00 S
4311-174-218 1'IPE CULVERT VERT 52 IF S 150.00 $ 7.810.00 $ ?(10,1111 S
43)1-982-123 MITERED END SECTION 2 EA $ 1,500.(10 S 300)0))) 5 1,600 UU S
9 521)-1-10 CONCRETE('LIRA AND GIITIR TYPE F 386 IF S 30.0(1 5 11.580.00 S 6600 S 35.47600 - '
l0 5222 CONCRETE SIDEWALK AN)DRIVEWAYS-F"THICK 131 SY S 60.00 $ 7.860.00 5 86.0(1 S 1126600 i I
527-2 DETECTABLE WARNINGS 136 SF S 4000 5 5440.00 S 66.(1(1 S
32 570-1-2 PERFORMANCE TURF 402 SF S 11.00 $ 4,422,101 $ 6,6)1 S ,65120 ,1
590-711-1 IRRGATTON SYSTEM(REIf)CATION) 1 LS S 4010 00 S 4,1100 00 $ 3,750 00 5
030-2-11 CONDUn-(FURNISHED&INSTALL)(OPEN TRENCH) 544 IF S 6 011 5 4.35'00 A 19.00 $
15 6311--22-122 CONDUIT(FE IIRNI SHED&INSTALL)(DIRECT IONAI.BORE) 1387 U' $ 26.110 S 36,062,00 $ 16511 S
is 6327-1 SIGNAL CABLE-(FIIILMSH&INSTAI,I I 1 PI $ 9.1(00.1)0 $ 8000,011 S 0.400,((0 5 64)611)(7 3
17 633-1-111 ITS FB3ER OPTIC CABLE,12 STRAND FIBER OPTIC 1011 IF S 2,00 S 200 00 $ 250 S
5 613-1-122 ITS FIBER OPTIC CABLE,48 STRAND 17NER OPTIC IUI IF S 3.00 S 31)00 3.30 S 340110 - J=
6333-II IFS FIBER OPTIC CONNECTION HARDWARI:,SPLICE I EA S 1.22(10.0(1 S 1200011 S 1.350 00 S
zo 033-3-14 ITS FI13ER OPTIC CONNECTION HARDWARE,BLUFFER TUBE , 1 EA 5 00.00 $ 60.01) S 660(1 S
00 633-3-16 ITS FIBER OPTIC CONNECTION HARDWARE-FIBER PATCLI 1 FA S 1,400.00 5 1.400.01) $ 1.600 00 S
12 6352-I1 PI/1.1,&SPLICE BOXES(FURNISH&INSTALL,) 37 RA S 700 00 S 25.91)0.00 $ 595.01) $
23 039-1-121 ELECTRICAL SERVICE(FURNISH&INSTALL) I AS S 1,801)1)(1 S 1,8110.00 S 1.900.00 S
63921 ELECTRICAL SERVI CE WIRE.(FI IRNSI I&INS'FALL1 220 IF S 4.1)0 5 880,00 S 5.9(1 A
21 030.312 Fl ECTRIC AL SERVICE DISCONNECT(F&I)(CABINEI I I PA $ 210101) $ 200,110 5 215110 $ "15110 dd
fi41-22-12 PRESTRESSED CONCRETE POLE(FURNI.SII&INS'FAl-I.) 1 EA 5 7(10111) S 71111.00 S 625.110 S
zs 27 940-1-11 ALUMINUM SIGNAL POI E(Pl)RNISII&INSTALL) 0 EA 5 750.10) S 6,75010) 5 1,1011.00 A 9,90)1.00 1
2e 05111311 TRAFFIC SIGNAL(PLBRNISH&INS)All.1(3 SECTION)(1-WAY) 7 AS $ 800.00 S 9,0)0.110 $ 775.111 5 5,425110 1
650-1-411 TRAFFIC SIGNS)(FURNISH&INSTALL)(4 SECTION)(I-WAY) 4 AS $ 1,101100 S 4)100.00 $ 1.)00.0(1 $
653-191 PEDESTRIAN SIGNAL(FURNISH A INSTALL)(LED) 6 AS S 5)11.0(1 S 3,)1011.0(1
$ 495.00 5
3t 653-192_ PEDESTRIAN SIGNAL(FURNISH&INSTALL)(LED) 3 AS S 1.000.0) $ 3.)101.)1
$ 1.000.00 S 3,00000
32 66(1-1-0)5 LOOP DETECTOR 7 EA S (211011 S 84000
5 130,00 $
33 0611--2-106 IDOP ASSEMBLY,TYPE F 7 AS S 800.00 S 5,6)10.01 $ 1.101-00 S 7,701(115 I,'
060-3-11 VEI-0(.LF DETECTOR CABINET 1 AS S 6,)1011011 S 6000111/ $ 1200.00 $ 12)1110)
34 660-312 VEI IICLF DETECTOR ABOVE GERUND 2 EA S 5,0(10,(0( S 1(1,)100.10 $ 8,300.011 5 (661)1100 '
6
,0.'4-14 VBHIC.IC DETECTOR PRE EMPF 4 PA $ 2,5(11)10) S 10.000.00 $ 3,0011-00 5 12110000 {'
31-.--_095-1-11 PEDESTRIAN DETECTOR 10 EA S 22)100(1 A 2,0(31(X1 $ 315.00 F
670-5-112 TRAFFIC CONTROLLE7R ASSEMBLY(FNRNRH&INSTALL) I EA S 19,1100.110 5 19,0(10.00 S 2222,51)0011 S
082-1-13 ('CIV CAMERA DOME ENCIOSURE I LA 5 7,5(1)1(01 6 7,500.00 $ 5.500.00 5
00 6841-1 ITS MANAGED FIELD EP IERNF I SW1'I CIi,FM I EA 5 2.300 00 S 2,300.00 S 2,6110.((0 S
al 685-106 SYSTEM AIIXIIAARIES,FAL IININTERRUPDBLE PO WEID 1 FA S 9,5011.00 S 9,500,10) S 11300.111) S I 1 30000 `.t i
az 685-141) .SYSTEM AUXILIARIES(FIBER-0011C MOD111/DF,MOD)IL) I EA S 3000.011 $ 3.10)/00 S 25011/111 S
6911-10 REMOVE TRAFFIC SIGNAL IlliAD 8 EA 5 1(111.00 $ 800.00 S 35.5(1 S
as 090 (REMOVE PEDESTIAN SIGNAL. 4 LA S 5(100 $ 201).0(1 $
112 3350 5
03 6911-31 REMOVE SIGNAL PEDESTAL. 4 FA 5 200.00 S 801100 $ 87,0)) $ 3480(1 J
00 69)-32-1 POLE REMOVAL SHALLOW 4 PA $ 3.500 00 $ 14.0(10.00 S 1,050.011 5 7.8UU.U11 fI
42 090-51 REMOVE CON'ROI I.FR I EA 5 31)0.00 5 3011011 $ 260011 S
as 0911-711 REMOVE,PEDESTRIAN DETECTOR 4 EA A 40.00 S 161100 $ 29.00 $ (16 00 )
49 6911-8)) REMOVE SPAN WIRE 1 PI S 101)1100 S 1,11(111.00 $ 405011 S
so 690-90 REMOVE CABLE CONDUIT I I PI S 200.00 S 200.110 S 695(0) 5 69600 -
69090 REMOVE MISC I PI S 1,500.00 S 1,501).111 5 350110 S 3511.)11 "I 1
090-1-01 INTFIRNAILY II AIMINA'H:1)SIGN 4 FA S 3,000.00 $ 8,)10000 S 3,3511.011 $ 04)6)01)
710-1-11 SINGLE POST SIGN 8 AS 5 45000 $ 3,600.00 $ 550.011 $ 44(10.00 { I
54 7111148-18 SIGNI'ANEI,MAST ARM MOUNT(INS1-ALI,1 4 AS S 4101011 $ 1,61)11110 $ 4411.0(1 $ 1,761101) .j- i
710-I1=911 THERMOPLASTIC,STANDARD.YELLOW.ISIAN)NOSE 122 SP S 3.00 $ 36600 S 2 00 S
710-11-1711 PAVEMENT ARROWS 2 FA S 150.00 $ 30000 $ 86,00 S 172.11(1 l:
711-15-111 THERMOPLASTIC.STANDARD.WHITE 901.31),6" 11.1)3 NM $ 901111.00 $ 270.00 $ 01))(L00 S
711-11-123 THERMOPLASTIC',STANDARD_WRITE,SOI O),12" 505 IF $ 600 $ 3.390 00 $ 3.311 $ LNG4.5) 1-
s9 _711-11-124 'IHERMOPLAS'D('.,STANDARD,WHITE,SOLID,21" 570 U $ 7.011 $ 3,990.00 S 6611 $ 3,7621111 I 1
711-11-151 THERMOPLASTIC.HOT SPRAY,WIB7L GUIDELINE 0" 115 II $ 9 0)) $ 345.011 $ 2-711 S 311)50 1 r.
so 711-11-251 TNFRMOI'IASTIC,HOT SPRAY,YFI.13)W,GUIDELINE 6" 191) lF $ 3.110 $ 5711.0)
$ 2.70 $
715-11400 LIGHT POLE RELOCATE I AS $ 50111)1111 $ 5,01)0110 S 4350.00 $ 4,350.10)
1 x w "' 1.- .$;, 9 -4"v 3 S t *'" is I :.,1 ne t 2i "' `$ 1 41"' k;..,+ 3'''�4 ai `' 2 r r 3 ,. 1,� 6' fi I.
E }"t ±�1 k€lh
1 v'' ., ya) tii a r r•ry,1 y,* " r 1 "'il.I 5. 't zt 4'a#'Z2g %;',-, .,;;,s-,,,,,,,,R�JEC ','i' a 5"l '` 'k ,,X,','LIaTECT'„r?r,:,.,-"")'": Y a `N.:', ,PROJECT
63.-' ,N",':'1,10. `-'6°,,,,',"-P447:.-1,5'; _ TOTAL $=;1 525538.00 ,TOTAL-= S;400,5i)30' ,TOTAL V$
Alternate A-Most Arm Assemhl3(Not Painter((
049-3)-112- S'FEEL MAST ARM ASSFMBI,Y IDOIIBLE ARM 2 FA $ 42)1110.III) 5 8411110,00 5 35,700.00 $
Total Alternate >t Total Alternate 1'
A `! $ .609,538.00 " - .,A $'471,967.30 Total Alternate $
Alternate R-Most Arm Assemhlr (Painted)
049-31-112 STEEL.MAST ARM ASSEMBLY D011BIE ARM 2 EA S 47,)10000 5 94.1)0).00 S 39.700.00 5 ''94000(1 I
Total Alternate--, Total Alternate 4% t
5 `619 538.00 A '' 1 B .: S 479,96730; Total Alternate $
Construction Bid Form yes Yes
Material Manufacturers Form Yes Yes
List of Mapor Subcontractors Yes Yes
Statement of Experience Yes Yes
I rench Safety Act Yes Yes
Local Vendor Preterence Affidavit Yes Yes
Immigration Affidavit-Signed and Notarized Yes Yes
Solicitations Substitute W-9-Signed and Notarized Yes Yes
_Bid Bond-Signed and Seal Yes Yes
bidder's Checklist Yes Yes
'Revised bid Schedule No Yes
Addendum 1 Yes Yes
Addendum 2 Yes yes
Addendum 3 yes Yes
Addendum 4 Yes Yes
Opened by:Jason Crouch,Procurement Strategist
Witnessed by:Evelyn Colon,Procurement Strategist