GG MSTU Minutes 10/17/2017 - , 1
GOLDEN GATE M.S.T.U. ADVISORY
1M M I7EE
3299 East Tamiami Trail, Suite 103
Naples, FL 34112
MINUTES
I. Call to Order
The meeting was called to order at 4:30 P.M. by Ms. Spencer. Attendance was called and a quorum was
established.
II. Attendance: Patricia Spencer, Chairman; Herman Haeger, Vice Chairman; Ron Jefferson;
Paula Rogan; Dusty Holmes
County: Dan Schumacher, Project Manager; Harry Sells, Project Manager
Others: Janet Acevedo, Hannula Landscaping; Dale Hannula, Hannula Landscaping; Wendy Warren,
Jurisolutions
III. Pledge of Allegiance
The Pledge of Allegiance was recited.
IV. Approval of Agenda
Ms. Spencer moved to approve the Agenda of the Golden Gate Advisory Committee as submitted.
Second by Mr. Haeger. Carried unanimously 5- 0.
V. Approval of Minutes: July 18,2017
Mr. Haeger moved to approve the minutes of the July 18, 2017 meeting as presented. Second by Ms.
Spencer. Carried unanimously 5- 0.
VI. Landscape Maintenance Report—Hannula Landscaping & Irrigation
Ms. Acevedo reported on landscape maintenance as follows:
General
• Regular maintenance is on schedule.
• Plant material scheduled for replacement, except for Perennial Peanut, was deferred due to
Hurricane Irma preparation.
• Tree pruning in conformance with the annual landscape contract, reduced hurricane tree damage.
• Stump removal will be addressed.
1
• A proposal for plant/tree removal and replacement will be submitted based on an inventory
analysis by Mr. Schumacher and Ms. Acevedo.
Mr. Sells reported on Hurricane Irma Recovery as follows:
• An MSTU Plan for Hurricane Irma Recovery was drafted on September 13, 2017 highlighting.
1. Evaluate situation as soon as safely possible. First week(Sept. 11th— 17th).
2. Evaluate remaining landscape with landscaper. Weeks 2-3 (Sept. 18th—Oct. 1st)
3. Evaluate remaining landscape. Weeks 4—24 (Oct. 2, 2017—Feb. 26, 2018).
4. File claim for damage as soon as actual costs are known(deductible waived by County).
• Phases I&2 of the plan are complete.
• Two million dollars has been allocated to road maintenance and MSTU clean up (replacement
not included).
• FEMA contractors remove debris and take down trees but do not replace material.
• Inspectors observe and record the FEMA contractors' performance.
• Landscaping will be evaluated and replacement decisions made over the next six months.
During Committee discussion the following was noted:
• Hannula Landscaping removes hurricane debris in MSTU medians.
• FEMA will be billed for the purchase order generated to fund Hurricane Irma debris removal.
• Uncollected funds billed to FEMA will be submitted as an insurance claim by Collier County.
• Collier County is currently financing the hurricane recovery costs from Fund 111.
• The Parks and Recreation Department is responsible for hurricane debris and tree removal and
pruning at Golden Gate Community Center. Safety concerns should be reported to Steve
Cornell, Director, Public Services Department.
• Traffic Operations is responsible for replacing street signs. Due to the significant number of
damaged signs the estimated time frame for total replacement is three plus months.
• Street light outages should be reported to Florida Power&Light. The location and/or pole
number should be included in the report.
VII. Landscape Architect's Report—McGee and Associates
A. Maintenance Reports
A report was not submitted for October 2017.
VIII. Project Manager's Report
A. Nomination of Officers
Mr. Schumacher distributed Patricia Spencer's and Florence Holmes' applications for re-
appointment to the Golden Gate Advisory M.S.T.U. Committee.
Patricia Spencer and Florence (Dusty) Holmes expressed their desire to be reappointed to the
Golden Gate M.S.T.U. Advisory Committee noting their meeting participation has been consistent.
Mr. Haeger moved to recommend the Board of County Commissioners appoint Patricia Spencer and
Florence Holmes to the Golden Gate M.S.T.U. Advisory Committee for a four year term commencing
October 7, 2017. Second by Mr. Jefferson. Carried unanimously 5- 0.
B. Budget Report
Mr. Schumacher summarized the Golden Gate MSTU Fund Budget 153 dated October 17, 2017
noting:
2
a. Monthly Report
• FY18 Ad Valorem property tax revenue budget is $376,900.00, an increase of 11.88%.
• Total revenue FY18 is $735,800.00 including investment interest,transfers and
contributions (minus a 5%reserve of$18,900).
• The Millage rate is 0.5000.
• FY18 planned Operating Expense Budget is $340,800. Current commitments total
$94,400.
• Uncommitted Operating Expense funds available are $246,400.
• A purchase order was created for Hannula Landscaping for Hurricane Irma debris pick-up.
It is anticipated costs will be reimbursed by FEMA at a rate of 85% - 100%.
• Improvements General Fund of$345,200. (Line 31)is reserved to finance special projects
subject to review and approval of the County accounting office.
• Total available balance less committed expenses totals $641,400.
C. Irrigation Status
Mr. Sells reported as follows:
a. Coronado & Hunter Design—Conduits for Bid
A"Request for Quote"was distributed to qualified bidders for installation of the irrigation
control system valve wiring and conduits on Coronado Parkway and Hunter Boulevard utilizing
HydroPoint controls.
One vendor, Superior Landscaping, submitted a proposal for the project at a cost of$159,000.;
$29K higher than Staff's estimate. The M.S.T.U. has three courses of action:
• Accept the bid.
• Reject the bid.
• Re-bid the project.
During Committee discussion the following was addressed:
• Re-bidding the project may result in a six week delay in the start date.
• The start date is negotiated with the contractor. Typical time frame is one month from
contract execution with an estimated completion time of six months.
Ms. Holmes motioned to redistribute the "Request for Quote"for the Coronado Parkway and
Hunter Boulevard irrigation control system valve wiring and conduit project to qualified bidders.
Second by Mr. Jefferson. Carried unanimously S—0.
D. MSTU Priorities to Commissioner Saunders
Mr. Schumacher distributed a recap of the Golden Gate Beautification M.S.T.U. Advisory
Committee's Priorities submitted to Commissioner Saunders. Installation of sidewalks and
enhanced lighting were identified as important improvements.
The Committee discussed the suggested projects and agreed to pursue lighting for the commercial
district.
Ms. Spencer requested members present recommendations and ideas for a"lighting enhancement
project" for Golden Gate City at the November meeting.
3
E. Quotes
JuriStaff
Mr. Schumacher distributed JuriStaff s contract 14-6214 "Temporary Clerical Services" for the
Golden Gate MSTU for transcription services FY-18.
Ms. Spencer motioned to approve the JuriStaff contract number 14-6214 "Temporary Clerical
Services"for Fiscal Year 2018. Second by Mr. Haeger. Carried unanimously 5—0.
McGee & Associates
Mr. Schumacher distributed the proposal from Mike McGee, McGee &Associates, Landscape
Architecture, for contract renewal for"Annual Services for Landscape Architectural Maintenance
Consulting Services for Golden Gate MSTU Advisory Committee" for consideration and a
spreadsheet analysis of category costs.
The Committee discussed the contract which defines Maintenance Consulting Services totaling
$27,720 noting:
• The contract proposal cost is 1.1%higher than 2016; CPI (Consumer Price Index) for 2017
is tracking at 2.2%.
• The report provides historical data for the M.S.T.U. and a guideline of issues to be addressed
for the landscape contractor
• The water, Golden Gate Parkway and 951 reports can be excluded from the monthly
summary at the discretion of the Committee.
Staff noted Mr. McGee's contract proposal is within budget and a purchase order will be issued on
Committee approval to renew.
Mr. Haeger motioned to approve renewal of McGee&Associates,Landscape Architecture,
Contract number 16-6598, "Fixed Term Landscape Architectural Services', in the amount of
$27,720.00 for Annual Services for Landscape Architectural Maintenance Consulting Services
for Golden Gate Beautification MSTU effective October 1, 2017 through September 30, 2018.
Second by Ms. Holmes. Carried unanimously 5-0.
IX. Old Business
A. Canal Bridge Fencing(Golden Gate Parkway)
Mr. Schumacher presented an update of the canal bridge project as follows:
• County representatives advised irrigation is not feasible due to lack of pressure in the water
line.
• Plants should not be installed without irrigation provision.
Mr. Schumacher is investigating alternative fencing materials to aesthetically enhance the bridge
fencing.
B. Santa Barbara and Golden Gate Refurbishment Status
Mr. Schumacher updated the Committee on the County refurbishment project as follows:
• Current irrigation in the vicinity cannot be"tapped"to water the area.
• The project is being re-designed to accommodate tree placement thirty feet from the roadway
to prevent potential blockage from downed trees in the future.
• The new design specifications incorporate routing irrigation to the area,potentially a positive
impact to M.S.T.U. assets.
4
• The Countyis in theprocess of securingbids for the project.
X. New Business
A. Stormwater Update
Mr. Schumacher distributed a Golden Gate City stormwater improvements grid map
demonstrating the quadrant designated for construction. Replacement of existing Corrugated
Metal Pipe (CMP)with Reinforced Concrete Pipe (RCP)will benefit the M.S.T.U. area currently
prone to wash outs.
XI. Public/Board Comments
Santa Barbara and 55th Street Project
Mr. Schumacher will update the Committee on an estimated completion date for the County project
at a future meeting.
Light Pole Replacement Bulbs
Mr. Schumacher is researching light bulb replacement options and securing pricing for LED's.
Canal Hurricane Irma Vegetation
Ms. Spencer reported Australian Pines toppled by Hurricane Irma are in the canals and was advised
the County will be removing them. Ms. Holmes noted the Green Canal has been cleared.
Light Pole Damaged by Auto Accident
Ms. Holmes reported a light pole was hit by an automobile on Sunshine Boulevard.
Mr. Schumacher stated Hart's Electrical removed the fixture and sealed the box. Hart's initial
proposal for replacement is $5 - $6K.
Mr. Schumacher requested Ms. Sillery research documentation of the incident. The vehicle driver's
insurance company is liable for damage. An insurance claim with a$500 deductible can be filed with
the County if a police report is not located.
November Meeting
The November meeting will commence at 4:00 pm to enable a workshop discussion for the proposed
lighting project.
There being no further business to come before the Committee, the meeting was adjourned
by the Chair at 5:45 P.M.
GOLDEN GATE MSTU ADVISORY COMMITTEE
•
Patricia Spencer,Chairman
The Minutes were approved by the Committee on N OY YI(3 l , 2017 as presented lX
or as amended
NEXT MEETING: NOVEMBER 21,2017—4:00 PM
GOLDEN GATE COMMUNITY CENTER
4701 GOLDEN GATE PARKWAY
NAPLES,FL 34116
5