Loading...
Agenda 12/12/2017 Item #16A 312/12/2017 EXECUTIVE SUMMARY Recommendation to approve and authorize the Chair to execute Contract Number 16-7010, “Design and Related Services for CR-846/ Immokalee Rd over Gator Canal Bridge Replacement or Rehabilitation (Bridge Number 030160)” in the amount of $326,991.00 with T.Y. Lin International (Project No. 66066). _____________________________________________________________________________________ OBJECTIVE: To obtain professional engineering design and related services for the replacement or rehabilitation of bridge number 030160 on CR 846/Immokalee Rd. over the Gator Canal to maintain a safe and reliable public transportation route. CONSIDERATIONS: After considering the bridge inspection reports and condition letters received from the Florida Department of Transportation (FDOT), the existing condition of the timber foundations, the year of construction (1955), widening previously performed (1977), and previous pile repair history, bridge replacement or rehabilitation was determined to be necessary. At the January 10, 2017 meeting, the Board accepted the selection committee’s ranking and authorized staff to negotiate a contract with T.Y. Lin International (Agenda Item 16.A.5). This contract will allow staff to obtain the professional engineering design and related services necessary to develop construction plans and related documents for the replacement or rehabilitation of the bridge. During the design phase, staff will continue to monitor the condition of the bridge and take additional temporary measures, as necessary, to maintain the serviceability of the structure until it is replaced or refurbished under a subsequent construction contract. The attached contract was reviewed and approved by the County Attorney. FISCAL IMPACT: Funds in the amount of $326,991.00 are available within the Transportation Gas Tax Supported Fund (313) Bridge Project No. 66066 for the design and engineering services of the Gator Canal Bridge (#030160). The construction project is planned for the later part of FY19, with an expected cost of $3.5 to $4.5 million. The bridge replacement has been approved by the Board as part of the five year Capital Improvement Plan (CIP). Post-construction, reconstructed bridges are expected to have minimal to no maintenance costs during the first 5 to 7 years of service. Future maintenance costs will be absorbed into the regular maintenance schedule thereafter within the Road and Bridge Maintenance Fund (101). GROWTH MANAGEMENT IMPACT: The project is in conformance with the goals and objectives of the Transportation Element of the Growth Management Plan. LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority vote for Board approval. -SRT RECOMMENDATION: Recommendation to approve and authorize the Chair to execute Contract Number 16-7010, “Design and Related Services for CR-846/ Immokalee Rd over Gator Canal Bridge Replacement or Rehabilitation (Bridge Number 030160)” in the amount of $326,991, with T.Y. Lin International. Prepared by: Mario A. Puente, P.E., Sr. Project Manager, Transportation Engineering Division, Growth Management Department ATTACHMENT(S) 1. [Linked] 16-7010 TYLI_Contract_VendSign (137 Pages) (PDF) 12/12/2017 COLLIER COUNTY Board of County Commissioners Item Number: 16.A.3 Doc ID: 3990 Item Summary: Recommendation to approve and authorize the Chair to execute Contract Number 16-7010, “Design and Related Services for CR-846/ Immokalee Rd over Gator Canal Bridge Replacement or Rehabilitation (Bridge Number 030160)” in the amount of $326,991.00, with T.Y. Lin International (Project No. 66066). Meeting Date: 12/12/2017 Prepared by: Title: – Transportation Engineering Name: Mario Puente 10/18/2017 12:16 PM Submitted by: Title: Division Director - Transportation Eng – Transportation Engineering Name: Jay Ahmad 10/18/2017 12:16 PM Approved By: Review: Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 10/20/2017 10:59 AM Procurement Services Evelyn Colon Additional Reviewer Completed 10/23/2017 2:19 PM Procurement Services Ted Coyman Additional Reviewer Completed 10/23/2017 4:31 PM Growth Management Department Diane Lynch Level 1 Reviewer Completed 10/24/2017 3:20 PM Transportation Engineering Jay Ahmad Additional Reviewer Completed 10/25/2017 8:16 AM Procurement Services Sandra Herrera Additional Reviewer Completed 11/03/2017 8:34 AM Growth Management Department Lisa Taylor Additional Reviewer Completed 11/06/2017 8:01 AM Transportation Engineering Andrew Miller Additional Reviewer Completed 11/06/2017 9:48 AM Procurement Services Swainson Hall Additional Reviewer Completed 11/06/2017 11:44 AM Growth Management Department Gene Shue Additional Reviewer Completed 11/07/2017 5:52 PM Road Maintenance Travis Gossard Additional Reviewer Completed 11/09/2017 12:44 PM Growth Management Operations Support Allison Kearns Additional Reviewer Completed 11/09/2017 4:42 PM Growth Management Department James French Deputy Department Head Review Skipped 11/12/2017 10:35 PM Growth Management Department Thaddeus Cohen Department Head Review Completed 11/14/2017 10:03 AM County Attorney's Office Scott Teach Level 2 Attorney Review Completed 11/17/2017 2:40 PM County Attorney's Office Scott Teach Level 3 County Attorney's Office Review Completed 11/17/2017 2:41 PM 12/12/2017 Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 11/17/2017 3:15 PM Office of Management and Budget Susan Usher Additional Reviewer Completed 11/20/2017 9:12 AM County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 11/30/2017 8:16 AM Board of County Commissioners MaryJo Brock Meeting Pending 12/12/2017 9:00 AM Atiq Alvi, PE. Vice Presidentvc Veronica Castro-Ciucio- Adminstrative AssistantJeffrey McCloskey - Project Accountant