Agenda 09/26/2017 Item #16G709/26/2017
EXECUTIVE SUMMARY
Recommendation to award Invitation to Bid No. 17-7126 - Immokalee Regional Airport Taxiway B
Rehabilitation to O-A-K/Florida, Inc. d/b/a Owen-Ames-Kimball Company for $971,013.74, and
approve and authorize the Chair to execute the contract (Project No. 33485).
OBJECTIVE: To rehabilitate the remaining section of Taxiway B at the Immokalee Regional Airport
(IMM) that was not rehabilitated during the Runway 9-27 project.
CONSIDERATIONS: The Airport Authority has been awarded a Federal Aviation Administration
(FAA) grant in the amount of $983,920 and a Florida Department of Transportation (FDOT) grant in the
amount of $42,350 to fund the rehabilitation of Taxiway B at IMM.
On April 18, 2017, the Procurement Services Division released notices of Invitation to Bid (ITB) No. 17-
7126 to 2,237 vendors for the IMM Taxiway B Rehabilitation. Vendors downloaded eighty-two (82) bid
packages and the County received five (5) bids on May 19, 2017. The attached Bid Tabulation,
summarized below, and the NORA shows the results of the bid. Pursuant to Procurement Ordinance
Section 12, Reserved Rights, the Bid Schedule was revised to eliminate line items 19 and the Allowance,
per the Grantor and Staff’s recommended prudent fiscal approach. A summary of the bids is as follows:
Contractors Total Bid Price
Owen Ames Kimball $971,013.74
Preferred Materials $1,061,233.00
Wright Construction $1,069,932.00
Cobb Site Development $1,192,906.00
General Asphalt $1,226,377.00
The basis of the revised award was confirmed and accepted by the lowest bidder. As such, Staff
recommends the award to O-A-K Florida, Inc. d/b/a Owen Ames Kimball Company in the amount of
$971,013.74, as the lowest, responsible and responsive bidder. The lowest qualified bid is 5.71% below
the engineer’s comparable cost estimate of $1,029,851.
The engineer’s opinion of probable cost, bid analysis and engineer's recommendation to award are
included as attachments to this item.
FISCAL IMPACT: The total estimated cost of this project, including engineering services and contract
administration during construction is $1,093,244. Funding in the amount of $1,093,244 will be
appropriated within Project 33485 supported by Federal FAA and State FDOT grant awards and a local
match transfer from Airport Capital Fund (496) Reserves, broken out as follows.
Federal Funding (FAA) $ 983,920
State Funding (FDOT) $ 42,350
County (Local Requirement) $ 66,974
GROWTH IMPACT: There is no growth impact associated with this Executive Summary.
LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority
vote for Board approval. -SRT
16.G.7
Packet Pg. 2980
09/26/2017
RECOMMENDATION: To award ITB No. 17-7126 for IMM Taxiway B Rehabilitation to O-A-K
Florida, Inc. d/b/a Owen-Ames-Kimball Company, and approve and authorize the Chair to execute
Contract No. 17-7126 in the amount of $971,013.74 with O-A-K and authorize the necessary budget
amendments.
Prepared by: Justin Lobb, Airports Manager, Airport Authority
ATTACHMENT(S)
1. [Linked] 17-7126 O-A-K_Agreement_VendSign (PDF)
2. 17-7126 NORA - Executed (PDF)
3. 17-7126 - Bid Tabulation (PDF)
4. 17-7126 - Engineer's Recommendation & Opinion of Probable Cost (PDF)
16.G.7
Packet Pg. 2981
09/26/2017
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.G.7
Doc ID: 3648
Item Summary: Recommendation to award Invitation to Bid No. 17-7126 - Immokalee Regional
Airport Taxiway B Rehabilitation to O-A-K/Florida, Inc. d/b/a Owen-Ames-Kimball Company (OAK)
for $971,013.74, and approve and authorize the Chair to execute the contract (Project No. 33485).
Meeting Date: 09/26/2017
Prepared by:
Title: Manager - Airport – Airport Authority
Name: Justin Lobb
08/18/2017 2:32 PM
Submitted by:
Title: Division Director - Operations Support – Growth Management Department
Name: Gene Shue
08/18/2017 2:32 PM
Approved By:
Review:
Capital Project Planning, Impact Fees, and Program Management Rookmin Nauth Additional Reviewer Completed 08/21/2017 9:37 AM
Procurement Services Opal Vann Level 1 Purchasing Gatekeeper Completed 08/21/2017 10:46 AM
Airport Authority Justin Lobb Additional Reviewer Completed 08/22/2017 12:06 PM
Board of County Commissioners Jim Flanagan Additional Reviewer Completed 08/22/2017 2:18 PM
Procurement Services Sandra Herrera Additional Reviewer Completed 08/23/2017 7:16 AM
Procurement Services Ted Coyman Additional Reviewer Completed 08/23/2017 4:25 PM
Growth Management Department Diane Lynch Level 1 Reviewer Completed 08/25/2017 2:50 PM
Growth Management Operations Support Allison Kearns Additional Reviewer Completed 08/27/2017 8:25 AM
Growth Management Department Gene Shue Additional Reviewer Completed 08/28/2017 4:10 PM
Procurement Services Swainson Hall Additional Reviewer Completed 09/08/2017 11:26 PM
Growth Management Department Diane Lynch Department Head Review Skipped 08/25/2017 2:50 PM
Growth Management Department Len Price Deputy Department Head Review Skipped 09/18/2017 8:45 AM
County Attorney's Office Scott Teach Level 2 Attorney Review Completed 09/18/2017 10:08 AM
Grants Kimberly Lingar Level 2 Grants Review Completed 09/18/2017 11:24 AM
County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 09/18/2017 12:48 PM
Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 09/18/2017 2:18 PM
16.G.7
Packet Pg. 2982
09/26/2017
Grants Therese Stanley Additional Reviewer Completed 09/19/2017 12:16 PM
County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 09/20/2017 11:54 AM
Board of County Commissioners MaryJo Brock Meeting Pending 09/26/2017 9:00 AM
16.G.7
Packet Pg. 2983
16.G.7.bPacket Pg. 2984Attachment: 17-7126 NORA - Executed (3648 : 17-7126 IMM Taxiway B Rehabilitation Construction)
17-7126 - Bid TabulationProcurement Strategist: Jim Flanagan No. of Notices: 2213IMM Taxiway B RehabilitationProject Manager: Justin Lobb No. of Downloads 825/19/2017No. of Bids Rec'd 5Bidder: Owen Ames Kimball Wright Construction Preferred Materials Cobb Site Development General AsphaltITEM NO. SPEC NO. ITEM DESCRIPTIONUNITSTOTAL QUANTITYUNIT PRICE TOTAL COST UNIT PRICE TOTAL COST UNIT PRICE TOTAL COST UNIT PRICE TOTAL COST UNIT PRICE TOTAL COST1 M-100.5.1 MOBILIZATION LS 1 $175,349.63 $175,349.63 $109,873.59 $109,874 $200,945.00 $200,945 $258,916.16 $258,916 $200,000.00 $200,0005 M-100.5.2 TEMP. ACCESS ROAD SY 3,350 $2.31 $7,738.50 $11.66 $39,061 $9.00 $30,150 $4.24 $14,204 $13.70 $45,8956 P-101-5.1 REMOVE ASPHALTIC CONCRETE PAVEMENT -FULL DEPTH SY 14,520 $1.80 $26,136.00 $9.13 $132,568 $4.75 $68,970 $4.81 $69,841 $12.75 $185,1307 P-101-5.1 PAVEMENT MILLING (0"-2") SY 115 $13.64 $1,568.60 $12.30 $1,415 $12.35 $1,420 $18.88 $2,171 $33.50 $3,8538 P-152-4.1 UNCLASSIFED EXCAVATION CY 250 $5.10 $1,275.00 $10.00 $2,500 $10.68 $2,670 $18.13 $4,533 $9.50 $2,3759 P-152-4.5 BORROW MATERIAL CY 2,000 $0.75 $1,500.00 $6.72 $13,440 $14.50 $29,000 $13.64 $27,280 $5.75 $11,50010 P-152-4.7 EMBANKMENT IN PLACE CY 2,000 $1.76 $3,520.00 $3.75 $7,500 $4.00 $8,000 $5.31 $10,620 $10.65 $21,30011 P-156-5.1E INSTALLATION AND REMOVAL OF SILT FENCE & INLET PROTECTION LS 1 $2,023.36 $2,023.36 $4,544.79 $4,545 $4,137.92 $4,138 $4,776.96 $4,777 $4,905.00 $4,90512 P-160-8.1 STABILIZED SUBGRADE (12") SY 15,620 $7.41 $115,744.20 $4.84 $75,601 $6.19 $96,688 $4.22 $65,916 $7.30 $114,02613 P-211-5.1 LIMEROCK BASE COURSE (6") SY 15,070 $9.31 $140,301.70 $11.19 $168,633 $9.40 $141,658 $10.33 $155,673 $11.55 $174,05914 P-401-8.1.1 BITUMINOUS SURFACE COURSE TON 3,500 $137.80 $482,300.00 $134.75 $471,625 $124.29 $435,015 $155.81 $545,335 $120.00 $420,00015 P-620-5.1.-1 YELLOW TAXIWAY MARKINGS WITH TYPE III BEADS SF 1,400 $1.11 $1,554.00 $7.90 $11,060 $6.45 $9,030 $4.42 $6,188 $2.45 $3,43016 P-620-5.1.-2 BLACK OUTLINE PAINT SF 2,800 $0.78 $2,184.00 $4.85 $13,580 $4.16 $11,648 $3.78 $10,584 $0.85 $2,38017 T-901-5.1 SEEDING1000 SF25 $110.87 $2,771.75 $333.02 $8,326 $306.90 $7,673 $256.72 $6,418 $1,150.00 $28,75018 T-904-5.1 SODDINGSY 2,700 $2.61 $7,047.00 $3.78 $10,206 $5.27 $14,229 $3.87 $10,449 $3.25 $8,77519 F-162-5.1 CHAIN LINK WILDLIFE DETERRENT FENCE LF 1600 $37.00 $59,200.00 $29.49 $47,184 $69.48 $111,168 $25.57 $40,912 $31.60 $50,560SUBTOTALSUBTOTAL $1,030,213.74 SUBTOTAL $1,117,116 SUBTOTAL $1,172,401 SUBTOTAL $1,233,818 SUBTOTAL $1,276,937ALLOWANCELS 1$120,000.00 $120,000 $120,000.00 $120,000 $120,000.00 $120,000 $120,000.00 $120,000 $120,000.00 $120,000TOTALTOTAL $1,150,214 TOTAL $1,237,116 TOTAL $1,292,401 TOTAL $1,353,818 TOTAL $1,396,937Completed Bid Form (solicitation page 12)YYYYYCompleted Bid Schedule (17‐7126 Bid Schedule)YYYYYCompleted Bid Forms: Material Manufacturers (solicitation page 14)YYYYY List of Major Subcontractors (solicitation page 15)YYYYY Statement of Experience of Bidder (soliciation page 16)YYYYY Trench Safety Act Acknowledgement (solicitation page 17)YYYYY E‐Verify Immigration Law Affidavit Certification (solicitation page 18)YYYYY Solicitations Substitute W‐9 (solicitation page 19‐22)YYYYY Bid Bond Form (solicitaiton page 23)Y Y Y Y/AIA Form Y Bidders Checklist (solitication page 24)YYYYY Florida Division of CorporationsYYYYYCompleted Grant Forms Buy American Certificate (Item 9 of Bidders Checklist on solicitation page 24)YYYYY Certification regarding Debarment (item 10 of Bidders Checklist on solicitation page 24)YYYYY Bid Opportunity List (Item 11 of Bidders Checklist on solicitation page 24)YYYYY DBE Assurance (item 12 of Bidders Checklist on solicitation page 24)YYYYY Schedule of DBE participation (Item 13 of Bidders Checklist on solicitation page 24)YYYYY Letter of Intente to perform as DBE (Item 14 of Bidders Checklist on solicitation page 24)YYYYY Conflict of Interest Certification (Item 15 of Bidders Checklist on solicitation page 24YYYYY Certification regarding Lobbying (Item 16 of Bidders Checkist on solicitation page 24)YYYYY Acknowledgement of Terms Conditions and Grant Clauses (Item 17 on solicitation page 24)YYYYY Insurance and Bonding Requirements (solicitation pages 41 and 42)YYYNYAcknowledgement ‐ Receipt of Addendum #1YYYYYAcknowledgement ‐ Receipt of Addendum #2YYYYYStrategist: Confirm validity w/FL Divisions of Corporations on‐lineY Y Y* *address not same Y YStrategist: Confirm Insurance and Bonding RequirementsYYYNYStrategist: CONFIRM ALL BID DOCUMENTS COMPLETED AND SIGNED:YYYYYNOTE: Items and quantity of spreadsheet are correct. Numeration of items is as was posted (1, 5-19) with no missing line-items. Spreadsheet Functioning reviewed and confirmed with Engineer 05/09/17 - Tim Parker/Hole Montes EngineeringOpened By: Jim FlanaganWitnessed by: Kris Lopez16.G.7.cPacket Pg. 2985Attachment: 17-7126 - Bid Tabulation (3648 : 17-7126 IMM Taxiway B Rehabilitation Construction)
16.G.7.dPacket Pg. 2986Attachment: 17-7126 - Engineer's Recommendation & Opinion of Probable Cost (3648 : 17-7126 IMM Taxiway B Rehabilitation Construction)
16.G.7.dPacket Pg. 2987Attachment: 17-7126 - Engineer's Recommendation & Opinion of Probable Cost (3648 : 17-7126 IMM Taxiway B Rehabilitation Construction)
APPENDIX B
IMM - REHABILITATION OF TAXIWAY B
ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST
MARCH 30, 2017
1 of 1
ITEM NO.SPEC NO.ITEM DESCRIPTION UNITS TOTAL
QUANTITY UNIT PRICE TOTAL COST
1 M-100.5.1 MOBILIZATION LS 1 $98,713.75 $98,714
2 M-100.5.2 TEMP. ACCESS ROAD SY 3,350 $12.00 $40,200
3 P-101-5.1 REMOVE ASPHALTIC CONCRETE PAVEMENT -FULL DEPTH SY 14,520 $5.00 $72,600
4 P-101-5.1 PAVEMENT MILLING (0"-2")SY 115 $4.50 $518
5 P-152-4.1 UNCLASSIFED EXCAVATION CY 250 $8.00 $2,000
6 P-152-4.5 BORROW MATERIAL CY 2,000 $12.00 $24,000
7 P-152-4.7 EMBANKMENT IN PLACE CY 2,000 $4.00 $8,000
8 P-156-5.1E INSTALLATION AND REMOVAL OF SILT FENCE & INLET PROTECTION LS 1 $3,000.00 $3,000
9 P-160-8.1 STABILIZED SUBGRADE (12")SY 15,620 $4.00 $62,480
10 P-211-5.1 LIMEROCK BASE COURSE (6")SY 15,070 $12.00 $180,840
11 P-401-8.1.1 BITUMINOUS SURFACE COURSE TON 3,500 $150.00 $525,000
12 P-620-5.1.-1 YELLOW TAXIWAY MARKINGS WITH TYPE III BEADS SF 1,400 $1.75 $2,450
13 P-620-5.1.-2 BLACK OUTLINE PAINT SF 2,800 $1.00 $2,800
14 T-901-5.1 SEEDING 1000
SF 25 $20.00 $500
15 T-904-5.1 SODDING SY 2,700 $2.50 $6,750
16 F-162-5.1 CHAIN LINK WILDLIFE DETERRENT FENCE LF 1600 $35.00 $56,000
17
Total $1,085,851
16.G.7.d
Packet Pg. 2988 Attachment: 17-7126 - Engineer's Recommendation & Opinion of Probable Cost (3648 : 17-7126 IMM
1
Construction Services Agreement: Revised 02132017
IMM Taxiway B Rehabilitation Construction
COLLIER COUNTY BID NO. 17-7126
COLLIER COUNTY, FLORIDA
Jim Flanagan, Procurement Strategist
Email: JimFlanagan@colliergov.net
Telephone: (239) 252 - 8946
Design Professional:
Hole Montes Engineering
2
Construction Services Agreement: Revised 02132017
TABLE OF CONTENTS
PUBLIC NOTICE ....................................................................................................................... 3
PART B - INSTRUCTIONS TO BIDDERS ................................................................................. 5
CONSTRUCTION BID ..............................................................................................................12
BID SCHEDULE .......................................................................................................................13
MATERIAL MANUFACTURERS ..............................................................................................14
LIST OF MAJOR SUBCONTRACTORS ..................................................................................14
STATEMENT OF EXPERIENCE OF BIDDER ..........................................................................16
TRENCH SAFETY ACT ............................................................................................................17
IMMIGRATION LAW AFFIDAVIT CERTIFICATION .................................................................18
COLLIER COUNTY SOLICITATIONS SUBSTITUTE W – 9 .....................................................19
BID BOND ................................................................................................................................23
BIDDERS CHECK LIST ...........................................................................................................24
CONSTRUCTION AGREEMENT..............................................................................................25
EXHIBIT A 1: PUBLIC PAYMENT BOND ................................................................................32
EXHIBIT A 2: PUBLIC PERFORMANCE BOND ......................................................................35
EXHIBIT B: INSURANCE REQUIREMENTS............................................................................38
EXHIBIT C: RELEASE AND AFFIDAVIT FORM ......................................................................42
EXHIBIT D: FORM OF CONTRACT APPLICATION FOR PAYMENT .....................................43
EXHIBIT E: CHANGE ORDER .................................................................................................44
EXHIBIT F: CERTIFICATE OF SUBSTANTIAL COMPLETION ...............................................45
EXHIBIT G: FINAL PAYMENT CHECKLIST ............................................................................47
EXHIBIT H: GENERAL TERMS AND CONDITIONS ................................................................48
EXHIBIT I: SUPPLEMENTAL TERMS AND CONDITIONS ......................................................75
EXHIBIT J: TECHNICAL SPECIFICATIONS ...........................................................................76
EXHIBIT K: PERMITS ..............................................................................................................77
EXHIBIT L: STANDARD DETAILS ..........................................................................................78
EXHIBIT M: PLANS AND SPECIFICATIONS ..........................................................................79
EXHIBIT N: CONTRACTOR’S KEY PERSONNEL ASSIGNED TO THE PROJECT ...............80
3
Construction Services Agreement: Revised 02132017
PUBLIC NOTICE
INVITATION TO BID
IMM Taxiway B Rehabilitation Construction
COUNTY BID NO. 17-7126
Sealed bids for the construction of Immokalee Airport Taxiway B Rehabilitation will be received
electronically until 2:30 P.M. LOCAL TIME, on the 19th day of May, 2017 on the County’s on-
line bidding system: www.colliergov.net/bid. All bids will be publicly opened and read
aloud. Any bids received after the time and date specified will not be accepted and shall be
returned unopened to the Bidder. The anticipated project budget is: $1,200,000.00.
A non-mandatory pre-bid conference shall be held at the Procurement Services Division,
Conference Room A, 3295 Tamiami Trail East (Bldg C2) – (please note new location) at
9:00 a.m. LOCAL TIME on the 28th day of April, 2017, at which time all prospective Bidders
may have questions answered regarding the Bidding Documents for this Project.
Bids shall be received on line by the Bid Date of May 19, 2017. No bid shall be considered
unless it is made on unaltered Bid forms which are included in the Bidding Documents. One
contract will be awarded for all Work. Bidding Documents may be examined on the Collier
County Procurement Services Division Online Bidding System website: www.colliergov.net/bid.
Copies of the Bidding Documents may be obtained only from the denoted website. Bidding
Documents obtained from sources other than the Collier County Procurement Services Division
website may not be accurate or current.
Each bid shall be accompanied by a certified or cashier’s check or a Bid Bond in an amount not
less than five percent (5%) of the total Bid to be retained as liquidated damages in the event the
Successful Bidder fails to execute the Agreement and file the required bonds and insurance
within ten (10) calendar days after the receipt of the Notice of Award. The Successful Bidder
acknowledges and agrees that it shall execute the Agreement in the form attached hereto and
incorporated herein.
The Successful Bidder shall be required to furnish the necessary Payment and Performance
Bonds, as prescribed in the General Conditions of the Contract Documents. All Bid Bonds,
Payment and Performance Bonds, Insurance Contracts and Certificates of Insurance shall be
either executed by or countersigned by a licensed resident agent of the surety or insurance
company having its place of business in the State of Florida. Further, the said surety or
insurance company shall be duly licensed and qualified to do business in the State of Florida.
Attorneys-in-fact that sign Bid Bonds or Payment and Performance Bonds must file with each
bond a certified and effective dated copy of their Power of Attorney.
In order to perform public work, the Successful Bidder shall, as applicable, hold or obtain such
contractor's and business licenses, certifications and registrations as required by State statutes
and County ordinances.
Before a contract will be awarded for the Work contemplated herein, the Owner shall conduct
such investigations as it deems necessary to determine the performance record and ability of
4
Construction Services Agreement: Revised 02132017
the apparent low Bidder to perform the size and type of work specified in the Bidding
Documents. Upon request, the Bidder shall submit such information as deemed necessary by
the Owner to evaluate the Bidder's qualifications.
The Successful Bidder shall be required to finally complete all Work within One Hundred Fifty
(150) calendar days from and after the Commencement Date specified in the Notice to Proceed.
The Owner reserves the right to reject all Bids or any Bid not conforming to the intent and
purpose of the Bidding Documents, and to postpone the award of the contract for a period of
time which, however, shall not extend beyond one hundred twenty (120) days from the bid
opening date without the consent of the Successful Bidder.
Dated this 18th day of April, 2017
BOARD OF COUNTY COMMISSIONERS
COLLIER COUNTY, FLORIDA
BY: /s/ Edward F. Coyman, Jr.
Director, Procurement Services Division
5
Construction Services Agreement: Revised 02132017
PART B - INSTRUCTIONS TO BIDDERS
Section 1. Definitions
1.1 The term "Owner" used herein refers to the Board of County Commissioners, or its duly
authorized representative.
1.2 The term "Project Manager" used herein refers to the Owner's duly authorized
representative and shall mean the Division Administrator or Department Director, as applicable,
acting directly or through duly authorized representatives.
1.3 The term "Design Professional" refers to the licensed professional engineer or architect
who is in privity with the Owner for the purpose of designing and/or monitoring the co nstruction
of the project. At the Owner’s discretion, any or all duties of the Design Professional referenced
in the Contract Documents may be assumed at any time by the Project Manager on behalf of
the Owner. Conversely, at the Owner’s discretion the Project Manager may formally assign any
of his/her duties specified in the Contract Documents to the Design Professional.
1.4 The term "Bidder" used herein means one who submits a bid directly to the Owner in
response to this solicitation.
1.5 The term "Successful Bidder" means the lowest, qualified, responsible and responsive
Bidder who is awarded the contract by the Board of County Commissioners, on the basis of the
Owner's evaluation.
1.6 The term "Bidding Documents" includes the Legal Advertisement, these Instructions to
Bidders, the Bid Schedule and the Contract Documents as defined in the Agreement.
1.7 The term "Bid" shall mean a completed Bid Schedule, bound in the Bidding Documents,
properly signed, providing the Owner a proposed cost for providing the services requir ed in the
Bidding Documents.
Section 2. Preparation of Bids
2.1 The Bids must be submitted on the standard form herein furnished by the Owner (pages
15 - 29 as bound in these Bidding Documents). By submitting a Bid, Bidder acknowledges and
agrees that it shall execute the Agreement in the form attached hereto and incorporated herein.
The Bidder shall complete the Bid and shall sign the Bid correctly. The Bid may be rejected if it
contains any omission, alteration of form, conditional bid or irregularities of any kind. Bids must
be submitted on www.colliergov.net/bid
Section 3. Bid Deposit Requirements
3.1 No Bid shall be considered or accepted unless at the time of Bid filing the same shall be
accompanied by a cashier’s check, a cash bond posted with the County Clerk, a certified check
payable to Owner on some bank or trust company located in the State of Florida insured by the
Federal Deposit Insurance Corporation, or Bid Bond, in an amount not less than 5% of the
bidder's maximum possible award (base bid plus all add alternates) (collectively referred to
herein as the "Bid Deposit"). The Bid Deposit shall be retained by Owner as liquidated damages
if the Successful Bidder fails to execute and deliver to Owner the unaltered Agreement, or fa ils
to deliver the required Performance and Payment Bonds or Certificates of Insurance, all within
ten (10) calendar days after receipt of the Notice of Award. Bid Bonds shall be executed by a
corporate surety licensed under the laws of the State of Florida to execute such bonds, with
6
Construction Services Agreement: Revised 02132017
conditions that the surety will, upon demand, forthwith make payment to Owner upon said bond.
Bid Deposits of the three (3) lowest Bidders shall be held until the Agreement has been
executed by the Successful Bidder and same has been delivered to Owner together with the
required bonds and insurance, after which all three (3) Bid Deposits shall be returned to the
respective Bidders. All other Bid Deposits shall be released within ten (10) working days of the
Bid Opening. No Bid including alternates, shall be withdrawn within one hundred and twenty
(120) days after the public opening thereof. If a Bid is not accepted within said time period it
shall be deemed rejected and the Bid Deposit shall be returned to Bidder. In the event that the
Owner awards the contract prior to the expiration of the one hundred twenty (120) day period
without selecting any or all alternates, the Owner shall retain the right to subsequently award to
the Successful Bidder said alternates at a later time but no later than one hundred twenty (120)
days from opening, unless otherwise agreed by the Procurement Director and the Successful
Bidder.
3.2 The Successful Bidder shall execute two (2) copies of the Agreement in the form
attached and deliver same to Owner within the time period noted above. The Owner shall
execute all copies and return one fully executed copy of the Agreement to Successful Bidder
within thirty (30) working days after receipt of the executed Agreement from Successful Bidder
unless any governmental agency having funding control over the Project requires additional
time, in which event the Owner shall have such additional time to execute the Agreement as
may be reasonably necessary.
Section 4. Right to Reject Bids
4.1 The Owner reserves the right to reject any and all Bids or to waive informalities and
negotiate with the apparent lowest, qualified Bidder to such extent as may be necessary for
budgetary reasons.
Section 5. Signing of Bids
5.1 Bids submitted by a corporation must be executed in the corporate name by the
president, a vice president, or duly authorized representative. The corporate address and state
of incorporation must be shown below the signature.
5.2 Bids by a partnership must be executed in the partnership name and signed by a
general partner whose title must appear under the signature and the official address of the
partnership must be shown below said signature.
5.3 If Bidder is an individual, his or her signature shall be inscribed.
5.4 If signature is by an agent or other than an officer of corporation or general partner of
partnership, a properly notarized power of attorney must be submitted with the Bid.
5.5 All Bids shall have names typed or printed below all signatures.
5.6 All Bids shall state the Bidder's contractor license number.
5.7 Failure to follow the provisions of this section shall be grounds for rejecting the Bid as
irregular or unauthorized.
7
Construction Services Agreement: Revised 02132017
Section 6. Withdrawal of Bids
Any Bid may be withdrawn at any time prior to the hour fixed in the Legal Advertisement for the
opening of Bids, provided that the withdrawal is requested in writing, properly executed by the
Bidder and received by Owner prior to Bid Opening. The withdrawal of a Bid will not prejudice
the right of a Bidder to file a new Bid prior to the time specified for Bid opening.
Section 7. Late Bids
No Bid shall be accepted that fails to be submitted prior to the time specified in the Legal
Advertisement.
Section 8. Interpretation of Contract Documents
8.1 No interpretation of the meaning of the plans, specifications or other Bidding Documents
shall be made to a Bidder orally. Any such oral or other interpretations or clarifications shall be
without legal effect. All requests for interpretations or clarifications shall be in writing and
addressed on the County’s Online Bidding System to be given consideration. All such requests
for interpretations or clarification must be received as directed in the Online Bidding System
instructions and prior to the Bid opening date. Any and all such interpretations and
supplemental instructions shall be in the form of written addendum which, if issued via the
Online Bidding System at their respective email addresses furnished for such purposes no later
than three (3) working days prior to the date fixed for the opening of Bids. Such written
addenda shall be binding on Bidder and shall become a part of the Bidding Documents.
8.2 It shall be the responsibility of each Bidder to ascertain, prior to submitting its Bid, that it
has received all addenda issued and it shall acknowledge same in its Bid.
8.3 As noted in the Legal Advertisement, attendance by all bidders at the Pre-Bid
Conference is non-mandatory.
Section 9. Examination of Site and Contract Documents
9.1 By executing and submitting its Bid, each Bidder certifies that it has:
a. Examined all Bidding Documents thoroughly;
b. Visited the site to become familiar with local conditions that may in any manner affect
performance of the Work;
c. Become familiar with all federal, state and local laws, ordinances, rules, and regulations
affecting performance of the Work; and
d. Correlated all of its observations with the requirements of the Bidding documents.
No plea of ignorance of conditions or difficulties that may exist or conditions or difficulties that
may be encountered in the execution of the Work pursuant to these Bidding Documents as a
result of failure to make the necessary examinations and investigations shall be accepted as an
excuse for any failure or omission on the part of the Successful Bidder, nor shall they be
accepted as a basis for any claims whatsoever for extra compensation or for an extension of
time.
8
Construction Services Agreement: Revised 02132017
9.2 The Owner will make copies of surveys and reports performed in conjunction with this
Project available to any Bidder requesting them at cost; provided, however, the Owner does not
warrant or represent to any Bidder either the completeness or accuracy of any such surveys
and reports. Before submitting its Bid, each Bidder shall, at its own expense, make such
additional surveys and investigations as may be necessary to determine its Bid price for the
performance of the Work within the terms of the Bidding Documents. This provision shall be
subject to Section 2.3 of the General Conditions to the Agreement.
Section 10. Material Requirements
It is the intention of these Bidding Documents to identify standard materials. When space is
provided on the Bid Schedule, Bidders shall specify the materials which they propose to use in
the Project. The Owner may declare any Bid non-responsive or irregular if such materials are
not specifically named by Bidder.
Section 11. Bid Quantities
11.1 Quantities given in the Bid Schedule, while estimated from the best information
available, are approximate only. Payment for unit price items shall be based on the actual
number of units installed for the Work. Bids shall be compared on the basis of number of units
stated in the Bid Schedule as set forth in the Bidding Documents. Said unit prices shall be
multiplied by the bid quantities for the total Bid price. Any Bid not conforming to this requirement
may be rejected. Special attention to all Bidders is called to this provision, because if conditions
make it necessary or prudent to revise the unit quantities, the unit prices will be fixed for such
increased or decreased quantities. Compensation for such additive or subtractive changes in
the quantities shall be limited to the unit prices in the Bid. Subsequent to the issuance of a
notice to proceed, the Project Manager and the Successful Bidder shall have the discretion to
re-negotiate any unit price(s) where the actual quantity varies by more than twenty-five percent
(25%) from the estimate at the time of bid.
11.2 Alternate Bid Pricing: In the event that alternate pricing is requested, it is an expressed
requirement of the bid invitation to provide pricing for all alternates as listed. The omission of a
response or a no-bid or lack of a submitted price may be the basis for the rejection of the
submitted bid response.
Section 12. Award of Contract
12.1 Any prospective bidder who desires to protest any aspect(s) or provision(s) of the bid
invitation (including the form of the bid documents or bid procedures) shall file their protest with
the Procurement Director prior to the time of the bid opening strictly in accordance with Owner’s
then current procurement ordinance and policies.
12.2 Statement of Award: The Award of Contract shall be issued to the lowest, responsive
and responsible Bidder determined by the base bid, and any, or all, selected alternates, and the
Owner's investigations of the Bidder. In determining the lowest, responsive and responsible
bidder, the Owner shall consider the capability of the Bidder to perform the contract in a timely
and responsible manner. When the contract is awarded by Owner, such award shall be
evidenced by a written Notice of Award, signed by a Procurement professional of the Owner’s
Procurement Services Division or his or her designee and delivered to the intended awardee or
mailed to awardee at the business address shown in the Bid.
12.3 Award recommendations will be posted on the Procurement Services Division Web Site.
Award of Contract will be made by the Board of County Commissioners in public session. Any
9
Construction Services Agreement: Revised 02132017
actual or prospective bidder who desires to formally protest the recommended contract award
must file a notice of intent to protest with the Procurement Director within two (2) calendar days
(excluding weekends and holidays) of the date that the recommended award is posted. Upon
filing of said notice, the protesting party will have five (5) days to file a formal protest, said
protest to strictly comply with Owner’s then current procurement ordinance and policies. A copy
of the procurement ordinance is available at:
http://www.colliergov.net/Index.aspx?page=762
12.4 For Bidders who may wish to receive copies of Bids after the Bid opening, The Owner
reserves the right to recover all costs associated with the printing and distribution of such
copies.
12.5 Certificate of Authority to Conduct Business in the State of Florida (FL Statute
607.1501)
In order to be considered for award, firms must be registered with the Florida Department of State
Divisions of Corporations in accordance with the requirements of Florida Statute 607.1501 and
provide a certificate of authority (www.sunbiz.org/search.html) prior to execution of a contract. A
copy of the document may be submitted with the solicitation response and the document number
shall be identified. Firms who do not provide the certificate of authority at the time of response
shall be required to provide same within five (5) days upon notification of selection for award. If
the firm cannot provide the document within the referenced timeframe, the County reserves the
right to award to another firm.
Section 13. Sales Tax
13.1 The Successful Bidder acknowledges and agrees that Owner may utilize a sales tax
savings program and the Successful Bidder agrees to fully comply, at no additional cost to
Owner, with such sales tax savings program implemented by the Owner as set forth in the
Agreement and in accordance with Owner’s policies and procedures.
Section 14. Exclusion of County Permits in Bid Prices
14.1 To ensure compliance with Section 218.80, F.S., otherwise known as “The Public Bid
Disclosure Act”, Collier County will pay the Contractor for all Collier County permits and fees
applicable to the Project, including license fees, permit fees, impact fees or inspection fees
applicable to this Work through an internal budget transfer(s). Hence, bidders shall not include
these permit/fee amounts in their bid offer. However, the Successful Bidder shall retain the
responsibility to initiate and complete all necessary and appropriate actions to obtain the
required permits other than payment for the items identified in this section. Owner will not be
obligated to pay for any permits obtained by Subcontractors.
14.2 The Successful Bidder shall be responsible for procuring and paying for all necessary
permits not issued by Collier County pursuant to the prosecution of the work.
Section 15. Use of Subcontractors
15.1 To ensure the Work contemplated by the Contract Documents is performed in a
professional and timely manner, all Subcontractors performing any portion of the work on this
Project shall be “qualified” as defined in Collier County Ordinance 2017-08, as amended,
meaning a person or entity that has the capability in all respects to perform fully the Agreement
10
Construction Services Agreement: Revised 02132017
requirements and has the integrity and reliability to assure good faith performance. A
Subcontractor’s disqualification from bidding by the Owner, or other public contracting entity
within the past twelve months shall be considered by the Owner when determining whether the
Subcontractors are “qualified.”
15.2 The Owner may consider the past performance and capability of a Subcontractor when
evaluating the ability, capacity and skill of the Bidder and its ability to perform the Agreement
within the time required. Owner reserves the right to disqualify a Bidder who includes
Subcontractors in its bid offer which are not “qualified” or who do not meet the legal
requirements applicable to and necessitated by this Agreement.
15.3 The Owner may reject all bids proposing the use of any subcontractors who have been
disqualified from submitting bids to the Owner, disqualified or de-certified for bidding purposes
by any public contracting entity, or who has exhibited an inability to perform through any other
means.
15.4 Notwithstanding anything in the Contract Documents to the contrary, the Bidder shall
identify the subcontractor(s) it intends to use for the categories of work as set forth in the List of
Subcontracts attached hereto, said list to be submitted with its bid. Bidders acknowledge and
agree that the subcontractors identified on the list is not a complete list of the subcontractors to
be used on the Project, but rather only the major subcontractors for each category of Work as
established by Owner. Bidders further acknowledge that once there is an Award of Contract,
the Successful Bidder shall identify, subject to Owner’s review and approval, all the
subcontractors it intends to use on the Project. Once approved by Owner, no subcontractor
shall be removed or replaced without Owner’s prior written approval.
Section 16. Prohibition of Gifts
No organization or individual shall offer or give, either directly or indirectly, any favor, gift, loan,
fee, service or other item of value to any County employee, as set forth in Chapter 112, Part III,
Florida Statutes, Collier County Ethics Ordinance No. 2003-53, as amended, and County
Administrative Procedure 5311. Violation of this provision may result in one or more of the
following consequences: a. Prohibition by the individual, firm, and/or any employee of the firm
from contact with County staff for a specified period of time; b. Prohibition by the individual
and/or firm from doing business with the County for a specified period of time, including but not
limited to: submitting bids, RFP, and/or quotes; and, c. immediate termination of any contract
held by the individual and/or firm for cause.
Section 17. Lobbying
All firms are hereby placed on NOTICE that the Board of County Commissioners does
not wish to be lobbied, either individually or collectively about a project for which a firm
has submitted a response. Firms and their agents are not to contact members of the County
Commission for such purposes as meeting or introduction, luncheons, dinners, etc. During the
process, from solicitation closing to final Board approval, no firm or their agent shall contact any
other employee of Collier County in reference to this solicitation, or the vendor’s response, with
the exception of the Procurement Director or his designee(s). Failure to abide by this provision
may serve as grounds for disqualification for award of this contract to the firm.
Section 18. Public Entity Crimes
By its submitting a Bid, Bidder acknowledges and agrees to and represents it is in compliance
with the terms of Section 287.133(2)(a) of the Florida Statutes which read as follows:
11
Construction Services Agreement: Revised 02132017
"A person or affiliate who has been placed on the convicted vendor list
following a conviction for a public entity crime may not submit a bid,
proposal, or reply on a contract to provide any goods or services to a
public entity; may not submit a bid, proposal, or reply on a contract with a
public entity for the construction or repair of a public building or public
work; may not submit bids, proposals, or replies on leases of real property
to a public entity’; may not be awarded or perform work as a contractor,
supplier, subcontractor, or consultant under a contract with any public
entity; and may not transact business with any public entity in excess of
the threshold amount provided in s. 287.017 for CATEGORY TWO for a
period of 36 months from the date of being placed on the convicted vendor
list.”
Department of State /Division of Corporations /Search Records /Detail By Document Number /
Document Number
FEI/EIN Number
Date Filed
State
Status
Detail by Entity Name
Foreign Profit Corporation
OWEN-AMES-KIMBALL CO.
Filing Information
849848
38-0900420
07/28/1981
MI
ACTIVE
Principal Address
300 IONIA AVE N W
GRAND RAPIDS, MI 49503
Changed: 01/20/2004
Mailing Address
11941 FAIRWAY LAKES DR.
FT. MYERS, FL 33913-8338
Changed: 05/08/1992
Registered Agent Name & Address
DALE, DAVID J
11941 FAIRWAY LAKES DR.
FORT MYERS, FL 33913
Name Changed: 04/07/2008
Address Changed: 04/23/2015
Officer/Director Detail
Name & Address
Title PD
STANEK, FRANK
4676 WALKER RIDGE RD
KALAMAZOO, MI 49009
Title STD
LA BARGE, JOHN CJR
DIVISION OF CORPORATIONSFlorida Department of State
Page 1 of 3Detail by Entity Name
8/3/2017http://search.sunbiz.org/Inquiry/CorporationSearch/SearchResultDetail?inquirytype=Entity...
7264 TORY DR
HUDSONVILLE, MI 49426
Title VD
DALE, DAVID
3761 DOWNWIND LANE
NORTH FORT MYERS, FL 33917
Title D
SHIMP, KEVIN C.
14841 CALEB DRIVE
FORT MYERS, FL 33908
Annual Reports
Report Year Filed Date
2015 04/23/2015
2016 03/28/2016
2017 01/09/2017
Document Images
01/09/2017 -- ANNUAL REPORT View image in PDF format
03/28/2016 -- ANNUAL REPORT View image in PDF format
04/23/2015 -- ANNUAL REPORT View image in PDF format
04/22/2014 -- ANNUAL REPORT View image in PDF format
04/16/2013 -- ANNUAL REPORT View image in PDF format
03/29/2012 -- ANNUAL REPORT View image in PDF format
01/31/2011 -- ANNUAL REPORT View image in PDF format
03/22/2010 -- ANNUAL REPORT View image in PDF format
04/24/2009 -- ANNUAL REPORT View image in PDF format
04/07/2008 -- ANNUAL REPORT View image in PDF format
03/19/2007 -- ANNUAL REPORT View image in PDF format
04/04/2006 -- ANNUAL REPORT View image in PDF format
05/02/2005 -- ANNUAL REPORT View image in PDF format
01/20/2004 -- ANNUAL REPORT View image in PDF format
04/07/2003 -- ANNUAL REPORT View image in PDF format
03/24/2002 -- ANNUAL REPORT View image in PDF format
02/06/2001 -- ANNUAL REPORT View image in PDF format
02/08/2000 -- ANNUAL REPORT View image in PDF format
04/30/1999 -- ANNUAL REPORT View image in PDF format
04/03/1998 -- ANNUAL REPORT View image in PDF format
05/08/1997 -- ANNUAL REPORT View image in PDF format
03/28/1996 -- ANNUAL REPORT View image in PDF format
03/21/1995 -- ANNUAL REPORT View image in PDF format
Florida Department of State, Division of Corporations
Page 2 of 3Detail by Entity Name
8/3/2017http://search.sunbiz.org/Inquiry/CorporationSearch/SearchResultDetail?inquirytype=Entity...
13
Construction Services Agreement: Revised 02132017
BID SCHEDULE
IMM Taxiway B Rehabilitation Construction Bid No. 17-7126
"Also attached, hereto, following this page"
"Also attached hereto, following this page"
EXHIBIT I: SUPPLEMENTAL TERMS AND CONDITIONS
FAA GENERAL PROVISIONS
FEDERAL REQUIREMENTS
SPECIAL PROVISIONS
GENERAL PROVISIONS
GENERAL PROVISIONS
The following sections contain the General Provisions. Federal Aviation
Administration Standard Specifications for specifying of airports as found in FAA
Advisory Circular 150/5370-10G to be utilized on this project. The contractor is to
note the modifications made to the FAA general provisions. These modifications
appear in two forms:
Strikeout: Language shown in this manner is to be ignored and is not applicable
to the work.
Italics: Language shown in this manner is additional language, which is
relevant to, and is part of the contract documents specific to this
project.
Part 1 – General Provisions
Section 10 Definition of Terms ........................................................................................................ 1-4
Section 20 Proposal Requirements and Conditions ......................................................................... 5-8
Section 30 Award and Execution of Contract ................................................................................ 9-10
Section 40 Scope of Work ........................................................................................................... 11-14
Section 50 Control of Work ......................................................................................................... 15-20
Section 60 Control of Materials ................................................................................................... 21-24
Section 70 Legal Regulations and Responsibility to Public ........................................................ 25-30
Section 80 Execution and Progress .............................................................................................. 31-36
Section 90 Measurement and Payment ........................................................................................ 37-44
Section 100 Contractor Quality Control Program ........................................................................ 45-50
Section 105 Mobilization ............................................................................................................. 51-52
Section 110 Method of Estimating Percentage of Material Within Specification Limits (PWL) 53-58
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-1
Reference: AC 150/5370-10G (7/21/2014)
Part 1 – General Provisions
Section 10 Definition of Terms
Whenever the following terms are used in these specifications, in the contract, or in any documents or
other instruments pertaining to construction where these specifications govern, the intent and meaning
shall be interpreted as follows:
10-01 AASHTO. The American Association of State Highway and Transportation Officials, the
successor association to AASHO.
10-02 Access road. The right-of-way, the roadway and all improvements constructed thereon connecting
the airport to a public highway.
10-03 Advertisement. A public announcement, as required by local law, inviting bids for work to be
performed and materials to be furnished.
10-04 Airport Improvement Program (AIP). A grant-in-aid program, administered by the Federal
Aviation Administration (FAA).
10-05 Air operations area (AOA). For the purpose of these specifications, the term air operations area
(AOA) shall mean any area of the airport used or intended to be used for the landing, takeoff, or surface
maneuvering of aircraft. An air operation area shall include such paved or unpaved areas that are used or
intended to be used for the unobstructed movement of aircraft in addition to its associated runway,
taxiway, or apron.
10-06 Airport. Airport means an area of land or water which is used or intended to be used for the
landing and takeoff of aircraft; an appurtenant area used or intended to be used for airport buildings or
other airport facilities or rights of way; and airport buildings and facilities located in any of these areas,
and includes a heliport.
10-07 ASTM International (ASTM). Formerly known as the American Society for Testing and
Materials (ASTM).
10-08 Award. The Owner’s notice to the successful bidder of the acceptance of the submitted bid.
10-09 Bidder. Any individual, partnership, firm, or corporation, acting directly or through a duly
authorized representative, who submits a proposal for the work contemplated.
10-10 Building area. An area on the airport to be used, considered, or intended to be used for airport
buildings or other airport facilities or rights-of-way together with all airport buildings and facilities
located thereon.
10-11 Calendar day. Every day shown on the calendar.
10-12 Change order. A written order to the Contractor covering changes in the plans, specifications, or
proposal quantities and establishing the basis of payment and contract time adjustment, if any, for the
work affected by such changes. The work, covered by a change order, must be within the scope of the
contract.
10-13 Contract. The written agreement covering the work to be performed. The awarded contract shall
include, but is not limited to: Advertisement, Contract Form, Proposal, Performance Bond, Payment
Bond, any required insurance certificates, Specifications, Plans, and any addenda issued to bidders.
10-14 Contract item (pay item). A specific unit of work for which a price is provided in the contract.
10-15 Contract time. The number of calendar days or working days, stated in the proposal, allowed for
completion of the contract, including authorized time extensions. If a calendar date of completion is stated
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-2 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
in the proposal, in lieu of a number of calendar or working days, the contract shall be completed by that
date.
10-16 Contractor. The individual, partnership, firm, or corporation primarily liable for the acceptable
performance of the work contracted and for the payment of all legal debts pertaining to the work who acts
directly or through lawful agents or employees to complete the contract work.
10-17 Contractor’s laboratory. The Contractor’s quality control organization in accordance with the
Contractor Quality Control Program.
10-18 Construction Safety and Phasing Plan (CSPP). The overall plan for safety and phasing of a
construction project developed by the airport operator, or developed by the airport operator’s consultant
and approved by the airport operator. It is included in the invitation for bids and becomes part of the
project specifications.
10-19 Drainage system. The system of pipes, ditches, and structures by which surface or subsurface
waters are collected and conducted from the airport area.
10-20 Engineer. The individual, partnership, firm, or corporation duly authorized by the Owner to be
responsible for engineering observation and acceptance of the contract work and acting directly or
through an authorized representative.
10-21 Equipment. All machinery, together with the necessary supplies for upkeep and maintenance, and
also all tools and apparatus necessary for the proper construction and acceptable completion of the work.
10-22 Extra work. An item of work not provided for in the awarded contract as previously modified by
change order or supplemental agreement, but which is found by the Engineer to be necessary to complete
the work within the intended scope of the contract as previously modified.
10-23 FAA. The Federal Aviation Administration of the U.S. Department of Transportation. When used
to designate a person, FAA shall mean the Administrator or his or her duly authorized representative.
10-24 Federal specifications. The Federal Specifications and Standards, Commercial Item Descriptions,
and supplements, amendments, and indices thereto are prepared and issued by the General Services
Administration of the Federal Government.
10-25 Force account. Force account work is planning, engineering, or construction work done by the
Sponsor’s employees.
10-26 Inspector. An authorized representative of the Engineer assigned to make all necessary
inspections, observations and/or tests of the work performed or being performed, or of the materials
furnished or being furnished by the Contractor.
10-27 Intention of terms. Whenever, in these specifications or on the plans, the words “directed,”
“required,” “permitted,” “ordered,” “designated,” “prescribed,” or words of like import are used, it shall
be understood that the direction, requirement, permission, order, designation, or prescription of the
Engineer is intended; and similarly, the words “approved,” “acceptable,” “satisfactory,” or words of like
import, shall mean approved by, or acceptable to, or satisfactory to the Engineer, subject in each case to
the final determination of the Owner.
Any reference to a specific requirement of a numbered paragraph of the contract specifications or a cited
standard shall be interpreted to include all general requirements of the entire section, specification item,
or cited standard that may be pertinent to such specific reference.
10-28 Laboratory. The official testing laboratories of the Owner or such other laboratories as may be
designated by the Engineer. Also referred to as “Engineer’s Laboratory” or “quality assurance
laboratory.”
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-3
Reference: AC 150/5370-10G (7/21/2014)
10-29 Lighting. A system of fixtures providing or controlling the light sources used on or near the airport
or within the airport buildings. The field lighting includes all luminous signals, markers, floodlights, and
illuminating devices used on or near the airport or to aid in the operation of aircraft landing at, taking off
from, or taxiing on the airport surface.
10-30 Major and minor contract items. A major contract item shall be any item that is listed in the
proposal, the total cost of which is equal to or greater than 20% of the total amount of the award contract.
All other items shall be considered minor contract items.
10-31 Materials. Any substance specified for use in the construction of the contract work.
10-32 Notice to Proceed (NTP). A written notice to the Contractor to begin the actual contract work on a
previously agreed to date. If applicable, the Notice to Proceed shall state the date on which the contract
time begins.
10-33 Owner. The term “Owner” shall mean the party of the first part or the contracting agency signatory
to the contract. Where the term “Owner” is capitalized in this document, it shall mean airport Sponsor
only.
10-34 Passenger Facility Charge (PFC). Per 14 CFR Part 158 and 49 USC § 40117, a PFC is a charge
imposed by a public agency on passengers enplaned at a commercial service airport it controls.”
10-35 Pavement. The combined surface course, base course, and subbase course, if any, considered as a
single unit.
10-36 Payment bond. The approved form of security furnished by the Contractor and his or her surety as
a guaranty that the Contractor will pay in full all bills and accounts for materials and labor used in the
construction of the work.
10-37 Performance bond. The approved form of security furnished by the Contractor and his or her
surety as a guaranty that the Contractor will complete the work in accordance with the terms of the
contract.
10-38 Plans. The official drawings or exact reproductions which show the location, character, dimensions
and details of the airport and the work to be done and which are to be considered as a part of the contract,
supplementary to the specifications.
10-39 Project. The agreed scope of work for accomplishing specific airport development with respect to
a particular airport.
10-40 Proposal. The written offer of the bidder (when submitted on the approved proposal form) to
perform the contemplated work and furnish the necessary materials in accordance with the provisions of
the plans and specifications.
10-41 Proposal guaranty. The security furnished with a proposal to guarantee that the bidder will enter
into a contract if his or her proposal is accepted by the Owner.
10-42 Runway. The area on the airport prepared for the landing and takeoff of aircraft.
10-43 Specifications. A part of the contract containing the written directions and requirements for
completing the contract work. Standards for specifying materials or testing which are cited in the contract
specifications by reference shall have the same force and effect as if included in the contract physically.
10-44 Sponsor. A Sponsor is defined in 49 USC § 47102(24) as a public agency that submits to the FAA
for an AIP grant; or a private Owner of a public-use airport that submits to the FAA an application for an
AIP grant for the airport.
10-45 Structures. Airport facilities such as bridges; culverts; catch basins, inlets, retaining walls,
cribbing; storm and sanitary sewer lines; water lines; underdrains; electrical ducts, manholes, handholes,
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-4 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
lighting fixtures and bases; transformers; flexible and rigid pavements; navigational aids; buildings;
vaults; and, other manmade features of the airport that may be encountered in the work and not otherwise
classified herein.
10-46 Subgrade. The soil that forms the pavement foundation.
10-47 Superintendent. The Contractor’s executive representative who is present on the work during
progress, authorized to receive and fulfill instructions from the Engineer, and who shall supervise and
direct the construction.
10-48 Supplemental agreement. A written agreement between the Contractor and the Owner covering
(1) work that would increase or decrease the total amount of the awarded contract, or any major contract
item, by more than 25%, such increased or decreased work being within the scope of the originally
awarded contract; or (2) work that is not within the scope of the originally awarded contract.
10-49 Surety. The corporation, partnership, or individual, other than the Contractor, executing payment
or performance bonds that are furnished to the Owner by the Contractor.
10-50 Taxiway. For the purpose of this document, the term taxiway means the portion of the air
operations area of an airport that has been designated by competent airport authority for movement of
aircraft to and from the airport’s runways, aircraft parking areas, and terminal areas.
10-51 Work. The furnishing of all labor, materials, tools, equipment, and incidentals necessary or
convenient to the Contractor’s performance of all duties and obligations imposed by the contract, plans,
and specifications.
10-52 Working day. A working day shall be any day other than a legal holiday, Saturday, or Sunday on
which the normal working forces of the Contractor may proceed with regular work for at least six (6)
hours toward completion of the contract. When work is suspended for causes beyond the Contractor’s
control, it will not be counted as a working day. Saturdays, Sundays and holidays on which the
Contractor’s forces engage in regular work will be considered as working days.
END OF SECTION 10
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-5
Reference: AC 150/5370-10G (7/21/2014)
Section 20 Proposal Requirements and Conditions
20-01 Advertisement (Notice to Bidders).
20-02 Qualification of bidders. Each bidder shall furnish the Owner satisfactory evidence of his or her
competency to perform the proposed work. Such evidence of competency, unless otherwise specified,
shall consist of statements covering the bidder’s past experience on similar work, a list of equipment that
would be available for the work, and a list of key personnel that would be available. In addition, each
bidder shall furnish the Owner satisfactory evidence of his or her financial responsibility. Such evidence
of financial responsibility, unless otherwise specified, shall consist of a confidential statement or report of
the bidder’s financial resources and liabilities as of the last calendar year or the bidder’s last fiscal year.
Such statements or reports shall be certified by a public accountant. At the time of submitting such
financial statements or reports, the bidder shall further certify whether his or her financial responsibility is
approximately the same as stated or reported by the public accountant. If the bidder’s financial
responsibility has changed, the bidder shall qualify the public accountant’s statement or report to reflect
the bidder’s true financial condition at the time such qualified statement or report is submitted to the
Owner.
Unless otherwise specified, a bidder may submit evidence that he or she is prequalified with the State
Highway Division and is on the current “bidder’s list” of the state in which the proposed work is located.
Such evidence of State Highway Division prequalification may be submitted as evidence of financial
responsibility in lieu of the certified statements or reports specified above.
Each bidder shall submit “evidence of competency” and “evidence of financial responsibility” to the
Owner at the time of bid opening.
20-03 Contents of proposal forms. The Owner shall furnish bidders with proposal forms. All papers
bound with or attached to the proposal forms are necessary parts and must not be detached.
The plans, specifications, and other documents designated in the proposal form shall be considered a part
of the proposal whether attached or not.
20-04 Issuance of proposal forms. The Owner reserves the right to refuse to issue a proposal form to a
prospective bidder should such bidder be in default for any of the following reasons:
a. Failure to comply with any prequalification regulations of the Owner, if such regulations are cited,
or otherwise included, in the proposal as a requirement for bidding.
b. Failure to pay, or satisfactorily settle, all bills due for labor and materials on former contracts in
force with the Owner at the time the Owner issues the proposal to a prospective bidder.
c. Documented record of Contractor default under previous contracts with the Owner.
d. Documented record of unsatisfactory work on previous contracts with the Owner.
20-05 Interpretation of estimated proposal quantities. An estimate of quantities of work to be done
and materials to be furnished under these specifications is given in the proposal. It is the result of careful
calculations and is believed to be correct. It is given only as a basis for comparison of proposals and the
award of the contract. The Owner does not expressly, or by implication, agree that the actual quantities
involved will correspond exactly therewith; nor shall the bidder plead misunderstanding or deception
because of such estimates of quantities, or of the character, location, or other conditions pertaining to the
work. Payment to the Contractor will be made only for the actual quantities of work performed or
materials furnished in accordance with the plans and specifications. It is understood that the quantities
may be increased or decreased as hereinafter provided in the subsection 40-02 titled ALTERATION OF
WORK AND QUANTITIES of Section 40 without in any way invalidating the unit bid prices.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-6 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
20-06 Examination of plans, specifications, and site. The bidder is expected to carefully examine the
site of the proposed work, the proposal, plans, specifications, and contract forms. Bidders shall satisfy
themselves as to the character, quality, and quantities of work to be performed, materials to be furnished,
and as to the requirements of the proposed contract. The submission of a proposal shall be prima facie
evidence that the bidder has made such examination and is satisfied as to the conditions to be encountered
in performing the work and as to the requirements of the proposed contract, plans, and specifications.
Boring logs and other records of subsurface investigations and tests are available for inspection of
bidders. It is understood and agreed that such subsurface information, whether included in the plans,
specifications, or otherwise made available to the bidder, was obtained and is intended for the Owner’s
design and estimating purposes only. Such information has been made available for the convenience of all
bidders. It is further understood and agreed that each bidder is solely responsible for all assumptions,
deductions, or conclusions which the bidder may make or obtain from his or her examination of the
boring logs and other records of subsurface investigations and tests that are furnished by the Owner.
20-07 Preparation of proposal. The bidder shall submit his or her proposal on the forms furnished by
the Owner. All blank spaces in the proposal forms must be correctly filled in where indicated for each and
every item for which a quantity is given. The bidder shall state the price (written in ink or typed) both in
words and numerals for which they propose to do for each pay item furnished in the proposal. In case of
conflict between words and numerals, the words, unless obviously incorrect, shall govern.
The bidder shall sign the proposal correctly and in ink. If the proposal is made by an individual, his or her
name and post office address must be shown. If made by a partnership, the name and post office address
of each member of the partnership must be shown. If made by a corporation, the person signing the
proposal shall give the name of the state under the laws of which the corporation was chartered and the
name, titles, and business address of the president, secretary, and the treasurer. Anyone signing a proposal
as an agent shall file evidence of his or her authority to do so and that the signature is binding upon the
firm or corporation.
20-08 Responsive and responsible bidder. A responsive bid conforms to all significant terms and
conditions contained in the Sponsor’s invitation for bid. It is the Sponsor’s responsibility to decide if the
exceptions taken by a bidder to the solicitation are material or not and the extent of deviation it is willing
to accept.
A responsible bidder has the ability to perform successfully under the terms and conditions of a proposed
procurement, as defined in 49 CFR § 18.36(b)(8). This includes such matters as Contractor integrity,
compliance with public policy, record of past performance, and financial and technical resources.
20-09 Irregular proposals. Proposals shall be considered irregular for the following reasons:
a. If the proposal is on a form other than that furnished by the Owner, or if the Owner’s form is
altered, or if any part of the proposal form is detached.
b. If there are unauthorized additions, conditional or alternate pay items, or irregularities of any kind
that make the proposal incomplete, indefinite, or otherwise ambiguous.
c. If the proposal does not contain a unit price for each pay item listed in the proposal, except in the
case of authorized alternate pay items, for which the bidder is not required to furnish a unit price.
d. If the proposal contains unit prices that are obviously unbalanced.
e. If the proposal is not accompanied by the proposal guaranty specified by the Owner.
The Owner reserves the right to reject any irregular proposal and the right to waive technicalities if such
waiver is in the best interest of the Owner and conforms to local laws and ordinances pertaining to the
letting of construction contracts.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-7
Reference: AC 150/5370-10G (7/21/2014)
20-10 Bid guarantee. Each separate proposal shall be accompanied by a certified check, or other
specified acceptable collateral, in the amount specified in the proposal form. Such check, or collateral,
shall be made payable to the Owner.
20-11 Delivery of proposal. Each proposal submitted shall be placed in a sealed envelope plainly marked
with the project number, location of airport, and name and business address of the bidder on the outside.
When sent by mail, preferably registered, the sealed proposal, marked as indicated above, should be
enclosed in an additional envelope. No proposal will be considered unless received at the place specified
in the advertisement or as modified by Addendum before the time specified for opening all bids.
Proposals received after the bid opening time shall be returned to the bidder unopened.
20-12 Withdrawal or revision of proposals. A bidder may withdraw or revise (by withdrawal of one
proposal and submission of another) a proposal provided that the bidder’s request for withdrawal is
received by the Owner in writing or by email before the time specified for opening bids. Revised
proposals must be received at the place specified in the advertisement before the time specified for
opening all bids.
20-13 Public opening of proposals. Proposals shall be opened, and read, publicly at the time and place
specified in the advertisement. Bidders, their authorized agents, and other interested persons are invited to
attend. Proposals that have been withdrawn (by written or telegraphic request) or received after the time
specified for opening bids shall be returned to the bidder unopened.
20-14 Disqualification of bidders. A bidder shall be considered disqualified for any of the following
reasons:
a. Submitting more than one proposal from the same partnership, firm, or corporation under the same
or different name.
b. Evidence of collusion among bidders. Bidders participating in such collusion shall be disqualified
as bidders for any future work of the Owner until any such participating bidder has been reinstated by the
Owner as a qualified bidder.
c. If the bidder is considered to be in “default” for any reason specified in the subsection 20-04 titled
ISSUANCE OF PROPOSAL FORMS of this section.
END OF SECTION 20
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-8 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
Intentionally Left Blank
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-9
Reference: AC 150/5370-10G (7/21/2014)
Section 30 Award and Execution of Contract
30-01 Consideration of proposals. After the proposals are publicly opened and read, they will be
compared on the basis of the summation of the products obtained by multiplying the estimated quantities
shown in the proposal by the unit bid prices. If a bidder’s proposal contains a discrepancy between unit
bid prices written in words and unit bid prices written in numbers, the unit price written in words shall
govern.
Until the award of a contract is made, the Owner reserves the right to reject a bidder’s proposal for any of
the following reasons:
a. If the proposal is irregular as specified in the subsection 20-09 titled IRREGULAR PROPOSALS
of Section 20.
b. If the bidder is disqualified for any of the reasons specified in the subsection 20-14 titled
DISQUALIFICATION OF BIDDERS of Section 20.
In addition, until the award of a contract is made, the Owner reserves the right to reject any or all
proposals, waive technicalities, if such waiver is in the best interest of the Owner and is in conformance
with applicable state and local laws or regulations pertaining to the letting of construction contracts;
advertise for new proposals; or proceed with the work otherwise. All such actions shall promote the
Owner’s best interests.
30-02 Award of contract. The award of a contract, if it is to be awarded, shall be made within 120
calendar days of the date specified for publicly opening proposals, unless otherwise specified herein.
Award of the contract shall be made by the Owner to the lowest, qualified bidder whose proposal
conforms to the cited requirements of the Owner.
For AIP contracts, unless otherwise specified in this subsection, no award shall be made
until the FAA has concurred in the Owner’s recommendation to make such award and has
approved the Owner’s proposed contract to the extent that such concurrence and approval
are required by 49 CFR Part 18.
30-03 Cancellation of award. The Owner reserves the right to cancel the award without liability to the
bidder, except return of proposal guaranty, at any time before a contract has been fully executed by all
parties and is approved by the Owner in accordance with the subsection 30-07 titled APPROVAL OF
CONTRACT of this section.
30-04 Return of proposal guaranty. All proposal guaranties, except those of the two lowest bidders,
will be returned immediately after the Owner has made a comparison of bids as specified in the
subsection 30-01 titled CONSIDERATION OF PROPOSALS of this section. Proposal guaranties of the
two lowest bidders will be retained by the Owner until such time as an award is made, at which time, the
unsuccessful bidder’s proposal guaranty will be returned. The successful bidder’s proposal guaranty will
be returned as soon as the Owner receives the contract bonds as specified in the subsection 30-05 titled
REQUIREMENTS OF CONTRACT BONDS of this section.
30-05 Requirements of contract bonds. At the time of the execution of the contract, the successful
bidder shall furnish the Owner a surety bond or bonds that have been fully executed by the bidder and the
surety guaranteeing the performance of the work and the payment of all legal debts that may be incurred
by reason of the Contractor’s performance of the work. The surety and the form of the bond or bonds
shall be acceptable to the Owner. Unless otherwise specified in this subsection, the surety bond or bonds
shall be in a sum equal to the full amount of the contract.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-10 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
30-06 Execution of contract. The successful bidder shall sign (execute) the necessary agreements for
entering into the contract and return the signed contract to the Owner, along with the fully executed surety
bond or bonds specified in the subsection 30-05 titled REQUIREMENTS OF CONTRACT BONDS of
this section, within 15 calendar days from the date mailed or otherwise delivered to the successful bidder.
30-07 Approval of contract. Upon receipt of the contract and contract bond or bonds that have been
executed by the successful bidder, the Owner shall complete the execution of the contract in accordance
with local laws or ordinances, and return the fully executed contract to the Contractor. Delivery of the
fully executed contract to the Contractor shall constitute the Owner’s approval to be bound by the
successful bidder’s proposal and the terms of the contract.
30-08 Failure to execute contract. Failure of the successful bidder to execute the contract and furnish an
acceptable surety bond or bonds within the 15 calendar day period specified in the subsection 30-06 titled
EXECUTION OF CONTRACT of this section shall be just cause for cancellation of the award and
forfeiture of the proposal guaranty, not as a penalty, but as liquidation of damages to the Owner.
END OF SECTION 30
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-11
Reference: AC 150/5370-10G (7/21/2014)
40 Scope of Work
40-01 Intent of contract. The intent of the contract is to provide for construction and completion, in
every detail, of the work described. It is further intended that the Contractor shall furnish all labor,
materials, equipment, tools, transportation, and supplies required to complete the work in accordance with
the plans, specifications, and terms of the contract.
40-02 Alteration of work and quantities. The Owner reserves and shall have the right to make such
alterations in the work as may be necessary or desirable to complete the work originally intended in an
acceptable manner. Unless otherwise specified herein, the Engineer shall be and is hereby authorized to
make such alterations in the work as may increase or decrease the originally awarded contract quantities,
provided that the aggregate of such alterations does not change the total contract cost or the total cost of
any major contract item by more than 25% (total cost being based on the unit prices and estimated
quantities in the awarded contract). Alterations that do not exceed the 25% limitation shall not invalidate
the contract nor release the surety, and the Contractor agrees to accept payment for such alterations as if
the altered work had been a part of the original contract. These alterations that are for work within the
general scope of the contract shall be covered by “Change Orders” issued by the Engineer. Change orders
for altered work shall include extensions of contract time where, in the Engineer’s opinion, such
extensions are commensurate with the amount and difficulty of added work.
Should the aggregate amount of altered work exceed the 25% limitation hereinbefore specified, such
excess altered work shall be covered by supplemental agreement. If the Owner and the Contractor are
unable to agree on a unit adjustment for any contract item that requires a supplemental agreement, the
Owner reserves the right to terminate the contract with respect to the item and make other arrangements
for its completion.
Supplemental agreements shall be approved by the FAA and shall include all applicable Federal contract
provisions for procurement and contracting required under AIP. Supplemental agreements shall also
require consent of the Contractor’s surety and separate performance and payment bonds.
40-03 Omitted items. The Engineer may, in the Owner’s best interest, omit from the work any contract
item, except major contract items. Major contract items may be omitted by a supplemental agreement.
Such omission of contract items shall not invalidate any other contract provision or requirement.
Should a contract item be omitted or otherwise ordered to be non-performed, the Contractor shall be paid
for all work performed toward completion of such item prior to the date of the order to omit such item.
Payment for work performed shall be in accordance with the subsection 90-04 titled PAYMENT FOR
OMITTED ITEMS of Section 90.
40-04 Extra work. Should acceptable completion of the contract require the Contractor to perform an
item of work for which no basis of payment has been provided in the original contract or previously
issued change orders or supplemental agreements, the same shall be called “Extra Work.” Extra Work
that is within the general scope of the contract shall be covered by written change order. Change orders
for such Extra Work shall contain agreed unit prices for performing the change order work in accordance
with the requirements specified in the order, and shall contain any adjustment to the contract time that, in
the Engineer’s opinion, is necessary for completion of such Extra Work.
When determined by the Engineer to be in the Owner’s best interest, the Engineer may order the
Contractor to proceed with Extra Work as provided in the subsection 90-05 titled PAYMENT FOR
EXTRA WORK of Section 90. Extra Work that is necessary for acceptable completion of the project, but
is not within the general scope of the work covered by the original contract shall be covered by a
Supplemental Agreement as defined in the subsection 10-48 titled SUPPLEMENTAL AGREEMENT of
Section 10.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-12 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
Any claim for payment of Extra Work that is not covered by written agreement (change order or
supplemental agreement) shall be rejected by the Owner.
40-05 Maintenance of traffic. It is the explicit intention of the contract that the safety of aircraft, as well
as the Contractor’s equipment and personnel, is the most important consideration.
a. It is understood and agreed that the Contractor shall provide for the free and unobstructed
movement of aircraft in the air operations areas (AOAs) of the airport with respect to his or her own
operations and the operations of all subcontractors as specified in the subsection 80-04 titled
LIMITATION OF OPERATIONS of Section 80. It is further understood and agreed that the Contractor
shall provide for the uninterrupted operation of visual and electronic signals (including power supplies
thereto) used in the guidance of aircraft while operating to, from, and upon the airport as specified in the
subsection 70-15 titled CONTRACTOR’S RESPONSIBILITY FOR UTILITY SERVICE AND
FACILITIES OF OTHERS in Section 70.
b. With respect to his or her own operations and the operations of all subcontractors, the Contractor
shall provide marking, lighting, and other acceptable means of identifying personnel, equipment, vehicles,
storage areas, and any work area or condition that may be hazardous to the operation of aircraft, fire-
rescue equipment, or maintenance vehicles at the airport.
c. When the contract requires the maintenance of vehicular traffic on an existing road, street, or
highway during the Contractor’s performance of work that is otherwise provided for in the contract,
plans, and specifications, the Contractor shall keep such road, street, or highway open to all traffic and
shall provide such maintenance as may be required to accommodate traffic. The Contractor shall be
responsible for the repair of any damage caused by the Contractor’s equipment and personnel. The
Contractor shall furnish, erect, and maintain barricades, warning signs, flag person, and other traffic
control devices in reasonable conformity with the Manual on Uniform Traffic Control Devices (MUTCD)
(http://mutcd.fhwa.dot.gov/), unless otherwise specified. The Contractor shall also construct and maintain
in a safe condition any temporary connections necessary for ingress to and egress from abutting property
or intersecting roads, streets or highways. Unless otherwise specified herein, the Contractor will not be
required to furnish snow removal for such existing road, street, or highway.
40-06 Removal of existing structures. All existing structures encountered within the established lines,
grades, or grading sections shall be removed by the Contractor, unless such existing structures are
otherwise specified to be relocated, adjusted up or down, salvaged, abandoned in place, reused in the
work or to remain in place. The cost of removing such existing structures shall not be measured or paid
for directly, but shall be included in the various contract items.
Should the Contractor encounter an existing structure (above or below ground) in the work for which the
disposition is not indicated on the plans, the Engineer shall be notified prior to disturbing such structure.
The disposition of existing structures so encountered shall be immediately determined by the Engineer in
accordance with the provisions of the contract.
Except as provided in the subsection 40-07 titled RIGHTS IN AND USE OF MATERIALS FOUND IN
THE WORK of this section, it is intended that all existing materials or structures that may be encountered
(within the lines, grades, or grading sections established for completion of the work) shall be used in the
work as otherwise provided for in the contract and shall remain the property of the Owner when so used
in the work.
40-07 Rights in and use of materials found in the work. Should the Contractor encounter any material
such as (but not restricted to) sand, stone, gravel, slag, or concrete slabs within the established lines,
grades, or grading sections, the use of which is intended by the terms of the contract to be either
embankment or waste, the Contractor may at his or her option either:
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-13
Reference: AC 150/5370-10G (7/21/2014)
a. Use such material in another contract item, providing such use is approved by the Engineer and is
in conformance with the contract specifications applicable to such use; or,
b. Remove such material from the site, upon written approval of the Engineer; or
c. Use such material for the Contractor’s own temporary construction on site; or,
d. Use such material as intended by the terms of the contract.
Should the Contractor wish to exercise option a., b., or c., the Contractor shall request the Engineer’s
approval in advance of such use.
Should the Engineer approve the Contractor’s request to exercise option a., b., or c., the Contractor shall
be paid for the excavation or removal of such material at the applicable contract price. The Contractor
shall replace, at his or her own expense, such removed or excavated material with an agreed equal volume
of material that is acceptable for use in constructing embankment, backfills, or otherwise to the extent that
such replacement material is needed to complete the contract work. The Contractor shall not be charged
for use of such material used in the work or removed from the site.
Should the Engineer approve the Contractor’s exercise of option a., the Contractor shall be paid, at the
applicable contract price, for furnishing and installing such material in accordance with requirements of
the contract item in which the material is used.
It is understood and agreed that the Contractor shall make no claim for delays by reason of his or her
exercise of option a., b., or c.
The Contractor shall not excavate, remove, or otherwise disturb any material, structure, or part of a
structure which is located outside the lines, grades, or grading sections established for the work, except
where such excavation or removal is provided for in the contract, plans, or specifications.
40-08 Final cleanup. Upon completion of the work and before acceptance and final payment will be
made, the Contractor shall remove from the site all machinery, equipment, surplus and discarded
materials, rubbish, temporary structures, and stumps or portions of trees. The Contractor shall cut all
brush and woods within the limits indicated and shall leave the site in a neat and presentable condition.
Material cleared from the site and deposited on adjacent property will not be considered as having been
disposed of satisfactorily, unless the Contractor has obtained the written permission of such property
Owner.
END OF SECTION 40
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-14 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
Intentionally Left Blank
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-15
Reference: AC 150/5370-10G (7/21/2014)
Section 50 Control of Work
50-01 Authority of the Engineer. The Engineer shall decide any and all questions which may arise as to
the quality and acceptability of materials furnished, work performed, and as to the manner of performance
and rate of progress of the work. The Engineer shall decide all questions that may arise as to the
interpretation of the specifications or plans relating to the work. The Engineer shall determine the amount
and quality of the several kinds of work performed and materials furnished which are to be paid for the
under contract.
The Engineer does not have the authority to accept pavements that do not conform to FAA specification
requirements.
50-02 Conformity with plans and specifications. All work and all materials furnished shall be in
reasonably close conformity with the lines, grades, grading sections, cross-sections, dimensions, material
requirements, and testing requirements that are specified (including specified tolerances) in the contract,
plans or specifications.
If the Engineer finds the materials furnished, work performed, or the finished product not within
reasonably close conformity with the plans and specifications but that the portion of the work affected
will, in his or her opinion, result in a finished product having a level of safety, economy, durability, and
workmanship acceptable to the Owner, the Engineer will advise the Owner of his or her determination
that the affected work be accepted and remain in place. In this event, the Engineer will document the
determination and recommend to the Owner a basis of acceptance that will provide for an adjustment in
the contract price for the affected portion of the work. The Engineer’s determination and recommended
contract price adjustments will be based on sound engineering judgment and such tests or retests of the
affected work as are, in the Engineer’s opinion, needed. Changes in the contract price shall be covered by
contract change order or supplemental agreement as applicable.
If the Engineer finds the materials furnished, work performed, or the finished product are not in
reasonably close conformity with the plans and specifications and have resulted in an unacceptable
finished product, the affected work or materials shall be removed and replaced or otherwise corrected by
and at the expense of the Contractor in accordance with the Engineer’s written orders.
For the purpose of this subsection, the term “reasonably close conformity” shall not be construed as
waiving the Contractor’s responsibility to complete the work in accordance with the contract, plans, and
specifications. The term shall not be construed as waiving the Engineer’s responsibility to insist on strict
compliance with the requirements of the contract, plans, and specifications during the Contractor’s
execution of the work, when, in the Engineer’s opinion, such compliance is essential to provide an
acceptable finished portion of the work.
For the purpose of this subsection, the term “reasonably close conformity” is also intended to provide the
Engineer with the authority, after consultation with the FAA, to use sound engineering judgment in his or
her determinations as to acceptance of work that is not in strict conformity, but will provide a finished
product equal to or better than that intended by the requirements of the contract, plans and specifications.
The Engineer will not be responsible for the Contractor’s means, methods, techniques, sequences, or
procedures of construction or the safety precautions incident thereto.
50-03 Coordination of contract, plans, and specifications. The contract, plans, specifications, and all
referenced standards cited are essential parts of the contract requirements. A requirement occurring in one
is as binding as though occurring in all. They are intended to be complementary and to describe and
provide for a complete work. In case of discrepancy, calculated dimensions will govern over scaled
dimensions; contract technical specifications shall govern over contract general provisions, plans, cited
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-16 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
standards for materials or testing, and cited advisory circulars (ACs); contract general provisions shall
govern over plans, cited standards for materials or testing, and cited ACs; plans shall govern over cited
standards for materials or testing and cited ACs. If any paragraphs contained in the Special Provisions
conflict with General Provisions or Technical Specifications, the Special Provisions shall govern.
From time to time, discrepancies within cited testing standards occur due to the timing of the change,
edits, and/or replacement of the standards. If the Contractor discovers any apparent discrepancy within
standard test methods, the Contractor shall immediately ask the Engineer for an interpretation and
decision, and such decision shall be final.
LIST OF SPECIAL PROVISIONS
Special Provision No. 1 – Construction Safety and Phasing Plan.
50-04 Cooperation of Contractor. The Contractor will be supplied with five copies each of the plans
and specifications. The Contractor shall have available on the work at all times one copy each of the plans
and specifications. Additional copies of plans and specifications may be obtained by the Contractor for
the cost of reproduction.
The Contractor shall give constant attention to the work to facilitate the progress thereof, and shall
cooperate with the Engineer and his or her inspectors and with other contractors in every way possible.
The Contractor shall have a competent superintendent on the work at all times who is fully authorized as
his or her agent on the work. The superintendent shall be capable of reading and thoroughly
understanding the plans and specifications and shall receive and fulfill instructions from the Engineer or
his or her authorized representative.
50-05 Cooperation between contractors. The Owner reserves the right to contract for and perform other
or additional work on or near the work covered by this contract.
When separate contracts are let within the limits of any one project, each Contractor shall conduct the
work so as not to interfere with or hinder the progress of completion of the work being performed by
other Contractors. Contractors working on the same project shall cooperate with each other as directed.
Each Contractor involved shall assume all liability, financial or otherwise, in connection with his or her
contract and shall protect and save harmless the Owner from any and all damages or claims that may arise
because of inconvenience, delays, or loss experienced because of the presence and operations of other
Contractors working within the limits of the same project.
The Contractor shall arrange his or her work and shall place and dispose of the materials being used so as
not to interfere with the operations of the other Contractors within the limits of the same project. The
Contractor shall join his or her work with that of the others in an acceptable manner and shall perform it
in proper sequence to that of the others.
50-06 Construction layout and stakes. The Engineer shall establish horizontal and vertical control only.
The Contractor must establish all layout required for the construction of the work. Such stakes and
markings as the Engineer may set for either their own or the Contractor’s guidance shall be preserved by
the Contractor. In case of negligence on the part of the Contractor, or their employees, resulting in the
destruction of such stakes or markings, an amount equal to the cost of replacing the same may be
deducted from subsequent estimates due the Contractor at the discretion of the Engineer.
The Contractor will be required to furnish all lines, grades and measurements from the control points
necessary for the proper execution and control of the work contracted for under these specifications.
The Contractor must give copies of survey notes to the Engineer for each area of construction and for
each placement of material as specified to allow the Engineer to make periodic checks for conformance
with plan grades, alignments and grade tolerances required by the applicable material specifications. All
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-17
Reference: AC 150/5370-10G (7/21/2014)
surveys must be provided to the Engineer prior to commencing work items that will cover or disturb the
survey staking as set by the Contractor’s surveyor. Survey(s) and notes shall be provided in the following
format(s): XML file format. In the case of error, on the part of the Contractor, their surveyor, employees
or subcontractors, resulting in established grades, alignment or grade tolerances that do not concur with
those specified or shown on the plans, the Contractor is solely responsible for correction, removal,
replacement and all associated costs at no additional cost to the Owner.
No direct payment will be made, unless otherwise specified in contract documents, for this labor,
materials, or other expenses. The cost shall be included in the price of the bid for the various items of the
Contract.
Construction Staking and Layout includes but is not limited to:
a. Clearing and Grubbing perimeter staking
b. Rough Grade slope stakes at 100-foot (30-m) stations
c. Drainage Swales slope stakes and flow line blue tops at 50-foot (15-m) stations
Subgrade blue tops at 25-foot (7.5-m) stations and 25-foot (7.5-m) offset distance (maximum) for the
following section locations:
a. Runway – minimum five (5) per station
b. Taxiways – minimum three (3) per station
c. Holding apron areas – minimum three (3) per station
d. Roadways – minimum three (3) per station
Base Course blue tops at 25-foot (7.5-m) stations and 25-foot (7.5-m) offset distance (maximum) for the
following section locations:
a. Runway – minimum five (5) per station
b. Taxiways – minimum three (3) per station
c. Holding apron areas – minimum three (3) per station
Pavement areas:
a. Edge of Pavement hubs and tacks (for stringline by Contractor) at 100-foot (30-m) stations.
b. Between Lifts at 25-foot (7.5-m) stations for the following section locations:
(1) Runways – each paving lane width
(2) Taxiways – each paving lane width
(3) Holding areas – each paving lane width
c. After finish paving operations at 50-foot (15-m) stations:
(1) All paved areas – Edge of each paving lane prior to next paving lot
d. Shoulder and safety area blue tops at 50-foot (15-m) stations and at all break points with maximum
of 50-foot (15-m) offsets.
e. Fence lines at 100-foot (30-m) stations minimum.
f. Electrical and Communications System locations, lines and grades including but not limited to duct
runs, connections, fixtures, signs, lights, Visual Approach Slope Indicators (VASIs), Precision Approach
Path Indicators (PAPIs), Runway End Identifier Lighting (REIL), Wind Cones, Distance Markers (signs),
pull boxes and manholes.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-18 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
g. Drain lines, cut stakes and alignment on 25-foot (7.5-m) stations, inlet and manholes.
h. Painting and Striping layout (pinned with 1.5 inch PK nails) marked for paint Contractor. (All nails
shall be removed after painting).
i. Laser, or other automatic control devices, shall be checked with temporary control point or grade
hub at a minimum of once per 400 feet (120 m) per pass (that is, paving lane).
The establishment of Survey Control and/or reestablishment of survey control shall be by a State
Licensed Land Surveyor.
Controls and stakes disturbed or suspect of having been disturbed shall be checked and/or reset as
directed by the Engineer without additional cost to the Owner.
50-07 Automatically controlled equipment. Whenever batching or mixing plant equipment is required
to be operated automatically under the contract and a breakdown or malfunction of the automatic controls
occurs, the equipment may be operated manually or by other methods for a period 48 hours following the
breakdown or malfunction, provided this method of operations will produce results which conform to all
other requirements of the contract.
50-08 Authority and duties of inspectors. Inspectors shall be authorized to inspect all work done and all
material furnished. Such inspection may extend to all or any part of the work and to the preparation,
fabrication, or manufacture of the materials to be used. Inspectors are not authorized to revoke, alter, or
waive any provision of the contract. Inspectors are not authorized to issue instructions contrary to the
plans and specifications or to act as foreman for the Contractor.
Inspectors are authorized to notify the Contractor or his or her representatives of any failure of the work
or materials to conform to the requirements of the contract, plans, or specifications and to reject such
nonconforming materials in question until such issues can be referred to the Engineer for a decision.
50-09 Inspection of the work. All materials and each part or detail of the work shall be subject to
inspection. The Engineer shall be allowed access to all parts of the work and shall be furnished with such
information and assistance by the Contractor as is required to make a complete and detailed inspection.
If the Engineer requests it, the Contractor, at any time before acceptance of the work, shall remove or
uncover such portions of the finished work as may be directed. After examination, the Contractor shall
restore said portions of the work to the standard required by the specifications. Should the work thus
exposed or examined prove acceptable, the uncovering, or removing, and the replacing of the covering or
making good of the parts removed will be paid for as extra work; but should the work so exposed or
examined prove unacceptable, the uncovering, or removing, and the replacing of the covering or making
good of the parts removed will be at the Contractor’s expense.
Any work done or materials used without supervision or inspection by an authorized representative of the
Owner may be ordered removed and replaced at the Contractor’s expense unless the Owner’s
representative failed to inspect after having been given reasonable notice in writing that the work was to
be performed.
Should the contract work include relocation, adjustment, or any other modification to existing facilities,
not the property of the (contract) Owner, authorized representatives of the Owners of such facilities shall
have the right to inspect such work. Such inspection shall in no sense make any facility owner a party to
the contract, and shall in no way interfere with the rights of the parties to this contract.
50-10 Removal of unacceptable and unauthorized work. All work that does not conform to the
requirements of the contract, plans, and specifications will be considered unacceptable, unless otherwise
determined acceptable by the Engineer as provided in the subsection 50-02 titled CONFORMITY WITH
PLANS AND SPECIFICATIONS of this section.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-19
Reference: AC 150/5370-10G (7/21/2014)
Unacceptable work, whether the result of poor workmanship, use of defective materials, damage through
carelessness, or any other cause found to exist prior to the final acceptance of the work, shall be removed
immediately and replaced in an acceptable manner in accordance with the provisions of the subsection
70-14 titled CONTRACTOR’S RESPONSIBILITY FOR WORK of Section 70.
No removal work made under provision of this subsection shall be done without lines and grades having
been established by the Engineer. Work done contrary to the instructions of the Engineer, work done
beyond the lines shown on the plans or as established by the Engineer, except as herein specified, or any
extra work done without authority, will be considered as unauthorized and will not be paid for under the
provisions of the contract. Work so done may be ordered removed or replaced at the Contractor’s
expense.
Upon failure on the part of the Contractor to comply with any order of the Engineer made under the
provisions of this subsection, the Engineer will have authority to cause unacceptable work to be remedied
or removed and replaced and unauthorized work to be removed and to deduct the costs incurred by the
Owner from any monies due or to become due the Contractor.
50-11 Load restrictions. The Contractor shall comply with all legal load restrictions in the hauling of
materials on public roads beyond the limits of the work. A special permit will not relieve the Contractor
of liability for damage that may result from the moving of material or equipment.
The operation of equipment of such weight or so loaded as to cause damage to structures or to any other
type of construction will not be permitted. Hauling of materials over the base course or surface course
under construction shall be limited as directed. No loads will be permitted on a concrete pavement, base,
or structure before the expiration of the curing period. The Contractor shall be responsible for all damage
done by his or her hauling equipment and shall correct such damage at his or her own expense.
50-12 Maintenance during construction. The Contractor shall maintain the work during construction
and until the work is accepted. Maintenance shall constitute continuous and effective work prosecuted
day by day, with adequate equipment and forces so that the work is maintained in satisfactory condition at
all times.
In the case of a contract for the placing of a course upon a course or subgrade previously constructed, the
Contractor shall maintain the previous course or subgrade during all construction operations.
All costs of maintenance work during construction and before the project is accepted shall be included in
the unit prices bid on the various contract items, and the Contractor will not be paid an additional amount
for such work.
50-13 Failure to maintain the work. Should the Contractor at any time fail to maintain the work as
provided in the subsection 50-12 titled MAINTENANCE DURING CONSTRUCTION of this section,
the Engineer shall immediately notify the Contractor of such noncompliance. Such notification shall
specify a reasonable time within which the Contractor shall be required to remedy such unsatisfactory
maintenance condition. The time specified will give due consideration to the exigency that exists.
Should the Contractor fail to respond to the Engineer’s notification, the Owner may suspend any work
necessary for the Owner to correct such unsatisfactory maintenance condition, depending on the exigency
that exists. Any maintenance cost incurred by the Owner, shall be deducted from monies due or to
become due the Contractor.
50-14 Partial acceptance. If at any time during the execution of the project the Contractor substantially
completes a usable unit or portion of the work, the occupancy of which will benefit the Owner, the
Contractor may request the Engineer to make final inspection of that unit. If the Engineer finds upon
inspection that the unit has been satisfactorily completed in compliance with the contract, the Engineer
may accept it as being complete, and the Contractor may be relieved of further responsibility for that unit.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-20 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
Such partial acceptance and beneficial occupancy by the Owner shall not void or alter any provision of
the contract.
50-15 Final acceptance. Upon due notice from the Contractor of presumptive completion of the entire
project, the Engineer and Owner will make an inspection. If all construction provided for and
contemplated by the contract is found to be complete in accordance with the contract, plans, and
specifications, such inspection shall constitute the final inspection. The Engineer shall notify the
Contractor in writing of final acceptance as of the date of the final inspection.
If, however, the inspection discloses any work, in whole or in part, as being unsatisfactory, the Engineer
will give the Contractor the necessary instructions for correction of same and the Contractor shall
immediately comply with and execute such instructions. Upon correction of the work, another inspection
will be made which shall constitute the final inspection, provided the work has been satisfactorily
completed. In such event, the Engineer will make the final acceptance and notify the Contractor in writing
of this acceptance as of the date of final inspection.
50-16 Claims for adjustment and disputes. If for any reason the Contractor deems that additional
compensation is due for work or materials not clearly provided for in the contract, plans, or specifications
or previously authorized as extra work, the Contractor shall notify the Engineer in writing of his or her
intention to claim such additional compensation before the Contractor begins the work on which the
Contractor bases the claim. If such notification is not given or the Engineer is not afforded proper
opportunity by the Contractor for keeping strict account of actual cost as required, then the Contractor
hereby agrees to waive any claim for such additional compensation. Such notice by the Contractor and the
fact that the Engineer has kept account of the cost of the work shall not in any way be construed as
proving or substantiating the validity of the claim. When the work on which the claim for additional
compensation is based has been completed, the Contractor shall, within 10 calendar days, submit a written
claim to the Engineer who will present it to the Owner for consideration in accordance with local laws or
ordinances.
Nothing in this subsection shall be construed as a waiver of the Contractor’s right to dispute final
payment based on differences in measurements or computations.
END OF SECTION 50
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-21
Reference: AC 150/5370-10G (7/21/2014)
Section 60 Control of Materials
60-01 Source of supply and quality requirements. The materials used in the work shall conform to the
requirements of the contract, plans, and specifications. Unless otherwise specified, such materials that are
manufactured or processed shall be new (as compared to used or reprocessed).
In order to expedite the inspection and testing of materials, the Contractor shall furnish complete
statements to the Engineer as to the origin, composition, and manufacture of all materials to be used in the
work. Such statements shall be furnished promptly after execution of the contract but, in all cases, prior to
delivery of such materials.
At the Engineer’s option, materials may be approved at the source of supply before delivery is stated. If it
is found after trial that sources of supply for previously approved materials do not produce specified
products, the Contractor shall furnish materials from other sources.
The Contractor shall furnish airport lighting equipment that conforms to the requirements of cited
materials specifications. In addition, where an FAA specification for airport lighting equipment is cited in
the plans or specifications, the Contractor shall furnish such equipment that is:
a. Listed in advisory circular (AC) 150/5345-53, Airport Lighting Equipment Certification Program,
and Addendum that is in effect on the date of advertisement; and,
b. Produced by the manufacturer as listed in the Addendum cited above for the certified equipment
part number.
The following airport lighting equipment is required for this contract and is to be furnished by the
Contractor in accordance with the requirements of this subsection: [ ].
60-02 Samples, tests, and cited specifications. Unless otherwise designated, all materials used in the
work shall be inspected, tested, and approved by the Engineer before incorporation in the work. Any work
in which untested materials are used without approval or written permission of the Engineer shall be
performed at the Contractor’s risk. Materials found to be unacceptable and unauthorized will not be paid
for and, if directed by the Engineer, shall be removed at the Contractor’s expense.
Unless otherwise designated, quality assurance tests in accordance with the cited standard methods of
ASTM, American Association of State Highway and Transportation Officials (AASHTO), Federal
Specifications, Commercial Item Descriptions, and all other cited methods, which are current on the date
of advertisement for bids, will be made by and at the expense of the Engineer.
The testing organizations performing on-site quality assurance field tests shall have copies of all
referenced standards on the construction site for use by all technicians and other personnel, including the
Contractor’s representative at his or her request. Unless otherwise designated, samples for quality
assurance will be taken by a qualified representative of the Engineer. All materials being used are subject
to inspection, test, or rejection at any time prior to or during incorporation into the work. Copies of all
tests will be furnished to the Contractor’s representative at their request after review and approval of the
Engineer.
The Contractor shall employ a testing organization to perform all Contractor required Quality Control
tests. The Contractor shall submit to the Engineer resumes on all testing organizations and individual
persons who will be performing the tests. The Engineer will determine if such persons are qualified. All
the test data shall be reported to the Engineer after the results are known. A legible, handwritten copy of
all test data shall be given to the Engineer daily, along with printed reports, in an approved format, on a
weekly basis. After completion of the project, and prior to final payment, the Contractor shall submit a
final report to the Engineer showing all test data reports, plus an analysis of all results showing ranges,
averages, and corrective action taken on all failing tests.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-22 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
60-03 Certification of compliance. The Engineer may permit the use, prior to sampling and testing, of
certain materials or assemblies when accompanied by manufacturer’s certificates of compliance stating
that such materials or assemblies fully comply with the requirements of the contract. The certificate shall
be signed by the manufacturer. Each lot of such materials or assemblies delivered to the work must be
accompanied by a certificate of compliance in which the lot is clearly identified.
Materials or assemblies used on the basis of certificates of compliance may be sampled and tested at any
time and if found not to be in conformity with contract requirements will be subject to rejection whether
in place or not.
The form and distribution of certificates of compliance shall be as approved by the Engineer.
When a material or assembly is specified by “brand name or equal” and the Contractor elects to furnish
the specified “brand name,” the Contractor shall be required to furnish the manufacturer’s certificate of
compliance for each lot of such material or assembly delivered to the work. Such certificate of
compliance shall clearly identify each lot delivered and shall certify as to:
a. Conformance to the specified performance, testing, quality or dimensional requirements; and,
b. Suitability of the material or assembly for the use intended in the contract work.
Should the Contractor propose to furnish an “or equal” material or assembly, the Contractor shall furnish
the manufacturer’s certificates of compliance as hereinbefore described for the specified brand name
material or assembly. However, the Engineer shall be the sole judge as to whether the proposed “or
equal” is suitable for use in the work.
The Engineer reserves the right to refuse permission for use of materials or assemblies on the basis of
certificates of compliance.
60-04 Plant inspection. The Engineer or his or her authorized representative may inspect, at its source,
any specified material or assembly to be used in the work. Manufacturing plants may be inspected from
time to time for the purpose of determining compliance with specified manufacturing methods or
materials to be used in the work and to obtain samples required for acceptance of the material or
assembly.
Should the Engineer conduct plant inspections, the following conditions shall exist:
a. The Engineer shall have the cooperation and assistance of the Contractor and the producer with
whom the Engineer has contracted for materials.
b. The Engineer shall have full entry at all reasonable times to such parts of the plant that concern the
manufacture or production of the materials being furnished.
c. If required by the Engineer, the Contractor shall arrange for adequate office or working space that
may be reasonably needed for conducting plant inspections. Office or working space should be
conveniently located with respect to the plant.
It is understood and agreed that the Owner shall have the right to retest any material that has been tested
and approved at the source of supply after it has been delivered to the site. The Engineer shall have the
right to reject only material which, when retested, does not meet the requirements of the contract, plans,
or specifications.
60-05 Engineer’s field office. An Engineer’s field office is not required.
60-06 Storage of materials. Materials shall be so stored as to assure the preservation of their quality and
fitness for the work. Stored materials, even though approved before storage, may again be inspected prior
to their use in the work. Stored materials shall be located to facilitate their prompt inspection. The
Contractor shall coordinate the storage of all materials with the Engineer. Materials to be stored on airport
property shall not create an obstruction to air navigation nor shall they interfere with the free and
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-23
Reference: AC 150/5370-10G (7/21/2014)
unobstructed movement of aircraft. Unless otherwise shown on the plans, the storage of materials and the
location of the Contractor’s plant and parked equipment or vehicles shall be as directed by the Engineer.
Private property shall not be used for storage purposes without written permission of the Owner or lessee
of such property. The Contractor shall make all arrangements and bear all expenses for the storage of
materials on private property. Upon request, the Contractor shall furnish the Engineer a copy of the
property Owner’s permission.
All storage sites on private or airport property shall be restored to their original condition by the
Contractor at his or her entire expense, except as otherwise agreed to (in writing) by the Owner or lessee
of the property.
60-07 Unacceptable materials. Any material or assembly that does not conform to the requirements of
the contract, plans, or specifications shall be considered unacceptable and shall be rejected. The
Contractor shall remove any rejected material or assembly from the site of the work, unless otherwise
instructed by the Engineer.
Rejected material or assembly, the defects of which have been corrected by the Contractor, shall not be
returned to the site of the work until such time as the Engineer has approved its use in the work.
60-08 Owner furnished materials. The Contractor shall furnish all materials required to complete the
work, except those specified, if any, to be furnished by the Owner. Owner-furnished materials shall be
made available to the Contractor at the location specified.
All costs of handling, transportation from the specified location to the site of work, storage, and installing
Owner-furnished materials shall be included in the unit price bid for the contract item in which such
Owner-furnished material is used.
After any Owner-furnished material has been delivered to the location specified, the Contractor shall be
responsible for any demurrage, damage, loss, or other deficiencies that may occur during the Contractor’s
handling, storage, or use of such Owner-furnished material. The Owner will deduct from any monies due
or to become due the Contractor any cost incurred by the Owner in making good such loss due to the
Contractor’s handling, storage, or use of Owner-furnished materials.
END OF SECTION 60
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-24 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
Intentionally Left Blank
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-25
Reference: AC 150/5370-10G (7/21/2014)
Section 70 Legal Regulations and Responsibility to Public
70-01 Laws to be observed. The Contractor shall keep fully informed of all Federal and state laws, all
local laws, ordinances, and regulations and all orders and decrees of bodies or tribunals having any
jurisdiction or authority, which in any manner affect those engaged or employed on the work, or which in
any way affect the conduct of the work. The Contractor shall at all times observe and comply with all
such laws, ordinances, regulations, orders, and decrees; and shall protect and indemnify the Owner and all
his or her officers, agents, or servants against any claim or liability arising from or based on the violation
of any such law, ordinance, regulation, order, or decree, whether by the Contractor or the Contractor’s
employees.
70-02 Permits, licenses, and taxes. The Contractor shall procure all permits and licenses, pay all charges,
fees, and taxes, and give all notices necessary and incidental to the due and lawful execution of the work.
70-03 Patented devices, materials, and processes. If the Contractor is required or desires to use any
design, device, material, or process covered by letters of patent or copyright, the Contractor shall provide
for such use by suitable legal agreement with the Patentee or Owner. The Contractor and the surety shall
indemnify and hold harmless the Owner, any third party, or political subdivision from any and all claims
for infringement by reason of the use of any such patented design, device, material or process, or any
trademark or copyright, and shall indemnify the Owner for any costs, expenses, and damages which it
may be obliged to pay by reason of an infringement, at any time during the execution or after the
completion of the work.
70-04 Restoration of surfaces disturbed by others. The Owner reserves the right to authorize the
construction, reconstruction, or maintenance of any public or private utility service, FAA or National
Oceanic and Atmospheric Administration (NOAA) facility, or a utility service of another government
agency at any time during the progress of the work. To the extent that such construction, reconstruction,
or maintenance has been coordinated with the Owner, such authorized work (by others) is indicated as
follows: None known.
Except as listed above, the Contractor shall not permit any individual, firm, or corporation to excavate or
otherwise disturb such utility services or facilities located within the limits of the work without the
written permission of the Engineer.
Should the Owner of public or private utility service, FAA, or NOAA facility, or a utility service of
another government agency be authorized to construct, reconstruct, or maintain such utility service or
facility during the progress of the work, the Contractor shall cooperate with such Owners by arranging
and performing the work in this contract to facilitate such construction, reconstruction or maintenance by
others whether or not such work by others is listed above. When ordered as extra work by the Engineer,
the Contractor shall make all necessary repairs to the work which are due to such authorized work by
others, unless otherwise provided for in the contract, plans, or specifications. It is understood and agreed
that the Contractor shall not be entitled to make any claim for damages due to such authorized work by
others or for any delay to the work resulting from such authorized work.
70-05 Federal aid participation. For Airport Improvement Program (AIP) contracts, the United States
Government has agreed to reimburse the Owner for some portion of the contract costs. Such
reimbursement is made from time to time upon the Owner’s request to the FAA. In consideration of the
United States Government’s (FAA’s) agreement with the Owner, the Owner has included provisions in
this contract pursuant to the requirements of Title 49 of the USC and the Rules and Regulations of the
FAA that pertain to the work.
As required by the USC, the contract work is subject to the inspection and approval of duly authorized
representatives of the FAA Administrator, and is further subject to those provisions of the rules and
regulations that are cited in the contract, plans, or specifications.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-26 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
No requirement of the USC, the rules and regulations implementing the USC, or this contract shall be
construed as making the Federal Government a party to the contract nor will any such requirement
interfere, in any way, with the rights of either party to the contract.
70-06 Sanitary, health, and safety provisions. The Contractor shall provide and maintain in a neat,
sanitary condition such accommodations for the use of his or her employees as may be necessary to
comply with the requirements of the state and local Board of Health, or of other bodies or tribunals
having jurisdiction.
Attention is directed to Federal, state, and local laws, rules and regulations concerning construction safety
and health standards. The Contractor shall not require any worker to work in surroundings or under
conditions that are unsanitary, hazardous, or dangerous to his or her health or safety.
70-07 Public convenience and safety. The Contractor shall control his or her operations and those of his
or her subcontractors and all suppliers, to assure the least inconvenience to the traveling public. Under all
circumstances, safety shall be the most important consideration.
The Contractor shall maintain the free and unobstructed movement of aircraft and vehicular traffic with
respect to his or her own operations and those of his or her subcontractors and all suppliers in accordance
with the subsection 40-05 titled MAINTENANCE OF TRAFFIC of Section 40 hereinbefore specified and
shall limit such operations for the convenience and safety of the traveling public as specified in the
subsection 80-04 titled LIMITATION OF OPERATIONS of Section 80 hereinafter.
70-08 Barricades, warning signs, and hazard markings. The Contractor shall furnish, erect, and
maintain all barricades, warning signs, and markings for hazards necessary to protect the public and the
work. When used during periods of darkness, such barricades, warning signs, and hazard markings shall
be suitably illuminated. Unless otherwise specified, barricades, warning signs, and markings for hazards
that are in the air operations area (AOAs) shall be a maximum of 18 inches (0.5 m) high. Unless
otherwise specified, barricades shall be spaced not more than 4 feet (1.2 m) apart. Barricades, warning
signs, and markings shall be paid for under subsection 40-05.
For vehicular and pedestrian traffic, the Contractor shall furnish, erect, and maintain barricades, warning
signs, lights and other traffic control devices in reasonable conformity with the Manual on Uniform
Traffic Control Devices.
When the work requires closing an air operations area of the airport or portion of such area, the
Contractor shall furnish, erect, and maintain temporary markings and associated lighting conforming to
the requirements of advisory circular (AC) 150/5340-1, Standards for Airport Markings.
The Contractor shall furnish, erect, and maintain markings and associated lighting of open trenches,
excavations, temporary stock piles, and the Contractor’s parked construction equipment that may be
hazardous to the operation of emergency fire-rescue or maintenance vehicles on the airport in reasonable
conformance to AC 150/5370-2, Operational Safety on Airports During Construction.
The Contractor shall identify each motorized vehicle or piece of construction equipment in reasonable
conformance to AC 150/5370-2.
The Contractor shall furnish and erect all barricades, warning signs, and markings for hazards prior to
commencing work that requires such erection and shall maintain the barricades, warning signs, and
markings for hazards until their removal is directed by the Engineer.
Open-flame type lights shall not be permitted.
70-09 Use of explosives. Explosives shall not be used. When the use of explosives is necessary for the
execution of the work, the Contractor shall exercise the utmost care not to endanger life or property,
including new work. The Contractor shall be responsible for all damage resulting from the use of
explosives.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-27
Reference: AC 150/5370-10G (7/21/2014)
All explosives shall be stored in a secure manner in compliance with all laws and ordinances, and all such
storage places shall be clearly marked. Where no local laws or ordinances apply, storage shall be provided
satisfactory to the Engineer and, in general, not closer than 1,000 feet (300 m) from the work or from any
building, road, or other place of human occupancy.
The Contractor shall notify each property Owner and public utility company having structures or facilities
in proximity to the site of the work of his or her intention to use explosives. Such notice shall be given
sufficiently in advance to enable them to take such steps as they may deem necessary to protect their
property from injury.
The use of electrical blasting caps shall not be permitted on or within 1,000 feet (300 m) of the airport
property.
70-10 Protection and restoration of property and landscape. The Contractor shall be responsible for
the preservation of all public and private property, and shall protect carefully from disturbance or damage
all land monuments and property markers until the Engineer has witnessed or otherwise referenced their
location and shall not move them until directed.
The Contractor shall be responsible for all damage or injury to property of any character, during the
execution of the work, resulting from any act, omission, neglect, or misconduct in manner or method of
executing the work, or at any time due to defective work or materials, and said responsibility shall not be
released until the project has been completed and accepted.
When or where any direct or indirect damage or injury is done to public or private property by or on
account of any act, omission, neglect, or misconduct in the execution of the work, or in consequence of
the non-execution thereof by the Contractor, the Contractor shall restore, at his or her own expense, such
property to a condition similar or equal to that existing before such damage or injury was done, by
repairing, or otherwise restoring as may be directed, or the Contractor shall make good such damage or
injury in an acceptable manner.
70-11 Responsibility for damage claims. The Contractor shall indemnify and save harmless the
Engineer and the Owner and their officers, and employees from all suits, actions, or claims, of any
character, brought because of any injuries or damage received or sustained by any person, persons, or
property on account of the operations of the Contractor; or on account of or in consequence of any neglect
in safeguarding the work; or through use of unacceptable materials in constructing the work; or because
of any act or omission, neglect, or misconduct of said Contractor; or because of any claims or amounts
recovered from any infringements of patent, trademark, or copyright; or from any claims or amounts
arising or recovered under the “Workmen’s Compensation Act,” or any other law, ordinance, order, or
decree. Money due the Contractor under and by virtue of his or her contract considered necessary by the
Owner for such purpose may be retained for the use of the Owner or, in case no money is due, his or her
surety may be held until such suits, actions, or claims for injuries or damages shall have been settled and
suitable evidence to that effect furnished to the Owner, except that money due the Contractor will not be
withheld when the Contractor produces satisfactory evidence that he or she is adequately protected by
public liability and property damage insurance.
70-12 Third party beneficiary clause. It is specifically agreed between the parties executing the contract
that it is not intended by any of the provisions of any part of the contract to create for the public or any
member thereof, a third party beneficiary or to authorize anyone not a party to the contract to maintain a
suit for personal injuries or property damage pursuant to the terms or provisions of the contract.
70-13 Opening sections of the work to traffic. Should it be necessary for the Contractor to complete
portions of the contract work for the beneficial occupancy of the Owner prior to completion of the entire
contract, such “phasing” of the work shall be specified herein and indicated on the plans. When so
specified, the Contractor shall complete such portions of the work on or before the date specified or as
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-28 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
otherwise specified. The Contractor shall make his or her own estimate of the difficulties involved in
arranging the work to permit such beneficial occupancy by the Owner as described below:
None.
Upon completion of any portion of the work listed above, such portion shall be accepted by the Owner in
accordance with the subsection 50-14 titled PARTIAL ACCEPTANCE of Section 50.
No portion of the work may be opened by the Contractor for public use until ordered by the Engineer in
writing. Should it become necessary to open a portion of the work to public traffic on a temporary or
intermittent basis, such openings shall be made when, in the opinion of the Engineer, such portion of the
work is in an acceptable condition to support the intended traffic. Temporary or intermittent openings are
considered to be inherent in the work and shall not constitute either acceptance of the portion of the work
so opened or a waiver of any provision of the contract. Any damage to the portion of the work so opened
that is not attributable to traffic which is permitted by the Owner shall be repaired by the Contractor at his
or her expense.
The Contractor shall make his or her own estimate of the inherent difficulties involved in completing the
work under the conditions herein described and shall not claim any added compensation by reason of
delay or increased cost due to opening a portion of the contract work.
Contractor shall be required to conform to safety standards contained AC 150/5370-2 (see Special
Provisions).
Contractor shall refer to the approved Construction Safety Phasing Plan (CSPP) to identify barricade
requirements and other safety requirements prior to opening up sections of work to traffic.
70-14 Contractor’s responsibility for work. Until the Engineer’s final written acceptance of the entire
completed work, excepting only those portions of the work accepted in accordance with the subsection
50-14 titled PARTIAL ACCEPTANCE of Section 50, the Contractor shall have the charge and care
thereof and shall take every precaution against injury or damage to any part due to the action of the
elements or from any other cause, whether arising from the execution or from the non-execution of the
work. The Contractor shall rebuild, repair, restore, and make good all injuries or damages to any portion
of the work occasioned by any of the above causes before final acceptance and shall bear the expense
thereof except damage to the work due to unforeseeable causes beyond the control of and without the
fault or negligence of the Contractor, including but not restricted to acts of God such as earthquake, tidal
wave, tornado, hurricane or other cataclysmic phenomenon of nature, or acts of the public enemy or of
government authorities.
If the work is suspended for any cause whatever, the Contractor shall be responsible for the work and
shall take such precautions necessary to prevent damage to the work. The Contractor shall provide for
normal drainage and shall erect necessary temporary structures, signs, or other facilities at his or her
expense. During such period of suspension of work, the Contractor shall properly and continuously
maintain in an acceptable growing condition all living material in newly established planting, seeding,
and sodding furnished under the contract, and shall take adequate precautions to protect new tree growth
and other important vegetative growth against injury.
70-15 Contractor’s responsibility for utility service and facilities of others. As provided in the
subsection 70-04 titled RESTORATION OF SURFACES DISTURBED BY OTHERS of this section, the
Contractor shall cooperate with the Owner of any public or private utility service, FAA or NOAA, or a
utility service of another government agency that may be authorized by the Owner to construct,
reconstruct or maintain such utility services or facilities during the progress of the work. In addition, the
Contractor shall control their operations to prevent the unscheduled interruption of such utility services
and facilities.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-29
Reference: AC 150/5370-10G (7/21/2014)
To the extent that such public or private utility services, FAA, or NOAA facilities, or utility services of
another governmental agency are known to exist within the limits of the contract work, the approximate
locations have been indicated on the plans and the Owners are indicated as follows: None Known.
It is understood and agreed that the Owner does not guarantee the accuracy or the completeness of the
location information relating to existing utility services, facilities, or structures that may be shown on the
plans or encountered in the work. Any inaccuracy or omission in such information shall not relieve the
Contractor of the responsibility to protect such existing features from damage or unscheduled interruption
of service.
It is further understood and agreed that the Contractor shall, upon execution of the contract, notify the
Owners of all utility services or other facilities of his or her plan of operations. Such notification shall be
in writing addressed to THE PERSON TO CONTACT as provided in this subsection and subsection 70-
04 titled RESTORATION OF SURFACES DISTURBED BY OTHERS of this section. A copy of each
notification shall be given to the Engineer.
In addition to the general written notification provided, it shall be the responsibility of the Contractor to
keep such individual Owners advised of changes in their plan of operations that would affect such
Owners.
Prior to beginning the work in the general vicinity of an existing utility service or facility, the Contractor
shall again notify each such Owner of their plan of operation. If, in the Contractor’s opinion, the Owner’s
assistance is needed to locate the utility service or facility or the presence of a representative of the Owner
is desirable to observe the work, such advice should be included in the notification. Such notification shall
be given by the most expeditious means to reach the utility owner’s PERSON TO CONTACT no later
than two normal business days prior to the Contractor’s commencement of operations in such general
vicinity. The Contractor shall furnish a written summary of the notification to the Engineer.
The Contractor’s failure to give the two days’ notice shall be cause for the Owner to suspend the
Contractor’s operations in the general vicinity of a utility service or facility.
Where the outside limits of an underground utility service have been located and staked on the ground,
the Contractor shall be required to use hand excavation methods within 3 feet (1 m) of such outside limits
at such points as may be required to ensure protection from damage due to the Contractor’s operations.
Should the Contractor damage or interrupt the operation of a utility service or facility by accident or
otherwise, the Contractor shall immediately notify the proper authority and the Engineer and shall take all
reasonable measures to prevent further damage or interruption of service. The Contractor, in such events,
shall cooperate with the utility service or facility owner and the Engineer continuously until such damage
has been repaired and service restored to the satisfaction of the utility or facility owner.
The Contractor shall bear all costs of damage and restoration of service to any utility service or facility
due to their operations whether due to negligence or accident. The Owner reserves the right to deduct
such costs from any monies due or which may become due the Contractor, or his or her surety.
70-16 Furnishing rights-of-way. The Owner will be responsible for furnishing all rights-of-way upon
which the work is to be constructed in advance of the Contractor’s operations.
70-17 Personal liability of public officials. In carrying out any of the contract provisions or in exercising
any power or authority granted by this contract, there shall be no liability upon the Engineer, his or her
authorized representatives, or any officials of the Owner either personally or as an official of the Owner.
It is understood that in such matters they act solely as agents and representatives of the Owner.
70-18 No waiver of legal rights. Upon completion of the work, the Owner will expeditiously make final
inspection and notify the Contractor of final acceptance. Such final acceptance, however, shall not
preclude or stop the Owner from correcting any measurement, estimate, or certificate made before or after
completion of the work, nor shall the Owner be precluded or stopped from recovering from the Contractor
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-30 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
or his or her surety, or both, such overpayment as may be sustained, or by failure on the part of the
Contractor to fulfill his or her obligations under the contract. A waiver on the part of the Owner of any
breach of any part of the contract shall not be held to be a waiver of any other or subsequent breach.
The Contractor, without prejudice to the terms of the contract, shall be liable to the Owner for latent
defects, fraud, or such gross mistakes as may amount to fraud, or as regards the Owner’s rights under any
warranty or guaranty.
70-19 Environmental protection. The Contractor shall comply with all Federal, state, and local laws and
regulations controlling pollution of the environment. The Contractor shall take necessary precautions to
prevent pollution of streams, lakes, ponds, and reservoirs with fuels, oils, bitumens, chemicals, or other
harmful materials and to prevent pollution of the atmosphere from particulate and gaseous matter.
70-20 Archaeological and historical findings. Unless otherwise specified in this subsection, the
Contractor is advised that the site of the work is not within any property, district, or site, and does not
contain any building, structure, or object listed in the current National Register of Historic Places
published by the United States Department of Interior.
Should the Contractor encounter, during his or her operations, any building, part of a building, structure,
or object that is incongruous with its surroundings, the Contractor shall immediately cease operations in
that location and notify the Engineer. The Engineer will immediately investigate the Contractor’s finding
and the Owner will direct the Contractor to either resume operations or to suspend operations as directed.
Should the Owner order suspension of the Contractor’s operations in order to protect an archaeological or
historical finding, or order the Contractor to perform extra work, such shall be covered by an appropriate
contract change order or supplemental agreement as provided in the subsection 40-04 titled EXTRA
WORK of Section 40 and the subsection 90-05 titled PAYMENT FOR EXTRA WORK of Section 90. If
appropriate, the contract change order or supplemental agreement shall include an extension of contract
time in accordance with the subsection 80-07 titled DETERMINATION AND EXTENSION OF
CONTRACT TIME of Section 80.
END OF SECTION 70
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-31
Reference: AC 150/5370-10G (7/21/2014)
Section 80 Execution and Progress
80-01 Subletting of contract. The Owner will not recognize any subcontractor on the work. The
Contractor shall at all times when work is in progress be represented either in person, by a qualified
superintendent, or by other designated, qualified representative who is duly authorized to receive and
execute orders of the Engineer.
The Contractor shall provide copies of all subcontracts to the Engineer. The Contractor shall perform,
with his organization, an amount of work equal to at least 25 percent of the total contract cost.
Should the Contractor elect to assign his or her contract, said assignment shall be concurred in by the
surety, shall be presented for the consideration and approval of the Owner, and shall be consummated
only on the written approval of the Owner.
80-02 Notice to proceed. The notice to proceed shall state the date on which it is expected the Contractor
will begin the construction and from which date contract time will be charged. The Contractor shall begin
the work to be performed under the contract within 10 days of the date set by the Engineer in the written
notice to proceed, but in any event, the Contractor shall notify the Engineer at least 24 hours in advance
of the time actual construction operations will begin. The Contractor shall not commence any actual
construction prior to the date on which the notice to proceed is issued by the Owner.
80-03 Execution and progress. Unless otherwise specified, the Contractor shall submit their progress
schedule for the Engineer’s approval within 10 days after the effective date of the notice to proceed. The
Contractor’s progress schedule, when approved by the Engineer, may be used to establish major
construction operations and to check on the progress of the work. The Contractor shall provide sufficient
materials, equipment, and labor to guarantee the completion of the project in accordance with the plans
and specifications within the time set forth in the proposal.
If the Contractor falls significantly behind the submitted schedule, the Contractor shall, upon the
Engineer’s request, submit a revised schedule for completion of the work within the contract time and
modify their operations to provide such additional materials, equipment, and labor necessary to meet the
revised schedule. Should the execution of the work be discontinued for any reason, the Contractor shall
notify the Engineer at least 24 hours in advance of resuming operations.
The Contractor shall not commence any actual construction prior to the date on which the notice to
proceed is issued by the Owner.
80-04 Limitation of operations. The Contractor shall control his or her operations and the operations of
his or her subcontractors and all suppliers to provide for the free and unobstructed movement of aircraft in
the air operations areas (AOA) of the airport.
When the work requires the Contractor to conduct his or her operations within an AOA of the airport, the
work shall be coordinated with airport operations (through the Engineer) at least 48 hours prior to
commencement of such work. The Contractor shall not close an AOA until so authorized by the Engineer
and until the necessary temporary marking and associated lighting is in place as provided in the
subsection 70-08 titled BARRICADES, WARNING SIGNS, AND HAZARD MARKINGS of Section
70.
When the contract work requires the Contractor to work within an AOA of the airport on an intermittent
basis (intermittent opening and closing of the AOA), the Contractor shall maintain constant
communications as specified; immediately obey all instructions to vacate the AOA; immediately obey all
instructions to resume work in such AOA. Failure to maintain the specified communications or to obey
instructions shall be cause for suspension of the Contractor’s operations in the AOA until the satisfactory
conditions are provided. The following AOA cannot be closed to operating aircraft to permit the
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-32 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
Contractor’s operations on a continuous basis and will therefore be closed to aircraft operations
intermittently as follows:
None.
Contractor shall be required to conform to safety standards contained in AC 150/5370-2, Operational
Safety on Airports During Construction (see Special Provisions).
80-04.1 Operational safety on airport during construction. All Contractors’ operations shall be
conducted in accordance with the project Construction Safety and Phasing Plan (CSPP) and the
provisions set forth within the current version of AC 150/5370-2. The CSPP included within the contract
documents conveys minimum requirements for operational safety on the airport during construction
activities. The Contractor shall prepare and submit a Safety Plan Compliance Document that details how
it proposes to comply with the requirements presented within the CSPP.
The Contractor shall implement all necessary safety plan measures prior to commencement of any work
activity. The Contractor shall conduct routine checks to assure compliance with the safety plan measures.
The Contractor is responsible to the Owner for the conduct of all subcontractors it employs on the project.
The Contractor shall assure that all subcontractors are made aware of the requirements of the CSPP and
that they implement and maintain all necessary measures.
No deviation or modifications may be made to the approved CSPP unless approved in writing by the
Owner or Engineer.
80-05 Character of workers, methods, and equipment. The Contractor shall, at all times, employ
sufficient labor and equipment for prosecuting the work to full completion in the manner and time
required by the contract, plans, and specifications.
All workers shall have sufficient skill and experience to perform properly the work assigned to them.
Workers engaged in special work or skilled work shall have sufficient experience in such work and in the
operation of the equipment required to perform the work satisfactorily.
Any person employed by the Contractor or by any subcontractor who violates any operational regulations
or operational safety requirements and, in the opinion of the Engineer, does not perform his work in a
proper and skillful manner or is intemperate or disorderly shall, at the written request of the Engineer, be
removed forthwith by the Contractor or subcontractor employing such person, and shall not be employed
again in any portion of the work without approval of the Engineer.
Should the Contractor fail to remove such persons or person, or fail to furnish suitable and sufficient
personnel for the proper execution of the work, the Engineer may suspend the work by written notice until
compliance with such orders.
All equipment that is proposed to be used on the work shall be of sufficient size and in such mechanical
condition as to meet requirements of the work and to produce a satisfactory quality of work. Equipment
used on any portion of the work shall be such that no injury to previously completed work, adjacent
property, or existing airport facilities will result from its use.
When the methods and equipment to be used by the Contractor in accomplishing the work are not
prescribed in the contract, the Contractor is free to use any methods or equipment that will accomplish the
work in conformity with the requirements of the contract, plans, and specifications.
When the contract specifies the use of certain methods and equipment, such methods and equipment shall
be used unless others are authorized by the Engineer. If the Contractor desires to use a method or type of
equipment other than specified in the contract, the Contractor may request authority from the Engineer to
do so. The request shall be in writing and shall include a full description of the methods and equipment
proposed and of the reasons for desiring to make the change. If approval is given, it will be on the
condition that the Contractor will be fully responsible for producing work in conformity with contract
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-33
Reference: AC 150/5370-10G (7/21/2014)
requirements. If, after trial use of the substituted methods or equipment, the Engineer determines that the
work produced does not meet contract requirements, the Contractor shall discontinue the use of the
substitute method or equipment and shall complete the remaining work with the specified methods and
equipment. The Contractor shall remove any deficient work and replace it with work of specified quality,
or take such other corrective action as the Engineer may direct. No change will be made in basis of
payment for the contract items involved nor in contract time as a result of authorizing a change in
methods or equipment under this subsection.
80-06 Temporary suspension of the work. The Owner shall have the authority to suspend the work
wholly, or in part, for such period or periods as the Owner may deem necessary, due to unsuitable
weather, or such other conditions as are considered unfavorable for the execution of the work, or for such
time as is necessary due to the failure on the part of the Contractor to carry out orders given or perform
any or all provisions of the contract.
In the event that the Contractor is ordered by the Owner, in writing, to suspend work for some unforeseen
cause not otherwise provided for in the contract and over which the Contractor has no control, the
Contractor may be reimbursed for actual money expended on the work during the period of shutdown. No
allowance will be made for anticipated profits. The period of shutdown shall be computed from the
effective date of the Engineer’s order to suspend work to the effective date of the Engineer’s order to
resume the work. Claims for such compensation shall be filed with the Engineer within the time period
stated in the Engineer’s order to resume work. The Contractor shall submit with his or her claim
information substantiating the amount shown on the claim. The Engineer will forward the Contractor’s
claim to the Owner for consideration in accordance with local laws or ordinances. No provision of this
article shall be construed as entitling the Contractor to compensation for delays due to inclement weather,
for suspensions made at the request of the Owner, or for any other delay provided for in the contract,
plans, or specifications.
If it should become necessary to suspend work for an indefinite period, the Contractor shall store all
materials in such manner that they will not become an obstruction nor become damaged in any way. The
Contractor shall take every precaution to prevent damage or deterioration of the work performed and
provide for normal drainage of the work. The Contractor shall erect temporary structures where necessary
to provide for traffic on, to, or from the airport.
80-07 Determination and extension of contract time. The number of calendar or working days allowed
for completion of the work shall be stated in the proposal and contract and shall be known as the
CONTRACT TIME.
Should the contract time require extension for reasons beyond the Contractor’s control, it shall be
adjusted as follows:
a. CONTRACT TIME based on WORKING DAYS shall be calculated weekly by the Engineer. The
Engineer will furnish the Contractor a copy of his or her weekly statement of the number of working days
charged against the contract time during the week and the number of working days currently specified for
completion of the contract (the original contract time plus the number of working days, if any, that have
been included in approved CHANGE ORDERS or SUPPLEMENTAL AGREEMENTS covering
EXTRA WORK).
The Engineer shall base his or her weekly statement of contract time charged on the following
considerations:
(1) No time shall be charged for days on which the Contractor is unable to proceed with the
principal item of work under construction at the time for at least six (6) hours with the normal work force
employed on such principal item. Should the normal work force be on a double-shift, 12 hours shall be
used. Should the normal work force be on a triple-shift, 18 hours shall apply. Conditions beyond the
Contractor’s control such as strikes, lockouts, unusual delays in transportation, temporary suspension of
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-34 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
the principal item of work under construction or temporary suspension of the entire work which have
been ordered by the Owner for reasons not the fault of the Contractor, shall not be charged against the
contract time.
(2) The Engineer will not make charges against the contract time prior to the effective date of the
notice to proceed.
(3) The Engineer will begin charges against the contract time on the first working day after the
effective date of the notice to proceed.
(4) The Engineer will not make charges against the contract time after the date of final acceptance
as defined in the subsection 50-15 titled FINAL ACCEPTANCE of Section 50.
(5) The Contractor will be allowed one (1) week in which to file a written protest setting forth his
or her objections to the Engineer’s weekly statement. If no objection is filed within such specified time,
the weekly statement shall be considered as acceptable to the Contractor.
The contract time (stated in the proposal) is based on the originally estimated quantities as described in
the subsection 20-05 titled INTERPRETATION OF ESTIMATED PROPOSAL QUANTITIES of
Section 20. Should the satisfactory completion of the contract require performance of work in greater
quantities than those estimated in the proposal, the contract time shall be increased in the same proportion
as the cost of the actually completed quantities bears to the cost of the originally estimated quantities in
the proposal. Such increase in contract time shall not consider either the cost of work or the extension of
contract time that has been covered by change order or supplemental agreement and shall be made at the
time of final payment.
b. Contract Time based on calendar days shall consist of the number of calendar days stated in the
contract counting from the effective date of the notice to proceed and including all Saturdays, Sundays,
holidays, and non-work days. All calendar days elapsing between the effective dates of the Owner’s
orders to suspend and resume all work, due to causes not the fault of the Contractor, shall be excluded.
At the time of final payment, the contract time shall be increased in the same proportion as the cost of
the actually completed quantities bears to the cost of the originally estimated quantities in the proposal.
Such increase in the contract time shall not consider either cost of work or the extension of contract time
that has been covered by a change order or supplemental agreement. Charges against the contract time
will cease as of the date of final acceptance.
c. When the contract time is a specified completion date, it shall be the date on which all contract
work shall be substantially complete.
If the Contractor finds it impossible for reasons beyond his or her control to complete the work within the
contract time as specified, or as extended in accordance with the provisions of this subsection, the
Contractor may, at any time prior to the expiration of the contract time as extended, make a written
request to the Owner for an extension of time setting forth the reasons which the Contractor believes will
justify the granting of his or her request. Requests for extension of time on calendar day projects, caused
by inclement weather, shall be supported with National Weather Bureau data showing the actual amount
of inclement weather exceeded what could normally be expected during the contract period. The
Contractor’s plea that insufficient time was specified is not a valid reason for extension of time. If the
supporting documentation justify the work was delayed because of conditions beyond the control and
without the fault of the Contractor, the Owner may extend the time for completion by a change order that
adjusts the contract time or completion date. The extended time for completion shall then be in full force
and effect, the same as though it were the original time for completion.
80-08 Failure to complete on time. For each calendar day or working day, as specified in the contract,
that any work remains uncompleted after the contract time (including all extensions and adjustments as
provided in the subsection 80-07 titled DETERMINATION AND EXTENSION OF CONTRACT TIME
of this Section) the sum specified in the contract and proposal as liquidated damages will be deducted
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-35
Reference: AC 150/5370-10G (7/21/2014)
from any money due or to become due the Contractor or his or her surety. Such deducted sums shall not
be deducted as a penalty but shall be considered as liquidation of a reasonable portion of damages
including but not limited to additional engineering services that will be incurred by the Owner should the
Contractor fail to complete the work in the time provided in their contract.
The maximum construction time allowed for Schedules [ ] will be the sum of the time allowed for
individual schedules but not more than [ ] days is stipulated in the Construction Agreement. Permitting
the Contractor to continue and finish the work or any part of it after the time fixed for its completion, or
after the date to which the time for completion may have been extended, will in no way operate as a
wavier on the part of the Owner of any of its rights under the contract.
80-09 Default and termination of contract. The Contractor shall be considered in default of his or her
contract and such default will be considered as cause for the Owner to terminate the contract for any of
the following reasons if the Contractor:
a. Fails to begin the work under the contract within the time specified in the Notice to Proceed, or
b. Fails to perform the work or fails to provide sufficient workers, equipment and/or materials to
assure completion of work in accordance with the terms of the contract, or
c. Performs the work unsuitably or neglects or refuses to remove materials or to perform anew such
work as may be rejected as unacceptable and unsuitable, or
d. Discontinues the execution of the work, or
e. Fails to resume work which has been discontinued within a reasonable time after notice to do so, or
f. Becomes insolvent or is declared bankrupt, or commits any act of bankruptcy or insolvency, or
g. Allows any final judgment to stand against the Contractor unsatisfied for a period of 10 days, or
h. Makes an assignment for the benefit of creditors, or
i. For any other cause whatsoever, fails to carry on the work in an acceptable manner.
Should the Engineer consider the Contractor in default of the contract for any reason above, the Engineer
shall immediately give written notice to the Contractor and the Contractor’s surety as to the reasons for
considering the Contractor in default and the Owner’s intentions to terminate the contract.
If the Contractor or surety, within a period of 10 days after such notice, does not proceed in accordance
therewith, then the Owner will, upon written notification from the Engineer of the facts of such delay,
neglect, or default and the Contractor’s failure to comply with such notice, have full power and authority
without violating the contract, to take the execution of the work out of the hands of the Contractor. The
Owner may appropriate or use any or all materials and equipment that have been mobilized for use in the
work and are acceptable and may enter into an agreement for the completion of said contract according to
the terms and provisions thereof, or use such other methods as in the opinion of the Engineer will be
required for the completion of said contract in an acceptable manner.
All costs and charges incurred by the Owner, together with the cost of completing the work under
contract, will be deducted from any monies due or which may become due the Contractor. If such
expense exceeds the sum which would have been payable under the contract, then the Contractor and the
surety shall be liable and shall pay to the Owner the amount of such excess.
80-10 Termination for national emergencies. The Owner shall terminate the contract or portion thereof
by written notice when the Contractor is prevented from proceeding with the construction contract as a
direct result of an Executive Order of the President with respect to the execution of war or in the interest
of national defense.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-36 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
When the contract, or any portion thereof, is terminated before completion of all items of work in the
contract, payment will be made for the actual number of units or items of work completed at the contract
price or as mutually agreed for items of work partially completed or not started. No claims or loss of
anticipated profits shall be considered.
Reimbursement for organization of the work, and other overhead expenses, (when not otherwise included
in the contract) and moving equipment and materials to and from the job will be considered, the intent
being that an equitable settlement will be made with the Contractor.
Acceptable materials, obtained or ordered by the Contractor for the work and that are not incorporated in
the work shall, at the option of the Contractor, be purchased from the Contractor at actual cost as shown
by receipted bills and actual cost records at such points of delivery as may be designated by the Engineer.
Termination of the contract or a portion thereof shall neither relieve the Contractor of his or her
responsibilities for the completed work nor shall it relieve his or her surety of its obligation for and
concerning any just claim arising out of the work performed.
80-11 Work area, storage area and sequence of operations. The Contractor shall obtain approval from
the Engineer prior to beginning any work in all areas of the airport. No operating runway, taxiway, or air
operations area (AOA) shall be crossed, entered, or obstructed while it is operational. The Contractor
shall plan and coordinate his or her work in such a manner as to ensure safety and a minimum of
hindrance to flight operations. All Contractor equipment and material stockpiles shall be stored a
minimum or 250 feet from the centerline of an active runway. No equipment will be allowed to park
within the approach area of an active runway at any time. No equipment shall be within 250 feet of an
active runway at any time.
END OF SECTION 80
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-37
Reference: AC 150/5370-10G (7/21/2014)
Section 90 Measurement and Payment
90-01 Measurement of quantities. All work completed under the contract will be measured by the
Engineer, or his or her authorized representatives, using United States Customary Units of Measurement
or the International System of Units.
The method of measurement and computations to be used in determination of quantities of material
furnished and of work performed under the contract will be those methods generally recognized as
conforming to good engineering practice.
Unless otherwise specified, longitudinal measurements for area computations will be made horizontally,
and no deductions will be made for individual fixtures (or leave-outs) having an area of 9 square feet (0.8
square meters) or less. Unless otherwise specified, transverse measurements for area computations will be
the neat dimensions shown on the plans or ordered in writing by the Engineer.
Structures will be measured according to neat lines shown on the plans or as altered to fit field conditions.
Unless otherwise specified, all contract items which are measured by the linear foot such as electrical
ducts, conduits, pipe culverts, underdrains, and similar items shall be measured parallel to the base or
foundation upon which such items are placed.
In computing volumes of excavation the average end area method or other acceptable methods will be
used.
The thickness of plates and galvanized sheet used in the manufacture of corrugated metal pipe, metal
plate pipe culverts and arches, and metal cribbing will be specified and measured in decimal fraction of
inch.
The term “ton” will mean the short ton consisting of 2,000 lb (907 km) avoirdupois. All materials that are
measured or proportioned by weights shall be weighed on accurate, approved scales by competent,
qualified personnel at locations designed by the Engineer. If material is shipped by rail, the car weight
may be accepted provided that only the actual weight of material is paid for. However, car weights will
not be acceptable for material to be passed through mixing plants. Trucks used to haul material being paid
for by weight shall be weighed empty daily at such times as the Engineer directs, and each truck shall
bear a plainly legible identification mark.
Materials to be measured by volume in the hauling vehicle shall be hauled in approved vehicles and
measured therein at the point of delivery. Vehicles for this purpose may be of any size or type acceptable
for the materials hauled, provided that the body is of such shape that the actual contents may be readily
and accurately determined. All vehicles shall be loaded to at least their water level capacity, and all loads
shall be leveled when the vehicles arrive at the point of delivery.
When requested by the Contractor and approved by the Engineer in writing, material specified to be
measured by the cubic yard (cubic meter) may be weighed, and such weights will be converted to cubic
yards (cubic meters) for payment purposes. Factors for conversion from weight measurement to volume
measurement will be determined by the Engineer and shall be agreed to by the Contractor before such
method of measurement of pay quantities is used.
Bituminous materials will be measured by the gallon (liter) or ton (kg). When measured by volume, such
volumes will be measured at 60°F (16°C) or will be corrected to the volume at 60°F (16°C) using ASTM
D1250 for asphalts or ASTM D633 for tars.
Net certified scale weights or weights based on certified volumes in the case of rail shipments will be
used as a basis of measurement, subject to correction when bituminous material has been lost from the car
or the distributor, wasted, or otherwise not incorporated in the work.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-38 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
When bituminous materials are shipped by truck or transport, net certified weights by volume, subject to
correction for loss or foaming, may be used for computing quantities.
Cement will be measured by the ton (kg) or hundredweight (km).
Timber will be measured by the thousand feet board measure (MFBM) actually incorporated in the
structure. Measurement will be based on nominal widths and thicknesses and the extreme length of each
piece.
The term “lump sum” when used as an item of payment will mean complete payment for the work
described in the contract.
When a complete structure or structural unit (in effect, “lump sum” work) is specified as the unit of
measurement, the unit will be construed to include all necessary fittings and accessories.
Rental of equipment will be measured by time in hours of actual working time and necessary traveling
time of the equipment within the limits of the work. Special equipment ordered by the Engineer in
connection with force account work will be measured as agreed in the change order or supplemental
agreement authorizing such force account work as provided in the subsection 90-05 titled PAYMENT
FOR EXTRA WORK of this section.
When standard manufactured items are specified such as fence, wire, plates, rolled shapes, pipe conduit,
etc., and these items are identified by gauge, unit weight, section dimensions, etc., such identification will
be considered to be nominal weights or dimensions. Unless more stringently controlled by tolerances in
cited specifications, manufacturing tolerances established by the industries involved will be accepted.
Scales for weighing materials which are required to be proportioned or measured and paid for by weight
shall be furnished, erected, and maintained by the Contractor, or be certified permanently installed
commercial scales.
Scales shall be accurate within 1/2% of the correct weight throughout the range of use. The Contractor
shall have the scales checked under the observation of the inspector before beginning work and at such
other times as requested. The intervals shall be uniform in spacing throughout the graduated or marked
length of the beam or dial and shall not exceed one-tenth of 1% of the nominal rated capacity of the scale,
but not less than 1 pound (454 grams). The use of spring balances will not be permitted.
Beams, dials, platforms, and other scale equipment shall be so arranged that the operator and the inspector
can safely and conveniently view them.
Scale installations shall have available ten standard 50-pound (2.3 km) weights for testing the weighing
equipment or suitable weights and devices for other approved equipment.
Scales must be tested for accuracy and serviced before use at a new site. Platform scales shall be installed
and maintained with the platform level and rigid bulkheads at each end.
Scales “overweighing” (indicating more than correct weight) will not be permitted to operate, and all
materials received subsequent to the last previous correct weighting-accuracy test will be reduced by the
percentage of error in excess of one-half of 1%.
In the event inspection reveals the scales have been underweighing (indicating less than correct weight),
they shall be adjusted, and no additional payment to the Contractor will be allowed for materials
previously weighed and recorded.
All costs in connection with furnishing, installing, certifying, testing, and maintaining scales; for
furnishing check weights and scale house; and for all other items specified in this subsection, for the
weighing of materials for proportioning or payment, shall be included in the unit contract prices for the
various items of the project.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-39
Reference: AC 150/5370-10G (7/21/2014)
When the estimated quantities for a specific portion of the work are designated as the pay quantities in the
contract, they shall be the final quantities for which payment for such specific portion of the work will be
made, unless the dimensions of said portions of the work shown on the plans are revised by the Engineer.
If revised dimensions result in an increase or decrease in the quantities of such work, the final quantities
for payment will be revised in the amount represented by the authorized changes in the dimensions.
90-02 Scope of payment. The Contractor shall receive and accept compensation provided for in the
contract as full payment for furnishing all materials, for performing all work under the contract in a
complete and acceptable manner, and for all risk, loss, damage, or expense of whatever character arising
out of the nature of the work or the execution thereof, subject to the provisions of the subsection 70-18
titled NO WAIVER OF LEGAL RIGHTS of Section 70.
When the “basis of payment” subsection of a technical specification requires that the contract price (price
bid) include compensation for certain work or material essential to the item, this same work or material
will not also be measured for payment under any other contract item which may appear elsewhere in the
contract, plans, or specifications.
90-03 Compensation for altered quantities. When the accepted quantities of work vary from the
quantities in the proposal, the Contractor shall accept as payment in full, so far as contract items are
concerned, payment at the original contract price for the accepted quantities of work actually completed
and accepted. No allowance, except as provided for in the subsection 40-02 titled ALTERATION OF
WORK AND QUANTITIES of Section 40 will be made for any increased expense, loss of expected
reimbursement, or loss of anticipated profits suffered or claimed by the Contractor which results directly
from such alterations or indirectly from his or her unbalanced allocation of overhead and profit among the
contract items, or from any other cause.
90-04 Payment for omitted items. As specified in the subsection 40-03 titled OMITTED ITEMS of
Section 40, the Engineer shall have the right to omit from the work (order nonperformance) any contract
item, except major contract items, in the best interest of the Owner.
Should the Engineer omit or order nonperformance of a contract item or portion of such item from the
work, the Contractor shall accept payment in full at the contract prices for any work actually completed
and acceptable prior to the Engineer’s order to omit or non-perform such contract item.
Acceptable materials ordered by the Contractor or delivered on the work prior to the date of the
Engineer’s order will be paid for at the actual cost to the Contractor and shall thereupon become the
property of the Owner.
In addition to the reimbursement hereinbefore provided, the Contractor shall be reimbursed for all actual
costs incurred for the purpose of performing the omitted contract item prior to the date of the Engineer’s
order. Such additional costs incurred by the Contractor must be directly related to the deleted contract
item and shall be supported by certified statements by the Contractor as to the nature the amount of such
costs.
90-05 Payment for extra work. Extra work, performed in accordance with the subsection 40-04 titled
EXTRA WORK of Section 40, will be paid for at the contract prices or agreed prices specified in the
change order or supplemental agreement authorizing the extra work.
90-06 Partial payments. Partial payments will be made to the Contractor at least once each month as the
work progresses. Said payments will be based upon estimates, prepared by the Engineer, of the value of
the work performed and materials complete and in place, in accordance with the contract, plans, and
specifications. Such partial payments may also include the delivered actual cost of those materials
stockpiled and stored in accordance with the subsection 90-07 titled PAYMENT FOR MATERIALS ON
HAND of this section. No partial payment will be made when the amount due to the Contractor since the
last estimate amounts to less than five hundred dollars.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-40 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
The Contractor is required to pay all subcontractors for satisfactory performance of their contracts no later
than 30 days after the Contractor has received a partial payment. The Owner must ensure prompt and full
payment of retainage from the prime Contractor to the subcontractor within 30 days after the
subcontractor’s work is satisfactorily completed. A subcontractor’s work is satisfactorily completed when
all the tasks called for in the subcontract have been accomplished and documented as required by the
Owner. When the Owner has made an incremental acceptance of a portion of a prime contract, the work
of a subcontractor covered by that acceptance is deemed to be satisfactorily completed.
From the total of the amount determined to be payable on a partial payment, 10 percent of such total
amount will be deducted and retained by the Owner until the final payment is made, except as may be
provided (at the Contractor’s option) in the subsection 90-08 titled PAYMENT OF WITHHELD FUNDS
of this section. The balance 90% of the amount payable, less all previous payments, shall be certified for
payment. Should the Contractor exercise his or her option, as provided in the subsection 90-08 titled
PAYMENT OF WITHHELD FUNDS of this section, no such percent retainage shall be deducted.
When at least 95% of the work has been completed, the Engineer shall, at the Owner’s discretion and with
the consent of the surety, prepare estimates of both the contract value and the cost of the remaining work
to be done.
The Owner may retain an amount not less than twice the contract value or estimated cost, whichever is
greater, of the work remaining to be done. The remainder, less all previous payments and deductions, will
then be certified for payment to the Contractor.
It is understood and agreed that the Contractor shall not be entitled to demand or receive partial payment
based on quantities of work in excess of those provided in the proposal or covered by approved change
orders or supplemental agreements, except when such excess quantities have been determined by the
Engineer to be a part of the final quantity for the item of work in question.
No partial payment shall bind the Owner to the acceptance of any materials or work in place as to quality
or quantity. All partial payments are subject to correction at the time of final payment as provided in the
subsection 90-09 titled ACCEPTANCE AND FINAL PAYMENT of this section.
The Contractor shall deliver to the Owner a complete release of all claims for labor and material arising
out of this contract before the final payment is made. If any subcontractor or supplier fails to furnish such
a release in full, the Contractor may furnish a bond or other collateral satisfactory to the Owner to
indemnify the Owner against any potential lien or other such claim. The bond or collateral shall include
all costs, expenses, and attorney fees the Owner may be compelled to pay in discharging any such lien or
claim.
90-07 Payment for materials on hand. Partial payments may be made to the extent of the delivered cost
of materials to be incorporated in the work, provided that such materials meet the requirements of the
contract, plans, and specifications and are delivered to acceptable sites on the airport property or at other
sites in the vicinity that are acceptable to the Owner. Such delivered costs of stored or stockpiled
materials may be included in the next partial payment after the following conditions are met:
a. The material has been stored or stockpiled in a manner acceptable to the Engineer at or on an
approved site.
b. The Contractor has furnished the Engineer with acceptable evidence of the quantity and quality of
such stored or stockpiled materials.
c. The Contractor has furnished the Engineer with satisfactory evidence that the material and
transportation costs have been paid.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-41
Reference: AC 150/5370-10G (7/21/2014)
d. The Contractor has furnished the Owner legal title (free of liens or encumbrances of any kind) to
the material so stored or stockpiled.
e. The Contractor has furnished the Owner evidence that the material so stored or stockpiled is
insured against loss by damage to or disappearance of such materials at any time prior to use in the work.
It is understood and agreed that the transfer of title and the Owner’s payment for such stored or stockpiled
materials shall in no way relieve the Contractor of his or her responsibility for furnishing and placing such
materials in accordance with the requirements of the contract, plans, and specifications.
In no case will the amount of partial payments for materials on hand exceed the contract price for such
materials or the contract price for the contract item in which the material is intended to be used.
No partial payment will be made for stored or stockpiled living or perishable plant materials.
The Contractor shall bear all costs associated with the partial payment of stored or stockpiled materials in
accordance with the provisions of this subsection.
90-08 Payment of withheld funds. At the Contractor’s option, if an Owner withholds retainage in
accordance with the methods described in subsection 90-06 PARTIAL PAYMENTS, the Contractor may
request that the Owner deposit the retainage into an escrow account. The Owner’s deposit of retainage
into an escrow account is subject to the following conditions:
a. The Contractor shall bear all expenses of establishing and maintaining an escrow account and
escrow agreement acceptable to the Owner.
b. The Contractor shall deposit to and maintain in such escrow only those securities or bank
certificates of deposit as are acceptable to the Owner and having a value not less than the retainage that
would otherwise be withheld from partial payment.
c. The Contractor shall enter into an escrow agreement satisfactory to the Owner.
d. The Contractor shall obtain the written consent of the surety to such agreement.
90-09 Acceptance and final payment. When the contract work has been accepted in accordance with the
requirements of the subsection 50-15 titled FINAL ACCEPTANCE of Section 50, the Engineer will
prepare the final estimate of the items of work actually performed. The Contractor shall approve the
Engineer’s final estimate or advise the Engineer of the Contractor’s objections to the final estimate which
are based on disputes in measurements or computations of the final quantities to be paid under the
contract as amended by change order or supplemental agreement. The Contractor and the Engineer shall
resolve all disputes (if any) in the measurement and computation of final quantities to be paid within 30
calendar days of the Contractor’s receipt of the Engineer’s final estimate. If, after such 30-day period, a
dispute still exists, the Contractor may approve the Engineer’s estimate under protest of the quantities in
dispute, and such disputed quantities shall be considered by the Owner as a claim in accordance with the
subsection 50-16 titled CLAIMS FOR ADJUSTMENT AND DISPUTES of Section 50.
After the Contractor has approved, or approved under protest, the Engineer’s final estimate, and after the
Engineer’s receipt of the project closeout documentation required in subsection 90-11 Project Closeout,
final payment will be processed based on the entire sum, or the undisputed sum in case of approval under
protest, determined to be due the Contractor less all previous payments and all amounts to be deducted
under the provisions of the contract. All prior partial estimates and payments shall be subject to correction
in the final estimate and payment.
If the Contractor has filed a claim for additional compensation under the provisions of the subsection 50-
16 titled CLAIMS FOR ADJUSTMENTS AND DISPUTES of Section 50 or under the provisions of this
subsection, such claims will be considered by the Owner in accordance with local laws or ordinances.
Upon final adjudication of such claims, any additional payment determined to be due the Contractor will
be paid pursuant to a supplemental final estimate.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-42 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
90-10 Construction warranty.
a. In addition to any other warranties in this contract, the Contractor warrants that work performed
under this contract conforms to the contract requirements and is free of any defect in equipment, material,
workmanship, or design furnished, or performed by the Contractor or any subcontractor or supplier at any
tier.
b. This warranty shall continue for a period of one year from the date of final acceptance of the work.
If the Owner takes possession of any part of the work before final acceptance, this warranty shall continue
for a period of one year from the date the Owner takes possession. However, this will not relieve the
Contractor from corrective items required by the final acceptance of the project work.
c. The Contractor shall remedy at the Contractor’s expense any failure to conform, or any defect. In
addition, the Contractor shall remedy at the Contractor’s expense any damage to Owner real or personal
property, when that damage is the result of:
(1) The Contractor’s failure to conform to contract requirements; or
(2) Any defect of equipment, material, workmanship, or design furnished by the Contractor.
d. The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause.
The Contractor’s warranty with respect to work repaired or replaced will run for one year from the date of
repair or replacement.
e. The Owner will notify the Contractor, in writing, within seven (7) days after the discovery of any
failure, defect, or damage.
f. If the Contractor fails to remedy any failure, defect, or damage within 14 days after receipt of
notice, the Owner shall have the right to replace, repair, or otherwise remedy the failure, defect, or
damage at the Contractor’s expense.
g. With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers
for work performed and materials furnished under this contract, the Contractor shall: (1) Obtain all
warranties that would be given in normal commercial practice; (2) Require all warranties to be executed,
in writing, for the benefit of the Owner, as directed by the Owner, and (3) Enforce all warranties for the
benefit of the Owner.
h. This warranty shall not limit the Owner’s rights with respect to latent defects, gross mistakes, or
fraud.
90-11 Project closeout. Approval of final payment to the Contractor is contingent upon completion and
submittal of the items listed below. The final payment will not be approved until the Engineer approves
the Contractor’s final submittal. The Contractor shall:
a. Provide two (2) copies of all manufacturers warranties specified for materials, equipment, and
installations.
b. Provide weekly payroll records (not previously received) from the general Contractor and all
subcontractors.
c. Complete final cleanup in accordance with subsection 40-08, FINAL CLEANUP.
d. Complete all punch list items identified during the Final Inspection.
e. Provide complete release of all claims for labor and material arising out of the Contract.
f. Provide a certified statement signed by the subcontractors, indicating actual amounts paid to the
Disadvantaged Business Enterprise (DBE) subcontractors and/or suppliers associated with the project.
g. When applicable per state requirements, return copies of sales tax completion forms.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-43
Reference: AC 150/5370-10G (7/21/2014)
h. Manufacturer's certifications for all items incorporated in the work.
i. All required record drawings, as-built drawings or as-constructed drawings.
j. Project Operation and Maintenance (O&M) Manual.
k. Security for Construction Warranty.
l. Equipment commissioning documentation submitted, if required.
END OF SECTION 90
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-44 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
Intentionally Left Blank
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-45
Reference: AC 150/5370-10G (7/21/2014)
Section 100 Contractor Quality Control Program
100-01 General. When the specification requires a Contractor Quality Control Program, the Contractor
shall establish, provide, and maintain an effective Quality Control Program that details the methods and
procedures that will be taken to assure that all materials and completed construction required by this
contract conform to contract plans, technical specifications and other requirements, whether manufactured
by the Contractor, or procured from subcontractors or vendors. Although guidelines are established and
certain minimum requirements are specified here and elsewhere in the contract technical specifications,
the Contractor shall assume full responsibility for accomplishing the stated purpose.
The intent of this section is to enable the Contractor to establish a necessary level of control that will:
a. Adequately provide for the production of acceptable quality materials.
b. Provide sufficient information to assure both the Contractor and the Engineer that the specification
requirements can be met.
c. Allow the Contractor as much latitude as possible to develop his or her own standard of control.
The Contractor shall be prepared to discuss and present, at the preconstruction conference, their
understanding of the quality control requirements. The Contractor shall not begin any construction or
production of materials to be incorporated into the completed work until the Quality Control Program has
been reviewed and accepted by the Engineer. No partial payment will be made for materials subject to
specific quality control requirements until the Quality Control Program has been reviewed.
The quality control requirements contained in this section and elsewhere in the contract technical
specifications are in addition to and separate from the acceptance testing requirements. Acceptance testing
requirements are the responsibility of the Engineer.
Paving projects over $500,000 shall have a Quality Control (QC)/Quality Assurance (QA) workshop with
the Engineer, Contractor, subcontractors, testing laboratories, and Owner’s representative at start of
construction. The workshop shall address QC and QA requirements of the project specifications. The
Contractor shall coordinate with the Airport and the Engineer on time and location of the QC/QA
workshop.
100-02 Description of program.
a. General description. The Contractor shall establish a Quality Control Program to perform quality
control inspection and testing of all items of work required by the technical specifications, including those
performed by subcontractors. This Quality Control Program shall ensure conformance to applicable
specifications and plans with respect to materials, workmanship, construction, finish, and functional
performance. The Quality Control Program shall be effective for control of all construction work
performed under this Contract and shall specifically include surveillance and tests required by the
technical specifications, in addition to other requirements of this section and any other activities deemed
necessary by the Contractor to establish an effective level of quality control.
b. Quality Control Program. The Contractor shall describe the Quality Control Program in a written
document that shall be reviewed and approved by the Engineer prior to the start of any production,
construction, or off-site fabrication. The written Quality Control Program shall be submitted to the
Engineer for review and approval at least 10 calendar days before the preconstruction meeting. The
Contractor’s Quality Control Plan and Quality Control testing laboratory must be approved in writing by
the Engineer prior to the Notice to Proceed (NTP).
The Quality Control Program shall be organized to address, as a minimum, the following items:
a. Quality control organization
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-46 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
b. Project progress schedule
c. Submittals schedule
d. Inspection requirements
e. Quality control testing plan
f. Documentation of quality control activities
g. Requirements for corrective action when quality control and/or acceptance criteria are not met
The Contractor is encouraged to add any additional elements to the Quality Control Program that is
deemed necessary to adequately control all production and/or construction processes required by this
contract.
100-03 Quality control organization. The Contractor Quality Control Program shall be implemented by
the establishment of a separate quality control organization. An organizational chart shall be developed to
show all quality control personnel and how these personnel integrate with other management/production
and construction functions and personnel.
The organizational chart shall identify all quality control staff by name and function, and shall indicate
the total staff required to implement all elements of the Quality Control Program, including inspection
and testing for each item of work. If necessary, different technicians can be used for specific inspection
and testing functions for different items of work. If an outside organization or independent testing
laboratory is used for implementation of all or part of the Quality Control Program, the personnel
assigned shall be subject to the qualification requirements of paragraph 100-03a and 100-03b. The
organizational chart shall indicate which personnel are Contractor employees and which are provided by
an outside organization.
The quality control organization shall, as a minimum, consist of the following personnel:
a. Program Administrator. The Program Administrator shall be a full-time employee of the
Contractor, or a consultant engaged by the Contractor. The Program Administrator shall have a minimum
of five (5) years of experience in airport and/or highway construction and shall have had prior quality
control experience on a project of comparable size and scope as the contract.
Additional qualifications for the Program Administrator shall include at least one of the following
requirements:
(1) Professional Engineer with one (1) year of airport paving experience.
(2) Engineer-in-training with two (2) years of airport paving experience.
(3) An individual with three (3) years of highway and/or airport paving experience, with a
Bachelor of Science Degree in Civil Engineering, Civil Engineering Technology or Construction.
(4) Construction materials technician certified at Level III by the National Institute for
Certification in Engineering Technologies (NICET).
(5) Highway materials technician certified at Level III by NICET.
(6) Highway construction technician certified at Level III by NICET.
(7) A NICET certified engineering technician in Civil Engineering Technology with five (5)
years of highway and/or airport paving experience.
The Program Administrator shall have full authority to institute any and all actions necessary for the
successful implementation of the Quality Control Program to ensure compliance with the contract plans
and technical specifications. The Program Administrator shall report directly to a responsible officer of
the construction firm. The Program Administrator may supervise the Quality Control Program on more
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-47
Reference: AC 150/5370-10G (7/21/2014)
than one project provided that person can be at the job site within two (2) hours after being notified of a
problem.
b. Quality control technicians. A sufficient number of quality control technicians necessary to
adequately implement the Quality Control Program shall be provided. These personnel shall be either
Engineers, engineering technicians, or experienced craftsman with qualifications in the appropriate field
equivalent to NICET Level II or higher construction materials technician or highway construction
technician and shall have a minimum of two (2) years of experience in their area of expertise.
The quality control technicians shall report directly to the Program Administrator and shall perform
the following functions:
(1) Inspection of all materials, construction, plant, and equipment for conformance to the
technical specifications, and as required by subsection 100-06.
(2) Performance of all quality control tests as required by the technical specifications and
subsection 100-07.
(3) Performance of density tests for the Engineer when required by the technical specifications.
Certification at an equivalent level, by a state or nationally recognized organization will be acceptable
in lieu of NICET certification.
c. Staffing levels. The Contractor shall provide sufficient qualified quality control personnel to
monitor each work activity at all times. Where material is being produced in a plant for incorporation into
the work, separate plant and field technicians shall be provided at each plant and field placement location.
The scheduling and coordinating of all inspection and testing must match the type and pace of work
activity. The Quality Control Program shall state where different technicians will be required for different
work elements.
100-04 Project progress schedule. The Contractor shall submit a coordinated construction schedule for
all work activities. The schedule shall be prepared as a network diagram in Critical Path Method (CPM),
Program Evaluation and Review Technique (PERT), or other format, or as otherwise specified in the
contract. As a minimum, it shall provide information on the sequence of work activities, milestone dates,
and activity duration.
The Contractor shall maintain the work schedule and provide an update and analysis of the progress
schedule on a twice monthly basis, or as otherwise specified in the contract. Submission of the work
schedule shall not relieve the Contractor of overall responsibility for scheduling, sequencing, and
coordinating all work to comply with the requirements of the contract.
100-05 Submittals schedule. The Contractor shall submit a detailed listing of all submittals (for example,
mix designs, material certifications) and shop drawings required by the technical specifications. The
listing can be developed in a spreadsheet format and shall include:
a. Specification item number
b. Item description
c. Description of submittal
d. Specification paragraph requiring submittal
e. Scheduled date of submittal
100-06 Inspection requirements. Quality control inspection functions shall be organized to provide
inspections for all definable features of work, as detailed below. All inspections shall be documented by
the Contractor as specified by subsection 100-07.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-48 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
Inspections shall be performed daily to ensure continuing compliance with contract requirements until
completion of the particular feature of work. These shall include the following minimum requirements:
a. During plant operation for material production, quality control test results and periodic inspections
shall be used to ensure the quality of aggregates and other mix components, and to adjust and control mix
proportioning to meet the approved mix design and other requirements of the technical specifications. All
equipment used in proportioning and mixing shall be inspected to ensure its proper operating condition.
The Quality Control Program shall detail how these and other quality control functions will be
accomplished and used.
b. During field operations, quality control test results and periodic inspections shall be used to ensure
the quality of all materials and workmanship. All equipment used in placing, finishing, and compacting
shall be inspected to ensure its proper operating condition and to ensure that all such operations are in
conformance to the technical specifications and are within the plan dimensions, lines, grades, and
tolerances specified. The Program shall document how these and other quality control functions will be
accomplished and used.
100-07 Quality control testing plan. As a part of the overall Quality Control Program, the Contractor
shall implement a quality control testing plan, as required by the technical specifications. The testing plan
shall include the minimum tests and test frequencies required by each technical specification Item, as well
as any additional quality control tests that the Contractor deems necessary to adequately control
production and/or construction processes.
The testing plan can be developed in a spreadsheet fashion and shall, as a minimum, include the
following:
a. Specification item number (for example, P-401)
b. Item description (for example, Plant Mix Bituminous Pavements)
c. Test type (for example, gradation, grade, asphalt content)
d. Test standard (for example, ASTM or American Association of State Highway and Transportation
Officials (AASHTO) test number, as applicable)
e. Test frequency (for example, as required by technical specifications or minimum frequency when
requirements are not stated)
f. Responsibility (for example, plant technician)
g. Control requirements (for example, target, permissible deviations)
The testing plan shall contain a statistically-based procedure of random sampling for acquiring test
samples in accordance with ASTM D3665. The Engineer shall be provided the opportunity to witness
quality control sampling and testing.
All quality control test results shall be documented by the Contractor as required by subsection 100-08.
100-08 Documentation. The Contractor shall maintain current quality control records of all inspections
and tests performed. These records shall include factual evidence that the required inspections or tests
have been performed, including type and number of inspections or tests involved; results of inspections or
tests; nature of defects, deviations, causes for rejection, etc.; proposed remedial action; and corrective
actions taken.
These records must cover both conforming and defective or deficient features, and must include a
statement that all supplies and materials incorporated in the work are in full compliance with the terms of
the contract. Legible copies of these records shall be furnished to the Engineer daily. The records shall
cover all work placed subsequent to the previously furnished records and shall be verified and signed by
the Contractor’s Program Administrator.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-49
Reference: AC 150/5370-10G (7/21/2014)
Specific Contractor quality control records required for the contract shall include, but are not necessarily
limited to, the following records:
a. Daily inspection reports. Each Contractor quality control technician shall maintain a daily log of
all inspections performed for both Contractor and subcontractor operations. These technician’s daily
reports shall provide factual evidence that continuous quality control inspections have been performed
and shall, as a minimum, include the following:
(1) Technical specification item number and description
(2) Compliance with approved submittals
(3) Proper storage of materials and equipment
(4) Proper operation of all equipment
(5) Adherence to plans and technical specifications
(6) Review of quality control tests
(7) Safety inspection.
The daily inspection reports shall identify inspections conducted, results of inspections, location and
nature of defects found, causes for rejection, and remedial or corrective actions taken or proposed.
The daily inspection reports shall be signed by the responsible quality control technician and the Program
Administrator. The Engineer shall be provided at least one copy of each daily inspection report on the
work day following the day of record.
b. Daily test reports. The Contractor shall be responsible for establishing a system that will record
all quality control test results. Daily test reports shall document the following information:
(1) Technical specification item number and description
(2) Test designation
(3) Location
(4) Date of test
(5) Control requirements
(6) Test results
(7) Causes for rejection
(8) Recommended remedial actions
(9) Retests
Test results from each day’s work period shall be submitted to the Engineer prior to the start of the next
day’s work period. When required by the technical specifications, the Contractor shall maintain statistical
quality control charts. The daily test reports shall be signed by the responsible quality control technician
and the Program Administrator.
100-09 Corrective action requirements. The Quality Control Program shall indicate the appropriate
action to be taken when a process is deemed, or believed, to be out of control (out of tolerance) and detail
what action will be taken to bring the process into control. The requirements for corrective action shall
include both general requirements for operation of the Quality Control Program as a whole, and for
individual items of work contained in the technical specifications.
The Quality Control Program shall detail how the results of quality control inspections and tests will be
used for determining the need for corrective action and shall contain clear sets of rules to gauge when a
process is out of control and the type of correction to be taken to regain process control.
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-50 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
When applicable or required by the technical specifications, the Contractor shall establish and use
statistical quality control charts for individual quality control tests. The requirements for corrective action
shall be linked to the control charts.
100-10 Surveillance by the Engineer. All items of material and equipment shall be subject to
surveillance by the Engineer at the point of production, manufacture or shipment to determine if the
Contractor, producer, manufacturer or shipper maintains an adequate quality control system in
conformance with the requirements detailed here and the applicable technical specifications and plans. In
addition, all items of materials, equipment and work in place shall be subject to surveillance by the
Engineer at the site for the same purpose.
Surveillance by the Engineer does not relieve the Contractor of performing quality control inspections of
either on-site or off-site Contractor’s or subcontractor’s work.
100-11 Noncompliance.
a. The Engineer will notify the Contractor of any noncompliance with any of the foregoing
requirements. The Contractor shall, after receipt of such notice, immediately take corrective action. Any
notice, when delivered by the Engineer or his or her authorized representative to the Contractor or his or
her authorized representative at the site of the work, shall be considered sufficient notice.
b. In cases where quality control activities do not comply with either the Contractor Quality Control
Program or the contract provisions, or where the Contractor fails to properly operate and maintain an
effective Quality Control Program, as determined by the Engineer, the Engineer may:
(1) Order the Contractor to replace ineffective or unqualified quality control personnel or
subcontractors.
(2) Order the Contractor to stop operations until appropriate corrective actions are taken.
END OF SECTION 100
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GENERAL PROVISIONS GP-51
Reference: AC 150/5370-10G (7/21/2014)
Section 105 Mobilization
105-1 Description. This item shall consist of work and operations, but is not limited to, work and
operations necessary for the movement of personnel, equipment, material and supplies to and from the
project site for work on the project except as provided in the contract as separate pay items.
105-1.1 Posted notices. Prior to commencement of construction activities the Contractor must post the
following documents in a prominent and accessible place where they may be easily viewed by all
employees of the prime Contractor and by all employees of subcontractors engaged by the prime
Contractor: Equal Employment Opportunity (EEO) Poster “Equal Employment Opportunity is the Law”
in accordance with the Office of Federal Contract Compliance Programs Executive Order 11246, as
amended; Davis Bacon Wage Poster (WH 1321) - DOL “Notice to All Employees” Poster; and
Applicable Davis-Bacon Wage Rate Determination. These notices must remain posted until final
acceptance of the work by the Owner.
105-2 Basis of measurement and payment. Based upon the contract lump sum price for “Mobilization”
partial payments will be allowed as follows:
a. With first pay request, 25%.
b. When 25% or more of the original contract is earned, an additional 25%.
c. When 50% or more of the original contract is earned, an additional 40%.
d. After Final Inspection, Staging area clean-up and delivery of all Project Closeout materials as
required by 90-11, the final 10%.
END OF SECTION 105
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
GP-52 GENERAL PROVISIONS
Reference: AC 150/5370-10G (7/21/2014)
Intentionally Left Blank
IMMOKALEE REGIONAL AIRPORT
60% DESIGN SUBMITTAL REHABILITATION OF TAXIWAY B
SURFACE PREPARATION GP-53
Reference: AC 150/5370-10G (7/21/2014)
Section 110 Method of Estimating Percentage of Material Within Specification Limits
(PWL)
110-01 General. When the specifications provide for acceptance of material based on the method of
estimating percentage of material within specification limits (PWL), the PWL will be determined in
accordance with this section. All test results for a lot will be analyzed statistically to determine the total
estimated percent of the lot that is within specification limits. The PWL is computed using the sample
average (X) and sample standard deviation (S n ) of the specified number (n) of sublots for the lot and the
specification tolerance limits, L for lower and U for upper, for the particular acceptance parameter. From
these values, the respective Quality index, QL for Lower Quality Index and/or Q U for Upper Quality
Index, is computed and the PWL for the lot for the specified n is determined from Table 1. All
specification limits specified in the technical sections shall be absolute values. Test results used in the
calculations shall be to the significant figure given in the test procedure.
There is some degree of uncertainty (risk) in the measurement for acceptance because only a small
fraction of production material (the population) is sampled and tested. This uncertainty exists because all
portions of the production material have the same probability to be randomly sampled. The Contractor’s
risk is the probability that material produced at the acceptable quality level is rejected or subjected to a
pay adjustment. The Owner’s risk is the probability that material produced at the rejectable quality level
is accepted.
It is the intent of this section to inform the Contractor that, in order to consistently offset the Contractor’s
risk for material evaluated, production quality (using population average and population standard
deviation) must be maintained at the acceptable quality specified or higher. In all cases, it is the
responsibility of the Contractor to produce at quality levels that will meet the specified acceptance criteria
when sampled and tested at the frequencies specified.
110-02 Method for computing PWL. The computational sequence for computing PWL is as follows:
a. Divide the lot into n sublots in accordance with the acceptance requirements of the specification.
b. Locate the random sampling position within the sublot in accordance with the requirements of the
specification.
c. Make a measurement at each location, or take a test portion and make the measurement on the test
portion in accordance with the testing requirements of the specification.
d. Find the sample average (X) for all sublot values within the lot by using the following formula:
X = (x 1 + x 2 + x 3 + . . .x n ) / n
Where: X = Sample average of all sublot values within a lot
x 1 , x 2 = Individual sublot values
n = Number of sublots
e. Find the sample standard deviation (S n ) by use of the following formula:
S n = [(d 1 2 + d 2 2 + d 3 2 + . . .d n 2)/(n-1)]1/2
Where: S n = Sample standard deviation of the number of sublot values in the set
d 1 , d 2 = Deviations of the individual sublot values x 1 , x 2 , … from the average value X
that is: d 1 = (x 1 - X), d 2 = (x 2 - X) … d n = (x n - X)
n = Number of sublots
IMMOKALEE REGIONAL AIRPORT
60% DESIGN SUBMITTAL REHABILITATION OF TAXIWAY B
GP-54 SURFACE PREPARATION
Reference: AC 150/5370-10G (7/21/2014)
f. For single sided specification limits (that is, L only), compute the Lower Quality Index Q L by use
of the following formula:
Q L = (X - L) / S n
Where: L = specification lower tolerance limit
Estimate the percentage of material within limits (PWL) by entering Table 1 with Q L , using the
column appropriate to the total number (n) of measurements. If the value of Q L falls between values
shown on the table, use the next higher value of PWL.
g. For double-sided specification limits (that is, L and U), compute the Quality Indexes Q L and Q U by
use of the following formulas:
Q L = (X - L) / S n
and
Q U = (U - X) / S n
Where: L and U = specification lower and upper tolerance limits
Estimate the percentage of material between the lower (L) and upper (U) tolerance limits (PWL)
by entering Table 1 separately with Q L and Q U , using the column appropriate to the total number (n) of
measurements, and determining the percent of material above PL and percent of material below P U for
each tolerance limit. If the values of Q L fall between values shown on the table, use the next higher value
of P L or P U . Determine the PWL by use of the following formula:
PWL = (P U + P L) - 100
Where: P L = percent within lower specification limit
P U = percent within upper specification limit
EXAMPLE OF PWL CALCULATION
Project: Example Project
Test Item: Item P -401, Lot A.
A. PWL Determination for Mat Density.
1. Density of four random cores taken from Lot A.
A-1 = 96.60
A-2 = 97.55
A-3 = 99.30
A-4 = 98.35
n = 4
2. Calculate average density for the lot.
X = (x 1 + x 2 + x 3 + . . .x n ) / n
X = (96.60 + 97.55 + 99.30 + 98.35) / 4
X = 97.95% density
IMMOKALEE REGIONAL AIRPORT
60% DESIGN SUBMITTAL REHABILITATION OF TAXIWAY B
SURFACE PREPARATION GP-55
Reference: AC 150/5370-10G (7/21/2014)
3. Calculate the standard deviation for the lot.
S n = [((96.60 - 97.95)2 + (97.55 - 97.95)2 +(99.30 -97.95)2 + (98.35 -97.95)2)) / (4 - 1)]1/2
S n = [(1.82 + 0.16 + 1.82 + 0.16) / 3]1/2
S n = 1.15
4. Calculate the Lower Quality Index Q L for the lot. (L=96.3)
Q L = (X -L) / S n
Q L = (97.95 - 96.30) / 1.15
Q L = 1.4348
5. Determine PWL by entering Table 1 with Q L = 1.44 and n= 4.
PWL = 98
B. PWL Determination for Air Voids.
1. Air Voids of four random samples taken from Lot A.
A-1 = 5.00
A-2 = 3.74
A-3 = 2.30
A-4 = 3.25
2. Calculate the average air voids for the lot.
X = (x 1 + x 2 + x 3 . . .n) / n
X = (5.00 + 3.74 + 2.30 + 3.25) / 4
X = 3.57%
3. Calculate the standard deviation Sn for the lot.
S n = [((3.57 - 5.00)2 + (3.57 - 3.74)2 + (3.57 - 2.30)2 + (3.57 -3.25)2) / (4 - 1)]1/2
S n = [(2.04 + 0.03 + 1.62 + 0.10) / 3]1/2
S n = 1.12
4. Calculate the Lower Quality Index Q L for the lot. (L= 2.0)
Q L = (X - L) / S n
Q L = (3.57 - 2.00) / 1.12
Q L = 1.3992
5. Determine P L by entering Table 1 with Q L = 1.41 and n = 4.
P L = 97
6. Calculate the Upper Quality Index Q U for the lot. (U= 5.0)
Q U = (U - X) / S n
Q U = (5.00 - 3.57) / 1.12
Q U = 1.2702
7. Determine P U by entering Table 1 with Q U = 1.29 and n = 4.
P U = 93
8. Calculate Air Voids PWL
IMMOKALEE REGIONAL AIRPORT
60% DESIGN SUBMITTAL REHABILITATION OF TAXIWAY B
GP-56 SURFACE PREPARATION
Reference: AC 150/5370-10G (7/21/2014)
PWL = (P L + P U ) - 100
PWL = (97 + 93) - 100 = 90
EXAMPLE OF OUTLIER CALCULATION (REFERENCE ASTM E178)
Project: Example Project
Test Item: Item P -401, Lot A.
A. Outlier Determination for Mat Density.
1. Density of four random cores taken from Lot A arranged in descending order.
A-3 = 99.30
A-4 = 98.35
A-2 = 97.55
A-1 = 96.60
2. Use n=4 and upper 5% significance level of to find the critical value for test criterion = 1.463.
3. Use average density, standard deviation, and test criterion value to evaluate density measurements.
a. For measurements greater than the average:
If (measurement - average)/(standard deviation) is less than test criterion,
then the measurement is not considered an outlier
For A-3, check if (99.30 - 97.95) / 1.15 is greater than 1.463.
Since 1.174 is less than 1.463, the value is not an outlier.
b. For measurements less than the average:
If (average - measurement)/(standard deviation) is less than test criterion,
then the measurement is not considered an outlier.
For A-1, check if (97.95 - 96.60) / 1.15 is greater than 1.463.
Since 1.435 is less than 1.463, the value is not an outlier.
Note: In this example, a measurement would be considered an outlier if the density were:
Greater than (97.95 + 1.463 × 1.15) = 99.63%
OR
less than (97.95 - 1.463 × 1.15) = 96.27%.
Table 1. Table for Estimating Percent of Lot Within Limits (PWL)
Percent Within
Limits
(P L and P U )
Positive Values of Q (Q L and Q U )
n=3 n=4 n=5 n=6 n=7 n=8 n=9 n=10
IMMOKALEE REGIONAL AIRPORT
60% DESIGN SUBMITTAL REHABILITATION OF TAXIWAY B
SURFACE PREPARATION GP-57
Reference: AC 150/5370-10G (7/21/2014)
Percent Within
Limits
(P L and P U )
Positive Values of Q (Q L and Q U )
n=3 n=4 n=5 n=6 n=7 n=8 n=9 n=10
99 1.1541 1.4700 1.6714 1.8008 1.8888 1.9520 1.9994 2.0362
98 1.1524 1.4400 1.6016 1.6982 1.7612 1.8053 1.8379 1.8630
97 1.1496 1.4100 1.5427 1.6181 1.6661 1.6993 1.7235 1.7420
96 1.1456 1.3800 1.4897 1.5497 1.5871 1.6127 1.6313 1.6454
95 1.1405 1.3500 1.4407 1.4887 1.5181 1.5381 1.5525 1.5635
94 1.1342 1.3200 1.3946 1.4329 1.4561 1.4717 1.4829 1.4914
93 1.1269 1.2900 1.3508 1.3810 1.3991 1.4112 1.4199 1.4265
92 1.1184 1.2600 1.3088 1.3323 1.3461 1.3554 1.3620 1.3670
91 1.1089 1.2300 1.2683 1.2860 1.2964 1.3032 1.3081 1.3118
90 1.0982 1.2000 1.2290 1.2419 1.2492 1.2541 1.2576 1.2602
89 1.0864 1.1700 1.1909 1.1995 1.2043 1.2075 1.2098 1.2115
88 1.0736 1.1400 1.1537 1.1587 1.1613 1.1630 1.1643 1.1653
87 1.0597 1.1100 1.1173 1.1192 1.1199 1.1204 1.1208 1.1212
86 1.0448 1.0800 1.0817 1.0808 1.0800 1.0794 1.0791 1.0789
85 1.0288 1.0500 1.0467 1.0435 1.0413 1.0399 1.0389 1.0382
84 1.0119 1.0200 1.0124 1.0071 1.0037 1.0015 1.0000 0.9990
83 0.9939 0.9900 0.9785 0.9715 0.9671 0.9643 0.9624 0.9610
82 0.9749 0.9600 0.9452 0.9367 0.9315 0.9281 0.9258 0.9241
81 0.9550 0.9300 0.9123 0.9025 0.8966 0.8928 0.8901 0.8882
80 0.9342 0.9000 0.8799 0.8690 0.8625 0.8583 0.8554 0.8533
79 0.9124 0.8700 0.8478 0.8360 0.8291 0.8245 0.8214 0.8192
78 0.8897 0.8400 0.8160 0.8036 0.7962 0.7915 0.7882 0.7858
77 0.8662 0.8100 0.7846 0.7716 0.7640 0.7590 0.7556 0.7531
76 0.8417 0.7800 0.7535 0.7401 0.7322 0.7271 0.7236 0.7211
75 0.8165 0.7500 0.7226 0.7089 0.7009 0.6958 0.6922 0.6896
74 0.7904 0.7200 0.6921 0.6781 0.6701 0.6649 0.6613 0.6587
73 0.7636 0.6900 0.6617 0.6477 0.6396 0.6344 0.6308 0.6282
72 0.7360 0.6600 0.6316 0.6176 0.6095 0.6044 0.6008 0.5982
71 0.7077 0.6300 0.6016 0.5878 0.5798 0.5747 0.5712 0.5686
70 0.6787 0.6000 0.5719 0.5582 0.5504 0.5454 0.5419 0.5394
69 0.6490 0.5700 0.5423 0.5290 0.5213 0.5164 0.5130 0.5105
68 0.6187 0.5400 0.5129 0.4999 0.4924 0.4877 0.4844 0.4820
67 0.5878 0.5100 0.4836 0.4710 0.4638 0.4592 0.4560 0.4537
66 0.5563 0.4800 0.4545 0.4424 0.4355 0.4310 0.4280 0.4257
65 0.5242 0.4500 0.4255 0.4139 0.4073 0.4030 0.4001 0.3980
64 0.4916 0.4200 0.3967 0.3856 0.3793 0.3753 0.3725 0.3705
63 0.4586 0.3900 0.3679 0.3575 0.3515 0.3477 0.3451 0.3432
62 0.4251 0.3600 0.3392 0.3295 0.3239 0.3203 0.3179 0.3161
61 0.3911 0.3300 0.3107 0.3016 0.2964 0.2931 0.2908 0.2892
60 0.3568 0.3000 0.2822 0.2738 0.2691 0.2660 0.2639 0.2624
59 0.3222 0.2700 0.2537 0.2461 0.2418 0.2391 0.2372 0.2358
58 0.2872 0.2400 0.2254 0.2186 0.2147 0.2122 0.2105 0.2093
57 0.2519 0.2100 0.1971 0.1911 0.1877 0.1855 0.1840 0.1829
56 0.2164 0.1800 0.1688 0.1636 0.1607 0.1588 0.1575 0.1566
55 0.1806 0.1500 0.1406 0.1363 0.1338 0.1322 0.1312 0.1304
54 0.1447 0.1200 0.1125 0.1090 0.1070 0.1057 0.1049 0.1042
53 0.1087 0.0900 0.0843 0.0817 0.0802 0.0793 0.0786 0.0781
52 0.0725 0.0600 0.0562 0.0544 0.0534 0.0528 0.0524 0.0521
51 0.0363 0.0300 0.0281 0.0272 0.0267 0.0264 0.0262 0.0260
50 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
IMMOKALEE REGIONAL AIRPORT
60% DESIGN SUBMITTAL REHABILITATION OF TAXIWAY B
GP-58 SURFACE PREPARATION
Reference: AC 150/5370-10G (7/21/2014)
Percent Within
Limits
(P L and P U )
Negative Values of Q (Q L and Q U )
n=3 n=4 n=5 n=6 n=7 n=8 n=9 n=10
49 -0.0363 -0.0300 -0.0281 -0.0272 -0.0267 -0.0264 -0.0262 -0.0260
48 -0.0725 -0.0600 -0.0562 -0.0544 -0.0534 -0.0528 -0.0524 -0.0521
47 -0.1087 -0.0900 -0.0843 -0.0817 -0.0802 -0.0793 -0.0786 -0.0781
46 -0.1447 -0.1200 -0.1125 -0.1090 -0.1070 -0.1057 -0.1049 -0.1042
45 -0.1806 -0.1500 -0.1406 -0.1363 -0.1338 -0.1322 -0.1312 -0.1304
44 -0.2164 -0.1800 -0.1688 -0.1636 -0.1607 -0.1588 -0.1575 -0.1566
43 -0.2519 -0.2100 -0.1971 -0.1911 -0.1877 -0.1855 -0.1840 -0.1829
42 -0.2872 -0.2400 -0.2254 -0.2186 -0.2147 -0.2122 -0.2105 -0.2093
41 -0.3222 -0.2700 -0.2537 -0.2461 -0.2418 -0.2391 -0.2372 -0.2358
40 -0.3568 -0.3000 -0.2822 -0.2738 -0.2691 -0.2660 -0.2639 -0.2624
39 -0.3911 -0.3300 -0.3107 -0.3016 -0.2964 -0.2931 -0.2908 -0.2892
38 -0.4251 -0.3600 -0.3392 -0.3295 -0.3239 -0.3203 -0.3179 -0.3161
37 -0.4586 -0.3900 -0.3679 -0.3575 -0.3515 -0.3477 -0.3451 -0.3432
36 -0.4916 -0.4200 -0.3967 -0.3856 -0.3793 -0.3753 -0.3725 -0.3705
35 -0.5242 -0.4500 -0.4255 -0.4139 -0.4073 -0.4030 -0.4001 -0.3980
34 -0.5563 -0.4800 -0.4545 -0.4424 -0.4355 -0.4310 -0.4280 -0.4257
33 -0.5878 -0.5100 -0.4836 -0.4710 -0.4638 -0.4592 -0.4560 -0.4537
32 -0.6187 -0.5400 -0.5129 -0.4999 -0.4924 -0.4877 -0.4844 -0.4820
31 -0.6490 -0.5700 -0.5423 -0.5290 -0.5213 -0.5164 -0.5130 -0.5105
30 -0.6787 -0.6000 -0.5719 -0.5582 -0.5504 -0.5454 -0.5419 -0.5394
29 -0.7077 -0.6300 -0.6016 -0.5878 -0.5798 -0.5747 -0.5712 -0.5686
28 -0.7360 -0.6600 -0.6316 -0.6176 -0.6095 -0.6044 -0.6008 -0.5982
27 -0.7636 -0.6900 -0.6617 -0.6477 -0.6396 -0.6344 -0.6308 -0.6282
26 -0.7904 -0.7200 -0.6921 -0.6781 -0.6701 -0.6649 -0.6613 -0.6587
25 -0.8165 -0.7500 -0.7226 -0.7089 -0.7009 -0.6958 -0.6922 -0.6896
24 -0.8417 -0.7800 -0.7535 -0.7401 -0.7322 -0.7271 -0.7236 -0.7211
23 -0.8662 -0.8100 -0.7846 -0.7716 -0.7640 -0.7590 -0.7556 -0.7531
22 -0.8897 -0.8400 -0.8160 -0.8036 -0.7962 -0.7915 -0.7882 -0.7858
21 -0.9124 -0.8700 -0.8478 -0.8360 -0.8291 -0.8245 -0.8214 -0.8192
20 -0.9342 -0.9000 -0.8799 -0.8690 -0.8625 -0.8583 -0.8554 -0.8533
19 -0.9550 -0.9300 -0.9123 -0.9025 -0.8966 -0.8928 -0.8901 -0.8882
18 -0.9749 -0.9600 -0.9452 -0.9367 -0.9315 -0.9281 -0.9258 -0.9241
17 -0.9939 -0.9900 -0.9785 -0.9715 -0.9671 -0.9643 -0.9624 -0.9610
16 -1.0119 -1.0200 -1.0124 -1.0071 -1.0037 -1.0015 -1.0000 -0.9990
15 -1.0288 -1.0500 -1.0467 -1.0435 -1.0413 -1.0399 -1.0389 -1.0382
14 -1.0448 -1.0800 -1.0817 -1.0808 -1.0800 -1.0794 -1.0791 -1.0789
13 -1.0597 -1.1100 -1.1173 -1.1192 -1.1199 -1.1204 -1.1208 -1.1212
12 -1.0736 -1.1400 -1.1537 -1.1587 -1.1613 -1.1630 -1.1643 -1.1653
11 -1.0864 -1.1700 -1.1909 -1.1995 -1.2043 -1.2075 -1.2098 -1.2115
10 -1.0982 -1.2000 -1.2290 -1.2419 -1.2492 -1.2541 -1.2576 -1.2602
9 -1.1089 -1.2300 -1.2683 -1.2860 -1.2964 -1.3032 -1.3081 -1.3118
8 -1.1184 -1.2600 -1.3088 -1.3323 -1.3461 -1.3554 -1.3620 -1.3670
7 -1.1269 -1.2900 -1.3508 -1.3810 -1.3991 -1.4112 -1.4199 -1.4265
6 -1.1342 -1.3200 -1.3946 -1.4329 -1.4561 -1.4717 -1.4829 -1.4914
5 -1.1405 -1.3500 -1.4407 -1.4887 -1.5181 -1.5381 -1.5525 -1.5635
4 -1.1456 -1.3800 -1.4897 -1.5497 -1.5871 -1.6127 -1.6313 -1.6454
3 -1.1496 -1.4100 -1.5427 -1.6181 -1.6661 -1.6993 -1.7235 -1.7420
2 -1.1524 -1.4400 -1.6016 -1.6982 -1.7612 -1.8053 -1.8379 -1.8630
1 -1.1541 -1.4700 -1.6714 -1.8008 -1.8888 -1.9520 -1.9994 -2.0362
END OF SECTION 110
FEDERAL REQUIREMENTS
Federal Aviation Administration Provisions - CFDA 20.106
The supplemental conditions contained in this section are intended to cooperate with, to supplement, and
to modify the general conditions and other specifications. In cases of disagreement with any other section
of this contract, the Supplemental Conditions shall govern.
The services performed by the awarded Contractor shall be in compliance with all applicable FAA
regulations/requirements, and additional requirements specified in this document. It shall be the awarded
Contractor’s responsibility to acquire and utilize the necessary manuals and guidelines that apply to the
work required to complete this project. In general,
1) The contractor (including all subcontractors) must insert these contract provisions in each lower
tier contracts ( e.g. subcontract or sub-agreement);
2) The contractor (or subcontractor) must incorporate the applicable requirements of these contract
provisions by reference for work done under any purchase orders, rental agreements and other
agreements for supplies or services;
3) The prime contractor is responsible for compliance with these contract provisions by any
subcontractor, lower-tier subcontractor or service provider
Box is Checked
If Applicable
1. ACCESS TO RECORDS AND REPORTS
2. AFFIRMATIVE ACTION REQUIREMENT
3. BREACH OF CONTRACT TERMS
4. BUY AMERICAN PREFERENCE
5. CIVIL RIGHTS - GENERAL
6. CIVIL RIGHTS – TITLE VI ASSURANCE
7. CLEAN AIR AND WATER POLLUTION CONTROL
8. CONTRACT WORKHOURS AND SAFETY STANDARDS ACT REQUIREMENTS
9. COPLELAND “ANTI-KICKBACK” ACT
10. DAVIS-BACON REQUIREMENTS
11. DEBARMENT AND SUSPENSION
12. DISADVANTAGED B USINESS ENTERPRISE
13. DISTRACTED DRIVING
14. ENERGY CONSERVATION REQUIREMENTS
15. EQUAL EMPLOYMENT OPPORTUNTY (E.E.O.)
16. FEDERAL FAIR LABOR STANDARDS ACT (FEDERAL MINIMUM WAGE)
17. LOBBYIGN AND INFLUENCING FEDERAL EMPLOYEES
18. PROHIBITION OF SEGREGATED FACILILITIES
19. OCCUPATIONAL SAFETY AND HEALTH ACT OF 1970
20. PROCUREMENT OF RECOVERED MATERIALS
21. RIGHT TO INVENTIONS
22. SEISMIC SAFETY
23. TERMINATION OF CONTRACT
24. TRADE RESTRICTION CERTIFICATION
25. VETERAN’S PREFERENCE
Federal Aviation Administration Provisions - CFDA 20.106
1. ACCESS TO RECORDS AND REPORTS
(Applies to subcontracts)
2 CFR § 200.333, 2 CFR § 200.336, FAA Order 5100.38
The Contractor must maintain an acceptable cost accounting system. The Contractor agrees to provide the
sponsor, the Federal Aviation Administration, and the Comptroller General of the United States or any of
their duly authorized representatives, access to any books, documents, papers, and records of the
contractor which are directly pertinent to the specific contract for the purpose of making audit,
examination, excerpts and transcriptions. The Contractor agrees to maintain all books, records and reports
required under this contract for a period of not less than three years after final payment is made and all
pending matters are closed.
2. NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION to ENSURE EQUAL
EMPLOYMENT OPPORTUNITY
(Applies to subcontracts in excess of $10,000)
41 CFR part 60-4, Executive Order 11246
1. The Offeror's or Bidder’s attention is called to the "Equal Opportunity Clause" and the "Standard
Federal Equal Employment Opportunity Construction Contract Specifications" set forth herein.
2. The goals and timetables for minority and female participation, expressed in percentage terms for the
contractor's aggregate workforce in each trade on all construction work in the covered area, are as
follows:
Timetables
Goals for minority participation for each trade: 17.1%
Goals for female participation in each trade: 6.9%
These goals are applicable to all of the contractor's construction work (whether or not it is Federal or
federally-assisted) performed in the covered area. If the contractor performs construction work in a
geographical area located outside of the covered area, it shall apply the goals established for such
geographical area where the work is actually performed. With regard to this second area, the contractor
also is subject to the goals for both its federally involved and non-federally involved construction.
The Contractor's compliance with the Executive Order and the regulations in 41 CFR Part 60-4 shall be
based on its implementation of the Equal Opportunity Clause, specific affirmative action obligations
required by the specifications set forth in 41 CFR 60-4.3(a), and its efforts to meet the goals. The hours of
minority and female employment and training must be substantially uniform throughout the length of the
contract, and in each trade, and the contractor shall make a good faith effort to employ minorities and
women evenly on each of its projects. The transfer of minority or female employees or trainees from
Contractor to Contractor or from project to project for the sole purpose of meeting the Contractor's goals
shall be a violation of the contract, the Executive Order and the regulations in 41 CFR Part 60-4.
Compliance with the goals will be measured against the total work hours performed.
3. The Contractor shall provide written notification to the Director of the Office of Federal Contract
Compliance Programs (OFCCP) within 10 working days of award of any construction subcontract in
excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The
notification shall list the name, address, and telephone number of the subcontractor; employer
identification number of the subcontractor; estimated dollar amount of the subcontract; estimated starting
and completion dates of the subcontract; and the geographical area in which the subcontract is to be
performed.
Federal Aviation Administration Provisions - CFDA 20.106
4. As used in this notice and in the contract resulting from this solicitation, the "covered area" is Florida,
Collier, Immokalee.
3. BREACH OF CONTRACT TERMS
2 CFR § 200 Appendix II(A)
Any violation or breach of terms of this contract on the part of the contractor or its subcontractors may
result in the suspension or termination of this contract or such other action that may be necessary to
enforce the rights of the parties of this agreement. The County will provide the Contractor or Consultant
written notice that describes the nature of the breach and corrective actions the Contractor or Consultant
must undertake in order to avoid termination of the contract. County reserves the right to withhold
payments to Contractor until such time the Contractor corrects the breach or the County elects to
terminate the contract. The County’s notice will identify a specific date by which the Contractor or
Consultant must correct the breach. County may proceed with termination of the contract if the
Contractor or Consultant fails to correct the breach by deadline indicated in the County’s notice. The
duties and obligations imposed by the Contract Documents and the rights and remedies available there
under are in addition to, and not a limitation of, any duties, obligations, rights and remedies otherwise
imposed or available by law.
4. BUY AMERICAN PREFERENCE
Title 49 USC § 50101
The contractor agrees to comply with 49 USC § 50101, which provides that Federal funds may not be
obligated unless all steel and manufactured goods used in AIP funded projects are produced in the United
States, unless the FAA has issued a waiver for the product; the product is listed as an Excepted Article,
Material Or Supply in Federal Acquisition Regulation subpart 25.108; or is included in the FAA
Nationwide Buy American Waivers Issued list. A bidder or offeror must complete and submit the Buy
America certification included herein with their bid or offer. The County will reject as nonresponsive
any bid or offer that does not include a completed Certificate of Buy American Compliance.
5. GENERAL CIVIL RIGHTS PROVISIONS
49 USC § 47123
The contractor agrees to comply with pertinent statutes, Executive Orders and such rules as are
promulgated to ensure that no person shall, on the grounds of race, creed, color, national origin, sex, age,
or disability be excluded from participating in any activity conducted with or benefiting from Federal
assistance. This provision binds the contractor and subtier contractors from the bid solicitation period
through the completion of the contract. This provision is in addition to that required of Title VI of the
Civil Rights Act of 1964.
6. Title VI CIVIL RIGHTS PROVISIONS
Solicitation Notice:
Collier County, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat.
252, 42 U.S.C. §§ 2000d to 2000d-4) and the Regulations, hereby notifies all bidders that it will
affirmatively ensure that any contract entered into pursuant to this advertisement, disadvantaged business
enterprises will be afforded full and fair opportunity to submit bids in response to this invitation and will
not be discriminated against on the grounds of race, color, or national origin in consideration for an
award.
Compliance with Nondiscrimination Requirements:
Federal Aviation Administration Provisions - CFDA 20.106
During the performance of this contract, the contractor, for itself, its assignees, and successors in interest
(hereinafter referred to as the “contractor”) agrees as follows:
1. Compliance with Regulations: The contractor (hereinafter includes consultants) will comply with
the Title VI List of Pertinent Nondiscrimination Acts And Authorities, as they may be amended from
time to time, which are herein incorporated by reference and made a part of this contract.
2. Non-discrimination: The contractor, with regard to the work performed by it during the contract,
will not discriminate on the grounds of race, color, or national origin in the selection and retention of
subcontractors, including procurements of materials and leases of equipment. The contractor will not
participate directly or indirectly in the discrimination prohibited by the Nondiscrimination Acts and
Authorities, including employment practices when the contract covers any activity, project, or
program set forth in Appendix B of 49 CFR part 21.
3. Solicitations for Subcontracts, Including Procurements of Materials and Equipment: In all
solicitations, either by competitive bidding, or negotiation made by the contractor for work to be
performed under a subcontract, including procurements of materials, or leases of equipment, each
potential subcontractor or supplier will be notified by the contractor of the contractor’s obligations
under this contract and the Nondiscrimination Acts And Authorities on the grounds of race, color, or
national origin.
4. Information and Reports: The contractor will provide all information and reports required by the
Acts, the Regulations, and directives issued pursuant thereto and will permit access to its books,
records, accounts, other sources of information, and its facilities as may be determined by the sponsor
or the Federal Aviation Administration to be pertinent to ascertain compliance with such
Nondiscrimination Acts And Authorities and instructions. Where any information required of a
contractor is in the exclusive possession of another who fails or refuses to furnish the information, the
contractor will so certify to the sponsor or the Federal Aviation Administration, as appropriate, and
will set forth what efforts it has made to obtain the information.
5. Sanctions for Noncompliance: In the event of a contractor’s noncompliance with the Non-
discrimination provisions of this contract, the sponsor will impose such contract sanctions as it or the
Federal Aviation Administration may determine to be appropriate, including, but not limited to:
a. Withholding payments to the contractor under the contract until the contractor complies; and/or
b. Cancelling, terminating, or suspending a contract, in whole or in part.
6. Incorporation of Provisions: The contractor will include the provisions of paragraphs one through
six in every subcontract, including procurements of materials and leases of equipment, unless exempt
by the Acts, the Regulations and directives issued pursuant thereto. The contractor will take action
with respect to any subcontract or procurement as the sponsor or the Federal Aviation Administration
may direct as a means of enforcing such provisions including sanctions for noncompliance. Provided,
that if the contractor becomes involved in, or is threatened with litigation by a subcontractor, or
supplier because of such direction, the contractor may request the sponsor to enter into any litigation
to protect the interests of the sponsor. In addition, the contractor may request the United States to
enter into the litigation to protect the interests of the United States.
CLAUSES FOR CONSTRUCTION/USE/ACCESS TO REAL PROPERTY ACQUIRED
UNDER THE ACTIVITY, FACILITY OR PROGRAM:
The (grantee, licensee, permittee, etc., as appropriate) for himself/herself, his/her heirs, personal
representatives, successors in interest, and assigns, as a part of the consideration hereof, does hereby
covenant and agree \ that (1) no person on the ground of race, color, or national origin, will be excluded
from participation in, denied the benefits of, or be otherwise subjected to discrimination in the use of said
Federal Aviation Administration Provisions - CFDA 20.106
facilities, (2) that in the construction of any improvements on, over, or under such land, and the furnishing
of services thereon, no person on the ground of race, color, or national origin, will be excluded from
participation in, denied the benefits of, or otherwise be subjected to discrimination, (3) that the (grantee,
licensee, lessee, permittee, etc.) will use the premises in compliance with all other requirements imposed
by or pursuant to the List of discrimination Acts And Authorities.
Title VI List of Pertinent Nondiscrimination Acts and Authorities:
During the performance of this contract, the contractor, for itself, its assignees, and successors in interest
(hereinafter referred to as the “contractor”) agrees to comply with the following non-discrimination
statutes and authorities; including but not limited to:
Title VI of the Civil Rights Act of 1964 (42 U.S.C. § 2000d et seq., 78 stat. 252), (prohibits
discrimination on the basis of race, color, national origin);
49 CFR part 21 (Non-discrimination In Federally-Assisted Programs of The Department of
Transportation—Effectuation of Title VI of The Civil Rights Act of 1964);
The Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, (42
U.S.C. § 4601), (prohibits unfair treatment of persons displaced or whose property has been acquired
because of Federal or Federal-aid programs and projects);
Section 504 of the Rehabilitation Act of 1973, (29 U.S.C. § 794 et seq.), as amended, (prohibits
discrimination on the basis of disability); and 49 CFR part 27;
The Age Discrimination Act of 1975, as amended, (42 U.S.C. § 6101 et seq.), (prohibits
discrimination on the basis of age);
Airport and Airway Improvement Act of 1982, (49 USC § 471, Section 47123), as amended,
(prohibits discrimination based on race, creed, color, national origin, or sex);
The Civil Rights Restoration Act of 1987, (PL 100-209), (Broadened the scope, coverage and
applicability of Title VI of the Civil Rights Act of 1964, The Age Discrimination Act of 1975 and
Section 504 of the Rehabilitation Act of 1973, by expanding the definition of the terms “programs or
activities” to include all of the programs or activities of the Federal-aid recipients, sub-recipients and
contractors, whether such programs or activities are Federally funded or not);
Titles II and III of the Americans with Disabilities Act of 1990, which prohibit discrimination on
the basis of disability in the operation of public entities, public and private transportation systems,
places of public accommodation, and certain testing entities (42 U.S.C. §§ 12131 – 12189) as
implemented by Department of Transportation regulations at 49 CFR parts 37 and 38;
The Federal Aviation Administration’s Non-discrimination statute (49 U.S.C. § 47123) (prohibits
discrimination on the basis of race, color, national origin, and sex);
Executive Order 12898, Federal Actions to Address Environmental Justice in Minority
Populations and Low-Income Populations, which ensures non-discrimination against minority
populations by discouraging programs, policies, and activities with disproportionately high and
adverse human health or environmental effects on minority and low-income populations;
Executive Order 13166, Improving Access to Services for Persons with Limited English
Proficiency, and resulting agency guidance, national origin discrimination includes discrimination
because of limited English proficiency (LEP). To ensure compliance with Title VI, you must take
reasonable steps to ensure that LEP persons have meaningful access to your programs (70 Fed. Reg.
at 74087 to 74100);
Title IX of the Education Amendments of 1972, as amended, which prohibits you from
discriminating because of sex in education programs or activities (20 U.S.C. 1681 et seq
7. CLEAN AIR AND WATER POLLUTION CONTROL
2 CFR § 200, Appendix II(G)
(Applies to subcontracts in excess of $150,000)
Contractor agrees to comply with all applicable standards, orders, and regulations issued pursuant to the
Clean Air Act (42 U.S.C. § 740-7671q) and the Federal Water Pollution Control Act as amended
(33 U.S.C. § 1251-1387). The Contractor agrees to report any violation to the County immediately upon
discovery. The County assumes responsibility for notifying the Environmental Protection Agency (EPA)
and the Federal Aviation Administration.
8. CONTRACT WORKHOURS AND SAFETY STANDARDS ACT REQUIREMENTS
(Applies to subcontracts)
2 CFR § 200, Appendix II(E)
1. Overtime Requirements.
No contractor or subcontractor contracting for any part of the contract work which may require or involve
the employment of laborers or mechanics shall require or permit any such laborer or mechanic, including
watchmen and guards, in any workweek in which he or she is employed on such work to work in excess of
forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less
than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such
workweek.
2. Violation; Liability for Unpaid Wages; Liquidated Damages.
In the event of any violation of the clause set forth in paragraph (1) of this clause, the contractor and any
subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such contractor and
subcontractor shall be liable to the United States (in the case of work done under contract for the District
of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated
damages shall be computed with respect to each individual laborer or mechanic, including watchmen and
guards, employed in violation of the clause set forth in paragraph (1) of this clause, in the sum of $10 for
each calendar day on which such individual was required or permitted to work in excess of the standard
workweek of forty hours without payment of the overtime wages required by the clause set forth in
paragraph (1) of this clause.
3. Withholding for Unpaid Wages and Liquidated Damages.
The Federal Aviation Administration (FAA) or the County shall upon its own action or upon written
request of an authorized representative of the Department of Labor withhold or cause to be withheld, from
any moneys payable on account of work performed by the contractor or subcontractor under any such
contract or any other Federal contract with the same prime contractor, or any other Federally-assisted
contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime
contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or
subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph 2
of this clause.
4. Subcontractors.
The contractor or subcontractor shall insert in any subcontracts the clauses set forth in paragraphs (1)
through (4) and also a clause requiring the subcontractor to include these clauses in any lower tier
subcontracts. The prime contractor shall be responsible for compliance by any subcontractor or lower tier
subcontractor with the clauses set forth in paragraphs (1) through (4) of this clause.
9. COPELAND “ANTI-KICKBACK” ACT
2 CFR § 200, Appendix II(D), 29 CFR Parts 3 & 5
Contractor must comply with the requirements of the Copeland “Anti-Kickback” Act (18 U.S.C. 874 and
40 U.S.C. 3145), as supplemented by Department of Labor regulation 29 CFR part 3. Contractor and
subcontractors are prohibited from inducing, by any means, any person employed on the project to give up
any part of the compensation to which the employee is entitled. The Contractor and each Subcontractor
must submit to the Owner, a weekly statement on the wages paid to each employee performing on covered
work during the prior week. Owner must report any violations of the Act to the Federal Aviation
Administration.
10. DAVIS-BACON REQUIREMENTS
2 CFR § 200, Appendix II(D), 29 CFR Part 5
1. Minimum Wages
(i) All laborers and mechanics employed or working upon the site of the work will be paid
unconditionally and not less often than once a week, and without subsequent deduction or rebate on any
account (except such payroll deductions as are permitted by the Secretary of Labor under the Copeland
Act (29 CFR Part 3)), the full amount of wages and bona fide fringe benefits (or cash equivalent thereof)
due at time of payment computed at rates not less than those contained in the wage determination
(General Decision Number: FL170206 01/06/2017 FL206) of the Secretary of Labor which is attached
hereto and made a part hereof, regardless of any contractual relationship which may be alleged to exist
between the contractor and such laborers and mechanics.
Contributions made or costs reasonably anticipated for bona fide fringe benefits under section 1(b)(2) of
the Davis-Bacon Act on behalf of laborers or mechanics are considered wages paid to such laborers or
mechanics, subject to the provisions of paragraph (1)(iv) of this section; also, regular contributions made
or costs incurred for more than a weekly period (but not less often than quarterly) under plans, funds, or
programs which cover the particular weekly period, are deemed to be constructively made or incurred
during such weekly period. Such laborers and mechanics shall be paid the appropriate wage rate and fringe
benefits on the wage determination for the classification of work actually performed, without regard to
skill, except as provided in 29 CFR Part 5.5(a)(4). Laborers or mechanics performing work in more than
one classification may be compensated at the rate specified for each classification for the time actually
worked therein: Provided, that the employer's payroll records accurately set forth the time spent in each
classification in which work is performed. The wage determination (including any additional classification
and wage rates conformed under (1)(ii) of this section) and the Davis-Bacon poster (WH-1321) shall be
posted at all times by the contractor and its subcontractors at the site of the work in a prominent and
accessible place where it can easily be seen by the workers.
(ii) (A) The contracting officer shall require that any class of laborers or mechanics, including helpers,
which is not listed in the wage determination and which is to be employed under the contract shall be
classified in conformance with the wage determination. The contracting officer shall approve an additional
classification and wage rate and fringe benefits therefore only when the following criteria have been met:
(1) The work to be performed by the classification requested is not performed by a classification in the
wage determination; and
(2) The classification is utilized in the area by the construction industry; and
(3) The proposed wage rate, including any bona fide fringe benefits, bears a reasonable relationship to the
wage rates contained in the wage determination.
(B) If the contractor and the laborers and mechanics to be employed in the classification (if
known), or their representatives, and the contracting officer agree on the classification and wage rate
(including the amount designated for fringe benefits where appropriate), a report of the action taken shall
be sent by the contracting officer to the Administrator of the Wage and Hour Division, Employment
Standards Administration, U.S. Department of Labor, Washington, D.C. 20210. The Administrator, or an
authorized representative, will approve, modify, or disapprove every additional classification action within
30 days of receipt and so advise the contracting officer or will notify the contracting officer within the 30-
day period that additional time is necessary.
(C) In the event the contractor, the laborers or mechanics to be employed in the classification or
their representatives, and the contracting officer do not agree on the proposed classification and wage rate
(including the amount designated for fringe benefits where appropriate), the contracting officer shall refer
the questions, including the views of all interested parties and the recommendation of the contracting
officer, to the Administrator for determination. The Administrator, or an authorized representative, will
issue a determination within 30 days of receipt and so advise the contracting officer or will notify the
contracting officer within the 30-day period that additional time is necessary.
(D) The wage rate (including fringe benefits where appropriate) determined pursuant to
subparagraphs (1)(ii) (B) or (C) of this paragraph, shall be paid to all workers performing work in the
classification under this contract from the first day on which work is performed in the classification.
(iii) Whenever the minimum wage rate prescribed in the contract for a class of laborers or mechanics
includes a fringe benefit which is not expressed as an hourly rate, the contractor shall either pay the benefit
as stated in the wage determination or shall pay another bona fide fringe benefit or an hourly cash
equivalent thereof. (iv) If the contractor does not make payments to a trustee or other third person, the
contractor may consider as part of the wages of any laborer or mechanic the amount of any costs
reasonably anticipated in providing bona fide fringe benefits under a plan or program, Provided, That the
Secretary of Labor has found, upon the written request of the contractor, that the applicable standards of
the Davis-Bacon Act have been met. The Secretary of Labor may require the contractor to set aside in a
separate account assets for the meeting of obligations under the plan or program.
2 Withholding.
The Federal Aviation Administration or the sponsor shall upon its own action or upon written request of
an authorized representative of the Department of Labor withhold or cause to be withheld from the
contractor under this contract or any other Federal contract with the same prime contractor, or any other
Federally-assisted contract subject to Davis-Bacon prevailing wage requirements, which is held by the
same prime contractor, so much of the accrued payments or advances as may be considered necessary to
pay laborers and mechanics, including apprentices, trainees, and helpers, employed by the contractor or
any subcontractor the full amount of wages required by the contract. In the event of failure to pay any
laborer or mechanic, including any apprentice, trainee, or helper, employed or working on the site of work,
all or part of the wages required by the contract, the Federal Aviation Administration may, after written
notice to the contractor, sponsor, applicant, or owner, take such action as may be necessary to cause the
suspension of any further payment, advance, or guarantee of funds until such violations have ceased.
3. Payrolls and basic records.
(i) Payrolls and basic records relating thereto shall be maintained by the contractor during the course of the
work and preserved for a period of three years thereafter for all laborers and mechanics working at the site
of the work. Such records shall contain the name, address, and social security number of each such
worker, his or her correct classification, hourly rates of wages paid (including rates of contributions or
costs anticipated for bona fide fringe benefits or cash equivalents thereof of the types described in
1(b)(2)(B) of the Davis-Bacon Act), daily and weekly number of hours worked, deductions made and
actual wages paid. Whenever the Secretary of Labor has found under 29 CFR 5.5(a)(1)(iv) that the wages
of any laborer or mechanic include the amount of any costs reasonably anticipated in providing benefits
under a plan or program described in section 1(b)(2)(B) of the Davis-Bacon Act, the contractor shall
maintain records which show that the commitment to provide such benefits is enforceable, that the plan or
program is financially responsible, and that the plan or program has been communicated in writing to the
laborers or mechanics affected, and records which show the costs anticipated or the actual costs incurred
in providing such benefits. Contractors employing apprentices or trainees under approved programs shall
maintain written evidence of the registration of apprenticeship programs and certification of trainee
programs, the registration of the apprentices and trainees, and the ratios and wage rates prescribed in the
applicable programs.
(ii) (A) The contractor shall submit weekly for each week in which any contract work is performed a
copy of all payrolls to the Federal Aviation Administration if the agency is a party to the contract, but if
the agency is not such a party, the contractor will submit the payrolls to the applicant, sponsor, or owner,
as the case may be, for transmission to the Federal Aviation Administration. The payrolls submitted shall
set out accurately and completely all of the information required to be maintained under 29 CFR
5.5(a)(3)(i), except that full social security numbers and home addresses shall not be included on weekly
transmittals. Instead the payrolls shall only need to include an individually identifying number for each
employee (e.g. , the last four digits of the employee's social security number). The required weekly payroll
information may be submitted in any form desired. Optional Form WH–347 is available for this purpose
from the Wage and Hour Division Web site at http://www.dol.gov/esa/whd/forms/wh347instr.htm or its
successor site. The prime contractor is responsible for the submission of copies of payrolls by all
subcontractors. Contractors and subcontractors shall maintain the full social security number and current
address of each covered worker, and shall provide them upon request to the Federal Aviation
Administration if the agency is a party to the contract, but if the agency is not such a party, the contractor
will submit them to the applicant, sponsor, or owner, as the case may be, for transmission to the Federal
Aviation Administration, the contractor, or the Wage and Hour Division of the Department of Labor for
purposes of an investigation or audit of compliance with prevailing wage requirements. It is not a violation
of this section for a prime contractor to require a subcontractor to provide addresses and social security
numbers to the prime contractor for its own records, without weekly submission to the sponsoring
government agency (or the applicant, sponsor, or owner).
(B) Each payroll submitted shall be accompanied by a "Statement of Compliance," signed by the
contractor or subcontractor or his or her agent who pays or supervises the payment of the persons
employed under the contract and shall certify the following:
(1) That the payroll for the payroll period contains the information required to be provided under 29 CFR
§ 5.5(a)(3)(ii), the appropriate information is being maintained under 29 CFR § 5.5 (a)(3)(i) and that such
information is correct and complete;
(2) That each laborer and mechanic (including each helper, apprentice and trainee) employed on the
contract during the payroll period has been paid the full weekly wages earned, without rebate, either
directly or indirectly, and that no deductions have been made either directly or indirectly from the full
wages earned, other than permissible deductions as set forth in Regulations 29 CFR Part 3;
(3) That each laborer or mechanic has been paid not less than the applicable wage rates and fringe benefits
or cash equivalents for the classification of work performed, as specified in the applicable wage
determination incorporated into the contract.
(C) The weekly submission of a properly executed certification set forth on the reverse side of
Optional Form WH-347 shall satisfy the requirement for submission of the "Statement of Compliance"
required by paragraph (3)(ii)(B) of this section.
(D) The falsification of any of the above certifications may subject the contractor or subcontractor
to civil or criminal prosecution under Section 1001 of Title 18 and Section 231 of Title 31 of the United
States Code.
(iii) The contractor or subcontractor shall make the records required under paragraph (3)(i) of this section
available for inspection, copying or transcription by authorized representatives of the sponsor, the Federal
Aviation Administration or the Department of Labor, and shall permit such representatives to interview
employees during working hours on the job. If the contractor or subcontractor fails to submit the required
records or to make them available, the Federal agency may, after written notice to the contractor, sponsor,
applicant or owner, take such action as may be necessary to cause the suspension of any further payment,
advance, or guarantee of funds. Furthermore, failure to submit the required records upon request or to
make such records available may be grounds for debarment action pursuant to 29 CFR 5.12.
4. Apprentices and Trainees.
(i) Apprentices. Apprentices will be permitted to work at less than the predetermined rate for the work
they performed when they are employed pursuant to and individually registered in a bona fide
apprenticeship program registered with the U.S. Department of Labor, Employment and Training
Administration, Bureau of Apprenticeship and Training, or with a State Apprenticeship Agency
recognized by the Bureau, or if a person is employed in his or her first 90 days of probationary
employment as an apprentice in such an apprenticeship program, who is not individually registered in the
program, but who has been certified by the Bureau of Apprenticeship and Training or a State
Apprenticeship Agency (where appropriate) to be eligible for probationary employment as an apprentice.
The allowable ratio of apprentices to journeymen on the job site in any craft classification shall not be
greater than the ratio permitted to the contractor as to the entire work force under the registered program.
Any worker listed on a payroll at an apprentice wage rate, who is not registered or otherwise employed as
stated above, shall be paid not less than the applicable wage rate on the wage determination for the
classification of work actually performed. In addition, any apprentice performing work on the job site in
excess of the ratio permitted under the registered program shall be paid not less than the applicable wage
rate on the wage determination for the work actually performed. Where a contractor is performing
construction on a project in a locality other than that in which its program is registered, the ratios and
wage rates (expressed in percentages of the journeyman's hourly rate) specified in the contractor's or
subcontractor's registered program shall be observed. Every apprentice must be paid at not less than the
rate specified in the registered program for the apprentice's level of progress, expressed as a percentage of
the journeymen hourly rate specified in the applicable wage determination. Apprentices shall be paid
fringe benefits in accordance with the provisions of the apprenticeship program. If the apprenticeship
program does not specify fringe benefits, apprentices must be paid the full amount of fringe benefits listed
on the wage determination for the applicable classification. If the Administrator determines that a different
practice prevails for the applicable apprentice classification, fringes shall be paid in accordance with that
determination. In the event the Bureau of Apprenticeship and Training, or a State Apprenticeship Agency
recognized by the Bureau, withdraws approval of an apprenticeship program, the contractor will no longer
be permitted to utilize apprentices at less than the applicable predetermined rate for the work performed
until an acceptable program is approved.
(ii) Trainees. Except as provided in 29 CFR 5.16, trainees will not be permitted to work at less than the
predetermined rate for the work performed unless they are employed pursuant to and individually
registered in a program which has received prior approval, evidenced by formal certification by the U.S.
Department of Labor, Employment and Training Administration. The ratio of trainees to journeymen on
the job site shall not be greater than permitted under the plan approved by the Employment and Training
Administration. Every trainee must be paid at not less than the rate specified in the approved program for
the trainee's level of progress, expressed as a percentage of the journeyman hourly rate specified in the
applicable wage determination. Trainees shall be paid fringe benefits in accordance with the provisions of
the trainee program. If the trainee program does not mention fringe benefits, trainees shall be paid the full
amount of fringe benefits listed on the wage determination unless the Administrator of the Wage and Hour
Division determines that there is an apprenticeship program associated with the corresponding journeyman
wage rate on the wage determination which provides for less than full fringe benefits for apprentices. Any
employee listed on the payroll at a trainee rate that is not registered and participating in a training plan
approved by the Employment and Training Administration shall be paid not less than the applicable wage
rate on the wage determination for the classification of work actually performed. In addition, any trainee
performing work on the job site in excess of the ratio permitted under the registered program shall be paid
not less than the applicable wage rate on the wage determination for the work actually performed. In the
event the Employment and Training Administration withdraws approval of a training program, the
contractor will no longer be permitted to utilize trainees at less than the applicable predetermined rate for
the work performed until an acceptable program is approved. (iii) Equal Employment Opportunity. The
utilization of apprentices, trainees and journeymen under this part shall be in conformity with the equal
employment opportunity requirements of Executive Order 11246, as amended, and 29 CFR Part 30.
5. Compliance with Copeland Act Requirements.
The contractor shall comply with the requirements of 29 CFR Part 3, which are incorporated by reference
in this contract.
6. Subcontracts.
The contractor or subcontractor shall insert in any subcontracts the clauses contained in 29 CFR Part
5.5(a)(1) through (10) and such other clauses as the Federal Aviation Administration may by appropriate
instructions require, and also a clause requiring the subcontractors to include these clauses in any lower
tier subcontracts. The prime contractor shall be responsible for the compliance by any subcontractor or
lower tier subcontractor with all the contract clauses in 29 CFR Part 5.5.
7. Contract Termination: Debarment.
A breach of the contract clauses in paragraph 1 through 10 of this section may be grounds for termination
of the contract, and for debarment as a contractor and a subcontractor as provided in 29 CFR 5.12.
8. Compliance With Davis-Bacon and Related Act Requirements.
All rulings and interpretations of the Davis-Bacon and Related Acts contained in 29 CFR Parts 1, 3, and 5
are herein incorporated by reference in this contract.
9. Disputes Concerning Labor Standards.
Disputes arising out of the labor standards provisions of this contract shall not be subject to the general
disputes clause of this contract. Such disputes shall be resolved in accordance with the procedures of the
Department of Labor set forth in 29 CFR Parts 5, 6 and 7. Disputes within the meaning of this clause
include disputes between the contractor (or any of its subcontractors) and the contracting agency, the U.S.
Department of Labor, or the employees or their representatives.
10. Certification of Eligibility.
(i) By entering into this contract, the contractor certifies that neither it (nor he or she) nor any person or
firm who has an interest in the contractor's firm is a person or firm ineligible to be awarded Government
contracts by virtue of section 3(a) of the Davis-Bacon Act or 29 CFR 5.12(a)(1). (ii) No part of this
contract shall be subcontracted to any person or firm ineligible for award of a Government contract by
virtue of section 3(a) of the Davis-Bacon Act or 29 CFR 5.12(a)(1). (iii) The penalty for making false
statements is prescribed in the U.S. Criminal Code, 18 U.S.C. 1001.
DEPARTMENT OF LABOR WAGE DETERMINATION
General Decision Number: FL170206 01/06/2017 FL206
Superseded General Decision Number: FL20160206
State: Florida
Construction Type: Highway
County: Collier County in Florida.
HIGHWAY CONSTRUCTION PROJECTS
Note: Under Executive Order (EO) 13658, an hourly minimum wage
of $10.20 for calendar year 2017 applies to all contracts
subject to the Davis-Bacon Act for which the contract is awarded
(and any solicitation was issued) on or after January 1, 2015.
If this contract is covered by the EO, the contractor must pay
all workers in any classification listed on this wage
determination at least $10.20 per hour (or the applicable
wage rate listed on this wage determination, if it is higher)
for all hours spent performing on the contract in calendar
year 2017. The EO minimum wage rate will be adjusted annually.
Additional information on contractor requirements and worker
protections under the EO is available at
www.dol.gov/whd/govcontracts.
Modification Number Publication Date
0 01/06/2017
* SUFL2013-024 08/19/2013
Rates Fringes
CARPENTER, Includes Form Work....$ 12.52 0.00
CEMENT MASON/CONCRETE FINISHER...$ 12.98 0.00
ELECTRICIAN......................$ 21.92 6.60
HIGHWAY/PARKING LOT STRIPING:
Operator (Striping Machine).....$ 16.72 0.00
HIGHWAY/PARKING LOT STRIPING:
Painter.........................$ 12.13 0.00
IRONWORKER, ORNAMENTAL...........$ 13.48 0.00
IRONWORKER, REINFORCING..........$ 16.39 0.00
IRONWORKER, STRUCTURAL...........$ 16.42 0.00
LABORER (Traffic Control
Specialist)......................$ 12.05 1.95
LABORER: Asphalt, Includes
Raker, Shoveler, Spreader and
Distributor......................$ 13.89 0.00
LABORER: Common or General......$ 11.76 0.00
LABORER: Flagger................$ 11.77 0.00
LABORER: Grade Checker..........$ 15.88 0.00
LABORER: Landscape &
Irrigation.......................$ 11.12 0.00
LABORER: Mason Tender -
Cement/Concrete..................$ 12.93 0.00
LABORER: Pipelayer..............$ 13.63 0.00
OPERATOR:
Backhoe/Excavator/Trackhoe.......$ 16.55 0.00
OPERATOR: Bobcat/Skid
Steer/Skid Loader................$ 12.88 0.00
OPERATOR: Broom/Sweeper.........$ 13.69 0.00
OPERATOR: Bulldozer.............$ 18.01 0.00
OPERATOR: Concrete Finishing
Machine..........................$ 15.44 0.00
OPERATOR: Crane.................$ 21.69 0.00
OPERATOR: Curb Machine..........$ 19.67 0.00
OPERATOR: Drill.................$ 14.78 0.00
OPERATOR: Forklift..............$ 12.58 0.00
OPERATOR: Gradall...............$ 14.71 0.00
OPERATOR: Grader/Blade..........$ 20.34 0.00
OPERATOR: Loader................$ 16.24 0.00
OPERATOR: Mechanic..............$ 17.86 0.00
OPERATOR: Milling Machine.......$ 17.23 0.00
OPERATOR: Oiler.................$ 17.31 0.00
OPERATOR: Paver (Asphalt,
Aggregate, and Concrete).........$ 16.82 0.00
OPERATOR: Piledriver............$ 17.23 0.00
OPERATOR: Post Driver
(Guardrail/Fences)...............$ 19.35 0.00
OPERATOR: Roller................$ 15.56 0.00
OPERATOR: Scraper...............$ 11.74 0.00
OPERATOR: Screed................$ 16.67 0.00
OPERATOR: Trencher..............$ 16.07 0.66
PAINTER: Spray..................$ 16.38 0.00
TRUCK DRIVER: Dump Truck........$ 14.99 0.00
TRUCK DRIVER: Flatbed Truck.....$ 14.13 0.00
TRUCK DRIVER: Lowboy Truck......$ 18.00 0.00
TRUCK DRIVER: Slurry Truck......$ 11.96 0.00
TRUCK DRIVER: Water Truck.......$ 14.16 0.00
----------------------------------------------------------------
WELDERS - Receive rate prescribed for craft performing
operation to which welding is incidental.
================================================================
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave
for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any
solicitation was issued) on or after January 1, 2017. If this
contract is covered by the EO, the contractor must provide
employees with 1 hour of paid sick leave for every 30 hours
they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their
own illness, injury or other health-related needs, including
preventive care; to assist a family member (or person who is
like family to the employee) who is ill, injured, or has other
health-related needs, including preventive care; or for reasons
resulting from, or to assist a family member (or person who is
like family to the employee) who is a victim of, domestic
violence, sexual assault, or stalking. Additional information
on contractor requirements and worker protections under the EO
is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within
the scope of the classifications listed may be added after
award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (ii)).
----------------------------------------------------------------
The body of each wage determination lists the classification
and wage rates that have been found to be prevailing for the
cited type(s) of construction in the area covered by the wage
determination. The classifications are listed in alphabetical
order of "identifiers" that indicate whether the particular
rate is a union rate (current union negotiated rate for local),
a survey rate (weighted average rate) or a union average rate
(weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed
in dotted lines beginning with characters other than "SU" or
"UAVG" denotes that the union classification and rate were
prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of
the union which prevailed in the survey for this
classification, which in this example would be Plumbers. 0198
indicates the local union number or district council number
where applicable, i.e., Plumbers Local 0198. The next number,
005 in the example, is an internal number used in processing
the wage determination. 07/01/2014 is the effective date of the
most current negotiated rate, which in this example is July 1,
2014.
Union prevailing wage rates are updated to reflect all rate
changes in the collective bargaining agreement (CBA) governing
this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that
no one rate prevailed for this classification in the survey and
the published rate is derived by computing a weighted average
rate based on all the rates reported in the survey for that
classification. As this weighted average rate includes all
rates reported in the survey, it may include both union and
non-union rates. Example: SULA2012-007 5/13/2014. SU indicates
the rates are survey rates based on a weighted average
calculation of rates and are not majority rates. LA indicates
the State of Louisiana. 2012 is the year of survey on which
these classifications and rates are based. The next number, 007
in the example, is an internal number used in producing the
wage determination. 5/13/2014 indicates the survey completion
date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a
new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate
that no single majority rate prevailed for those
classifications; however, 100% of the data reported for the
classifications was union data. EXAMPLE: UAVG-OH-0010
08/29/2014. UAVG indicates that the rate is a weighted union
average rate. OH indicates the state. The next number, 0010 in
the example, is an internal number used in producing the wage
determination. 08/29/2014 indicates the survey completion date
for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of
each year, to reflect a weighted average of the current
negotiated/CBA rate of the union locals from which the rate is
based.
----------------------------------------------------------------
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can
be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on
a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests
for summaries of surveys, should be with the Wage and Hour
Regional Office for the area in which the survey was conducted
because those Regional Offices have responsibility for the
Davis-Bacon survey program. If the response from this initial
contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal
process described here, initial contact should be with the
Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an
interested party (those affected by the action) can request
review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the
interested party's position and by any information (wage
payment data, project description, area practice material,
etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an
interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
================================================================
END OF GENERAL DECISION
�
11. DEBARMENT AND SUSPENSION
2 CFR part 180 (Subpart C), 2 CFR part 1200, DOT Order 4200.5
Bidder or Offeror Certification
By submitting a bid/proposal under this solicitation, the bidder or offeror certifies that neither it nor its
principals are presently debarred or suspended by any Federal department or agency from participation in
this transaction.
Lower Tier Contract Certification
The successful bidder, by administering each lower tier subcontract that exceeds $25,000 as a “covered
transaction”, must verify each lower tier participant of a “covered transaction” under the project is not
presently debarred or otherwise disqualified from participation in this federally assisted project. The
successful bidder will accomplish this by:
1. Checking the System for Award Management at website: http://www.sam.gov
2. Collecting a certification statement similar to the Certificate Regarding Debarment and Suspension
(Bidder or Offeror), above.
3. Inserting a clause or condition in the covered transaction with the lower tier contract
If the FAA later determines that a lower tier participant failed to disclose to a higher tier participant that it
was excluded or disqualified at the time it entered the covered transaction, the FAA may pursue any
available remedies, including suspension and debarment of the non-compliant participant.
12. DISADVANTAGED BUSINESS ENTERPRISES
(Applies to subcontracts)
49 CFR part 26
The requirements of 49 CFR Part 26, Regulations of the U.S. Department of Transportation, apply to this
contract. It is the policy of the Collier County Airport Authority, as owner of the Collier County General
Aviation Airports, to practice nondiscrimination based on race, color, sex, or national origin in the award or
performance of this contract. All firms qualifying under this solicitation are encouraged to submit
bids/proposals. Award of this contract will be conditioned upon satisfying the requirements of this bid
specification. These requirements apply to all bidders, including those who qualify as a DBE. A DBE
contract goal of 5.9 percent has been established for this contract. The bidder shall make good faith
efforts, as defined in Appendix A, 49 CFR Part 26, to meet the contract goal for DBE participation in the
performance of this contract.
The bidder will be required to submit the following information with their proposal on the forms provided
herein:
(1) The names and addresses of DBE firms that will participate in the contract;
(2) A description of the work that each DBE firm will perform;
(3) The dollar amount of the participation of each DBE firm participating;
(4) Written documentation of the bidder’s commitment to use a DBE subcontractor whose
participation it submits to meet the contract goal;
(5) Written confirmation from the DBE that it is participating in the contract as provided in the
commitment made under (4);
(6) If the contract goal is not met, evidence of good faith efforts.
Contract Assurance (§ 26.13) - The contractor or subcontractor shall not discriminate on the basis of
race, color, national origin, or sex in the performance of this contract. The contractor shall carry out
applicable requirements of 49 CFR Part 26 in the award and administration of DOT assisted contracts.
Failure by the contractor to carry out these requirements is a material breach of this contract, which may
result in the termination of this contract or such other remedy, as the recipient deems appropriate.
Prompt Payment Mechanisms (§26.29) - The prime contractor agrees to pay each subcontractor under
this prime contract for satisfactory performance of its contract no later than thirty (30) days from the
receipt of each payment the prime contract receives from the Authority. The prime contractor agrees
further to return retainage payments to each subcontractor within thirty (30) days after the subcontractors
work is satisfactorily completed. Any delay or postponement of payment from the above referenced time
frame may occur only for good cause following written approval of the Authority. This clause applies to
both DBE and non-DBE subcontracts.
Directory (§26.31)
The Authority uses the Florida Unified Certification Program (FL UCP) DBE Directory, maintained by the
Florida Department of Transportation (FDOT). The Directory lists the firm’s name, address, phone number,
date of the most recent certification, and the type of work the firm has been certified to perform as a DBE.
In addition, the Directory lists each type of work for which a firm is eligible to be certified by using the
most specific NAICS code available to describe each type of work.
The Florida Department of Transportation updates the Directory at least annually, and periodically, as
necessary. The Directory is available for review by contacting: Justin Lobb, Airport Manager, Collier
County Airport Authority, 2005 Mainsail Drive, Suite 1, Naples, FL 34114, 239-642-7878. The Directory
may be found at http://www.dot.state.fl.us/equalopportunityoffice/
Certification Process (§ 26.61 – 26.73)
The Authority will refer all matters pertaining to certification to the Florida Department of Transportation in
accordance with the Florida UCP program. The Florida Department of Transportation will use the
certification standards of Subpart D of Part 26 to determine the eligibility of firms to participate as DBEs in
USDOT-assisted contracts. To be certified as a DBE, a firm must meet all certification eligibility standards.
The Florida Department of Transportation will make all certification decisions based on the facts as a
whole.
For information about the certification process or to apply for certification, firms should contact:
Florida Department of Transportation (FDOT)
Equal Opportunity Office
605 Suwannee St. MS 65
Tallahassee, Florida 32399-0450
(850) 414-4747
Equal Opportunity Office
http://www.dot.state.fl.us/equalopportunityoffice/
Administrative reconsideration (§26.53(d))
Within ten (10) days of being informed by the Authority that it is not responsive because it has not
documented sufficient good faith efforts, a bidder may request administrative reconsideration. Bidders
should make this request in writing to the following reconsideration official: Gene Shue, Operations
Support Director, Collier County Airport Authority, 2885 S. Horseshoe Drive, Naples, FL 34104, 239-
252-5169. The reconsideration official will not have played any role in the original determination that the
bidder did not document sufficient good faith efforts.
As part of this reconsideration, the bidder will have the opportunity to provide written documentation or
argument concerning the issue of whether it met the goal or made adequate good faith efforts to do so. The
bidder will have the opportunity to meet in person with the Authority’s administrative reconsideration
official to discuss the issue of whether it met the goal or made adequate good faith efforts to do. The
Authority will send the bidder a written decision on reconsideration, explaining the basis for finding that
the bidder did or did not meet the goal or make adequate good faith efforts to do so. The result of the
reconsideration process is not administratively appealable to the US Department of Transportation.
13. TEXTING WHEN DRIVING
Executive Order 13513, DOT Order 3902.10
In accordance with Executive Order 13513, "Federal Leadership on Reducing Text Messaging While
Driving" (10/1/2009) and DOT Order 3902.10 “Text Messaging While Driving” (12/30/2009), the FAA
encourages recipients of Federal grant funds to adopt and enforce safety policies that decrease crashes by
distracted drivers, including policies to ban text messaging while driving when performing work related to
a grant or sub-grant.
In support of this initiative, the Owner encourages the Contractor to promote policies and initiatives for its
employees and other work personnel that decrease crashes by distracted drivers, including policies that
ban text messaging while driving motor vehicles while performing work activities associated with the
project. The Contractor must include the substance of this clause in all sub-tier contracts exceeding
$3,500 and involve driving a motor vehicle in performance of work activities associated with the project.
14. ENERGY CONSERVATION REQUIREMENTS
2 CFR § 200, Appendix II(H)
Contractor and Subcontractor agree to comply with mandatory standards and policies relating to energy
efficiency as contained in the state energy conservation plan issued in compliance with the Energy Policy
and Conservation Act (42 U.S.C. 6201et seq).
15. EQUAL OPPORTUNITY
(Applies to subcontracts)
2 CFR 200, Appendix II(C), 41 CFR § 60-1.4, 41 CFR § 60-4.3, Executive Order 11246
During the performance of this contract, the contractor agrees as follows:
(1) The contractor will not discriminate against any employee or applicant for employment because of
race, color, religion, sex, or national origin. The contractor will take affirmative action to ensure that
applicants are employed, and that employees are treated during employment without regard to their race,
color, religion, sex, sexual orientation, gender identify or national origin. Such action shall include, but not
be limited to the following: employment, upgrading, demotion, or transfer; recruitment or recruitment
advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training,
including apprenticeship. The contractor agrees to post in conspicuous places, available to employees and
applicants for employment, notices to be provided setting forth the provisions of this nondiscrimination
clause.
(2) The contractor will, in all solicitations or advertisements for employees placed by or on behalf of the
contractor, state that all qualified applicants will receive considerations for employment without regard to
race, color, religion, sex, or national origin.
(3) The contractor will send to each labor union or representative of workers with which he has a
collective bargaining agreement or other contract or understanding, a notice to be provided advising the
said labor union or workers' representatives of the contractor's commitments under this section, and shall
post copies of the notice in conspicuous places available to employees and applicants for employment.
(4) The contractor will comply with all provisions of Executive Order 11246 of September 24, 1965, and
of the rules, regulations, and relevant orders of the Secretary of Labor.
(5) The contractor will furnish all information and reports required by Executive Order 11246 of
September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant thereto,
and will permit access to his books, records, and accounts by the administering agency and the Secretary
of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.
(6) In the event of the contractor's noncompliance with the nondiscrimination clauses of this contract or
with any of the said rules, regulations, or orders, this contract may be canceled, terminated, or suspended
in whole or in part and the contractor may be declared ineligible for further Government contracts or
federally assisted construction contracts in accordance with procedures authorized in Executive Order
11246 of September 24, 1965, and such other sanctions may be imposed and remedies invoked as
provided in Executive Order 11246 of September 24, 1965, or by rule, regulation, or order of the Secretary
of Labor, or as otherwise provided by law.
(7) The contractor will include the portion of the sentence immediately preceding paragraph (1) and the
provisions of paragraphs (1) through (7) in every subcontract or purchase order unless exempted by rules,
regulations, or orders of the Secretary of Labor issued pursuant to section 204 of Executive Order 11246
of September 24, 1965, so that such provisions will be binding upon each subcontractor or vendor. The
contractor will take such action with respect to any subcontract or purchase order as the administering
agency may direct as a means of enforcing such provisions, including sanctions for noncompliance:
Provided, however, That in the event a contractor becomes involved in, or is threatened with, litigation
with a subcontractor or vendor as a result of such direction by the administering agency the contractor may
request the United States to enter into such litigation to protect the interests of the United States.
STANDARD FEDERAL EQUAL EMPLOYMENT OPPORTUNITY CONSTRUCTION
CONTRACT SPECIFICATIONS
1. As used in these specifications:
a. "Covered area" means the geographical area described in the solicitation from which this contract
resulted;
b. "Director" means Director, Office of Federal Contract Compliance Programs (OFCCP), U.S.
Department of Labor, or any person to whom the Director delegates authority;
c. "Employer identification number" means the Federal social security number used on the
Employer's Quarterly Federal Tax Return, U.S. Treasury Department Form 941;
d. "Minority" includes:
(1) Black (all) persons having origins in any of the Black African racial groups not of Hispanic
origin);
(2) Hispanic (all persons of Mexican, Puerto Rican, Cuban, Central or South American, or other
Spanish culture or origin regardless of race);
(3) Asian and Pacific Islander (all persons having origins in any of the original peoples of the
Far East, Southeast Asia, the Indian Subcontinent, or the Pacific Islands); and
(4) American Indian or Alaskan native (all persons having origins in any of the original peoples
of North America and maintaining identifiable tribal affiliations through membership and
participation or community identification).
2. Whenever the contractor, or any subcontractor at any tier, subcontracts a portion of the work involving
any construction trade, it shall physically include in each subcontract in excess of $10,000 the provisions
of these specifications and the Notice which contains the applicable goals for minority and female
participation and which is set forth in the solicitations from which this contract resulted.
3. If the contractor is participating (pursuant to 41 CFR 60-4.5) in a Hometown Plan approved by the U.S.
Department of Labor in the covered area either individually or through an association, its affirmative
action obligations on all work in the Plan area (including goals and timetables) shall be in accordance with
that Plan for those trades which have unions participating in the Plan. Contractors shall be able to
demonstrate their participation in and compliance with the provisions of any such Hometown Plan. Each
contractor or subcontractor participating in an approved plan is individually required to comply with its
obligations under the EEO clause and to make a good faith effort to achieve each goal under the Plan in
each trade in which it has employees. The overall good faith performance by other contractors or
subcontractors toward a goal in an approved Plan does not excuse any covered contractor's or
subcontractor's failure to take good faith efforts to achieve the Plan goals and timetables.
4. The contractor shall implement the specific affirmative action standards provided in paragraphs 7a
through 7p of these specifications. The goals set forth in the solicitation from which this contract resulted
are expressed as percentages of the total hours of employment and training of minority and female
utilization the contractor should reasonably be able to achieve in each construction trade in which it has
employees in the covered area. Covered construction contractors performing construction work in a
geographical area where they do not have a Federal or federally assisted construction contract shall apply
the minority and female goals established for the geographical area where the work is being performed.
Goals are published periodically in the Federal Register in notice form, and such notices may be obtained
from any Office of Federal Contract Compliance Programs office or from Federal procurement contracting
officers. The contractor is expected to make substantially uniform progress in meeting its goals in each
craft during the period specified.
5. Neither the provisions of any collective bargaining agreement nor the failure by a union with whom the
contractor has a collective bargaining agreement to refer either minorities or women shall excuse the
contractor's obligations under these specifications, Executive Order 11246 or the regulations promulgated
pursuant thereto.
6. In order for the non-working training hours of apprentices and trainees to be counted in meeting the
goals, such apprentices and trainees shall be employed by the contractor during the training period and the
contractor shall have made a commitment to employ the apprentices and trainees at the completion of their
training, subject to the availability of employment opportunities. Trainees shall be trained pursuant to
training programs approved by the U.S. Department of Labor.
7. The contractor shall take specific affirmative actions to ensure equal employment opportunity. The
evaluation of the contractor's compliance with these specifications shall be based upon its effort to achieve
maximum results from its actions. The contractor shall document these efforts fully and shall implement
affirmative action steps at least as extensive as the following:
a. Ensure and maintain a working environment free of harassment, intimidation, and coercion at all
sites, and in all facilities at which the contractor's employees are assigned to work. The contractor,
where possible, will assign two or more women to each construction project. The contractor shall
specifically ensure that all foremen, superintendents, and other onsite supervisory personnel are aware
of and carry out the contractor's obligation to maintain such a working environment, with specific
attention to minority or female individuals working at such sites or in such facilities.
b. Establish and maintain a current list of minority and female recruitment sources, provide written
notification to minority and female recruitment sources and to community organizations when the
contractor or its unions have employment opportunities available, and maintain a record of the
organizations' responses.
c. Maintain a current file of the names, addresses, and telephone numbers of each minority and female
off-the-street applicant and minority or female referral from a union, a recruitment source, or
community organization and of what action was taken with respect to each such individual. If such
individual was sent to the union hiring hall for referral and was not referred back to the contractor by
the union or, if referred, not employed by the contractor, this shall be documented in the file with the
reason therefore along with whatever additional actions the contractor may have taken.
d. Provide immediate written notification to the Director when the union or unions with which the
contractor has a collective bargaining agreement has not referred to the contractor a minority person or
female sent by the contractor, or when the contractor has other information that the union referral
process has impeded the contractor's efforts to meet its obligations.
e. Develop on-the-job training opportunities and/or participate in training programs for the area which
expressly include minorities and women, including upgrading programs and apprenticeship and
trainee programs relevant to the contractor's employment needs, especially those programs funded or
approved by the Department of Labor. The contractor shall provide notice of these programs to the
sources compiled under 7b above.
f. Disseminate the contractor's EEO policy by providing notice of the policy to unions and training
programs and requesting their cooperation in assisting the contractor in meeting its EEO obligations;
by including it in any policy manual and collective bargaining agreement; by publicizing it in the
company newspaper, annual report, etc.; by specific review of the policy with all management
personnel and with all minority and female employees at least once a year; and by posting the
company EEO policy on bulletin boards accessible to all employees at each location where
construction work is performed.
g. Review, at least annually, the company's EEO policy and affirmative action obligations under these
specifications with all employees having any responsibility for hiring, assignment, layoff, termination,
or other employment decisions including specific review of these items with onsite supervisory
personnel such a superintendents, general foremen, etc., prior to the initiation of construction work at
any job site. A written record shall be made and maintained identifying the time and place of these
meetings, persons attending, subject matter discussed, and disposition of the subject matter.
h. Disseminate the contractor's EEO policy externally by including it in any advertising in the news
media, specifically including minority and female news media, and providing written notification to
and discussing the contractor's EEO policy with other contractors and subcontractors with whom the
contractor does or anticipates doing business.
i. Direct its recruitment efforts, both oral and written, to minority, female, and community
organizations, to schools with minority and female students; and to minority and female recruitment
and training organizations serving the contractor's recruitment area and employment needs. Not later
than one month prior to the date for the acceptance of applications for apprenticeship or other training
by any recruitment source, the contractor shall send written notification to organizations, such as the
above, describing the openings, screening procedures, and tests to be used in the selection process.
j. Encourage present minority and female employees to recruit other minority persons and women and,
where reasonable, provide after school, summer, and vacation employment to minority and female
youth both on the site and in other areas of a contractor's workforce.
k. Validate all tests and other selection requirements where there is an obligation to do so under 41
CFR Part 60-3.
l. Conduct, at least annually, an inventory and evaluation at least of all minority and female personnel,
for promotional opportunities and encourage these employees to seek or to prepare for, through
appropriate training, etc., such opportunities.
m. Ensure that seniority practices, job classifications, work assignments, and other personnel practices
do not have a discriminatory effect by continually monitoring all personnel and employment related
activities to ensure that the EEO policy and the contractor's obligations under these specifications are
being carried out.
n. Ensure that all facilities and company activities are non-segregated except that separate or single
user toilet and necessary changing facilities shall be provided to assure privacy between the sexes.
o. Document and maintain a record of all solicitations of offers for subcontracts from minority and
female construction contractors and suppliers, including circulation of solicitations to minority and
female contractor associations and other business associations.
p. Conduct a review, at least annually, of all supervisor's adherence to and performance under the
contractor's EEO policies and affirmative action obligations.
8. Contractors are encouraged to participate in voluntary associations, which assist in fulfilling one or
more of their affirmative action obligations (7a through 7p). The efforts of a contractor association, joint
contractor union, contractor community, or other similar groups of which the contractor is a member and
participant, may be asserted as fulfilling any one or more of its obligations under 7a through 7p of these
specifications provided that the contractor actively participates in the group, makes every effort to assure
that the group has a positive impact on the employment of minorities and women in the industry, ensures
that the concrete benefits of the program are reflected in the contractor's minority and female workforce
participation, makes a good faith effort to meet its individual goals and timetables, and can provide access
to documentation which demonstrates the effectiveness of actions taken on behalf of the contractor. The
obligation to comply, however, is the contractor's and failure of such a group to fulfill an obligation shall
not be a defense for the contractor's noncompliance.
9. A single goal for minorities and a separate single goal for women have been established. The
contractor, however, is required to provide equal employment opportunity and to take affirmative action
for all minority groups, both male and female, and all women, both minority and non-minority.
Consequently, if the particular group is employed in a substantially disparate manner (for example, even
though the contractor has achieved its goals for women generally,) the contractor may be in violation of
the Executive Order if a specific minority group of women is underutilized.
10. The contractor shall not use the goals and timetables or affirmative action standards to discriminate
against any person because of race, color, religion, sex, or national origin.
11. The contractor shall not enter into any subcontract with any person or firm debarred from Government
contracts pursuant to Executive Order 11246.
12. The contractor shall carry out such sanctions and penalties for violation of these specifications and of
the Equal Opportunity Clause, including suspension, termination, and cancellation of existing subcontracts
as may be imposed or ordered pursuant to Executive Order 11246, as amended, and its implementing
regulations, by the Office of Federal Contract Compliance Programs. Any contractor who fails to carry out
such sanctions and penalties shall be in violation of these specifications and Executive Order 11246, as
amended.
13. The contractor, in fulfilling its obligations under these specifications, shall implement specific
affirmative action steps, at least as extensive as those standards prescribed in paragraph 7 of these
specifications, so as to achieve maximum results from its efforts to ensure equal employment opportunity.
If the contractor fails to comply with the requirements of the Executive Order, the implementing
regulations, or these specifications, the Director shall proceed in accordance with 41 CFR 60-4.8.
14. The contractor shall designate a responsible official to monitor all employment related activity to
ensure that the company EEO policy is being carried out, to submit reports relating to the provisions
hereof as may be required by the Government, and to keep records. Records shall at least include for each
employee, the name, address, telephone number, construction trade, union affiliation if any, employee
identification number when assigned, social security number, race, sex, status (e.g., mechanic, apprentice,
trainee, helper, or laborer), dates of changes in status, hours worked per week in the indicated trade, rate of
pay, and locations at which the work was performed. Records shall be maintained in an easily
understandable and retrievable form; however, to the degree that existing records satisfy this requirement,
contractors shall not be required to maintain separate records.
15. Nothing herein provided shall be construed as a limitation upon the application of other laws which
establish different standards of compliance or upon the application of requirements for the hiring of local
or other area residents (e.g., those under the Public Works Employment Act of 1977 and the Community
Development Block Grant Program).
16. FEDERAL FAIR LABOR STANDARDS ACT (FEDERAL MINIMUM WAGE)
29 U.S.C. § 201, et seq
All contracts and subcontracts that result from this solicitation incorporate by reference the provisions of
29 CFR part 201, the Federal Fair Labor Standards Act (FLSA), with the same force and effect as if given
in full text. The FLSA sets minimum wage, overtime pay, recordkeeping, and child labor standards for
full and part time workers. The contractor or consultant has full responsibility to monitor compliance to
the referenced statute or regulation. The contractor or consultant must address any claims or disputes that
arise from this requirement directly with the U.S. Department of Labor – Wage and Hour Division
17. LOBBYING AND INFLUENCING FEDERAL EMPLOYEES
31 U.S.C. § 1352 – Byrd Anti-Lobbying Amendment, 2 CFR part 200, Appendix II(J), 49 CFR part
20, Appendix A
The bidder or offeror certifies by signing and submitting this bid or proposal, to the best of his or her
knowledge and belief, that:
(1) No Federal appropriated funds have been paid or will be paid, by or on behalf of the Bidder or
Offeror, to any person for influencing or attempting to influence an officer or employee of an
agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member
of Congress in connection with the awarding of any Federal contract, the making of any Federal
grant, the making of any Federal loan, the entering into of any cooperative agreement, and the
extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan,
or cooperative agreement.
(2) If any funds other than Federal appropriated funds have been paid or will be paid to any person for
influencing or attempting to influence an officer or employee of any agency, a Member of
Congress, an officer or employee of Congress, or an employee of a Member of Congress in
connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall
complete and submit Standard Form-LLL, “Disclosure Form to Report Lobbying,” in accordance
with its instructions.
(3) The undersigned shall require that the language of this certification be included in the award
documents for all sub-awards at all tiers (including subcontracts, sub-grants, and contracts under
grants, loans, and cooperative agreements) and that all sub-recipients shall certify and disclose
accordingly.
This certification is a material representation of fact upon which reliance was placed when this transaction
was made or entered into. Submission of this certification is a prerequisite for making or entering into this
transaction imposed by section 1352, title 31, U.S. Code. Any person who fails to file the required
certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for
each such failure
18. PROHIBITION of SEGREGATED FACILITIES
41 CFR § 60
(a) The Contractor agrees that it does not and will not maintain or provide for its employees any
segregated facilities at any of its establishments, and that it does not and will not permit its employees to
perform their services at any location under its control where segregated facilities are maintained. The
Contractor agrees that a breach of this clause is a violation of the Equal Opportunity clause in this
contract.
(b) “Segregated facilities,” as used in this clause, means any waiting rooms, work areas, rest rooms and
wash rooms, restaurants and other eating areas, time clocks, locker rooms and other storage or dressing
areas, parking lots, drinking fountains, recreation or entertainment areas, transportation, and housing
facilities provided for employees, that are segregated by explicit directive or are in fact segregated on the
basis of race, color, religion, sex, or national origin because of written or oral policies or employee
custom. The term does not include separate or single-user rest rooms or necessary dressing or sleeping
areas provided to assure privacy between the sexes.
(c) The Contractor shall include this clause in every subcontract and purchase order that is subject to the
Equal Opportunity clause of this contract.
19. OCCUPATIONAL SAFETY AND HEALTH ACT OF 1970
20 CFR part 1910
All contracts and subcontracts that result from this solicitation incorporate by reference the requirements
of 29 CFR Part 1910 with the same force and effect as if given in full text. Contractor must provide a
work environment that is free from recognized hazards that may cause death or serious physical harm to
the employee. The Contractor retains full responsibility to monitor its compliance and their
subcontractor’s compliance with the applicable requirements of the Occupational Safety and Health Act of
1970 (20 CFR Part 1910). Contractor must address any claims or disputes that pertain to a referenced
requirement directly with the U.S. Department of Labor – Occupational Safety and Health Administration.
20. PROCUREMENT OF RECOVERED MATERIALS
2 CFR § 200.322, 40 CFR part 247
Contractor and subcontractor agree to comply with Section 6002 of the Solid Waste Disposal Act, as
amended by the Resource Conservation and Recovery Act, and the regulatory provisions of 40 CFR Part
247. In the performance of this contract and to the extent practicable, the Contractor and subcontractors
are to use of products containing the highest percentage of recovered materials for items designated by the
Environmental Protection Agency (EPA) under 40 CFR Part 247 whenever:
a) The contract requires procurement of $10,000 or more of a designated item during the fiscal year;
or,
b) The contractor has procured $10,000 or more of a designated item using Federal funding during the
previous fiscal year.
The list of EPA-designated items is available at www.epa.gov/epawaste/conserve/tools/cpg/products/.
Section 6002(c) establishes exceptions to the preference for recovery of EPA-designated products if the
contractor can demonstrate the item is:
a) Not reasonably available within a timeframe providing for compliance with the contract
performance schedule;
b) Fails to meet reasonable contract performance requirements; or
c) Is only available at an unreasonable price.
21. RIGHT TO INVENTIONS
2 CFR § 200, Appendix II(F), 37 CFR §401
Contracts or agreements that include the performance of experimental, developmental, or research work
must provide for the rights of the Federal Government and the Owner in any resulting invention as
established by 37 CFR part 401, Rights to Inventions Made by Non-profit Organizations and Small
Business Firms under Government Grants, Contracts, and Cooperative Agreements. This contract
incorporates by reference the patent and inventions rights as specified within in the 37 CFR §401.14.
Contractor must include this requirement in all sub-tier contracts involving experimental, developmental or
research work.
22. SEISMIC SAFETY
49 CFR part 41
The contractor agrees to ensure that all work performed under this contract, including work performed by
subcontractors, conforms to a building code standard that provides a level of seismic safety substantially
equivalent to standards established by the National Earthquake Hazards Reduction Program (NEHRP).
Local building codes that model their code after the current version of the International Building Code
(IBC) meet the NEHRP equivalency level for seismic safety.
23. TERMINATION
Termination for Default (Construction)
Section 80-09 of FAA Advisory Circular 150/5370-10 establishes conditions, rights and remedies
associated with Owner termination of this contract due default of the Contractor.
Termination for Convenience (Construction & Equipment Contracts)
The Owner may terminate this contract in whole or in part at any time by providing written notice to the
Contractor. Such action may be without cause and without prejudice to any other right or remedy of
Owner. Upon receipt of a written notice of termination, except as explicitly directed by the Owner, the
Contractor shall immediately proceed with the following obligations regardless of any delay in
determining or adjusting amounts due under this clause:
1. Contractor must immediately discontinue work as specified in the written notice.
2. Terminate all subcontracts to the extent they relate to the work terminated under the notice.
3. Discontinue orders for materials and services except as directed by the written notice.
4. Deliver to the owner all fabricated and partially fabricated parts, completed and partially
completed work, supplies, equipment and materials acquired prior to termination of the work and
as directed in the written notice.
5. Complete performance of the work not terminated by the notice.
6. Take action as directed by the owner to protect and preserve property and work related to this
contract that Owner will take possession.
Owner agrees to pay Contractor for:
a) completed and acceptable work executed in accordance with the contract documents prior to the
effective date of termination;
b) documented expenses sustained prior to the effective date of termination in performing work and
furnishing labor, materials, or equipment as required by the contract documents in connection with
uncompleted work;
c) reasonable and substantiated claims, costs and damages incurred in settlement of terminated
contracts with Subcontractors and Suppliers; and
d) reasonable and substantiated expenses to the contractor directly attributable to Owner’s termination
action
Owner will not pay Contractor for loss of anticipated profits or revenue or other economic loss arising out
of or resulting from the Owner’s termination action.
The rights and remedies this clause provides are in addition to any other rights and remedies provided by
law or under this contract.
24. TRADE RESTRICTION CERTIFICATION
49 USC § 50104, 49 CFR part 30
By submission of an offer, the Offeror certifies that with respect to this solicitation and any resultant
contract, the Offeror -
a. is not owned or controlled by one or more citizens of a foreign country included in the list of
countries that discriminate against U.S. firms as published by the Office of the United States
Trade Representative (U.S.T.R.);
b. has not knowingly entered into any contract or subcontract for this project with a person that is a
citizen or national of a foreign country included on the list of countries that discriminate against
U.S. firms as published by the U.S.T.R; and
c. has not entered into any subcontract for any product to be used on the Federal on the project that is
produced in a foreign country included on the list of countries that discriminate against U.S. firms
published by the U.S.T.R.
This certification concerns a matter within the jurisdiction of an agency of the United States of America
and the making of a false, fictitious, or fraudulent certification may render the maker subject to
prosecution under Title 18, United States Code, Section 1001.
The Offeror/Contractor must provide immediate written notice to the Owner if the Offeror/Contractor
learns that its certification or that of a subcontractor was erroneous when submitted or has become
erroneous by reason of changed circumstances. The Contractor must require subcontractors provide
immediate written notice to the Contractor if at any time it learns that its certification was erroneous by
reason of changed circumstances.
Unless the restrictions of this clause are waived by the Secretary of Transportation in accordance with 49
CFR 30.17, no contract shall be awarded to an Offeror or subcontractor:
(1) who is owned or controlled by one or more citizens or nationals of a foreign country included on the
list of countries that discriminate against U.S. firms published by the U.S.T.R. or
(2) whose subcontractors are owned or controlled by one or more citizens or nationals of a foreign
country on such U.S.T.R. list or
(3) who incorporates in the public works project any product of a foreign country on such U.S.T.R. list;
Nothing contained in the foregoing shall be construed to require establishment of a system of records in
order to render, in good faith, the certification required by this provision. The knowledge and information
of a contractor is not required to exceed that which is normally possessed by a prudent person in the
ordinary course of business dealings.
The Offeror agrees that, if awarded a contract resulting from this solicitation, it will incorporate this
provision for certification without modification in in all lower tier subcontracts. The contractor may rely
on the certification of a prospective subcontractor that it is not a firm from a foreign country included on
the list of countries that discriminate against U.S. firms as published by U.S.T.R, unless the Offeror has
knowledge that the certification is erroneous.
This certification is a material representation of fact upon which reliance was placed when making an
award. If it is later determined that the Contractor or subcontractor knowingly rendered an erroneous
certification, the Federal Aviation Administration may direct through the Owner cancellation of the
contract or subcontract for default at no cost to the Owner or the FAA.
25. VETERAN’S PREFERENCE
49 USC § 47112(c)
In the employment of labor (excluding executive, administrative, and supervisory positions), the
contractor and all sub-tier contractors must give preference to covered veterans as defined within Title 49
United States Code Section 47112. Covered veterans include Vietnam-era veterans, Persian Gulf
veterans, Afghanistan-Iraq war veterans, disabled veterans, and small business concerns (as defined by 15
U.S.C. 632) owned and controlled by disabled veterans. This preference only applies when there are
covered veterans readily available and qualified to perform the work to which the employment relates.
26. DISCRIMINATORY VENDORS LIST
287.134 F.S.
The contractor will not discriminate against any person on legally protected basis in any activity under this
solicitation or a contract. Any entity or affiliate that has been placed on the discriminatory vendor list may
not submit a bid on a contract to provide any goods or services to a public entity, may not submit a bid on a
contract with a public entity for the construction or repair of a public building or public work, may not
submit bids on leases of real property to a public entity, may not be awarded or perform work as a
contractor, supplier, subcontractor, or consultant under a contract with any public entity, and many not
transact business with any public entity.
CERTIFICATIONS AND FORMS
THE FOLLOWING DOCUMENTS NEED TO BE RETURNED WITH SOLICIATION
DOCUMENTS BY DEADLINE TO BE CONSIDERED RESPONSIVE
1. Certification Regarding Debarment, Suspension, and Other Responsibility Matters Primary
Covered Transactions
2. Conflict of Interest
3. Disclosure of Lobbying Activities
4. Buy American Certification for Manufactured Steel
5. Grant Acknowledgement of Terms and Conditions
6. Disadvantage Business Enterprise Utilization Forms 1-4
Certification Regarding Debarment, Suspension, and Other Responsibility Matters
Primary Covered Transactions
(1) The prospective primary participant certifies to the best of its knowledge and belief, that it and its principals: (a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency; (b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, or receiving stolen property; (c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offenses enumerated in paragraph (l)(b) of this certification; and (d) Have not within a three-year period preceding this application/proposal had one or more public transactions (Federal, State or local) terminated for cause or default. (2) Where the prospective primary participant is unable to certify to any of the statements in this certification, such prospective participant shall attach an explanation to this proposal.
__________________________ ________________________________________
Name Project Name
__________________________ ________________________________________
Title Project Number
__________________________ ________________________________________
Firm Tax ID Number
________________________________________
DUNS Number
_________________________________________________________________________
Street Address, City, State, Zip
__________________________________
Signature
Vendor Submittal – Conflict of Interest Certification
_______________________
Collier County Solicitation No.
I, ________________________________________, hereby certify that to the best of my
knowledge, neither I nor my spouse, dependent child, general partner, or any organization for
which I am serving as an officer, director, trustee, general partner or employee, or any person or
organization with whom I am negotiating or have an arrangement concerning prospective
employment has a financial interest in this matter.
I further certify to the best of my knowledge that this matter will not affect the financial interests of
any member of my household. Also, to the best of my knowledge, no member of my household; no
relative with whom I have a close relationship; no one with whom my spouse, parent or dependent
child has or seeks employment; and no organization with which I am seeking a business
relationship nor which I now serve actively or have served within the last year are parties or
represent a party to the matter.
I also acknowledge my responsibility to disclose the acquisition of any financial or personal
interest as described above that would be affected by the matter, and to disclose any interest I, or
anyone noted above, has in any person or organization that does become involved in, or is affected
at a later date by, the conduct of this matter.
Name Signature
Position Date
Privacy Act Statement
Title I of the Ethics in Government Act of 1978 (5 U.S.C. App.), Executive Order 12674 and 5 CFR Part 2634, Subpart I
require the reporting of this information. The primary use of the information on this form is for review by officials of The
Justice Department to determine compliance with applicable federal conflict of interest laws and regulations. Additional
disclosures of the information on this report may be made: (1) to a federal, state or local law enforcement agency if the
Justice Department becomes aware of a violation or potential violation of law or regulations; (2) to a court or party in a
court or federal administrative proceeding if the government is a party or in order to comply with a judge-issued
subpoena; (3) to a source when necessary to obtain information relevant to a conflict of interest investigation or
decision; (4) to the National Archives and Records Administration or the General Services Administration in records
management inspections; (5) to the Office of Management and Budget during legislative coordination on private relief
legislation; and (6) in response to a request for discovery or for the appearance of a witness in a judicial or
administrative proceeding, if the information is relevant to the subject matter. This confidential certification will not be
disclosed to any requesting person unless authorized by law. See also the OGE/GOVT-2 executive branch-wide Privacy
Act system of records.
Certification Regarding Lobbying
The undersigned (Vendor/ Contractor) certifies, to the best of
his or her knowledge and belief, that:
(1) No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any
person for influencing or attempting to influence an officer or employee of an agency, a Member of
Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with
the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the
entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or
modification of any Federal contract, grant, loan, or cooperative agreement.
(2) If any funds other than Federal appropriated funds have been paid or will be paid to any person for
making lobbying contacts to an officer or employee of any agency, a Member of Congress, an officer or
employee of Congress, or an employee of a Member of Congress in connection with this Federal contract,
grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard Form--LLL,
"Disclosure Form to Report Lobbying," in accordance with its instructions [as amended by "Government
wide Guidance for New Restrictions on Lobbying," 61 Fed. Reg. 1413 (1/19/96). Note: Language in
paragraph (2) herein has been modified in accordance with Section 10 of the Lobbying Disclosure Act of
1995 (P.L. 104-65, to be codified at 2 U.S.C. 1601, et seq.)]
(3) The undersigned shall require that the language of this certification be included in the award documents
for all subawards at all tiers (including subcontracts, subgrants, and contracts under grants, loans, and
cooperative agreements) and that all subrecipients shall certify and disclose accordingly.
This certification is a material representation of fact upon which reliance was placed when this transaction
was made or entered into. Submission of this certification is a prerequisite for making or entering into
this transaction imposed by 31, U.S.C. § 1352 (as amended by the Lobbying Disclosure Act of 1995).
Any person who fails to file the required certification shall be subject to a civil penalty of not less than
$10,000 and not more than $100,000 for each such failure.
[Note: Pursuant to 31 U.S.C. § 1352(c)(1)-(2)(A), any person who makes a prohibited expenditure or fails to
file or amend a required certification or disclosure form shall be subject to a civil penalty of not less than
$10,000 and not more than $100,000 for each such expenditure or failure.] The Vendor/Contractor, , certifies or affirms the truthfulness and
accuracy of each statement of its certification and disclosure, if any. In addition, the Contractor
understands and agrees that the provisions of 31 U.S.C. A 3801, et seq., apply to this certification and
disclosure, if any.
Name of Authorized Official
Title
Signature of Vendor/Contractor's Authorized Official
Date
Federal Aviation Administration (FAA)
Certification of Buy American Certification for Manufactured Products (1 of 2)
As a matter of bid responsiveness, the bidder or offeror must complete, sign, date, and submit
this certification statement with their proposal. The bidder or offeror must indicate how they
intend to comply with 49 USC § 50101 by selecting one on the following certification statements.
These statements are mutually exclusive. Bidder must select one or the other (not both) by
inserting a checkmark () or the letter “X”.
Bidder or offeror hereby certifies that it will comply with 49 USC § 50101 by:
a) Only installing steel and manufactured products produced in the United States, or;
b) Installing manufactured products for which the FAA has issued a waiver as
indicated by inclusion on the current FAA Nationwide Buy American Waivers
Issued listing, or;
c) Installing products listed as an Excepted Article, Material or Supply in Federal
Acquisition Regulation Subpart 25.108.
By selecting this certification statement, the bidder or offeror agrees:
1. To provide to the Owner evidence that documents the source and origin of the
steel and manufactured product.
2. To faithfully comply with providing US domestic product
3. To furnish US domestic product for any waiver request that the FAA rejects
4. To refrain from seeking a waiver request after establishment of the contract,
unless extenuating circumstances emerge that the FAA determines justified.
The bidder or offeror hereby certifies it cannot comply with the 100% Buy American
Preferences of 49 USC § 50101(a) but may qualify for either a Type 3 or Type 4 waiver
under 49 USC § 50101(b). By selecting this certification statement, the apparent bidder or
offeror with the apparent low bid agrees:
1. To the submit to the Owner within 15 calendar days of the bid opening, a formal
waiver request and required documentation that support the type of waiver being
requested.
2. That failure to submit the required documentation within the specified timeframe
is cause for a non-responsive determination may result in rejection of the
proposal.
3. To faithfully comply with providing US domestic products at or above the
approved US domestic content percentage as approved by the FAA.
4. To refrain from seeking a waiver request after establishment of the contract,
unless extenuating circumstances emerge that the FAA determines justified.
Federal Aviation Administration (FAA)
Certification of Buy American Certification for Manufactured Products (2 of 2)
Required Documentation
Type 3 Waiver - The cost of the item components and subcomponents produced in the United
States is more that 60% of the cost of all components and subcomponents of the “item”. The
required documentation for a type 3 waiver is:
a) Listing of all product components and subcomponents that are not comprised of
100% US domestic content (Excludes products listed on the FAA Nationwide Buy
American Waivers Issued listing and products excluded by Federal Acquisition
Regulation Subpart 25.108; products of unknown origin must be considered as non-
domestic products in their entirety).
b) Cost of non-domestic components and subcomponents, excluding labor costs
associated with final assembly at place of manufacture.
c) Percentage of non-domestic component and subcomponent cost as compared to total
“item” component and subcomponent costs, excluding labor costs associated with
final assembly at place of manufacture.
Type 4 Waiver – Total cost of project using US domestic source product exceeds the total
project cost using non-domestic product by 25%. The required documentation for a type 4 of
waiver is:
a) Detailed cost information for total project using US domestic product
b) Detailed cost information for total project using non-domestic product
False Statements: Per 49 USC § 47126, this certification concerns a matter within the
jurisdiction of the Federal Aviation Administration and the making of a false, fictitious or
fraudulent certification may render the maker subject to prosecution under Title 18, United States
Code.
Date Signature
Company Name Title
Acknowledgement of Terms, Conditions, and Grant Clauses
Flow Down of Terms and Conditions from the Grant Agreement
Subcontracts: If the vendor subcontracts any of the work required under this Agreement, a copy
of the signed subcontract must be available to the Department for review and approval. The
vendor agrees to include in the subcontract that (1) the subcontractor is bound by the terms of
this Agreement, (ii) the subcontractor is bound by all applicable state and federal laws and
regulations, and (iii) the subcontractor shall hold the Department and Recipient harmless against
all claims of whatever nature arising out of the subcontractor’s performance of work under this
Agreement, to the extent allowed and required by law. The recipient shall document in the
quarterly report the subcontractor’s progress in performing its work under this agreement.
For each subcontract, the Recipient shall provide a written statement to the Department as to
whether the subcontractor is a minority vendor as defined in Section 288.703, Fla. Stat.
Certification
On behalf of my firm, I acknowledge, and agree to perform all of the specifications and grant
requirements identified in this solicitation document(s).
Vendor/Contractor Name ______________________________
Date __________________
Authorized Signature ___________________________________________________________
Address _____________________________________________________________________
Solicitation/Contract # ____________________________
COLLIER COUNTY AIRPORT AUTHORITY
Disadvantaged Business Enterprise (DBE) Utilization
FORM 1
The undersigned bidder/offerer has satisfied the requirements of the bid specification in the
following manner (please check the appropriate space):
The bidder is committed to a minimum of % DBE utilization on this contract.
The bidder (if unable to meet the applicable DBE goal of 5.9% DBE goal for
Immokalee is committed to a minimum of % DBE utilization on this
contract and has submitted documentation demonstrating good faith efforts.
Name of bidder’s firm:
State Registration No.
By
(Signature)
Title
COLLIER COUNTY AIRPORT AUTHORITY
Disadvantaged Business Enterprise (DBE) Utilization
LETTER OF INTENT
FORM 2
(Submit this page for each DBE subcontractor.)
Name of bidder’s firm: _____
Address:
City: State: ____ Zip:
Name of DBE firm:
Address:
City: State: ____ Zip:
Telephone:
Description of work to be performed by DBE firm:
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
The bidder is committed to utilizing the above-named DBE firm for the work described
above. The estimated dollar value of this work is $ _.
Affirmation
The above-named DBE firm affirms that it will perform the portion of the contract for
the estimated dollar value as stated above.
By (Signature) (Title)
If the bidder does not receive award of the prime contract, any and all representations in
this
Letter of Intent and Affirmation shall be null and void.
COLLIER COUNTY AIRPORT AUTHORITY
Disadvantaged Business Enterprise (DBE) Ut ilization (M/WBE)
GOOD FAITH EFFORTS
FORM 3
Prior to an award, all bidders/proposers will be required to document a "Good Faith Effort" to
secure disadvantaged, minority/women-owned and/or businesses as subcontractors/sub-
consultants/suppliers. In the case of some construction projects, this documentation may be
submitted after award of the contract, for those subcontract areas occurring later in the
construction process.
Fulfillment of the "good faith effort" can be accomplished by:
1. Attendance of pre-bid/pre-proposal conference, as scheduled by the County.
2. Efforts to follow-up initial solicitation of interest by contacting
disadvantaged/minority/women-owned firms to determine with certainty whether these firms are
interested.
3. Efforts made to select portions of the work proposed to be performed by
disadvantaged/minority/women-owned firms in order to increase the likelihood of achieving
participation (including, where appropriate, breakdown of subcontracts into economically
feasible units to facilitate participation).
4. Documenting each disadvantaged/minority/woman-owned firm contacted the conclusion or
decision regarding inclusion and reasons for the conclusions.
5. Efforts to assist the disadvantaged/minority/women-owned firms contacted that needed
assistance in obtaining bonding, lines of credit or insurance.
6. Efforts that demonstrate that the contractor effectively used the services of available
community organizations, contractor's groups, local, state and federal agencies, small businesses,
disadvantaged/minority/women business assistance offices and other organizations that provide
assistance and placement of disadvantaged/minority/woman-owned businesses.
Company Name: _______________________________________________
Printed Name: _______________________________________________
Title: _______________________________________________
Signed: _______________________________________________
Date: _______________________________________________
COLLIER COUNTY AIRPORT AUTHORITY
Disadvantaged Business Enterprise (DBE) Ut ilization (M/WBE)
OPPORTUNITY LIST
FORM 4
Disadvantaged businesses and minority vendors, as defined in the Federal Code of Federal Regulations or Florida
State Statutes must have the opportunity to participate on contracts with federal and/or state grant assistance.
FIRM INFORMATION FIRM TYPE ANNUAL GROSS RECEIPTS
FEDERAL TAX ID # DBE (Disadvantaged) LESS THAN $1 MIILION
FIRM NAME MBE (Minority) BETWEEN $1 - $5 MIILION
PHONE WBE (Women) BETWEEN $5 - $10 MIILION
STREET ADDRESS NON-DBE BETWEEN $10 - $15 MIILION
CITY, STATE, ZIP MORE THAN $15 MIILION
YEAR FIRM EST.
FIRM INFORMATION FIRM TYPE ANNUAL GROSS RECEIPTS
FEDERAL TAX ID # DBE (Disadvantaged) LESS THAN $1 MIILION
FIRM NAME MBE (Minority) BETWEEN $1 - $5 MIILION
PHONE WBE (Women) BETWEEN $5 - $10 MIILION
STREET ADDRESS NON-DBE BETWEEN $10 - $15 MIILION
CITY, STATE, ZIP MORE THAN $15 MIILION
YEAR FIRM EST.
FIRM INFORMATION FIRM TYPE ANNUAL GROSS RECEIPTS
FEDERAL TAX ID # DBE (Disadvantaged) LESS THAN $1 MIILION
FIRM NAME MBE (Minority) BETWEEN $1 - $5 MIILION
PHONE WBE (Women) BETWEEN $5 - $10 MIILION
STREET ADDRESS NON-DBE BETWEEN $10 - $15 MIILION
CITY, STATE, ZIP MORE THAN $15 MIILION
YEAR FIRM EST.
FIRM INFORMATION FIRM TYPE ANNUAL GROSS RECEIPTS
FEDERAL TAX ID # DBE (Disadvantaged) LESS THAN $1 MIILION
FIRM NAME MBE (Minority) BETWEEN $1 - $5 MIILION
PHONE WBE (Women) BETWEEN $5 - $10 MIILION
STREET ADDRESS NON-DBE BETWEEN $10 - $15 MIILION
CITY, STATE, ZIP MORE THAN $15 MIILION
YEAR FIRM EST.
FIRM INFORMATION FIRM TYPE ANNUAL GROSS RECEIPTS
FEDERAL TAX ID # DBE (Disadvantaged) LESS THAN $1 MIILION
FIRM NAME MBE (Minority) BETWEEN $1 - $5 MIILION
PHONE WBE (Women) BETWEEN $5 - $10 MIILION
STREET ADDRESS NON-DBE BETWEEN $10 - $15 MIILION
CITY, STATE, ZIP MORE THAN $15 MIILION
YEAR FIRM EST.
FIRM INFORMATION FIRM TYPE ANNUAL GROSS RECEIPTS
FEDERAL TAX ID # DBE (Disadvantaged) LESS THAN $1 MIILION
FIRM NAME MBE (Minority) BETWEEN $1 - $5 MIILION
PHONE WBE (Women) BETWEEN $5 - $10 MIILION
STREET ADDRESS NON-DBE BETWEEN $10 - $15 MIILION
CITY, STATE, ZIP MORE THAN $15 MIILION
YEAR FIRM EST.
Prime Contractor/Consultant
Address / Phone Number
Procurement Number
SPECIAL PROVISIONS
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
SP-1 - CONSTRUCTION SAFETY AND PHASING PLAN SP 1-1
NON-FAA ITEM
SPECIAL PROVISION NO. 1
CONSTRUCTION SAFETY AND PHASING PLANS
1. See Construction Safety and Phasing Plan (CSPP) document enclosed in Exhibit L, Standard Details of the
Contract Documents.
END OF SPECIAL PROVISION NO. 1
IMMOKALEE REGIONAL AIRPORT
APRIL 10, 2017 SUBMITTAL REHABILITATION OF TAXIWAY B
SP 1-2 SP-1 - CONSTRUCTION SAFETY AND PHASING PLAN
NON-FAA ITEM
Intentionally Left Blank