Agenda 02/28/2017 Item #16C 202/28/2017
EXECUTIVE SUMMARY
Recommendation to approve a $502,324 purchase order for Stantec Consulting Services, Inc.,
under Contract Number 14-6345 for Construction, Engineering, and Inspection Services for the
107th Avenue North Public Utility Renewal Project, Project Nos. 60139 and 70120. (This is a
companion to Agenda Item 11.E)
OBJECTIVE: To obtain professional Construction, Engineering, and Inspection (CEI) services during
construction of the Basin 101 integrated water, wastewater and stormwater project spe cific to 107th
Avenue North. A companion executive summary is requesting Board of County Commissioners (Board)
approval for the construction contract for the project.
CONSIDERATIONS: The proposed scope of work under Project Number 60139, “Naples Park
Stormwater Improvements,” is consistent with the Stormwater Five-year Work Program of the 2015
Stormwater Management AUIR/CIE approved by the Board of County Commissioners (Board) on
November 10, 2015, and with the goals, objectives and policies of the Cons ervation and Coastal
Management Element and the Stormwater Management Sub-Element of the Growth Management Plan.
The proposed scope of work under Project Number 70120, “Naples Park Area Basin Optimization” is
consistent with the Capital Improvement Program (CIP) contained in the 2014 Water, Wastewater,
Irrigation Quality Water, and Bulk Potable Water Master Plan/CIP Plan also approved by the Board on
November 10, 2015, as Agenda Item 9C, as Appendix III of the 2015 AUIR/CIE.
On July 7, 2015, as Agenda Item 16C6, the Board awarded Contract No. 14-6345 for CEI Services for the
Basin 101 Program to Stantec Consultant Services, Inc. The contract encompassed CEI services
pertaining to substantially similar integrated wastewater collections, water distribution, and stormwater
system construction projects within Basin 101. This project, 107th Avenue North Public Utility Renewal,
is within Basin 101.
On December 5, 2016, Stantec Consulting Services, Inc., provided a time and materials proposal for
$502,324 to provide CEI services during construction of the 107th Avenue North Public Utility Renewal
Project (Attachment 1). The scope of services proposal includes construction observation and
documentation services, general management and oversight, and public outreach services. The cost of
CEI-related services is 13 percent of the project construction cost. The project scope includes replacing
and rehabilitating water, wastewater and stormwater assets in one coordinated project designed to
minimize cost and neighborhood impact as opposed to multiple separate mobilizations.
Staff shall not issue a notice to proceed for these CEI services unless the Board awards Bid Number 16 -
7020 (the construction contract) as contained in the regular agenda companion item 2691.
FISCAL IMPACT: Funding is available in the Stormwater Capital Fund (325), Water User Fee Fund
(412) and Wastewater User Fee Fund (414), allocated as shown below. The companion to this item
provides the necessary budget amendment.
FUNDING SOURCE AMOUNT BID %
Stormwater Capital Fund (325) $150,697.20 30%
Water Capital Fund (412) $150,697.20 30%
Wastewater Capital Fund (414) $200,929.60 40%
Total $502,324.00 100%
LEGAL CONSIDERATIONS: This item is approved as to form and legality, and requires majority
16.C.2
Packet Pg. 735
02/28/2017
vote for Board approval.-SRT
GROWTH MANAGEMENT IMPACT: This project meets current Growth Management Plan
standards to ensure the adequacy and availability of viable public facilities.
RECOMMENDATION: That the Board of County Commissioners, Ex-officio the Governing Board of
the Collier County Water-Sewer District, approves a $502,324.00 purchase order for Stantec Consulting
Services, Inc., under Contract Number 14-6345 for CEI services for the 107th Avenue North Public Utility
Renewal Project, with direction that staff shall not issue a notice to proceed for these CEI services unless
the Board awards Bid Number 16-7020 (the construction contract) as contained in the regular agenda
companion item 2691.
Prepared By: Diana Dueri, PMP, Project Manager, Public Utilities Planning and Project Management
Division
ATTACHMENT(S)
1. Attachment 1 - Stantec Proposal (PDF)
16.C.2
Packet Pg. 736
02/28/2017
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.C.2
Doc ID: 2692
Item Summary: Recommendation to approve a $502,324 purchase order to Stantec Consulting
Services, Inc., under Contract Number 14-6345 for Construction, Engineering, and Inspection Services
for the 107th Avenue North Public Utility Renewal Project, Project Nos. 60139 and 70120. (This is a
companion to Agenda Item 11.E)
Meeting Date: 02/28/2017
Prepared by:
Title: Project Manager – Public Utilities Planning and Project Management
Name: Diana Dueri
02/02/2017 6:46 PM
Submitted by:
Title: Division Director - Public Utilities Eng – Public Utilities Planning and Project Management
Name: Tom Chmelik
02/02/2017 6:46 PM
Approved By:
Review:
Water Steve Messner Additional Reviewer Completed 02/03/2017 8:58 AM
Public Utilities Department Margie Hapke Additional Reviewer Completed 02/03/2017 11:05 AM
Public Utilities Planning and Project Management Tom Chmelik Additional Reviewer Completed 02/03/2017 11:37 AM
Public Utilities Operations Support Joseph Bellone Additional Reviewer Completed 02/06/2017 11:55 AM
Growth Management Department Lisa Taylor Additional Reviewer Completed 02/06/2017 12:53 PM
Wastewater Beth Johnssen Additional Reviewer Completed 02/06/2017 3:12 PM
Capital Project Planning, Impact Fees, and Program Management Gerald Kurtz Additional Reviewer Completed 02/06/2017 4:16 PM
Procurement Services Lissett DeLaRosa Level 1 Purchasing Gatekeeper Completed 02/06/2017 4:24 PM
Procurement Services Swainson Hall Additional Reviewer Completed 02/07/2017 10:40 AM
Public Utilities Department Heather Bustos Level 1 Division Reviewer Completed 02/07/2017 1:38 PM
Procurement Services Allison Kearns Additional Reviewer Completed 02/07/2017 1:43 PM
Procurement Services Brenda Brilhart Additional Reviewer Completed 02/07/2017 2:27 PM
Procurement Services Ted Coyman Additional Reviewer Completed 02/07/2017 5:34 PM
Capital Project Planning, Impact Fees, and Program Management Amy Patterson Additional Reviewer Completed 02/08/2017 4:22 PM
Growth Management Department Jeanne Marcella Additional Reviewer Completed 02/09/2017 10:16 AM
Public Utilities Department George Yilmaz Level 2 Division Administrator Review Completed 02/10/2017 12:24 PM
16.C.2
Packet Pg. 737
02/28/2017
County Attorney's Office Scott Teach Level 2 Attorney Review Completed 02/13/2017 4:01 PM
Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 02/14/2017 10:34 AM
County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 02/15/2017 10:08 AM
Office of Management and Budget Susan Usher Additional Reviewer Completed 02/18/2017 3:42 PM
County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 02/19/2017 11:04 AM
Board of County Commissioners MaryJo Brock Meeting Pending 02/28/2017 9:00 AM
16.C.2
Packet Pg. 738
16.C.2.a
Packet Pg. 739 Attachment: Attachment 1 - Stantec Proposal (2692 : Construction, Engineering, and Inspection Services for 107th Avenue North Public
1
asdsadasdwd
Design with community in mind
SCHEDULE A – SCOPE OF SERVICES
Collier County Contract 14-6345
Construction Engineering & Inspection (CEI) Services
Work Authorization ____
107th Avenue North Public Utility Renewal
1.0 BACKGROUND
Collier County Public Utilities Department Planning and Project Management Division (PPMD) is
implementing a series of utility improvement projects within Wastewater Basin 101, known as the
Naples Park area, in an effort to optimize existing wastewater infrastructure and maximize
wastewater treatment and conveyance system capacity. Naples Park is predominantly a
residential community located west of Tamiami Trail North to the Gulf of Mexico and between
Vanderbilt Beach Road and 111th Ave. North. This system ultimately conveys wastewater to the
County’s North Water Reclamation Facility (NCWRF) located on Goodlette- Frank Road south of
the intersection with Immokalee Road.
1.1 107th AVENUE NORTH – PUBLIC UTILITY RENEWAL PROJECT
PPMD retained CDM Smith and Q Grady Minor & Associates as the Engineers of Record (EORs) to
renew or replace the existing pump stations, force mains, water mains, and gravity sanitary sewers
within Naples Park to revitalize the wastewater basin and implement improvements to meet
PPMD’s standard level of service. PPMD has selected Stantec Consulting Services Inc. (Stantec) to
provide construction and engineering and inspection services throughout the duration of the
preconstruction, construction, and commissioning of the overall Naples Park Basin 101 Program
Improvements.
The 107th Avenue North Public Utility Renewal project includes the repair and replacement of
water, wastewater, and stormwater systems along 107th Avenue between 8th Street North and
Vanderbilt Drive (see attached map). As part of the improvements, the Contractor may need to
replace water and sewer service lines. Each clay sewer pipe lateral from the property will be
replaced with new PVC pipe. The service line work may need to take place on private property,
and permission from the owner will be necessary. Stormwater collection and treatment system
rehabilitation work will take place in the right-of-way.
2.0 PURPOSE
Collier County requires certain professional services during the services for construction water,
wastewater and stormwater improvements on 107th Avenue. Stantec’s CEI services will observe
and document progress of the work, as well as assess whether the work is in general conformance
with the Contract Documents.
16.C.2.a
Packet Pg. 740 Attachment: Attachment 1 - Stantec Proposal (2692 : Construction, Engineering, and Inspection Services for 107th Avenue North Public
2
asdsadasdwd
Design with community in mind
3.0 SCOPE OF SERVICES
The tasks for this project are presented below and include the following:
Task 1.0 – Construction Observation and Documentation
Task 2.0 – CEI Construction and Project Oversight
Task 3.0 – Public Involvement
TASK 1.0 CONSTRUCTION INSPECTION AND OBSERVATION
Services to be provided as part of this task will include the following:
1.1 Construction/Testing Observation – Stantec will conduct on-site observations and
inspections of construction/testing activities on the Project on a full time basis, unless directed
otherwise by the County’s Project Manager, to assess whether work is completed in general
conformance with the Contract Documents. Stantec will notify the Contractor of any issues
related to conformance of the work with the Contract Documents and document these
notifications on the Daily Work Report (DWR). All Stantec field personnel will communicate directly
with Collier County Project Manager as necessary. Stantec will provide interpretation of plans and
specifications and assist the Contractor in developing solutions to field issues/conflicts at the
project level. If the issue/conflict cannot be resolved at the project level, Stantec will submit a
Request for Information (RFI) to the Design Engineer/Engineer of Record (EOR) within one business
day and provide a copy to the County’s Project Manager. The EOR will review the issue and
provide a written response to Stantec so that written direction can be given to the Contractor.
Stantec will maintain an RFI log to track the final disposition of all issues/ conflicts and keep the
County’s Project Manager updated as the project progresses.
1.2 DWR and Construction Documentation – Stantec will prepare a Daily Work Report (DWR)
with pictures recording activities and details related to the work on a form approved in advance
by the County’s Project Manager. Information will be recorded in the DWR when at the Project
Site. The DWR will record relevant aspects of the construction observed while on site including,
but not limited to: construction crew (labor) details, equipment used, materials used, compliance
testing and inspection performed, site conditions, trench conditions, backfill material used,
dewatering methods, compaction methods, location of the work, and other details related to the
Work. The DWR will reference the digital photographs and/or video taken with appropriate
caption summarizing subject matter and location. In addition to the construction details, the DWR
will contain information related to: time and hours on the job site, weather conditions, data
pertaining to questions of quantities of materials used, extras or deductions, list of visiting officials
and representatives of manufacturers, fabricators, suppliers and distributors, observations in
general and specific observations in more detail as in observing test procedures, conformance
inspection of materials and fittings, name plate data for equipment and material installed,
customer service field log, and other information requested by the County’s Project Manager.
DWRs will be provided to the County’s Project Manager by Stantec on a daily basis in an electronic
file via E-mail, on a digital CD, if requested by the County’s Project Manager, and a printed copy
to be maintained on the project site in the inspector’s trailer. All daily reports will be prepared in
the field. All other construction documentation produced by Stantec will be provided upon
request.
1.3 Photographic and Video Record – Stantec will provide a digital photographic record of
construction activities related to the Project in the DWR along with a brief description of the
photograph, and the date and time of the photograph. A photograph log and photographic
record will be provided to the County at the end of the project’s construction phase.
16.C.2.a
Packet Pg. 741 Attachment: Attachment 1 - Stantec Proposal (2692 : Construction, Engineering, and Inspection Services for 107th Avenue North Public
3
asdsadasdwd
Design with community in mind
1.4 General Coordination – Stantec will coordinate information related to the Project between
the construction Contractor, the EOR and the County’s Project Manager. Stantec will oversee
substantial and final completion inspections, and prepare and maintain the punch list, including
follow-up inspections to confirm whether punch list items are corrected and/or completed.
Stantec will coordinate with the County Utilities Department for testing and construction of
required connections to existing facilities. Stantec will communicate, as directed by the County’s
Project Manager, with community members, business owners, and the general public through the
Public Information Manager (PIM).
1.5 Construction Progress Meetings – Stantec will conduct bi-weekly progress meetings to
review project status and identify issues that may affect the Project. Stantec will prepare a DRAFT
Agenda at least two (2) business days in advance of the meeting and produce meeting minutes
within two (2) days after the meeting for distribution to the County’s Project Manager, EOR, and
the construction Contractor.
1.6 Substantial Completion Inspections – Stantec will conduct Substantial Completion
inspections when requested by the construction Contractor and the EOR recommends that the
work is sufficiently complete to warrant a Substantial Completion inspection. During the
Substantial Completion inspection, Stantec will prepare a punch list of items requiring completion
or correction to the satisfaction of the EOR and the County’s Project Manager. Stantec will be
responsible for maintaining the punch-list and issuing updates to the punch-list on a weekly basis.
Stantec will coordinate and participate in the final walk-through to confirm whether the punch-
list items are completed to the satisfaction of the EOR and the County’s Project Manager. All
services related to the Substantial Completion Inspection will be provided in writing and pictures
provided to the County’s Project Manager.
1.7 Final Completion Inspection - Upon the request of the construction Contractor and
concurrence of the EOR and the County’s Project Manager, Stantec will conduct Final
Completion inspections of portions of the project, as they are finished, to determine if construction
has been completed in conformance with the Contract Documents and the construction
Contractor has fulfilled all obligations therein. Based on the results of the Final Completion
inspection, the EOR, County’s Project Manager, and Stantec will judge the work complete or not
complete. If the work is judged complete, Stantec will issue a “notice of final acceptance and
recommendation for final payment”. If the work is judged not complete, Stantec will issue written
notification to the construction Contractor identifying the work judged not complete. Upon
provision of the construction Contractor’s evidence or assurance that the deficiencies noted
above have been corrected or completed, a second Final Completion inspection will be
scheduled to verify that the outstanding issues have been resolved and Stantec can issue a
“notice of final acceptance and recommendation for final payment”. All services related to the
Final Completion Inspection will be provided to the Project Manager.
1.8 Final Construction Certification – Upon issuance of a “notice of final acceptance and
recommendation for final payment” Stantec will provide the County’s Project Manager a signed
and sealed certification by a professional engineer stating that the “Project has been completed
by the construction Contractor in reasonable conformance to the Contract Documents, and as
amended by the Engineer of Record”.
16.C.2.a
Packet Pg. 742 Attachment: Attachment 1 - Stantec Proposal (2692 : Construction, Engineering, and Inspection Services for 107th Avenue North Public
4
asdsadasdwd
Design with community in mind
TASK 2.0 CONSTRUCTION ADMINISTRATION
Services to be provided for this task will include the following:
2.1 General Management and Oversight – Stantec will provide support services customarily
related to the construction observation and inspection of similar projects including, but not limited
to the following:
a. Participate in a pre-construction meeting with the County’s Project Manager, EOR, the
construction Contractor, and all other interested parties.
b. Participate in other meetings as described or implied herein.
c. Review and verify correctness of the construction Contractor’s monthly applications
for payment and accompanying data and recommend approval of payments due
and payable to the construction Contractor. Stantec’s recommendation of any
payment requested in an application for payment will constitute a representation by
Stantec to the County’s Project Manager as an experienced and qualified
professional, that based on Stantec’s onsite observations and inspections of
construction in progress, that the quantities of work completed in the applications for
payment accurately reflect the progress of the work completed in conformance with
the Contract Documents. Stantec will process pay requests in accordance with the
Florida Prompt Payment Act. All incoming pay requests processed by the Stantec will
be mechanically stamped with the date received.
d. Stantec will review the monthly updates to the construction schedule prepared by
the construction Contractor and provide written comments to the County’s Project
Manager and EOR.
e. Stantec will oversee such field testing and provide an opinion whether materials,
equipment and supplies installed or utilized on the Project are in conformance with
the Contract Documents and Shop Drawings approved by the EOR.
f. Stantec will have access to, collate, file, and distribute required Project records,
including but not limited to construction Contractor’s progress schedules, DWRs, and
testing reports.
2.2 Coordination of Shop Drawings, Contract Interpretations, and Clarifications – Stantec will
coordinate with the design engineer (EOR) regarding the issuance of interpretations and
clarifications of Contract Documents during construction. The EOR will be responsible for technical
review and decisions regarding interpretation and clarification of Contract Documents. Stantec
will communicate the EOR’s decisions and responses with the construction Contractor.
2.3 Change Orders – Upon identification of an unforeseen condition or additional work,
Stantec will analyze the extent of the change and compare it to the proposed change order cost
submitted by the construction Contractor. If necessary, Stantec will negotiate the cost of the
Change Order, and assist the County in issuing a Work Directive and subsequent Change Order.
2.4 As Constructed Field Drawings – Stantec will maintain red pencil “mark-up” notations and
sketches on full size construction plans that reflect the actual details of constructed facilities. These
As Constructed Field Drawings will be used by Stantec to validate the “As Built” documentation
provided by the construction Contractor.
2.5 Start-up and Re-commissioning Support – Stantec will assist the County’s Project Manager,
the EOR, and the construction Contractor during start-up of each segment, as designated for
Beneficial Use by the EOR, and provide general coordination during these activities.
16.C.2.a
Packet Pg. 743 Attachment: Attachment 1 - Stantec Proposal (2692 : Construction, Engineering, and Inspection Services for 107th Avenue North Public
5
asdsadasdwd
Design with community in mind
TASK 3.0 PUBLIC INVOLVEMENT
Collier County has emphasized that communicating project initiatives, plans, and progress with
community members is a high priority during the completion of the Basin projects. For Naples Park
projects, Stantec will provide a full time information team that will consist of a Public Information
Manager (PIM), a Public Information Officer (PIO) and a Public Information Assistant (PIA) to
support to the County with the following:
3.1 Public Outreach Plan - Work with the County to develop the vision of the project which
includes identifying why the project is needed, what work will be done, how the project will benefit
customers, how the project fit into the community, and how the project fit into the broader County
initiative plans. The vision, once defined will be provided to the public through various methods
throughout the duration of this project.
Develop a plan to educate, engage, and inform residents, business owners, local and seasonal
visitors and, in general, the impacted community; to continue to build community trust, and to
provide a solid messaging process to in-house departments and the media. This will include
Grassroots communication efforts paired with the use of technology including social media, e-
newsletters, etc. The plan will be prepared to assist the team with review, assess input, and will be
updated quarterly.
3.2 24 Hour Project Hot Line – The PIM or PIO will be accessible five days a week for activities
associated with public information. Project representatives will receive community member
complaints or concerns and will provide responses within a 24-hour period to prevent interruptions
of Public Utility Department staff. The PIM will also be capable of communicating about the
project vision, progress, goals, and objectives, as well as the specifics of day to day activities. A
single number will be provided for this service and will be active 24 hours. All calls will be
documented and databased. Periodic reports will be provided to the Stantec team.
3.3 Coordination with Collier County Communications & Customer Relations Department –
The PIM will work in partnership (seamlessly) to serve the community. Our Public Outreach
professional will provide Mike Sheffield with accurate, timely, and useful information. Our
approach mirrors that of the County and use a multi-media approach already in place to include
access television, printed publications, and media releases.
3.4 Report Information –The PIM or PIO will compile information to be included in regularly
scheduled reports to provide quality feedback, reporting and materials to Collier County
Government staff members such as County Manager.
3.5 Outreach and Meetings
3.5.1 Project Specific Community Outreach - Participate in community meetings before
and after the project bid, as well as during construction progress of each project.
Professional Communications Services during construction will be proactive to assist with
minimizing disturbances and restoration efforts to residents, as well as to all project
stakeholders
3.5.2 Project Progress – The PIM will provide ongoing messages to keep public and other
stakeholders informed about the project including project schedule, traffic impacts, major
milestones, etc.
16.C.2.a
Packet Pg. 744 Attachment: Attachment 1 - Stantec Proposal (2692 : Construction, Engineering, and Inspection Services for 107th Avenue North Public
6
asdsadasdwd
Design with community in mind
3.5.3 Additional Outreach Efforts– These include the services listed below:
a. Coordinate with community members and Contractor during construction to
sequence construction as necessary to provide community members continuous,
reasonable access to their property during construction.
b. Provide coping information to residents and business that may have inconveniences
caused by the project. This could include details regarding access, services, etc. and
can be in the form of formal and informal communications as necessary.
c. Provide community members with advanced notice of scheduled service outages.
d. Coordinate use of variable message boards (VMBs) to inform community members of
when and where work activities will be occurring.
e. Coordinate with Naples Park HOA.
f. Develop informational material to provide to the community and stakeholders as
directed by the County. Informational materials may include narratives identifying why
the project is needed, what work will be done, how the project will benefit customers,
how the project fits into the community, and how the project fits into the broader
County initiative plans. Once defined, the materials will be provided to the public
through various methods including letters, e-mails, special printings such as door
hangers, and other forms of formal and informal communication, throughout the
duration of this project, as directed by Collier County. The cost for all reimbursable
materials will be invoiced to the project with supporting back-up information.
3.6 Graphic Design for Publications - Stantec will provide a graphic designer to assist the
County and project staff in developing graphic content for the website, publications, and
materials to be utilized to provide information to the public and project personnel.
4.0 FEE
All work will be charged on a Time & Material basis in accordance with the Project Budget Form.
Many facets that control the length of the project and necessary effort are outside the control of
Stantec. Hours shown in this work assignment are only estimates. Any additional work that may
be required, will be performed under a separate Work Assignment, or as an amendment to this
one.
Task
Estimated
Fee Fee Type
Task 1 – Construction Inspection and Observation $264,520 T&M
Task 2 – Construction Administration $149,029 T&M
Task 3 – Public Involvement $88,775 T&M
Total Fee $502,324 T&M
16.C.2.a
Packet Pg. 745 Attachment: Attachment 1 - Stantec Proposal (2692 : Construction, Engineering, and Inspection Services for 107th Avenue North Public
7
asdsadasdwd
Design with community in mind
5.0 SCHEDULE
Stantec will provide services throughout the duration of the project as directed by the County in
accordance with the Project Schedule as defined by Contract #14-6345 “Construction
Engineering and Inspection (CEI) Services for the Wastewater Basin Programs (MPS 101 Basin)” and
its amendments.
16.C.2.a
Packet Pg. 746 Attachment: Attachment 1 - Stantec Proposal (2692 : Construction, Engineering, and Inspection Services for 107th Avenue North Public
Sr. Project
Manager
(QA/QC)
Senior
Inspector
Engineer
Intern
Clerical /
Administrative PI Assistant PI Officer PI Manager Total Labor Survey Total
Task 1 - Construction Inspection & Observation 100 2132 220 $264,520.00 $264,520.00
Task 2 - Construction Administration 472 645 210 $149,029.00 $149,029.00
Task 3 - Public Involvement 215 220 220 220 $88,775.00 $88,775.00
TOTAL HOURS 572 2132 645 645 220 220 220
HOURLY RATE $157.00 $110.00 $95.00 $65.00 $105.00 $115.00 $120.00
DIRECT LABOR COST $89,804.00 $234,520.00 $61,275.00 $41,925.00 $23,100.00 $25,300.00 $26,400.00
Construction Cost 3,837,675.00$
Proposal Percentage 13.09%
WBS#
Construction engineering & Inspection Services for 107th Avenue North Public Utility Renewal
Wastewater Basin Program
Collier County Contract 14-6345
$502,324.00
Task
$0.00
Project Personnel (Hrs)
$502,324.00
16.C.2.a
Packet Pg. 747 Attachment: Attachment 1 - Stantec Proposal (2692 : Construction, Engineering, and Inspection Services
!
!
!
!!
!
!
!
!!
!
!
!
!
!
!
!!
!
!
!!
!
!
!
!!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!!
107th AVE N
7th ST8th ST778B 782B
741 723 7012 721
798 742
786 730 706 704
733
774
777
722 754
785
770 790
737
766
717 781
782A738
725
750 758
769
718
789 703
749
7011
778A
799
714 726
729 773
734
746
762
713 757
745
702 794
CCPA, Stantec
Stantec Consulting Services Inc.6900 Professional Parkway EastSarasota, FL 34240tel 941.907.6900fax 941.907.6911
107TH AVE NORTHADJACENT PARCEL LOCATION MAPJune 2016\\US1226-F01\V:\1773\active\177310803\gis\mxd\N107thAve_20160630_v03_106492.mxd Revised: 2016-06-30 By: esturmDisclaimer: Stantec assumes no responsibility for datasupplied in electro nic format. The recipient acceptsfull responsibility for verifying the accuracy andcompleteness of the data. The recipient releases Stantec, its officers, employees, consultants andagents, from any and all claims arising in any wayfrom the content o r provision of the data.Prepared by:E.E.S. 06/30/16
Notes:1. Coordinate System: NAD 1983 StatePlane Florida East FIPS 0901 Feet2. Source data: COLLIER COUNTY GIS3. Imagery: CCPA 2016
!
!
!
!!
!!
!!
!
!
!
!
!
!!
!
!
!
!
!
!
!
!
!
!
!
!!
!
!!!!
!
!!
!
!
!
!
!
!
!
!!
!
107th AVE N
Vanderbilt DR6th ST560
547515 589563
544 572
535 583
556
531
528524 548
591523511
514
551
580
559
596
508A
592
10720
588568
571527
520
539519 575 10701
526
567543
522 564 576
555
510A
587
530
510B510C
508B
CCPA, Stantec
!
!
!!
!
!
!
!
!
!
!!
!!
!
!
!
!
!
!
!
!
!
!
!
!
!!!
!
!!!!!!
!
!!
!
!!!!
!
!
!
106th AVE N
107th AVE N
108th AVE N
6th ST7th ST665
670
669 681
668
677 689
658
690
657
678 698674662
673 685
682
661
694
697B693
10680
621
610
653
634 646 658642606
657601645649613617
614 650626618
629 635609A609B
630622
625
CCPA, Stantec
0 60 120Feet
($$¯0 60 120Feet
0 60 120Feet ($$¯
($$¯
16.C.2.a
Packet Pg. 748 Attachment: Attachment 1 - Stantec Proposal (2692 : Construction, Engineering, and Inspection Services for 107th Avenue North Public Utilities Renewal)