Agenda 02/28/2017 Item #16A1202/28/2017 EXECUTIVE SUMMARY Recommendation to award Bid #16-6572R to Quality Enterprises USA, Inc., for construction of the “Golden Gate Parkway at Livingston Road Intersection Improvements” project in the amount of $289,129.70, Project 33431, authorize the Chairman to execute the contract, and authorize the necessary budget amendments. OBJECTIVE: To provide intersection improvements at the Golden Gate Parkway and Livingston Road intersection. CONSIDERATION: On September 8, 2015, Item 16A36, the Board of County Commissioners (Board) approved a Local Agency Program (LAP) Agreement with the Florida Department of Transportation (FDOT) for intersection improvements on Golden Gate Parkway at Livingston Road. This agreement set aside funding to be reimbursable up to the amount of $272,184 for construction and $59,179 for construction engineering inspection (CEI) of this project. On October 21, 2016, the Procurement Services Division sent 5,363 (five thousand, three hundred sixty three) notices to vendors for Bid #16-6572R for the construction of intersection improvements on Golden Gate Parkway at Livingston Road. This project includes extension of both the eastbound and westbound right turn lanes. On November 21, 2016, 7 (seven) bids were received and opened. The qualified and responsive bid results are as follows: Contractor Bid 1 Quality Enterprises USA, Inc. $289,129.70 2 Haskins, Inc. $303,510.35 3 Southern Striping Solutions, LLC $317,472.10 4 Preferred Materials, Inc. $381,958.51 5 Coastal Site Development, LLC $382,025.60 6 Ajax Paving Industries of Florida, LLC $392,769.60 7 Community Asphalt Corp. $414,498.00 Staff reviewed the unit pricing on the bid tab, and Quality Enterprises USA, Inc., was the lowest, qualified and responsive bidder with a bid of $289,129.70. The Design Engineer’s opinion of probable cost for the project was $306,315.69. The Quality Enterprises USA, Inc., bid is 5.9% lower than the Engineer’s estimate. The Design Engineer recommend the award of the bid to Quality Enterprises USA, Inc., (see attached letter). FISCAL IMPACT: The anticipated cost for this intersection improvements project is $289,129.70. Funding from the Federal Highway Administration passed through FDOT in the amount of $272,184 and is available within Growth Management Grant Fund 711, Project 33431. Budget amendments are required to appropriate local funds in the amount of $16,945.70 within Growth Management Capital Fund 313, Project 33431 for the remainder of the cost. The estimated useful life of roadway improvements is 15 years, with minimal to no repair cost during that duration of time. GROWTH MANAGEMENT IMPACT: This project is consistent with the Transportation Element of 16.A.12 Packet Pg. 690 02/28/2017 the Growth Management Plan. LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for approval. - CMG RECOMMENDATION: To award Bid #16-6572R, “Golden Gate Parkway at Livingston Road Intersection Improvements” to Quality Enterprises USA, Inc. in the amount of $289,129.70, authorize the Chairman to execute the attached contract, and authorize all budget amendments necessary to recognize and appropriate funds for the project. Prepared by: Daniel G. Hall, P.E., Principal Project Manager, Transportation Engineering Di vision ATTACHMENT(S) 1. Bid Tabulation #16-6572R (PDF) 2. Bid Tabulation with Analysis (PDF) 3. Bid Analysis (DOCX) 4. [linked]16-6572R Contract (PDF) 5. 16-6572R NORA (PDF) 16.A.12 Packet Pg. 691 02/28/2017 COLLIER COUNTY Board of County Commissioners Item Number: 16.A.12 Doc ID: 2503 Item Summary: Recommendation to award Bid #16-6572R to Quality Enterprises USA, Inc., for construction of the “Golden Gate Parkway at Livingston Road Intersection Improvements” project in the amount of $289,129.70, Project 33431, authorize the Chairman to execute the contract, and authorize the necessary budget amendments. Meeting Date: 02/28/2017 Prepared by: Title: Project Manager, Senior – Transportation Engineering Name: Daniel Hall 12/20/2016 1:04 PM Submitted by: Title: Division Director - Transportation Eng – Transportation Engineering Name: Jay Ahmad 12/20/2016 1:04 PM Approved By: Review: Growth Management Department Anthony Khawaja Additional Reviewer Completed 12/20/2016 1:40 PM Transportation Engineering Jay Ahmad Additional Reviewer Completed 12/20/2016 1:42 PM Capital Project Planning, Impact Fees, and Program Management Rookmin Nauth Additional Reviewer Completed 12/21/2016 8:39 AM Growth Management Department Diane Lynch Level 1 Division Reviewer Completed 01/12/2017 1:34 PM Growth Management Department Gene Shue Additional Reviewer Completed 01/13/2017 5:17 PM Procurement Services Allison Kearns Additional Reviewer Completed 01/17/2017 12:48 PM Growth Management Department Jeanne Marcella Level 2 Division Administrator Completed 01/17/2017 1:07 PM Procurement Services Lissett DeLaRosa Level 1 Purchasing Gatekeeper Completed 01/17/2017 1:56 PM Procurement Services Ted Coyman Additional Reviewer Completed 01/23/2017 8:40 AM Grants Kimberly Lingar Level 2 Grants Review Completed 02/15/2017 4:52 PM Procurement Services Brenda Brilhart Additional Reviewer Completed 02/16/2017 8:13 AM County Attorney's Office Colleen Greene Level 2 Attorney Review Completed 02/17/2017 8:53 AM Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 02/17/2017 10:12 AM County Attorney's Office Jeffrey A. Klatzkow Level 3 County Attorney's Office Review Completed 02/17/2017 10:47 AM Grants Therese Stanley Additional Reviewer Completed 02/17/2017 12:26 PM Office of Management and Budget Susan Usher Additional Reviewer Completed 02/21/2017 4:31 PM 16.A.12 Packet Pg. 692 02/28/2017 County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 02/21/2017 4:39 PM Board of County Commissioners MaryJo Brock Meeting Pending 02/28/2017 9:00 AM 16.A.12 Packet Pg. 693 PM: Dan Hall PS: Brenda Brilhart ITB 16- 6572R GOLDEN GATE PARKWAY AT LIVINGSTON ROAD INTERSECTION IMPROVEMENTS Notices: 5,363 Pkgs Picked Up: 75 Bids: 7 FDOT FM No. 433177-1-58-01 Collier County Project No. 66065 ITEM No.DESCRIPTION UNIT QTY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL 1 101-1 MOBILIZATION LS 1 $52,000.00 52,000.00$ $30,515.00 30,515.00$ $27,450.00 27,450.00$ $63,000.00 63,000.00$ $37,500.00 37,500.00$ $41,000.00 41,000.00$ $82,000.00 82,000.00$ 2 102-1 MAINTENANCE OF TRAFFIC LS 1 $3,300.00 3,300.00$ $23,000.00 23,000.00$ $32,200.00 32,200.00$ $36,400.00 36,400.00$ $17,500.00 17,500.00$ $68,500.00 68,500.00$ $72,100.00 72,100.00$ 3 110-1-1 STANDARD CLEARING & GRUBBING LS 1 $19,000.00 19,000.00$ $26,750.00 26,750.00$ $22,200.00 22,200.00$ $6,435.00 6,435.00$ $8,500.00 8,500.00$ $13,700.00 13,700.00$ $12,720.20 12,720.20$ 4 110-4 REMOVAL OF EXISTING CONCRETE PAVEMENT SY 164 $17.00 2,788.00$ $16.50 2,706.00$ $18.00 2,952.00$ $32.15 5,272.60$ $30.00 4,920.00$ $85.00 13,940.00$ $20.00 3,280.00$ 5 120-1 EXCAVATION CY 351 $32.00 11,232.00$ $21.60 7,581.60$ $18.00 6,318.00$ $32.15 11,284.65$ $25.00 8,775.00$ $40.00 14,040.00$ $31.50 11,056.50$ 6 120-6 EMBANKMENT CY 217 $35.00 7,595.00$ $35.00 7,595.00$ $38.00 8,246.00$ $25.75 5,587.75$ $50.00 10,850.00$ $50.00 10,850.00$ $42.40 9,200.80$ 7 121-70 FLOWABLE FILL CY 5 $280.00 1,400.00$ $300.00 1,500.00$ $375.00 1,875.00$ $154.35 771.75$ $850.00 4,250.00$ $400.00 2,000.00$ $303.00 1,515.00$ 8 285-715 OPTIONAL BASE GROUP, BASE GROUP 15 (9" THICK)SY 635 $65.00 41,275.00$ $35.00 22,225.00$ $31.00 19,685.00$ $80.55 51,149.25$ $45.00 28,575.00$ $110.00 69,850.00$ $89.60 56,896.00$ 9 327-70-1 MILLING EXISTING PAVEMENT (1" THICK)SY 538 $9.50 5,111.00$ $9.35 5,030.30$ $8.25 4,438.50$ $12.85 6,913.30$ $15.00 8,070.00$ $11.00 5,918.00$ $8.60 4,626.80$ 10 334-1-12 SUPERPAVE ASPH. CONC. (TRAFFIC B, 1" THICK, RESURFACING) TN 30 $180.00 5,400.00$ $435.00 13,050.00$ $355.00 10,650.00$ $309.50 9,285.00$ $800.00 24,000.00$ $300.00 9,000.00$ $395.00 11,850.00$ 11 334-1-12 SUPERPAVE ASPH. CONC. (TRAFFIC B, 3" THICK) TN 105 $169.00 17,745.00$ $176.00 18,480.00$ $220.00 23,100.00$ $367.55 38,592.75$ $800.00 84,000.00$ $220.00 23,100.00$ $162.00 17,010.00$ 12 425-1-361 INLET, CURB TYPE P-6 EA 1 $3,780.00 3,780.00$ $6,000.00 6,000.00$ $10,000.00 10,000.00$ $9,005.00 9,005.00$ $4,500.00 4,500.00$ $7,830.00 7,830.00$ $8,360.00 8,360.00$ 13 425-2-43 MANHOLE, P-7 PARTIAL (REMOVE INLET TOP)EA 1 $2,530.00 2,530.00$ $4,555.00 4,555.00$ $4,000.00 4,000.00$ $4,505.00 4,505.00$ $4,500.00 4,500.00$ $3,915.00 3,915.00$ $5,510.00 5,510.00$ 14 520-1-10 CONCRETE CURB & GUTTER TYPE F LF 659 $15.50 10,214.50$ $20.00 13,180.00$ $22.50 14,827.50$ $38.60 25,437.40$ $28.00 18,452.00$ $17.60 11,598.40$ $27.00 17,793.00$ 15 522-2 SIDEWALK (CONCRETE, 3,000 PSI, 6") (INCL. DRIVEWAYS)SY 402 $44.00 17,688.00$ $58.00 23,316.00$ $54.00 21,708.00$ $57.90 23,275.80$ $60.00 24,120.00$ $50.00 20,100.00$ $65.20 26,210.40$ 16 570-1-2 PERFORMANCE TURF (BAHIA)SY 742 $3.30 2,448.60$ $4.40 3,264.80$ $3.00 2,226.00$ $3.67 2,723.14$ $5.00 3,710.00$ $3.75 2,782.50$ $2.70 2,003.40$ 17 625-2-11 PULL & SPLICE BOX EA 5 $577.30 2,886.50$ $1,015.00 5,075.00$ $1,180.00 5,900.00$ $645.74 3,228.70$ $1,200.00 6,000.00$ $655.00 3,275.00$ $608.00 3,040.00$ 18 625-2-41 PULL & SPLICE BOX, RELOCATE EA 1 $508.30 508.30$ $1,015.00 1,015.00$ $1,150.00 1,150.00$ $568.56 568.56$ $1,200.00 1,200.00$ $575.00 575.00$ $536.00 536.00$ 19 630-2-11 CONDUIT, LIGHTING, 2' PVC, OPEN TRENCH LF 672 $7.00 4,704.00$ $15.40 10,348.80$ $18.00 12,096.00$ $7.85 5,275.20$ $10.50 7,056.00$ $8.00 5,376.00$ $7.40 4,972.80$ 20 630-2-12 CONDUIT, LIGHTING, 2' PVC, DIRECTIONAL BORE LF 119 $23.00 2,737.00$ $31.00 3,689.00$ $36.00 4,284.00$ $25.79 3,069.01$ $25.00 2,975.00$ $26.00 3,094.00$ $24.30 2,891.70$ 21 700-20-11 SIGN, SINGLE POST AS 2 $460.00 920.00$ $440.00 880.00$ $775.00 1,550.00$ $514.53 1,029.06$ $400.00 800.00$ $590.00 1,180.00$ $485.00 970.00$ 22 700-20-51 SIGN, SINGLE POST (RELOCATE)AS 2 $316.25 632.50$ $305.00 610.00$ $530.00 1,060.00$ $353.75 707.50$ $400.00 800.00$ $65.00 130.00$ $333.00 666.00$ 23 706-3 PAVEMENT MARKERS, RETRO-REFLECTIVE EA 64 $4.60 294.40$ $4.40 281.60$ $15.00 960.00$ $5.15 329.60$ $10.00 640.00$ $5.20 332.80$ $4.90 313.60$ 24 711-1 PAVEMENT MESSAGES (PAINT)EA 2 $115.00 230.00$ $110.00 220.00$ $120.00 240.00$ $128.63 257.26$ $100.00 200.00$ $130.50 261.00$ $121.00 242.00$ 25 711-11-121 TRAFFIC STRIPE, SOLID, THERMO. (6" WHITE)LF 1806 $1.15 2,076.90$ $1.10 1,986.60$ $1.70 3,070.20$ $1.29 2,329.74$ $3.00 5,418.00$ $1.30 2,347.80$ $1.20 2,167.20$ 26 711-11-123 TRAFFIC STRIPE, SOLID, THERMOPLASTIC (12" WHITE), (RESTRIPE)LF 125 $3.16 395.00$ $3.05 381.25$ $2.30 287.50$ $3.54 442.50$ $6.00 750.00$ $3.60 450.00$ $3.30 412.50$ 27 711-11-125 TRAFFIC STRIPE, SOLID, THERMOPLASTIC (24" WHITE) (RESTRIPE)LF 24 $6.35 152.40$ $6.10 146.40$ $3.50 84.00$ $7.08 169.92$ $12.00 288.00$ $7.20 172.80$ $6.70 160.80$ 28 711-11-127 DIRECTIONAL ARROW, THERMOPLASTIC EA 7 $69.00 483.00$ $66.00 462.00$ $120.00 840.00$ $77.18 540.26$ $150.00 1,050.00$ $78.30 548.10$ $72.70 508.90$ 29 711-17 REMOVE EXIST. PAVEMENT MARKINGS LS 1 $862.50 862.50$ $825.00 825.00$ $750.00 750.00$ $964.75 964.75$ $2,500.00 $980.00 980.00$ $909.00 909.00$ 30 715-1-11 LIGHTING CONDUCTORS (AWG10 MINIMUM)LF 600 $1.25 750.00$ $1.35 810.00$ $1.50 900.00$ $1.35 810.00$ $2.00 1,200.00$ $1.40 840.00$ $1.30 780.00$ 31 715-1-12 LIGHTING CONDUCTORS (AWG6 MINIMUM)LF 3228 $1.70 5,487.60$ $2.00 6,456.00$ $2.30 7,424.40$ $1.87 6,036.36$ $2.20 7,101.60$ $1.90 6,133.20$ $1.80 5,810.40$ 32 715-4-119 LIGHT POLE COMPLETE (INCL FOUNDATION, FUSE HOLDER & SURGE ARRESTER)EA 5 $6,842.50 34,212.50$ $9,020.00 45,100.00$ $10,500.00 52,500.00$ $7,653.68 38,268.40$ $8,750.00 43,750.00$ $8,000.00 40,000.00$ $7,210.00 36,050.00$ 33 715-46 LIGHT POLE COMPLETE (REMOVE & DISPOSE)EA 5 $701.50 3,507.50$ $605.00 3,025.00$ $700.00 3,500.00$ $784.66 3,923.30$ $915.00 4,575.00$ $800.00 4,000.00$ $739.00 3,695.00$ 34 737-70-1 UTILITY LOCATES, UNDERGROUND EA 10 $2,300.00 23,000.00$ $675.00 6,750.00$ $380.00 3,800.00$ $1,287.00 12,870.00$ $250.00 2,500.00$ $260.00 2,600.00$ $606.00 6,060.00$ 35 REC-DWGS PREPARE/SIGN & SEAL RECORD DRAWINGS LS 1 $1,782.50 1,782.50$ $6,700.00 6,700.00$ $5,200.00 5,200.00$ $1,500.00 1,500.00$ $3,500.00 3,500.00$ $2,350.00 2,350.00$ $2,180.00 2,180.00$ TOTAL BASE BID 289,129.70$ 303,510.35$ 317,472.10$ 381,958.51$ 382,025.60$ 392,769.60$ 414,498.00$ Bid Documents: -Material Manufacturers Y Y Y Y Y Y Y -Subcontractors Y Y Y Y Y Y Y -Statement of Experience Y Y Y Y Y Y Y -Trench Safety Act Y Y Y Y Y Y Y -Immigration Law Affidavit / MOU or Profile Page Y / Y Y / N Y / N Y / Y Y / Y Y / N Y / N -W-9 Y Y Y Y Y Y Y -Bid Bond Y Y Y Y Y Y Y Granting Agency Documents: - Acknowledgement of Terms, Conditions and Grant Clauses Y Y Y Y Y Y N -Certification Regarding Debarment, Suspension and Other Matters Y Y Y Y Y Y N -Certification Regarding Lobbying Y Y Y Y Y Y N -Anticipated Disadvantaged, Minority, Women or Veteran Participation Y Y Y Y Y Y N -Affidavit of Vehicle Registration Y Y Y Y Y Y N -Certification of Sublet Work Y Y Y Y Y Y N -Notification of EEO Officer Y Y Y Y Y Y N -Conflict of Interest Y Y Y Y Y Y N -Drug Free Workplace Y Y Y Y Y Y N -Certification of Current Capacity Y Y Y Y Y Y N -Contractor Certificate: Non-Collusion, Lobbying, Suspension and Debarment Provision Y Y Y Y Y Y N -Bid Opportunity List For Commodities and Contractual Services Y Y Y Y Y Y N -EEO/ AA Plan Y Y N Y Y Y Y Brenda Brilhart, Procurement Strategist 11/21/2016 Viviana Giarimoustas, Witness Collier Paving & Concrete dba Southern Striping Solutions, LLC Naples Ajax Paving Industries of Florida, LLC. North Venice Quality Enterprises USA, Inc. Naples Coastal Concrete Products, LLC dba Coastal Site Development Ft. Myers Community Asphalt Corp. Ft. Myers Haskins, Inc. Bonita Springs Preferred Materials, Inc. Tampa 16.A.12.a Packet Pg. 694 Attachment: Bid Tabulation #16-6572R (2503 : Award bid to Quality Enterprises USA, Inc for Golden Gate PM: Dan Hall PS: Brenda Brilhart ITB 16- 6572R GOLDEN GATE PARKWAY AT LIVINGSTON ROAD INTERSECTION IMPROVEMENTS Notices: 5,363 Pkgs Picked Up: 75 Bids: 7 FDOT FM No. 433177-1-58-01 Collier County Project No. 66065 Low Bid Low Bid ITEM No.DESCRIPTION UNIT QTY UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL Low Bid Engineer's Estimate Average % of Eng Est to Low Bid % of Avg to Low Bid Low Bid Engineer's Estimate DIFFERENCE 1 101-1 MOBILIZATION LS 1 $31,377.49 $31,377.49 $52,000.00 52,000.00$ $30,515.00 30,515.00$ $27,450.00 27,450.00$ $63,000.00 63,000.00$ $37,500.00 37,500.00$ $41,000.00 41,000.00$ $82,000.00 82,000.00$ $52,000.00 $31,377.49 47,637.86$ -39.66%51.82%52,000.00$ $31,377.49 $20,622.51 2 102-1 MAINTENANCE OF TRAFFIC LS 1 $62,754.97 $62,754.97 $3,300.00 3,300.00$ $23,000.00 23,000.00$ $32,200.00 32,200.00$ $36,400.00 36,400.00$ $17,500.00 17,500.00$ $68,500.00 68,500.00$ $72,100.00 72,100.00$ $3,300.00 $62,754.97 36,142.86$ 1801.67%-42.41%3,300.00$ $62,754.97 ($59,454.97) 3 110-1-1 STANDARD CLEARING & GRUBBING LS 1 $10,000.00 $10,000.00 $19,000.00 19,000.00$ $26,750.00 26,750.00$ $22,200.00 22,200.00$ $6,435.00 6,435.00$ $8,500.00 8,500.00$ $13,700.00 13,700.00$ $12,720.20 12,720.20$ $19,000.00 $10,000.00 15,615.03$ -47.37%56.15%19,000.00$ $10,000.00 $9,000.00 4 110-4 REMOVAL OF EXISTING CONCRETE PAVEMENT SY 164 $15.00 $2,463.33 $17.00 2,788.00$ $16.50 2,706.00$ $18.00 2,952.00$ $32.15 5,272.60$ $30.00 4,920.00$ $85.00 13,940.00$ $20.00 3,280.00$ $17.00 $15.00 31.24$ -11.76%108.27%2,788.00$ $2,463.33 $324.67 5 120-1 EXCAVATION CY 351 $25.00 $8,767.56 $32.00 11,232.00$ $21.60 7,581.60$ $18.00 6,318.00$ $32.15 11,284.65$ $25.00 8,775.00$ $40.00 14,040.00$ $31.50 11,056.50$ $32.00 $25.00 28.61$ -21.88%14.44%11,232.00$ $8,767.56 $2,464.44 6 120-6 EMBANKMENT CY 217 $30.00 $6,509.87 $35.00 7,595.00$ $35.00 7,595.00$ $38.00 8,246.00$ $25.75 5,587.75$ $50.00 10,850.00$ $50.00 10,850.00$ $42.40 9,200.80$ $35.00 $30.00 39.45$ -14.29%31.50%7,595.00$ $6,509.87 $1,085.13 7 121-70 FLOWABLE FILL CY 5 $200.00 $1,000.00 $280.00 1,400.00$ $300.00 1,500.00$ $375.00 1,875.00$ $154.35 771.75$ $850.00 4,250.00$ $400.00 2,000.00$ $303.00 1,515.00$ $280.00 $200.00 380.34$ -28.57%90.17%1,400.00$ $1,000.00 $400.00 8 285-715 OPTIONAL BASE GROUP, BASE GROUP 15 (9" THICK)SY 635 $25.00 $15,877.78 $65.00 41,275.00$ $35.00 22,225.00$ $31.00 19,685.00$ $80.55 51,149.25$ $45.00 28,575.00$ $110.00 69,850.00$ $89.60 56,896.00$ $65.00 $25.00 65.16$ -61.54%160.64%41,275.00$ $15,877.78 $25,397.22 9 327-70-1 MILLING EXISTING PAVEMENT (1" THICK)SY 538 $15.00 $8,075.00 $9.50 5,111.00$ $9.35 5,030.30$ $8.25 4,438.50$ $12.85 6,913.30$ $15.00 8,070.00$ $11.00 5,918.00$ $8.60 4,626.80$ $9.50 $15.00 10.65$ 57.89%-29.00%5,111.00$ $8,075.00 ($2,964.00) 10 334-1-12 SUPERPAVE ASPH. CONC. (TRAFFIC B, 1" THICK, RESURFACING) TN 30 $200.00 $5,921.67 $180.00 5,400.00$ $435.00 13,050.00$ $355.00 10,650.00$ $309.50 9,285.00$ $800.00 24,000.00$ $300.00 9,000.00$ $395.00 11,850.00$ $180.00 $200.00 396.36$ 11.11%98.18%5,400.00$ $5,921.67 ($521.67) 11 334-1-12 SUPERPAVE ASPH. CONC. (TRAFFIC B, 3" THICK) TN 105 $200.00 $20,959.03 $169.00 17,745.00$ $176.00 18,480.00$ $220.00 23,100.00$ $367.55 38,592.75$ $800.00 84,000.00$ $220.00 23,100.00$ $162.00 17,010.00$ $169.00 $200.00 302.08$ 18.34%51.04%17,745.00$ $20,959.03 ($3,214.03) 12 425-1-361 INLET, CURB TYPE P-6 EA 1 $5,000.00 $5,000.00 $3,780.00 3,780.00$ $6,000.00 6,000.00$ $10,000.00 10,000.00$ $9,005.00 9,005.00$ $4,500.00 4,500.00$ $7,830.00 7,830.00$ $8,360.00 8,360.00$ $3,780.00 $5,000.00 7,067.86$ 32.28%41.36%3,780.00$ $5,000.00 ($1,220.00) 13 425-2-43 MANHOLE, P-7 PARTIAL (REMOVE INLET TOP)EA 1 $4,500.00 $4,500.00 $2,530.00 2,530.00$ $4,555.00 4,555.00$ $4,000.00 4,000.00$ $4,505.00 4,505.00$ $4,500.00 4,500.00$ $3,915.00 3,915.00$ $5,510.00 5,510.00$ $2,530.00 $4,500.00 4,216.43$ 77.87%-6.30%2,530.00$ $4,500.00 ($1,970.00) 14 520-1-10 CONCRETE CURB & GUTTER TYPE F LF 659 $25.00 $16,475.00 $15.50 10,214.50$ $20.00 13,180.00$ $22.50 14,827.50$ $38.60 25,437.40$ $28.00 18,452.00$ $17.60 11,598.40$ $27.00 17,793.00$ $15.50 $25.00 24.17$ 61.29%-3.32%10,214.50$ $16,475.00 ($6,260.50) 15 522-2 SIDEWALK (CONCRETE, 3,000 PSI, 6") (INCL. DRIVEWAYS)SY 402 $40.00 $16,066.67 $44.00 17,688.00$ $58.00 23,316.00$ $54.00 21,708.00$ $57.90 23,275.80$ $60.00 24,120.00$ $50.00 20,100.00$ $65.20 26,210.40$ $44.00 $40.00 55.59$ -9.09%38.98%17,688.00$ $16,066.67 $1,621.33 16 570-1-2 PERFORMANCE TURF (BAHIA)SY 742 $3.00 $2,225.33 $3.30 2,448.60$ $4.40 3,264.80$ $3.00 2,226.00$ $3.67 2,723.14$ $5.00 3,710.00$ $3.75 2,782.50$ $2.70 2,003.40$ $3.30 $3.00 3.69$ -9.09%23.00%2,448.60$ $2,225.33 $223.27 17 625-2-11 PULL & SPLICE BOX EA 5 $700.00 $3,500.00 $577.30 2,886.50$ $1,015.00 5,075.00$ $1,180.00 5,900.00$ $645.74 3,228.70$ $1,200.00 6,000.00$ $655.00 3,275.00$ $608.00 3,040.00$ $577.30 $700.00 840.15$ 21.25%20.02%2,886.50$ $3,500.00 ($613.50) 18 625-2-41 PULL & SPLICE BOX, RELOCATE EA 1 $250.00 $250.00 $508.30 508.30$ $1,015.00 1,015.00$ $1,150.00 1,150.00$ $568.56 568.56$ $1,200.00 1,200.00$ $575.00 575.00$ $536.00 536.00$ $508.30 $250.00 793.27$ -50.82%217.31%508.30$ $250.00 $258.30 19 630-2-11 CONDUIT, LIGHTING, 2' PVC, OPEN TRENCH LF 672 $10.00 $6,720.00 $7.00 4,704.00$ $15.40 10,348.80$ $18.00 12,096.00$ $7.85 5,275.20$ $10.50 7,056.00$ $8.00 5,376.00$ $7.40 4,972.80$ $7.00 $10.00 10.59$ 42.86%5.90%4,704.00$ $6,720.00 ($2,016.00) 20 630-2-12 CONDUIT, LIGHTING, 2' PVC, DIRECTIONAL BORE LF 119 $26.00 $3,094.00 $23.00 2,737.00$ $31.00 3,689.00$ $36.00 4,284.00$ $25.79 3,069.01$ $25.00 2,975.00$ $26.00 3,094.00$ $24.30 2,891.70$ $23.00 $26.00 27.30$ 13.04%5.00%2,737.00$ $3,094.00 ($357.00) 21 700-20-11 SIGN, SINGLE POST AS 2 $300.00 $600.00 $460.00 920.00$ $440.00 880.00$ $775.00 1,550.00$ $514.53 1,029.06$ $400.00 800.00$ $590.00 1,180.00$ $485.00 970.00$ $460.00 $300.00 523.50$ -34.78%74.50%920.00$ $600.00 $320.00 22 700-20-51 SIGN, SINGLE POST (RELOCATE)AS 2 $300.00 $600.00 $316.25 632.50$ $305.00 610.00$ $530.00 1,060.00$ $353.75 707.50$ $400.00 800.00$ $65.00 130.00$ $333.00 666.00$ $316.25 $300.00 329.00$ -5.14%9.67%632.50$ $600.00 $32.50 23 706-3 PAVEMENT MARKERS, RETRO-REFLECTIVE EA 64 $4.00 $256.00 $4.60 294.40$ $4.40 281.60$ $15.00 960.00$ $5.15 329.60$ $10.00 640.00$ $5.20 332.80$ $4.90 313.60$ $4.60 $4.00 7.04$ -13.04%76.00%294.40$ $256.00 $38.40 24 711-1 PAVEMENT MESSAGES (PAINT)EA 2 $100.00 $200.00 $115.00 230.00$ $110.00 220.00$ $120.00 240.00$ $128.63 257.26$ $100.00 200.00$ $130.50 261.00$ $121.00 242.00$ $115.00 $100.00 117.88$ -13.04%17.88%230.00$ $200.00 $30.00 25 711-11-121 TRAFFIC STRIPE, SOLID, THERMO. (6" WHITE)LF 1806 $2.00 $3,612.00 $1.15 2,076.90$ $1.10 1,986.60$ $1.70 3,070.20$ $1.29 2,329.74$ $3.00 5,418.00$ $1.30 2,347.80$ $1.20 2,167.20$ $1.15 $2.00 1.53$ 73.91%-23.50%2,076.90$ $3,612.00 ($1,535.10) 26 711-11-123 TRAFFIC STRIPE, SOLID, THERMOPLASTIC (12" WHITE), (RESTRIPE)LF 125 $5.00 $625.00 $3.16 395.00$ $3.05 381.25$ $2.30 287.50$ $3.54 442.50$ $6.00 750.00$ $3.60 450.00$ $3.30 412.50$ $3.16 $5.00 3.56$ 58.23%-28.80%395.00$ $625.00 ($230.00) 27 711-11-125 TRAFFIC STRIPE, SOLID, THERMOPLASTIC (24" WHITE) (RESTRIPE)LF 24 $10.00 $240.00 $6.35 152.40$ $6.10 146.40$ $3.50 84.00$ $7.08 169.92$ $12.00 288.00$ $7.20 172.80$ $6.70 160.80$ $6.35 $10.00 6.99$ 57.48%-30.10%152.40$ $240.00 ($87.60) 28 711-11-127 DIRECTIONAL ARROW, THERMOPLASTIC EA 7 $25.00 $175.00 $69.00 483.00$ $66.00 462.00$ $120.00 840.00$ $77.18 540.26$ $150.00 1,050.00$ $78.30 548.10$ $72.70 508.90$ $69.00 $25.00 90.45$ -63.77%261.80%483.00$ $175.00 $308.00 29 711-17 REMOVE EXIST. PAVEMENT MARKINGS LS 1 $2,000.00 $2,000.00 $862.50 862.50$ $825.00 825.00$ $750.00 750.00$ $964.75 964.75$ $2,500.00 $980.00 980.00$ $909.00 909.00$ $862.50 $2,000.00 1,113.04$ 131.88%-44.35%862.50$ $2,000.00 ($1,137.50) 30 715-1-11 LIGHTING CONDUCTORS (AWG10 MINIMUM)LF 600 $1.50 $900.00 $1.25 750.00$ $1.35 810.00$ $1.50 900.00$ $1.35 810.00$ $2.00 1,200.00$ $1.40 840.00$ $1.30 780.00$ $1.25 $1.50 1.45$ 20.00%-3.33%750.00$ $900.00 ($150.00) 31 715-1-12 LIGHTING CONDUCTORS (AWG6 MINIMUM)LF 3228 $2.50 $8,070.00 $1.70 5,487.60$ $2.00 6,456.00$ $2.30 7,424.40$ $1.87 6,036.36$ $2.20 7,101.60$ $1.90 6,133.20$ $1.80 5,810.40$ $1.70 $2.50 1.97$ 47.06%-21.20%5,487.60$ $8,070.00 ($2,582.40) 32 715-4-119 LIGHT POLE COMPLETE (INCL FOUNDATION, FUSE HOLDER & SURGE ARRESTER)EA 5 $10,000.00 $50,000.00 $6,842.50 34,212.50$ $9,020.00 45,100.00$ $10,500.00 52,500.00$ $7,653.68 38,268.40$ $8,750.00 43,750.00$ $8,000.00 40,000.00$ $7,210.00 36,050.00$ $6,842.50 $10,000.00 8,282.31$ 46.15%-17.18%34,212.50$ $50,000.00 ($15,787.50) 33 715-46 LIGHT POLE COMPLETE (REMOVE & DISPOSE)EA 5 $500.00 $2,500.00 $701.50 3,507.50$ $605.00 3,025.00$ $700.00 3,500.00$ $784.66 3,923.30$ $915.00 4,575.00$ $800.00 4,000.00$ $739.00 3,695.00$ $701.50 $500.00 749.31$ -28.72%49.86%3,507.50$ $2,500.00 $1,007.50 34 737-70-1 UTILITY LOCATES, UNDERGROUND EA 10 $200.00 $2,000.00 $2,300.00 23,000.00$ $675.00 6,750.00$ $380.00 3,800.00$ $1,287.00 12,870.00$ $250.00 2,500.00$ $260.00 2,600.00$ $606.00 6,060.00$ $2,300.00 $200.00 822.57$ -91.30%311.29%23,000.00$ $2,000.00 $21,000.00 35 REC-DWGS PREPARE/SIGN & SEAL RECORD DRAWINGS LS 1 $3,000.00 $3,000.00 $1,782.50 1,782.50$ $6,700.00 6,700.00$ $5,200.00 5,200.00$ $1,500.00 1,500.00$ $3,500.00 3,500.00$ $2,350.00 2,350.00$ $2,180.00 2,180.00$ $1,782.50 $3,000.00 3,316.07$ 68.30%10.54%1,782.50$ $3,000.00 ($1,217.50) TOTAL BASE BID TOTAL:$306,315.69 289,129.70$ 303,510.35$ 317,472.10$ 381,958.51$ 382,025.60$ 392,769.60$ 414,498.00$ Bid Documents: -Material Manufacturers Y Y Y Y Y Y Y -Subcontractors Y Y Y Y Y Y Y -Statement of Experience Y Y Y Y Y Y Y -Trench Safety Act Y Y Y Y Y Y Y -Immigration Law Affidavit / MOU or Profile Page Y / Y Y / N Y / N Y / Y Y / Y Y / N Y / N -W-9 Y Y Y Y Y Y Y -Bid Bond Y Y Y Y Y Y Y Granting Agency Documents: - Acknowledgement of Terms, Conditions and Grant Clauses Y Y Y Y Y Y N -Certification Regarding Debarment, Suspension and Other Matters Y Y Y Y Y Y N -Certification Regarding Lobbying Y Y Y Y Y Y N -Anticipated Disadvantaged, Minority, Women or Veteran Participation Y Y Y Y Y Y N -Affidavit of Vehicle Registration Y Y Y Y Y Y N -Certification of Sublet Work Y Y Y Y Y Y N -Notification of EEO Officer Y Y Y Y Y Y N -Conflict of Interest Y Y Y Y Y Y N -Drug Free Workplace Y Y Y Y Y Y N -Certification of Current Capacity Y Y Y Y Y Y N -Contractor Certificate: Non-Collusion, Lobbying, Suspension and Debarment Provision Y Y Y Y Y Y N -Bid Opportunity List For Commodities and Contractual Services Y Y Y Y Y Y N -EEO/ AA Plan Y Y N Y Y Y Y Brenda Brilhart, Procurement Strategist 11/21/2016 Viviana Giarimoustas, Witness Engineer's Estimate UNIT PRICE COMPARISON TOTAL PRICE COMPARISON Collier Paving & Concrete dba Southern Striping Solutions, LLC Naples Ajax Paving Industries of Florida, LLC. North Venice Quality Enterprises USA, Inc. Naples Coastal Concrete Products, LLC dba Coastal Site Development Ft. Myers Community Asphalt Corp. Ft. Myers Haskins, Inc. Bonita Springs Preferred Materials, Inc. Tampa 16.A.12.b Packet Pg. 695 Attachment: Bid Tabulation with Analysis (2503 : Award bid to Quality Enterprises USA, Inc for Golden ITB 16-6572R – Bid Analysis Golden Gate Parkway at Livingston Road Intersection Improvements I have reviewed the bid and analyzed it for anomalies by comparing it to the engineer’s estimate and the average of the bid price. Below are pay items in which the Contractor’s price was significantly different than the Engineer’s Estimate: 101-1 Mobilization (1 LS) – Higher than estimated 102-1 Maintenance of Traffic (1 LS) - Lower than estimated 285-715 Optional Base Group, Base Group 15 (9” Thick) (SY) - Higher than estimated 715-4-119 Light Pole Complete (Incl. Foundation, Fuse Holder & Surge arrester) (EA) - Lower than estimated 737-70-1 Utility Locates, Underground (EA) - Higher than estimated Unit Prices for Engineer’s Estimate were taken from historical pricing from County projects and FDOT Area Averages. All pay items and associated quantities have been reviewed and deemed correct based on the proposed plans. Overall the bid was 5.9 % lower than the engineer’s estimate. I have verified the plan quantities for these items and find minimal risk to the county in awarding the bid. Daniel G Hall, P.E. Principal Project Manager Transportation Engineering Division 16.A.12.c Packet Pg. 696 Attachment: Bid Analysis (2503 : Award bid to Quality Enterprises USA, Inc for Golden Gate Pkwy at Livingston Road Intersection) 16.A.12.f Packet Pg. 697 Attachment: 16-6572R NORA (2503 : Award bid to Quality Enterprises USA, Inc for Golden Gate Pkwy at