Agenda 01/10/2017 Item #16A15 16A.15 .` 01/10/2017 EXECUTIVE SUMMARY Recommendation to approve and authorize the County Manager or his designee to execute an after the fact Change Order No. 1 to CB&I Environmental & Infrastructure, Inc. (CB&I), Marco Island Beach Renourishment under Contract No. 15-6382, to add an additional 66 days to complete the final report for the project. OBJECTIVE: To provide additional time for completion for the Marco Island Beach Renourishment. CONSIDERATIONS: The 2016 beach renourishment construction project for the Marco Island Beach Renourishment was not completed until November 11, 2016. The completion date for Work Order 4500163510 was November 8, 2016. Due to a change in means and methods that resulted in reduced cost to Collier County, work and mobilization did not begin as expected and work was not completed until November 11,2016. A final report will be completed by January 13, 2017. This will require an additional 66 days to be added to the original Work Order, extending the date to January 13, 2017. FISCAL IMPACT: There is no Fiscal Impact associated with this Executive Summary. GROWTH MANAGEMENT IMPACT: There is no Growth Management impact associated with this Executive Summary. ADVISORY COMMITTEE RECOMMENDATIONS: The original Work Order was approved by the Coastal Advisory Committee (CAC) on September 10, 2015; the Tourist Development Council (TDC) on September 28,2016 and the Board of County Commissioners (Board)on October 13,2016. LEGAL CONSIDERATIONS: This item has been reviewed by the County Attorney, is approved as to form and legality, and requires majority vote for approval. -JAI( RECOMMENDATION: To approve and authorize the County Manager or his designee to execute an after the fact Change Order No. 1 to CB&I Environmental & Infrastructure, Inc. (CB&I), Marco Island Beach Renourishment under Contract No. 15-6382 to add an additional 66 days to complete the final report for the project.. Prepared By: J. Gary McAlpin, P.E., Coastal Zone Management, Capital Project Planning, Impact Fees and Program Management Division, Growth Management Department ATTACHMENT(S) 1. CO letter (PDF) 2. CO# 1 (PDF) Packet Pg. 509 16.A.15 01/10/2017 COLLIER COUNTY Board of County Commissioners Item Number: 16.A.15 Item Summary: Recommendation to approve and authorize the County Manager or his designee to execute an after the fact Change Order No. 1 to CB&I Environmental & Infrastructure, Inc. (CB&I), Marco Island Beach Renourishment under Contract No. 15-6382, to add an additional 66 days to complete the final report for the project. Meeting Date: 01/10/2017 Prepared by: Title: Accountant—Capital Project Planning, Impact Fees, and Program Management Name: Gail Hambright 12/13/2016 2:46 PM Submitted by: Title: Division Director-IF, CPP &PM—Capital Project Planning, Impact Fees, and Program Management Name: Amy Patterson 12/13/2016 2:46 PM Approved By: Review: Growth Management Department Judy Puig Level 1 Division Reviewer Completed 12/14/2016 4:04 PM Procurement Services Lissett DeLaRosa Level 1 Purchasing Gatekeeper Completed 12/15/2016 11:36 AM Capital Project Planning,Impact Fees,and Program Management Amy Patterson Additional Reviewer Completed Zoning Gary McAlpin Additional Reviewer Completed 12/19/2016 3:42 PM Growth Management Department Gene Shue Additional Reviewer Completed 12/20/2016 11:57 AM Procurement Services Adam Northrup Additional Reviewer Completed 12/20/2016 2:15 PM Procurement Services Ted Coyman Additional Reviewer Completed 12/20/2016 5:37 PM Grants Edmond Kushi Level 2 Grants Review Completed 12/21/2016 1:47 PM Growth Management Department Bendisa Marku Level 2 Division Administrator Completed 12/21/2016 2:24 PM County Attorney's Office Colleen Greene Level 2 Attorney Review Completed 12/27/2016 8:54 AM County Attorney's Office Jeffrey A.Klatzkow Level 3 County Attorney's Office Review Completed 12/21/2016 2:41 PM Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 12/21/2016 4:13 PM Budget and Management Office Ed Finn Additional Reviewer Completed 12/28/2016 9:50 AM Grants Therese Stanley Additional Reviewer Completed 12/28/2016 11:07 AM County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 12/28/2016 2:53 PM Board of County Commissioners MaryJo Brock Meeting Pending 01/10/2017 9:00 AM Packet Pg. 510 16.A.15.a CB&I Environmental & Infrastructure, [«... s 2481 NW Boca Raton Blvd. Boca Raton, FL 33431 Tel:+1 561 391 8102 Fax: +1 561 391 9116 www.CBI.com December 9, 2016 Gary McAlpin, Director Collier County Coastal Zone Management 2800 N. Horseshoe Drive Naples, FL 34104 Re: Modification to PO #45-163510 —Tropical Storm Debby Marco Island (Contract No. 15-6382) Dear Gary: CB&I Environmental & Infrastructure, Inc. would like to request a modification to PO #45-163510 as a result of the timing of the renourishment event. It was anticipated that the Marco Island Beach Toi Renourishment would be completed by 11/8/2016. Due to a change in means and methods that resulted in reduced cost to Collier County, work and mobilization did not begin as expected and work was not completed until 11/11/16. A final report will be written and completed by January 13, 2017. Please allow o` for an additional 66 days and revise the completion date to January 13, 2017. This will be a zero dollar change order. Very truly yours, N - Thomas P. Pierro, P.E., D.CE. Director o U CB&I Environmental & Infrastructure, Inc. C) E cc: Tara Brenner, P.G., P.E., CB&I Packet Pg. 511 I 6.A.1 5.b Procurement Services FILer Co 1.1mcv -......-_—:L_ Change Order Form 4.1,.11511ALY, '..1 VC Contract Contract Modification Z Work Order Modification E Amendment iil v-1 Contract Cr: 15-6332 ...-' Change 4: 1 1 ." I Purchase Order tr: ./.5-15?.51:: ' proect#: 195-9061 i Contractor/Firm Name:. CB&I Environmental& Infrastructure, Project Name: Trobica Storm Debbie Marco Island 3 Gary MicAlpin Coastal Zone Management Project Manager Name:: Department: Original Contract/Work Order Amount S 57,649 00-7-7' ' '. 7 • ' Original BCC Approval Date, Agenda Itern # Current BCC Approved Amount $ 57,649.00 1::: 'lir', ',II.-.:,.:- Last BCC Approval Date,Agenda Item# Current Contract/Work Order Amount $ 57,649.00 6/812019 SAP Contract Expiration Date(Master) Dollar Amount of this Change $ 0.00 1 0 00%1 Total Change from Original Amount Revised Contract/Work Order Total I S 57 649 00-1 000%1 Change from Current BCC Approved Amount Cumulative Changes I 5 000J 0 00%1 Chanpe from Current Amount ..., I . .. Completion Date, Description of the Tasigs) Change,and Rationale for the Change ti c re 7- ./ 1 1/13/17 Notice to Proceed{ 11/9'15 e•-• 1 Original , i 11/8/16 i Last Approved 1 11/8116 1 Revised Date Date I --.1 Completion Date i„ ; Date L_ l(In.:wain rills cone) i 0 0 4 of Days Added Select Tasks Add new task(*) Li Delete task(s) 7 Change task* r,3 Other 4ee beiew) E 8 Provide a response to the following: 1.) detailed and specific explanationtrationaie of the requested change(*) to the task(*)and for , the additional days added(if requested); 2.)why this change was not included in the original contract,and,3.) describe the impact if ,7-6 this change is not processed. Artaco additional information from the r,:A..sign Professional andtor Contractor it needed M 0 1 ) A zero 'dollar cnange order to add an additional 66 days and levlse the completion Cate to January 13. 2017 to allow ._ the engineering firm to complete the during and post-construction tasks This is an after the fact Change order. 0 0 2 ) I was anticipated that the Marco Island Beach Renounshme.nt would be =plated by 11/6(2015 Due to a change in tg means and methods that resulted ,n reduced cost to Coiii.r County: work and modil;zatiar, did not begin as expected and cl; work was not completed until 11/11/16 * 3.) Construction contmued past 11/516 and C5&I needs to prepare the lif101 report in order To certify tne project as 0 repuired by permits 0 .;..: c a) E ..= o / Cti ,:.....LL' :,-___. . Prepared try ;.%"*•1•11 f k; ar. , ‘..iaie ii. .iary McJoir. P- E C-7-IrManege.r Acceptance(11f this Criange Order sriali constitute a ninDifi;-,aiinn to conIrs..:. ;wcrk ardor ;De--itition aove and will De SubieCt IC al;Inc same terms and conditions as aOniane:; in ine contract r work order ingcawd above as'...:115 as I`fro 5.1an-.E.: were stated in this acceptonce The adjustment. !l any,to Inc Contract shall cr.-Jr-statue a tuli and dnasettlement c any ano all ::jrn,.;cl ttie Contractor/vendor/Consultant, Desigr• Professional arising iii - i: reiatr_id to'?,r, '..!,:,',6' set for;herein ,n;-„ludrg ca,rns for in-Ir.:ad',and delay costs , , Accepted by .., •, • ,; ..; i.rs,,. . . .. _ ' _ ;rid .iy, • • ,,,,, pi ,.;,.:,„:„. ' .._ . Approvrid t.) APp roved t '' ' , 7 :.• : ,.. , . Approved by —-';'----1;?----7" - , :.•'-'-,--.-_,_-;:i ..,-' Adam Northrdp7Proci_rement Professionai il (Thiviscis wriu may'eor.rirr adcltinna'sgita!u:e;-,r-,i,,,r,r‘zi,._-,t,,:r,,- ,,,,.,p, , s„,, , Rev.stli 1026!2-314 Packet Pg. 512