Loading...
Agenda 11/15/2016 Item #16A30 16.A.30 11/15/2016 EXECUTIVE SUMMARY Recommendation to award Work Order No. 14-6213-77,to Haskins Inc., for the Eagle Creek Weir Refurbishment in the amount of$223,806,Project No. 60124. OBJECTIVE: To commence with the refurbishment construction of the Eagle Creek Weir by awarding Work Order No. 14-6213-77,to Haskins,Inc.,who provided the lowest,responsive and qualified quote. CONSIDERATIONS: This is the first of three weir improvement projects for which the Stormwater Management staff completed an overall assessment of in 2014, and subsequently had design plans completed. Many of the weirs within Collier County are old, are currently undersized because of designs based on conditions of 20 to 30 years ago, and have damaged and/or worn out parts. The Eagle Creek Weir has had nearly inoperable water control gates for many years. The Request for Quotes were emailed out on August 30, 2016, to all six (6) contractors on The Underground Utility Annual Contract # 14-6213. The following three quotes were received by the September 13,2016,due date: Contractor Quote 1 Quality Enterprises Inc. $ 144,787.97-Withdrawn 2 Haskins Inc. $223,806.00 3 D.N. Higgins Inc. $242,935.00 The other three contractors on Annual Contract#14-6213 did not respond for various reasons. Staff and the Engineering Consultant tabulated and reviewed the quotes. Quality Enterprise, Inc. (QE), was initially the apparent low quote provider. However, QE subsequently withdrew their quote and cited an error in their cost estimating.As such,QE was deemed non-responsive. The next lowest responsive quote was the one submitted by Haskins, Inc. Staff and our Engineer of Record(EOR) have reviewed their quote as well and found it to be responsive and the lowest quote after QE withdrew. The quote distribution is reasonable compared to the engineer's opinion of probable cost (OPC);the OPC is between the initial low quote and the second lowest. Haskins' quote is approximately 21%higher than the Engineer's OPC which is $176,451.50. This is due to the fact that contractors' pricing has increased because they are significantly busier with large projects. Half of the contractors on Annual Contract# 14-6213 did not submit a quote on this project. Staff and the EOR (see attached letter) recommend awarding the construction contract to Haskins, Inc., the lowest responsive and qualified quote provider. FISCAL IMPACT: Funds in the amount of$ 223,806 are available in project number 60124 within the Stormwater Capital Improvement Fund 325. Source of funds is transfers from the General Fund (001) and Unincorporated Area General Fund(111). With this particular work, there is no increase to the Road Maintenance Division work schedule. The Eagle Creek Weir is an existing facility. GROWTH MANAGEMENT IMPACT: The project is in accordance with the goals and objectives of the Drainage Sub-element of the Growth Management Plan for Collier County Stormwater Management. Packet Pg.592 16.A.30 11/15/2016 LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote for Board approval. -CMG RECOMMENDATION: To award Work Order # 14-6213-77, to Haskins, Inc, in the amount of $223,806 for the construction of the Eagle Creek Weir Refurbishment and authorize the Chairman to sign the attached Work Order after final review by the County Attorney. Prepared by: Shane Cox P.E., Sr. Project Manager, Capital Project Planning, Impact Fees, and Program Management Division,Growth Management Department ATTACHMENT(S) 1.Quote Tabulation Sheet (PDF) 2.Engineer's Recommendation (PDF) 3.Work Order No. 14-6213-77 (PDF) Packet Pg.593 16.A.30 11/15/2016 COLLIER COUNTY Board of County Commissioners Item Number: 16.A.30 Item Summary: Recommendation to award Work Order No. 14-6213-77, to Haskins Inc., for the Eagle Creek Weir Refurbishment in the amount of$223,806,Project No. 60124. Meeting Date: 11/15/2016 Prepared by: Title:Project Manager, Senior—Capital Project Planning,Impact Fees,and Program Management Name: Shane Cox 10/17/2016 1:24 PM Submitted by: Title:Division Director-IF,CPP&PM—Capital Project Planning,Impact Fees,and Program Management Name: Amy Patterson 10/17/2016 1:24 PM Approved By: w Review: Procurement Services Ted Coyman Additional Reviewer Completed 10/20/2016 11:05 AM Procurement Services Lissett DeLaRosa Level 1 Purchasing Gatekeeper Completed 10/21/2016 2:03 PM Procurement Services Sandra Herrera Additional Reviewer Completed 10/21/2016 3:45 PM Capital Project Planning,Impact Fees,and Program Management Gerald Kurtz Additional Reviewer Completed Growth Management Department Jeanne Marcella Level 1 Division Reviewer Completed 10/24/2016 10:50 AM Growth Management Department Lisa Taylor Additional Reviewer Completed 10/27/2016 8:56 AM Growth Management Department Jeanne Marcella Level 2 Division Administrator Completed 10/27/2016 9:29 AM County Attorney's Office Jeffrey A.Klatzkow Level 3 County Attorney's Office Review Completed 10/27/2016 3:36 PM Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 10/27/2016 4:02 PM Office of Management and Budget Susan Usher Additional Reviewer Completed 11/03/2016 3:05 PM County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 11/07/2016 3:03 PM Board of County Commissioners MaryJo Brock Meeting Pending 11/15/2016 9:00 AM Packet Pg.594 as (;uauaysiganjay aieM jeal3 aiBe3 : paz) ways uoi;eingel a;on° :;ueuay�e;;v rr s a a- C Oiler C014.14ty 40 AO Administrative Seivices Department Procurement Services Division REQUEST FOR QUOTATIONS FOR MULTIPLE PROJECTS UNDER CONTRACT #14-6213 "Annual Contract for Underground Utilities&General Contractors" Date: August 30, 2016 From: Shane Cox PE, Sr Project Manager 239-252-5792,Telephone Number shanecox(aJcoiliergo r.net To: Potential Proposers Subject: RFQ 14-6213-77-Eagle Creek Weir Refurbishment As provided in the referenced contract, the Collier County Purchasing Department is soliciting quotes for the referenced project. RFQ Due Date: 2:00 PM 9/13/2016 Q&A Deadline: 5:00 PM 9/8/2016 Pre-Quote Meeting no Number of Days to Final Completion: 60 Days Substantial+30 Days Final =90 Days Total /"'N • Scope Provided Yes Plans and Specs: Yes Liquidated Damages: $758.00 per day(fr FDOT Manual) Payment&Performance Bonds Yes, if project value exceeds$200,000.00 Your quotation response for this project is due no later than the date and time specified above.We wilt not accept any quotation responses later than the noted time and date. if your firm is unable to respond electronically,your quotation must be received in the office of the Purchasing Department at the above referenced address no tater than the time and date specified.We look forward to your participation in this request for information/quotation process. Haskins Inc. Firm's Complete Le!, Name 239-947-1846 4 9-947-3857 TFi- ele one :► , /Fax Number Si t e easurer Title Ryan MacPhee 9/13/16 Print Name Date 1 RFQ 14-6213-54 ,as, (;uewgsninjeu.naM Aaaa3 ape3 : y4ZZ) ;eegs uoi;eingej a;on j :;uewg3e;;y tis in P"*.,.' Bid Tabulation , Eagle Creek Weir Refurbishment(Phase I) D. ' 500 Tower Road Naples,Florida Date: 11-Aug-16 ITEM DESCRIPTION QUANTITY UNIT UNIT COST SUBTOTAL PAVING,GRADING,AND DRAINAGE I Maintenance of Traffic 1 LS $15,000.00 $15,000.00 2 Mobilization 1 LS $30,000.00 $30 000.00 3 Provide Construction Survey Layout I LS $3,000.00 $3;000.00 4 Remove exotic plants,treat area with glyphosate I LS $3,600.00 $3,600.00 5 Chain link fence removal 91 LF $6.00 $546.00 6 Furnish and install barbed wire on existing chain link fence 45 LF $38:00 $1,710.00 7 Furnish and install new chain link fence(PVC coated) 350 LF $55.00 $19,250.00 8 Furnish and install 12'wide double swing gates 2 EA $3,050.00 $6,100.00 9 Mangrove Trimming 1 LS $2,450.00 $2,450.00 10 Brazilian Pepper removal/area treatment 1 LS $3,700.00 $3,700.00 SUB-TOTAI, $85,356.00 ITEM DESCRIPTION QUANTITY UNIT UNIT COST SUBTOTAL WEIR GATES 12 Existing weir gates removal 1 LS $12,000.00 $12,000.00 13 New weir gates(WACO Model 5564) I LS $52,500.00 $52,500.00 14 Weir gates installation 1 LS $62,750.00 $62,750.00 SUB-TOTAL $127,250.00 EROSION CONTROL 15 Type III Staked Silt Fence 200 LF $7.00 $1,400.00 16 Floating Turbidity Barrier 350 LF $28.00 $9,800.00 SUB-TOTAL $11,200.00 PAVING,GRADING,AND DRAINAGE $85,356.00 WEIR GATES $127,250.00 EROSION CONTROL $11,200.00 Sub-Total $223,806.00 Total 1 1 r $223,806.00 C:\Userslcox sV+ppDatalLoca5Microsoft\WindowstTemporary Internet Foes\Content.OuUook'EYEY5V2X\Eagle,Creek.Bid Tabulation OB•11-16-Bid Tabulation 16.A.30.b 4414 ca.m e c foster October 3, 2016 wheeler Shane Cox, PE Sr Project Manager Capital Project Planning, Impact Fees & Program Management Collier County Government L SUBJECT: RFQ 14-6213-77 EAGLE CREEK WEIR REFURBISHMENT CC BID REVIEW AND RECOMMENDATION Dear Mr. Cox: Amec Foster Wheeler Environment & Infrastructure, Inc. (Amec Foster Wheeler) has reviewed the Uo, bids submitted to Collier County by each of the two respondents (Higgins, Inc., and Haskins, Inc.)for a) co the purpose of constructing Phase I of the Eagle Creek Weir Refurbishment project. w The bids were reviewed for both an understanding of the proposed scope of work as well as unit ccs, pricing and total cost. In addition to comparing each bid against the other, the bids were evaluated with respect to the probable cost estimate completed by Amec Foster Wheeler. Based on the above referenced criteria, the bid submitted by Haskins Inc. not only demonstrated pricing more closely in line with the probable cost estimate but more importantly contained no irregularities which would c indicate a misunderstanding of the requested services. °' E In conclusion, Amec Foster Wheeler recommends the selection of Haskins Inc. as the contractor for the Eagle Creek Weir Refurbishment project. cc GS d AMEC FOSTER WHEELER ENVIRONMENT&INFRASTRUCTURE, INC. W c cu css NestofFernandei9A, LEED AP Jeremy Paris, PWS Naples Branch Manager Project Manager Distributions: Addressee (1) File (1) P:\Projects\Facilities Projects\Projects 2015\6788-15-2711 -Eagle Creek Weir Replacement\bid response 10-3-16.docx Packet Pg. 597 9 (;ueunisigJn;aa JiaM leo.i3 ape3 : KU) LL-£129174 'oN Jarmo)JOM :;uewyoe 4y C co in 4 a WORK ORDER/PURCHASE ORDERo RFQ/WORK ORDER 14-6213-77 ti. Contract14-6213 "Underground Utility Contractors" Contract Expiration Date: 7 July 2018 This Work Order is for underground construction services for work known as following: Project Name:Eagle Creek Weir Refurbishment Project No: 60124 The work is specified in the proposal dated 13 September 2016. which is attached hereto and made a part of this Work Order. In accordance with Terms and Conditions of the Agreement referenced above,this Work Order/Purchase Order is assigned to: Haskins Inc Scope of Work: As detailed in the attached proposal and the following: Refurbish Eagle Creek weir: replace weir's water control gates, install security fencing, clear excess vegetation from channel * Task I Paving Grading, and Drainage * Task II Weir Gates * Task III Erosion Control Schedule of Work: Complete work within 120 days from the date of the Notice to Proceed which is accompanying this Work Order. The Consultant agrees that any Work Order that extends beyond the ,-- expiration date of Agreement #14-6213 will survive and remain subject to the terms and conditions of that Agreement until the completion or termination of this Work Order 14-6213-77. Compensation: In accordance with the Agreement referenced above,the County will compensate the Firm in accordance with following method(s): ® Lump Sum (QUOTE—attached schedule of values) as provided in the attached proposal. Task I $ 85,356.00 LS Task II $ 127,250.00 LS Task III $ 11,200.00 LS TOTAL FEE $ 223,806.00 PREPARED BY: >kY/44_,- � q/260 6 Shane Cox,PE, Sr Pr9j `ct Manager Date Capital Project,Planning,Impact Fees&Program Mgt Div APPROVED BY: Ge ald N urtz E a,' cip al Project Manager Data '7 J Capital Project,Planning,Impact Fees&Program.Mgt Div n. Page 1 of 3 (lueweisminjeld aief loaa3 ei6e3 : b6ZZ) LL-£4Z9-trb 'oN aapao$aoM :luawyoelly a) Mr, u M a ea APPROVED BY: ((' v '�r , Amy Patter��pn,Director Date Capital Project,Planning, Impact Fees&Program Mgt Div 041 APPROVED B : 6 lC l f 10 David Wilkison,Dept Head Date Growth Management Dept By the signature below, the Firm (including employees, officers and/or agents) certifies, and hereby discloses,that,to the best of their knowledge and belief, all relevant facts concerning past,present, or currently planned interest or activity(financial,contractual,organizational,or otherwise)which relates to the proposed work; and bear on whether the Firm has a potential conflict have been fully disclosed. Additionally,the Firm agrees to notify the Procurement Director, in writing within 48 hours of learning of any actual or potential conflict of interest that arises during the Work Order and/or project duration. ACCEPTED BY: Haskins, Inc 10/10/16 Rya acPhee, Treasurer Date (Remainder of page intentionally left blank) Page 2 of 3 i t (}ueunisiganlau J!eM hair ei6e3 : 176ZZ) LL-£6Z911 ON aapap laoM :�uewgoe;;d r a to IN WITNESS WHEREOF,the parties hereto,have each,respectively, by an authorized person or agent,have executed this Work Order on the date and year first written below. ATTEST: BOARD OF COUNTY COMMISSIONERS Dwight E.Brock,Clerk of Courts COLLIER COUNTY,FLORIDA By: By: Donna Fiala,Chairman Dated: (SEAL) Name of Firm By: First Witness Signature TType/print signature and title' tType/print witness namet Second Witness TType/print witness namet Approved as to Form and Legality: Assistant County Attorney Print Name Contract#14-6213-77 Work Order#14-6213-77 Page 3 of 3