Agenda 10/11/2016 Item #16A17 16.A.17
10/11/2016
EXECUTIVE SUMMARY
Recommendation to approve and authorize the Chairman to execute Change Order No. 1 to CB&I
Environmental & Infrastructure, Inc. (CB&I), to provide pre-placement survey, post-placement
survey, quality control and quality assurance professional engineering services under Contract No.
16-6629 - 2016 Beach Renourishment for time and materials not to exceed $86,153.50, and make a
finding that this item promotes tourism.
OBJECTIVE: To provide pre- and post-placement surveys, quality control (QC) and quality assurance
(QA)professional engineering services as required for the 2016 beach renourishment project.
CONSIDERATIONS: The 2016 beach renourishment project for the Vanderbilt, Pelican Bay, Park
Shore and Marco Island South beaches will require a pre-placement survey, post-placement survey,
construction observation and inspections along with quality assurance and quality control checks during
construction.
Verification and updating of the fill templates as required during construction to achieve uniform fill
distribution as intended by the project design along with verification of proper placement technique to
minimize sand loss into the intertidal zone during placement is critical to the successful execution of this
project. CB&I professional engineering staff will work closely with Collier County staff and all
contractor personnel to assure that these activities are properly coordinated and executed.
The scope of work is outlined as follows in the September 13, 2016 proposal from CB&I Environmental
&Infrastructure,Inc.:
1. Task Item 1: Pre-Placement Survey-$23,361.70
2. Task Item 2: Construction Quality Assurance and Post-Placement Surveys-$62,791.80
The work that is taking place in this change order is required to construct this project and has been
typically included in the construction solicitation as a subcontractor to the awardee. Staff believes that the
inclusion of these services in the construction solicitation does not give Collier County enough oversight
on the QA/QC process as the engineer providing oversight would be working for the contractor.
By executing this change order with the Engineer of Record,we will have full oversight over the process,
and be better able to intervene if the situation warrants. In the future, the design solicitation will include
the services during construction and post construction certifications. The Engineer of Record has also
agreed to update his contract to include the State of Florida grants compliance language.
FISCAL IMPACT: Funding for the proposed Change Order is budgeted in Tourist Development Tax
Fund 195, Project 80301, Beach Renourishment. Funding for this project will be requested for
reimbursement from FDEP Cost Share Program.
GROWTH MANAGEMENT IMPACT: There is no impact to the Growth Management Plan related to
this action.
ADVISORY COMMITTEE RECOMMENDATIONS: This item will be presented to the Coastal
Advisory Committee on October 12, 2016 for after the fact approval. This item will also be presented to
the Tourist Development Council on October 25, 2016 for after the fact approval. The CAC and TDC
have previously approved the budget for the 2016/2017 Beach Renourishment, CAC on May 12, 2016
and TDC on June 27,2016.
Packet Pg. 770
I6.A.17
10/11/2016
LEGAL CONSIDERATIONS: This item is approved as to form and legality and requires majority vote
for approval. -CMG
RECOMMENDATION: To approve and authorize the Chairman to execute Change Order No. 1 to
CB&I Environmental & Infrastructure, Inc. (CB&I) to provide pre-placement survey, post-placement
survey, quality control and quality assurance professional engineering services under Contract No. 16-
6629 - 2016 Beach Renourishment for time and materials not to exceed $86,153.50, and make a finding
that this item promotes tourism.
Prepared By: J. Gary McAlpin, P.E., Coastal Zone Management, Capital Project Planning, Impact Fees
and Program Management Division,Growth Management Department
ATTACHMENT(S)
1.Proposal (PDF)
2.Change Order No 1 FINAL (PDF)
Packet Pg. 771
16.A.17
10/11/2016
COLLIER COUNTY
Board of County Commissioners
Item Number: 16.A.17
Item Summary: Recommendation to approve and authorize the Chairman to execute Change
Order No. 1 to CB&I Environmental&Infrastructure,Inc. (CB&I)to provide pre-placement survey,post-
placement survey, quality control and quality assurance professional engineering services under Contract
No. 16-6629 - 2016 Beach Renourishment for time and material not to exceed $86,153.50, and make a
finding that this item promotes tourism.
Meeting Date: 10/11/2016
Prepared by:
Title: Accountant—Capital Project Planning,Impact Fees,and Program Management
Name: Gail Hambright
09/22/2016 5:02 PM
Submitted by:
Title:Division Director-IF,CPP&PM—Capital Project Planning,Impact Fees,and Program
Management
Name: Amy Patterson
09/22/2016 5:02 PM
Approved By:
Review:
Procurement Services Lissett DeLaRosa Level 1 Purchasing Gatekeeper Completed 09/23/2016 8:28 AM
Growth Management Department Jeanne Marcella Level 1 Division Reviewer Completed 09/26/2016 7:35 AM
Capital Project Planning,Impact Fees,and Program Management Tara Castillo Level 1 Sim.Reviewer 1-8Completed
Procurement Services Sandra Herrera Level 1 Purchasing Reviewer 1-4 Completed 09/28/2016 12:48 PM
Zoning Gary McAlpin Level 1 Sim.Reviewer 1-8 Completed 09/28/2016 4:31 PM
Procurement Services Allison Kearns Level 1 Purchasing Reviewer 1-4 Completed 09/29/2016 11:41 AM
Capital Project Planning,Impact Fees,and Program Management Amy Patterson Level 1 Sim.Reviewer 1-8Completed
County Attorney's Office Colleen Greene Level 2 Attorney Review Completed 09/29/2016 1:21 PM
Growth Management Department Jeanne Marcella Level 2 Division Administrator Completed 09/29/2016 3:25 PM
Grants Edmond Kushi Level 2 Grants Review Completed 09/29/2016 4:03 PM
Office of Management and Budget Valerie Fleming Level 3 OMB Gatekeeper Review Completed 09/29/2016 4:28 PM
County Attorney's Office Jeffrey A.Klatzkow Level 3 County Attorney's Office Review Completed 09/29/2016 5:05 PM
Grants Therese Stanley Level 3 OMB 1st Reviewer 1-4 Completed 09/30/2016 1:14 PM
Budget and Management Office Ed Finn Level 3 OMB 2nd Reviewer Completed 09/30/2016 2:49 PM
County Manager's Office Nick Casalanguida Level 4 County Manager Review Completed 10/03/2016 11:30 AM
Packet Pg.772
6A17
10/11/2016
Board of County Commissioners MaryJo Brock Meeting Pending 10/11/2016 9:00 AM
/'\
Packet Pg 773-
16.A.17.a
CB&I Environmental & Infrastructure, Inc.
-13 c
2481 NW Boca Raton Blvd.
Boca Raton, FL 33431
Tel:+1 561 391 8102
Fax: +1 561 391 9116
www.CBl.com
September 13, 2016
Gary McAlpin, Director
Collier County Coastal Zone Management
2800 N. Horseshoe Drive
Naples, FL 34104
Re: 2016 Beach Renourishment(Contract No. 15-6382): Additional Services
0
us
ai
Dear Gary: 147
03
This letter is in response to Collier County's request for a proposal for CB&I Environmental & to
Infrastructure, Inc. (CB&I)to perform additional survey,quality control,and quality assurance tasks during 0
the upcoming 2016 truck haul beach renourishment. CB&I will provide pre-placement, post-placement E
and post-construction surveying services, as well as onsite construction presence. A scope of this work g
is detailed below. o.
0
1. Pre-Placement Surveys- $23,361.70 a
CB&I surveyors will perform pre-placement surveys of the project areas. These short (wading E
depth) survey profiles will be collected approximately 25 ft. offshore of the permitted toe of fill 0
^, along each 200 ft. station including R-monuments. It is anticipated that there will be 84 profiles a
surveyed as detailed below. 1
a
Reach Range Number of Profiles
m
o
Vanderbilt Beach R-24 to R-30 33
0
to
Pelican Bay R-34+500 to R-36+500 14
Park Shore N. R-43+400 to R-47 21 y
0
a.
Park Shore S. R-51 to R-53 16 o
a
Total 84 d
-- E
U
0
Survey data will be collected, processed and provided to the Engineer of Record at least 10 days a
prior to the start of construction.
2. Construction Quality Assurance and Post-Placement Surveys -$62,791.80
A CB&I representative with survey capabilities will be onsite 5 days per week, 9 hours per day,
for the 7 week construction period of November 1 to December 24. CB&I will perform construction
observations to supplement those conducted by the County or Engineer of Record (under a
separate scope of work) as well as collect post-placement surveys as the project progresses.
Post-placement,short(wading depth)survey profiles on each 200 ft. station will be collected upon
notification by the County and Contractor of a completed work section. The surveyor will collect
and process the data, then perform placed volume calculations, and deliver information to the
Packet Pg.774
'16A17.a '
r.
Engineer of Record who will perform verification calculations (under existing scope of work).
In additional to the on-site surveyor, CB&I will provide additional engineering services and
construction quality assurance tasks to ensure accurate accounting of sand quantities and
construction activities, as follows:
• Lead, train and coordinate an inspection team comprised of County employed inspectors
and CB&I staff
• Oversee daily sand accounting
• Prepare plot of delivered vs. surveyed vs. design quantities in
• Periodic checks of all active construction sites In
• Observe placement methods, quality control method and safety operations
00
• Observations for permit compliance w
• Record daily start and end stations d
• Report deficiencies to the Contractor for correction E
• Update fill templates as required during construction to achieve uniform fill distribution o
throughout intended project areas a
• Verify sand volumes measured by surveys (covered under existing scope of work) o
a
3. Post-Construction/Annual Monitoring Surveys - $41,825.65 c
a>
Within 60 days following completion of construction of the project, CB&I surveyors will perform 0
north county permit required physical monitoring surveys of R-22 through R-84, as shown in the �/'�
table below. These surveys will extend landward to the seawalls or 50 feet landward of the 5.0' a)
contour line. Profile surveys will extend seaward to the —14.3' NAVD contour or 2,000 feet from a
the shoreline, whichever is the greater distance. All work activities and deliverables will be m
conducted in accordance with the May 2014 Bureau of Beaches and Coastal Systems (BBCS)
Monitoring Standards for Beach Erosion Control Projects, Sections 01000 - Beach Profile c
Topographic Surveying and 01100- Offshore Profile Surveying. o
N
Reach Range Number of Profiles iii
U)
0
Vanderbilt Beach R-22 to R-30 9 Q
0
L
a
Pelican Bay R-31 to R-41 11
c
CD
Park Shore R-42 to R-57 16 E
c.)
ca
Naples Beach R-58A to R-84 28 a
Total 64
It is anticipated that these full (bathymetric and topographic) beach profile surveys can be used
to satisfy immediate post-construction permit requirements as well as annual physical monitoring
requirements. Note that this proposal does not include surveying Wiggins Pass or Marco Island.
If found to be beneficial to the County, CB&I can perform physical monitoring surveys to include
additional lines at a negotiated additional price.
Packet Pg.775
16.A.17.a
4. Annual Physical Monitoring Engineering Report- $25,880.00
CB&I engineers will incorporate post-construction certification requirements (covered under
existing scope of work) and the post-construction surveys into a physical monitoring engineering
report. Engineering calculations will be performed to measure the performance of the beach as
outlined in the physical monitoring plan. This report will be written to satisfy immediate post-
construction permit requirements as well as annual physical monitoring permit requirements for
the North County project area.
A fee proposal is included as Exhibit A, and a rate schedule is provided as Exhibit B. These services will
be performed on a time and material basis not to exceed $153,859.20 under existing Contract No. 1511)
-
6382 between Collier County and CB&I. Barring any unforeseen circumstances, all work will be
completed and submitted to the County within 180 days of receiving the Notice to Proceed.
Very truly yours, °;
n.
N
O
a
Thomas P. Pierro, P.E., D.CE E
Director of Operations
CB&I Environmental & Infrastructure, Inc. co
a
cc: Adam Northrup, Collier County Government a`
Tara Brenner, P.G., CB&I
Steve Keehn, P.E., CB&I 0°
0
co
0
N
O
In
O
Q
O
a
_
CD
E
Packet Pg 776,
'16A-17.a
p m
Sc N N 10
69
6E a
a
a
C
6 pTSU
0 l7 N co u
S.
F N
iy o
p
l N 0 Yom} co v 2 N
A i/1
E
�
Qc 2 o 2 o
a. NNrab 7 N r N m co W 6-
ms O G
to
O2a a td Z O
ara
F W a 8¢ - a ; M
W 40 IsE aimt-g w O N ,51 ° Bei e—
a ECU Y t144c 2Qt�-y� i T.. 7, A t
2. KLo,.x0 _ �'
di et8c''=Ux e v C
x 0 `o g$n S N v u° m 0 * r C)
Pi 5jaE a g : E
.. p
at 9 f0 0 A N i r
A a' �' 1 0
�C . ,. . . N g m
� y "' E
aU�e a x
esoy 3 m ' F. J `
a o co va '< v m v ^ a C
H ?, w a §
i
= a
o" N `_ N prti& T
S N o.a w 3 5 m
V
T.
23 N m 0 o p 0
CO
a x 2 U $ O
N
1a0tio n " 0« gg
G 4N14cI O2U w
N
U " N 0
em }} — ei 0
NMWw
0.
f° N 0
L
J a.
cc
o +r
I- C
C)
cc E
E uI0
H
W m O
a
NI Q
2 coE W
� R g 8 F
c
C
o o I
g cf w
w g c
c
t e e
tai ¢ e
g
3 e E r
0 0.
e Y 3
c
4.4. 0 a.a. d
Packet Pg.777
I6:A.17.a
a
i a ^ g � TgA
aV. a �
A
R Y N r iA n;:
C r'
h
oe
r '- 'r ' g8
W W
re O
Y
N U)
3 = 04 es
2 g 04 /7 N K C1 Os sI
t
n.Si 3'
q0 CO
r O� o�tf Irf
EA-
t"
yc * V yy ++
Er J s
- C)
C)
a C ? d
a.
to ; r
it oo d
tw 5. tssa w z E
in s Ql
�,. S 8, i Q.
a a
a s a
g m A O 11 II 11 o „ W
3 ei a .. ..,, = � c� m a V
0 M N` N N ••
0 a O
& t0
g 0
0 N
Ofp-
us
N
a0
w Q.
t 1— 0
A n L
t > s. a.
4 m d
8 S e . C
E 9 co a IIIF
I a a 1 t
N c S a 0
a
lit _
1 3 0 2
I v a° .11r
N N a
Packet Pg 778.:
ACA17 a
SCHEDULE B
RATE SCHEDULE
Title Rate
Principal $207.00
Senior Project Manager $173.00
Project Manager $148.00
Senior Engineer $158.00 0
to
Engineer $124.00 ei
Senior Inspector $97.00
Inspector $77.00 v
Senior Planner $140.00 .
Planner $111.00 E
Senior Designer $115.00
cou
Designer $95.00 a
Environmental Specialist $110.00 o
Senior Environmental Specialist $135.00 a.
Scientist/Geologist $94.00 a
Senior Scientist/Geologist $119.00 E
Marine Biologist/Hydrogeologist $111.00 �^
Senior Marine Biologist/Hydrogeologist $139.00 c
L
Senior GIS Specialist $146.00 a
GIS Specialist $103.00 m
Clerical/Administrative $63.00 U
Senior Technician $86.00 co
Technician $73.00 cocsi
Surveyor and Mapper $121.00 —
CAD Technician $82.00 Q.
Survey Crew-2 man $136.00 2
Survey Crew-3 man $172.00 a.
Survey Crew-4 man $205.00 a
Senior Architect $155.00 E
Architect $122.00 0
a
This list is not intended to be all inclusive. Hourly rates for other categories of professional, support and
other services shall be mutually negotiated by Collier County and firm on a project by project basis as
needed.
n
6-1
Packet Pg.779
se (Og'Egb`9g$;uewaoeld;sod `;uawaoeld-aid I'880 : 0906 TdNII 1 oN.IartIO a6uey0 :;uawyoe;;b
co
Qom;
, ^f
uo-
0.
et
��. Y,
...4 _COY Procurement Services a
ns«++o.6a Change Order Form
®Contract Modification ❑Work Order Modification 0 Amendment
Contract#: 16-6629 Change#: 1 Purchase Order*: 45-169684 Project#: 195-90033
Contractor/Firm Name: CB&i Environmental&infrastructure, project Name: 2016 Beach Renourishment
Project Manager Name: .J.Gary McAlpin Department Coastal Zone Management
Original Contract/Work Order Amount $ 1.11,756,30 61213/16 16A:10 Original BCC Approval Date;Agenda Item#
Current BCC Approved Amount $ 111.756.30 6126146 16411 Last BCC Approval Date;Agenda Item#
Current Contract/Work Order Amount $ 111,756;30 6/28/2017 SAP Contract Expiration Date(Master)
I Dollar Amount of this Change $ 86,16350 77.09% Total Change from Original Amount
l Revised Contract/Work Order Total $ 197,909.80 77.09% Change from Current BCC Approved Amount
Cuniilative Changes $ .86,153.50 77.09% Change from Current Amount
Completion Date,Description of the Task(s)Change,and Rationale for the Change
Notice to Proceed 8/19/16 Original 7/21/17 Last Approved 7/21/17 Revised Date 7/21117
Date Completion Date Date (Includes this change) _____
a of Days Added 0 Select Tasks 0 Add new task(s) 0 Delete task(s) 0 Change task(s) ®Other(see below)
Provide a response to the following: 1.) detailed and specific explanation/rationale of the requested change(s) to the lask(s) and I or the
additional days added(if requested);2.)why this change was not included in the original contract;and,3.) describe the impact if this change
is not processed. Attach additional information from the Design Professional and/or Contractor if needed.
1. This change order is to add County approved grant language and the following services to the above mentioned contract: the
pre-placement beach survey,the post-placement beach survey,survey control parameters and quality assurance/quality
control services from the Engineer of Record to manage sand placement on the beach.The addition of these services will not
increase the overall project costs but rather shift costs from the construction contract to the Engineer of Record contract By
doing this we assure better control and Quality Assurance over these services by County Staff.
2. The change being requested was not included in the original contract because in previous beach renourishment projects,this
work has always been included as a task In the construction contract,however,lessons learned from previous truck haul
projects have showed a need for increased coordination between the Engineer of Record and the survey provider,and greater
oversight by county staff.At the time of contract award,staff believed that the Issuance of a new Work Order to perform the
surveys and quality assurance was the appropriate contacting method to order this work. After consultation with the County
Attorneys office,and out of an abundance of caution to adhere to CCNA laws,staff is seeking a change order to the original
Engineer of Record contract In the future we will include these services In the Engineer of Record contract The grant
language and forms were not included In the original contract because of an unintentional oversight Please see the
attachment for additional information.
3. If this modification is not processed the survey control during construction will need to be solely performed by the contractor.
In the past this has led to placement errors and significant rework that could cost the county additional funds. In addition,
quality control would be been compromised. Performance of this change through the Engineer of Record will provide a level
of Quality Assurance required by this project. If grant language/forms are not Included then possible grant reimbursement will
be forfeited,costing the County thousands of dollars.
A j
Prepared by: r r 4 A`�t / Date: 9125//2.Oi ,a
ry M in,P.E.,C Manager
Acceptance of this Change Order shall constitute a modification to contract/work order identified above and will be subject to all the same
terms and conditions as contained in the contract/work order indicated above,as fully as if the same were stated in this acceptance. The
adjustment,if any,to the Contract shall constitute a full and final settlement of any and •rms of the Contractor/Vendor/Consultant./
Design Professional arising out,.ofior relatedeto the change set forth herein,including •-ims impa a del sts.
Approved b : C :.,w� i. 1''�//�"1 III .1 Fri j' ,�
Y (t ,. t wtsu r Oate: Approved r//• iw. Date: 97 1 e.o
Amy Patter>sijen,Division Director savid S.Wilkison,Department Head
Approved by: cn=adamnorthru
Adam Northrup,Procurement Professional p@collicrgov.net
„...."( .._____
Date: 9/29/2016
2016.09.29
'00'04-1.9:07:04 1 1)-
Change Ord
eI�
16-6629-2016 Beach Renourish
(Og'£gG`98$;ueweoeld lsod `;ueweoeld-eJd MEM : 0906 1YNII G oN.tap1O e6uey3 :;uawyoenv
a..
.
IN WITNESS WHEREOF, CB&I Environmental and Infrastructure, Inc. and the County, have
each, respectively, by an authorized person or agent, hereunder set their hands and seals on a'I
the date and year first above written.
BOARD OF COUNTYCOMMISSIONERS
ATTEST: COLLIER COUNTY, FLORIDA
Dwight E. Brock, Clerk of Courts
By: By:
Donna Fiala, Chairman
Dated:
(SEAL)
CB&I Environmental and Infrastructure,
Inc
First Witness
By:
Signature
TType/print witness namet
Thomas P. Pierro, P.E. Director
Second Witness
1Type/print witness namel
Approved as to Form and Legality:
sistant County Attorney
2
Change Order#1
16-6629-2016 Beach Renourishment
.d (09T91.`98$luatueoeld;sod `;uawaoeld-aid 11383 0902) 1YNld I. oN aap.io e6ueg3 :;ueuuyoe;;y N r
09
d tip
a.
9/28/2016-Gary McAlpin :
42)
eo,
Survey and Quality Assurance Management on the 2016 Truck Haul Beach
Renourishment Project
The beaches need to be renourished with a closely coordinated,timely and continuous information
exchange between the Engineer of Record that is responsible for the design and the survey company
hired to perform survey activities during construction.
The initial beach design is performed from a monitoring survey that occurs at the beginning of each
year. Just prior to construction activities a pre-placement survey is performed to modify the design
based on current existing conditions this is done by the Engineer of Record. As construction begins,
progress surveys are required by the Engineer of Record to allow for specific template adjustments that
address specific site conditions and placement concerns/issues. Following construction,a post
placement survey is required by the Engineer of Record.This survey is sent to FDEP in a closeout report.
This is required by permit.
The Engineer of Record is always selected through the RFP process by at least a 5 member Selection
Committee and Approved by the BCC.
With the recent increased usage of Truck Hall projects,survey control and coordination has been found
to be especially critical. The County has purchased the sand and the placement contractor is paid based
on tons delivered to the site. In addition,the sand needs to be placed in such a manner that it remains
on the dry beach and not the intertidal zone. On a Truck Haul project,the quantities of sand placed are
usually much less than a typical cutter head or hopper dredge project. This requires tighter placement
and control procedures. Collier County staff must know how much sand is on the beach and where it is
at any given time. Also,the sand is not"free"as is the case of a dredge project and more care must be
exercised in the placement and transport down the beach. This has been one of the significant lessons
learned by Collier County staff since focusing on Truck Haul construction.
On previous Truck Haul projects,the construction contractor has contracted the survey. With this
method,staff has had no input to the qualifications of the survey contractor,the survey method
(equipment GPS or staking)and has relied on the willingness of the construction contractor to provide
accurate and timely information to the Engineer of Record to manage the fill templates and placement.
Results have been unacceptable to date and a higher level of quality control and quality assurance is
required.
Staff is proposing that the Engineer of Record have these services added through a change order to their
existing contract. The additional work will be to perform the pre-placement survey,the post-placement
survey and provide additional placement quality assurance expertise to manage this process. The
Engineer of Record will provide all critical survey control information to the contractor but the
contractor will be required to set their own grade stakes and manage fill placement using their own
survey control personnel. Staff feels that this method will allow the County to have great control of the
entire process and result in a more successful project.
(09'£g6`98$1uawa3eld1sod `;uauaaoeld-aid 1'88° : 090Z) 1VNld 4 ON Jam aBuey3 :;uauayoe;;y
ar
tsa'
9/28/2016-Gary McAlpin
vl
This approach will not increase the total costs of the project,but rather shift costs from the construction a')
contract to the Engineer of Record contract.
lOSES6 9$$;uawaoeid sod ;uawaoeld-aad I883 09021tlNlA 11. oN Ja O a6ue4� : uew oe
td
ti co
Exhibit X
Supplemental General Grant Terms and Conditions CSFA 37.003
The supplemental conditions contained in this section are intended to cooperate with, to supplement, and
to modify the general conditions and other specifications. In cases of disagreement with any other section
of this contract,the Supplemental Conditions shall govern.
Flow Down of Terms and Conditions from the Grant Agreement
Subcontracts: If the vendor subcontracts any of the work required under this Agreement, a copy of the
signed subcontract must be forwarded to the Department for review and approval. The vendor agrees
to include in the subcontract that (1) the subcontractors is bound by the terms of this Agreement, (ii)
the subcontractor is bound by all applicable state and federal laws and regulations, and (iii)the
subcontractor shall hold the Department and Recipient harmless against all claims of whatever nature
arising out of the subcontractor's performance of work under this Agreement, to the extent allowed and
required by law. The recipient shall document in the quarterly report the subcontractor's progress in
performing its work under this agreement. For each subcontract,the Recipient shall provide a written
statement to the Department as to whether the subcontractor is a minority vendor as defined in Section
288.703,Fla. Stat.
1. Conflict of Interest- This Contract/Work Order is subject to chapter 112, F.S. The vendor shall
disclose the name of any officer, director, employee, or other agent who is also an employee of the State.
Grantee shall also disclose the name of any State employee who owns, directly or indirectly, more than a
five percent(5%) interest in the Contractor's company or its affiliates.
2. Convicted Vendors— Vendor shall disclose if they are on the convicted vendor list. A person or
affiliate placed on the convicted vendor list following a conviction for a public entity crime is prohibited
from doing any of the activities as defined by the Florida Department of Management Services for a
period of thirty-six(36)months from the date of being placed on the convicted vendor list.
3. Discriminatory Vendors
a) No person,on the grounds of race, creed, color, religion, national origin,age, gender, or
disability, shall be excluded from participation in;be denied the proceeds or benefits of; or be
otherwise subjected to discrimination in performance during the term of the contract.
b) Contractor shall disclose if they appear on the discriminatory vendor list. An entity or
affiliate placed on the discriminatory vendor list pursuant to section 287.134, F.S. may not: 1)
Submit a bid on an agreement to provide any goods or services to a public entity; 2) Submit a
bid on an agreement with a public entity for the construction or repair of a public building or
public work; 3)Submit bids on leases of real property to a public entity; or 4)Be awarded or
perform work as a consultant under an agreement with any public entity; or transact business
with any public entity,.
4. Employment Eligibility Verification - Executive Order 11-116, signed May 27, 2011, by the
Governor of Florida, requires contracts to utilize the U.S. Department of Homeland Security's E-Verify
system to verify the employment eligibility of all new employees hired by the vendor during the
Contract/Work Order term and include in all subcontracts under this Contract/Work Order, the
requirement that subcontractors performing work or providing services pursuant to this Agreement utilize
the E-Verify system to verify the employment eligibility of all new employees hired by the subcontractor
1
Est 9/16 v.0
(05'£56`98$Wawaoeld;sod `;uauaaoeld-aid 1'880 : 090Z) 1tlNld 6 oN aapap a6uego :;uewgoe;;y
r•-•co:,
d
t
Exhibit X
Supplemental General Grant Terms and Conditions CSFA 37.003
during the term of the subcontract. a
5. Lobbying-No funds received pursuant to this Agreement may be expended for lobbying the State
Legislature,the judicial branch, or a state agency.
6. Record Retention —The contractor shall maintain and retain sufficient records demonstrating its
compliance with the terms of the Agreement for a period of at least five (5) years after final payment is
made and shall allow the County,FDOT,or its designee's access to such records upon request.
7. Diversity—All contracting and subcontracting opportunities afforded by this solicitation/contract
embrace diversity enthusiastically. The award of subcontracts should reflect the full diversity of the
citizens of the State of Florida. Firms qualifying under this solicitation are encouraged to submit
bids/proposals. Award of this contract will be conditioned upon satisfying the requirements of this bid
specification. These requirements apply to all bidders/offerors, including those who qualify as a Minority
Business vendor. A list of minority owned firms that could be offered subcontracting opportunities may
be obtained by contacting the Office of Supplier Diversity at(850) 487-0915.
8. Indemnity Provision -- Indemnification shall be included in all contracts with
contractors/subcontractors, consultants/sub-consultants who perform work in connection with this
contract.
"The Contractor shall indemnify, defend, save, and hold harmless the Florida Department
of Transportation and all of its officers, agents or employees from all suits, actions,
claims, demands, liability of any nature whatsoever arising out of, because of, or due to
any negligent act or occurrence of omission or commission of the Contractor, its officers,
agents, or employees."
2
Est 9/16 v.0
sa_
Ws-Es V99$luawaoeld;sod luawaoeld-aid I'880 : 0906 1YNII 1. ON iapi0 a6uey.D :;uawy3e14V
eQ`
ti as
44
coo' a`
COLLIER COUNTY
Certification Regarding Lobbying
The undersigned CB&I Environmental &Infrastructure, Inc. (Vendor/ Contractor) certifies, to the best of
his or her knowledge and belief,that:
(1) No State appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any
person for influencing or attempting to influence an officer or employee of an agency, a member of the
Legislature, an officer or employee of the judicial branch, or an employee of a State agency in connection
with the awarding of any State contract, the making of any State grant, the making of any State loan, the
entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or
modification of any State contract, grant, loan, or cooperative agreement.
(2) No grantee, nor its persons or affiliates, may employ any person or organization with funds received
pursuant to any State agreement for the purpose of lobbying the Legislature, the judicial branch, or a State
agency. The purpose of lobbying includes, but is not limited to, salaries, travel expenses and per diem, the
cost for advertising, including production costs; postage; entertainment; and telephone and telegraph; and
association dues. The provisions of this paragraph supplement the provisions of section 11.062, Florida
Statutes,which is incorporated by reference into this solicitation, purchase order or contract.
(3)The undersigned shall require that the language of this certification be included in the award documents
for all subawards at all tiers (including subcontracts, subgrants, and contracts under grants, loans, and
cooperative agreements) and that all subrecipients shall certify and disclose accordingly.
The Vendor/Contractor, CB&I Environmental&Infrastructure, Inc. , certifies or affirms the truthfulness and
accuracy of each statement of its certification and disclosure, if any. In addition,the Contractor understands
and agrees that the provisions of 11.062, Florida Statutes., apply to this certification and disclosure, if any.
Thomas P. Pierro Name of Authorized Official Director of Operations Title
Signature of Vendor/Contractor's Authorized Official
9/29/16 Date
02/15 R3
(09"c9V98$;uauaaoeid;sod `;uauaaoeld-aid I'880 090Z) WNW I. ON iapiO a6ue43 :;uauiyoe;;v
co
th
COLLIER COUNTY sv
Acknowledgement of Terms, Conditions,and Grant Clauses
Flow Down of Terms and Conditions from the Grant Agreement
Subcontracts: If the vendor subcontracts any of the work required under this Agreement, a copy of the
signed subcontract must be available to the Department for review and approval. The vendbr agrees
to include in the subcontract that (1) the subcontractor is bound by the terms of this Agreement, (ii) the
subcontractor is bound by all applicable state and federal laws and regulations, and (iii)the subcontractor
shall hold the Department and Recipient harmless against all claims of whatever nature arising out of the
subcontractor's performance of work under this Agreement, to the extent allowed and required by law.
The recipient shall document in the quarterly report the subcontractor's progress in performing its work
under this agreement. For each subcontract, the Recipient shall provide a written statement to the
Department as to whether the subcontractor is a minority vendor as defined in Section 288.703, Fla. Stat
Certification
On behalf of my firm, I acknowledge, and agree to perform all of the specifications and grant
requirements identified in this solicitation document(s).
Vendor/Contractor Name CB&I Environmental&Infrastructure, Inc. Date 9/29/16
Authorized Signature. ( .----714(1.
Address 2481 NW Boca Raton Blvd., Boca Raton,FL 33431
Solicitation/Contract# 16-6629
02/15 R3
,00•1
.0 (05'£56`98$luauaaoeld;sod `;uauaaoeld-ead 1'883 : 0902) TdNII I.ON JapJ)a6uey3 :;uauayoemf
7„!= xr00o
�.` ;
.32
COLLIER COUNTY =a,
Certification Regarding Debarment, Suspension,and Other Responsibility Matters
Primary Covered Transactions
(1) The prospective primary participant certifies to the best of its knowledge and belief, that it and its
principals:
(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily
excluded from covered transactions by any Federal department or agency;
(b) Have not within a three-year period preceding this proposal been convicted of or had a civil
judgment rendered against them for commission of fraud or a criminal offense in connection with
obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or
contract under a public transaction; violation of Federal or State antitrust statutes or commission of
embezzlement,theft, forgery, bribery,falsification or destruction of records, making false statements,
or receiving stolen property;
(c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity
(Federal, State or local) with commission of any of the offenses enumerated in paragraph (I)(b) of
this certification; and
(d) Have not within a three-year period preceding this application/proposal had one or more public
transactions(Federal, State or local)terminated for cause or default.
(2) Where the prospective primary participant is unable to certify to any of the statements in this
certification,such prospective participant shall attach an explanation to this proposal.
Thomas P. Pierro 2016 Beach Renourishment Design
Name Project Name
Director of Operations 16-6629
Title Project Number
CB&I Environmental&Infrastructure, Inc. 77-058-9932
Firm Tax ID Number
04-347-6810
DUNS Number
2481 NW Boca Raton Blvd.,Boca Raton,FL 33431
Street Address,City, State, Zi
&. ,,,,_.116:7____
Signature
03/04/2013-(2)
1
(09•ESi,`99$;uawe eld;sod `;uewaaeld-aid I'880 090Z) 1VNld 6 oN aapi0 e6ue40 :;uauayae;;d .
OP-
441
COLLIER COUNTY ✓'••,.,
ANTICIPATED DISADVANTAGED, MINORITY,WOMEN OR VETERAN PARTICIPATION STATEMENT
:a )Status will be verified. Unverifable statuses will require the PRIME to either proivde a revised statement or provide source documentation that validates a
status.
A- .PRIME.VENDOR/CONTRACTOR:INFORMATION
PRIME NAME PRIME FEID NUMBER CONTRACT DOLLAR AMOUNT
CB&I Environmental&Infrastructure,Inc. 77-058-9932 TBD
IS THE PRIME A FLORIDA-CERTIFIED DISADVANTAGED, VETERAN Y J.(siNk IS THE ACTIVITY OF THIS CONTRACT...
MINORITY OR WOMEN BUSINESS ENTERPRISE? DBE? Y N CONSTRUCTION? Y `.J
(DBE/MBE/WBE)OR HAVE A SMALL DISADVANTAGED
BUSINESS 8A CERTIFICATION FROM THE SMALL BUSINESS MBE? Y N CONSULTATION?
ADMINISTRATION? A SERVICE DISABLED VETERAN? WBE? Y Nj OTHER?
`Y /
SDB8A? Y NI'
IS THIS SUBMISSION A REVISION? Y (IC) IF YES,REVISION NUMBER
B. IF PRIME HAS SUBCONTRACTOR OR SUPPLIER WHO IS A DISADVANTAGED MINORITY,WOMEN OWNED,SMALL
BUSINESS CONCERN OR SERVICE DISABLED VETERAN,PRIME I5 TO COMPLETETHIS NEXJ SECTION
DBE M/WBE SUBCONTRACTOR OR SUPPUER TYPE OF WORK OR ETHNICITY CODE , SUB/SUPPUER PERCENT OF CONTRACT
VETERAN NAME SPECIALTY (See Below) DOLLAR AMOUNT DOLLARS
TOTALS:
C SECTION TO BECOMPLEEED BY.PRIMEVENDOR/CONTRACTOR
NAME OF SUBMITTER DATE TITLE OF SUBMITTER
Thomas P.Pierro (.. 11/14"` 9/29/16 Director of Opeations
EMAIL ADDRESS OF PRIME(SUBMITTER) TELEPHONE NUMBER FAX NUMBER
thomas.pierro@cbi,com 561.361.3150 561,391.9116
NOTE:This information is used to track and report anticipated DBE or MBE participation in federally-funded contracts.The anticipated DBE or
MBE amount is voluntary and will not become part of the contractual terms. This form must be submitted at time of response to a
solicitation. If and when awarded a County contract,the prime will be asked to update the information for the grant compliance files.
Black American BA
Hispanic American HA
• •Native American NA`
Subcont.Asian American SAA
Asian-Pacific American " APA
Non-Minority Women NMW
Other:not of any.other: ou•listed 0'' •
D SECTION TO BE COMPLETED BY COLLIER COUNTY
DEPARTMENT NAME COLDER CONTRACT it IIFB/RFP or PO/REO) . GRANT PROGRAM/CONTRACT
ACCEPTED BY: DATE /'\
Est.2010 v.2
.q (05'E56`98$;uowooeld;sod `;ueweoeld-aid 1'89D : 0906 1VNIA I. oN aapao a6ue43 :;uauayoeny
t- ti
4. a
toy' 0.
COLLIER COUNTY _
Vendor Submittal—Conflict of Interest Certification
16-6629
Collier County Solicitation No.
1, Thomas P. Pierro , hereby certify that to the best of my
knowledge, neither 1 nor my spouse, dependent child, general partner, or any organization for
which I am serving as an officer, director, trustee, general partner or employee, or any person or
organization with whom I am negotiating or have an arrangement concerning prospective
employment has a financial interest in this matter.
I further certify to the best of my knowledge that this matter will not affect the financial interests
of any member of my household. Also,to the best of my knowledge, no member of my
household; no relative with whom I have a close relationship; no one with whom my spouse,
parent or dependent child has or seeks employment; and no organization with which I am
seeking a business relationship nor which I now serve actively or have served within the last
year are parties or represent a party to the matter.
I also acknowledge my responsibility to disclose the acquisition of any financial or personal
interest as described above that would be affected by the matter, and to disclose any interest I,
or anyone noted above, has in any person or organization that does become involved in, or is
affected at a later date by, the conduct of this matter.
Name Signature
Thomas P. Pierro
Position Director of Operations Date 9/29/16
Privacy Act Statement
Title I of the Ethics in Government Act of 1978 (5 U.S.C. App.), Executive Order 12674 and 5 CFR Part 2634,
Subpart I require the reporting of this information. The primary use of the information on this form is for review by
officials of The Justice Department to determine compliance with applicable federal conflict of interest laws and
regulations.Additional disclosures of the information on this report may be made: (1)to a federal, state or local law
enforcement agency if the Justice Department becomes aware of a violation or potential violation of law or
regulations; (2) to a court or party in a court or federal administrative proceeding if the government is a party or in
order to comply with a judge-issued subpoena; (3) to a source when necessary to obtain information relevant to a
conflict of interest investigation or decision; (4)to the National Archives and Records Administration or the General
Services Administration in records management inspections; (5) to the Office of Management and Budget during
legislative coordination on private relief legislation; and (6) in response to a request for discovery or for the
appearance of a witness in a judicial or administrative proceeding, if the information is relevant to the subject matter.
This confidential certification will not be disclosed to any requesting person unless authorized by law. See also the
OGE/GOVT-2 executive branch-wide Privacy Act system of records.
X (0s'£s6`92$;ueuaaoeld;sod `;uatmeoeld-ead P993 : 090Z) 1VNIJ I. oN Jam a6ueL3 :;uauayoe IV
`4t,
cod'; "at.
, a
CONSTRUCTION CONTRACTORS .
BID OPPORTUNITY LIST aS
1. Federal Tax ID Number: 77-058-9932 6. ❑ DBE 8. Annual Gross Receipts
2. Firm Name: CB&I Environmental&Infrastructure,Inc. ❑x Non-DBE ❑ Less than$1 million
3. Phone: 561.361.3150
0 Between$1 -$5 million
4. Address: 2481 NW Boca Raton Blvd. 0 Between$5-$10 million
Boca Raton,FL 33431 7, ❑ Subcontractor 0 Between$10-$15 million
O Subconsultant 0 More than$15 million
5. Year Firm Established: 2002
1. Federal Tax ID Number: 6. ❑ DBE 8. Annual Gross Receipts
2. Firm Name: El Non-DBE 0 Less than$1 million
3. Phone: 0 Between$1 -$5 million
4. Address: 0 Between$5-$10 million
7. 0 Subcontractor ❑ Between$10-$15 million
❑ Subconsultant 0 More than$15 million
5. Year Firm Established:
1. Federal Tax ID Number: 6. 0 DBE 8. Annual Gross Receipts
2. Firm Name: ❑ Non-DBE 0 Less than$1 million
3. Phone: 0 Between$1 -$5 million
4. Address: 0 Between$5-$10 million
7. 0 Subcontractor 0 Between$10-$15 million
❑ Subconsultant 0 More than$15 million
5. Year Firm Established:
1. Federal Tax ID Number: 6. ❑ DBE 8. Annual Gross Receipts
2. Firm Name: 0 Non-DBE 0 Less than$1 million
3. Phone: 0 Between$1 -$5 million
4. Address: 0 Between$5-$10 million
7. 0 Subcontractor 0 Between$10-$15 million
❑ Subconsultant 0 More than$15 million
5. Year Firm Established:
1. Federal Tax ID Number: 6. ❑ DBE 8. Annual Gross Receipts
2. Firm Name: ❑ Non-DBE 0 Less than$1 million
3. Phone: 0 Between$1 -$5 million
4. Address: 0 Between$5-$10 million
7. 0 Subcontractor ❑ Between$10-$15 million
❑ Subconsultant 0 More than$15 million
5. Year Firm Established:
/'\
- (05'£56`98$;ueweoeld;sod luawaoeld-aJd 119130 : 090Z) 1VNld I.ON Jam 96ue40 :;uawyoe;;b
CONSTRUCTION CONTRACTORS
BID OPPORTUNITY LIST
1, Federal Tax ID Number: 6. ❑ DBE 8. Annual Gross Receipts
2. Firm Name: 0 Non-DBE ❑ Less than$1 million
3. Phone: El Between$1 -$5 million
4. Address: ❑ Between$5-$10 million
7. 0 Subcontractor ❑ Between$10-$15 million
0 Subconsultant ❑ More than$15 million
5. Year Firm Established:
1, Federal Tax ID Number: 6. 0 DBE 8. Annual Gross Receipts
2. Firm Name: ❑ Non-DBE ❑ Less than$1 million
3. Phone: 0 Between$1 -$5 million
4. Address: ❑ Between$5-$10 million
7. 0 Subcontractor ❑ Between$10-$15 million
❑ Subconsultant 0 More than$15 million
5. Year Firm Established:
1. Federal Tax ID Number: 6. ❑ DBE 8. Annual Gross Receipts
2. Firm Name: ❑ Non-DBE 0 Less than$1 million
3. Phone: 0 Between$1 -$5 million
4. Address: El Between$5-$10 million
7. ❑ Subcontractor ❑ Between$10-$15 million
0 Subconsultant ❑ More than$15 million
5. Year Firm Established:
1. Federal Tax ID Number: 6. ❑ DBE 8. Annual Gross Receipts
2. Firm Name: ❑ Non-DBE ❑ Less than$1 million
3. Phone: ❑ Between$1 -$5 million
4. Address: 0 Between$5-$10 million
7, ❑ Subcontractor ❑ Between$10-$15 million
❑ Subconsultant ❑ More than$15 million
5. Year Firm Established:
1. Federal Tax ID Number: 6. ❑ DBE 8. Annual Gross Receipts
2. Firm Name: 0 Non-DBE ❑ Less than$1 million
3. Phone: ❑ Between$1 -$5 million
4. Address: 0 Between$5-$10 million
7, 0 Subcontractor 0 Between$10-$15 million
❑ Subconsultant ❑ More than$15 million
5. Year Firm Established: