Agenda 05/24/2016 Item #16D10 5/24/2016 16.D.10. EXECUTIVE SUMMARY Recommendation to approve change order #1 to McGee & Associates for safety improvements associated with the design plans to the sidewalk/pathway connecting the Collier County beach parking lot at the end of Seagate Drive to the North Gulf Shore Boulevard beach access for $5,140 and make a finding that this expenditure promotes tourism. OBJECTIVE: To seek the change order to reflect the pedestrian and bicycle improvements that are consistent with community input. CONSIDERATIONS: On November 23, 2015, the Tourist Development Council approved three (3) Work Orders for the design of landscape enhancement at three(3) locations:North Gulf Shore Boulevard Beach Access, South Marco Beach Access Parking Lot, and South Marco Beach Access Boardwalk and Landscape to McGee & Associates, utilizing a Board approved contract 12-5892 —"Fixed Term Landscape Architectural Services." The County has received a number of public requests for safety improvements to the sidewalk/pathway connecting the North Gulf Shore Boulevard Beach Access to the Collier County beach parking lot located at the west end of Seagate Drive. The issue is that the narrow, 4.75 foot, sidewalk/pathway that is highly utilized by visitors result in conflicts between walkers and bikers sharing the much used connection. Preliminary community input was obtained from staff with the City of Naples, Naples Cay, Seagate Home Owners' Association (HOA) and Gulf Shore Association of Condominiums (GSAC). There is general agreement that widening and making improvements will resolve the conflict and improve public safety. The improvements will also provide capacity, encourage bikers and walkers to safely use the access point to the beach, and provide additional width for the sidewalk. The construction of the sidewalk/pathway will be solicited separately. The Parks and Recreation staff reviewed the proposal and recommends proceeding with this change order. If approved, Change Order #1 will allow staff to work closely with the neighborhoods identified above to design a consensus plan that reflects greater input from the community for these improvements. TDC RECOMMENDATION: On March 28, 2016, the Tourist Development Council approved the change order#1 to McGee &Associates and expenditure of funds with a recommended finding that this expenditure promotes tourism by unanimous vote (8-0). FISCAL IMPACT: Funding in the amount of$5,140 is budgeted from the Parks and Recreation Beach Park Facilities Capital Fund 183 (TDC Beach Parking Facilities), Project No. 80335 —North Gulf Shore Access. GROWTH MANAGEMENT IMPACT: There are no Growth Management Impacts associated with this action. LEGAL CONSIDERATIONS: This item has been approved as to form and legality and requires majority vote for approval.—CMG RECOMMENDATION: That the Board: 1. Approves change order#1 to McGee & Associates in the amount of$5,140 and make a finding that this expenditure promotes tourism. Prepared by:Vicky Ahmad,Project Manager,Facilities Management Division Attachments: 1.Change Order#1/2.Proposal/3.Concept Plan Packet Page -870- 5/24/2016 16.D.10. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.D.16.D.10. Item Summary: Recommendation to approve change order#1 to McGee &Associates for safety improvements associated with the design plans to the sidewalk/pathway connecting the Collier County beach parking lot at the end of Seagate Drive to the North Gulf Shore Boulevard beach access for$5,140 and make a finding that this expenditure promotes tourism. Meeting Date: 4/12/2016 Prepared By Name: AhmadVicky Title: Project Manager,Facilities Management 3/10/2016 8:22:31 AM Submitted by Title:Project Manager,Facilities Management Name: AhmadVicky 3/10/2016 8:22:32 AM Approved By Name: JonesHank Title: Project Manager,Principal,Facilities Management Date: 3/11/2016 2:21:25 PM Name:pochopinpat Title: Operations Coordinator,Administrative Services Department Date: 3/11/2016 2:38:04 PM Name: LinguidiDennis Title:Division Director-Facilities Mgmt,Facilities Management Date: 3/14/2016 11:16:00 AM Name: WilliamsBarry Title:Division Director-Parks&Recreation,Parks&Recreation Date: 3/15/2016 9:38:19 AM Packet Page -871- 5/24/2016 16.D.10. Name: BetancurNatali Title: Operations Analyst,Parks&Recreation Date: 3/15/2016 2:26:12 PM Name: MarkiewiczJoanne Title: Division Director-Procurement Services,Procurement Services Date: 3/18/2016 10:31:44 AM Name: JohnsonScott Title: Manager-Procurement,Procurement Services Date: 3/18/2016 2:07:56 PM Name: BurnsRhonda Title:Procurement Specialist,Procurement Services Date: 3/22/2016 4:33:12 PM Name: CarnellSteve Title: Department Head-Public Services,Public Services Department Date: 3/30/2016 9:42:55 AM Name: GreeneColleen Title:Assistant County Attorney,CAO General Services Date: 3/30/2016 12:10:04 PM Name: KlatzkowJeff Title: County Attorney, Date: 3/30/2016 3:18:12 PM Name: FinnEd Title:Management/Budget Analyst, Senior, Office of Management&Budget Date:4/4/2016 6:12:42 PM Name: OchsLeo Title: County Manager, County Managers Office Date: 4/5/2016 10:13:36 AM Packet Page -872- 5/24/2016 16.D.10. Cc e-r County Procurement Services Change Order Form 0 Contract Modification a Work Order Modification 0 Amendment Contract#: 12-5892 Change#: 1 Purchase Order#: 4500164682 Project#: 80335 Contractor/Firm Name: Mc Gee&Associates contract/Project 12-5892/80335 t'~`tfs� '� tdd t3�=ukftcr Project Manager Name: Vicky Ahmad Division Name: Facilities Management Original Contract/Work Order Amount $ 3,730.00 N/A Original BCC Approval Date;Agenda Item# Current BCC Approved Amount N/A N/A Last BCC Approval Date;Agenda Item# Current Contract/Work Order Amount $ 3,730.00 9/10/2016 SAP Contract Expiration Date(Master) Dollar Amount of this Change $ 5,140,00 137.80% Total Change from Original Amount Revised Contract/Work Order Total $ 8,870.00 *VALUE! Change from Current BCC Approved Amount Cumulative Changes $ 5,140.00 137.80% Change from Current Amount I4 Completion Date.Description of the Task(s)Change,and Rationale for the Change Notice to Proceed 1211/2015 Original 12/6/15 Last Approved 11/23/15 Revised Date t•Jt/A Date Completion Date Date (Includes this change) #of Days Added 0 Select Tasks II Add new task(s) 0 Delete task(s) 0 Change task(s) 0 Other(see below) Provide a response to the following: 1.)detailed and specific explanation/rationale of the requested change(s)to the task(s)and I or the additional days added(if requested);2,)why this change was not included in the original contract;and,3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed. 1. Contract 12-5892—Fixed Term Landscape Architectural Services with Mcgee&Associates initial scope of work was to prepare the professional landscape architectural services to enhance the landscaping for the Gulf Shore Blvd. North to Seagate Drive beach access walkway. Public input into the project revealed a need to address the conflict between walkers and bikers safety in the area connecting the Collier County parking lot located at the west end of Seagate Drive to the west end of Gulf Shore Drive North cul-de-sac. This change order will provide design plans to address the safety concerns and improve the narrow 4.75 feet existing shared sidewalk/pathway for bikers and walkers going to the beach. 2. The original scope of work was for landscape enhancement at Gulf Shore Boulevard North to the Seagate Drive beach access walkway; this change order is the result of public input received by staff during the design of landscaping. 3. If this change is not processed,walkers and bikers will continue to use the same narrow width of sidewalk/ pathway that exist. The safety improvements of the project will not be realized. / ,r Prepared by:_Vicky Ahmad, Facilities Management Division Date:— 3,y ee i i!'' (Project Manager Name and Division) it Acceptance of this Change Order snail constitute a modification to contract/work order identified above and will be subject to all the same terms and conditions as contained in the contract/work order indicated above,as fully as if the same were stated in this acceptance. The adjustment,if any,to the Contract shall constitute a full and final settlement of any and ail claims of the Contractor!Vendor/Consultant/ Design Professional arising out of or related to the change set forth herein,including claims for impact and delay costs. Accepted by:_Mike'McGee,McGee&Associates - � Date: 3//6//4./Co itant/�-sib,Profen' Hata.al,.. -ame o imp,if project applicable) ....../7 Approved by:_Rhonda Cummings 1f .7% --= Date: (Procurement Proles ions I) (Divisions who may require additional signatures may include on separate sheet.) Revised: 10/28/2014 0 Packet Page-873- 5/24/2016 16.D.10. IN WITNESS WHEREOF,the parties have each,respectively,by an authorized person or agent,have executed this Amendment on the date(s)indicated below. Accepted: ,20_ Dwight E.Brock,Clerk OWNER: BOARD OF COUNTY COMMISSIONERS BY: OF COLLIER COUNTY,FLORIDA Contractor's First Witness: By: Donna Fiala, Chairman By: Signature CONTRACTOR: name of company Print Name By: Contractor's Second Witness: Signature By: Print Name and Title Signature Print Name roved as to Form and Legality: ssistant County Attorney Change Order#1—Contract 12-5892,PO#4500164682 Page 2 0 Packet Page-874- 5/24/2016 16.D.10. J 6G►ee & Adoeletted Landscape Architecture February 4, 2016 Ms.Vicky Ahmad, Project Manager Collier County Administrative Services Division Facilities Management Department 3335 Tamiami trail East, Suite 101 Naples, Florida 34112 Subject: Proposal of Landscape Architectural Services for Modifications to Hardscape Improvements to Gulf Shore Blvd. North to Seagate Dr. Beach Access Walkway per Contract No. 12-5892, (M&A 2016-003P) Dear Ms. Ahmad: As requested McGee&Associates is providing the following proposal for your review and approval. McGee&Associates(M&A)agrees to provide services for the landscape, hardscape and irrigation renovation design and contract administration as generally described in the following"Scope of Services" for the above listed project. Scope of Services Task 1.1 -Planning Review County's existing landscape and irrigation"Record Drawings"for preparation of proposed plans. Perform site review to verify locations of existing materials and irrigation system. 1.1.1 Site Observation 1.1.2 Review existing plans and provide field confirmation of existing conditions 1.1.3 Research&Review of existing permit documents 1.1.4 Base plan development-Update base plan for project areas Task 2.1 -Final Hardscape Design Prepare hardscape renovation plans per applicable Collier County Right of Way Ordinance and Land Development Code requirements and per requested program elements. 2.1.1 Meetings &Correspondence:Attend necessary staff and/or project on-site meetings for the project design development and provide required written correspondence, verbal communications or presentations for the project development. 2.1.2 Concept&Design Development: To minimally include items or services as follows: a. Alternate concept layouts for presentation purposes. b. Materials Tabulation of Quantities, bid schedule containing, quantities, sizes&specifications. c. Hardscape paving installation details and notes as identified or as applicable. d. Site features details and specifications. 2.1.3 Construction Drawings: Prepare plans to County approved bidding and installation construction drawings and specifications for exhibits or attachments to the final Contract Documents. 2.1.3 Opinion of Costs: Develop opinion of costs related to the approved final drawings. Design * Environmental Management * planning * Arborist 5079 Tamiami Trail East/P.O. Box 8052 Naples,Florida 34101 Phone (239) 417-0707* Fax (239) 417-0708 LC 098*FL 1023A Packet Page-875- 5/24/2016 16.D.10. Page Two—2/4/2016 Renovation N GulfShore Bch Access Walkway Proposal#2016-003P Schedule of Work Design services will be completed within 30 days from the date of the Notice to Proceed. Contract Administration services to be determined based upon bidding and construction dates. Compensation Task 1.1 $ 1,385.00 Task 2.1 $ 3,755.00 Total Fee: $ 5,140.00 Vied:4 LeG / 7114ee Michael A. McGee, r.l.a. President, McGee&Associates. LCC000098 Packet Page -876- 5/24/2016 16.D.10. 0 0 0 0 0 0 0 0 7 0 4 e' 0 0 0 0 0 0 0 0 o P ,o .. o E w `530 $ LA0 $ uwiLLA U) v, Z N w g W w sr '- 0 N CD 1, a•? C Q. J t• it W is.VI' CD EE 4 ° t E � � .. N O J O2- 2 J N 5.. 0-0 'O 0 2 t . t 0 N w 'mkt" `t l' 6h N N t,r I Z Z z �i 0 , 0w �t JH Z N W .9 V. 10 M Y9 va w .9 opf p i'3', T 0 8 8 8 0 0 8 8 8 8 0 , N H W w w us r N W '. w W w kg, 1 W Zd .3 4Cn I Om T W S s:' p ;pt�a�b�tt . ha Q O W 8 8 8 0 8 8 8 8 C Q: J 6 U H H a ta 6; 2 IR a» IR r, N 0 oLL w w us «n .n u1 � M U &o O N 0- i w a� (tSOp d 3 J °()N U ? y o o o �f ui Q 0N1Nd oya = Vit( -. y _. U ..., to 0 0 0 0 , 0 0 0 0 0 0 I� OE-Wll! 0000 8"' o000 otq, 0000 o006 ap .ki Z U F r W g W . . y,' N N W N N w O NI Wd I- ow s a wN; ww �.o- m fo Oa. ma LL 0 z _�( O x o 0 0 w o w w ,- ,a, 1- U m 7 (n (n ¢ 1- = p p tO p pO Irv; W U JY 8 8 0 0 8 8 8 8 0 r0 t 6,�r 661 0 r Z IoW e., Mc9 ., w o o w o 1{} I.I. w a•• to g ui LL N M �» en N' t9 ;ft- M., W M '�. in M ;N�,„ CI m -oi E a U r M ii}. E u, _ .yy. N 0 _ M tD r w w X46 '(y N. Q m z cc n o U` a g a `g n.J O Q 0 p 2'd N N C7 c E X 'DUO NE Z c o 7 N W-O w t 7 pg.' Nc 2 1'N . m .pZT@ O U Z' wdm N Q U U Z ; n0 ` IPG " F- O ims °' m aO ill L oMO - U dpcF•• ZNi= COJO Qmcgi6Oa N d J7 W Q F2 N O.L tp - 0 C N .2-. O - WZZ.J I N (� a .2' C C . N - O2- LL W °a Z Irm 2 ° U °o4NJ4 Z y - N M N Z .CQ q C. 00 N N it O d ni t i N ci w Ai a. �J 0 1— N I- 0 0 Q •N O L 7 CD Z O CL M O O thO N Packet Page -877- • Al,4dales°,, 5/24/2016 16.D.1 9. e�,..�,n v Ow,�� .,,,r._,,,....,,, .,_. o.x en,ua>!vu�vrado�sPuo1 J.11 1� j�� O�O�/J �� 0 T. ; J ;%1.�� ""r"• D� ✓M,.J '/"� \ NOISI/xld NOIlH3b73T� Y 5�2IVd r� W Ll `/I//f//�� /'/`A'(/A f�/�//1//�� NOISIh IO iN3W39VNVW 531lIOVd `�z J.1Nf100?�31fi00 /� ilio[.0.AWP V 1..0.33 d0 4CGSI tauaw ail IIIOXIM caw 3p 1v1e m 4134040444341 zA 031400 E AYR mama EDIT 40 13/Id oil 'I 3!'JISiO 344.d0*1413 040 Iwlwam 3LL MIR3x 5oI33Va0 1vONp3I 310 53IV3d EDu __\\ I CO 4 =O 5 m / \ f.- 0° p O m a-Z 1 z ¢¢ a -w 2w _ o ', Y Q JCC go< . u) w § / \� o � w m w w wm xs> asp �= 3 I 53 j �� � ori I o_ F Q Qy wo �w a� a� ink 71 N� w w o m U' Q d i ,.,1-z w} rsy \-l%1 175 " ? w w w z� zZ z J Urx v� waw s `_ _�� z ~ OLL �� wy wo wz O0U 0-, 0aw 1 a� Q ¢N ., o_, Occ Q 02 OLiE 01111— ....0_. 1 Dzr ��� I I W o , Uw gz o o> LI) 0410 ¢wo e"pf - oQ o o, > Oa� �� ago �� o J ? ?¢ ?� da as a2¢a a?g I /� 1 o U Z 3 (moo a o �' Q 'r-0 1 • I / / �\ > ,. :--i �� I d v— ,,,. — __Ji_,, ,„ iw 41 Ti],1 Vl� a , Z Z ———— �, ��r LINO p1`././:(v W W ---1=\1. Iwo Ii i Atz y >\c�3\�—. F. m m 11 S'SY" 111;1 I.E!,Fe.i ''R S. wg; I / Y 2 dg gg 7.1.4_414?1,r17\ / _ <wdm I ° 0 lok w a o0 Z z ; 1k1i AO,' ♦�9� i � O m 0 0¢O $� `oma rcu ��l ;; �, a1 I rw a WL. as z w r' l o u 8 x >u. w �i Wes i _ 3° i �m� O > �/ rco i. T I`ve, -t-; : �I { 5 =o4a.ig z, w Q "IOW J,gw l i I' 1°w�;=Fs ao sh L z d3 liFq1 9 Y n?:e eileBOLL i e .. 6` r /8 `J l • 2 x1w / WPI dI ' e /F5 V �H S31V'J iNJVViS °�' ,.,3i '' pQ a /--�.`Gt((.F' // /L E_ =o a 2 1341101 3 I W /'�y / 7 /11 I Zco a i " 3 „ 4Q,/��--FAS / /i, Z Z 4450 41rc ODaI a , •\ h ]//oo?/ ‘;0 �_ C� waQ W \',1 #a " '�''''U> '\ // P \\ M W x u •1,r� f / I— k, e ,.,--,4-,,,+. toe i,��p• „dr, �/ ^ ,4,44,1-,,,,,.. , ,s„,,,,, , cf.1 .. •,,,/ 2 e,.it,L Iri, ,c+.,`,7J,, -.,,,',,,,,,,. t+, 2.2 - g,. 8 8 6 4 1', yre • iW z- Gyf' . n I vYI °Fw l y x I 0 °z \ /� $ L— ¢ zII xzw4 V • 1EI \ o 1 g - � ZZsi \ ��°"a a,,, i , z k - _� " 1 " s• ; � t iu / V -oFG 3 I ��� I 101 �/ • v\VI „GO Ac�����E Q 1 1: k 7 \ W. '" "� f1ALL Ry ar 1 II!gl �.I w \ 0 o v ��I i-I48o, 6111 ;�c �y^, n � \ O>< \ I o° ia., yKyVV.,1 a \ ,...f_U w )� _ e Packet Page-878- J