Agenda 06/14/2016 Item #16D 6 6/14/2016 16.D.6. EXECUTIVE SUMMARY Recommendation to approve and authorize the Chairman to execute Change Order number one to Wright Construction Corporation to upgrade the proposed Pickleball Courts surface at Veterans Community Park and authorize necessary budget amendments. (Fiscal Impact$36,832.85) OBJECTIVE:To upgrade the proposed Pickleball Court surface at the Veterans Community Park. CONSIDERATIONS: Pursuant to Contract 14-6307, staff awarded a work order, in the amount of $198,751.56, on February 24, 2016 to Wright Construction Corporation to convert the sand volleyball courts at Veterans Community Park into Pickleball Courts. The construction of the courts is complete, however the court surface remains to be installed. The work order provided two line items for court surfaces products: Deco Color Textured Acrylic Color Surfacing ($28,132.42) and a bid alternate to additional laying through the DecoTurf 6 Layer Cushion System($33,618.60).The Parks and Recreation Division originally accepted the less expensive product DecoColor Textured Acrylic Color Surfacing due to budgetary constraints; however, after further review and input from local pickleball enthusiasts, the additional layering provides a tournament quality surface that is more durable and requires less maintenance. The more expensive bid alternate was selected after the initial work order was issued necessitating a change order and due to market material increase in cost is$36,832.85. FISCAL IMPACT: Initially the project was budgeted in the Parks Impact Fee Fund 346 for $211,890.20; however, since this project is converting existing courts to pickleball courts, budget amendments are needed to move and to properly account for this improvement in the Parks Capital Improvement Fund (306). The budget amendment will establish the Veteran's Park Pickleball project 80284 budget of $211,890.20 plus the above change order of $36,832.85, total amount of the budget amendment will be $248,723.05. Funding will be from recognizing an insurance refund of$28,939 plus $195,663.23 in residual budget from the completed Gordon Greenway project 80065 and $24,120.82 from the Immokalee Sports Complex renovations project 80320. The Immokalee Sports Complex is not construction ready at this time but is scheduled for construction in FY 17. In the FY17 proposed budget, staff reallocate funds back to the Immokalee Sports Complex. GROWTH MANAGEMENT IMPACT: There is no impact to the Growth Management Plan related to this action. LEGAL CONSIDERATIONS: This item has been approved as to form and legality and requires majority vote for approval.—CMG RECOMMENDATION: That the Board of County Commissioners approves and authorizes the Chairman to execute Change Order #1 to Wright Construction Corporation to upgrade the proposed Pickleball Courts surface at Veterans Community Park and authorize all necessary budget amendments. Prepared by:Margaret A.Bishop,P.E., Senior Project Manager,Facilities Management Division Attachments: 1. Change Order#1 2. Project No. 80284 Work Order Packet Page -1019- 6/14/2016 16.D.6. COLLIER COUNTY Board of County Commissioners Item Number: 16.16.D.16.D.6. Item Summary: Recommendation to approve and authorize the Chairman to execute Change Order number one to Wright Construction Corporation to upgrade the proposed Pickleball Courts surface at Veterans Community Park and authorize necessary budget amendments. (Fiscal Impact$36,832.85) Meeting Date: 6/14/2016 Prepared By Name: BishopMargaret Title: Project Manager, Senior,Facilities Management 5/9/2016 4:45:16 PM Submitted by Title: Project Manager, Senior,Facilities Management Name:BishopMargaret 5/9/2016 4:45:17 PM Approved By Name: Washburnllonka Title: Manager-Park Operations,Parks&Recreation Date: 5/10/2016 10:00:55 AM Name: LinguidiDennis Title: Division Director-Facilities Mgmt,Facilities Management Date: 5/10/2016 3:08:46 PM Name: JonesHank Title:Project Manager,Principal,Facilities Management Date: 5/10/2016 6:24:44 PM Name:BurnsRhonda Title:Procurement Specialist,Procurement Services Date: 5/11/2016 9:58:16 AM Packet Page -1020- 6/14/2016 16.D.6. Name: HerreraSandra Title: Manager-Procurement,Procurement Services Date: 5/11/2016 3:46:38 PM Name: WilliamsBarry Title: Division Director-Parks&Recreation,Parks &Recreation Date: 5/12/2016 4:02:49 PM Name: AlonsoHailey Title: Operations Analyst,Public Services Department Date: 5/18/2016 8:45:35 AM Name: JohnsonScott Title: Manager-Procurement,Procurement Services Date: 5/20/2016 2:54:20 PM Name: CarnellSteve Title: Department Head-Public Services,Public Services Department Date: 5/24/2016 2:21:02 PM Name: GreeneColleen Title:Assistant County Attorney,CAO General Services Date: 5/25/2016 8:13:25 AM Name: KlatzkowJeff Title: County Attorney, Date: 5/25/2016 12:28:10 PM Name:UsherSusan Title: Management/Budget Analyst, Senior, Office of Management&Budget Date: 6/6/2016 10:52:03 AM Name: UsherSusan Title:Management/Budget Analyst, Senior,Office of Management&Budget Date: 6/6/2016 10:52:30 AM Name: CasalanguidaNick Title: Deputy County Manager,County Managers Office Date: 6/6/2016 12:12:10 PM Packet Page-1021- 1 6/14/2016 16.D.6. !, I Procurement Servicee ' CAP Cough Change ardor Form ❑Contract Modifloatton la Work Order Modification ❑Amendment Contract/I: 14.0307 Champ 1 Purchase Order 0: dofl4500106047 Projeot 11: 80284 i ContraotorWFlrm Name: Wright Construction Corporation ContraouProject: Veterans Community Park Pick(eball Courts " Projeot Manager Name: Margaret Bishop Dtvialon Nam: + Parks&Recreation Original ContraotlWork Order Amount $ 108,761,$6 6/23/16;11.F Original 800 Approval Date;Agenda Item# Current BCC Approved Amount f/N/A` 0/23/16;11.F Last BCC Approval Dlate;Agenda Item# Current Contract/Work Order Amount $ 108,761.60 8/23/2016 SAP Contract Expiration Date(Master) Dollar Amount of this Charge ' $ 30,832.86 18.63% Total Change from Original Amount Revised Contract/Work Order Total $ 236,684.41 1/N/A Change from Current BCC Approved Amount Cumulative Changes $ 36,832.86 18.63% Change from Current Amount Completion Date,Description of the Takla)Change,and Rationale for the Change Notice to Proceed 2124/10 Original 7/20/10 Last Approved Revised Date On•hold Date - Completion Dnto Date N (includes this change) Il of Days Added 30 Select Tasks 0 Add now task(e) 0 Delete taek(e) Change taah(e) p Other(sen below) Provido a response to the following)1.)detailed and specific explanation/rationato of the requested oitango(a)to the(asks)and I or the additional clays added(If requested);2.)why this change woe not Included in the original oontreat;and,3.) dosorlbe the impact if this change le not preowned. Atlach additional Information from the Design Profosstonal andlor Contractor if needed. 1.) Wright Consiruction Corporation was awarded a work order for the conversion of the Veterans Community Park sand volleyball ' court to 0 plckleball courts.At the time of the award,only the funding for the lower cost DecoCotor surface was available ($20,132.42)us opposed to the DecoTurf($64,065.27).The contractor began the work on schedule and has prepared the asphalt base for Installation of the DecoColor surface.Because of etakehotdor input,It was decided that DecoTurf is a better option.The • contractor has been Issued a time suspension until additional funding is secured for the DecoTurf surface.As a result,an additional 30 days Is needed because of the installation procedure. • 2.) This change was not included In the original contract because the only funding available was to provide a DecoCotor surface,The , more expensive OscoTarf material was listed as a bid alternate.The bids were received on December 10,2016,and the difference In price for the more expensive surface was$33,010.00.Since that time,material cost has increased to$36,032.0. Stakeholder Input requested that the more expensive surface material be installed because 11 Is a professional,tournament grade, 0 layer cushioned surface that is easier to play on and will accommodate the growing demand for years to come. 3.) If the change la not processed the contractor can continue with the original work and Install the DecoColor surface.However, stakeholder concerns will not be addressed and we will be provided Wth what Is considered an inferior product.This may risk future court use. Prepared by: / - Date: �1°� lb (Ftl ai�;FaciltibsN"anegementONlsion) i i Acceptance of this Change Order shall constitute a modifcation to contract/work order Identified above and will be subject to all the same terms and conditions as contained in the contract/work order Indicated above,as fully as if the same were stated in this acceptance. The adjustment,If any,to the.Contract shalt constitute a full end final settlement of any and all claims of the Contractor/Vendor/Consultant I Design Professional a (fig out of Ui to re•ch angeset forth herein,Including claims for Impact and delay coats.i^7 F 1116 Accepted by: Delo. 8cot[l acanb,W t C struction,Corporation) j Approved by: - Date: S 1 =M t:le;P.E.;Q . arty Mi Associates,P.A.) -- Approved by: I r r/ ' � 0 l�sca; Date: <66 f ho ,a Burns;•r•= rents Pre essional devised:10/2012014 (MvIsiortswhomayrequireadditionalsignaturesmayincludeenseparatoaimot.) PRoc sarr:nrussoarr Ad#44A alto Licosa Packet Page -1022- 6/14/2016 16.D.6. VETERANS PARK IMPROVEMENTS BID NO.__Wright Construction UNIT ITEM DESCRIPTION QTY UNIT PRICE AMOUNT 1 Mobilization/Demobilization 1 LS 3,998.01 _3,998.01_ 2 Stormwater Pollution Plan 1 LS `1,000.00 _1,000.00_ Clearing,Demolition,Grubbing 3 &Grading 1 LS 39,994.38 _39,994.38 4 Court Construction 1 LS _72,662.92 _72,662.92 5 DecoColor Textured Acrylic 1 LS '_28,132.45 28,132.42 Color Surfacing 6 Conduits 1 LS 2,580.00 2,580.00 7 Landscaping 1 LS _15,476.15 _15,476.15 8 Fencing 1 LS _23,407.68 23,407.68 Allowance for Unforeseen and 9 Unknown Underground Utility 1 LS $4,500 $4,500 Services Conflict Resolution Allowance for Unsuitable Soil 10 Removal and Replacement 1 LS $7,000 $7,000 Bid Alternate 1 Add-4"Concrete Courts Surface with stabilized base and 1 LS _20,634.62 20,634.62 vapor barrier 2 Add-DecoTurf 6 Layer 1 LS _33,618.60 _33,618.60 Cushion System CAUserslrhondacummings.lTDOMA N\AppDatalocatNicrosoft Windows1Tempora y Internet Files1Content.Outlook1S14l4M101Wright Construction 8id.doo Packet Page-1023- 6/14/2016 16.D.6. From: David Valin To: BishooMargaret;FelidaKirbvVEN Subject: Veterans Pickle ball Date: Monday,May 02,2016 3:05:22 PM Attachments; lrnage001.onq Margaret, To upgrade the courts to a Deco Turf Layer"Cushion"product would be an additional$36,832.85. We will also need an additional 30 days from whenever this addition gets approved.If the approval process is expected to take more than a couple days,can you please issue a"suspend work"notice so our clock is not ticking If you need anything else from me please let me know. David Valin Project Manager Wright Construction Group Cell:239-738-5856 5811 Youngquist Road, Fort Myers,FL 33912 Phone:239-481-5000 Fax:239-481-2448 1105-1 Taylor Road, Punta Gorda,FL 33950 Phone:941-637-4728 121r 1Rn 1 taffi . , ccrsrEuC TION GROUF Packet Page -1024- 6/14/2016 16.D.6. IN WITNESS WHEREOF,the parties hereto,have each,respectively, by an authorized person or agent,have executed this Work Order on the date and year first written below. ATTEST; BOARD OF COUNTY COMMISSIONERS Dwight E. Brock,Clerk of Courts COLLIER COUNTY,FLORIDA By: By: Donna Fiala, Chairman Dated: (SEAL) Wright Construction Company,Inc. By: First Witness i a are xc��-1 c�.ccati� Ceps. NeA.,Y TType/print signature and thief TType/print witness namet Second Witness TType/print witness namet Approved as to Form and Legality: �/ ssistant County Attorney Print Name CO/Il Wright Construction Corporation Veterans Community Park Pickleball Surface Packet Page-1025- 6/14/2016 16.D.6. WORIC ORDER/PURCHASE ORDER Contract 14-6307"General Contractors Services" Contract Expiration Date:June 22,2016 This Work Order is for professional general contractor services for work known.as: Project Name:Veterans Community Park Pickleball Courts Project No: 80284 The work is specified in the proposal dated December 15th 2015,which is attached hereto and made a part of this Work Order: In accordance with Terms and Conditions of the. Agreement referenced above,this Work Order/Purchase Order is assigned to: Wright Construction,Inc. Scope of Work: As detailed in the attached proposal and the following: • Task I Mobilization/Demobilization * Task It Stormwater Pollution Plan Task III Clearing,Demolition,Grubbing&Grading 4 Task IV Court Construction * Task V DecoColor Textured Acrylic Color Surfacing * Task VI Conduits a Task VII Landscaping x Task VIII Fencing * Task IX Allowance for Unforeseen and Unknown Underground Utility * Task X Allowance for Soil Removal and Replacement Schedule of Work: Complete work within 150 days from the date of the Notice to Proceed which is accompanying this Work Order. The Consultant agrees that any Work Order that extends beyond the expiration date of Agreement# 14.6307 will survive and remain subject to the terms and conditions of that Agreement until the completion or termination of this Work Order. Compofsittiorc In accordance with the Agreement referenced above,the County will compensate the Firm in accordance with following method(s): ONegotialed Lump Sum(NLS) Li Lump Sum Plus Reimbursable Costs (L,S+RC)D'I'ime&Material (T&M) (established hourly rate Schedule A)D Cost Plus Fixed Fee(CPPT),as provided in the attached proposal. Task I $3,998.01 Lump Sum Task H $ 1,000,00 Lump Sum Task 111 $39,994.38 Lump Sum Task IV $72,662.92 Lump Sum Task V $28,132.42 Lump Sum Task VI $2,580.00 Lump Sum Task VII $15,476.15 Lump Sum Task VIII $23,407.68 Lump Sum Task 1X $4,500.00 Allowance Task IX x7..000.00 Allowance TOTAL FEE $198,751,56 Page 1 of 2 • Packet Page -1026- 6/14/2016 16.D.6. PREPARED BY: 91)J(12(AM/W7) • I Felicia Kirby,Pject Manager Date Facilities Management Division REVIEWED BY: 1ia,r -q, C ,.A /�- 1 7 — / (,, A e Mar t A.Bis top,P.E.,Sr,Project Manager Date Facilit •. M• agement Division REVIEWED BY: `41111 r.41 I I J& Hadi". e.'P.r.,'rut 'al Project Manager Date F•ciht es ana:cn at Division APPROVED BY: ��6' ,at r Lf'J'— --- Barry illlams,Division Director Dat: Parks& tecrcation Division APPROVED BY: 441 S 'l/ ' t ' f� °t Steve rnell, epailment Head Date Public Services Administration By the signature below,the Firm(including employees,officers and/or agents)certifies,and hereby discloses, that,to the best of their knowledge and belief,all relevant facts concerning past,present,or currently planned I interest or activity(financial,contractual,organizational,or otherwise)which relates to the proposed work;and bear on whether the Firm has a potential conflict have been nilly disclosed, Additionally,the Firm agrees to notify the Procurement Director,in writing within 48 hours of learning of any actual or potential conflict of interest that arises during the Work Order and/or project duration. ACCEPTED BY: Wri tGC ns ruction,Mc. ' -'' f r. Vii/iG C;trns D,at)n Date Aisistt'irmt Project Manager I t Page 2 of 2 Packet Page-1027- 6/14/2016 16.D.6. VETERANS PARK IMPROVEMENTS BID NO.__Wright Construction_ UNIT ITEM DESCRIPTION QTY UNIT PRICE AMOUNT 1 Mobilization/Demobilization 1 LS _3,998.01 _3,998.01_ 2 Stormwatcr Pollution Plan 1 LS __1,000.00 _1,000.00-_ Clearing, Demolition, Grubbing 3 & Grading 1 LS _39,994.38 _39,994.38_ 4 Court Construction 1 LS _72,662.92 _72,662.92 5 DecoColor Textured Acrylic 1 LS _28,132,45 _28,132.42 Color Surfacing 6 Conduits 1 LS _2,580.00 _2,580.00 7 Landscaping 1 LS _15,476.15 __15,476.15 8 Fencing 1 LS _23,407.68 _23,407.68 Allowance for Unforeseen and 9 Unknown Underground Utility 1 LS $4,500 _$4,500__, Services Conflict Resolution Allowance for Unsuitable Soil • 10 Removal and Replacement 1 LS $7,000_ _.$7,000__-_ Bid Alternate Add-4"Concrete Courts Surface with stabilized base and 1 LS __20,634.62 _20,634.62 vapor barrier 2 Add- DecoTurf 6 Layer 1 LS _33,618.60 _33,618.60 Cushion System UUca.coihmov.acttdala\ss-P4AANAGF.1Construcsion fi Capital hems PARKS&Real*Capital Projeeis10284 Veterans Picklebalh lid Doi-unions Construction Bids 12,10.151Wt;EN Construction-Veterans Bid Do-mutt RaInd dea • Packet Page -1028-