Loading...
VB MSTU Minutes 03/03/2016 V a,d 0,1418( Ooac4 M.S.7,1I. Advisory eve*itta¢ 3299 East Tamiarni Trail Suite 103 =� Naples, FL 34112 MINUTES MARCH 3,2016 I. CALL TO ORDER: Chairman Arthur called the meeting to order at 1:59 P.M. II. ATTENDANCE Advisory Committee Charles Arthur—Chairman William Sjostrom—Vice Chair Mark Weber Bruce Forman Gabriella R. Miyamoto Staff Harry Sells, Project Manager Others Gary Gorden—Commercial Land Maintenance Dale Slabaugh—DAS and Associates Wendy Warren—Juristaff III. APPROVAL OF AGENDA Mr. Sjostrom moved to approve the Agenda as presented. Second by Mr. Weber. Carried unanimously 5—0. IV. APPROVAL OF MINUTES FEBRUARY 4,2016 Mr. Sjostrom moved to approve the minutes of the February 4, 2016 Vanderbilt Beach MSTU meeting subject to the following changes: Page 3, Item VII. D. Hart's Electrical Quotes Motion from "...Carried unanimously 5 - 0) ..,"to ... Carried unanimously 4 -0). " Page 3, Item IX. B. By Laws Motion from"...Carried unanimously 5 - 0) ..,"to .... Carried unanimously 4 -0). " Second by Mr. Weber. Carried unanimously 5- 0. V. LANDSCAPE REPORT—GARY GORDEN,COMMERCIAL LAND MAINTENANCE Mr. Gorden, Commercial Land Maintenance,reported on landscape maintenance noting: • Plants and trees have been pruned to address site line issues on all travel lanes. • Seasonal applications of fertilizer and mulch will not be applied due to construction activity. 1 VI. CONSTRUCTION REPORT-RAY BENZA HOLE MONTES None VII. PROJECT MANAGER'S REPORT-HARRY SELLS A. BUDGET REPORT for 3/3/2016 Mr. Sells provided an overview on the "Vanderbilt MSTU Budget Report on Fund 143" dated March 3, 2016 highlighting: • Property taxes collected to date total $976,323 with a balance of$121,476 remaining. • Recovery of Carry forward funds of approximately $1M will cover the CWSI(cable wiring specialists) $770,000 contract for cable installation for Phases II, III and IV. • Operating expense remaining balance totals $287,172. • Century Link's contract for equipment installation, estimated in the range of$200,000 - $250,000 is not reflected in total commitments. • Actual cash balance available as of March 3, 2016 is $2,017,000. Mr. Sells will provide a budget recap including Phase IV for the April meeting. B. GENERAL STATUS OF BURIAL PROJECT Mr. Sells updated the Committee on construction Phases II and III noting: • Danella Utility Construction is 99.5% complete with estimated finalization date week ending March 5, 2016. • Mastec North America, Inc. has completed pulling cable feeder lines on the finger streets and is working on Vanderbilt Beach Road and Bluebill Avenue. All but fifteen transformers are installed. Estimated completion date for Mastec's work is September 2016. • CWSI cable conduit installation is two-thirds complete on the finger streets with the three most northern streets to be finished this year. Estimated completion date for the project is one and one-half years. • Sidewalk repairs are scheduled. • Utility power poles will be removed following Florida Power and Light Service activation at the end of Phases II and III. C. PHASE IV STATUS Mr. Sells recapped the status of Phase IV Construction from Bluebill Avenue north to Wiggins Pass Road noting: • A third set of preliminary design plans from FPL for Phase IV is pending. • On receipt of final design plans and Scope of Work proposal an Underground Conversion Agreement will be executed and presented to the Board of County Commissioners for approval. • Designs for Century Link and Comcast are finalized. • A further update on the project will be provided at the May 2016 meeting: 2 VIII. OLD BUSINESS Mr. Slabaugh, Landscape Architect,DAS and Associates,distributed a sample landscape plan for Vanderbilt Drive to the Committee for discussion. He highlighted the "repetitive"theme noting: • Foxtail Palms Trees are grouped at intervals along the drive with under plantings of Green Island Ficus (Ficus variety not affected by White Fly). • Coconut Palm Trees planted selectively. • Groupings of Pewtite Red Ixora. • Other plant material includes Arboricola Schefflera, White Fountain Grass, Bizmark Palms and Pitch Apple. • The landscaped area encompassing Conner Park requires approval by the Parks and Recreation Department. Mr. Slabaugh estimated installation would be approximately$100,888 excluding site preparation, irrigation and mulch. The Committee stated the design should be low maintenance and requested Mr. Slabaugh bring photographs of the proposed plants and an elevation sketch to the April meeting. Mr. Slabaugh will research the setback requirements for placement of Palm Trees. Mr. Sells will inquire if the County replaces or contributes to the cost of replacement of the landscaping removed for the Water Main Replacement Project,particularly on the corners by the finger streets. IX. NEW BUSINESS None X. MEMBER COMMENT None XII. PUBLIC COMMENT Vincent Bacon of Vanderbilt Drive requested an update on the status of the Water Main Replacement Project. The Committee advised his property is not part of the Vanderbilt Beach MSTU and Mr. Sells provided him with the name of the individual to contact at the County. There being no further business for the good of the County,the meeting was adjourned by order of the Chair at 3:20 P.M. 3 VANDERBILT BEACH MSTU A VISORY COMMITTEE 1,141 Charles Arthur, 'airman The minutes approved by the Board/Committee on / Piz 1 L I , 2016 "as submitted" ( 1 OR "as amended" [X 1. NEXT MEETING DATE: APRIL 7,2016 AT 2:00 P.M. "CLAUSSEN FAMILY CENTER"AT ST.JOHN'S CHURCH 625 111111 AVENUE,NAPLES,FLORIDA 4