Loading...
#11-5639 ( T. Y. Lin International Change Order #4) Co e-r County GROWTH MANAGEMENT DEPARTMENT MEMORANDUM DATE: September 30, 2015 TO: File—Chokoloskee Bridge Replacement, Project# 66066.9 FROM: Andrew Miller, P.E., Senior Project Manager Collier County Transportation Division SUBJECT: Back-up Memo for Change Order#4 The Chokoloskee Bridge Replacement Project, originally scheduled to begin construction in the fall of 2013, has undergone several design changes and permit delays that have significantly affected the timeline for completing the project. On a positive note, the latest obstacle encountered,the USCG permit, has finally been approved as of September 7, 2015. The invitation to bidders was advertised on September 28, and it appears that construction can begin in the upcoming months. The design contract for TY Linn has undergone three previous change orders for additional time and fees related to the design and permitting issues described above, but due to the last delay due to obtaining the USCG permit, the current contract will expire prior to project close out. Additionally, the design change eliminating the use of a temporary detour bridge and now proposes a staged construction of the new bridge, although saving significant construction dollars, will very likely result in an increase in requests for information(RFI's) from the engineer of record. This change order provides the consultant with adequate time and fees to remain available for post design services through the completion of construction. Collier County Procurement Services Change Order Form ® Contract Modification ❑Work Order Modification El Amendment Contract#: 11-5639 —1 Change#: 4 Purchase Order#: 45-134104 Project#: 66066.9 Contractor/Firm Name: T Y Linn International Contract/Project: Chokoloskee Bridge Replacement Project Manager Name: Andrew Miller, PE Division Name: Transportation Engineering Original Contract/Work Order Amount $ 450,000.00 9/13/11 16A11 Original BCC Approval Date; Agenda Item# Current BCC Approved Amount $ 518,500.00 9/10/13, 16A48 Last BCC Approval Date; Agenda Item# Current Contract/Work Order Amount $ 559,800.00 N/A SAP Contract Expiration Date(Master) Dollar Amount of this Change $ 35,016.00 32.18% Total Change from Original Amount Revised Contract/Work Order Total $ 594,816.00 14.72% Change from Current BCC Approved Amount Cumulative Changes $ 144,816.00 6.26% Change from Current Amount Completion Date, Description of the Task(s)Change,and Rationale for the Change Notice to Proceed 1/31/12 Original 1/30/16 Last Approved 8/17/16 Revised Date 4/9/18 Date . Completion Date Date (Includes this change) #of Days Added 600 Select Tasks ❑ Add new task(s) ❑ Delete task(s) ❑ Change task(s) ® Other(see below) Provide a response to the following: 1.) detailed and specific explanation/rationale of the requested change(s)to the task(s) and/or the additional days added (if requested); 2.)why this change was not included in the original contract; and, 3.) describe the impact if this change is not processed. Attach additional information from the Design Professional and/or Contractor if needed. 1.) detailed and specific explanation/rationale of the requested change(s) Due to the extensive time required to obtain a United States Coast Guard Permit for the construction of the new bridge, the subsequent delay of the construction start date has depleted the contract time allotted for the consultant to complete post-design services. In addition,the phased construction of the bridge, along with unknown subsurface site conditions will very likely result in above normal requests for information (RFI's)and submittal I reviews which will require additional post design services than previously budgeted in the original contract. Change Order 4 will provide sufficient time and funding to provide Post Design Services for the designer of record to serve the project through advertisement,award, construction and project close out of a $6.9 million construction project on an 18 month construction schedule. 2.) why this change was not included in the original contract; The initial contract allowed for a reasonable time to obtain the various permits required prior to beginning construction, and in particular allowed for approximately 326 days to obtain the permit from the USCG. The application for the USCG permit was submitted July 11, 2014,and was finally approved September 8, 2015(423 days). Post-design services were included in the original contract but the complexity of the design and construction was not known at that time. This change order will increase Post design Services from the original amount of$38,000 to a total of$73,000 to administer a $6.9 M construction project. 3.) describe the impact if this change is not processed. The engineer of record would not be available subsequent to the expiration of the current contract time and fee,and issues arising during construction that would require his expertise would very likely cause delays and cost over-runs. The bridge at this location is vital to the safety and welfare of the people of Chokoloskee as it their only link to the mainland. It is critical that the construction team of the new bridge have access to the design professional until the project is complete. (Divisions who may require additional signatures may include on separate sheet.) Revised: 10/28/2014 Acceptance of this Change Order shall constitute a modification to contract/work order identified above and will be subject to all the same terms and conditions as contained in the contract/work order indicated above, as fully as if the same were stated in this acceptance. The adjustment, if any,to the Contract shall constitute a full and final settlement of any and all claims of the Contractor/Vendor/Consultant/ Design Professional arising out of or related to the change set forth herein, including claims for impact and delay costs. Prepared by: `.jam/ Date: /1-l7 - /S Andrew Miller P.E., e • r Project Manager,Transportation Engineering Division Accepted by: _ ..i •3.1•-`_ 734TeGl' 1.44-, e.l2r Tn1�'.1 Date: II/�//S- (Contract r/Vendor/Consultant/Design Professional and Name of Firm, if project applicable) Approved by: . f ,�, . T Date: //-/A-45- Gary Putaansuu, P.E., Principal Project Manager,Transportation Engineering Division Approved by: �2?- ��.i Date: /// i ? / l J.-'• ad, P I• ision Dfr ,ctor,Transportation Engineering Division al Approve. :.: ,0"L.. '� AN- Date: \\\\) ��, David S.Wilkison, P.E., Department Head,Growth Management Dept. r � Approved by: �(,�'677--, (10/1- Date: /1/Q //'S- Evelyn Colon, Procurement Specialist, Procurement Services Division IN WITNESS WHEREOF, the parties hereto, have each, respectively, by an authorized person or agent, have executed this Change Order on the date and year first written below. ATTEST: BOARD OF COUNTY COMMISSIONERS Dwight E. Brock,Clerk of Courts COLLIER COUNTY, FLORIDA , ,,. a A' Tim ance, C ain Dated: : 2-- i s r , ZAI\ %.s (ST •$ a -'. r. .. . ecids Lure,0ly.,,. and legali .t R. each Deputy County Attorney \J (Divisions who may require additional signatures may include on separate sheet.) Revised: 10/28/2014 TYILININTERNATIONAL engineers I planners I scientists September 22,2015 Gary Putaansuu,PE Principal Project Manager Collier County Growth Management Division Transportation Engineering 2885 S. Horseshoe Drive Naples, FL 34104 Re: CR 29 Bridge over Chokoloskee Bay,Collier County Florida Bridge Number 030161 Dear Mr. Putaansuu: Since the United States Coast Guard Permit for the new bridge construction has now been issued, we understand the project is moving towards advertisement for construction. Due to the extraordinary time required to secure said permit, the contract time limits on our current design and post design contract with the County is in danger of expiring (August 17, 2016) prior to construction completion. In addition, due to the complex nature of the phased-construction design, remote site conditions and unknown sub-surface conditions we anticipate the amount of Requests for Information and Submittal Reviews will exceed the normal and previously negotiated hourly fee budget for post design services. Accordingly, T.Y. Lin International (CONSULTANT) proposes to provide the following additional services in accordance with Contract 11-5639 ARTICLE TWO: 1. Provide Post Design Services during construction operations as defined in Section 2.1 of Contract 11-5639. 2. Increase the Time for project completion by 600 days. The above described services were part of the contract scope, but are being supplemented and extended due to project complexity and regulatory and administrative scheduling. If this change is not incorporated, the CONSULTANT will be unable to fully support staff and the construction team with technical reviews, plan modifications, drawing interpretations, etc. typically required for a project of this complexity. CONSULTANT proposes to provide the above services for an additional Hourly/Not to Exceed fee amount of$35,016 in accordance with the conditions of Contract 11-5639. Please call if you need additional information on this matter. Sincerely, Jim Molnar, P.E. An Affirmative Action/Equal Opportunity Employer M/F/DN 2400 1st Street,Suite 200 I Fort Myers,Florida 33901 I T 239.332.4846 I F 239.332.4798 I www.tylin.com £ ƒ 0 CO 2 0 ) ± S - o 0 7 \ < d / / an \ o - E a) C » C \ £ f 3 f $ _ / / \ a « e / � \ ® / § o E ® # - 0 ° k ° E \ 2 = _ / \ S— / o ® CO I— / 2 \ -I C _ o 0 \ ƒ / 2 / 2 2 \ $ O I- 0 w 2 a, 0 CL o @ ® / a /� / ° o I co w (7). U) 0 O § \ G 0 O . 2 a o f m / 7 U) � / I— I ® re G/w ? 7 S /) I m Ce & 0 U \ y \= G G p O \ \ K Q C /w � k ® « 2 \ } P cn E w as TD_ \ 3 Et U G §$ a) \ § k a) 2 I U a)o \ 9 § o 0 ƒ k j r w ._ o i_ \ ,_ k f c 7 @ \ E 0_ \ @ \ / \ k / 5 Ez \ \ k / EL / $ : .An