VB MSTU Minutes 11/05/2015 V aNd artlf Ot Oaac& M.S.7.t1.
Advisory committee
3299 East Tamiami Trail Suite 103
Naples, FL 34112
MINUTES
NOVEMBER 5,2015
CALL TO ORDER: by Chairman Arthur called the meeting at 1:58 P.M.
II. ATTENDANCE
Advisory Committee
Charles Arthur—Chairman
William Sjostrom—Vice Chair
Mark Weber
Bruce Forman
Vacancy
Staff Harry Sells, Project Manager
Others Raymond Benza—Hole Montes, Senior Construction Field Representative
Robert Kindelan—Commercial Land Management
Wendy Warren- Juristaff
III. APPROVAL OF AGENDA
Mr.Sjostrom moved to approve the Agenda. Second by Mr. Forman. Carried; 4—0.
IV. APPROVAL OF MINUTES- OCTOBER 5, 2015
Mr. Sjostrom moved to approve the minutes of the October 5, 2015 Vanderbilt Beach M.S.T.U.
meeting subject to the following changes:
Page 2, Item VI.—Construction Report—"...Danella Construction boring crews are directly
behind their crews)...to"...Danella Construction worcrews are directly behind their
boring crews)."
Second by Mr. Weber. Carried unanimously 4—0.
V. LANDSCAPE REPORT-ROBERT KINDELAN COMMERCIAL LAND MAINTENANCE
Mr. Kindelan, Commercial Land Management, reported on landscape maintenance.
• Trimming of sidewalk plantings will be complete the week of November 14, 2015.
• Debris in irrigation lines caused by breaks in the main line will be flushed out.
• Conduit for new irrigation lines is physically in place and will be connected by Danella
Construction.
• Mulch and fertilizer will not be applied this year due construction activity.
Mr. Sells reported on the following landscape maintenance items:
1
• The M.S.T.U. maintains hedges originally planted by homeowners before the MSTU was
formed. All maintenance is currently on landscape within the County Right of Way.
• Danella Construction will clean swales and install sod to damaged areas once sidewalks are
installed.
VI. CONSTRUCTION REPORT-RAY BENZA HOLE MONTES
Mr. Benza reported construction is on schedule noting:
• Crews finished work at the end of Vanderbilt Drive/Bluebill Avenue and will move to the corner
of Vanderbilt Drive/Bluebill Avenue (Vanderbilt Towers area).
• Conduit will be installed under the Mangroves to the first utility pole.
• Two 6"conduits, one by each of the first and second poles, will be drilled on Bluebill Avenue.
• In approximately one week, boring all the way on Bluebill Avenue will restrict traffic flow and
block off some driveways.
• Conduit will be buried and connected on the North side of Bluebill Avenue.
Mr, Sells reported in approximately one week, boring on the West side of Bluebill Avenue
encompassing portions of the street will restrict traffic flow and block off some driveways. The MSTU
will work to resolve entry/exit conflicts with owners.
VII. INTRODUCTION OF VOLUNTEERS FOR OPEN POSITIONS
A. Gabriella R. Miyamoto
B. Domenic Lucarelli
The Committee discussed the candidate's applications for the open positions.
• Mr. Lucarelli was not present to review his application.
• Ms. Miyamoto presented her background to the Committee and expressed her interest in
becoming a member.
Mr.Arthur moved to recommend Ms. Miyamoto be appointed to the Vanderbilt Beach M.S.T.U.
Advisory Committee. Second by Mr. Sjostrum. Carried; 4-0.
VIII. PROJECT MANAGER'S REPORT
A. BUDGET REPORT FOR 11/5/2015
Staff distributed and reviewed the Vanderbilt MSTU budget report on Fund 143, dated
November 5, 2015. Mr. Sells reported:
• Actual Cash totals $3,339,921.
• Revenue generated for FY16 of$1,097,777 (an increase of$75,664 over FY15)will be
reflected in the total Actual Cash Total when the tax funds are received. The County
allows expenditure of these funds prior to receipt.
• The actual dollar figure for Line 9, Carry Forward Generated, is $1,120,000 and the
variance is not reflected on Line 36, Total Operating Expenses.
• The CWSI contract for cable installation in the amount of$776,000 will be heard by the
Board of County Commissioners in December 8, 2015.
• Neubert Construction Purchase Order#4500159226 for sidewalk replacement will be
closed out now that a new PO reflecting their county wide contract is in effect.
2
Mr. Sells noted the budget provides enough funding to enable the Committee to accomplish their
goals.
B. GENERAL STATUS OF BURIAL PROJECT
Mr. Sells reported that Phases 2 and 3 of the project are scheduled for completion July 2016.
Utility Construction Update
Mr. Sells updated the Committee on construction Phases 2 and 3 noting:
• MASTEC has been awarded a contract and a purchase order has been created to install
the FPL network. Construction is scheduled to commence on November 16, 2015 on
Flamingo Avenue. Once the installation is active and stabilized individual owners will be
connected.
• Collier County is undertaking a sewer line and storm sewer project in February 2016 for
Vanderbilt Drive and the finger streets. The project will start at Flamingo Avenue on the
north end and work south, and will take two years.
• Century Link equipment installation will be going out to bid.
Phase 4 Florida Power and Light
Mr. Sells reported he conducted a walk-through with John Lehr(Florida Power and Light)of the
project area. On receipt of final design plans and a Scope of Work proposal an Underground
Conversion Agreement will be executed and presented to the Board of County Commissioners
for approval.
Sidewalks East Side of Vanderbilt Drive
Application for a grant to the County to build sidewalks on the East side of Vanderbilt Drive
was denied.
Road,Bridge,Walkway,and Utility project
Construction from Bluebill Avenue north to Wiggins Pass Road is scheduled to commence in
June of 2016. Two bridges as part of the Greenway project will be rebuilt closing Vanderbilt
Drive to Wiggins Pass Road sometime in 2016. A bike path will be constructed on the west side
of the street. The FPL burial project can't be conducted at the same time as this construction.
IX. OLD BUSINESS
A. DISCUSSION ON FUTURE LANDSCAPING ON VANDERBILT DRIVE
Mr. Sells recommended the Committee give consideration to the visual appearance they
would like to achieve for Vanderbilt Drive. Options include:
• Replace existing landscaping with identical plantings.
• Modify current landscaping with addition of new plants or;
• Retain a landscape architect to design a landscape scheme for the entire street.
Staff noted replacement of damaged plants will be taken care of in the near future. A
comprehensive landscape plan for the entire street would be a long term project(perhaps two
years)and based on Committee design approval.
3
Mr. Sells will invite Dale Slabaugh of Dale A. Slabaugh and Associates, to the December
meeting for a design consultation with the Committee for Vanderbilt Drive landscaping.
Mr. Sells informed the Committee the damaged slats on the park benches will be replaced .
X. NEW BUSINESS
None
XI. MEMBER COMMENT
None
XII. PUBLIC COMMENT
Lourdes Placid suggested a homogenous landscape plan be developed for the finger streets
intersecting Vanderbilt Drive.
Staff took the suggestion under advisement noting the project is long term and requires
allocation of budget funding.
Staff updated the attendees on the status of the Greenway project noting two bridges will be
rebuilt and a boardwalk/pathway will encompass a four mile section of Vanderbilt Drive from
111th Avenue N. to Bonita Beach Road.
There being no further business for the good of the County,the meeting was adjourned by
order of the Chair at 3:45 P.M.
VANDERBILT BEACH MSTU ADVISORY COMMITTEE
L/7.‘ Jr,/ANY
Char es Arthur, h.1 an
The minutes approved by the Board/Committee on 23 , 2015,
"as submitted" [X 1 OR "as amended" [ 1.
NEXT MEETING DATE: DECEMBER 3,2015 AT 2:00 P.M.
"CLAUSSEN FAMILY CENTER"AT ST.JOHN'S CHURCH