Minutes 09/23/1992 R Parks & Recreation
Advisory [hoard
( PARAH )
Minutes
September 23 , 1992
MINUTES
COLLIER COUNTY PARKS AND RECREATION ADVISORY BOARD
Golden Gate community Park
Naples, Florida 33999
Wednesday, September 23, 1992
PRESENT: Ms. Cherryle Thomas, Chairman
Mr. Gil Mueller, Vice Chairman
Mr. Timothy Blackford
Ms. Geneva Till
ALSO PRESENT: Mr. Steve Brinkman, Parks & Recreation Director
Mr. Murdo Smith, Parks & Recreation Operations Manager
Ms. Mary Ellen Donner, Recreation Supervisor
Ms. Barbara L. Johnson, Sr. Secretary
ABSENT: Mr. William Clendenon
GUESTS: Collier County Women's Tennis Association Members
Ms. Nancy Farnsworth, President; Sandy Acres, Vice President;
Diane Jacob, Div. Director; Nancy Eubauk
I. CALL TO ORDER 2:00 p.m.
II. PLEDGE OF ALLEGIANCE TO THE FLAG
III. APPROVAL OF MINUTES:
Approval of August 26, 1992 minutes. Motioned by Mr. Gil Mueller,
seconded by Ms. Geneva Till , passed 4/0
IV. NEW BUSINESS/PRESENTATIONS:
C. PRESENTATION - TENNIS
Ms. Nancy Farnsworth, President of the CCWTA made a presentation
requesting some additional tennis courts, particularly in the North
Naples and Golden Gate area. The organization has grown to a
membership of 598 women - 300 actively play each season. Due to the
lack of available courts to play on, it may become necessary to cap
off the membership of the group; a membership waiting list has
presently been established. The three sessions of play this year
has resulted in revenue of $4,300 for the County. The majority of
the games are played in the evening, which necessitates lighted
courts, and locations of play are determined by the area where the
players reside. Present scheduling allows the CCWTA to use 50% of
the County courts available, leaving the other 50% available to the
general public. CCWTA was instrumental in promoting the
construction of the last 4 courts at Veterans Park, and desire to
make their request for additional courts known.
1
Staff explained that the Parks Master Plan includes 2 additional
courts at Golden Gate and 2 at Veterans Park but there is no funding
available at the present time. The possibility exists for
construction of 6 courts at the Vineyards; also the possibility of 8
clay courts at the Pelican Bay property to be donated by
Westinghouse. The approximate cost for 2 courts is $44-50,000,
including lights and fencing. The Racquet Club on Marco Island also
has room for three additional courts. The use of the existing clay
courts at this facility would determine the type of courts to be
constructed. The Department is also considering some type of tennis
complex in different parts of the County, similar operation as the
one on Marco.
Mr. Brinkman offered to schedule a time with Ms. Farnsworth to talk
about the courts at the Vineyards. These would be the traditional
hard court due to the initial cost and the cost of maintenance. If
a complex were built with many courts, it could be half hard courts
and half clay courts. Older people prefer the softer courts.
B. PRESENTATION - BEACH PARKING
George Carse gave a presentation regarding the beach parking fees.
He distributed literature and pictures in reference to Tigertail
Beach. He explained that Tigertail Beach was different from other
Gulf beaches, as it was not on the Gulf itself but was a lagoon.
Although the water is considered safe for swimming, the appearance
of it is not appealing to bathers. There are numerous reports
available giving figures of beach users and residency of these
users, all showing different statistics. In reference to the beach
fees being discussed at the BCC meeting Tuesday, Mr. Carse favored a
free beach sticker for year round residents as opposed to increasing
the fee for beach parking. He noted that if a person drove to the
City beaches there would be no charge if the vehicle had a City
sticker. Consistency at all beaches was also favored.
Mr. Mueller spoke in reference to Tigertail - the status of the
murky water was due to the formation and growth of Sand Dollar
Island. He suggested that Mr. Carse contact Mr. Frank Blanchard who
has been very active regarding the beach concerns of Marco. Mr.
Mueller stated that he felt the users of Tigertail were different
than the users of the other County beaches and many hours have been
spent discussing the beaches, fees, etc.
A. A & B - These two items - (A) Sports Equipment and (B) Arts & Craft
Supplies were put out for bid last year. Since both agreements
contained renewal clauses, it is not necessary for these items to go
before the BCC again this year.
D. Mr. Brinkman reported that the Recreation Standards in the Growth
Management Plan have been revised. The lowest operating maintenance
costs results when grouping of like facilities occur and there is
also less stress on community parks. He then went down the list
that had been distributed.
2
The Department is suggesting developing two regional sports complexs
- 1 in the North and 1 in the South. Added is a regional events
complex with a very large park area for large County-wide special
events.
Recreation/pool/tennis complex - in addition to what we have, we
would build these large rec centers (25,000 sq. ft. ) - 1 for every
50,000 people, 1 center for every two community park areas. These
centers would be fitness oriented. There would also be an outdoor
pool and a tennis complex, with the center and one staff would run
all three facilities. This would be more effective cost wise. The
standards call for four centers; we have the option of expanding
existing facilities - Immokalee Middle School , add on to the
Recreation Center at Golden Gate, FMCP, and we could expand the
Racquet Center.
Regional Sr. Ctr. - This would be an outdoor educational center in a
large regional park. The Park Rangers headquarters could be located
there, a training room, exhibit hall , nature trails, lake, etc.
It would be nice to work with the School District and have the
School Board and County purchase land together for development.
Barefoot Beach Preserve - expanding the facility to include an
interpretative center. Summer camps, etc. could be held here.
Neighborhood Parks - use existing elementary schools. We wish to
develop an agreement and standard with the School District so that
they would put in a particular type of facility and the County would
reward them by sharing in 50% of the operation and maintenance cost.
These areas would be called school park areas. In the future if a
new elementary school site were designated as a neighborhood park,
the county would pay 50% of the operating and maintenance cost. The
School District has better capability of acquiring capital money,
but not operating and maintenance monies.
PROJECTS: This list is a Development Plan.
Community Recreation Facilities - expand 3 existing facilities with
swimming pools at those locations. Construct two new facilities to
serve North Naples and South Naples, consisting of a 25,000 sq. ft.
Center, pool , and tennis complex. Land is needed to develop a
number of community parks. South Naples Community Park hopefully
will be developed near Lely High School . The land for the Estates
community park is being worked on by another advisory group. Then
Community Park #9 and 10 would be constructed.
Regional sports complex - The proposed north facility would have the
highest priority and could be located at Barron Collier High School
or the new high school being developed on Immokalee Road. The
southern facility would probably be at Lely High School or the
Manatee site (Gran property) . Barron Collier High School has been
trying to correct existing problems with their athletic fields.
What we would like to do is have Barron Collier give us the land for
a regional sports complex and we would give them the new facilities
- one softball and one baseball field for their varsity. We could
use the complex weekends and evenings. There is a site for an
elementary school there and there is an open piece of land
3
available; we would like 5 softball , 4 baseball , and 8 soccer fields
in that location. Because of the amount of land it may be necessary
to reduce the scope or put the soccer fields at a different
location.
Another plan for Rec Center - maybe expanded at IMS. 10,000 sq. ft.
of gym could be renovated. In existence are a weight room, locker
rooms, office & maintenance (separate building) . It would be
necessry to join the two buildings. We would like to build
additional racquetball courts; this would require the School
District to demolish another facility a this loction. Additional
rooms of different sizes, kitchen, and a game room could be
constructed. This would give Immokalee a facility for the entire
family with a pool next door. We would build a rec center as home
base for staff and then have the supervisor also operate the
swimming pool .
There is a similar plan for Golden Gate Community Center as well .
3:40 take 10 minute break
VI. REPORTS AND UPDATES
Per the internal auditor, we should have the fees and formulas used for
rental of the facilities and program charges approved by the BCC.
These items are covered in this Draft and are generally the same as
currently in effect. .
Draft Fees and Charges - Includes, Recreation, Athletics, Racquet
Center, Swimming Pool and Golden Gate Community Center fees and
charges. The major changes are: proposing charging both profit and non
profit organizations for use of the facilities and there will be a
concession fee associated with events. Deposits can be waived for
various reasons. It also covers the insurance requirements per Risk
Management. The Athletic Section will be charging $5.00 per
participant for programs not sponsored by the County.
The formulas for program charges have not changed.
Golden Gate Community Center - fee structure has been approved by their
Advisory Board - fees have been increased, the policy states insurance
requirements and recommendations for serving alcohol .
MOTION: Gil Mueller: We accept the fee policy on the condition that
staff review the possibility of variation between residents and non
residents showing a minimum of 20% or there abouts breaking it off on
even dollars at RC.
Geneva Till : Seconded. Passed 4-0.
Mr. Blackford inquired about the swimming pool at Golden Gate.
Weller Pool was the low bidder, but all bids were over budget.
Permission has been granted to renegotiate with Weller and determine if
the cost can be cut to $1 .6 million. Staff desires to keep the slide
and cut something else. There will be locker/restrooms, but the ozone
pool sanitation has been dropped.
4
Barefoot Beach Friends would like to run the concession at Barefoot
Beach Preserve, keeping 10% of the profits and give 90% to the County.
The organization of 200 members has 3 people that have retail
experience and would head this committee. Two people would be on duty
in the stand year round, a separate checking account would be
established, the account will be audited and reviewed by County. The
group would need to come before PARAB to make report annually. The
"Friends" are willing to do this because they are interested in
keeping up the facility and would like to help provide educational
programs, etc.
MOTION: Geneva Till - BCC waive bidding requirements for Barefoot
Beach Preserve, and authorize Friends to operate this facility
according to these guidelines.
Mr. Blackford - seconded the motion. Passed 4 to 0.
Ballfields at GGCP and Veterans Park - should be substantial completion
by December or January. New football/soccer field to start
construction soon in Immokalee. Clay courts just about done at the
Racquet Center.
Conklin Point - Bids will be coming on for this project. Staff to send
tab sheet to PARAB members and if they so desire a special meeting will
be called to discuss this item.
Adjourned 5:00 pm.