CCAA Agenda 01-11-2010 Executive Director Report [1]CCAA Project Status Summary
PROJECT
STATUS
Immokalee Regional Airport PUD
Planning Commission Hearing – consent agenda: 1/8/10
BCC Summary Agenda 2/23/10
Immokalee 20,000
SF USDA Building
USDA State Office reviewing bid documents for concurrence
Construction to begin 1Q10
Groundbreaking – to be scheduled after USDA pre-construction meeting
IMM -
Business Development Center
Interlocal Agreement w/CRA on CCAA 1/11/10 Agenda
Everglades T-Hangar Project
Substantially Complete
CCAA to request utilizing approx. $43,000 from
the Immokalee Infrastructure fund, and will transfer future FAA entitlement $ from Everglades back to Immokalee.
Rookery Bay Mitigation
Mitigation for X01 South Taxiway & MKY Taxiway
projects complete
Continued maintenance, monitoring and reporting required for 5 years
Marco Executive Airport Parking Lot & Aircraft Apron Expansion
Notice to Proceed issued for
1/18/10
Contractor pre-construction meeting with subs – 1/11/10
Ground breaking w/Commissioner Fiala to be scheduled
Executive Director Search
Posted on County site 1/8/10; Closing
date 2/8/10
Will be put up on AAAE site this week. Directions to access posting on AAA site:
Go to www.aaae.org
Scroll cursor over to “membership” button at the top of the home page
and left double click on “career center” on drop down menu.
“Career Center” page will appear, double left click on “Job Seekers” Icon.
On lower left hand side of career center page,
look for “shortcuts” box and double left click on “view all jobs” button.
FY2011 Budget
Draft to be provided to Authority in February; to be adopted in March
Due to County OMB mid-March
MKY Taxiway
Grant Pre-Application submitted to FAA 1/7/09
Preparing bid package to compete for discretionary FAA funding
Everglades South Taxiway
Grant Pre-Application submitted
to FAA 1/7/09