Resolution 2014-190 RESOLUTION NO. 2014 - 1 90
A RESOLUTION OF THE BOARD OF COUNTY COMMISSIONERS OF
COLLIER COUNTY, FLORIDA, SUPERSEDING RESOLUTION NO.
2007-162 IN ORDER TO ESTABLISH A REVISED SCHEDULE OF FEES
FOR RIGHT-OF-WAY PERMITS.
WHEREAS, Collier County Resolution No. 2007-162 established a Schedule of Fees for
Right-of-Way Permits; and
WHEREAS, as directed by the Board of County Commissioners (Board), County staff
reviewed the existing regulatory framework for issuance of permits for special event signs in
public rights-of-way and, based on this review, is proposing changes to the permit forms for
these temporary signs; and
WHEREAS, staff is also proposing a revision to the current Schedule of Fees for Right-
of-Way Permits so as to include a fee for a Temporary Directional Sign Permit for Public Event;
and
WHEREAS, new or increased fees for certain land development activities, including, but
not limited to, permitting of special event directional signs for placement in the public rights-of-
way, are reflective of the actual cost of processing, reviewing, and inspecting such permit work.
NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF COUNTY
COMMISSIONERS OF COLLIER COUNTY, FLORIDA, that the Board of County
Commissioners hereby declares and approves the revised Schedule of Fees for Right-of-Way
Permits, as set forth in the attached Exhibit "A," and finds that said fees are reasonable sums to
be assessed to those who receive the benefits of these services, reviews, and inspections required
by the County permitting process.
BE IT FURTHER RESOLVED, that this Resolution shall be recorded in the minutes of
this Board and that Resolution No. 2007-162 is hereby superseded by the adoption of this
Resolution.
[14-CED-00933/1113818/1]
THIS RESOLUTION adopted after motion, second, and majority vote favoring
adoption thisZday of sue, e),S,ey— , 2014.
ATTEST: BOARD OF COUNTY COMMISSIONERS
DWIGHT E. BROCK, Clerk COLLIE/4U QTY, FLORIDA
04 0 l►'�bl'l B !t
Attest as to chairmliKeuty Clerk TOM HE ING, C i AIRMAN
signature only.
Approved as to form and legality:
Kevin L. Noell L'
Assistant County Attorney
[14-CED-00933/1113818/1]
i..
Exhibit "A"
Right-of-way Permits
Type Residential Non-residential
Small Large
Right-of-way Construction $ 200.00 $ 1000.00 (June-Nov) $2000.00 (June-Nov)
$ 2000.00 (Dec-May) $4000.00(Dec-May)
Work in the ROW (Without Lane $ 50.00(June-Nov) $ 100.00(June-Nov)
Closures), Cost Per Day $ 100.00 (Dec-May) $ 200.00 (Dec-May)
Miscellaneous Events $ 200.00
PSC Regulated Franchise Utility $100.00
Application Fee + $50/Day inspection fee
Renewal/Modification of unexpired or *S 100.00 $ 500.00 $ 1000.00
incomplete Permit
Re-inspection-First $ 100.00 $ 100.00 $ 100.00
Second $ 150.00 $ 150.00 S 150.00
Third $ 200.00 $ 200.00 $ 200.00
All subsequent inspections $ 250.00 $ 250.00 S 250.00
Jack-and-Bore/Directional Bore $ 500.00 $ 1000.00 $2000.00
Open-cut Construction $2000.00 $4000.00 $6000.00
Sprinkler I lead Placement in R/W $ 50.00 $ 200.00 S 400.00
Turn Lane Construction $ 500.00 $ 1500.00 $3000.00
County Engineering review on behalf of $ 500.00 S 1000.00
FDOT Drainage Permit. No Discharge into
State System
** County Engineering review on behalf of $ 1000.00 $ 2000.00
FDOT Drainage Permit. with Discharge
into State System
Temporary Directional Sign Permit for $75.00
Public Event
After-the-Fact Permit 4 X Normal Fee ($24000.00 max)
* If the Renewal/Modification does not require additional staff time and field check
(unexpired permit only), there will not be any fees charged
**Development two (2) acres or less are considered small
Page I 01'4
Exhibit "A"
Right-of-way Permit Notes:
1. Unjustified delays meeting permitted deadlines shall require additional fees as authorized.
2. Small Commercial Development shall be defined as a non-residential(single-family or duplex)
project generating 600 vehicles trips per day or less.
3. Large Commercial Development shall be defined as a non-residential (single-family or duplex)
project generating greater than 600 trips per day.
4. A right-of-way use fee(chart attached) per day shall apply to all non-residential projects
requiring a lane closure on a major roadway or sidewalk closure on any roadway(chart
attached).A major roadway is defined herein as being one of the following Collier County
maintained roadways:
Roadway Name From To
Immokalee Road Tatman Trail North(US 41) SR 29(Immokalee)
Vanderbilt Beach Road Tamiami Trail North(US 41) Collier Boulevard
Pine Ridge Road Tamiami Trail North(US 41) Collier Boulevard
Golden Gate Parkway Tamiami Trail North(US 41) Collier Boulevard
Radio Road Airport Road Davis Boulevard
Rattlesnake Hammock Road Tamiami Trail East(US 41) Collier Boulevard
Goodlette-Frank Road Tamiami Trail East(US 411 Immokalee Road
Airport Road Tamiami Trail East(US 411 Immokalee Road
Livingston Road Radio Road Lee County Line
Santa Barbara Boulevard Davis-Boulevard Rattlesnake Pine Ridge Rd
Hammock
Logan Boulevard Pine Ridge Road Lee County Line
Collier Boulevard Judge Jolley Bridge Immokalee Road
CR 29 Everglades City SR 90(US 41)
Bayshore Drive U.S.41 Thomasson Drive
Golden Gate Boulevard C R.951 Desoto Boulevard
Vanderbilt Drive VBR Vanderbilt Beach Road Lee County Line
Gulfshore Boulevard VBR Vanderbilt Beach Road Bluebill Ave.
Oil Well Rd Immokalee Rd S.R.29
Randall Boulevard Immokalee Rd Desoto Boulevard
Everglades Boulevard Golden Gate Boulevard Immokalee Rd
Naples Boulevard Pine Ridge Road Airport Road
County Barn Road Davis Boulevard Rattlesnake Hammock Road
5. No refunds of unused fees shall be allowed.
6. Lane use fees shall be calculated by Collier County and shall be due and payable at the time
of permit application if a permit is issued. If a Notice of Intent to Issue a permit is provided by
the County in lieu of a permit, then the lane use fee shall be due and payable at the time of
issuance of the actual permit.
7. If work continues beyond the originally estimated lane use period, then additional lane use fees
shall be due and payable within two working days of notice to the Perm ttee of such additional
fees. Failure to provide the additional fees to the County within three working days of such
notice shall be cause for the project to be "red-tagged" and shut down. Lane use fees shall
continue to accrue during any period of shutdown and shall he added to the additional lane use
fees calculated by Collier County.
8. Any deviation from the above must be approved by the ROW Permitting and Inspection
manager or designee prior to implementation.
9 All future County Projects shall be exempt from the Lane Rental Fee Incentive Program.
Page 2 of 4
Exhib�' ",�"
Lxhibit "A"
SIDEWALK RENTAL FEE (PER DAY) INCENTIVE PROGRAM
LANE RENTAL FEE (PER DAY) INCENTIVE PROGRAM
$100 $100 $100 $100 $100 $100
$600 $600
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Page 3 of 4
Exhibit "A"
SIDEWALK RENTAL FEE (PER DAY) INCENTIVE PROGRAM
$100 $100 $100 $100 $100 $100
Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July
Pagc 4 of 4